vd calculation
November 10, 2017 | Author: Abhijit Mandal | Category: N/A
Short Description
cable selection considering voltage drop...
Description
SECTION-9 ELECTRICAL DESIGN CALCULATION
507
TRANSFORMER SIZING FOR CWPS PLANT
1.0
Formula Used:
1.1
Working Load in kVA
=
[ Working Load (kW) x L. F. ] / [ D. F. x P. F. x Effi. ]
L. F.
= Load Factor
1.2
System P. F.
=
Total Working Load (kW) / Total Working Load (kVA)
P. F.
= Motor Power Factor
2.0
Item Description
Pump
Connected Load
Rating in kW
Effi.
280
0.946
P. F.
L. F.
0.85
D. F.
0.9
1
=
4.0 System P. F. = 5.0 Calculation to check the starting of largest size motor 5.1 Rating of transformer assumed = 5.2 % impedance of transformer assumed = 5.3 Rating of the largest size motor = 5.4 Supply voltage = 5.5 P.F of largest size motor = 5.6 Efficiency of largest size motor =
Total (kW)
3
840
2
504
626.79
504
626.79
0.8041 1250 5 280 3.3 0.85 0.946
kVA % KW kV
Nearest standard size (Confg. 33/3.3KV,Dyn11,Delta-star) From IS 2026 From the above table System voltage From the above table From the above table kW x 1000 1.7321 x V x p.f x efficiency kW P.F x Efficiency
60.92016454 A
Rating of largest size motor in kVA
=
348.2153961 kVA
=
348.2153961 kVA
(Considering only one motor is working and the Second motor is started)
=
2089.292377 kVA
= 6 x 1.7321 x kV x I FLC
696.4307922 kVA
= 3 x 1.7321 x kV x I FLC
5.11
Motor starting Kva with Star Delta start
=
5.12
Fault Level at transformer secondary side
=
5.13
Fault current of transformer secondary side (ISC)
=
5.14
S.C capacity of transformer Voltage drop at transformer terminal when largest motor start with DOL starting Voltage drop at transformer terminal when largest motor start with Star Delta starting
=
5.16
752.15 kVA
=
5.10
5.15
Working Load (kVA)
Unit
FLC of motor
Base load on transformer before starting Second largest motor Motor starting Kva with DOL start
5.9
Working Load
Total (kW) 840
3.0 Considering 20% contingency
5.8
= Motor Efficiency
Unit
Total Load
5.7
= Diversity Factor
Effi. Input Data and Calculations:
Sr. No. 2.1
D. F.
Rating of transformer in MVA x 100 Impedance of transformer in % Fault Level in MVA 1.7321 x kV
25 MVA 4.373741456 kA 25000 kVA
=
9.750031091 %
=
4.2 %
The selected rating of transformer is
508
1.7321 x kV x I SC [Motor Starting kVA (DOL) + Base Load kVA] x 100 S.C capacity of transformer [Motor Starting kVA (S/D) + Base Load kVA] x 100 S.C capacity of transformer 1250 kVA
(within 10%) (within 10%)
CAPACITOR BANK SIZING ACROSS MOTOR TERMINAL Main Pumps For Clear water pumping station 1 2 3 4 5 6
Motor rating (kW) Motor rating after 90% load factor (kW) Supply Voltage (V) Motor Power Factor (p.f 1) Motor efficiency (Effi.) Power Factor to be improved (p.f 2)
7 No load p.f. (p.f NL)
280 252 3300 0.85 0.946 0.98 0.1
To be considered for further calculations Based on actual Values given by jyoti Based on actual Values given by jyoti Assumption
8 Motor Full Load Current in amp.(FLC)
54.828
= (kW x 1000) / (1.7321 x V x cos(p.f 1) x Effi.)
9 No load current in amp. (INLC)
19.190
35% of FLC
10 Motor magnetising current in amp. 11 Capacitor current (Ic) Max. kVAR that can be connected across motor 12 terminal Total kVAR to be connected across the motor 13 terminal Excess kVAR to be connected across the 14 switchgear bus bars (13 - 12)
19.094 17.184
= [ INLC x sin(cos-1p.f NL) ] Shall be 90% of motor magnetising current
98.22
= (1.7321 x V x Ic) / 1000
105.00
= kW[ tan(cos-1p.f 1) - tan(cos-1p.f 2) ]
6.79
509
Negative value indicates capacitor bank is not required across the bus.
TRANSFORMER SIZING FOR CWPS PLANT
1.0
Formula Used:
1.1
Working Load in kVA
=
[ Working Load (kW) x L. F. ] / [ D. F. x P. F. x Effi. ]
L. F.
= Load Factor
1.2
System P. F.
=
Total Working Load (kW) / Total Working Load (kVA)
P. F.
= Motor Power Factor
2.0
D. F.
= Diversity Factor
Effi.
= Motor Efficiency
Input Data and Calculations:
Sr. No.
Item Description
Rating in kW
Connected Load Effi.
P. F.
L. F.
D. F.
Working Load
Unit
Total (kW)
Unit
Total (kW)
Working Load (kVA)
a
EOT crane
15
0.87
0.82
1
2
1
15
1
7.5
10.51
b c d
Exhaust fan Lighting (CWPS) Flash mixture
0.5 15 1.5
0.67 0.8 0.79
0.82 0.8 0.81
1 1 0.9
1 1.5 1
8 Lumpsum 2
4 15 3
8 Lumpsum 2
4 10 2.7
7.28 15.63 4.22
e
Clarifloculator mechanism phase-1
7.5
0.87
0.82
0.9
1
2
15
2
13.5
18.92
f
backwash pumps
160
0.962
0.86
0.9
2
2
320
1
72
87.03
g
Air blower
37
0.935
0.86
0.9
2
2
74
1
16.65
20.71
h
Chlorine booster pumps for prechlorination
1.1
0.79
0.81
0.9
2
2
2.2
1
0.495
0.77
i
Chlorine booster pumps for postchlorination
1.1
0.77
0.81
0.9
1
2
2.2
1
0.99
1.59
j
Service water pumps
3.7
0.77
0.82
0.9
1
2
7.4
1
3.33
5.27
k
Agitator for Alum dosing pump
1.5
0.79
0.81
1
2
3
4.5
3
2.25
3.52
l
Agitaotor for Lime dosing pump
1.5
0.79
0.81
1
2
3
4.5
3
2.25
3.52
m
Agitator for polyelectrolyte dosing tank
1.5
0.79
0.81
1
2
3
4.5
3
2.25
3.52
n
Dosing pump for alum
1.5
0.79
0.81
1
1
2
3
1
1.5
2.34
o
Dosing pump for lime
1.5
0.79
0.81
1
1
2
3
1
1.5
2.34
p
Dosing pump for polyelectrolyte
1.5
0.79
0.81
1
1
2
3
1
1.5
2.34
q
Valves
0.5
0.67
0.82
0.9
2
30
15
30
6.75
12.29
r
EOT crane
7.5
0.87
0.82
0.9
1
1
7.5
1
6.75
s
Lighting (chemical,Filter,pump,outdoor)
40
0.902
0.81
1
1.5
Lumpsum
40
Total Load
542.8
3.0 Considering 20% contingency
=
297.31 kVA
4.0 System P. F.
=
0.7369
5.0 Calculation to check the starting of largest size motor 5.1 Rating of transformer assumed = 5.2 = % impedance of transformer assumed 5.3 Rating of the largest size motor = 5.4 Supply voltage = 5.5 P.F of largest size motor = 5.6 Efficiency of largest size motor =
315 4.5 160 0.415 0.86 0.962
5.7 5.8
247.76
Nearest staanddard size (Confg. 33/0.433KV,Dyn11,Delta-star) From IS 2026 From the above table System voltage From the above table From the above table kW x 1000 1.7321 x V x p.f x efficiency kW P.F x Efficiency
269.0452946 A
Rating of largest size motor in kVA
=
193.3955422 kVA
=
121.6044578 kVA
(Rating in kVA of transformer assumed - Largest motor KVA)
=
1160.373253 kVA
= 6 x 1.7321 x kV x I FLC
386.7910845 kVA
= 3 x 1.7321 x kV x I FLC Rating of transformer in MVA x 100 Impedance of transformer in % Fault Level in MVA 1.7321 x kV 1.7321 x kV x I SC [Motor Starting kVA (DOL) + Base Load kVA] x 100 S.C capacity of transformer [Motor Starting kVA (S/D) + Base Load kVA] x 100 S.C capacity of transformer
5.11
Motor starting Kva with Star Delta start
=
5.12
Fault Level at transformer secondary side
=
5.13
Fault current of transformer secondary side (ISC)
=
5.14
S.C capacity of transformer Voltage drop at transformer terminal when largest motor start with DOL starting Voltage drop at transformer terminal when largest motor start with Star Delta starting
=
5.16
182.58167
=
5.10
5.15
36.50
FLC of motor
Base load on transformer before starting fourth largest motor Motor starting Kva with DOL start
5.9
kVA % KW kV
9.46
Lumpsum 26.666667
7 MVA 9.738161699 kA 7000 kVA
=
18.3139673 %
=
7.3 %
The selected rating of transformer is 400 kVA
510
(within 10%) (within 10%)
CAPACITOR BANK SIZING ACROSS BUS
Intermediate Pumping Station 1 Average Power factor (pf1)
0.737
2 Total Working load in IPS
210
3 Power factor To be improved (pf2)
0.98 Working load ( Tan ( Cos-1 pf1) - Tan (Cos-1 pf2))
Total kVAR to be connected across Bus 4 Total kVAR to be connected across Bus
kW
150
511
KVAR
Short circuit calculation CWPS main Pump Assumptions 1 Fault level at 220kV bus
20000 MVA
2 Base MVA
2000
Transformer Details at Chandaka220KV/132KV Ratio = 220kV / 132kV 100.00 MVA Capacity = 9.27% Z= 1 Nos Qty 8.34% Considering negative tolerance Z = 8.34% Net Z for transformers single transformer= 3 Transformer Details at Chandaka 132KV/33KV Ratio = 132kV / 33kV 40.00 MVA Capacity = 10.18% Z= 1 Nos Qty 9.16% Considering negative tolerance Z = 9.16% Net Z for transformers single transformer= 4 33kV Over head line from Chandaka to CWPS Line length = Conductor Type = Conductor Resiatance = Z,Considering Reactance Negligible =
15 DOG 0.2733 4.0995
kM Assumed ohm/kM ohm
5 Transformer at CWPS Ratio = 33kV / 3.3kV 1.25 MVA Capacity = 5.0% Z= 1 Nos Qty 4.5% Considering negative tolerance Z = 4.5% Net Z for transformers single transformer= 6
7
K' Constant for XLPE AL cable=
94
K' Constant for PVC AL cable=
75
K' Constant for PVC CU cable=
112
Fault clearing time for 33kV Breaker (t) = 1
Sec
Fault clearing time for 3.3kV Breaker (t) = 1
Sec
10
Starting Voltage dip =
11
Starting current for DOL=
6 times
12
Starting current for Y-D=
2 times
13
Starting current for FCMA softstarter=
2.5 times
15%
512
(as per IS :2026)
Calculation Sr No Description a chandaka Grid Substation
b
Impedance " Fault level Z" "MVA"
220KV Bus
0.1
220KV/132KV,100MVA transformer
1.7
1 132kV Bus
1.8
2 132kV/33kV,40MVA transformer
4.6
3 33kV Bus
6.3
Fault Current "kA"
Minimum Cable size "SQMM"
20000
52
1130.8
5
315.0
5.51
58.6
144.1
2.52
26.8
143.7
2.51
26.7
23.3
4.07
43.3 (XLPE,AL,3.3 kV)
22.8
3.98
42.4 (,AL,3.3 kV)
CWPS 1 15 kM 33kV O/H line from Chandaka Substation to CWPS
7.53
2 33kV Bus
13.88
33kV , XLPE, cable 3core x 95sqmm cable from 6 Pole 3 structure to 33KV panel 4 33kV panel 33kV , XLPE, cable 3core x 95sqmm cable from 33KV panel 5 to transformer
0.03950 13.92
0.000987
6 33kV/3.3kV, 1.25MVA transformer
72.00
7 3.3kV side of 1.25MVA transformer
86.02
3.3kV , XLPE, cable 3core x 300sqmm cable from 8 transformer secondary to CWPS PMCC
1.91
9 3.3kV CWPS PMCC Bus
87.83
513
! " #$# A) 1 2 2 3 4 5 6 7
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
%&" '(
= = = = = = =
Ish t K
B) 1 AREA OF CONDUCTOR 2 CABLE SIZE CHOSEN
C) LAYING CONDITIONS 1 AMBIENT AIR TEMPERATURE RATING FACTOR 2 GROUPING/SPACING WITH OTHER CABLES
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
= = =
Ish* t/K 43.2978723 50 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
= = =
45 0.95 Cable laid ground (3 cables touching)
= =
Ifl
2 CURRENT RATING REQ.AFTER CONSIDERING DERATING 3 Current carring capacity of 3C x300 Sqmm AL XLPE cable is 4 No of cable required E) 1 2 3 4 5 6
1250 3.3 0.8 4.07 1 94 70
CHECK FOR VOLTAGE DROP CABLE SIZE R AT CONDUCTOR TEMP. (3C x 300SQmm AL XLPE Cable) X AT CONDUCTOR TEMP. (3C x 300SQmm AL XLPE Cable) COSø SINø No of runs: % VOLTAGE DROP
7 % VOLTAGE DROP
0.69 0.6555
= = =
WORLING LOAD (KVA)/1.732 x VOLTAGE 218.70 FULL LOAD CURRENT/DERATING FACTOR 333.64 360 0.93
= =
= = = = = = =
=
CABLE SIZE CHOSEN
=
514
3C x300 Sqmm AL XLPE cable 0.13 0.072 0.8 0.6 1 (FULL LOAD CURRENT X LENGTH X IMPEDENCE)/NO OF RUNS X VOLTAGE 0.11827365 3CX300
sq.mm Al XLPE Cable
#$# A) 1 2 2 3 4 5 6 7
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
%&" '(
"
)
*+ "
= = = = = = =
Ish t K
B) 1 AREA OF CONDUCTOR 2 CABLE SIZE CHOSEN
C) LAYING CONDITIONS 1 AMBIENT AIR TEMPERATURE RATING FACTOR 2 GROUPING/SPACING WITH OTHER CABLES
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
= = =
Ish* t/K 42.34042553 50 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
= = =
45 0.95 Cable laid in trench (9 cables touching)
= =
Ifl
2 CURRENT RATING REQ.AFTER CONSIDERING DERATING 3 Current carring capacity of 3.5C x50 Sqmm AL XLPE cable is 4 No of cable required E) 1 2 3 4 5 6
349 3.3 0.8 3.98 1 94 40
0.76 0.722
= = =
WORLING LOAD (KVA)/1.732 x VOLTAGE x 1.732 35.25 FULL LOAD CURRENT/DERATING FACTOR 48.83 120 0.41
= =
CHECK FOR VOLTAGE DROP CABLE SIZE R AT CONDUCTOR TEMP. (3C x 50 SQmm AL XLPE Cable) X AT CONDUCTOR TEMP. (3C x 50 Qmm AL XLPE Cable) COSø SINø No of runs: % VOLTAGE DROP
7 % VOLTAGE DROP CABLE SIZE CHOSEN
515
= = = = = = =
3C x50 Sqmm AL XLPE cable 0.82 0.086 0.8 0.6 1 (FULL LOAD CURRENT X LENGTH X IMPEDENCE)/NO OF RUNS X VOLTAGE
=
0.052371797
=
3.5CX50
sq.mm Al XLPE Cable
Short circuit calculation CWPS Auxilary WTP load Assumptions 1 Fault level at 220kV bus
20000 MVA
2 Base MVA
(as per IS :2026)
2000
Transformer Details at Chandaka220KV/132KV Ratio = 220kV / 132kV 100.00 MVA Capacity = 9.27% Z= 1 Nos Qty 8.34% Considering negative tolerance Z = 8.34% Net Z for transformers single transformer= 3 Transformer Details at Chandaka 132KV/33KV Ratio = 132kV / 33kV 40.00 MVA Capacity = 10.18% Z= 1 Nos Qty 9.16% Considering negative tolerance Z = 9.16% Net Z for transformers single transformer= 4 33kV Over head line from Chandaka to CWPS Line length = Conductor Type = Conductor Resiatance = Z,Considering Reactance Negligible =
15 DOG 0.2733 4.0995
kM Assumed ohm/kM ohm
5 Transformer at CWPS Ratio = 33kV / 0.415kV 0.32 MVA Capacity = 4.5% Z= 1 Nos Qty 4.1% Considering negative tolerance Z = 4.1% Net Z for transformers single transformer= 6
7
K' Constant for XLPE AL cable=
94
K' Constant for PVC AL cable=
75
K' Constant for PVC CU cable=
112
Fault clearing time for 33kV Breaker (t) = 1
Sec
Fault clearing time for 0.415kV ACB Breaker (t) = 0.08
Sec
Fault clearing time for 0.415kV MCCB Breaker (t) = 0.04
Sec
10
Starting Voltage dip =
11
Starting current for DOL=
6 times
12
Starting current for Y-D=
3.5 times
13
Starting current for FCMA softstarter=
2.5 times
15%
Formula used 1
2
Zsource =
Ztransformer =
Base MVA Fault level at 132kV bus Base MVA Transformer capacity in MVA
X tranformer Z%
3
Zline =
Base MVA kV2
X Line Z
4
Zcable =
Base MVA 2 kV
X Cable Z
516
Calculation Sr No Description a chandaka Grid Substation
Impedance " Fault level Z" "MVA"
1
220KV Bus
0.1
2
220KV/132KV,100MVA transformer
1.7
b
3 132kV Bus
1.8
4 132kV/33kV,40MVA transformer
4.6
5 33kV Bus
6.3
Fault Current "kA"
Minimum Cable size "SQMM"
20000
52
1130.8
5
315.0
5.51
144.1
2.52
26.8
7.4
10.27
30.9 (XLPE,AL,0.415kV)
6.4
8.93
26.9 (,AL,0.415 kV)
5.1
7.08
15.1 (,AL,0.415 kV)
2.4
3.39
7.2 (,AL,0.415 kV)
CWPS 1 15 kM 33kV O/H line from Chandaka Substation to CWPS
7.53
2 33kV Bus
13.88
4 33kV/0.415kV, 315KVA transformer
257.14
5 0.415kV side of 315KVA transformer
271.02
0.415kV , XLPE, cable 2 X 3.5c x 240.sqmm cable from 6 transformer secondary to CWPS PMCC
40.66
7 0.415kV CWPS AUXILARY MCC
311.68
0.415kV , XLPE, cable 2 x 3.5core x 120sqmm cable from 8 CWPS PMCC to Motor (160KW)
81.31
9 0.415kV 160KW motor (194)
392.99
0.415kV , XLPE, cable 3.5C x 240sqmm cable from CWPS 10 PMCC to WTP & Chemical
508.19
11 0.415kV WTP & Chemical
819.87
517
" A) 1 2 2 3 4 5 6 7
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
"
*,
-+
= = = = = = =
Ish t K
B) 1 AREA OF CONDUCTOR 2 CABLE SIZE CHOSEN
C) LAYING CONDITIONS 1 AMBIENT AIR TEMPERATURE RATING FACTOR 2 GROUPING/SPACING WITH OTHER CABLES
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
= = =
Ish* t/K 30.90207082 35 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
= = =
45 0.95 Cable directly burried (3 cables touching)
= =
Ifl
0.69 0.6555
= = =
2 CURRENT RATING REQ.AFTER CONSIDERING DERATING 3 Current carring capacity of 3.5C x240 Sqmm AL XLPE cable is 4 No of cable required E) 1 2 3 4 5 6
315 0.415 0.8 10.27 0.08 94 40
WORLING LOAD (KVA)/1.732 x VOLTAGE 438.24 FULL LOAD CURRENT/DERATING FACTOR 668.56 326 2.05
= =
CHECK FOR VOLTAGE DROP CABLE SIZE R AT CONDUCTOR TEMP. (3.5C x 240 SQmm AL XLPE Cable) X AT CONDUCTOR TEMP. (3.5C x 240 Qmm AL XLPE Cable) COSø SINø No of runs: % VOLTAGE DROP
7 % VOLTAGE DROP
= = = = = = =
=
CABLE SIZE CHOSEN
=
518
3.5C x240 Sqmm AL XLPE cable 0.16 0.071 0.8 0.6 2 (FULL LOAD CURRENT X LENGTH X IMPEDENCE)/NO OF RUNS X VOLTAGE 0.624055741 2X3.5CX240
sq.mm Al XLPE Cable
*, A) 1 2 2 3 4 5 6 7
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
-+
"
.
*
"
= = = = = = =
Ish t K
B) 1 AREA OF CONDUCTOR
= = =
2 CABLE SIZE CHOSEN
C) LAYING CONDITIONS 1 AMBIENT AIR TEMPERATURE RATING FACTOR 2 GROUPING/SPACING WITH OTHER CABLES
19 25 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
45 0.95 Cable laid in trench (9 cables touching)
= =
Ifl
2 CURRENT RATING REQ.AFTER CONSIDERING DERATING 3 Current carring capacity of 3C x120 Sqmm AL XLPE cable is 4 No of cable required E) 1 2 3 4 5 6
Ish* t/K
= = =
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
194 0.415 0.8 8.93 0.04 94 40
0.66 0.627
= = =
WORLING LOAD (KVA)/1.732 x VOLTAGE x 1.732 155.83 FULL LOAD CURRENT/DERATING FACTOR 248.54 257 0.97
= =
CHECK FOR VOLTAGE DROP CABLE SIZE R AT CONDUCTOR TEMP. (3C x 120SQmm AL XLPE Cable) X AT CONDUCTOR TEMP. (3C x 120 Qmm AL XLPE Cable) COSø SINø No of runs: % VOLTAGE DROP
7 % VOLTAGE DROP CABLE SIZE CHOSEN
519
= = = = = = =
3C x120 Sqmm AL XLPE cable 0.324 0.0712 0.8 0.6 1 (FULL LOAD CURRENT X LENGTH X IMPEDENCE)/NO OF RUNS X VOLTAGE
=
0.785433685
=
2X3CX120
sq.mm Al XLPE Cable
*, A) 1 2 2 3 4 5 6 7
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
-+
" #/ *
"
= = = = = = =
Ish t K
B) 1 AREA OF CONDUCTOR
= = =
2 CABLE SIZE CHOSEN
C) LAYING CONDITIONS 1 AMBIENT AIR TEMPERATURE RATING FACTOR 2 GROUPING/SPACING WITH OTHER CABLES
19 25 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
45 0.95 Cable laid in trench (9 cables touching)
= =
0.66 0.627
= = =
Ifl
2 CURRENT RATING REQ.AFTER CONSIDERING DERATING 3 Current carring capacity of 3C x25 Sqmm AL XLPE cable is 4 No of cable required E) 1 2 3 4 5 6
Ish* t/K
= = =
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
46 0.415 0.8 8.93 0.04 94 40
WORLING LOAD (KVA)/1.732 x VOLTAGE x 1.732 36.95 FULL LOAD CURRENT/DERATING FACTOR 58.93 96 0.61
= =
CHECK FOR VOLTAGE DROP CABLE SIZE R AT CONDUCTOR TEMP. (3C x 25SQmm AL XLPE Cable) X AT CONDUCTOR TEMP. (3C x 25 Qmm AL XLPE Cable) COSø SINø No of runs: % VOLTAGE DROP
= = = = = = =
7 % VOLTAGE DROP
=
CABLE SIZE CHOSEN
=
520
3C x25 Sqmm AL XLPE cable 1.54 0.0805 0.8 0.6 1 (FULL LOAD CURRENT X LENGTH X IMPEDENCE)/NO OF RUNS X VOLTAGE 0.789742459 2X3CX25
sq.mm Al XLPE Cable
+ *, A) 1 2 2 3 4 5 6 7
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
-+
" * ,
+
= = = = = = =
Ish t K
B) 1 AREA OF CONDUCTOR
= = =
2 CABLE SIZE CHOSEN
C) LAYING CONDITIONS 1 AMBIENT AIR TEMPERATURE RATING FACTOR 2 GROUPING/SPACING WITH OTHER CABLES
19 25 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
45 0.95 Cable directly burried (3 cables touching)
= =
Ifl
2 CURRENT RATING REQ.AFTER CONSIDERING DERATING 3 Current carring capacity of 3.5C x240 Sqmm AL XLPE cable is 4 No of cable required E) 1 2 3 4 5 6
Ish* t/K
= = =
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
91 0.415 0.8 8.93 0.04 94 250
CHECK FOR VOLTAGE DROP CABLE SIZE R AT CONDUCTOR TEMP. (3.5C x 300 SQmm AL XLPE Cable) X AT CONDUCTOR TEMP. (3.5C x 300Qmm AL XLPE Cable) COSø SINø No of runs: % VOLTAGE DROP
7 % VOLTAGE DROP
0.69 0.6555
= = =
WORLING LOAD (KVA)/1.732 x VOLTAGE 126.60 FULL LOAD CURRENT/DERATING FACTOR 193.14 367 0.53
= =
= = = = = = =
=
CABLE SIZE CHOSEN
=
521
3.5C x240 Sqmm AL XLPE cable 0.128 0.0705 0.8 0.6 1 (FULL LOAD CURRENT X LENGTH X IMPEDENCE)/NO OF RUNS X VOLTAGE 1.911409493 3.5CX300
sq.mm Al XLPE Cable
* , A) 1 2 2 3 4 5 6 7
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
'
& 0+
"
,1
= = = = = = =
Ish t K
B) 1 AREA OF CONDUCTOR 2 CABLE SIZE CHOSEN
C) LAYING CONDITIONS 1 AMBIENT AIR TEMPERATURE RATING FACTOR 2 GROUPING/SPACING WITH OTHER CABLES
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
= = =
Ish* t/K 7.212765957 10 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
= = =
45 0.95 Cable directly burried (6 cables touching)
= =
Ifl
2 CURRENT RATING REQ.AFTER CONSIDERING DERATING 3 Current carring capacity of 3.5C x35 Sqmm AL XLPE cable is 4 No of cable required E) 1 2 3 4 5 6
20 0.415 0.8 3.39 0.04 94 120
0.54 0.513
= = =
WORLING LOAD (KVA)/1.732 x VOLTAGE 27.82 FULL LOAD CURRENT/DERATING FACTOR 54.24 113 0.48
= =
CHECK FOR VOLTAGE DROP CABLE SIZE R AT CONDUCTOR TEMP. (3.5C x 35 SQmm AL XLPE Cable) X AT CONDUCTOR TEMP. (3.5C x 35 Qmm AL XLPE Cable) COSø SINø No of runs: % VOLTAGE DROP
7 % VOLTAGE DROP CABLE SIZE CHOSEN
522
= = = = = = =
3.5C x35 Sqmm AL XLPE cable 1.11 0.0783 0.8 0.6 1 (FULL LOAD CURRENT X LENGTH X IMPEDENCE)/NO OF RUNS X VOLTAGE
=
1.302918856
=
3.5CX35
sq.mm Al XLPE Cable
* , A) 1 2 2 3 4 5 6 7
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
'
& 0+
"
,1
Ish t K
B) 1 AREA OF CONDUCTOR 2 CABLE SIZE CHOSEN
C) LAYING CONDITIONS 1 AMBIENT AIR TEMPERATURE RATING FACTOR 2 GROUPING/SPACING WITH OTHER CABLES
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
5.6 7 0.415 0.8 3.39 0.04 94 120
= = = = = = =
= = =
Ish* t/K 7.212765957 10 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
= = =
45 0.95 Cable directly burried (6 cables touching)
= =
0.54 0.513
Ifl
= = 2 CURRENT RATING REQ.AFTER CONSIDERING DERATING =
3 Current carring capacity of 4C x16 Sqmm AL XLPE cable is 4 No of cable required E) 1 2 3 4 5 6
WORLING LOAD (KVA)/1.732 x VOLTAGE 9.74 FULL LOAD CURRENT/DERATING FACTOR 18.98 67 0.28
= =
CHECK FOR VOLTAGE DROP CABLE SIZE = R AT CONDUCTOR TEMP. (4C x16 SQmm AL XLPE Cable) = X AT CONDUCTOR TEMP. (4C x16 Qmm AL XLPE Cable) = COSø = SINø = No of runs: = % VOLTAGE DROP =
7 % VOLTAGE DROP CABLE SIZE CHOSEN
523
4C x16 Sqmm AL XLPE cable 2.44 0.0837 0.8 0.6 1 (FULL LOAD CURRENT X LENGTH X IMPEDENCE)/NO OF RUNS X VOLTAGE
=
0.976550907
=
4CX16
sq.mm Al XLPE Cable
* , A) 1 2 2 3 4 5 6 7
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
'
& 0+
"
Ish t K
2 CABLE SIZE CHOSEN
C) LAYING CONDITIONS 1 AMBIENT AIR TEMPERATURE RATING FACTOR 2 GROUPING/SPACING WITH OTHER CABLES
RATING FACTOR 3 OVERALL DERATING FACTOR
= = =
Ish* t/K 7.212765957 10 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
= = =
45 0.95 Cable directly burried (6 cables touching)
= =
Ifl
2 CURRENT RATING REQ.AFTER CONSIDERING DERATING 3 Current carring capacity of 4C x16 Sqmm AL XLPE cable is 4 No of cable required E) 1 2 3 4 5 6
12 15 0.415 0.8 3.39 0.04 94 105
= = = = = = =
B) 1 AREA OF CONDUCTOR
D) 1 FULL LOAD CURRENT
,1#
CHECK FOR VOLTAGE DROP CABLE SIZE R AT CONDUCTOR TEMP. (4C x16 SQmm AL XLPE Cable) X AT CONDUCTOR TEMP. (4C x16 Qmm AL XLPE Cable) COSø SINø No of runs: % VOLTAGE DROP
7 % VOLTAGE DROP CABLE SIZE CHOSEN
524
0.54 0.513
= = =
WORLING LOAD (KVA)/1.732 x VOLTAGE 20.87 FULL LOAD CURRENT/DERATING FACTOR 40.68 67 0.61
= =
= = = = = = =
4C x16 Sqmm AL XLPE cable 2.44 0.0837 0.8 0.6 1 (FULL LOAD CURRENT X LENGTH X IMPEDENCE)/NO OF RUNS X VOLTAGE
=
1.831032951
=
4CX16
sq.mm Al XLPE Cable
*, A) 1 2 2 3 4 5 6 7
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
23&0 ! +
" /
4 &"
= = = = = = =
Ish t K
B) 1 AREA OF CONDUCTOR
= = =
2 CABLE SIZE CHOSEN
C) LAYING CONDITIONS 1 AMBIENT AIR TEMPERATURE RATING FACTOR 2 GROUPING/SPACING WITH OTHER CABLES
19 25 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
45 0.95 Cable laid in trench (9 cables touching)
= =
Ifl
2 CURRENT RATING REQ.AFTER CONSIDERING DERATING Considering 35% extra current 3 Current carring capacity of 3.5C x120 Sqmm AL XLPE cable is 4 No of cable required E) 1 2 3 4 5 6
Ish* t/K
= = =
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
75 0.415 0.8 8.93 0.04 94 25
CHECK FOR VOLTAGE DROP CABLE SIZE R AT CONDUCTOR TEMP. (3.5C x 120 SQmm AL XLPE Cable) X AT CONDUCTOR TEMP. (3.5C x 120 Qmm AL XLPE Cable) COSø SINø No of runs: % VOLTAGE DROP
7 % VOLTAGE DROP
0.66 0.627
= = =
WORLING LOAD (KVA)/1.732 x VOLTAGE 104.34 FULL LOAD CURRENT/DERATING FACTOR 166.42 224.66 257 0.87
= =
= = = = = = =
=
CABLE SIZE CHOSEN
=
525
3.5C x120 Sqmm AL XLPE cable 0.264 0.0716 0.8 0.6 1 (FULL LOAD CURRENT X LENGTH X IMPEDENCE)/NO OF RUNS X VOLTAGE 0.276701989 3.5CX120
sq.mm Al XLPE Cable
!" A) 1 2 2 3 4 5 6 7
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
Ish t K
B) 1 AREA OF CONDUCTOR
= = = = = = =
100 0.415 0.8 3.09 0.08 94 25
= = =
2 CABLE SIZE CHOSEN
Ish* t/K 9.297701931 10 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
C) LAYING CONDITIONS = 1 AMBIENT AIR TEMPERATURE RATING FACTOR = 2 GROUPING/SPACING WITH OTHER CABLES =
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
#
45 0.95 Cable laid in ground (3 cables touching)
= =
0.69 0.6555
= WORLING LOAD (KVA)/1.732 x VOLTAGE = 139.12 = DERATING FULL LOAD CURRENT/DERATING FACTOR 2 CURRENT RATING REQ.AFTER CONSIDERING 212.24 = cable is 223 3 Current carring capacity of 3.5C x120 Sqmm AL XLPE 4 No of cable required = 0.95
E) 1 2 3 4 5 6
Ifl
CHECK FOR VOLTAGE DROP CABLE SIZE = 3.5C x120 Sqmm AL XLPE cable R AT CONDUCTOR TEMP. (3.5C x 120 SQmm AL=XLPE Cable)0.324 X AT CONDUCTOR TEMP. (3.5C x 120 Qmm AL XLPE = Cable) 0.0712 COSø = 0.8 SINø = 0.6 No of runs: = 1 (FULL LOAD CURRENT X LENGTH X % VOLTAGE DROP = IMPEDENCE)/NO OF RUNS X VOLTAGE
7 % VOLTAGE DROP
=
CABLE SIZE CHOSEN
=
526
0.438263899 3.5CX120
sq.mm Al XLPE Cable
$ A) 1 2 2 3 4 5 6 7
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
!"
Ish t K
B) 1 AREA OF CONDUCTOR
#
%% &
= = = = = = =
29 0.415 0.8 2.64 0.08 94 45
= = =
2 CABLE SIZE CHOSEN
Ish* t/K 7.943667669 10 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
C) LAYING CONDITIONS = 1 AMBIENT AIR TEMPERATURE RATING FACTOR = 2 GROUPING/SPACING WITH OTHER CABLES =
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
45 0.95 Cable laid in trench (9 cables touching)
=
0.66 0.627
= WORLING LOAD (KVA)/1.732 x VOLTAGE = 40.35 = DERATING FULL LOAD CURRENT/DERATING FACTOR 2 CURRENT RATING REQ.AFTER CONSIDERING 64.35 70 3 Current carring capacity of 3C x16 Sqmm AL XLPE=cable is 4 No of cable required = 0.92
E) 1 2 3 4 5 6
Ifl
CHECK FOR VOLTAGE DROP CABLE SIZE = 3C x16Sqmm AL XLPE cable R AT CONDUCTOR TEMP. (3C x 16 SQmm AL XLPE = Cable) 2.44 X AT CONDUCTOR TEMP. (3C x 16 Qmm AL XLPE = Cable) 0.0808 COSø = 0.8 SINø = 0.6 No of runs: = 1 (FULL LOAD CURRENT X LENGTH X % VOLTAGE DROP = IMPEDENCE)/NO OF RUNS X VOLTAGE
7 % VOLTAGE DROP
=
CABLE SIZE CHOSEN
=
527
1.515823138 2X3CX16
sq.mm Al XLPE Cable
$ A) 1 2 2 3 4 5 6 7
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
!"
Ish t K
B) 1 AREA OF CONDUCTOR
#
&
= = = = = = =
16 0.415 0.8 2.64 0.08 94 55
= = =
2 CABLE SIZE CHOSEN
Ish* t/K 7.943667669 10 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
C) LAYING CONDITIONS = 1 AMBIENT AIR TEMPERATURE RATING FACTOR = 2 GROUPING/SPACING WITH OTHER CABLES =
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
45 0.95 Cable laid in trench (9 cables touching)
= =
0.66 0.627
= WORLING LOAD (KVA)/1.732 x VOLTAGE = 22.26 2 CURRENT RATING REQ.AFTER CONSIDERING = DERATING FULL LOAD CURRENT/DERATING FACTOR 35.50 3 Current carring capacity of 3C x10 Sqmm AL XLPE= cable is 67 4 No of cable required = 0.53
E) 1 2 3 4 5 6
Ifl
CHECK FOR VOLTAGE DROP CABLE SIZE = 3C x10 Sqmm AL XLPE cable R AT CONDUCTOR TEMP. (3C x 10 SQmm AL XLPE = Cable) 3.94 X AT CONDUCTOR TEMP. (3C x 10 Qmm AL XLPE = Cable) 0.0837 COSø = 0.8 SINø = 0.6 No of runs: = 1 % VOLTAGE DROP = (FULL LOAD CURRENT X LENGTH X IMPEDENCE)/NO OF RUNS X VOLTAGE
7 % VOLTAGE DROP
=
CABLE SIZE CHOSEN
=
528
1.636204732 2X3CX10
sq.mm Al XLPE Cable
$ A) 1 2 2 3 4 5 6 7
!"
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
Ish t K
B) 1 AREA OF CONDUCTOR
#
%
'
= = = = = = =
20 0.415 0.8 2.64 0.08 94 35
= = =
2 CABLE SIZE CHOSEN
Ish* t/K 7.943667669 10 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
C) LAYING CONDITIONS = 1 AMBIENT AIR TEMPERATURE RATING FACTOR = 2 GROUPING/SPACING WITH OTHER CABLES =
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
45 0.95 Cable laid in trench (9 cables touching)
= =
0.66 0.627
= WORLING LOAD (KVA)/1.732 x VOLTAGE = 27.82 = DERATING FULL LOAD CURRENT/DERATING FACTOR 2 CURRENT RATING REQ.AFTER CONSIDERING 44.38 Considering 35% extra current 59.91 3 Current carring capacity of 4C x10 Sqmm AL XLPE= cable is 67 4 No of cable required = 0.89
E) 1 2 3 4 5 6
Ifl
CHECK FOR VOLTAGE DROP CABLE SIZE = 4C x10 Sqmm AL XLPE cable R AT CONDUCTOR TEMP. (4C x 10 SQmm AL XLPE = Cable) 3.94 X AT CONDUCTOR TEMP. (4C x 10 Qmm AL XLPE = Cable) 0.0837 COSø = 0.8 SINø = 0.6 No of runs: = 1 (FULL LOAD CURRENT X LENGTH X % VOLTAGE DROP = IMPEDENCE)/NO OF RUNS X VOLTAGE
7 % VOLTAGE DROP
=
CABLE SIZE CHOSEN
=
529
1.301526492 4CX10
sq.mm Al XLPE Cable
$ A) 1 2 2 3 4 5 6 7
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
!"
Ish t K
B) 1 AREA OF CONDUCTOR
# 10 12.5 0.415 0.8 2.64 0.08 94 30
= = = = = = =
= = =
2 CABLE SIZE CHOSEN
Ish* t/K 7.943667669 10 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
C) LAYING CONDITIONS = 1 AMBIENT AIR TEMPERATURE RATING FACTOR = 2 GROUPING/SPACING WITH OTHER CABLES =
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
45 0.95 Cable laid in trench (9 cables touching)
= =
0.66 0.627
= WORLING LOAD (KVA)/1.732 x VOLTAGE = 17.39 = DERATING FULL LOAD CURRENT/DERATING FACTOR 2 CURRENT RATING REQ.AFTER CONSIDERING 27.74 67 3 Current carring capacity of 4C x10 Sqmm AL XLPE= cable is 4 No of cable required = 0.41
E) 1 2 3 4 5 6
Ifl
CHECK FOR VOLTAGE DROP CABLE SIZE = 4C x10 Sqmm AL XLPE cable R AT CONDUCTOR TEMP. (4C x 10 SQmm AL XLPE = Cable) 3.94 X AT CONDUCTOR TEMP. (4C x 10 Qmm AL XLPE = Cable) 0.0837 COSø = 0.8 SINø = 0.6 No of runs: = 1 (FULL LOAD CURRENT X LENGTH X % VOLTAGE DROP = IMPEDENCE)/NO OF RUNS X VOLTAGE
7 % VOLTAGE DROP
=
CABLE SIZE CHOSEN
=
530
0.697246335 4CX10
sq.mm Al XLPE Cable
TRANSFORMER SIZING FOR JATNI (KAJU PLANTATION) PUMPING STATION
1.0
Formula Used:
1.1
Working Load in kVA
=
[ Working Load (kW) x L. F. ] / [ D. F. x P. F. x Effi. ]
1.2
System P. F.
=
Total Working Load (kW) / Total Working Load (kVA)
2.0
L. F.
= Load Factor
P. F.
= Motor Power Factor
D. F.
= Diversity Factor
Effi.
= Motor Efficiency
Input Data and Calculations:
Sr. No.
Item Description
Connected Load
Rating in kW
Effi.
P. F.
L. F.
D. F.
Working Load
Unit
Total (kW)
Unit
Total (kW)
Working Load (kVA)
2.1
Pump-1
22
0.917
0.83
0.9
1
2
44
1
19.8
26.01
2.2
Pump-2
11
0.892
0.81
0.9
1
2
22
2
19.8
27.40
2.3
Chain pully
2
0.83
0.82
1
2
1
2
1
1
1.47
2.4 2.5
Exhaust Fan
0.5 10
0.67 0.8
0.82 0.8
1 1
1 1.5
6 Lumpsum
3 10 81
Lighting Total Load
3.0
Considering 20% contingency
=
4.0
System P. F.
=
0.71
5.0 5.1 5.2 5.3 5.4 5.5 5.6
Calculation to check the starting of largest size motor Rating of transformer assumed % impedance of transformer assumed Rating of the largest size motor Supply voltage P.F of largest size motor Efficiency of largest size motor
= = = = = =
100 4.5 22 0.415 0.83 0.917
6 3 Lumpsum 6.6666667 50.266667
5.46 10.42 70.77
84.92 kVA
kVA % KW kV
Nearest staanddard size (Confg. 11/0.433KV,Dyn11,Delta-star) From IS 2026 From the above table System voltage From the above table From the above table kW x 1000 1.7321 x V x p.f x efficiency kW P.F x Efficiency
5.7
FLC of motor
=
40.212 A
5.8
Rating of largest size motor in kVA
=
28.905 kVA
=
71.095 kVA
(Rating in kVA of transformer assumed - Largest motor KVA)
=
173.43 kVA
= 6 x 1.7321 x kV x I FLC = 3 x 1.7321 x kV x I FLC
5.10
Base load on transformer before starting fourth largest motor Motor starting Kva with DOL start
5.11
Motor starting Kva with Star-Delta start
=
101.17 kVA
5.12
Fault Level at transformer secondary side
=
2.2222 MVA
5.13
Fault current of transformer secondary side (ISC)
=
3.0915 kA
5.14
S.C capacity of transformer Voltage drop at transformer terminal when largest motor start with DOL starting Voltage drop at transformer terminal when largest motor start with Star-Delta starting
=
2222.2 kVA
=
11.004 %
=
7.8 %
5.9
5.15 5.16
Rating of transformer in MVA x 100 Impedance of transformer in % Fault Level in MVA 1.7321 x kV 1.7321 x kV x I SC [Motor Starting kVA (DOL) + Base Load kVA] x 100 S.C capacity of transformer [Motor Starting kVA (S/D) + Base Load kVA] x 100 S.C capacity of transformer
The selected rating of transformer is
531
100 kVA
(within 10%) (within 10%)
CAPACITOR BANK SIZING ACROSS BUS
1 Average Power factor (pf1) 2 Total Working load 3 Power factor To be improved (pf2)
0.710 50 0.98 Working load ( Tan ( Cos-1 pf1) - Tan (Cos-1 pf2))
Total kVAR to be connected across Bus 4 Total kVAR to be connected across Bus
kW
40
532
KVAR
TRANSFORMER SIZING FOR JATNI (KAJU PLANTATION) PUMPING STATION
1.0
Formula Used:
1.1
Working Load in kVA
=
[ Working Load (kW) x L. F. ] / [ D. F. x P. F. x Effi. ]
1.2
System P. F.
=
Total Working Load (kW) / Total Working Load (kVA)
2.0
L. F.
= Load Factor
P. F.
= Motor Power Factor
D. F.
= Diversity Factor
Effi.
= Motor Efficiency
Input Data and Calculations:
Sr. No.
Item Description
Connected Load
Rating in kW
Effi.
P. F.
L. F.
D. F.
Working Load
Unit
Total (kW)
Unit
Total (kW)
Working Load (kVA)
2.1
Pump-1
22
0.917
0.83
0.9
1
2
44
1
19.8
26.01
2.2
Pump-2
11
0.892
0.81
0.9
1
2
22
2
19.8
27.40
2.3
Chain pully
2
0.83
0.82
1
2
1
2
1
1
1.47
2.4 2.5
Exhaust Fan
0.5 10
0.67 0.8
0.82 0.8
1 1
1 1.5
6 Lumpsum
3 10 81
Lighting Total Load
3.0
Considering 20% contingency
=
4.0
System P. F.
=
0.71
5.0 5.1 5.2 5.3 5.4 5.5 5.6
Calculation to check the starting of largest size motor Rating of transformer assumed % impedance of transformer assumed Rating of the largest size motor Supply voltage P.F of largest size motor Efficiency of largest size motor
= = = = = =
100 4.5 22 0.415 0.83 0.917
6 3 Lumpsum 6.6666667 50.266667
5.46 10.42 70.77
84.92 kVA
kVA % KW kV
Nearest staanddard size (Confg. 11/0.433KV,Dyn11,Delta-star) From IS 2026 From the above table System voltage From the above table From the above table kW x 1000 1.7321 x V x p.f x efficiency kW P.F x Efficiency
5.7
FLC of motor
=
40.212 A
5.8
Rating of largest size motor in kVA
=
28.905 kVA
=
71.095 kVA
(Rating in kVA of transformer assumed - Largest motor KVA)
=
173.43 kVA
= 6 x 1.7321 x kV x I FLC = 3 x 1.7321 x kV x I FLC
5.10
Base load on transformer before starting fourth largest motor Motor starting Kva with DOL start
5.11
Motor starting Kva with Star-Delta start
=
101.17 kVA
5.12
Fault Level at transformer secondary side
=
2.2222 MVA
5.13
Fault current of transformer secondary side (ISC)
=
3.0915 kA
5.14
S.C capacity of transformer Voltage drop at transformer terminal when largest motor start with DOL starting Voltage drop at transformer terminal when largest motor start with Star-Delta starting
=
2222.2 kVA
=
11.004 %
=
7.8 %
5.9
5.15 5.16
Rating of transformer in MVA x 100 Impedance of transformer in % Fault Level in MVA 1.7321 x kV 1.7321 x kV x I SC [Motor Starting kVA (DOL) + Base Load kVA] x 100 S.C capacity of transformer [Motor Starting kVA (S/D) + Base Load kVA] x 100 S.C capacity of transformer
The selected rating of transformer is
533
100 kVA
(within 10%) (within 10%)
CAPACITOR BANK SIZING ACROSS BUS
1 Average Power factor (pf1) 2 Total Working load 3 Power factor To be improved (pf2)
0.710 50 0.98 Working load ( Tan ( Cos-1 pf1) - Tan (Cos-1 pf2))
Total kVAR to be connected across Bus 4 Total kVAR to be connected across Bus
kW
40
534
KVAR
!" A) 1 2 2 3 4 5 6 7
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
Ish t K
B) 1 AREA OF CONDUCTOR
= = = = = = =
100 0.415 0.8 3.09 0.08 94 25
= = =
2 CABLE SIZE CHOSEN
Ish* t/K 9.297701931 10 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
C) LAYING CONDITIONS = 1 AMBIENT AIR TEMPERATURE RATING FACTOR = 2 GROUPING/SPACING WITH OTHER CABLES =
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
#
45 0.95 Cable laid in ground (3 cables touching)
= =
0.69 0.6555
= WORLING LOAD (KVA)/1.732 x VOLTAGE = 139.12 = DERATING FULL LOAD CURRENT/DERATING FACTOR 2 CURRENT RATING REQ.AFTER CONSIDERING 212.24 = cable is 223 3 Current carring capacity of 3.5C x120 Sqmm AL XLPE 4 No of cable required = 0.95
E) 1 2 3 4 5 6
Ifl
CHECK FOR VOLTAGE DROP CABLE SIZE = 3.5C x120 Sqmm AL XLPE cable R AT CONDUCTOR TEMP. (3.5C x 120 SQmm AL=XLPE Cable)0.324 X AT CONDUCTOR TEMP. (3.5C x 120 Qmm AL XLPE = Cable) 0.0712 COSø = 0.8 SINø = 0.6 No of runs: = 1 (FULL LOAD CURRENT X LENGTH X % VOLTAGE DROP = IMPEDENCE)/NO OF RUNS X VOLTAGE
7 % VOLTAGE DROP
=
CABLE SIZE CHOSEN
=
535
0.438263899 3.5CX120
sq.mm Al XLPE Cable
$ A) 1 2 2 3 4 5 6 7
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
!"
Ish t K
B) 1 AREA OF CONDUCTOR
#
%% &
= = = = = = =
29 0.415 0.8 2.64 0.08 94 45
= = =
2 CABLE SIZE CHOSEN
Ish* t/K 7.943667669 10 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
C) LAYING CONDITIONS = 1 AMBIENT AIR TEMPERATURE RATING FACTOR = 2 GROUPING/SPACING WITH OTHER CABLES =
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
45 0.95 Cable laid in trench (9 cables touching)
=
0.66 0.627
= WORLING LOAD (KVA)/1.732 x VOLTAGE = 40.35 = DERATING FULL LOAD CURRENT/DERATING FACTOR 2 CURRENT RATING REQ.AFTER CONSIDERING 64.35 70 3 Current carring capacity of 3C x16 Sqmm AL XLPE=cable is 4 No of cable required = 0.92
E) 1 2 3 4 5 6
Ifl
CHECK FOR VOLTAGE DROP CABLE SIZE = 3C x16Sqmm AL XLPE cable R AT CONDUCTOR TEMP. (3C x 16 SQmm AL XLPE = Cable) 2.44 X AT CONDUCTOR TEMP. (3C x 16 Qmm AL XLPE = Cable) 0.0808 COSø = 0.8 SINø = 0.6 No of runs: = 1 (FULL LOAD CURRENT X LENGTH X % VOLTAGE DROP = IMPEDENCE)/NO OF RUNS X VOLTAGE
7 % VOLTAGE DROP
=
CABLE SIZE CHOSEN
=
536
1.515823138 2X3CX16
sq.mm Al XLPE Cable
$ A) 1 2 2 3 4 5 6 7
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
!"
Ish t K
B) 1 AREA OF CONDUCTOR
#
&
= = = = = = =
16 0.415 0.8 2.64 0.08 94 55
= = =
2 CABLE SIZE CHOSEN
Ish* t/K 7.943667669 10 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
C) LAYING CONDITIONS = 1 AMBIENT AIR TEMPERATURE RATING FACTOR = 2 GROUPING/SPACING WITH OTHER CABLES =
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
45 0.95 Cable laid in trench (9 cables touching)
= =
0.66 0.627
= WORLING LOAD (KVA)/1.732 x VOLTAGE = 22.26 2 CURRENT RATING REQ.AFTER CONSIDERING = DERATING FULL LOAD CURRENT/DERATING FACTOR 35.50 3 Current carring capacity of 3C x10 Sqmm AL XLPE= cable is 67 4 No of cable required = 0.53
E) 1 2 3 4 5 6
Ifl
CHECK FOR VOLTAGE DROP CABLE SIZE = 3C x10 Sqmm AL XLPE cable R AT CONDUCTOR TEMP. (3C x 10 SQmm AL XLPE = Cable) 3.94 X AT CONDUCTOR TEMP. (3C x 10 Qmm AL XLPE = Cable) 0.0837 COSø = 0.8 SINø = 0.6 No of runs: = 1 % VOLTAGE DROP = (FULL LOAD CURRENT X LENGTH X IMPEDENCE)/NO OF RUNS X VOLTAGE
7 % VOLTAGE DROP
=
CABLE SIZE CHOSEN
=
537
1.636204732 2X3CX10
sq.mm Al XLPE Cable
$ A) 1 2 2 3 4 5 6 7
!"
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
Ish t K
B) 1 AREA OF CONDUCTOR
#
%
'
= = = = = = =
20 0.415 0.8 2.64 0.08 94 35
= = =
2 CABLE SIZE CHOSEN
Ish* t/K 7.943667669 10 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
C) LAYING CONDITIONS = 1 AMBIENT AIR TEMPERATURE RATING FACTOR = 2 GROUPING/SPACING WITH OTHER CABLES =
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
45 0.95 Cable laid in trench (9 cables touching)
= =
0.66 0.627
= WORLING LOAD (KVA)/1.732 x VOLTAGE = 27.82 = DERATING FULL LOAD CURRENT/DERATING FACTOR 2 CURRENT RATING REQ.AFTER CONSIDERING 44.38 Considering 35% extra current 59.91 3 Current carring capacity of 4C x10 Sqmm AL XLPE= cable is 67 4 No of cable required = 0.89
E) 1 2 3 4 5 6
Ifl
CHECK FOR VOLTAGE DROP CABLE SIZE = 4C x10 Sqmm AL XLPE cable R AT CONDUCTOR TEMP. (4C x 10 SQmm AL XLPE = Cable) 3.94 X AT CONDUCTOR TEMP. (4C x 10 Qmm AL XLPE = Cable) 0.0837 COSø = 0.8 SINø = 0.6 No of runs: = 1 (FULL LOAD CURRENT X LENGTH X % VOLTAGE DROP = IMPEDENCE)/NO OF RUNS X VOLTAGE
7 % VOLTAGE DROP
=
CABLE SIZE CHOSEN
=
538
1.301526492 4CX10
sq.mm Al XLPE Cable
$ A) 1 2 2 3 4 5 6 7
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
!"
Ish t K
B) 1 AREA OF CONDUCTOR
# 10 12.5 0.415 0.8 2.64 0.08 94 30
= = = = = = =
= = =
2 CABLE SIZE CHOSEN
Ish* t/K 7.943667669 10 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
C) LAYING CONDITIONS = 1 AMBIENT AIR TEMPERATURE RATING FACTOR = 2 GROUPING/SPACING WITH OTHER CABLES =
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
45 0.95 Cable laid in trench (9 cables touching)
= =
0.66 0.627
= WORLING LOAD (KVA)/1.732 x VOLTAGE = 17.39 = DERATING FULL LOAD CURRENT/DERATING FACTOR 2 CURRENT RATING REQ.AFTER CONSIDERING 27.74 67 3 Current carring capacity of 4C x10 Sqmm AL XLPE= cable is 4 No of cable required = 0.41
E) 1 2 3 4 5 6
Ifl
CHECK FOR VOLTAGE DROP CABLE SIZE = 4C x10 Sqmm AL XLPE cable R AT CONDUCTOR TEMP. (4C x 10 SQmm AL XLPE = Cable) 3.94 X AT CONDUCTOR TEMP. (4C x 10 Qmm AL XLPE = Cable) 0.0837 COSø = 0.8 SINø = 0.6 No of runs: = 1 (FULL LOAD CURRENT X LENGTH X % VOLTAGE DROP = IMPEDENCE)/NO OF RUNS X VOLTAGE
7 % VOLTAGE DROP
=
CABLE SIZE CHOSEN
=
539
0.697246335 4CX10
sq.mm Al XLPE Cable
TRANSFORMER SIZING FOR JATNI (PHED Transmission) PUMPING STATION
1.0
Formula Used:
1.1
Working Load in kVA
=
[ Working Load (kW) x L. F. ] / [ D. F. x P. F. x Effi. ]
L. F.
= Load Factor
1.2
System P. F.
=
Total Working Load (kW) / Total Working Load (kVA)
P. F.
= Motor Power Factor
D. F.
= Diversity Factor
Effi.
= Motor Efficiency
2.0
Input Data and Calculations:
Sr. No.
Item Description
Connected Load
Rating in kW
Effi.
P. F.
L. F.
D. F. Unit
Working Load
Total (kW)
Unit
Total (kW)
2.1
Pump (existing)
45
0.936
0.86
0.9
1
2
90
1
40.5
2.2
Chain pully (existing)
2.5
0.83
0.82
1
1
1
2.5
1
2.5
2.3
Lighting
8
0.8
0.8
1
1.3
Lumpsum
8
2.4
Exhaust Fan (existing)
0.5
0.67
0.82
1
1
6
3
Total Load
103.5
Working Load (kVA)
Lumpsum 6.1538462 6
50.31 3.67 9.62
3
5.46
52.153846
69.06
3.0
Considering 20% contingency
=
4.0
System P. F.
=
0.76
5.0 5.1 5.2 5.3 5.4 5.5 5.6
Calculation to check the starting of largest size motor Rating of transformer assumed % impedance of transformer assumed Rating of the largest size motor Supply voltage P.F of largest size motor Efficiency of largest size motor
= = = = = =
100 4.5 45 0.415 0.86 0.936
FLC of motor
=
77.771 A
Rating of largest size motor in kVA
=
55.903 kVA
=
44.097 kVA
(Rating in kVA of transformer assumed - Largest motor KVA)
5.7 5.8
82.87 kVA
Nearest staanddard size (Confg. 11/0.433KV,Dyn11,Delta-star) From IS 2026 From the above table System voltage From the above table From the above table kW x 1000 1.7321 x V x p.f x efficiency kW P.F x Efficiency
kVA % KW kV
5.10
Base load on transformer before starting fourth largest motor Motor starting Kva with DOL start
=
335.42 kVA
= 6 x 1.7321 x kV x I FLC
5.11
Motor starting Kva with Star-Delta start
=
111.81 kVA
= 3 x 1.7321 x kV x I FLC
5.12
Fault Level at transformer secondary side
=
2.2222 MVA
5.13
Fault current of transformer secondary side (ISC)
=
3.0915 kA
5.14
S.C capacity of transformer Voltage drop at transformer terminal when largest motor start with DOL starting Voltage drop at transformer terminal when largest motor start with Star-Delta starting
=
2222.2 kVA
=
17.078 %
=
7.0 %
5.9
5.15 5.16
Rating of transformer in MVA x 100 Impedance of transformer in % Fault Level in MVA 1.7321 x kV 1.7321 x kV x I SC [Motor Starting kVA (DOL) + Base Load kVA] x 100 S.C capacity of transformer [Motor Starting kVA (S/D) + Base Load kVA] x 100 S.C capacity of transformer
The selected rating of transformer is
540
100 kVA
(within 10%) (within 10%)
CAPACITOR BANK SIZING ACROSS BUS
1 Average Power factor (pf1) 2 Total Working load 3 Power factor To be improved (pf2)
0.755 52 0.98 Working load ( Tan ( Cos-1 pf1) - Tan (Cos-1 pf2))
Total kVAR to be connected across Bus 4 Total kVAR to be connected across Bus
kW
35
541
KVAR
!"# A) 1 2 2 3 4 5 6 7
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
= = = = = = =
Ish t K
B) 1 AREA OF CONDUCTOR 2 CABLE SIZE CHOSEN
C) LAYING CONDITIONS 1 AMBIENT AIR TEMPERATURE RATING FACTOR 2 GROUPING/SPACING WITH OTHER CABLES
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
100 0.415 0.8 3.09 0.08 94 60
= = =
Ish* t/K 9.297701931 10 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
= = =
45 0.95 Cable laid in ground (3 cables touching)
= =
Ifl
0.69 0.6555
= = =
2 CURRENT RATING REQ.AFTER CONSIDERING DERATING 3 Current carring capacity of 3.5C x120 Sqmm AL XLPE cable is 4 No of cable required E) 1 2 3 4 5 6
$
CHECK FOR VOLTAGE DROP CABLE SIZE R AT CONDUCTOR TEMP. (3.5C x 120 SQmm AL XLPE Cable) X AT CONDUCTOR TEMP. (3.5C x 120 Qmm AL XLPE Cable) COSø SINø No of runs: % VOLTAGE DROP
7 % VOLTAGE DROP
WORLING LOAD (KVA)/1.732 x VOLTAGE 139.12 FULL LOAD CURRENT/DERATING FACTOR 212.24 223 0.95
= =
= = = = = = =
=
CABLE SIZE CHOSEN
=
542
3.5C x120 Sqmm AL XLPE cable 0.324 0.0712 0.8 0.6 1 (FULL LOAD CURRENT X LENGTH X IMPEDENCE)/NO OF RUNS X VOLTAGE 1.051833358 3.5CX120
sq.mm Al XLPE Cable
!"# A) 1 2 2 3 4 5 6 7
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
$
%& '
= = = = = = =
Ish t K
B) 1 AREA OF CONDUCTOR 2 CABLE SIZE CHOSEN
C) LAYING CONDITIONS 1 AMBIENT AIR TEMPERATURE RATING FACTOR 2 GROUPING/SPACING WITH OTHER CABLES
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
= = =
Ish* t/K 9.297701931 10 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
= = =
45 0.95 Cable laid in trench (9 cables touching)
= =
Ifl
2 CURRENT RATING REQ.AFTER CONSIDERING DERATING 3 Current carring capacity of 3C x50 Sqmm AL XLPE cable is 4 No of cable required E) 1 2 3 4 5 6
56 0.415 0.8 3.09 0.08 94 40
CHECK FOR VOLTAGE DROP CABLE SIZE R AT CONDUCTOR TEMP. (3C x 50 SQmm AL XLPE Cable) X AT CONDUCTOR TEMP. (3C x 50 Qmm AL XLPE Cable) COSø SINø No of runs: % VOLTAGE DROP
7 % VOLTAGE DROP
0.66 0.627
= = =
WORLING LOAD (KVA)/1.732 x VOLTAGE 77.91 FULL LOAD CURRENT/DERATING FACTOR 124.26 142 0.88
= =
= = = = = = =
=
CABLE SIZE CHOSEN
=
543
3C x50 Sqmm AL XLPE cable 0.82 0.075 0.8 0.6 1 (FULL LOAD CURRENT X LENGTH X IMPEDENCE)/NO OF RUNS X VOLTAGE 0.911737553 2X3CX50
sq.mm Al XLPE Cable
!"# A) 1 2 2 3 4 5 6 7
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
$
(
! ) !
= = = = = = =
Ish t K
B) 1 AREA OF CONDUCTOR 2 CABLE SIZE CHOSEN
C) LAYING CONDITIONS 1 AMBIENT AIR TEMPERATURE RATING FACTOR 2 GROUPING/SPACING WITH OTHER CABLES
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
= = =
Ish* t/K 9.297701931 10 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
= = =
45 0.95 Cable laid in trench (9 cables touching)
= =
Ifl
2 CURRENT RATING REQ.AFTER CONSIDERING DERATING Considering 35% extra current 3 Current carring capacity of 4C x10 Sqmm AL XLPE cable is 4 No of cable required E) 1 2 3 4 5 6
20 0.415 0.8 3.09 0.08 94 40
0.66 0.627
= = =
WORLING LOAD (KVA)/1.732 x VOLTAGE 27.82 FULL LOAD CURRENT/DERATING FACTOR 44.38 59.91 67 0.89
= =
CHECK FOR VOLTAGE DROP CABLE SIZE R AT CONDUCTOR TEMP. (4C x 10 SQmm AL XLPE Cable) X AT CONDUCTOR TEMP. (4C x 10 Qmm AL XLPE Cable) COSø SINø No of runs: % VOLTAGE DROP
7 % VOLTAGE DROP
= = = = = = =
=
CABLE SIZE CHOSEN
=
544
4C x10 Sqmm AL XLPE cable 3.94 0.0837 0.8 0.6 1 (FULL LOAD CURRENT X LENGTH X IMPEDENCE)/NO OF RUNS X VOLTAGE 1.487458847 4CX10
sq.mm Al XLPE Cable
!"# A) 1 2 2 3 4 5 6 7
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
$
Ish t K
B) 1 AREA OF CONDUCTOR 2 CABLE SIZE CHOSEN
C) LAYING CONDITIONS 1 AMBIENT AIR TEMPERATURE RATING FACTOR 2 GROUPING/SPACING WITH OTHER CABLES
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
= = =
Ish* t/K 9.297701931 10 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
= = =
45 0.95 Cable laid in trench (9 cables touching)
= =
Ifl
2 CURRENT RATING REQ.AFTER CONSIDERING DERATING 3 Current carring capacity of 4C x10 Sqmm AL XLPE cable is 4 No of cable required E) 1 2 3 4 5 6
15 18.75 0.415 0.8 3.09 0.08 94 40
= = = = = = =
CHECK FOR VOLTAGE DROP CABLE SIZE R AT CONDUCTOR TEMP. (4C x 10 SQmm AL XLPE Cable) X AT CONDUCTOR TEMP. (4C x 10 Qmm AL XLPE Cable) COSø SINø No of runs: % VOLTAGE DROP
7 % VOLTAGE DROP
0.66 0.627
= = =
WORLING LOAD (KVA)/1.732 x VOLTAGE 26.09 FULL LOAD CURRENT/DERATING FACTOR 41.60 67 0.62
= =
= = = = = = =
=
CABLE SIZE CHOSEN
=
545
4C x10 Sqmm AL XLPE cable 3.94 0.0837 0.8 0.6 1 (FULL LOAD CURRENT X LENGTH X IMPEDENCE)/NO OF RUNS X VOLTAGE 1.394492669 4CX10
sq.mm Al XLPE Cable
CAPACITOR BANK SIZING ACROSS BUS
1 Average Power factor (pf1) 2 Total Working load 3 Power factor To be improved (pf2)
0.749 81 0.98 Working load ( Tan ( Cos-1 pf1) - Tan (Cos-1 pf2))
Total kVAR to be connected across Bus 4 Total kVAR to be connected across Bus
kW
55
546
KVAR
TRANSFORMER SIZING FOR JATNI (PHED) PUMPING STATION
1.0
Formula Used:
1.1
Working Load in kVA
=
[ Working Load (kW) x L. F. ] / [ D. F. x P. F. x Effi. ]
L. F.
= Load Factor
1.2
System P. F.
=
Total Working Load (kW) / Total Working Load (kVA)
P. F.
= Motor Power Factor
D. F.
= Diversity Factor
Effi.
= Motor Efficiency
2.0
Input Data and Calculations:
Sr. No.
Item Description
Connected Load
Rating in kW
Effi.
P. F.
L. F.
D. F.
Working Load
Unit
Total (kW)
Unit
Total (kW)
Working Load (kVA)
2.1
Pump-1
37
0.935
0.86
0.9
1
2
74
1
33.3
41.41
2.2
Pump-2
18.5
0.913
0.83
0.9
1
2
37
2
33.3
43.94
2.3
Crane
2.5
0.87
0.82
1
1
1
2.5
1
2.5
3.50
2.4
Exhaust Fan
0.5
0.67
0.82
1
1
6
3
6
3
2.5
Lighting Total Load
10.124
0.8
0.8
1
1.2
Lumpsum
10.124
Lumpsum 8.4366667
13.18
126.624
80.536667
107.50
3.0
Considering 20% contingency
=
4.0
System P. F.
=
0.75
5.0 5.1 5.2 5.3 5.4 5.5 5.6
Calculation to check the starting of largest size motor Rating of transformer assumed % impedance of transformer assumed Rating of the largest size motor Supply voltage P.F of largest size motor Efficiency of largest size motor
= = = = = =
160 4.5 37 0.415 0.86 0.935
5.46
129.00 kVA
Nearest staanddard size (Confg. 11/0.433KV,Dyn11,Delta-star) From IS 2026 From the above table System voltage From the above table From the above table kW x 1000 1.7321 x V x p.f x efficiency kW P.F x Efficiency
kVA % KW kV
5.7
FLC of motor
=
64.013 A
5.8
Rating of largest size motor in kVA
=
46.014 kVA
=
113.99 kVA
(Rating in kVA of transformer assumed - Largest motor KVA)
5.10
Base load on transformer before starting fourth largest motor Motor starting Kva with DOL start
=
276.09 kVA
= 6 x 1.7321 x kV x I FLC
5.11
Motor starting Kva with Star-Delta start
=
161.05 kVA
= 3 x 1.7321 x kV x I FLC
5.12
Fault Level at transformer secondary side
=
3.5556 MVA
5.13
Fault current of transformer secondary side (ISC)
=
4.9464 kA
5.14
S.C capacity of transformer Voltage drop at transformer terminal when largest motor start with DOL starting Voltage drop at transformer terminal when largest motor start with Star-Delta starting
=
3555.6 kVA
=
10.971 %
=
7.7 %
5.9
5.15 5.16
Rating of transformer in MVA x 100 Impedance of transformer in % Fault Level in MVA 1.7321 x kV 1.7321 x kV x I SC [Motor Starting kVA (DOL) + Base Load kVA] x 100 S.C capacity of transformer [Motor Starting kVA (S/D) + Base Load kVA] x 100 S.C capacity of transformer
The selected rating of transformer is
547
160 kVA
(within 10%) (within 10%)
! "#$ A) 1 2 2 3 4 5 6 7
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
= = = = = = =
Ish t K
B) 1 AREA OF CONDUCTOR 2 CABLE SIZE CHOSEN
C) LAYING CONDITIONS 1 AMBIENT AIR TEMPERATURE RATING FACTOR 2 GROUPING/SPACING WITH OTHER CABLES
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
160 0.415 0.8 4.95 0.08 94 30
= = =
Ish* t/K 14.89437688 16 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
= = =
45 0.95 Cable laid in ground (3 cables touching)
= =
Ifl
0.69 0.6555
= = =
2 CURRENT RATING REQ.AFTER CONSIDERING DERATING 3 Current carring capacity of 3.5C x120 Sqmm AL XLPE cable is 4 No of cable required E) 1 2 3 4 5 6
%
CHECK FOR VOLTAGE DROP CABLE SIZE R AT CONDUCTOR TEMP. (3.5C x 120 SQmm AL XLPE Cable) X AT CONDUCTOR TEMP. (3.5C x 120 Qmm AL XLPE Cable) COSø SINø No of runs: % VOLTAGE DROP
7 % VOLTAGE DROP
WORLING LOAD (KVA)/1.732 x VOLTAGE 222.60 FULL LOAD CURRENT/DERATING FACTOR 339.59 223 1.52
= =
= = = = = = =
=
CABLE SIZE CHOSEN
=
548
3.5C x120 Sqmm AL XLPE cable 0.324 0.0712 0.8 0.6 2 (FULL LOAD CURRENT X LENGTH X IMPEDENCE)/NO OF RUNS X VOLTAGE 0.420733343 2X3.5CX120
sq.mm Al XLPE Cable
! "#$ A) 1 2 2 3 4 5 6 7
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
%
&' (
= = = = = = =
Ish t K
B) 1 AREA OF CONDUCTOR 2 CABLE SIZE CHOSEN
C) LAYING CONDITIONS 1 AMBIENT AIR TEMPERATURE RATING FACTOR 2 GROUPING/SPACING WITH OTHER CABLES
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
= = =
Ish* t/K 14.89437688 16 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
= = =
45 0.95 Cable laid in trench (9 cables touching)
= =
Ifl
2 CURRENT RATING REQ.AFTER CONSIDERING DERATING 3 Current carring capacity of 3C x35 Sqmm AL XLPE cable is 4 No of cable required E) 1 2 3 4 5 6
46 0.415 0.8 4.95 0.08 94 55
CHECK FOR VOLTAGE DROP CABLE SIZE R AT CONDUCTOR TEMP. (3C x 35 SQmm AL XLPE Cable) X AT CONDUCTOR TEMP. (3C x 35 Qmm AL XLPE Cable) COSø SINø No of runs: % VOLTAGE DROP
7 % VOLTAGE DROP
0.66 0.627
= = =
WORLING LOAD (KVA)/1.732 x VOLTAGE 64.00 FULL LOAD CURRENT/DERATING FACTOR 102.07 117 0.87
= =
= = = = = = =
=
CABLE SIZE CHOSEN
=
549
3C x35 Sqmm AL XLPE cable 1.11 0.0783 0.8 0.6 1 (FULL LOAD CURRENT X LENGTH X IMPEDENCE)/NO OF RUNS X VOLTAGE 1.373493628 2X3CX35
sq.mm Al XLPE Cable
! "#$ A) 1 2 2 3 4 5 6 7
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
%
)*+ (
= = = = = = =
Ish t K
B) 1 AREA OF CONDUCTOR 2 CABLE SIZE CHOSEN
C) LAYING CONDITIONS 1 AMBIENT AIR TEMPERATURE RATING FACTOR 2 GROUPING/SPACING WITH OTHER CABLES
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
= = =
Ish* t/K 14.89437688 16 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
= = =
45 0.95 Cable laid in trench (9 cables touching)
= =
Ifl
2 CURRENT RATING REQ.AFTER CONSIDERING DERATING 3 Current carring capacity of 3C x16 Sqmm AL XLPE cable is 4 No of cable required E) 1 2 3 4 5 6
25 0.415 0.8 4.95 0.08 94 65
CHECK FOR VOLTAGE DROP CABLE SIZE R AT CONDUCTOR TEMP. (3C x 16 SQmm AL XLPE Cable) X AT CONDUCTOR TEMP. (3C x 16 Qmm AL XLPE Cable) COSø SINø No of runs: % VOLTAGE DROP
7 % VOLTAGE DROP
0.66 0.627
= = =
WORLING LOAD (KVA)/1.732 x VOLTAGE 34.78 FULL LOAD CURRENT/DERATING FACTOR 55.47 70 0.79
= =
= = = = = = =
=
CABLE SIZE CHOSEN
=
550
3C x16 Sqmm AL XLPE cable 2.44 0.0783 0.8 0.6 1 (FULL LOAD CURRENT X LENGTH X IMPEDENCE)/NO OF RUNS X VOLTAGE 1.886103934 2X3CX16
sq.mm Al XLPE Cable
! "#$ A) 1 2 2 3 4 5 6 7
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
%
,'
" - "
= = = = = = =
Ish t K
B) 1 AREA OF CONDUCTOR 2 CABLE SIZE CHOSEN
C) LAYING CONDITIONS 1 AMBIENT AIR TEMPERATURE RATING FACTOR 2 GROUPING/SPACING WITH OTHER CABLES
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
= = =
Ish* t/K 14.89437688 16 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
= = =
45 0.95 Cable laid in trench (9 cables touching)
= =
Ifl
2 CURRENT RATING REQ.AFTER CONSIDERING DERATING Considering 35% extra current 3 Current carring capacity of 3.5C x25 Sqmm AL XLPE cable is 4 No of cable required E) 1 2 3 4 5 6
30 0.415 0.8 4.95 0.08 94 40
CHECK FOR VOLTAGE DROP CABLE SIZE R AT CONDUCTOR TEMP. (3.5C x 25 SQmm AL XLPE Cable) X AT CONDUCTOR TEMP. (3.5C x 25 Qmm AL XLPE Cable) COSø SINø No of runs: % VOLTAGE DROP
7 % VOLTAGE DROP
0.66 0.627
= = =
WORLING LOAD (KVA)/1.732 x VOLTAGE 41.74 FULL LOAD CURRENT/DERATING FACTOR 66.57 89.87 96 0.94
= =
= = = = = = =
=
CABLE SIZE CHOSEN
=
551
3.5C x25 Sqmm AL XLPE cable 1.54 0.0805 0.8 0.6 1 (FULL LOAD CURRENT X LENGTH X IMPEDENCE)/NO OF RUNS X VOLTAGE 0.892065612 3.5CX25
sq.mm Al XLPE Cable
! "#$ A) 1 2 2 3 4 5 6 7
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
%
Ish t K
B) 1 AREA OF CONDUCTOR 2 CABLE SIZE CHOSEN
C) LAYING CONDITIONS 1 AMBIENT AIR TEMPERATURE RATING FACTOR 2 GROUPING/SPACING WITH OTHER CABLES
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
= = =
Ish* t/K 14.89437688 16 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
= = =
45 0.95 Cable laid in trench (9 cables touching)
= =
Ifl
2 CURRENT RATING REQ.AFTER CONSIDERING DERATING 3 Current carring capacity of 4C x16 Sqmm AL XLPE cable is 4 No of cable required E) 1 2 3 4 5 6
10 12.5 0.415 0.8 4.95 0.08 94 40
= = = = = = =
0.66 0.627
= = =
WORLING LOAD (KVA)/1.732 x VOLTAGE 17.39 FULL LOAD CURRENT/DERATING FACTOR 27.74 67 0.41
= =
CHECK FOR VOLTAGE DROP CABLE SIZE R AT CONDUCTOR TEMP. (4C x 16 SQmm AL XLPE Cable) X AT CONDUCTOR TEMP. (4C x 16 Qmm AL XLPE Cable) COSø SINø No of runs: % VOLTAGE DROP
7 % VOLTAGE DROP
= = = = = = =
=
CABLE SIZE CHOSEN
=
552
4C x16 Sqmm AL XLPE cable 2.44 0.0808 0.8 0.6 1 (FULL LOAD CURRENT X LENGTH X IMPEDENCE)/NO OF RUNS X VOLTAGE 0.580775149 4CX16
sq.mm Al XLPE Cable
! "#$ A) 1 2 2 3 4 5 6 7
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
= = = = = = =
Ish t K
B) 1 AREA OF CONDUCTOR 2 CABLE SIZE CHOSEN
C) LAYING CONDITIONS 1 AMBIENT AIR TEMPERATURE RATING FACTOR 2 GROUPING/SPACING WITH OTHER CABLES
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
160 0.415 0.8 4.94 0.08 94 35
= = =
Ish* t/K
= = =
45 0.95 Cable laid in ground (3 cables touching)
14.86428723 16 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
= =
Ifl
0.69 0.6555
= = =
2 CURRENT RATING REQ.AFTER CONSIDERING DERATING 3 Current carring capacity of 3.5C x120 Sqmm AL XLPE cable is 4 No of cable required E) 1 2 3 4 5 6
%
WORLING LOAD (KVA)/1.732 x VOLTAGE 222.60 FULL LOAD CURRENT/DERATING FACTOR 339.59 223 1.52
= =
CHECK FOR VOLTAGE DROP CABLE SIZE R AT CONDUCTOR TEMP. (3.5C x 120 SQmm AL XLPE Cable) X AT CONDUCTOR TEMP. (3.5C x 120 Qmm AL XLPE Cable) COSø SINø No of runs: % VOLTAGE DROP
7 % VOLTAGE DROP
= = = = = = =
=
CABLE SIZE CHOSEN
=
553
3.5C x120 Sqmm AL XLPE cable 0.324 0.0712 0.8 0.6 2 (FULL LOAD CURRENT X LENGTH X IMPEDENCE)/NO OF RUNS X VOLTAGE 0.490855567 2 X 3.5CX120
sq.mm Al XLPE Cable
! "#$ A) 1 2 2 3 4 5 6 7
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
%
&
'
= = = = = = =
Ish t K
B) 1 AREA OF CONDUCTOR 2 CABLE SIZE CHOSEN
C) LAYING CONDITIONS 1 AMBIENT AIR TEMPERATURE RATING FACTOR 2 GROUPING/SPACING WITH OTHER CABLES
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
= = =
Ish* t/K 14.89437688 16 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
= = =
45 0.95 Cable laid in trench (9 cables touching)
= =
Ifl
0.66 0.627
= = =
2 CURRENT RATING REQ.AFTER CONSIDERING DERATING 3 Current carring capacity of 3C x16 Sqmm AL XLPE cable is 4 No of cable required E) 1 2 3 4 5 6
37 0.415 0.8 4.95 0.08 94 60
WORLING LOAD (KVA)/1.732 x VOLTAGE x 1.732 29.72 FULL LOAD CURRENT/DERATING FACTOR 47.40 70 0.68
= =
CHECK FOR VOLTAGE DROP CABLE SIZE R AT CONDUCTOR TEMP. (3C x 16 SQmm AL XLPE Cable) X AT CONDUCTOR TEMP. (3C x 16 Qmm AL XLPE Cable) COSø SINø No of runs: % VOLTAGE DROP
= = = = = = =
7 % VOLTAGE DROP
=
CABLE SIZE CHOSEN
=
554
3C x16 Sqmm AL XLPE cable 2.44 0.0808 0.8 0.6 1 (FULL LOAD CURRENT X LENGTH X IMPEDENCE)/NO OF RUNS X VOLTAGE 1.48882313 2X3CX16
sq.mm Al XLPE Cable
! "#$ A) 1 2 2 3 4 5 6 7
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
%
()* '
= = = = = = =
Ish t K
B) 1 AREA OF CONDUCTOR 2 CABLE SIZE CHOSEN
C) LAYING CONDITIONS 1 AMBIENT AIR TEMPERATURE RATING FACTOR 2 GROUPING/SPACING WITH OTHER CABLES
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
= = =
Ish* t/K 14.89437688 16 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
= = =
45 0.95 Cable laid in trench (9 cables touching)
= =
Ifl
2 CURRENT RATING REQ.AFTER CONSIDERING DERATING 3 Current carring capacity of 3C x16 Sqmm AL XLPE cable is 4 No of cable required E) 1 2 3 4 5 6
24 0.415 0.8 4.95 0.08 94 70
CHECK FOR VOLTAGE DROP CABLE SIZE R AT CONDUCTOR TEMP. (3C x 16 SQmm AL XLPE Cable) X AT CONDUCTOR TEMP. (3C x 16 Qmm AL XLPE Cable) COSø SINø No of runs: % VOLTAGE DROP
7 % VOLTAGE DROP
0.66 0.627
= = =
WORLING LOAD (KVA)/1.732 x VOLTAGE 33.39 FULL LOAD CURRENT/DERATING FACTOR 53.25 70 0.76
= =
= = = = = = =
=
CABLE SIZE CHOSEN
=
555
3C x16 Sqmm AL XLPE cable 2.44 0.0783 0.8 0.6 1 (FULL LOAD CURRENT X LENGTH X IMPEDENCE)/NO OF RUNS X VOLTAGE 1.949941298 2X3CX16
sq.mm Al XLPE Cable
! "#$ A) 1 2 2 3 4 5 6 7
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
%
+)& '
= = = = = = =
Ish t K
B) 1 AREA OF CONDUCTOR 2 CABLE SIZE CHOSEN
C) LAYING CONDITIONS 1 AMBIENT AIR TEMPERATURE RATING FACTOR 2 GROUPING/SPACING WITH OTHER CABLES
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
= = =
Ish* t/K 14.89437688 16 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
= = =
45 0.95 Cable laid in trench (9 cables touching)
= =
Ifl
2 CURRENT RATING REQ.AFTER CONSIDERING DERATING 3 Current carring capacity of 3C x16 Sqmm AL XLPE cable is 4 No of cable required E) 1 2 3 4 5 6
13 0.415 0.8 4.95 0.08 94 85
CHECK FOR VOLTAGE DROP CABLE SIZE R AT CONDUCTOR TEMP. (3C x 16 SQmm AL XLPE Cable) X AT CONDUCTOR TEMP. (3C x 16 Qmm AL XLPE Cable) COSø SINø No of runs: % VOLTAGE DROP
7 % VOLTAGE DROP
0.66 0.627
= = =
WORLING LOAD (KVA)/1.732 x VOLTAGE 18.09 FULL LOAD CURRENT/DERATING FACTOR 28.85 70 0.41
= =
= = = = = = =
=
CABLE SIZE CHOSEN
=
556
3C x16 Sqmm AL XLPE cable 2.44 0.0783 0.8 0.6 1 (FULL LOAD CURRENT X LENGTH X IMPEDENCE)/NO OF RUNS X VOLTAGE 1.282550675 2X3CX16
sq.mm Al XLPE Cable
! "#$ A) 1 2 2 3 4 5 6 7
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
%
,#
,
Ish t K
B) 1 AREA OF CONDUCTOR 2 CABLE SIZE CHOSEN
C) LAYING CONDITIONS 1 AMBIENT AIR TEMPERATURE RATING FACTOR 2 GROUPING/SPACING WITH OTHER CABLES
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
= = =
Ish* t/K 14.89437688 16 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
= = =
45 0.95 Cable laid in trench (9 cables touching)
= =
Ifl
0.66 0.627
= = =
2 CURRENT RATING REQ.AFTER CONSIDERING DERATING 3 Current carring capacity of 4C x16 Sqmm AL XLPE cable is 4 No of cable required E) 1 2 3 4 5 6
15 18.75 0.415 0.8 4.95 0.08 94 30
= = = = = = =
WORLING LOAD (KVA)/1.732 x VOLTAGE 26.09 FULL LOAD CURRENT/DERATING FACTOR 41.60 70 0.59
= =
CHECK FOR VOLTAGE DROP CABLE SIZE R AT CONDUCTOR TEMP. (4C x 16 SQmm AL XLPE Cable) X AT CONDUCTOR TEMP. (4C x 16 Qmm AL XLPE Cable) COSø SINø No of runs: % VOLTAGE DROP
= = = = = = =
7 % VOLTAGE DROP
=
CABLE SIZE CHOSEN
=
557
4C x16 Sqmm AL XLPE cable 2.44 0.0808 0.8 0.6 1 (FULL LOAD CURRENT X LENGTH X IMPEDENCE)/NO OF RUNS X VOLTAGE 0.653372042 4CX16
sq.mm Al XLPE Cable
! "#$ A) 1 2 2 3 4 5 6 7
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
%
&
" - "
= = = = = = =
Ish t K
B) 1 AREA OF CONDUCTOR 2 CABLE SIZE CHOSEN
C) LAYING CONDITIONS 1 AMBIENT AIR TEMPERATURE RATING FACTOR 2 GROUPING/SPACING WITH OTHER CABLES
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
= = =
Ish* t/K 14.89437688 16 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
= = =
45 0.95 Cable laid in trench (9 cables touching)
= =
Ifl
2 CURRENT RATING REQ.AFTER CONSIDERING DERATING Considering 35% extra current 3 Current carring capacity of 3.5C x25 Sqmm AL XLPE cable is 4 No of cable required E) 1 2 3 4 5 6
31 0.415 0.8 4.95 0.08 94 40
CHECK FOR VOLTAGE DROP CABLE SIZE R AT CONDUCTOR TEMP. (3.5C x 25 SQmm AL XLPE Cable) X AT CONDUCTOR TEMP. (3.5C x 25 Qmm AL XLPE Cable) COSø SINø No of runs: % VOLTAGE DROP
7 % VOLTAGE DROP
0.66 0.627
= = =
WORLING LOAD (KVA)/1.732 x VOLTAGE 43.13 FULL LOAD CURRENT/DERATING FACTOR 68.79 92.86 96 0.97
= =
= = = = = = =
=
CABLE SIZE CHOSEN
=
558
3.5C x25 Sqmm AL XLPE cable 3.94 0.0837 0.8 0.6 1 (FULL LOAD CURRENT X LENGTH X IMPEDENCE)/NO OF RUNS X VOLTAGE 2.305561214 3.5CX25 .
sq.mm Al XLPE Cable
TRANSFORMER SIZING FOR KHORDA (JAMADEI) PUMPING STATION
1.0
Formula Used:
1.1
Working Load in kVA
=
[ Working Load (kW) x L. F. ] / [ D. F. x P. F. x Effi. ]
1.2
System P. F.
=
Total Working Load (kW) / Total Working Load (kVA)
2.0
L. F.
= Load Factor
P. F.
= Motor Power Factor
D. F.
= Diversity Factor
Effi.
= Motor Efficiency
Input Data and Calculations:
Sr. No.
Item Description
Rating in kW
Connected Load Effi.
P. F.
L. F.
D. F. Unit
Working Load
Total (kW)
Unit
Total (kW)
Working Load (kVA)
2.1
Pump -1
18.5
0.913
0.83
0.95
1
2
37
1
17.575
23.19
2.2
Pump-2
9.3
0.892
0.81
0.95
1
2
18.6
2
17.67
24.46
2.3
Pump-3
30
0.925
0.84
0.95
1
2
60
1
28.5
36.68
2.4
Exhaust Fan
0.5
0.67
0.82
1
1
8
4
8
4
7.28
2.4
Crane
7.5
0.87
0.82
1
2
1
7.5
1
3.75
5.26
2.5
Lighting and small power (indoor and outdoor)
11.314
0.8
0.8
1
1.5
Lumpsum
11.314
Lumpsum 7.5426667
11.79
138.414
79.037667
108.65
Total Load
3.0
Considering 20% contingency
=
4.0
System P. F.
=
0.73
5.0 5.1 5.2 5.3 5.4 5.5 5.6
Calculation to check the starting of largest size motor Rating of transformer assumed % impedance of transformer assumed Rating of the largest size motor Supply voltage P.F of largest size motor Efficiency of largest size motor
= = = = = =
160 4.5 30 0.415 0.84 0.925
FLC of motor
=
53.713 A
Rating of largest size motor in kVA
=
38.61 kVA
=
121.39 kVA
(Rating in kVA of transformer assumed - Largest motor KVA)
5.7 5.8
130.38 kVA
kVA % KW kV
Nearest staanddard size (Confg. 11/0.433KV,Dyn11,Delta-star) From IS 2026 From the above table System voltage From the above table From the above table kW x 1000 1.7321 x V x p.f x efficiency kW P.F x Efficiency
5.10
Base load on transformer before starting fourth largest motor Motor starting Kva with DOL start
=
231.66 kVA
= 6 x 1.7321 x kV x I FLC
5.11
Motor starting Kva with Star-Delta start
=
77.22 kVA
= 3 x 1.7321 x kV x I FLC
5.12
Fault Level at transformer secondary side
=
3.5556 MVA
5.13
Fault current of transformer secondary side (ISC)
=
4.9464 kA
5.14
S.C capacity of transformer Voltage drop at transformer terminal when largest motor start with DOL starting Voltage drop at transformer terminal when largest motor start with Star-Delta starting
=
3555.6 kVA
=
9.9295 %
=
5.6 %
5.9
5.15 5.16
Rating of transformer in MVA x 100 Impedance of transformer in % Fault Level in MVA 1.7321 x kV 1.7321 x kV x I SC [Motor Starting kVA (DOL) + Base Load kVA] x 100 S.C capacity of transformer [Motor Starting kVA (S/D) + Base Load kVA] x 100 S.C capacity of transformer
The selected rating of transformer is
559
160 kVA
(within 10%) (within 10%)
CAPACITOR BANK SIZING ACROSS BUS
1 Average Power factor (pf1) 2 Total Working load 3 Power factor To be improved (pf2)
0.727 79 0.98 Working load ( Tan ( Cos-1 pf1) - Tan (Cos-1 pf2))
Total kVAR to be connected across Bus 4 Total kVAR to be connected across Bus
kW
59
560
KVAR
TRANSFORMER SIZING FOR KHORDA ( Gurjanga) PUMPING STATION
1.0
Formula Used:
1.1
Working Load in kVA
=
[ Working Load (kW) x L. F. ] / [ D. F. x P. F. x Effi. ]
1.2
System P. F.
=
Total Working Load (kW) / Total Working Load (kVA)
2.0
L. F.
= Load Factor
P. F.
= Motor Power Factor
D. F.
= Diversity Factor
Effi.
= Motor Efficiency
Input Data and Calculations:
Sr. No.
Item Description
Rating in kW
Connected Load Effi.
P. F.
L. F.
D. F.
Total (kW)
Unit
Working Load Unit
Total (kW)
Working Load (kVA)
2.1
Pump -1
22
0.917
0.83
0.95
1
2
44
1
20.9
27.46
2.2
Pump -2
11
0.892
0.81
1
1
2
22
2
22
30.45
2.3
Crane
7.5
0.87
0.82
0.9
2
1
7.5
1
3.375
4.73
2.4 2.5
Exhaust Fan
0.5 10.646
0.67 0.8
0.82 0.8
1 1
1 1.3
8 Lumpsum
4 10.646 88.146
3.0
Considering 20% contingency
=
4.0
System P. F.
=
0.71
5.0 5.1 5.2 5.3 5.4 5.5 5.6
Calculation to check the starting of largest size motor Rating of transformer assumed % impedance of transformer assumed Rating of the largest size motor Supply voltage P.F of largest size motor Efficiency of largest size motor
= = = = = =
100 4.5 22 0.415 0.83 0.917
Lighting Total Load
kVA % KW kV
Nearest staanddard size (Confg. 11/0.433KV,Dyn11,Delta-star) From IS 2026 From the above table System voltage From the above table From the above table kW x 1000 1.7321 x V x p.f x efficiency kW P.F x Efficiency
FLC of motor
=
40.212 A
5.8
Rating of largest size motor in kVA
=
28.905 kVA
=
71.095 kVA
=
173.43 kVA
= 6 x 1.7321 x kV x I FLC = 3 x 1.7321 x kV x I FLC
5.10
Base load on transformer before starting fourth largest motor Motor starting Kva with DOL start
5.11
Motor starting Kva with Star-Delta start
=
57.81 kVA
5.12
Fault Level at transformer secondary side
=
2.2222 MVA
5.13
Fault current of transformer secondary side (ISC)
=
3.0915 kA
5.14
S.C capacity of transformer Voltage drop at transformer terminal when largest motor start with DOL starting Voltage drop at transformer terminal when largest motor start with Star-Delta starting
=
2222.2 kVA
=
11.004 %
=
5.8 %
5.15 5.16
7.28 12.80 82.72
99.26 kVA
5.7
5.9
8 4 Lumpsum 8.1892308 58.464231
(Rating in kVA of transformer assumed - Largest motor KVA)
Rating of transformer in MVA x 100 Impedance of transformer in % Fault Level in MVA 1.7321 x kV 1.7321 x kV x I SC [Motor Starting kVA (DOL) + Base Load kVA] x 100 S.C capacity of transformer [Motor Starting kVA (S/D) + Base Load kVA] x 100 S.C capacity of transformer
The selected rating of transformer is
561
100 kVA
(within 10%) (within 10%)
CAPACITOR BANK SIZING ACROSS BUS
1 Average Power factor (pf1) 2 Total Working load 3 Power factor To be improved (pf2)
0.707 58 0.98 Working load ( Tan ( Cos-1 pf1) - Tan (Cos-1 pf2))
Total kVAR to be connected across Bus 4 Total kVAR to be connected across Bus
kW
47
562
KVAR
!" A) 1 2 2 3 4 5 6 7
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
Ish t K
B) 1 AREA OF CONDUCTOR
= = = = = = =
100 0.415 0.8 3.09 0.08 94 60
= = =
2 CABLE SIZE CHOSEN
Ish* t/K 9.297701931 10 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
C) LAYING CONDITIONS = 1 AMBIENT AIR TEMPERATURE RATING FACTOR = 2 GROUPING/SPACING WITH OTHER CABLES =
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
#
45 0.95 Cable laid in ground (3 cables touching)
= =
0.69 0.6555
= WORLING LOAD (KVA)/1.732 x VOLTAGE = 139.12 = DERATING FULL LOAD CURRENT/DERATING FACTOR 2 CURRENT RATING REQ.AFTER CONSIDERING 212.24 = cable is 223 3 Current carring capacity of 3.5C x120 Sqmm AL XLPE 4 No of cable required = 0.95
E) 1 2 3 4 5 6
Ifl
CHECK FOR VOLTAGE DROP CABLE SIZE = 3.5C x120 Sqmm AL XLPE cable R AT CONDUCTOR TEMP. (3.5C x 120 SQmm AL=XLPE Cable) 0.21 X AT CONDUCTOR TEMP. (3.5C x 120 Qmm AL XLPE = Cable) 0.0718 COSø = 0.8 SINø = 0.6 No of runs: = 1 (FULL LOAD CURRENT X LENGTH X % VOLTAGE DROP = IMPEDENCE)/NO OF RUNS X VOLTAGE
7 % VOLTAGE DROP
=
CABLE SIZE CHOSEN
=
563
0.735363623 3.5CX120
sq.mm Al XLPE Cable
$ A) 1 2 2 3 4 5 6 7
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
!"
Ish t K
B) 1 AREA OF CONDUCTOR
#
%
= = = = = = =
16 0.415 0.8 3.09 0.08 94 55
= = =
2 CABLE SIZE CHOSEN
Ish* t/K 9.297701931 10 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
C) LAYING CONDITIONS = 1 AMBIENT AIR TEMPERATURE RATING FACTOR = 2 GROUPING/SPACING WITH OTHER CABLES =
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
45 0.95 Cable laid in trench (9 cables touching)
= =
0.66 0.627
= WORLING LOAD (KVA)/1.732 x VOLTAGE x 1.732 = 12.85 = DERATING FULL LOAD CURRENT/DERATING FACTOR 2 CURRENT RATING REQ.AFTER CONSIDERING 20.50 67 3 Current carring capacity of 3C x10 Sqmm AL XLPE=cable is 4 No of cable required = 0.31
E) 1 2 3 4 5 6
Ifl
CHECK FOR VOLTAGE DROP CABLE SIZE = 3C x10Sqmm AL XLPE cable R AT CONDUCTOR TEMP. (3C x 10 SQmm AL XLPE = Cable) 3.94 X AT CONDUCTOR TEMP. (3C x 10 Qmm AL XLPE = Cable) 0.0837 COSø = 0.8 SINø = 0.6 No of runs: = 1 (FULL LOAD CURRENT X LENGTH X % VOLTAGE DROP = IMPEDENCE)/NO OF RUNS X VOLTAGE
7 % VOLTAGE DROP CABLE SIZE CHOSEN
= =
564
0.944690954 2X3CX10
sq.mm Al XLPE Cable
$ A) 1 2 2 3 4 5 6 7
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
!"
Ish t K
B) 1 AREA OF CONDUCTOR
#
&& %
= = = = = = =
29 0.415 0.8 3.09 0.08 94 40
= = =
2 CABLE SIZE CHOSEN
Ish* t/K 9.297701931 10 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
C) LAYING CONDITIONS = 1 AMBIENT AIR TEMPERATURE RATING FACTOR = 2 GROUPING/SPACING WITH OTHER CABLES =
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
45 0.95 Cable laid in trench (9 cables touching)
= =
0.66 0.627
= WORLING LOAD (KVA)/1.732 x VOLTAGE x 1.732 = 23.29 = DERATING FULL LOAD CURRENT/DERATING FACTOR 2 CURRENT RATING REQ.AFTER CONSIDERING 37.15 67 3 Current carring capacity of 3C x10 Sqmm AL XLPE=cable is 4 No of cable required = 0.55
E) 1 2 3 4 5 6
Ifl
CHECK FOR VOLTAGE DROP CABLE SIZE = 3C x10 Sqmm AL XLPE cable R AT CONDUCTOR TEMP. (3C x 10 SQmm AL XLPE = Cable) 3.94 X AT CONDUCTOR TEMP. (3C x 10 Qmm AL XLPE = Cable) 0.0837 COSø = 0.8 SINø = 0.6 No of runs: = 1 (FULL LOAD CURRENT X LENGTH X % VOLTAGE DROP = IMPEDENCE)/NO OF RUNS X VOLTAGE
7 % VOLTAGE DROP CABLE SIZE CHOSEN
= =
565
1.245274439 2X3CX10
sq.mm Al XLPE Cable
$ A) 1 2 2 3 4 5 6 7
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
!"
#
Ish t K
B) 1 AREA OF CONDUCTOR 2 CABLE SIZE CHOSEN
C) LAYING CONDITIONS 1 AMBIENT AIR TEMPERATURE RATING FACTOR 2 GROUPING/SPACING WITH OTHER CABLES
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
= = =
Ish* t/K 9.297701931 10 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
= = =
45 0.95 Cable laid in trench (9 cables touching)
= =
Ifl
2 CURRENT RATING REQ.AFTER CONSIDERING DERATING 3 Current carring capacity of 4C x10 Sqmm AL XLPE cable is 4 No of cable required E) 1 2 3 4 5 6
12 15 0.415 0.8 3.09 0.08 94 40
= = = = = = =
CHECK FOR VOLTAGE DROP CABLE SIZE R AT CONDUCTOR TEMP. (4C x 10 SQmm AL XLPE Cable) X AT CONDUCTOR TEMP. (4C x 10 Qmm AL XLPE Cable) COSø SINø No of runs: % VOLTAGE DROP
7 % VOLTAGE DROP
0.66 0.627
= = =
WORLING LOAD (KVA)/1.732 x VOLTAGE 20.87 FULL LOAD CURRENT/DERATING FACTOR 33.28 67 0.50
= =
= = = = = = =
=
CABLE SIZE CHOSEN
=
566
4C x10 Sqmm AL XLPE cable 3.94 0.0837 0.8 0.6 1 (FULL LOAD CURRENT X LENGTH X IMPEDENCE)/NO OF RUNS X VOLTAGE 1.115594136 4CX10
sq.mm Al XLPE Cable
$ A) 1 2 2 3 4 5 6 7
!"
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
Ish t K
B) 1 AREA OF CONDUCTOR
#
&'
(
= = = = = = =
25 0.415 0.8 3.09 0.08 94 40
= = =
2 CABLE SIZE CHOSEN
Ish* t/K 9.297701931 10 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
C) LAYING CONDITIONS = 1 AMBIENT AIR TEMPERATURE RATING FACTOR = 2 GROUPING/SPACING WITH OTHER CABLES =
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
45 0.95 Cable laid in trench (9 cables touching)
= =
0.66 0.627
= WORLING LOAD (KVA)/1.732 x VOLTAGE = 34.78 = DERATING FULL LOAD CURRENT/DERATING FACTOR 2 CURRENT RATING REQ.AFTER CONSIDERING 55.47 Considering 35% extra current 74.89 3 Current carring capacity of 3.5C x25 Sqmm AL XLPE = cable is 96 4 No of cable required = 0.78
E) 1 2 3 4 5 6
Ifl
CHECK FOR VOLTAGE DROP CABLE SIZE = 3.5C x25 Sqmm AL XLPE cable R AT CONDUCTOR TEMP. (3.5C x 25 SQmm AL XLPE = Cable) 3.94 X AT CONDUCTOR TEMP. (3.5C x 25 Qmm AL XLPE = Cable) 0.0837 COSø = 0.8 SINø = 0.6 No of runs: = 1 (FULL LOAD CURRENT X LENGTH X % VOLTAGE DROP = IMPEDENCE)/NO OF RUNS X VOLTAGE
7 % VOLTAGE DROP
=
CABLE SIZE CHOSEN
=
567
1.859323559 3.5CX25 .
sq.mm Al XLPE Cable
TRANSFORMER SIZING FOR KHORDA ( PHED) PUMPING STATION
1.0
Formula Used:
1.1
Working Load in kVA
=
[ Working Load (kW) x L. F. ] / [ D. F. x P. F. x Effi. ]
1.2
System P. F.
=
Total Working Load (kW) / Total Working Load (kVA)
2.0
L. F.
= Load Factor
P. F.
= Motor Power Factor
D. F.
= Diversity Factor
Effi.
= Motor Efficiency
Input Data and Calculations:
Sr. No.
Item Description
Rating in kW
Connected Load Effi.
L. F.
P. F.
D. F. Unit
Total (kW)
Working Load Unit
Total (kW)
Working Load (kVA)
2.1
Pump -1
90
0.95
0.85
0.9
1
2
180
1
81
100.31
2.2
Pump -2
45
0.936
0.86
0.9
1
2
90
2
81
100.63
2.3
Crane
7.5
0.87
0.82
0.9
2
1
7.5
1
3.375
4.73
2.3 2.4
Exhaust Fan
0.5 15
0.67 0.8
0.82 0.8
1 1
1 1.5
8 Lumpsum
4 15 296.5
8 Lumpsum
4 10 179.375
7.28 15.63 228.57
3.0
Considering 20% contingency
=
4.0
System P. F.
=
0.78
5.0 5.1 5.2 5.3 5.4 5.5 5.6
Calculation to check the starting of largest size motor Rating of transformer assumed % impedance of transformer assumed Rating of the largest size motor Supply voltage P.F of largest size motor Efficiency of largest size motor
= = = = = =
315 4.5 90 0.415 0.85 0.95
Lighting Total Load
274.29 kVA
kVA % KW kV
Nearest staanddard size (Confg. 11/0.433KV,Dyn11,Delta-star) From IS 2026 From the above table System voltage From the above table From the above table kW x 1000 1.7321 x V x p.f x efficiency kW P.F x Efficiency
5.7
FLC of motor
=
155.05 A
5.8
Rating of largest size motor in kVA
=
111.46 kVA
=
203.54 kVA
(Rating in kVA of transformer assumed - Largest motor KVA)
=
668.73 kVA
= 6 x 1.7321 x kV x I FLC
222.91 kVA
= 3 x 1.7321 x kV x I FLC
5.10
Base load on transformer before starting largest motor Motor starting Kva with DOL start
5.11
Motor starting Kva with Star-Delta start
=
5.12
Fault Level at transformer secondary side
=
5.13
Fault current of transformer secondary side (ISC)
=
5.14
S.C capacity of transformer Voltage drop at transformer terminal when largest motor start with DOL starting Voltage drop at transformer terminal when largest motor start with Star-Delta starting
=
5.9
5.15 5.16
Rating of transformer in MVA x 100 Impedance of transformer in % Fault Level in MVA 1.7321 x kV
7 MVA 9.7382 kA 7000 kVA
=
12.461 %
=
6.1 %
1.7321 x kV x I SC [Motor Starting kVA (DOL) + Base Load kVA] x 100 S.C capacity of transformer [Motor Starting kVA (S/D) + Base Load kVA] x 100 S.C capacity of transformer
The selected rating of transformer is
568
315 kVA
(within 10%) (within 10%)
CAPACITOR BANK SIZING ACROSS BUS
1 Average Power factor (pf1)
0.785
2 Total Working load
179
3 Power factor To be improved (pf2)
0.98 Working load ( Tan ( Cos-1 pf1) - Tan (Cos-1 pf2))
Total kVAR to be connected across Bus 4 Total kVAR to be connected across Bus
kW
105
569
KVAR
! A) 1 2 2 3 4 5 6 7
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
= = = = = = =
Ish t K
B) 1 AREA OF CONDUCTOR 2 CABLE SIZE CHOSEN
C) LAYING CONDITIONS 1 AMBIENT AIR TEMPERATURE RATING FACTOR 2 GROUPING/SPACING WITH OTHER CABLES
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
= = =
Ish* t/K 29.30130143 35 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
= = =
45 0.95 Cable laid in ground (3 cables touching)
= =
Ifl
2 CURRENT RATING REQ.AFTER CONSIDERING DERATING 3 Current carring capacity of 3.5C x240 Sqmm AL XLPE cable is 4 No of cable required E) 1 2 3 4 5 6
315 0.415 0.8 9.738 0.08 94 30
CHECK FOR VOLTAGE DROP CABLE SIZE R AT CONDUCTOR TEMP. (3.5C x 240 SQmm AL XLPE Cable) X AT CONDUCTOR TEMP. (3.5C x 240 Qmm AL XLPE Cable) COSø SINø No of runs: % VOLTAGE DROP
7 % VOLTAGE DROP
0.69 0.6555
= = =
WORLING LOAD (KVA)/1.732 x VOLTAGE 438.24 FULL LOAD CURRENT/DERATING FACTOR 668.56 326 2.05
= =
= = = = = = =
=
CABLE SIZE CHOSEN
=
570
3.5C x240 Sqmm AL XLPE cable 0.16 0.071 0.8 0.6 2 (FULL LOAD CURRENT X LENGTH X IMPEDENCE)/NO OF RUNS X VOLTAGE 0.468041806 2X3.5CX240
sq.mm Al XLPE Cable
" A) 1 2 2 3 4 5 6 7
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
!
Ish t K
B) 1 AREA OF CONDUCTOR
#$ %
= = = = = = =
112 0.415 0.8 9.73 0.08 94 55
= = =
2 CABLE SIZE CHOSEN
Ish* t/K 29.27722971 35 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
C) LAYING CONDITIONS = 1 AMBIENT AIR TEMPERATURE RATING FACTOR = 2 GROUPING/SPACING WITH OTHER CABLES =
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
45 0.95 Cable laid in trench (9 cables touching)
= =
0.66 0.627
= WORLING LOAD (KVA)/1.732 x VOLTAGE x 1.732 = 89.97 = DERATING FULL LOAD CURRENT/DERATING FACTOR 2 CURRENT RATING REQ.AFTER CONSIDERING 143.49 142 3 Current carring capacity of 3C x50 Sqmm AL XLPE=cable is = 1.01 4 No of cable required
E) 1 2 3 4 5 6
Ifl
CHECK FOR VOLTAGE DROP CABLE SIZE = 3C x50 Sqmm AL XLPE cable = Cable) 0.82 R AT CONDUCTOR TEMP. (3C x 50 SQmm AL XLPE = Cable) 0.075 X AT CONDUCTOR TEMP. (3C x 50 Qmm AL XLPE COSø = 0.8 SINø = 0.6 No of runs: = 1 (FULL LOAD CURRENT X LENGTH X % VOLTAGE DROP = IMPEDENCE)/NO OF RUNS X VOLTAGE
7 % VOLTAGE DROP CABLE SIZE CHOSEN
= =
571
1.447620248 2X3CX50
sq.mm Al XLPE Cable
" A) 1 2 2 3 4 5 6 7
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
!
Ish t K
B) 1 AREA OF CONDUCTOR
&' %
= = = = = = =
56 0.415 0.8 9.27 0.08 94 65
= = =
2 CABLE SIZE CHOSEN
Ish* t/K 27.89310579 35 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
C) LAYING CONDITIONS = 1 AMBIENT AIR TEMPERATURE RATING FACTOR = 2 GROUPING/SPACING WITH OTHER CABLES =
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
45 0.95 Cable laid in trench (6 cables touching)
= =
0.66 0.627
= WORLING LOAD (KVA)/1.732 x VOLTAGE x 1.732 = 44.98 = DERATING FULL LOAD CURRENT/DERATING FACTOR 2 CURRENT RATING REQ.AFTER CONSIDERING 71.74 117 3 Current carring capacity of 3C x35 Sqmm AL XLPE=cable is = 0.61 4 No of cable required
E) 1 2 3 4 5 6
Ifl
CHECK FOR VOLTAGE DROP CABLE SIZE = 3C x35 Sqmm AL XLPE cable = Cable) 1.11 R AT CONDUCTOR TEMP. (3C x 35 SQmm AL XLPE = Cable) 0.0783 X AT CONDUCTOR TEMP. (3C x 35 Qmm AL XLPE COSø = 0.8 SINø = 0.6 No of runs: = 1 (FULL LOAD CURRENT X LENGTH X % VOLTAGE DROP = IMPEDENCE)/NO OF RUNS X VOLTAGE
7 % VOLTAGE DROP CABLE SIZE CHOSEN
= =
572
1.140931639 2X3CX35
sq.mm Al XLPE Cable
" A) 1 2 2 3 4 5 6 7
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
!
''
(
= = = = = = =
Ish t K
B) 1 AREA OF CONDUCTOR 2 CABLE SIZE CHOSEN
C) LAYING CONDITIONS 1 AMBIENT AIR TEMPERATURE RATING FACTOR 2 GROUPING/SPACING WITH OTHER CABLES
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
= = =
Ish* t/K 27.89310579 35 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
= = =
45 0.95 Cable laid in trench (9 cables touching)
= =
Ifl
0.66 0.627
= = =
2 CURRENT RATING REQ.AFTER CONSIDERING DERATING Considering 35% extra current 3 Current carring capacity of 3.5C x70 Sqmm AL XLPE cable is 4 No of cable required E) 1 2 3 4 5 6
55 0.415 0.8 9.27 0.08 94 40
WORLING LOAD (KVA)/1.732 x VOLTAGE 76.52 FULL LOAD CURRENT/DERATING FACTOR 122.04 164.75 179 0.92
= =
CHECK FOR VOLTAGE DROP CABLE SIZE R AT CONDUCTOR TEMP. (3.5C x 70 SQmm AL XLPE Cable) X AT CONDUCTOR TEMP. (3.5C x 70 Qmm AL XLPE Cable) COSø SINø No of runs: % VOLTAGE DROP
= = = = = = =
7 % VOLTAGE DROP
=
CABLE SIZE CHOSEN
=
573
3.5C x70 Sqmm AL XLPE cable 0.567 0.074 0.8 0.6 1 (FULL LOAD CURRENT X LENGTH X IMPEDENCE)/NO OF RUNS X VOLTAGE 0.636144578 3.5CX70 .
sq.mm Al XLPE Cable
TRANSFORMER SIZING FOR RWPS PLANT
1.0
Formula Used:
1.1
Working Load in kVA
=
[ Working Load (kW) x L. F. ] / [ D. F. x P. F. x Effi. ]
L. F.
= Load Factor
1.2
System P. F.
=
Total Working Load (kW) / Total Working Load (kVA)
P. F.
= Motor Power Factor
2.0
D. F.
= Diversity Factor
Effi.
= Motor Efficiency
Input Data and Calculations:
Sr. No.
Item Description
Connected Load
Rating in kW
Effi.
P. F.
L. F.
D. F.
Working Load
Unit
Total (kW)
Unit
Total (kW)
Working Load (kVA)
2.1
Vertcal Pump
132
0.957
0.86
0.9
1
3
396
2
237.6
288.69
2.2
Dewatering pump
1.5
0.79
0.81
1
1.5
1
1.5
1
1
1.56
2.3
EOT crane
15
0.902
0.81
0.9
2
1
15
1
6.75
9.24
2.4
Chain pully
3.7
0.83
0.82
0.9
2
1
3.7
1
1.665
2.45
2.5
Exhaust fan
0.5
0.67
0.82
1
1
6
3
6
3
5.46
2.6
Lighting (Indoor & Outdoor)
10
0.9
0.8
1
1.5
Lumsum
10
Total Load
429.2
3.0 Considering 20% contingency
=
376.29 kVA
4.0 System P. F.
=
0.8186
5.0 Calculation to check the starting of largest size motor 5.1 Rating of transformer assumed = 5.2 % impedance of transformer assumed = 5.3 Rating of the largest size motor = 5.4 Supply voltage = 5.5 P.F of largest size motor = 5.6 = Efficiency of largest size motor
400 4.5 132 0.415 0.86 0.957
kVA % KW kV
223.122046 A
Lumsum 6.6666667 256.68167
6.17 313.57
Nearest staanddard size (Confg. 33/0.433KV,Dyn11,Delta-star) From IS 2026 From the above table System voltage From the above table From the above table kW x 1000 1.7321 x V x p.f x efficiency kW P.F x Efficiency
5.7
FLC of motor
=
5.8
Rating of largest size motor in kVA
=
160.3849238 kVA
=
239.6150762 kVA
(Rating in kVA of transformer assumed - Largest motor KVA)
=
962.3095429 kVA
= 6 x 1.7321 x kV x I FLC = 3 x 1.7321 x kV x I FLC
5.10
Base load on transformer before starting fourth largest motor Motor starting Kva with DOL start
5.11
Motor starting Kva with Star Delta start
=
320.7698476 kVA
5.12
Fault Level at transformer secondary side
=
8.888888889 MVA
5.13
Fault current of transformer secondary side (ISC)
=
12.36591962 kA
5.14
S.C capacity of transformer Voltage drop at transformer terminal when largest motor start with DOL starting Voltage drop at transformer terminal when largest motor start with Star Delta starting
=
8888.888889 kVA
=
13.52165196 %
=
6.3 %
5.9
5.15 5.16
Rating of transformer in MVA x 100 Impedance of transformer in % Fault Level in MVA 1.7321 x kV 1.7321 x kV x I SC [Motor Starting kVA (DOL) + Base Load kVA] x 100 S.C capacity of transformer [Motor Starting kVA (S/D) + Base Load kVA] x 100 S.C capacity of transformer
The selected rating of transformer is
574
400 kVA
(within 10%) (within 10%)
CAPACITOR BANK SIZING ACROSS BUS
Intermediate Pumping Station 1 Average Power factor (pf1)
0.819
2 Total Working load in IPS
257
3 Power factor To be improved (pf2)
0.98 Working load ( Tan ( Cos-1 pf1) - Tan (Cos-1 pf2))
Total kVAR to be connected across Bus 4 Total kVAR to be connected across Bus
kW
128
575
KVAR
Short circuit calculation RWPS Assumptions 1 Fault level at 220kV bus
20000 MVA
2 Base MVA
(as per IS :2026)
2000
Transformer Details at Chandaka220KV/132KV Ratio = 220kV / 132kV 100.00 MVA Capacity = 9.27% Z= 1 Nos Qty 8.34% Considering negative tolerance Z = 8.34% Net Z for transformers single transformer= 3 Transformer Details at Chandaka 132KV/33KV Ratio = 132kV / 33kV 40.00 MVA Capacity = 10.18% Z= 1 Nos Qty 9.16% Considering negative tolerance Z = 9.16% Net Z for transformers single transformer= 4 33kV Over head line from Chandaka to CWPS Line length = Conductor Type = Conductor Resiatance = Z,Considering Reactance Negligible =
18 DOG 0.2733 4.9194
kM Assumed ohm/kM ohm
5 Transformer at CWPS Ratio = 33kV / 0.415kV 0.40 MVA Capacity = 4.5% Z= 1 Nos Qty 4.1% Considering negative tolerance Z = 4.1% Net Z for transformers single transformer= 6
7
K' Constant for XLPE AL cable=
94
K' Constant for PVC AL cable=
75
K' Constant for PVC CU cable=
112
Fault clearing time for 33kV Breaker (t) = 1
Sec
Fault clearing time for 0.415kV ACB Breaker (t) = 0.08
10
Fault clearing time for 0.415kV MCCB Breaker (t) = 0.04 Starting Voltage dip =
Sec Sec 15%
11
Starting current for DOL=
6 times
12
Starting current for Y-D=
2 times
13
Starting current for FCMA softstarter=
2.5 times
Formula used 1
2
Zsource =
Ztransformer =
Base MVA Fault level at 220kV bus Base MVA Transformer capacity in MVA
X tranformer Z%
3
Zline =
Base MVA 2 kV
X Line Z
4
Zcable =
Base MVA 2 kV
X Cable Z
576
Calculation Sr No Description a chandaka Grid Substation
b
Impedance " Z"
220KV Bus
0.1
220KV/132KV,100MVA transformer
1.7
1 132kV Bus
1.8
2 132kV/33kV,40MVA transformer
4.6
3 33kV Bus
6.3
Fault level Fault Current "MVA" "kA"
Minimum Cable size "SQMM"
20000
52
1130.8
5
315.0
5.51
130.0
2.27
24.2
9.2
12.77
38.4 (XLPE,AL,0.415kV)
8.1
11.22
33.8 (,AL,0.415 kV)
3.7
5.20
11.1
RWPS 1 18 kM 33kV O/H line from Chandaka Substation to RWPS
9.03
2 33kV Bus
15.38
3 33kV/0.415kV, 0.4MVA transformer
202.50
4 0.415kV side of 0.4MVA transformer
217.88
0.415kV , XLPE ,3 X 3.5core x 185sqmm cable from 5 transformer to RWPS PMCC
30.07
6 RWPS PMCC
247.95
0.415kV , XLPE ,3.5core x 50sqmm cable from RWPS 7 PMCC to RWPS Auxilary MCC
286.87
8 RWPS Auxilary MCC
534.82
577
A) 1 2 2 3 4 5 6 7
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
= = = = = = =
Ish t K
B) 1 AREA OF CONDUCTOR 2 CABLE SIZE CHOSEN
C) LAYING CONDITIONS 1 AMBIENT AIR TEMPERATURE RATING FACTOR 2 GROUPING/SPACING WITH OTHER CABLES
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
= = =
Ish* t/K 36.76955262 50 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
= = =
45 0.95 Cable laid in Ground (3 cables touching)
= =
Ifl
2 CURRENT RATING REQ.AFTER CONSIDERING DERATING 3 Current carring capacity of 3.5C x185 Sqmm AL XLPE cable is 4 No of cable required E) 1 2 3 4 5 6
400 0.415 0.8 12.22 0.08 94 35
CHECK FOR VOLTAGE DROP CABLE SIZE R AT CONDUCTOR TEMP. (3.5C x 185SQmm AL XLPE Cable) X AT CONDUCTOR TEMP. (3.5C x 185 Qmm AL XLPE Cable) COSø SINø No of runs: % VOLTAGE DROP
7 % VOLTAGE DROP
0.69 0.6555
= = =
WORLING LOAD (KVA)/1.732 x VOLTAGE 556.50 FULL LOAD CURRENT/DERATING FACTOR 848.97 282 3.01
= =
= = = = = = =
=
CABLE SIZE CHOSEN
=
578
3.5C x185 Sqmm AL XLPE cable 0.21 0.0718 0.8 0.6 3 (FULL LOAD CURRENT X LENGTH X IMPEDENCE)/NO OF RUNS X VOLTAGE 0.571949485 3X3.5CX185 sq.mm Al XLPE Cable
!"# A) 1 2 2 3 4 5 6 7
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
= = = = = = =
Ish t K
B) 1 AREA OF CONDUCTOR 2 CABLE SIZE CHOSEN
C) LAYING CONDITIONS 1 AMBIENT AIR TEMPERATURE RATING FACTOR 2 GROUPING/SPACING WITH OTHER CABLES
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
= = =
Ish* t/K 31.08260872 35 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
= = =
45 0.95 Cable laid in trench (9 cables touching)
= =
Ifl
0.69 0.6555
= = =
2 CURRENT RATING REQ.AFTER CONSIDERING DERATING 3 Current carring capacity of 3C x95 Sqmm AL XLPE cable is 4 No of cable required E) 1 2 3 4 5 6
160 0.415 0.8 10.33 0.08 94 45
WORLING LOAD (KVA)/1.732 x VOLTAGE x 1.732 128.52 FULL LOAD CURRENT/DERATING FACTOR 196.07 221 0.89
= =
CHECK FOR VOLTAGE DROP CABLE SIZE R AT CONDUCTOR TEMP. (3C x 70SQmm AL XLPE Cable) X AT CONDUCTOR TEMP. (3C x 70SQmm AL XLPE Cable) COSø SINø No of runs: % VOLTAGE DROP
= = = = = = =
7 % VOLTAGE DROP
=
CABLE SIZE CHOSEN
=
579
3C x95 Sqmm AL XLPE cable 0.41 0.0724 0.8 0.6 1 (FULL LOAD CURRENT X LENGTH X IMPEDENCE)/NO OF RUNS X VOLTAGE 0.896555308 2X3CX95
sq.mm Al XLPE Cable
$%&' ( A) 1 2 2 3 4 5 6 7
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
= = = = = = =
Ish t K
B) 1 AREA OF CONDUCTOR 2 CABLE SIZE CHOSEN
C) LAYING CONDITIONS 1 AMBIENT AIR TEMPERATURE RATING FACTOR 2 GROUPING/SPACING WITH OTHER CABLES
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
= = =
Ish* t/K 31.08260872 35 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
= = =
45 0.95 Cable laid in trench (9 cables touching)
= =
Ifl
2 CURRENT RATING REQ.AFTER CONSIDERING DERATING 3 Current carring capacity of 3.5C x50 Sqmm AL XLPE cable is 4 No of cable required E) 1 2 3 4 5 6
59 0.415 0.8 10.33 0.08 94 30
CHECK FOR VOLTAGE DROP CABLE SIZE R AT CONDUCTOR TEMP. (3.5C x 50SQmm AL XLPE Cable) X AT CONDUCTOR TEMP. (3.5C x 50 Qmm AL XLPE Cable) COSø SINø No of runs: % VOLTAGE DROP
7 % VOLTAGE DROP
0.69 0.6555
= = =
WORLING LOAD (KVA)/1.732 x VOLTAGE 82.08 FULL LOAD CURRENT/DERATING FACTOR 125.22 142 0.88
= =
= = = = = = =
=
CABLE SIZE CHOSEN
=
580
3.5C x50 Sqmm AL XLPE cable 0.82 0.075 0.8 0.6 1 (FULL LOAD CURRENT X LENGTH X IMPEDENCE)/NO OF RUNS X VOLTAGE 0.720435477 3.5CX50
sq.mm Al XLPE Cable
)* A) 1 2 2 3 4 5 6 7
FEEDER DATA WORKING LOAD (KW) WORKING LOAD (KVA) VOLTAGE (V) PF FAULT CURRENT FAULT CLEARING TIME CONSTANT LENGTH
Ish t K
B) 1 AREA OF CONDUCTOR
+ , +&
= = = = = = =
75 0.415 0.8 10.63 0.08 94 40
= = =
2 CABLE SIZE CHOSEN
Ish* t/K 31.98529823 35 SQ.MM AL (AS PER SHORT CIRCUIT CALCULATION)
C) LAYING CONDITIONS = 1 AMBIENT AIR TEMPERATURE RATING FACTOR = 2 GROUPING/SPACING WITH OTHER CABLES =
RATING FACTOR 3 OVERALL DERATING FACTOR D) 1 FULL LOAD CURRENT
45 0.95 Cable laid in trench (9 cables touching)
= =
0.66 0.627
= WORLING LOAD (KVA)/1.732 x VOLTAGE = 104.34 = DERATING FULL LOAD CURRENT/DERATING FACTOR 2 CURRENT RATING REQ.AFTER CONSIDERING 166.42 Considering 35% extra current 224.66 3 Current carring capacity of 3.5C x95 Sqmm AL XLPE = cable is 221 4 No of cable required = 1.02
E) 1 2 3 4 5 6
Ifl
CHECK FOR VOLTAGE DROP CABLE SIZE = 3.5C x95 Sqmm AL XLPE cable R AT CONDUCTOR TEMP. (3.5C x 95 SQmm AL XLPE = Cable) 0.41 X AT CONDUCTOR TEMP. (3.5C x 95 Qmm AL XLPE = Cable) 0.0724 COSø = 0.8 SINø = 0.6 No of runs: = 1 (FULL LOAD CURRENT X LENGTH X % VOLTAGE DROP = IMPEDENCE)/NO OF RUNS X VOLTAGE
7 % VOLTAGE DROP
=
CABLE SIZE CHOSEN
=
581
0.64701408 3.5CX95
sq.mm Al XLPE Cable
View more...
Comments