Updated Project Schedule

July 8, 2018 | Author: Ahmad Ramin Abasy | Category: Wall, Sanitary Sewer, Roof, Structural Steel, Electrical Wiring
Share Embed Donate


Short Description

schedule...

Description

 Acti vity ID

 Acti vity Description

Orig Dur 

Rem Dur 

%

Ear l y Start

Early Finish

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A S

Total Float

W5J9JR-10-D-0005-0006 ANA Gardez  Total  Total

773 773

158 158

68 26J 26J UL11A UL11A

100 26J UL11A

05SEP 05SEP 13

-32 -32

Milestones Contract Milestones

KE Y-0001

Notice to P roceed (NTP )

KE Y-0002

P roject Duration

KE Y-0003

E nd Date of P roject

0

0

773*

158*

0

0

0 26J UL11A

05S EP 13

-32

0

05S EP 13

-32

Project Milestones

KE Y-0004

S tart Work on P roject

0

0

100 27J UL11A

KE Y-0005

R elease P artial Letter for CON

1

0

100 09 09MAY12A

KE Y-0006

R elease Letter for Full CON

1

1

0 01AP R13

09MAY 12A 01AP R 13

-7

Pre-construction Pre-construction Meetings

KE Y-0007

P rovide Documents for P re-CON

6

0

100 27 27J UL11A

01AUG11A

KE Y-0008

Hold P re-CON Meeting

1

0

100 02AUG11A

02AUG11A

Pre-construction Submittals

KE Y-0009

S ubmit ActivityHazard Analysis

1

0

100 02 02AUG11A

02AUG11A

KE Y-0010

S ubmit Baseline Schedule

1

0

100 02AUG11A

02AUG11A

KE Y-0011

S ubmit Accidend P reventionP lan

1

0

100 02 02AUG11A

02AUG11A

KE Y-0012

S ubmit Quality Control P lan

1

0

100 02 02AUG11A

02AUG11A

KE Y-0013

S ubmit Security P lan

1

0

100 02AUG11A

02AUG11A

KE Y-0014

Approve Activity Hazard Analysis

14

0

100 03 03AUG11A

16AUG11A

KE Y-0015

Approve Baseline S chedule

14

0

100 03 03AUG11A

16AUG11A

KE Y-0016

Approve AccidentP reventionP lan

14

0

100 03 03AUG11A

16AUG11A

KE Y-0017

Approve QC P lan by US ACE

14

0

100 03AUG11A

16AUG11A

KE Y-0018

Approved Security P lan by AED

14

0

100 03 03AUG11A

16AUG11A

S tart Date Finish Date Data Date Run Date

26J UL11 05S EP 13 01AP R13 13AP R13 10:09

Early Bar Progress Bar Critical Activity

P S 19

FCEC UIP rojects J V W5J 9J R-10-D-0005 R-10-D-0005-000 -0006 6 ANA Gardez P roject Management Layout

Sheet 1 of 38 Date

Revision

Checked

Approved

 Acti vity ID

 Acti vity Description

Orig Dur 

Rem Dur 

%

Ear l y Start

Early Finish

Total Float

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A S

DBA Insurance

KE Y-0019

DBA Insurance

1

0

100 26J UL11A

26AUG11A

Design 10% Design Submittal

DES -0001

S ite Survey

22

0

100 10AUG11A

05S EP 11A

DES -0003

10% Site Design Submittal

13

0

100 10 10OCT11A

25OCT11A

DES -0002

Geotechnical R eport

12

0

100 26OCT11A

06NOV11A

DES -0004

10% Site Design Conference / Approval

14

0

100 26 26OCT11A

08NOV11A

DES -0014

P ay Request 10% Desgin

1

0

100 09NOV11A

09NOV11A

65% Design Submittal

DES -0005

65% Design S ubmittal

DES -0016

65% Design Conference / Approval

DES -0006

P ay Request 65% Design

4

0

100 24MAR 12A

27MAR 12A

14

0

100 29 29MAR 12A

08AP R 12A

1

0

100 05J UN12A

05J UN12A

100% Design Submittall

DES -0009

100% Design Submittal

10

0

100 10OCT12A

24OCT12A

DES -0010

100% Design Conference / Approval

14

0

100 25 25OCT12A

31OCT12A

DES -0020

P ay Request 100% Design

1

0

100 01NOV12A

01NOV12A

Procurement Civil/Structural Concrete Reinforecement

P R O-0001

S ubmit R einforcement S teel

P R O-0002

Approved Reinforcement S teel

5

0

100 13 13NOV11A

17NOV11A

14

0

100 18 18NOV11A

01DEC11A

P R O-0003

Issue P archase Order for SS

2

0

100 17 17DE C11A

19DEC11A

P R O-0004

Delivery of SS to J obsite

5

0

100 08MAY12A

11MAY 12A

S tart Date Finish Date Data Date Run Date

26J UL11 05S EP 13 01AP R13 13AP R13 10:09

Early Bar Progress Bar Critical Activity

P S 19

FCEC UIP rojects J V W5J 9J R-10-D-0005 R-10-D-0005-000 -0006 6 ANA Gardez P roject Management Layout

Sheet 2 of 38 Date

Revision

Checked

Approved

 Acti vity ID

 Acti vity Description

Orig Dur 

Rem Dur 

%

Ear l y Start

Early Finish

Total Float

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A S

DBA Insurance

KE Y-0019

DBA Insurance

1

0

100 26J UL11A

26AUG11A

Design 10% Design Submittal

DES -0001

S ite Survey

22

0

100 10AUG11A

05S EP 11A

DES -0003

10% Site Design Submittal

13

0

100 10 10OCT11A

25OCT11A

DES -0002

Geotechnical R eport

12

0

100 26OCT11A

06NOV11A

DES -0004

10% Site Design Conference / Approval

14

0

100 26 26OCT11A

08NOV11A

DES -0014

P ay Request 10% Desgin

1

0

100 09NOV11A

09NOV11A

65% Design Submittal

DES -0005

65% Design S ubmittal

DES -0016

65% Design Conference / Approval

DES -0006

P ay Request 65% Design

4

0

100 24MAR 12A

27MAR 12A

14

0

100 29 29MAR 12A

08AP R 12A

1

0

100 05J UN12A

05J UN12A

100% Design Submittall

DES -0009

100% Design Submittal

10

0

100 10OCT12A

24OCT12A

DES -0010

100% Design Conference / Approval

14

0

100 25 25OCT12A

31OCT12A

DES -0020

P ay Request 100% Design

1

0

100 01NOV12A

01NOV12A

Procurement Civil/Structural Concrete Reinforecement

P R O-0001

S ubmit R einforcement S teel

P R O-0002

Approved Reinforcement S teel

5

0

100 13 13NOV11A

17NOV11A

14

0

100 18 18NOV11A

01DEC11A

P R O-0003

Issue P archase Order for SS

2

0

100 17 17DE C11A

19DEC11A

P R O-0004

Delivery of SS to J obsite

5

0

100 08MAY12A

11MAY 12A

S tart Date Finish Date Data Date Run Date

26J UL11 05S EP 13 01AP R13 13AP R13 10:09

Early Bar Progress Bar Critical Activity

P S 19

FCEC UIP rojects J V W5J 9J R-10-D-0005 R-10-D-0005-000 -0006 6 ANA Gardez P roject Management Layout

Sheet 2 of 38 Date

Revision

Checked

Approved

 Acti vity ID

P R O-0064

 Acti vity Description

Orig Dur 

P roduction of Concrete

Rem Dur 

10

%

0

Ear l y Start

100 12MAY12A

Early Finish

Total Float

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A S

21MAY 12A

3D Panel

P R O-0009

S ubmit 3D Data Sheet

P R O-0010

Approve 3D Data

5

0

100 21AP R12A

25AP R 12A

14

0

100 25AP R12A

05MAY 12A

P R O-0011 P R O-0072

Issue P urchase Order for 3D

5

0

100 05 05MAY12A

09MAY 12A

P roduction of 3D for P roject

10

0

100 10 10MAY12A

P R O-0012

Deliver of 3D to J obsite

20MAY 12A

5

0

100 21MAY12A

25MAY 12A

K Span

P R O-0060

S ubmit K S pan

5

0

100 21AP R12A

25AP R 12A

P R O-0061

Approve K Span

14

0

100 25AP R12A

08MAY 12A

P R O-0062

Manufacturing of K S pan

10

0

100 09MAY12A

19MAY 12A

P R O-0063

Deliver of K S pan to J obsite

5

0

100 19MAY12A

23MAY 12A

 Arch  Ar chit it ectu ral Joint Sealant

P R O-0005

S ubmit J oint S ealants

P R O-0006

Approved J oint S ealants

P R O-0007

Issue P urchase Order for SJ S

P R O-0068

Material's P roduction for P roject

P R O-0008

Delivery of S J S at J obsite

5

0

100 15AP R12A

19MAY 12A

14

0

100 20AP R12A

03MAY 12A 09MAY 12A

5

0

100 05 05MAY12A

15

0

100 09 09MAY12A

23MAY 12A

5

0

100 23MAY12A

27MAY 12A

Doors & Frames Frames

P R O-0013

S ubmit Doors & F rames

P R O-0014

Approved Doors & Frames

P R O-0015

Issue P urchase Order for DR

P R O-0016

Manufacturing of Doors

P R O-0017

Delivery of Doors to J obsite

5

0

100 02OCT11A

11OCT11A

14

0

100 12OCT11A

25OCT11A

2

0

100 29 29OCT11A

30OCT11A

10

0

100 12MAY12A

21MAY 12A

5

0

100 22J UN12A

01J UL12A

Windows and Frames

P R O-0018

S ubmit Windows & F rames

P R O-0019

Approved Windows & Frames

P R O-0020

Issue P ruchase Order for WDW

P R O-0021

Manufacturing of Windows

P R O-0022

Delivery of Windows to J obsite

S tart Date Finish Date Data Date Run Date

26J UL11 05S EP 13 01AP R13 13AP R13 10:09

Early Bar Progress Bar Critical Activity

5

0

100 18S E P 11A

27S EP 11A

14

0

100 12 12MAY12A

25MAY 12A 26MAY 12A

2

0

100 25 25MAY12A

10

0

100 10 10NOV12A

19NOV12A

5

0

100 20 20NOV12A

01J AN13A

P S 19

FCEC UIP rojects J V W5J 9J R-10-D-0005 R-10-D-0005-000 -0006 6 ANA Gardez P roject Management Layout

Sheet 3 of 38 Date

Revision

Checked

Approved

 Acti vity ID

 Acti vity Description

Orig Dur 

Rem Dur 

%

Early Start

Early Finish

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A S

Total Float

Stucco & Paint

PRO-0023

Sumbit Stucco, Paint&Coating

PRO-0024

Approve Stucco, Paint&Coating

PRO-0025

Purchase Order for Stucco & P

PRO-0066

Material's Manufacturing for Project

PRO-0026

Deliver Stucco & P at J obsite

5

0

100 20APR12A

24APR12A

14

0

100 24APR12A

07MAY12A

2

0

100 07MAY12A

08MAY12A

18

0

100 01OCT12A

07OCT12A

6

0

100 07OCT12A

14OCT12A

Electrical Generator 

PRO-0027

Submit Generator Product Data

10

0

100 31MAR12A

09APR12A

PRO-0028

Approve Generator Product Data

14

0

100 09APR12A

16APR12A

PRO-0029

Purchase Order for Generator

2

0

100 21APR12A

PRO-0030

Manufacturing the Generators

30

30

0 01APR13

30APR13

7

PRO-0031

Shipment of Generator

20

20

0 01MAY13

20MAY13

7

PRO-0032

Deliver of Generator at site

15

15

0 21MAY13

04J UN13

7

22APR12A

Lighting System

PRO-0033

Submit Lighting System

10

0

100 03SEP11A

13SEP11A

PRO-0034

Approve Lighting System

14

0

100 17SEP11A

30SEP11A

PRO-0035

Purchase Order for LTG SYS

PRO-0036

Shipment Lighting System

PRO-0037

Deliver of LTG SYS Material

2

0

100 01OCT11A

02OCT11A

20

0

100 01DEC12A

01J AN13A

8

0

100 01J AN13A

28FEB13A

Pannel Board and Transfer Switch

PRO-0038

Submit EP & TRANS Switch

PRO-0039

Approve EP & TRANS Switch

PRO-0040

Purchase Order for EP/TRANS SW

PRO-0041

Manufacture EP/TRANS Switch

PRO-0042

Shipment of EP & TRANS Switch

PRO-0043

Delivere EP & TRANS SW at Site

1

0

100 29AUG11A

29AUG11A

14

0

100 29AUG11A

03SEP11A

2

0

100 10SEP11A

11SEP11A

60

60

0 01APR13

30MAY13

-31

40

40

0 31MAY13

09J UL13

-31

10

10

0 10J UL13

19J UL13

-31

Electric al Distribution System

PRO-0044

Submit ELECT Distribution MAT

1

0

100 08SEP11A

08SEP11A

PRO-0045

Approve ELECT Distribution MAT

14

0

100 08SEP11A

13SEP11A

PRO-0046

PurchaseOrder forELEC Material

1

0

100 15SEP11A

15SEP11A

Start Date Finish Date Data Date Run Date

26J UL11 05SEP13 01APR13 13APR13 10:09

Early Bar Progress Bar Critical Activity

PS19

FCEC UIProjects J V W5J 9J R-10-D-0005-0006 ANA Gardez Project Management Layout

Sheet 4 of 38 Date

Revision

Checked

Approved

 Acti vity ID

 Acti vity Description

Orig Dur 

Rem Dur 

%

Early Start

Early Finish

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A S

Total Float

PRO-0048

Shipment of ELECT Material

6

3

50 23APR12A

03APR13

41

PRO-0049

Deliver ELECT Material at site

3

1

50 28APR12A

01APR13

41

PRO-0047

Manufacturing of ELEC Material

5

0

100 25MAY12A

05J UN12A

Mechanical

PRO-0055

Submit Mechcanical Matrials

PRO-0056

Approve Mechcanical Matrials

1

1

0 02APR13

02APR13

-7

14

14

0 03APR13

16APR13

-7

PRO-0057

Purchase Order Mechcanical Matrials

2

2

0 17APR13

18APR13

-7

PRO-0058

Shipment of Mechcanical Matrials

45

45

0 19APR13

02J UN13

-7

PRO-0059

Deliver Mechcanical Matrials to the site

15

15

0 03J UN13

17J UN13

-7

Plumbing Water and Sewer Pipes

PRO-0050

Submit Water & Sewer Pipes

30

0

100 17SEP11A

22SEP11A

PRO-0051

Approve Water & Sewer Pipes

14

0

100 23SEP11A

05OCT11A

PRO-0052

Purchase Order-W & Sewer Pipes

2

0

100 08OCT11A

09OCT11A

PRO-0053

Shipment of W & Sewer Pipes

35

0

100 16APR12A

21MAY12A

PRO-0054

Deliver W & Sewer Pipe at site

35

0

100 22APR12A

26MAY12A

Construction Mobilization

MOB-0001 Grading/Leveling the Area

19

0

100 10SEP11A

29SEP11A

MOB-0002 Install. of Fence around Camp Area

20

0

100 30SEP11A

15OCT11A

MOB-0012 Installation of Conexes

10

0

100 16OCT11A

26OCT11A

MOB-0022 Construction of Buildings

20

0

100 27OCT11A

08DEC11A

Sitework Site Demolition/Grading

SDG-0001

Grubbing of Site

SDG-0002

Grading & Demolising

SDG-0003

Removing Materials from site

Start Date Finish Date Data Date Run Date

26J UL11 05SEP13 01APR13 13APR13 10:09

Early Bar Progress Bar Critical Activity

10

0

100 01APR12A

05J UN12A

9

0

100 04APR12A

20OCT12A

12

0

100 10APR12A

23OCT12A

PS19

FCEC UIProjects J V W5J 9J R-10-D-0005-0006 ANA Gardez Project Management Layout

Sheet 5 of 38 Date

Revision

Checked

Approved

 Acti vity ID

 Acti vity Description

Orig Dur 

Rem Dur 

%

Early Start

Early Finish

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A S

Total Float

Soccer Field Irrigation System

STO-0001

Layout for Irrigation Pipes

10

10

0 01APR13

11APR13

27

STO-0002

Excavation/leveling/Lay Pipes

20

20

0 13APR13

05MAY13

27

STO-0003

Backfilling/Compaction

20

20

0 06MAY13

28MAY13

27

STO-0004

Punchlist Correction

8

8

0 29MAY13

06J UN13

27

STO-0005

Finish & Handover

1

1

0 08J UN13

08J UN13

27

Road Network, Walkways, Parking Roads RPS-0007

Road Layout

2

0

100 01MAY12A

RPS-0008

Road Sub-Grade

15

0

100 07MAY12A

15MAY12A 23MAY12A

RPS-0009

Compact Sub-Grade of Road

15

0

100 12MAY12A

03J UN12A

RPS-0010

Road Base Course

14

0

100 17MAY12A

22MAY12A

RPS-0011

Compact Base-Course of Road

10

0

100 24MAY12A

15SEP12A

RPS-0012

Asphalt pavement

10

0

100 12SEP12A

23SEP12A

RPS-0024

Soil Ditch

10

0

100 18SEP12A

29SEP12A

RPS-0013

Test & Completion

2

2

0 01APR13

02APR13

35

57

Crush Around Building RPS-0014

Layout/Level of Crush

1

1

0 13APR13

13APR13

RPS-0015

Sub Grade for Crush

10

10

0 14APR13

24APR13

57

RPS-0017

Compaction of Crush all arround Building

15

15

0 16APR13

02MAY13

57

RPS-0018

Test & Completion for Crush

1

1

0 04MAY13

04MAY13

57

35

Concrete walkways RPS-0019

Layout for Sidewalks

2

2

0 03APR13

04APR13

RPS-0020

Sub Base for Sidewalks

15

15

0 06APR13

22APR13

35

RPS-0021

Base Course for Sidewalks

15

15

0 23APR13

09MAY13

35

RPS-0022

Pour Concrete for Sidewalks

15

15

0 11MAY13

27MAY13

35

RPS-0023

Test & Completion of Sidewalks

2

2

0 28MAY13

29MAY13

35

 Athletic Field & Track Field & Track RPS-0025

Layout Athletic Field & Track

1

0

100 12MAY12A

12MAY12A

RPS-0026

Excavation Athletic Field & Track

10

0

100 15MAY12A

26MAY12A

RPS-0027

Backfiling/Compaction Athletic Field & Track

14

0

100 21MAY12A

18J UL12A

RPS-0028

Grass/Cursh for Athletic

10

10

0 01APR13

11APR13

75

RPS-0029

Test & Completion of Field & Track

1

1

0 13APR13

13APR13

75

Start Date Finish Date Data Date Run Date

26J UL11 05SEP13 01APR13 13APR13 10:09

Early Bar Progress Bar Critical Activity

PS19

FCEC UIProjects J V W5J 9J R-10-D-0005-0006 ANA Gardez Project Management Layout

Sheet 6 of 38 Date

Revision

Checked

Approved

 Acti vity ID

 Acti vity Description

Orig Dur 

Rem Dur 

%

Early Start

Early Finish

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A S

Total Float

Volleyball Fields 1st Field RPS-0030

Layout Volleyball Fields

1

0

100 12MAY12A

12MAY12A

RPS-0031

Excavation Volleyball Fields

10

0

100 20MAY12A

16J UL12A

RPS-0032

Backfiling / Compaction Volleyball Fields

10

0

100 03J UL12A

16J UL12A

RPS-0033

Sand for Volleyball Fields

10

0

100 22J UL12A

26AUG12A

RPS-0034

Test & Completion Volleyball Fields

1

1

0 01APR13

01APR13

85

2nd Field RPS-0035

Layout Volleyball Fields

1

0

100 12MAY12A

12MAY12A

RPS-0036

Excavation Volleyball Fields

12

0

100 16MAY12A

24J UL12A

RPS-0037

Backfiling / Compaction Volleyball Fields

12

0

100 04J UN12A

26AUG12A

RPS-0038

Sand for Volleyball Fields

12

0

100 18NOV12A

RPS-0039

Test & Completion Volleyball Fields

1

1

0 01APR13

01DEC12A 01APR13

85

Force Protection Personnel Bunker  BUNKER #1,2,3 FPR-0001

Layout for Bunker #1,2,3

1

0

100 18NOV12A

18NOV12A

FPR-0002

Casting for Bunker #1,2,3

8

0

100 19NOV12A

27NOV12A

FPR-0003

Construct Bunker #1,2,3

4

0

100 21NOV12A

09J AN13A

FPR-0004

Cmplt Sandbag & T. Barriers of B. #1,2,3

6

6

70 10DEC12A

07APR13

79

FPR-0005

Test & Completion of Bunker #1,2,3

1

1

0 08APR13

08APR13

79

BUNKER #4,5,6 FPR-0006

Layout for Bunker #4,5,6

1

0

100 02DEC12A

02DEC12A

FPR-0007

Casting for Bunker #4,5,6

8

0

100 03DEC12A

17DEC12A

FPR-0008

Construct Bunker #4,5,6

4

0

100 18DEC12A

09J AN13A

FPR-0009

Cmplt Sandbag & T. Barriers of B. #4,5,6

6

6

70 10FEB13A

07APR13

78

FPR-0010

Test & Completion of Bunker #4,5,6

1

1

0 08APR13

08APR13

78

BUNKER #7,8,9 FPR-0012

Casting Bunker #7,8,9

8

0

100 18DEC12A

26DEC12A

FPR-0011

Layout for Bunker #7,8,9

1

0

96 18DEC12A

31MAR13

FPR-0013

Construct Bunker #7,8,9

4

0

100 20DEC12A

14J AN13A

FPR-0014

Cmplt Sandbag & T. Barriers of B. #7,8,9

6

6

25 10J AN13A

07APR13

79

FPR-0015

Test & Completion of Bunker #7,8,9

1

1

0 09APR13

09APR13

78

85

BUNKER #10,11,12,13 FPR-0016

Layout for Bunker #10,11,12,13

1

0

100 31DEC12A

31DEC12A

FPR-0017

Casting for Bunker #10,11,12,13

10

0

100 31DEC12A

03J AN13A

FPR-0018

Construct Bunker #10,11,12,13

4

0

100 06J AN13A

FPR-0019

Cmplt Sandbag & T.Barriers of B.#10,11,12,13

6

6

25 18MAR13A

07APR13

78

FPR-0020

Test & Completion of Bunker#10,11,12,13

1

1

0 08APR13

08APR13

78

14J AN13A

BUNKER #14,15,16,17 FPR-0021

Layout for Bunker #14,15,16,17

1

0

100 31DEC12A

31DEC12A

FPR-0022

Casting for Bunker #14,15,16,17

10

0

100 31DEC12A

06J AN13A

Start Date Finish Date Data Date Run Date

26J UL11 05SEP13 01APR13 13APR13 10:09

Early Bar Progress Bar Critical Activity

PS19

FCEC UIProjects J V W5J 9J R-10-D-0005-0006 ANA Gardez Project Management Layout

Sheet 7 of 38 Date

Revision

Checked

Approved

 Acti vity ID

 Acti vity Description

Orig Dur 

Rem Dur 

%

Early Start

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A S

Total Float

FPR-0023

Construct Bunker #14,15,16,17

4

0

FPR-0024

Cmplt Sandbag & T.Barriers of B. #14,15,16,17

6

6

0 01APR13

07APR13

79

FPR-0025

Test & Completion of Bunker #14,15,16,17

1

1

0 09APR13

09APR13

78

FPR-0026

Layout for Bunker #18,19,20,21

1

0

100 10DEC12A

11DEC12A

FPR-0027

Casting for Bunker #18,19,20,21

10

0

100 12DEC12A

22DEC12A

FPR-0028

Construct Bunker #18,19,20,21

4

0

100 23DEC12A

14J AN13A

FPR-0029

Cmplt Sandbag & T.Barriers of B.#18,19,20,21

6

6

25 18MAR13A

07APR13

79

FPR-0030

Test & Completion of Bunker#18,19,20,21

1

1

0 08APR13

08APR13

79

FPR-0031

Layout for Bunker #22,23,24,25

1

0

100 10DEC12A

11DEC12A

FPR-0032

Casting for Bunker #22,23,24,25

10

0

100 12DEC12A

23DEC12A

FPR-0033

Construct Bunker #22,23,24,25

4

0

100 24DEC12A

14J AN13A

FPR-0034

Cmplt Sandbag & T.Barriers of B.#22,23,24,25

6

6

25 18MAR13A

07APR13

79

FPR-0035

Test & Completion of Bunker#22,23,24,25

1

1

0 08APR13

08APR13

79

FPR-0036

Area Layout for ECP

1

0

100 12MAY12A

12MAY12A

FPR-0044

ECP Construct Main Drop Gate

7

0

100 19MAY12A

25MAY12A

FPR-0037

ECP FDN Works

8

0

100 02J UN12A

09J UN12A

FPR-0038

Slab on Grade Work for ECP

12

0

100 12AUG12A

28AUG12A

FPR-0039

CMU Wall&Slab Work for ECP

14

0

100 15AUG12A

28AUG12A

FPR-0040

ECP Plaster & Insulation

15

0

100 10NOV12A

17MAR13A

FPR-0042

ECP Internal & External Paint

10

10

50 14J AN13A

10APR13

86

FPR-0041

ECP Install Doors & Windows

4

4

0 01APR13

04APR13

82

FPR-0043

ECP Install Barriers

12

12

0 05APR13

16APR13

82

FPR-0045

Test & Completion for ECP

2

2

0 17APR13

18APR13

82

FPR-0046

Area Layout for Wall

1

0

100 01APR12A

12MAY12A

FPR-0047

Excavation for Wall

8

0

100 03APR12A

12MAY12A

FPR-0048

Wall Backfilling/Compaction

7

0

95 12APR12A

31MAR13

FPR-0049

Wall PCC Works

5

0

100 14MAY12A

12SEP12A

FPR-0050

Wall Masonary Work

18

18

96 14MAY12A

18APR13

FPR-0051

Wall Copping

18

0

100 13SEP12A

FPR-0052

Wall-Install Concertina Wire

15

15

75 10NOV12A

15APR13

80

FPR-0053

Wall-Test & Completion

5

5

0 16APR13

20APR13

80

FPR-0054

FPs Layout

1

0

100 12MAY12A

12MAY12A

FPR-0055

FPs Excavation

4

0

100 13MAY12A

13J AN13A

FPR-0057

FPs HESCO Installation

14

0

100 28MAY12A

09J AN13A

FPR-0056

FPs Backfilling & Compaction

5

0

100 11SEP12A

14J AN13A

FPR-0058

FPs Sand Bag

9

9

Start Date Finish Date Data Date Run Date

26J UL11 05SEP13 01APR13 13APR13 10:09

Early Bar Progress Bar Critical Activity

PS19

100 06J AN13A

Early Finish

0 01APR13

14J AN13A

69 80

31MAR13A

09APR13

FCEC UIProjects J V W5J 9J R-10-D-0005-0006 ANA Gardez Project Management Layout

89 Sheet 8 of 38 Date

Revision

Checked

Approved

 Acti vity ID

FPR-0059

 Acti vity Description

Orig Dur 

FPs Test & Completion

Rem Dur 

2

%

2

Early Start

Early Finish

0 10APR13

11APR13

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A S

Total Float

89

Guard Tower  FPR-0060

GT - Layout

1

0

100 08APR12A

10MAY12A

FPR-0061

GT - Excavation

4

0

100 12MAY12A

15MAY12A

FPR-0063

GT - Foundation & Ring Beam Works

10

0

100 12MAY12A

22MAY12A

FPR-0062

GT - Watering, Backfilling & Compaction

5

0

100 14MAY12A

19MAY12A

FPR-0064

GT - Formwork & RFT for Slab on Grade

15

0

100 18J UN12A

05J UL12A

FPR-0065

GT - Concrete Works for Slab on Grade

7

0

100 23J UN12A

02J UL12A

FPR-0066

GT - Installation of CMU Wall&Slab

10

0

100 13SEP12A

20DEC12A

FPR-0067

GT - Plaster and Insulation

15

15

65 10FEB13A

17APR13

63

FPR-0068

GT - Electrical Works

8

8

80 18FEB13A

09APR13

63

FPR-0070

GT - Internal & External Painting

10

10

70 27FEB13A

11APR13

67

FPR-0069

GT - Bitumens&Corregated Sheets Inst.

6

6

0 10APR13

16APR13

63

FPR-0071

GT - Door&Windows Installation

4

4

0 17APR13

21APR13

63

FPR-0072

GT - Test & Commissioning

1

1

0 22APR13

22APR13

63

FPR-0073

GT - Punch list Correction

4

4

0 23APR13

27APR13

63

Trash Collection Point Trash Collect ion Point #1,2,3,4,5  TCP-0001

TPT#1 - Construct

14

14

80 06MAY12A

16APR13

67

 TCP-0002

TPT#1 - Install Fence

4

4

0 17APR13

21APR13

67

 TCP-0003

TPT#1 - Inspection

1

1

0 22APR13

22APR13

67

Trash Collection Point #6,7,8,9  TCP-0004

TPT#2 - Construct

14

14

80 07MAY12A

16APR13

67

 TCP-0005

TPT#2 - Install Fence

4

4

0 17APR13

21APR13

67

 TCP-0006

TPT#2 - Inspection

1

1

0 22APR13

22APR13

67

Trash Collect ion Point #10,11,12  TCP-0007

TPT#3 - Construct

14

14

80 08MAY12A

16APR13

67

 TCP-0008

TPT#3 - InstalI Fence

4

4

0 17APR13

21APR13

67

 TCP-0009

TPT#3 - Inspection

1

1

0 22APR13

22APR13

67

Trash Collect ion Point #13,14,15  TCP-0010

TPT#4 - Construct

14

14

80 08MAY12A

16APR13

67

 TCP-0011

TPT#4 - Install Fence

4

4

0 17APR13

21APR13

67

 TCP-0012

TPT#4 - Inspection

1

1

0 22APR13

22APR13

67

1

0

100 12MAY12A

Cover Walkway for Corps Headquarters Foundations CWW-0001 CW- Layout Start Date Finish Date Data Date Run Date

26J UL11 05SEP13 01APR13 13APR13 10:09

Early Bar Progress Bar Critical Activity

PS19

12MAY12A

FCEC UIProjects J V W5J 9J R-10-D-0005-0006 ANA Gardez Project Management Layout

Sheet 9 of 38 Date

Revision

Checked

Approved

 Acti vity ID

 Acti vity Description

Orig Dur 

Rem Dur 

%

Early Start

Early Finish

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A S

Total Float

CWW-0002 CW- Excavation

7

0

100 13MAY12A

CWW-0003 CW- Watering, Backfilling & Compaction

4

4

25 20MAY12A

04APR13

36

CWW-0004 CW- Graveling

7

7

0 06APR13

13APR13

36

10

10

0 14APR13

24APR13

36

10

10

0 25APR13

06MAY13

36

8

8

0 07MAY13

15MAY13

36

CWW-0010 CW- Test & Commission

2

2

0 16MAY13

18MAY13

36

CWW-0011 CW- Punchlist Correction

8

8

0 19MAY13

27MAY13

36

CWW-0012 CW- Finish and Handover

1

1

0 28MAY13

28MAY13

36

CWW-0005 CW- Foundation & Ring Beam

03OCT12A

Superstru cture & Close-in CWW-0008 CW- Column Installation

 Archi tect ural - Exter ior  CWW-0009 CW- Corregated Sheet Inst.

Inspections, Punchlists

Bleacher Enclosures Bleacher #1 OTH-0001

Bleacher #1- Layout

1

0

100 14MAY12A

OTH-0002

Bleacher #1 - Construct FDN

15

0

100 15MAY12A

14MAY12A 18J UL12A

OTH-0004

Bleacher #1- Construct COL

12

0

100 03J UN12A

18J UL12A

OTH-0005

Bleacher #1-Construct Stairs

12

0

100 07J UN12A

18J UL12A

OTH-0006

Bleacher #1- Install CORR Sheet

12

0

100 14AUG12A

30AUG12A

OTH-0003

Bleacher #1- Slab on Grade

18

2

90 18NOV12A

02APR13

76

OTH-0010

Bleacher #1 Test & Commission

2

2

0 03APR13

04APR13

76

OTH-0011

Bleacher #1 Punchlist Correction

5

5

0 06APR13

10APR13

76

OTH-0012

Bleacher #1 Finish and Handover

1

1

0 11APR13

11APR13

76

Bleacher #2 OTH-0013

Bleacher #2- Layout

1

0

100 14MAY12A

25J UN12A

OTH-0014

Bleacher #2 - Construct FDN

15

0

100 26J UN12A

17J UL12A

OTH-0015

Bleacher #2- Slab on Grade

18

18

0 01APR13

21APR13

48

OTH-0016

Bleacher #2- Construct COL

12

12

0 10APR13

23APR13

48

OTH-0017

Bleacher #2-Construct Stairs

12

12

0 17APR13

30APR13

48

OTH-0018

Bleacher #2- Install CORR Sheet

12

12

0 22APR13

05MAY13

48

OTH-0019

Bleacher #2 Test & Commission

2

2

0 06MAY13

07MAY13

48

OTH-0020

Bleacher #2 Punchlist Correction

5

5

0 08MAY13

13MAY13

48

OTH-0021

Bleacher #2 Finish and Handover

1

1

0 14MAY13

14MAY13

48

Start Date Finish Date Data Date Run Date

26J UL11 05SEP13 01APR13 13APR13 10:09

Early Bar Progress Bar Critical Activity

PS19

FCEC UIProjects J V W5J 9J R-10-D-0005-0006 ANA Gardez Project Management Layout

Sheet 10 of 38 Date

Revision

Checked

Approved

 Acti vity ID

 Acti vity Description

Orig Dur 

Rem Dur 

%

Early Start

Early Finish

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A S

Total Float

Utilities Water Supply and Dist ribution System Water Distribut ion WSD-0004 Layout for Water Pipes

1

0

100 07APR12A

10J AN13A

WSD-0005 Excavation for Water Pipes

8

8

96 25J UN12A

09APR13

66

WSD-0006 Lay Site Water Pipes

10

10

90 04J UL12A

11APR13

66

WSD-0008 Construction of Water Manholes

12

12

70 09J UL12A

14APR13

66

WSD-0009 Test & Completion for W Pipes

10

10

60 05OCT12A

11APR13

70

2

2

80 02DEC12A

16APR13

66

WSD-0007 Check W Pipes & Backfill WSD-0010 Punchlist Correction - W Pipes

5

5

0 17APR13

22APR13

66

WSD-0011 Finish and Handover - W Pipes

1

1

0 23APR13

23APR13

66

Sanitary Sewer System Sewage Collection SSS-0001

Layout for Sewer Pipes

1

0

100 04APR12A

21J UN12A

SSS-0002

Excavation for Sewer Pipe

8

8

97 07APR12A

09APR13

62

SSS-0003

Install Sewer Pipes

10

10

96 13MAY12A

11APR13

62

SSS-0004

Checking & Backfill Sewer Pipe

10

10

96 18J UN12A

11APR13

62

SSS-0005

Construction of Sewer Manholes

18

18

83 27J UN12A

21APR13

62

SSS-0006

Test & Completion - Sewer Pipe

18

18

75 05OCT12A

21APR13

62

SSS-0007

Correct Punchlist - Sewer Pipe

5

5

0 22APR13

27APR13

62

SSS-0008

Finish & Handover - Sewer Pipe

1

1

0 28APR13

28APR13

62

Site Electrical Distribu tion Network Power Distri bution ELE-0015

Layout for ELECT Pipes

2

0

100 07APR12A

ELE-0016

Excavation for ELECT Pipes

6

6

96 09APR12A

07APR13

16MAY12A 35

ELE-0018

Lay Electrical Pipes

10

10

80 06MAY12A

11APR13

35

ELE-0019

Concrete Work for Duct Bank

12

12

91 18J UN12A

14APR13

35

ELE-0024

Checking & Backfill Elect Pipes

10

10

93 20J UN12A

11APR13

42

ELE-0017

Electrical Manholes

20

20

90 23J UN12A

23APR13

42

ELE-0020

Electrical Cable Pulling

15

15

0 15APR13

01MAY13

35

ELE-0021

Test & Commission

4

4

0 02MAY13

06MAY13

47

ELE-0022

Puchlist Correction

5

5

0 07MAY13

12MAY13

49

ELE-0023

Finish and Handover

1

1

0 13MAY13

13MAY13

49

Power Generation Emergency Generator f or Headquarter  ELE-0009

Install Emergncy Generator

ELE-0010

Install Control Panel for Generator

ELE-0011 ELE-0012 Start Date Finish Date Data Date Run Date

9

9

0 05J UN13

15J UN13

6

12

12

0 10J UN13

23J UN13

6

Test & Commission

2

2

0 24J UN13

25J UN13

6

Puchlist Correction

5

5

0 26J UN13

01J UL13

6

26J UL11 05SEP13 01APR13 13APR13 10:09

Early Bar Progress Bar Critical Activity

PS19

FCEC UIProjects J V W5J 9J R-10-D-0005-0006 ANA Gardez Project Management Layout

Sheet 11 of 38 Date

Revision

Checked

Approved

 Acti vity ID

ELE-0013

 Acti vity Description

Orig Dur 

Finishing & Handover

Rem Dur 

1

%

Early Start

1

0 02J UL13

Early Finish

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A S

Total Float

02J UL13

6

Site Communication System

COM-0001 Layout for Communication SYS

1

0

100 13MAY12A

COM-0002 Excavation for Conduits

7

5

90 16MAY12A

06APR13

17

17

80 20J UN12A

20APR13

62

9

5

80 11OCT12A

06APR13

74

COM-0005 Construct Communication Manholes COM-0003 Install Counduits

15MAY12A 62

COM-0004 Backfilling & Compaction

3

5

75 18OCT12A

06APR13

74

COM-0006 Testing & Completion - Com Sys

2

2

0 21APR13

22APR13

62

COM-0007 Punchlist Correction - Com Sys

4

4

0 23APR13

27APR13

62

COM-0008 Finish & Handover - Com Sys

1

1

0 28APR13

28APR13

62

Buildings  Arms Sto rage Bui ldings #100 Foundations AB1-0001

100 S.ASB - Layout

1

0

100 01J AN12A

02J AN12A

AB1-0002

100 S.ASB - Excavation Work

6

0

100 03J AN12A

12J AN12A

AB1-0003

100 S.ASB - Concrete Work for Footings

9

0

100 05J UN12A

14J UN12A

AB1-0004

100 S.ASB - Under Ground Electrical Works

6

0

100 09J UN12A

17J UN12A

AB1-0005

100 S.ASB - Backfilling/Capillary Water Barrier

3

0

100 16J UN12A

14J UL12A

AB1-0006

100 S.ASB - Slab on Grade

6

0

100 13SEP12A

19SEP12A

Superstru cture & Close-in AB1-0008

100 S.ASB - Construction of Shear walls

10

0

100 15OCT12A

25OCT12A

AB1-0007

100 S.ASB - Construction of CMU Walls

10

0

100 10NOV12A

20NOV12A

AB1-0012

100 S.ASB - Steel J oists, Welding Plate& Purlins

6

6

0 01APR13

07APR13

52

02APR13

67

 Archi tect ural - Exter ior  AB1-0010

100 S.ASB - Exterior Door Installation

2

2

90 10FEB13A

AB1-0014

100 S.ASB - Roof insullation

8

0

100 20MAR13A

AB1-0015

100 S.ASB - External Paint

12

4

60 27MAR13A

04APR13

65

AB1-0013

100 S.ASB - Seam Metal Roof (Corr. Sheet)

6

6

0 14APR13

20APR13

52

28MAR13A

 Archi tect ural - Int erio r  AB1-0016

100 S.ASB - Plastering

10

0

100 29NOV12A

AB1-0017

100 S.ASB - Internal Painting

10

4

80 27FEB13A

04APR13

30NOV12A 65

AB1-0018

100 S.ASB - Conduits & Fittings

10

4

90 01DEC12A

04APR13

63

AB1-0019

100 S.ASB - Electrical Wiring Works

10

4

50 28MAR13A

04APR13

63

AB1-0020

100 S.ASB - Lighting Fix ,Cover Plates Inst.

1

1

0 06APR13

06APR13

63

Electrical

Start Date Finish Date Data Date Run Date

26J UL11 05SEP13 01APR13 13APR13 10:09

Early Bar Progress Bar Critical Activity

PS19

FCEC UIProjects J V W5J 9J R-10-D-0005-0006 ANA Gardez Project Management Layout

Sheet 12 of 38 Date

Revision

Checked

Approved

 Acti vity ID

AB1-0022

 Acti vity Description

Orig Dur 

100 S.ASB - Panel Boards

Rem Dur 

5

%

Early Start

Early Finish

5

0 20J UL13

24J UL13

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A S

Total Float

-25

Mechanical AB1-0024

100 S.ASB - Electric Heater Install

4

4

80 28MAR13A

04APR13

65

AB1-0021

100 S.ASB - Exhaust Fans install

1

1

0 07APR13

07APR13

63

-25

Inspections, Punchlists AB1-0023

100 S.ASB - Test & Commission

2

2

0 25J UL13

27J UL13

AB1-0025

100 S.ASB - Punchlist Works

5

5

0 28J UL13

03AUG13

-25

AB1-0026

100 S.ASB - Finishing & Handover

1

1

0 04AUG13

04AUG13

-25

 Arms Sto rage Bui ldings #101 Foundations AB2-0001

101 S.ASB - Layout

1

0

100 04APR12A

07APR12A

AB2-0002

101 S.ASB - Excavation Work

4

0

100 05APR12A

09APR12A

AB2-0003

101 S.ASB - Concrete Work for Footings

9

0

100 21APR12A

02MAY12A

AB2-0004

101 S.ASB - Backfilling/Capillary Water Barrier

6

0

100 14MAY12A

20MAY12A

AB2-0006

101 S.ASB - Slab On Grade

6

0

100 23MAY12A

02J UL12A

AB2-0005

101 S.ASB - Under Ground Electrical Works

6

0

100 21J UN12A

16J UL12A

Superstru cture & Close-in AB2-0007

101 S.ASB - Construction of CMU Walls

10

0

100 03J UL12A

17J UL12A

AB2-0008

101 S.ASB - Construction of Shear walls

10

0

100 05J UL12A

17J UL12A

AB2-0009

101 S.ASB - Steel J oists, Welding Plate& Purlins

7

7

90 18MAR13A

08APR13

61

 Archi tect ural - Exter ior  AB2-0012

101 S.ASB - External Paint

12

0

100 15OCT12A

AB2-0010

101 S.ASB - Roof insulation

10

7

75 09MAR13A

23J AN13A 08APR13

AB2-0011

101 S.ASB - Seam Metal Roof (Corr. Sheet)

7

7

85 28MAR13A

08APR13

61

AB2-0013

101 S.ASB - Ext Door Installation

8

8

0 01APR13

09APR13

61

61

 Archi tect ural - Int erio r  AB2-0014

101 S.ASB - Plastering

10

0

100 30SEP12A

AB2-0015

101 S.ASB - Internal Painting

10

7

90 01NOV12A

08APR13

09OCT12A 61

AB2-0016

101 S.ASB - Conduits & Fittings

10

7

95 01DEC12A

08APR13

61

AB2-0017

101 S.ASB - Electrical Wiring Works

10

7

95 01J AN13A

08APR13

61

AB2-0018

101 S.ASB - Lighting Fix ,Cover Plates Inst

7

7

10 05FEB13A

08APR13

61

AB2-0019

101 S.ASB - Panel Boards

9

9

0 20J UL13

29J UL13

-25

Electrical

Start Date Finish Date Data Date Run Date

26J UL11 05SEP13 01APR13 13APR13 10:09

Early Bar Progress Bar Critical Activity

PS19

FCEC UIProjects J V W5J 9J R-10-D-0005-0006 ANA Gardez Project Management Layout

Sheet 13 of 38 Date

Revision

Checked

Approved

 Acti vity ID

 Acti vity Description

Orig Dur 

Rem Dur 

%

Early Start

Early Finish

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A S

Total Float

Mechanical AB2-0021

101 S.ASB - Exhaust Fans inst

AB2-0020

101 S.ASB - Electric Heater Inst

10

7

60 03J AN13A

08APR13

62

1

1

0 09APR13

09APR13

61

-25

Inspections, Punchlists AB2-0022

101 S.ASB - Test & Commission

2

2

0 30J UL13

31J UL13

AB2-0023

101 S.ASB - Punchlist Works

5

5

0 01AUG13

06AUG13

-25

AB2-0024

101 S.ASB - Finishing & Handover

1

1

0 07AUG13

07AUG13

-25

 Arms Sto rage Bui ldings #102 Foundations AB3-0001

102 S.ASB - Layout

2

0

100 01J AN12A

02J AN12A

AB3-0002

102 S.ASB - Excavation Work

6

0

100 03J AN12A

09J AN12A

AB3-0003

102 S.ASB - Concrete Work for Footings

9

0

100 12MAY12A

21MAY12A

AB3-0004

102 S.ASB - Backfilling/Capillary Water Barrier

6

0

100 04J UN12A

21J UN12A

AB3-0005

102 S.ASB - Under Ground Electrical Works

6

0

100 07J UN12A

21J UN12A

AB3-0006

102 S.ASB - Slab on Grade

6

0

100 09J UN12A

23J UN12A

Superstru cture & Close-in AB3-0007

102 S.ASB - Construction of CMU Walls

10

0

100 24J UN12A

04J UL12A

AB3-0008

102 S.ASB - Construction of Shear walls

10

0

100 05J UL12A

16J UL12A

AB3-0009

102 S.ASB - Steel J oists, Welding Plate& Purlins

7

7

0 01APR13

08APR13

57

 Archi tect ural - Exter ior  AB3-0012

102 S.ASB - External Paint

18

0

100 01J AN13A

30J AN13A

AB3-0013

102 S.ASB - Ext Door Instalation

10

10

90 20FEB13A

16APR13

AB3-0010

102 S.ASB - Roof Insulation

12

0

100 27MAR13A

AB3-0011

102 S.ASB - Seam Metal Roof (Corr. Sheet)

8

8

0 09APR13

57

29MAR13A 17APR13

57

 Archi tect ural - Int erio r  AB3-0014

102 S.ASB - Plastering

10

0

100 28OCT12A

AB3-0015

102 S.ASB - Internal Painting

10

10

90 10DEC12A

20NOV12A 11APR13

57

67

Electrical AB3-0016

102 S.ASB - Conduits & Fittings

4

4

90 10NOV12A

04APR13

AB3-0017

102 S.ASB - Electrical Wiring Works

8

4

90 20FEB13A

04APR13

67

AB3-0018

102 S.ASB - Lighting Fix ,Cover Plates Inst

1

1

0 04APR13

04APR13

67

AB3-0019

102 S.ASB - Panel Boards

2

2

0 19J UN13

20J UN13

4

1

1

0 17APR13

17APR13

57

Mechanical AB3-0021 Start Date Finish Date Data Date Run Date

102 S.ASB - Exhaust Fans Inst 26J UL11 05SEP13 01APR13 13APR13 10:09

Early Bar Progress Bar Critical Activity

PS19

FCEC UIProjects J V W5J 9J R-10-D-0005-0006 ANA Gardez Project Management Layout

Sheet 14 of 38 Date

Revision

Checked

Approved

 Acti vity ID

AB3-0020

 Acti vity Description

Orig Dur 

102 S.ASB - Electric Heater Inst

Rem Dur 

%

Early Start

Early Finish

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A S

Total Float

1

1

0 18J UN13

18J UN13

4

4

Inspections, Punchlists AB3-0022

102 S.ASB - Test & Commission

2

2

0 22J UN13

23J UN13

AB3-0023

102 S.ASB - Punchlist Works

5

5

0 24J UN13

29J UN13

4

AB3-0024

102 S.ASB - Finishing & Handover

1

1

0 30J UN13

30J UN13

4

 Arms Sto rage Bui ldings #103 Foundations AB4-0001

103 S.ASB - Layout

1

0

100 02J AN12A

02J AN12A

AB4-0002

103 S.ASB - Excavation Work

6

0

100 03J AN12A

09J AN12A

AB4-0003

103 S.ASB - Concrete Work for Footings

4

0

100 14J AN12A

20MAY12A

AB4-0004

103 S.ASB - Backfilling/Capillary Water Barrier

6

0

100 03J UN12A

23J UN12A

AB4-0005

103 S.ASB - Under Ground Electrical Works

6

0

100 06J UN12A

23J UN12A

AB4-0006

103 S.ASB - Slab on Grade

6

0

100 12J UN12A

23J UN12A

Superstru cture & Close-in AB4-0007

103 S.ASB - Construction of CMU Walls

15

0

100 24J UN12A

10J UL12A

AB4-0008

103 S.ASB - Construction of Shear walls

18

0

100 11J UL12A

30J UL12A

AB4-0009

103 S.ASB - Steel J oists, Welding Plate& Purlins

10

10

0 01APR13

11APR13

50

 Archi tect ural - Exter ior  AB4-0012

103 S.ASB - External Paint

AB4-0013

103 S.ASB - Ext Door Installation

AB4-0010

103 S.ASB - Roof insullation

AB4-0011

103 S.ASB - Seam Metal Roof (Corr. Sheet)

10

2

95 18NOV12A

02APR13

60

5

5

90 21FEB13A

06APR13

57

10

10

90 27MAR13A

11APR13

49

5

5

0 13APR13

17APR13

50

 Archi tect ural - Int erio r  AB4-0014

103 S.ASB - Plastering

10

0

100 18SEP12A

AB4-0015

103 S.ASB - Internal Painting

10

5

90 04DEC12A

28SEP12A 06APR13

57

Electrical AB4-0017

103 S.ASB - Electrical Wiring Works

12

12

95 03J AN13A

14APR13

47

AB4-0016

103 S.ASB - Conduits & Fittings

10

10

90 10J AN13A

11APR13

49

AB4-0018

103 S.ASB - Lighting Fix ,Cover Plates Inst

2

2

0 15APR13

16APR13

47

AB4-0019

103 S.ASB - Panel Boards

9

9

0 23J UN13

02J UL13

-6

Mechanical AB4-0021

103 S.ASB - Exhaust Fans Inst

1

1

0 17APR13

17APR13

47

AB4-0020

103 S.ASB - Electric Heater Inst

1

1

0 18J UN13

18J UN13

-6

Start Date Finish Date Data Date Run Date

26J UL11 05SEP13 01APR13 13APR13 10:09

Early Bar Progress Bar Critical Activity

PS19

FCEC UIProjects J V W5J 9J R-10-D-0005-0006 ANA Gardez Project Management Layout

Sheet 15 of 38 Date

Revision

Checked

Approved

 Acti vity ID

 Acti vity Description

Orig Dur 

Rem Dur 

%

Early Start

Early Finish

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A S

Total Float

Inspections, Punchlists AB4-0022

103 S.ASB - Test & Commission

2

2

0 03J UL13

04J UL13

AB4-0023

103 S.ASB - Punchlist Works

5

5

0 06J UL13

10J UL13

-6 -6

AB4-0024

103 S.ASB - Finishing & Handover

1

1

0 11J UL13

11J UL13

-6

 Arms Sto rage Bui ldings #104 Foundations AB5-0001

104 S.ASB - Layout

1

0

100 01APR12A

01APR12A

AB5-0002

104 S.ASB - Excavation Work

5

0

100 02APR12A

07APR12A

AB5-0003

104 S.ASB - Concrete Work for Footings

AB5-0004

104 S.ASB - Backfilling/Capillary Water Barrier

AB5-0006

104 S.ASB - Slab on Grade

AB5-0005

104 S.ASB - Under Ground Electrical Works

12

0

100 14APR12A

20MAY12A

6

0

100 03J UN12A

27J UN12A

10

0

100 05J UN12A

30J UN12A

6

0

100 06J UN12A

26J UN12A

Superstru cture & Close-in AB5-0008

104 S.ASB - Construction of Shear walls

10

0

100 01J UL12A

12J UL12A

AB5-0007

104 S.ASB - Construction of CMU Walls

10

0

100 14AUG12A

27AUG12A

AB5-0009

104 S.ASB - Steel J oists, Welding Plate& Purlins

8

8

0 01APR13

13

10

70 03FEB13A

11APR13

57

6

6

90 20FEB13A

07APR13

62

12

10

90 27MAR13A

11APR13

57

6

6

0 10APR13

16APR13

54

09APR13

54

 Archi tect ural - Exter ior  AB5-0012

104 S.ASB - External Paint

AB5-0013

104 S.ASB - Ext Door Installation

AB5-0010

104 S.ASB - Roof Insulation

AB5-0011

104 S.ASB - Seam Metal Roof (Corr. Sheet)

 Archi tect ural - Int erio r  AB5-0014

104 S.ASB - Plastering

15

0

100 26NOV12A

AB5-0015

104 S.ASB - Internal Painting

15

6

90 10DEC12A

07APR13

05DEC12A

AB5-0016

104 S.ASB - Conduits & Fittings

10

0

100 10DEC12A

20FEB13A

AB5-0017

104 S.ASB - Electrical Wiring Works

10

10

95 21FEB13A

11APR13

57

AB5-0018

104 S.ASB - Lighting Fix ,Cover Plates Inst

10

10

95 22FEB13A

11APR13

57

AB5-0019

104 S.ASB - Panel Boards

6

6

0 19J UN13

25J UN13

0

62

Electrical

Mechanical AB5-0020

104 S.ASB - Electric Heater Inst

1

1

0 13APR13

13APR13

57

AB5-0021

104 S.ASB - Exhaust Fans inst

1

1

0 18J UN13

18J UN13

0

2

2

0 26J UN13

27J UN13

0

Inspections, Punchlists AB5-0022 Start Date Finish Date Data Date Run Date

104 S.ASB - Test & Commission 26J UL11 05SEP13 01APR13 13APR13 10:09

Early Bar Progress Bar Critical Activity

PS19

FCEC UIProjects J V W5J 9J R-10-D-0005-0006 ANA Gardez Project Management Layout

Sheet 16 of 38 Date

Revision

Checked

Approved

 Acti vity ID

 Acti vity Description

Orig Dur 

Rem Dur 

%

Early Start

Early Finish

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A S

Total Float

Mechanical GFC-0029

Nrth Prt Exhaust Fan Installation

10

10

40 27MAR13A

29J UN13

GFC-0030

Nrth Prt Unit Heater Installation

10

10

10 28MAR13A

29J UN13

1 1

GFC-0031

Nrth Prt AC Split Installation

10

10

0 30APR13

11MAY13

43

GFC-0032

Nrth Prt Hot & Cold Water Piping

15

15

25 01DEC12A

17APR13

44

GFC-0034

Nrth Prt Toilet & Misc.Accessories

4

4

0 18APR13

22APR13

44

GFC-0033

Nrth Prt Toilet Sanitry Fixture Installation

15

15

0 23APR13

09MAY13

44

Plumbing

Fire Protection System GFC-0035

Nrth Prt Smoke Detector Installation

1

1

10 29MAR13A

02APR13

83

GFC-0036

Nrth Prt Fire Extinguisher Installation

1

1

0 18J UN13

18J UN13

10

15

15

35 02J AN13A

17APR13

63

-21

Communications GFC-0037

Nrth Prt Telephone and Data wall recepticle Inst

Inspections, Punchlists GFC-0038

Nrth Prt Test & Commission

2

2

0 25J UL13

27J UL13

GFC-0039

Nrth Prt Punchlist Works

5

5

0 28J UL13

01AUG13

-21

GFC-0040

Nrth Prt Finishing & Handover

1

1

0 03AUG13

03AUG13

-21

Corps Headquarters (West) Foundations GFC-0042

West Prt GFCC Building Layout

1

0

100 07APR12A

07APR12A

GFC-0043

West Prt GFCC Excavation

4

0

100 14MAY12A

17MAY12A

GFC-0044

West Prt GFCC Watering, Backfilling & Compaction

5

0

100 20MAY12A

16J UN12A

GFC-0047

West Prt GFCC Formwork & RFT for Slab on Grade

14

0

100 18J UN12A

12J UL12A

GFC-0048

West Prt San Sewer Piping under Slab on Grade

5

0

100 21J UN12A

14AUG12A

GFC-0045

West Prt GFCC Foundation & Ring Beam Works

15

0

100 21J UN12A

12SEP12A

GFC-0046

West Prt GFCC BKFLNG, CMPCTN, CAP. & Vap. Bars

5

0

100 25J UN12A

12J UL12A

GFC-0049

West Prt Concrete Works for Slab on Grade

6

0

100 14J UL12A

15NOV12A

Superstru cture & Close-in GFC-0050

West Prt Installation of Shear Walls

GFC-0051

West Prt Installation of 3D Panels Walls

GFC-0052

West Prt Scaffolding for 3D Roof Slab

3

0

100 25SEP12A

12DEC12A

GFC-0053

West Prt Instalaltion of 3D Panels Roof Slabs

10

0

100 28SEP12A

12DEC12A

GFC-0054

West Prt Shotcreting for 3D Panels Roof & Walls

10

3

85 03OCT12A

03APR13

GFC-0055

West Prt Pouring Concrete on Roof

10

0

100 06OCT12A

13J AN13A

GFC-0073

West Prt Truss Installation

12

12

75 13DEC12A

14APR13

Start Date Finish Date Data Date Run Date

26J UL11 05SEP13 01APR13 13APR13 10:09

Early Bar Progress Bar Critical Activity

8

0

100 17J UL12A

22SEP12A

15

0

100 04AUG12A

12DEC12A

PS19

FCEC UIProjects J V W5J 9J R-10-D-0005-0006 ANA Gardez Project Management Layout

50 53 Sheet 18 of 38 Date

Revision

Checked

Approved

 Acti vity ID

 Acti vity Description

Orig Dur 

Rem Dur 

%

Early Start

Early Finish

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A S

Total Float

 Archi tect ural - Exter ior  GFC-0058

West Prt Exterior Doors Installation

10

10

40 01DEC12A

11APR13

GFC-0056

West Prt Cold Asphalt Damp Proofing

15

0

100 13DEC12A

27J AN13A

68

GFC-0057

West Prt Corregated Sheet Installation for 3D

12

10

67 13FEB13A

11APR13

68

GFC-0059

West Prt Window Installation

10

10

50 14FEB13A

11APR13

68

GFC-0060

West Prt External Painting

15

10

30 27FEB13A

11APR13

68

GFC-0085

West Prt Corregated Sheet Installation for Truss

12

12

50 27MAR13A

14APR13

53

 Archi tect ural - Int erio r  GFC-0062

West Prt Plaster Works

15

10

80 21NOV12A

11APR13

55

GFC-0063

West Prt Interior Doors Installation

10

10

36 28J AN13A

11APR13

60

GFC-0064

West Prt Internal Painting

15

10

55 01FEB13A

11APR13

60

GFC-0084

West Prt Glass Wool Insulation

12

12

70 28MAR13A

14APR13

53

GFC-0061

West Prt Terrazzo Tiles

15

15

0 04APR13

21APR13

50

GFC-0086

West Prt False Ceiling

15

15

0 01APR13

17APR13

53

GFC-0065

West Prt Sealed Concrete

7

7

0 20J UL13

27J UL13

-23

Electrical GFC-0066

West Prt Elec PVC Conduits & Fittings & Boxes

GFC-0068

West Prt Duplex and switch installation

5

0

100 01J AN13A

10

10

45 03J AN13A

GFC-0067

23MAR13A 11APR13

West Prt Electrical Wiring Works

5

5

50 10J AN13A

06APR13

65

GFC-0069

West Prt Lighting Fix. & Cover Plates Inst

2

2

0 22APR13

23APR13

50

GFC-0070

West Prt Panel Board Installation

5

5

0 20J UL13

24J UL13

-23

68

Mechanical GFC-0071

West Prt AC Split Installation

1

1

0 18J UN13

18J UN13

10

GFC-0072

West Prt Exhaust Fan Installation

1

1

0 18J UN13

18J UN13

10

GFC-0074

West Prt Hot & Cold Water Piping

15

15

25 01DEC12A

17APR13

55

GFC-0075

West Prt Kitchen & Misc.Accessories

5

5

0 18APR13

23APR13

57

GFC-0076

West Prt Kithen Fixture Installation

8

8

0 18APR13

27APR13

55

Plumbing

Fire Protection System GFC-0077

West Prt Smoke Detector Installation

1

1

0 23APR13

23APR13

58

GFC-0078

West Prt Fire Extinguisher Installation

1

1

0 18J UN13

18J UN13

10

15

15

40 02J AN13A

17APR13

63

Communications GFC-0079

Start Date Finish Date Data Date Run Date

West Prt Tele and Data wall receptacle Insta

26J UL11 05SEP13 01APR13 13APR13 10:09

Early Bar Progress Bar Critical Activity

PS19

FCEC UIProjects J V W5J 9J R-10-D-0005-0006 ANA Gardez Project Management Layout

Sheet 19 of 38 Date

Revision

Checked

Approved

 Acti vity ID

 Acti vity Description

Orig Dur 

Rem Dur 

%

Early Start

Early Finish

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A S

Total Float

Inspections, Punchlists GFC-0080

West Prt Test & Commission

2

2

0 28J UL13

29J UL13

GFC-0081

West Prt Punchlist Works

5

5

0 30J UL13

04AUG13

-23 -23

GFC-0082

West Prt Finishing & Handover

1

1

0 05AUG13

05AUG13

-23

Corps Headquarters (South) Foundations GFC-0087

Sout Prt GFCC Building Layout

1

0

100 07APR12A

07APR12A

GFC-0088

Sout Prt GFCC Excavation

5

0

100 12MAY12A

16MAY12A

GFC-0089

Sout Prt GFCC Watering, Backfilling & Compaction

5

0

100 16MAY12A

16J UN12A

GFC-0092

Sout Prt GFCC Formwork & RFT for Slab on Grade

14

0

100 20J UN12A

10J UL12A

GFC-0091

Sout Prt GFCC BKFLNG, CMPCTN, CAP. & Vap. Bars

5

0

100 26J UN12A

18NOV12A

GFC-0093

Sout Prt San Sewer Piping under Slab on Grade

8

0

100 01J UL12A

11J UL12A

GFC-0090

Sout Prt GFCC Foundation & Ring Beam Works

15

0

100 14J UL12A

12SEP12A

GFC-0094

Sout Prt Concrete Works for Slab on Grade

6

0

100 16J UL12A

09J AN13A

Superstru cture & Close-in GFC-0095

Sout Prt Installation of Shear Walls

GFC-0096

Sout Prt Installation of 3D Panels Walls

8

0

100 13AUG12A

22SEP12A

15

0

100 13SEP12A

GFC-0097

Sout Prt Scaffolding for 3D Roof Slab

23J AN13A

3

0

100 25SEP12A

GFC-0098

12DEC12A

Sout Prt Instalaltion of 3D Panels Roof Slabs

12

0

100 28SEP12A

23DEC12A

GFC-0099

Sout Prt Shotcreting for 3D Panels Roof & Walls

15

12

87 13OCT12A

14APR13

GFC-0100

Sout Prt Pouring Concrete on roof

12

0

100 20OCT12A

23J AN13A

GFC-0101

Sout Prt Truss Installation

10

10

50 25MAR13A

11APR13

51

49

 Archi tect ural - Exter ior  GFC-0105

Sout Prt Exterior Doors Installation

12

10

10 01DEC12A

11APR13

68

GFC-0102

Sout Prt Cold Asphalt Damp Proofing

10

10

60 24FEB13A

11APR13

57

GFC-0103

Sout Prt Corregated Sheet Installation for 3D

10

10

40 25FEB13A

11APR13

61

GFC-0107

Sout PrtExternal Painting

10

10

45 26FEB13A

11APR13

68

GFC-0104

Sout Prt Corregated Sheet Installation for Truss

10

10

10 27MAR13A

23APR13

51

GFC-0106

Sout PrtWindow Installation

12

12

0 01APR13

14APR13

61

 Archi tect ural - Int erio r  GFC-0111

Sout Prt Interior Doors Installation

10

10

30 01DEC12A

11APR13

53

GFC-0109

Sout Prt Plaster Works

15

15

85 03DEC12A

17APR13

53

GFC-0113

Sout Prt Internal Painting

10

10

60 27FEB13A

11APR13

61

GFC-0110

Sout Prt Glass Wool Insulation

10

10

40 27MAR13A

23APR13

51

GFC-0108

Sout Prt Terrazzo Tiles

12

12

0 15APR13

28APR13

49

GFC-0112

Sout Prt False Ceiling

2

2

0 24APR13

25APR13

51

GFC-0114

Sout Prt Sealed Concrete

5

5

0 23J UL13

28J UL13

-24

Start Date Finish Date Data Date Run Date

26J UL11 05SEP13 01APR13 13APR13 10:09

Early Bar Progress Bar Critical Activity

PS19

FCEC UIProjects J V W5J 9J R-10-D-0005-0006 ANA Gardez Project Management Layout

Sheet 20 of 38 Date

Revision

Checked

Approved

 Acti vity ID

 Acti vity Description

Orig Dur 

Rem Dur 

%

Early Start

Early Finish

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A S

Total Float

Electrical GFC-0115

Sout Prt Ele PVC Conduits & Fittings & Boxes

5

5

90 01FEB13A

07APR13

GFC-0116

Sout Prt Electrical Wiring Works

5

5

40 21FEB13A

07APR13

65 65

GFC-0118

Sout Prt Duplex and switch installation

10

10

20 28FEB13A

11APR13

77

GFC-0117

Sout Prt Lighting Fix. & Cover Plates Inst

2

2

0 13APR13

14APR13

61

GFC-0119

Sout Prt Panel Board Installation

5

5

0 20J UL13

24J UL13

-21

Mechanical GFC-0120

Sout Prt AC Split Installation

1

1

0 01APR13

01APR13

77

GFC-0121

Sout Prt Exhaust Fan Installation

1

1

0 18J UN13

18J UN13

10

GFC-0131

Sout Prt Unit Heater Installation

1

1

0 18J UN13

18J UN13

10

Plumbing GFC-0122

Sout Prt Hot & Cold Water Piping

15

15

25 01DEC12A

17APR13

53

GFC-0124

Sout Prt Toilet Sanitry Fixture Installation

3

3

0 18APR13

21APR13

55

GFC-0123

Sout Prt Toilet & Misc.Accessories

5

5

0 18APR13

23APR13

53

Fire Protection System GFC-0125

Sout Prt Smoke Detector Installation

2

2

0 18J UN13

19J UN13

6

GFC-0126

Sout Prt Fire Extinguisher Installation

2

2

0 20J UN13

22J UN13

7

3

3

38 01MAR13A

23J UN13

6

-24

Communications GFC-0127

Sout Prt Telephone and Data wall recepticle Inst

Inspections, Punchlists GFC-0128

Sout Prt Test & Commission

2

2

0 29J UL13

30J UL13

GFC-0129

Sout Prt Punchlist Works

5

5

0 31J UL13

05AUG13

-24

GFC-0130

Sout PrtFinishing & Handover

1

1

0 06AUG13

06AUG13

-24

Kandak Headquarters Foundations KAN-0001

KHQ - Layout

1

0

100 08APR12A

16J UN12A

KAN-0002

KHQ - Excavation Work

4

0

100 09APR12A

20J UN12A

KAN-0003

KHQ - Watering, Backfilling & Compaction

5

0

100 17J UN12A

21J UN12A

KAN-0004

KHQ - Foundation & Ring Beam Works

7

0

100 23J UN12A

11J UL12A

KAN-0005

KHQ - BKFLNG, CMPCTN, CAP. & Vap. Barriers

7

0

100 10J UL12A

12AUG12A

KAN-0006

KHQ - Formwork & RFT for Slab on Grade

8

0

100 16J UL12A

12AUG12A

KAN-0007

KHQ - Concrete Works for Slab on Grade

2

0

100 11NOV12A

09J AN13A

10

0

100 25J UL12A

12AUG12A

Superstru cture & Close-in KAN-0008 Start Date Finish Date Data Date Run Date

KHQ - Inst of Steel Bar for Stem Wall 26J UL11 05SEP13 01APR13 13APR13 10:09

Early Bar Progress Bar Critical Activity

PS19

FCEC UIProjects J V W5J 9J R-10-D-0005-0006 ANA Gardez Project Management Layout

Sheet 21 of 38 Date

Revision

Checked

Approved

 Acti vity ID

 Acti vity Description

Orig Dur 

Rem Dur 

%

Early Start

Early Finish

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A S

Total Float

KAN-0009

KHQ - Concrete for Stem Walls

12

0

100 10SEP12A

09J AN13A

KAN-0010

KHQ - Installation of K Span

15

0

100 28OCT12A

26FEB13A

 Archi tect ural - Exter ior  KAN-0013

KHQ - Windows Installation

8

8

50 05DEC12A

09APR13

45

KAN-0011

KHQ - Ext Door Instalation

8

8

40 05J AN13A

09APR13

45

KAN-0012

KHQ - Ext Painting of Stem Wall

7

7

75 01MAR13A

08APR13

46

15

15

90 10NOV12A

17APR13

21

7

7

0 18APR13

25APR13

21

 Archi tect ural - Int erio r  KAN-0014

KHQ - Plaster for Stem Wall

KAN-0015

KHQ - Spray Insulation

KAN-0017

KHQ - Inst. gypsum board

10

10

0 27APR13

07MAY13

21

KAN-0016

KHQ - Inst. Suspended Ceiling

15

15

0 27APR13

13MAY13

26

KAN-0018

KHQ - Interior Doors Inst

5

5

0 08MAY13

13MAY13

21

KAN-0019

KHQ - Sealed Concrete for floor

5

5

0 21MAY13

26MAY13

26

KAN-0020

KHQ - Ele PVC Conduits/Fittings/Boxes

6

0

100 01MAR13A

KAN-0021

KHQ - Electrical Wiring Works

7

7

0 01APR13

08APR13

56

KAN-0022

KHQ - Lighting Fix.&Cover Plates Inst

6

6

0 14MAY13

20MAY13

26

KAN-0023

KHQ - Duplex & Switch Inst

8

8

0 14MAY13

22MAY13

21

KAN-0024

KHQ - Panel Board Inst

3

3

0 20J UL13

22J UL13

-23

Electrical 08MAR13A

Mechanical KAN-0026

KHQ - Exhaust Fan Inst.

2

2

0 18J UN13

19J UN13

2

KAN-0025

KHQ - AC Split Installation

3

3

0 18J UN13

20J UN13

-1

KAN-0027

KHQ - Unit Heater Inst.

2

2

0 22J UN13

23J UN13

-1

Plumbing KAN-0028

KHQ - Hot&Cold Water Piping

9

9

50 05DEC12A

11APR13

51

KAN-0029

KHQ - Toilet & Misc. Accessories

5

5

0 13APR13

17APR13

54

KAN-0030

KHQ - Toilet Sanitry Fixture Inst.

8

8

0 13APR13

21APR13

51

3

3

0 20J UN13

23J UN13

2

-23

Fire Protection System KAN-0031

KHQ - Fire Extinguisher Inst.

Inspections, Punchlists KAN-0032

KHQ - Test & Commission

2

2

0 23J UL13

24J UL13

KAN-0033

KHQ - Punchlist Works

5

5

0 25J UL13

30J UL13

-23

KAN-0034

KHQ - Finishing & Handover

1

1

0 31J UL13

31J UL13

-23

Start Date Finish Date Data Date Run Date

26J UL11 05SEP13 01APR13 13APR13 10:09

Early Bar Progress Bar Critical Activity

PS19

FCEC UIProjects J V W5J 9J R-10-D-0005-0006 ANA Gardez Project Management Layout

Sheet 22 of 38 Date

Revision

Checked

Approved

 Acti vity ID

 Acti vity Description

Orig Dur 

Rem Dur 

%

Early Start

Early Finish

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A S

Total Float

 Administration Building #109 Foundations ADM-0001

ADB 109 - Layout

2

0

100 09APR12A

10APR12A

ADM-0002

ADB 109 - Excavation Work

4

0

100 12APR12A

16APR12A

ADM-0003

ADB 109 - Watering, Backfilling & Compaction

ADM-0004

ADB 109 - Foundation & Ring Beam

ADM-0005

ADB 109 - BKFLNG, CMPCTN, CAP. & Vap. Barriers

ADM-0006

ADB 109 - Formwork & RFT for Slab on Grade

ADM-0007

ADB 109 - Concrete Works for Slab on Grade

4

0

100 16APR12A

22APR12A

10

0

100 10MAY12A

18NOV12A

8

0

100 16J UN12A

24J UN12A

10

0

100 19J UN12A

30J UN12A

4

0

100 26J UN12A

30J UN12A

04J UL12A

Superstru cture & Close-in ADM-0008

ADB 109 - Inst. of Steel Bar for Stem Walls

4

0

100 01J UL12A

ADM-0009

ADB 109 - Concrete for Stem Walls

7

0

100 02J UL12A

20SEP12A

ADM-0010

ADB 109 - Installation of K Span

13

0

100 01OCT12A

09OCT12A

16J AN13A

 Archi tect ural - Exter ior  ADM-0013

ADB 109 - Windows Inst

ADM-0012

ADB 109 - Ext. Painting of Stem Walls

ADM-0011

ADB 109 - Ext. Door Inst

6

0

100 29NOV12A

13

13

15 18MAR13A

15APR13

39

5

5

0 09APR13

14APR13

57

 Archi tect ural - Int erio r  ADM-0014

ADB 109 - Plaster Work for steam Walls

8

0

100 10OCT12A

ADM-0015

ADB 109 - Spray Insulation

7

7

70 10DEC12A

08APR13

18OCT12A 37

ADM-0017

ADB 109 - Inst. of gypsum Board

8

8

10 18DEC12A

09APR13

37

ADM-0019

ADB 109 - Sealed Concrete for Floor

4

4

20 23MAR13A

04APR13

68

ADM-0018

ADB 109 - Interior Doors Instalation

5

5

0 10APR13

15APR13

39

ADM-0016

ADB 109 - Inst. of Suspended Ceiling

8

8

0 10APR13

18APR13

39

ADM-0020

ADB 109 - Ele PVC Conduits/Fittings/Boxes

9

7

75 18FEB13A

08APR13

38

ADM-0023

ADB 109 - Duplex & Switch Inst

7

7

0 10APR13

17APR13

37

ADM-0021

ADB 109 - Electrical Wiring Works

6

6

0 18APR13

24APR13

37

ADM-0022

ADB 109 - Lighting Fix. & Cover Plates Inst.

7

7

0 22APR13

29APR13

37

ADM-0024

ADB 109 - Panel Board Inst.

3

3

0 20J UL13

22J UL13

-25

Electrical

Mechanical ADM-0026

ADB 109 - Exhaust Fan Installation

3

3

30 28MAR13A

20J UN13

-1

ADM-0025

ADB 109 - AC Split Installation

5

5

0 30APR13

05MAY13

37

ADM-0027

ADB 109 - Unit Heater Installation

2

2

0 06MAY13

07MAY13

37

Start Date Finish Date Data Date Run Date

26J UL11 05SEP13 01APR13 13APR13 10:09

Early Bar Progress Bar Critical Activity

PS19

FCEC UIProjects J V W5J 9J R-10-D-0005-0006 ANA Gardez Project Management Layout

Sheet 23 of 38 Date

Revision

Checked

Approved

 Acti vity ID

 Acti vity Description

Orig Dur 

Rem Dur 

%

Early Start

Early Finish

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A S

Total Float

Plumbing ADM-0028

ADB 109 - Hot & Cold Water Piping

7

7

50 01DEC12A

08APR13

54

ADM-0029

ADB 109 - Toilet & Misc. Accessories

5

5

0 09APR13

14APR13

54

ADM-0030

ADB 109 - Toilet Sanitry Fixture Inst

6

6

0 09APR13

15APR13

54

3

3

0 08MAY13

11MAY13

37

-25

Fire Protection System ADM-0031

ADB 109 - Fire Extinguisher Inst.

Inspections, Punchlists ADM-0032

ADB 109 - Test & Commission

2

2

0 23J UL13

24J UL13

ADM-0033

ADB 109 - Punchlist Works

7

7

0 25J UL13

01AUG13

-25

ADM-0034

ADB 109 - Finishing & Handover

1

1

0 03AUG13

03AUG13

-25

Large Latrine #110 Foundations LA1-0001

LTB 110- Layout

2

0

100 04APR12A

05APR12A

LA1-0002

LTB 110- Excavation Work

5

0

100 07APR12A

11APR12A

LA1-0003

LTB 110- Watering, Backfilling & Compaction

19APR12A

LA1-0004

LTB 110- Foundation & Ring Beam

LA1-0005

LTB 110- BKFLNG, CMPCTN, CAP. & Vap. Barriers

LA1-0006

LTB 110- Formwork & RFT for Slab on Grade

12

0

100 14J UN12A

11J UL12A

LA1-0007

LTB 110- Concrete Works for Slab on Grade

4

0

100 25J UN12A

16SEP12A

02J UL12A

5

0

100 14APR12A

12

0

100 21APR12A

11J UN12A

9

0

100 12J UN12A

11J UL12A

Superstru cture & Close-in LA1-0008

LTB 110- Inst. Steel Bar for Stem Walls

13

0

100 17J UN12A

LA1-0009

LTB 110- Concrete for Stem Walls

15

0

100 19J UN12A

27OCT12A

LA1-0010

LTB 110- Installation of K Span

20

0

100 01OCT12A

09OCT12A

 Archi tect ural - Exter ior  LA1-0011

LTB 110- Exterior Door Installaion

6

6

45 18DEC12A

07APR13

LA1-0013

LTB 110- Windows Installation

7

0

100 20DEC12A

26J AN13A

56

LA1-0012

LTB 110- Ext. Painting of Stem Walls

10

7

90 18FEB13A

08APR13

56

 Archi tect ural - Int erio r  LA1-0014

LTB 110- Plaster Work for Steam Walls

12

0

100 18NOV12A

LA1-0018

LTB 110- Int. Doors Installation

7

7

30 30DEC12A

08APR13

56

LA1-0015

LTB 110- Spray Insulation

7

7

0 01APR13

08APR13

36

LA1-0017

LTB 110- Inst of gypsum Board

12

12

0 09APR13

22APR13

36

LA1-0016

LTB 110- Inst. of gypsum Board Ceiling

12

12

0 23APR13

06MAY13

36

LA1-0019

LTB 110- Tiles for floor

10

10

0 04MAY13

14MAY13

36

Start Date Finish Date Data Date Run Date

26J UL11 05SEP13 01APR13 13APR13 10:09

Early Bar Progress Bar Critical Activity

PS19

01DEC12A

FCEC UIProjects J V W5J 9J R-10-D-0005-0006 ANA Gardez Project Management Layout

Sheet 24 of 38 Date

Revision

Checked

Approved

 Acti vity ID

 Acti vity Description

Orig Dur 

Rem Dur 

%

Early Start

Early Finish

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A S

Total Float

Electrical LA1-0020

LTB 110- Ele PVC Conduits/Fittings/Boxes

5

0

LA1-0023

LTB 110- Duplex & Switch Inst.

5

5

100 18FEB13A 0 23APR13

23FEB13A 28APR13

40

LA1-0021

LTB 110- Electrical Wiring Works

3

3

0 06APR13

08APR13

56

LA1-0022

LTB 110- Lighting Fix. & Cover Plates Inst.

3

3

0 04MAY13

06MAY13

36

LA1-0024

LTB 110- Panel Board Inst.

3

3

0 20J UL13

22J UL13

-24

Mechanical LA1-0026

LTB 110- Exhaust Fan Inst.

1

1

90 01MAR13A

18J UN13

5

LA1-0027

LTB 110- Unit Heater Installation

1

1

0 18J UN13

18J UN13

6

Plumbing LA1-0028

LTB 110- Hot & Cold Water Piping

7

7

50 01DEC12A

08APR13

64

LA1-0030

LTB 110- Toilet Sanitry Fixture Inst.

7

7

50 02FEB13A

08APR13

67

LA1-0029

LTB 110- Toilet & Misc. Accessories

5

5

0 09APR13

14APR13

64

1

1

0 19J UN13

19J UN13

5

-23

Fire Protection System LA1-0031

LTB 110- Fire Extinguisher Inst.

Inspections, Punchlists LA1-0032

LTB 110- Test & Commission

2

2

0 23J UL13

24J UL13

LA1-0033

LTB 110- Punchlist Works

5

5

0 25J UL13

30J UL13

-23

LA1-0034

LTB 110- Finishing & Handover

1

1

0 31J UL13

31J UL13

-23

Large Latrine #111 Foundations LA2-0001

LTB 111- Layout

2

0

100 05APR12A

07APR12A

LA2-0002

LTB 111- Excavation Work

5

0

100 08APR12A

12APR12A

LA2-0003

LTB 111- Watering, Backfilling & Compaction

LA2-0004

LTB 111- Foundation & Ring Beam Works

LA2-0005

LTB 111- BKFLNG, CMPCTN, CAP. & Vap. Barriers

LA2-0006

LTB 111- Formwork & RFT for Slab on Grade

LA2-0007

LTB 111- Concrete for Slab on Grade

5

0

100 14APR12A

09OCT12A

12

0

100 15MAY12A

28MAY12A 11J UN12A

2

0

100 05J UN12A

12

0

100 12J UN12A

25J UN12A

7

0

100 14J UL12A

17SEP12A

Superstru cture & Close-in LA2-0008

LTB 111- Inst of Steel Bar for Stem Walls

12

0

100 18J UN12A

03J UL12A

LA2-0009

LTB 111- Inst. of Concrete Stem Walls

15

0

100 04J UL12A

01OCT12A

LA2-0010

LTB 111- Installation of K Span

15

0

100 01OCT12A

09OCT12A

7

0

100 24DEC12A

31J AN13A

 Archi tect ural - Exter ior  LA2-0013 Start Date Finish Date Data Date Run Date

LTB 111- Windows Installation 26J UL11 05SEP13 01APR13 13APR13 10:09

Early Bar Progress Bar Critical Activity

PS19

FCEC UIProjects J V W5J 9J R-10-D-0005-0006 ANA Gardez Project Management Layout

Sheet 25 of 38 Date

Revision

Checked

Approved

 Acti vity ID

 Acti vity Description

LA2-0011

LTB 111- Ext. Door installaion

LA2-0012

LTB 111- Ext. Painting of Stem Walls

Orig Dur 

Rem Dur 

%

Early Start

Early Finish

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A S

Total Float

5

5

40 19J AN13A

06APR13

12

15

15

30 26MAR13A

17APR13

26

 Archi tect ural - Int erio r  LA2-0014

LTB 111- Plaster for Steam Walls

7

0

100 18NOV12A

LA2-0015

LTB 111- Spray Insulation

7

7

0 07APR13

14APR13

25NOV12A 12

LA2-0016

LTB 111- Inst of gypsum Board Ceiling

6

6

0 15APR13

21APR13

39

LA2-0017

LTB 111- Inst. of gypsum Board

10

10

0 15APR13

25APR13

12

LA2-0018

LTB 111- Int. Doors Installation

7

7

0 27APR13

04MAY13

12

LA2-0019

LTB 111- Tiles for floor

15

15

0 24APR13

11MAY13

39

Electrical LA2-0020

LTB 111- Ele PVC Conduits/Fittings/Boxes

4

0

LA2-0021

LTB 111- Electrical Wiring Works

5

5

100 18FEB13A 0 01APR13

21FEB13A 06APR13

52

LA2-0022

LTB 111- Lighting Fix. & Cover Plates Inst.

2

2

0 22APR13

23APR13

39

LA2-0024

LTB 111- Panel Board Installation

6

6

0 20J UL13

25J UL13

-26

LA2-0023

LTB 111- Duplex & Switch Inst.

2

2

0 09J UN13

10J UN13

12

Mechanical LA2-0025

LTB 111- Exhaust Fan Installation

1

1

90 01MAR13A

18J UN13

5

LA2-0026

LTB 111- Unit Heater Installation

1

1

0 19J UN13

19J UN13

5

Plumbing LA2-0027

LTB 111- Hot & Cold Water Piping

7

7

25 01DEC12A

09APR13

60

LA2-0029

LTB 111- Toilet Sanitry Fixture Inst.

7

7

10 01MAR13A

09APR13

65

LA2-0028

LTB 111- Toilet & Misc. Accessories

4

4

0 10APR13

14APR13

60

1

1

0 18J UN13

18J UN13

6

-26

Fire Protection System LA2-0030

LTB 111- Fire Extinguisher Inst.

Inspections, Punchlists LA2-0031

LTB 111- Test & Commission

2

2

0 27J UL13

28J UL13

LA2-0032

LTB 111- Punchlist Works

5

5

0 29J UL13

03AUG13

-26

LA2-0033

LTB 111- Finishing & Handover

1

1

0 04AUG13

04AUG13

-26

Large Latrine #112 Foundations LA3-0001

LTB 112- Layout

2

0

100 07APR12A

08APR12A

LA3-0002

LTB 112- Excavation Work

5

0

100 11APR12A

16APR12A

LA3-0003

LTB 112- Watering, Backfilling & Compaction

LA3-0004

LTB 112- Foundation & Ring Beam Works

LA3-0005

LTB 112- BKFLNG, CMPCTN, CAP. & Vap. Barriers

Start Date Finish Date Data Date Run Date

26J UL11 05SEP13 01APR13 13APR13 10:09

Early Bar Progress Bar Critical Activity

5

0

100 21APR12A

25APR12A

15

0

100 12MAY12A

11J UN12A

9

0

100 12J UN12A

21J UN12A

PS19

FCEC UIProjects J V W5J 9J R-10-D-0005-0006 ANA Gardez Project Management Layout

Sheet 26 of 38 Date

Revision

Checked

Approved

 Acti vity ID

 Acti vity Description

Orig Dur 

Rem Dur 

%

Early Start

Early Finish

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A S

Total Float

LA3-0006

LTB 112- Formwork & RFT for Slab on Grade

12

0

100 23J UN12A

05J UL12A

LA3-0007

LTB 112- Concrete Works for Slab on Grade

8

0

100 07J UL12A

18SEP12A

Superstru cture & Close-in LA3-0008

LTB 112- Inst. of Steel Bar for Stem Walls

12

0

100 25J UN12A

10J UL12A

LA3-0009

LTB 112- Concrete Stem Walls

12

0

100 11J UL12A

02OCT12A

LA3-0010

LTB 112- Installation of K Span

15

0

100 02OCT12A

09OCT12A

 Archi tect ural - Exter ior  LA3-0011

LTB 112- Ext. Door Installaion

LA3-0012

LTB 112- Ext. Painting of Stem Walls

LA3-0013

LTB 112- Windows Installation

8

8

50 17DEC12A

08APR13

29

15

15

60 17DEC12A

17APR13

29

9

0

100 25DEC12A

04FEB13A

 Archi tect ural - Int erio r  LA3-0014

LTB 112- Plaster for Steam Walls

10

0

100 10NOV12A

LA3-0015

LTB 112- Spray Insulation

7

7

0 09APR13

15APR13

20NOV12A 29

LA3-0016

LTB 112- Inst. of gypsum Board ceiling

7

7

0 16APR13

22APR13

29

LA3-0017

LTB 112- Inst. of gypsum Board

15

15

0 23APR13

07MAY13

29

LA3-0019

LTB 112- Tiles for floor

10

10

0 27APR13

07MAY13

42

LA3-0018

LTB 112- Interior Doors Inst.

12

12

0 08MAY13

21MAY13

25

Electrical LA3-0020

LTB 112- Ele PVC Conduits/Fittings/Boxes

4

0

LA3-0021

LTB 112- Electrical Wiring Works

5

5

100 17FEB13A 0 01APR13

20FEB13A 06APR13

56

LA3-0022

LTB 112- Lighting Fix. & Cover Plates Inst.

3

3

0 23APR13

25APR13

42

LA3-0023

LTB 112- Duplex & Switch Inst.

2

2

0 22MAY13

23MAY13

25

LA3-0024

LTB 112- Panel Board Inst.

3

3

0 20J UL13

22J UL13

-23

Mechanical LA3-0025

LTB 112- Exhaust Fan Inst.

1

1

80 01MAR13A

18J UN13

2

LA3-0026

LTB 112- Unit Heater Inst.

1

1

0 19J UN13

19J UN13

2

Plumbing LA3-0027

LTB 112- Hot & Cold Water Piping

7

7

50 01DEC12A

09APR13

57

LA3-0029

LTB 112- Toilet Sanitry Fixture Inst.

7

7

10 01MAR13A

09APR13

62

LA3-0028

LTB 112- Toilet & Misc. Accessories

4

4

0 10APR13

14APR13

57

1

1

0 19J UN13

19J UN13

5

2

2

0 23J UL13

24J UL13

-23

Fire Protection System LA3-0030

LTB 112- Fire Extinguisher Inst.

Inspections, Punchlists LA3-0031 Start Date Finish Date Data Date Run Date

LTB 112- Test & Commission 26J UL11 05SEP13 01APR13 13APR13 10:09

Early Bar Progress Bar Critical Activity

PS19

FCEC UIProjects J V W5J 9J R-10-D-0005-0006 ANA Gardez Project Management Layout

Sheet 27 of 38 Date

Revision

Checked

Approved

 Acti vity ID

 Acti vity Description

Orig Dur 

Rem Dur 

%

Early Start

Early Finish

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A S

Total Float

LA3-0032

LTB 112- Punchlist Works

5

5

0 25J UL13

30J UL13

-23

LA3-0033

LTB 112- Finishing & Handover

1

1

0 31J UL13

31J UL13

-23

Large Latrine #113 Foundations L4-0001

LTB 113- Layout

1

0

100 07APR12A

07APR12A

L4-0002

LTB 113- Excavation Work

5

0

100 11APR12A

16APR12A

L4-0003

LTB 113- Watering, Backfilling & Compaction

L4-0004

LTB 113- Foundation & Ring Beam Works

L4-0005

LTB 113- BKFLNG, CMPCTN, CAP. & Vap. Barriers

L4-0006

LTB 113- Formwork & RFT for Slab on Grade

L4-0007

LTB 113- Concrete for Slab on Grade

12

5

0

100 17APR12A

22APR12A

12

0

100 01MAY12A

20MAY12A

9

0

100 21MAY12A

02J UN12A

12

0

100 03J UN12A

23J UN12A

0

100 24J UN12A

08J UL12A

Superstru cture & Close-in L4-0008

LTB 113- Inst. of Steel Bar for Steam Walls

10

0

100 30J UN12A

10J UL12A

L4-0009

LTB 113- Inst. of Concrete Steam Walls

12

0

100 11J UL12A

09DEC12A

L4-0010

LTB 113- Installation of K Span

15

0

100 02DEC12A

06DEC12A

 Archi tect ural - Exter ior  L4-0011

LTB 113- Exterior Door Inst.

6

6

40 26DEC12A

L4-0013

LTB 113- Windows Installation

12

0

100 01J AN13A

L4-0012

LTB 113- Ext. Painting of Stem Walls

14

14

60 20MAR13A

07APR13

64

09FEB13A 16APR13

49

 Archi tect ural - Int erio r  L4-0014

LTB 113- Plaster Work for Steam Walls

7

7

20 10J AN13A

08APR13

19

L4-0015

LTB 113- Spray Insulation

7

7

0 09APR13

16APR13

19

L4-0016

LTB 113- Inst. of gypsum Board Ceiling

10

10

0 17APR13

28APR13

19

L4-0017

LTB 113- Inst. of gypsum Board

14

14

0 17APR13

02MAY13

35

L4-0019

LTB 113- Tiles for floor

10

10

0 01MAY13

12MAY13

19

L4-0018

LTB 113- Int. Doors Installation

15

15

0 04MAY13

20MAY13

35

Electrical L4-0020

LTB 113- Ele PVC Conduits/Fittings/Boxes

4

0

L4-0021

LTB 113- Electrical Wiring Works

5

5

100 26FEB13A 0 01APR13

02MAR13A 06APR13

39

L4-0022

LTB 113- Lighting Fix. & Cover Plates Inst

2

2

0 29APR13

30APR13

19

L4-0023

LTB 113- Duplex & Switch Inst.

5

5

0 04MAY13

08MAY13

35

L4-0024

LTB 113- Panel Board Inst.

3

3

0 20J UL13

22J UL13

-24

Mechanical L4-0025

LTB 113- Exhaust Fan Inst.

2

2

90 27MAR13A

19J UN13

-1

L4-0026

LTB 113- Unit Heater Inst.

2

2

0 20J UN13

22J UN13

-1

Start Date Finish Date Data Date Run Date

26J UL11 05SEP13 01APR13 13APR13 10:09

Early Bar Progress Bar Critical Activity

PS19

FCEC UIProjects J V W5J 9J R-10-D-0005-0006 ANA Gardez Project Management Layout

Sheet 28 of 38 Date

Revision

Checked

Approved

 Acti vity ID

 Acti vity Description

Orig Dur 

Rem Dur 

%

Early Start

Early Finish

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A S

Total Float

Plumbing L4-0029

LTB 113- Toilet Sanitry Fixture Inst.

9

9

10 01MAR13A

10APR13

61

L4-0027

LTB 113- Hot & Cold Water Piping

7

7

0 13MAY13

20MAY13

19

L4-0028

LTB 113- Toilet & Misc. Accessories

4

4

0 21MAY13

25MAY13

19

2

2

0 23J UN13

24J UN13

1

-23

Fire Protection System L4-0030

LTB 113- Fire Extinguisher Inst.

Inspections, Punchlists L4-0031

LTB 113- Test & Commission

2

2

0 23J UL13

24J UL13

L4-0032

LTB 113- Punchlist Works

5

5

0 25J UL13

30J UL13

-23

L4-0033

LTB 113- Finishing & Handover

1

1

0 31J UL13

31J UL13

-23

Large Latrine #114 Foundations LA5-0001

LTB 114- Layout

1

0

100 08APR12A

08APR12A

LA5-0002

LTB 114- Excavation Work

5

0

100 14APR12A

19APR12A

LA5-0003

LTB 114- Watering, Backfilling & Compaction

26APR12A

LA5-0004

LTB 114- Foundation & Ring Beam Works

LA5-0005

LTB 114- BKFLNG, CMPCTN, CAP. & Vap. Barriers

LA5-0006

LTB 114- Formwork & RFT for Slab on Grade

LA5-0007

LTB 114- Concrete for Slab on Grade

5

0

100 21APR12A

12

0

100 28APR12A

10MAY12A

9

0

100 12MAY12A

21MAY12A

12

0

100 22MAY12A

05J UN12A

4

0

100 06J UN12A

11J UN12A

Superstru cture & Close-in LA5-0008

LTB 114- Inst. Steel Bar for Stem Walls

4

0

100 16J UN12A

09SEP12A

LA5-0009

LTB 114- Concrete for Stem Walls

8

0

100 11J UL12A

18SEP12A

LA5-0010

LTB 114- Installation of K Span

15

0

100 15AUG12A

26SEP12A

 Archi tect ural - Exter ior  LA5-0011

LTB 114- Ext. Door Installaion

15

15

40 18DEC12A

LA5-0013

LTB 114- Windows Installation

15

0

100 05J AN13A

LA5-0012

LTB 114- Ext. Painting of Stem Walls

18

18

0 27APR13

17APR13

8

09FEB13A 16MAY13

26

 Archi tect ural - Int erio r  LA5-0014

LTB 114- Plaster Work for Stem Walls

7

0

100 10OCT12A

LA5-0015

LTB 114- Spray Insulation

7

7

0 18APR13

25APR13

8

LA5-0016

LTB 114- Inst. of gypsum Board Ceiling

6

6

0 27APR13

02MAY13

8

LA5-0017

LTB 114- Inst. of gypsum Board

15

15

0 27APR13

13MAY13

29

LA5-0018

LTB 114- Int. Doors Installation

10

10

0 18MAY13

28MAY13

26

LA5-0019

LTB 114- Tiles for Floor

15

15

0 12MAY13

28MAY13

8

Start Date Finish Date Data Date Run Date

26J UL11 05SEP13 01APR13 13APR13 10:09

Early Bar Progress Bar Critical Activity

PS19

17OCT12A

FCEC UIProjects J V W5J 9J R-10-D-0005-0006 ANA Gardez Project Management Layout

Sheet 29 of 38 Date

Revision

Checked

Approved

 Acti vity ID

 Acti vity Description

Orig Dur 

Rem Dur 

%

Early Start

Early Finish

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A S

Total Float

Electrical LA5-0020

LTB 114- Ele PVC Conduits/Fittings/Boxes

4

0

LA5-0021

LTB 114- Electrical Wiring Works

5

5

100 18FEB13A 0 01APR13

21FEB13A 06APR13

LA5-0022

LTB 114- Lighting Fix. & Cover Plates Inst.

3

3

0 04MAY13

06MAY13

8

LA5-0023

LTB 114- Duplex & Switch Inst.

5

5

0 20MAY13

25MAY13

26

LA5-0024

LTB 114- Panel Board Inst.

3

3

0 20J UL13

22J UL13

-24

31

Mechanical LA5-0025

LTB 114- Exhaust Fan Inst.

1

1

90 28MAR13A

18J UN13

2

LA5-0026

LTB 114- Unit Heater Inst.

1

1

0 18J UN13

18J UN13

2

LA5-0028 LA5-0027

LTB 114- Toilet & Misc. Accessories LTB 114- Hot & Cold Water Piping

5 7

5 7

10 01MAR13A 0 29MAY13

06APR13 05J UN13

64 8

LA5-0029

LTB 114- Toilet Sanitry Fixture Inst.

4

4

0 06J UN13

10J UN13

8

1

1

0 19J UN13

19J UN13

5

-23

Plumbing

Fire Protection System LA5-0030

LTB 114- Fire Extinguisher Inst.

Inspections, Punchlists LA5-0031

LTB 114- Test & Commission

2

2

0 23J UL13

24J UL13

LA5-0032

LTB 114- Punchlist Works

5

5

0 25J UL13

30J UL13

-23

LA5-0033

LTB 114- Finishing & Handover

1

1

0 31J UL13

31J UL13

-23

Large Latrine #115 Foundations LA6-0001

LTB 115- Layout

1

0

100 09APR12A

09APR12A

LA6-0002

LTB 115- Excavation Work

5

0

100 14APR12A

19APR12A

LA6-0003

LTB 115- Watering, Backfilling & Compaction

25APR12A

LA6-0004

LTB 115- Foundation & Ring Beam

LA6-0005

LTB 115- BKFLNG, CMPCTN, CAP. & Vap. Barriers

LA6-0006

LTB 115- Formwork & RFT for Slab on Grade

LA6-0007

LTB 115- Concrete for Slab on Grade

5

0

100 21APR12A

12

0

100 26APR12A

10MAY12A

9

0

100 12MAY12A

24MAY12A

12

0

100 26MAY12A

10J UN12A

4

0

100 11J UN12A

16J UN12A

25J UN12A

Superstru cture & Close-in LA6-0008

LTB 115- Inst. of Steel Bar for Stem Walls

4

0

100 20J UN12A

LA6-0009

LTB 115- Concrete Stem Walls

8

0

100 26J UN12A

19J AN13A

LA6-0010

LTB 115- Installation of K Span

15

0

100 27NOV12A

05DEC12A

10

0

100 05J AN13A

09FEB13A

 Archi tect ural - Exter ior  LA6-0013 Start Date Finish Date Data Date Run Date

LTB 115- Windows Installation 26J UL11 05SEP13 01APR13 13APR13 10:10

Early Bar Progress Bar Critical Activity

PS19

FCEC UIProjects J V W5J 9J R-10-D-0005-0006 ANA Gardez Project Management Layout

Sheet 30 of 38 Date

Revision

Checked

Approved

 Acti vity ID

 Acti vity Description

Orig Dur 

Rem Dur 

%

Early Start

Early Finish

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A S

Total Float

LA6-0011

LTB 115- Ext. Door Installaion

15

15

40 05J AN13A

17APR13

11

LA6-0012

LTB 115- Ext. Painting of Steam Walls

15

15

20 21MAR13A

17APR13

27

 Archi tect ural - Int erio r  LA6-0014

LTB 115- Plaster for Stem Walls

7

0

100 18MAR13A

LA6-0015

LTB 115- Spray Insulation

7

7

0 18APR13

25APR13

25MAR13A 11

LA6-0016

LTB 115- Inst. of gypsum Board Ceiling

6

6

0 27APR13

02MAY13

11

LA6-0017

LTB 115- Inst. of gypsum Board

14

14

0 27APR13

12MAY13

23

LA6-0018

LTB 115- Int. Doors Installation

10

10

0 13MAY13

23MAY13

23

LA6-0019

LTB 115- Tiles for Floor

15

15

0 07MAY13

23MAY13

11

Electrical LA6-0020

LTB 115- Ele PVC Conduits/Fittings/Boxes

4

0

LA6-0021

LTB 115- Electrical Wiring Works

5

5

100 26FEB13A 0 01APR13

20MAR13A 06APR13

34

LA6-0022

LTB 115- Lighting Fix. & Cover Plates Inst.

3

3

0 04MAY13

06MAY13

11

LA6-0023

LTB 115- Duplex & Switch Inst.

4

4

0 20MAY13

23MAY13

23

LA6-0024

LTB 115- Panel Board Installation

3

3

0 20J UL13

22J UL13

-24

Mechanical LA6-0025

LTB 115- Exhaust Fan Installation

1

1

90 26MAR13A

18J UN13

2

LA6-0026

LTB 115- Unit Heater Installation

1

1

0 18J UN13

18J UN13

2

Plumbing LA6-0027

LTB 115- Hot & Cold Water Piping

7

7

0 25MAY13

01J UN13

11

LA6-0029

LTB 115- Toilet Sanitry Fixture Inst.

4

4

0 02J UN13

05J UN13

12

LA6-0028

LTB 115- Toilet & Misc. Accessories

5

5

0 02J UN13

06J UN13

11

1

1

0 19J UN13

19J UN13

5

-23

Fire Protection System LA6-0030

LTB 115- Fire Extinguisher Inst.

Inspections, Punchlists LA6-0031

LTB 115- Test & Commission

2

2

0 23J UL13

24J UL13

LA6-0032

LTB 115- Punchlist Works

5

5

0 25J UL13

30J UL13

-23

LA6-0033

LTB 115- Finishing & Handover

1

1

0 31J UL13

31J UL13

-23

MWR Building #105D Foundations MWR-0001 MWR 105D- Layout

1

0

100 01APR12A

01APR12A

MWR-0002 MWR 105D- Excavation Work

3

0

100 02APR12A

04APR12A

MWR-0003 MWR 105D- Watering, Backfilling & Compaction

4

0

100 05APR12A

09APR12A

MWR-0004 MWR 105D- Foundation & Ring Beam

8

0

100 14APR12A

25APR12A

MWR-0005 MWR 105D- BKFLNG, CMPCTN, CAP. & Vap. Barriers

8

0

100 10J UN12A

18J UN12A

Start Date Finish Date Data Date Run Date

26J UL11 05SEP13 01APR13 13APR13 10:10

Early Bar Progress Bar Critical Activity

PS19

FCEC UIProjects J V W5J 9J R-10-D-0005-0006 ANA Gardez Project Management Layout

Sheet 31 of 38 Date

Revision

Checked

Approved

 Acti vity ID

 Acti vity Description

Orig Dur 

MWR-0006 MWR 105D- Formwork & RFT for Slab on Grade

Rem Dur 

%

Early Start

Early Finish

10

0

100 19J UN12A

30J UN12A

7

0

100 01J UL12A

08J UL12A

25SEP12A

MWR-0007 MWR 105D- Concrete for Slab on Grade

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A S

Total Float

Superstru cture & Close-in MWR-0008 MWR 105D- Inst. of Steel Bar for Stem Walls

6

0

100 09J UL12A

MWR-0009 MWR 105D- Inst of Concrete Stem Walls

9

0

100 26SEP12A

19NOV12A

13

0

100 03OCT12A

24NOV12A

MWR-0010 MWR 105D- Installation of K Span

 Archi tect ural - Exter ior  MWR-0011 MWR 105D- Ext. Door Installation MWR-0012 MWR 105D- Ext. Painting of Stem Walls

9

9

90 14FEB13A

15APR13

16

16

90 14FEB13A

23APR13

43

6

6

50 25FEB13A

22APR13

44

MWR-0013 MWR 105D- Windows Installation

44

 Archi tect ural - Int erio r  MWR-0014 MWR 105D- Plaster Work for Stem Walls

6

0

100 20NOV12A

MWR-0015 MWR 105D- Spray Insulation

4

4

25 25NOV12A

04APR13

26NOV12A

MWR-0016 MWR 105D- Fence Installation

9

9

0 06APR13

15APR13

47

DPW-0018 MWR 105D- Int. Doors Installation

6

6

0 24APR13

30APR13

43

MWR-0019 MWR 105D- Sealed Concrete for Floor

4

4

0 30APR13

04MAY13

46

43

Electrical MWR-0020 MWR 105D- Ele PVC Conduits/Fittings/Boxes

8

0

MWR-0021 MWR 105D- Electrical Wiring Works

11

11

100 14FEB13A 0 06APR13

23FEB13A 17APR13

45

MWR-0022 MWR 105D- Lighting Fix. & Cover Plates Inst.

10

10

0 18APR13

29APR13

45

MWR-0023 MWR 105D- Duplex & Switch Inst.

6

6

0 01MAY13

07MAY13

43

MWR-0024 MWR 105D- Panel Board Inst.

5

5

0 20J UL13

24J UL13

-24

MWR-0026 MWR 105D- Exhaust Fan Inst.

2

2

0 18J UN13

19J UN13

2

MWR-0027 MWR 105D- Unit Heater Inst.

2

2

0 20J UN13

22J UN13

2

2

2

0 23J UN13

24J UN13

2

MWR-0032 MWR 105D- Test & Commission

2

2

0 25J UL13

27J UL13

-24

MWR-0033 MWR 105D- Punchlist Works

4

4

0 28J UL13

31J UL13

-24

MWR-0034 MWR 105D- Finishing & Handover

1

1

0 01AUG13

01AUG13

-24

1

0

Mechanical

Fire Protection System MWR-0031 MWR 105D- Fire Extinguisher Inst.

Inspections, Punchlists

DPW Buil ding #116 Foundations DPW-0001 DPW 116- Layout Start Date Finish Date Data Date Run Date

26J UL11 05SEP13 01APR13 13APR13 10:10

Early Bar Progress Bar Critical Activity

PS19

100 09APR12A

09APR12A

FCEC UIProjects J V W5J 9J R-10-D-0005-0006 ANA Gardez Project Management Layout

Sheet 32 of 38 Date

Revision

Checked

Approved

 Acti vity ID

 Acti vity Description

Orig Dur 

Rem Dur 

%

Early Start

Early Finish

DPW-0002 DPW 116- Excavation Work

8

0

100 11APR12A

21APR12A

DPW-0003 DPW 116- Watering, Backfilling & Compaction

5

0

100 22APR12A

26APR12A

16

0

100 22APR12A

09J AN13A

9

0

100 20MAY12A

21J UN12A

DPW-0004 DPW 116- Foundation & Ring Beam DPW-0005 DPW 116- BKFLNG, CMPCTN, CAP. & Vap. Barriers

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A S

Total Float

DPW-0006 DPW 116- Formwork & RFT for Slab on Grade

15

0

100 25J UN12A

12AUG12A

DPW-0007 DPW 116- Concrete for Slab on Grade

10

0

100 13AUG12A

09SEP12A

08J UL12A

Superstru cture & Close-in DPW-0008 DPW 116- Inst. of Steel Bar for Steam Walls

12

0

100 26J UN12A

DPW-0009 DPW 116- Inst. of Concrete Steam Walls

12

0

100 10SEP12A

14J AN13A

DPW-0010 DPW 116- Installation of K Span

15

0

100 02OCT12A

26NOV12A

DPW-0013 DPW 116- Windows Installation

10

10

95 05DEC12A

11APR13

66

DPW-0011 DPW 116- Ext. Door Installaion

8

8

30 01J AN13A

09APR13

66

18

10

20 16FEB13A

11APR13

49

 Archi tect ural - Exter ior 

DPW-0012 DPW 116- Ext. Painting of Stem Walls

 Archi tect ural - Int erio r  DPW-0014 DPW 116- Plaster for Steam Walls

15

15

85 14NOV12A

17APR13

35

DPW-0015 DPW 116- Spray Insulation

15

10

60 10DEC12A

11APR13

40

DPW-0017 DPW 116- Inst. of gypsum Board

15

10

20 16FEB13A

11APR13

66

DPW-0016 DPW 116- Inst. of Suspended Ceiling

8

8

0 18APR13

27APR13

35

DPW-0019 DPW 116- Sealed Concrete for Floor

5

5

0 29APR13

04MAY13

35

DPW-0020 DPW 116- Ele PVC Conduits/Fittings/Boxes

3

0

DPW-0023 DPW 116- Duplex & Switch Inst.

4

4

0 01APR13

04APR13

66

DPW-0021 DPW 116- Electrical Wiring Works

6

6

0 01APR13

07APR13

52

DPW-0022 DPW 116- Lighting Fix. & Cover Plates Inst.

2

2

0 28APR13

29APR13

35

DPW-0024 DPW 116- Panel Board Inst.

3

3

0 20J UL13

22J UL13

-23

DPW-0025 DPW 116- AC Split Installation

1

1

0 06APR13

06APR13

66

DPW-0027 DPW 116- Unit Heater Installation

1

1

0 12MAY13

12MAY13

35

DPW-0026 DPW 116- Exhaust Fan Installation

1

1

0 18J UN13

18J UN13

3

Electrical 100 16FEB13A

18FEB13A

Mechanical

Plumbing DPW-0028 DPW 116- Hot & Cold Water Piping

6

6

0 30APR13

06MAY13

35

DPW-0030 DPW 116- Toilet Sanitry Fixture Inst.

4

4

0 07MAY13

11MAY13

35

DPW-0029 DPW 116- Toilet & Misc. Accessories

5

5

0 07MAY13

12MAY13

35

1

1

0 30APR13

30APR13

Fire Protection System DPW-0031 DPW 116- Fire Extinguisher Inst. Start Date Finish Date Data Date Run Date

26J UL11 05SEP13 01APR13 13APR13 10:10

Early Bar Progress Bar Critical Activity

PS19

FCEC UIProjects J V W5J 9J R-10-D-0005-0006 ANA Gardez Project Management Layout

48 Sheet 33 of 38 Date

Revision

Checked

Approved

 Acti vity ID

 Acti vity Description

Orig Dur 

Rem Dur 

%

Early Start

Early Finish

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A S

Total Float

Inspections, Punchlists DPW-0032 DPW 116- Test & Commission

2

2

0 23J UL13

24J UL13

DPW-0033 DPW 116- Punchlist Works

5

5

0 25J UL13

30J UL13

-23 -23

DPW-0034 DPW 116- Finishing & Handover

1

1

0 31J UL13

31J UL13

-23

Literacy Classroom #117A Foundations LCR1-001

LCR 117A - Layout

1

0

100 03APR12A

03APR12A

LCR1-002

LCR 117A - Excavation Work

3

0

100 04APR12A

07APR12A

LCR1-003

LCR 117A - Watering, Backfilling & Compaction

3

0

100 08APR12A

10APR12A

LCR1-004

LCR 117A - Foundation & Ring Beam

8

0

100 14APR12A

25APR12A

LCR1-005

LCR 117A - BKFLNG, CMPCTN, CAP. & Vap. Barriers

8

0

100 21MAY12A

05J UL12A

LCR1-007

LCR 117A - Concrete for Slab on Grade

LCR1-006

LCR 117A - Formwork & RFT for Slab on Grade

5

0

100 25J UN12A

02J UL12A

13

0

100 25J UN12A

08J UL12A

Superstru cture & Close-in LCR1-008

LCR 117A - Inst. of Steel Bar for Stem Walls

6

0

100 28J UN12A

04J UL12A

LCR1-009

LCR 117A - Concrete for Stem Walls

10

0

100 05J UL12A

02OCT12A

LCR1-010

LCR 117A - Installation of K Span

15

0

100 12AUG12A

08OCT12A

 Archi tect ural - Exter ior  LCR1-013

LCR 117A - Windows Installation

5

0

100 01DEC12A

29J AN13A

LCR1-011

LCR 117A - Ext. Door Installaion

5

5

90 18DEC12A

06APR13

LCR1-012

LCR 117A - Ext. Painting of Stem Walls

11

0

100 18FEB13A

60

31MAR13A

 Archi tect ural - Int erio r  LCR1-014

LCR 117A - Plaster Work for Steam Walls

13

0

100 10OCT12A

LCR1-015

LCR 117A - Spray Insulation

7

7

95 25NOV12A

08APR13

24OCT12A 48

LCR1-017

LCR 117A - Int. Doors Installation

5

5

30 03MAR13A

06APR13

61

LCR1-016

LCR 117A - Fence Installation

10

10

0 09APR13

20APR13

48

LCR1-018

LCR 117A - Sealed Concrete for Floor

8

8

0 21APR13

29APR13

48

LCR1-019

LCR 117A - Ele PVC Conduits/Fittings/Boxes

7

0

LCR1-020

LCR 117A - Electrical Wiring Works

6

5

30 26MAR13A

06APR13

LCR1-021

LCR 117A - Duplex & Switch Inst.

5

5

30 26MAR13A

06APR13

61

LCR1-022

LCR 117A - Lighting Fix. & Cover Plates Inst.

5

5

50 27MAR13A

20APR13

48

LCR1-023

LCR 117A - Panel Board Installation

3

3

0 20J UL13

22J UL13

-24

1

1

60 27MAR13A

18J UN13

2

Electrical 100 18FEB13A

25FEB13A 60

Mechanical LCR1-024 Start Date Finish Date Data Date Run Date

LCR 117A - Exhaust Fan Installation 26J UL11 05SEP13 01APR13 13APR13 10:10

Early Bar Progress Bar Critical Activity

PS19

FCEC UIProjects J V W5J 9J R-10-D-0005-0006 ANA Gardez Project Management Layout

Sheet 34 of 38 Date

Revision

Checked

Approved

 Acti vity ID

 Acti vity Description

Orig Dur 

Rem Dur 

%

Early Start

Early Finish

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A S

Total Float

LCR1-025

LCR 117A - Unit Heater Installation

1

1

0 19J UN13

19J UN13

4

LCR1-026

LCR 117A - Fire Extinguisher Inst.

1

1

0 21APR13

21APR13

55

LCR1-027

LCR 117A - Test & Commission

2

2

0 23J UL13

24J UL13

-24

LCR1-028

LCR 117A - Punchlist Works

6

6

0 25J UL13

01AUG13

-24

LCR1-029

LCR 117A - Finishing & Handover

1

1

0 03AUG13

03AUG13

-24

LCR2-001

LCR 117B- Layout

1

0

100 04APR12A

04APR12A

LCR2-002

LCR 117B- Excavation Work

3

0

100 05APR12A

07APR12A

LCR2-003

LCR 117B- Watering, Backfilling & Compaction

10APR12A

LCR2-004

LCR 117B- Foundation & Ring Beam

LCR2-005

LCR 117B- BKFLNG, CMPCTN, CAP. & Vap. Barriers

LCR2-006

LCR 117B- Formwork & RFT for Slab on Grade

15

0

100 04J UN12A

26J UN12A

LCR2-007

LCR 117B- Concrete for Slab on Grade

12

0

100 20J UN12A

05J UL12A

LCR2-008

LCR 117B- Inst. of Steel Bar for Stem Walls

10

0

100 20J UN12A

02J UL12A

LCR2-009

LCR 117B- Concrete for Stem Walls

15

0

100 03J UL12A

02OCT12A

LCR2-010

LCR 117B- Installation of K Span

15

0

100 13AUG12A

08OCT12A

LCR2-013

LCR 117B- Windows Installation

8

0

100 01DEC12A

27J AN13A

LCR2-011

LCR 117B- Ext. Door Installation

8

8

90 18DEC12A

09APR13

LCR2-012

LCR 117B- Ext. Painting of Stem Walls

12

0

100 18FEB13A

LCR2-014

LCR 117B- Plaster for Stem Walls

10

0

100 10OCT12A

09FEB13A

LCR2-015

LCR 117B- Spray Insulation

7

7

90 10DEC12A

08APR13

52

LCR2-017

LCR 117B- Int. Doors Installation

5

5

30 04MAR13A

06APR13

61

LCR2-016

LCR 117B- Fence Installation

10

10

0 09APR13

20APR13

52

LCR2-018

LCR 117B- Sealed Concrete for Floor

8

8

0 10APR13

18APR13

56

LCR2-019

LCR 117B- Ele PVC Conduits/Fittings/Boxes

6

0

100 18FEB13A

LCR2-020

LCR 117B- Electrical Wiring Works

7

7

30 25FEB13A

08APR13

LCR2-021

LCR 117B- Duplex & Switch Inst.

7

7

30 27MAR13A

08APR13

61

LCR2-022

LCR 117B- Lighting Fix. & Cover Plates Inst.

7

7

60 27MAR13A

08APR13

57

Start Date Finish Date Data Date Run Date

26J UL11 05SEP13 01APR13 13APR13 10:10

Early Bar Progress Bar Critical Activity

3

0

100 08APR12A

10

0

100 11APR12A

23APR12A

9

0

100 12MAY12A

21MAY12A

PS19

56

31MAR13A

24FEB13A

FCEC UIProjects J V W5J 9J R-10-D-0005-0006 ANA Gardez Project Management Layout

57

Sheet 35 of 38 Date

Revision

Checked

Approved

 Acti vity ID

LCR2-023

 Acti vity Description

Orig Dur 

LCR 117B- Panel Board Inst.

Rem Dur 

%

Early Start

Early Finish

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A S

Total Float

3

3

0 20J UL13

22J UL13

-25

Mechanical LCR2-024

LCR 117B- Exhaust Fan Inst.

1

1

60 27MAR13A

18J UN13

0

LCR2-025

LCR 117B- Unit Heater Inst.

1

1

0 19J UN13

19J UN13

0

1

1

0 10APR13

10APR13

63

-25

Fire Protection System LCR2-026

LCR 117B- Fire Extinguisher Inst.

Inspections, Punchlists LCR2-027

LCR 117B- Test & Commission

2

2

0 23J UL13

24J UL13

LCR2-028

LCR 117B- Punchlist Works

7

7

0 25J UL13

01AUG13

-25

LCR2-029

LCR 117B- Finishing & Handover

1

1

0 03AUG13

03AUG13

-25

Fire Station #118 Foundations FSB-0001

FSB 118- Layout

1

0

100 06APR12A

07APR12A

FSB-0002

FSB 118- Excavation Work

3

0

100 07APR12A

09APR12A

FSB-0003

FSB 118- Watering, Backfilling & Compaction

3

0

100 14APR12A

19APR12A

FSB-0004

FSB 118- FDN & Ring Beam

8

0

100 21APR12A

03MAY12A

FSB-0005

FSB 118- BKFLNG, CMPCTN, CAP. & Vap. Barriers

7

0

100 12MAY12A

05J UL12A

FSB-0006

FSB 118- Formwork & RFT for Slab on Grade

5

0

100 07J UL12A

12J UL12A

FSB-0007

FSB 118- Concrete for Slab on Grade

1

0

100 14J UL12A

12AUG12A

Superstru cture & Close-in FSB-0010

FSB 118- Installation of K Span

13

0

100 12AUG12A

24NOV12A

FSB-0008

FSB 118- Inst. of Steel Bar for Stem Walls

12

0

100 13AUG12A

29AUG12A

FSB-0009

FSB 118- Concrete Stem Walls

10

0

100 03SEP12A

21J AN13A

 Archi tect ural - Exter ior  FSB-0011

FSB 118- Ext. Door Installation

7

7

90 28DEC12A

07APR13

FSB-0013

FSB 118- Windows Installation

7

0

100 30DEC12A

17J AN13A

69

FSB-0012

FSB 118- Ext. Painting of Stem Walls

8

7

90 28FEB13A

08APR13

59

 Archi tect ural - Int erio r  FSB-0014

FSB 118- Plaster for Stem Walls

10

0

100 10DEC12A

FSB-0015

FSB 118- Spray Insulation

7

7

25 21FEB13A

07APR13

54

FSB-0017

FSB 118- Int. Doors Instalation

7

7

20 01MAR13A

08APR13

59

FSB-0016

FSB 118- Fence Installation

8

8

0 08APR13

15APR13

54

FSB-0018

FSB 118- Sealed Concrete for Floor

5

5

0 28APR13

02MAY13

46

Start Date Finish Date Data Date Run Date

26J UL11 05SEP13 01APR13 13APR13 10:10

Early Bar Progress Bar Critical Activity

PS19

28MAR13A

FCEC UIProjects J V W5J 9J R-10-D-0005-0006 ANA Gardez Project Management Layout

Sheet 36 of 38 Date

Revision

Checked

Approved

 Acti vity ID

 Acti vity Description

Orig Dur 

Rem Dur 

%

Early Start

Early Finish

2011 2012 2013 J A S O N D J F M A M J J A S O N D J F M A M J J A S

Total Float

Electrical FSB-0019

FSB 118- Ele PVC Conduits/Fittings/Boxes

10

0

FSB-0020

FSB 118- Electrical Wiring Works

12

12

100 23FEB13A 0 01APR13

01MAR13A 14APR13

47

FSB-0021

FSB 118- Duplex & Switch Inst.

9

9

0 16APR13

25APR13

53

FSB-0022

FSB 118- Lighting Fix. & Cover Plates Inst.

10

10

0 16APR13

27APR13

46

FSB-0023

FSB 118- Panel Board Installation

5

5

0 20J UL13

24J UL13

-25

Mechanical FSB-0024

FSB 118- Exhaust Fan Inst.

3

3

45 28MAR13A

20J UN13

-1

FSB-0025

FSB 118- Unit Heater Inst.

3

3

25 29MAR13A

20J UN13

-1

5

5

0 22J UN13

26J UN13

-1

-25

Fire Protection System FSB-0026

FSB 118- Fire Extinguisher Inst.

Inspections, Punchlists FSB-0027

FSB 118- Test & Commission

2

2

0 25J UL13

27J UL13

FSB-0028

FSB 118- Punchlist Works

5

5

0 28J UL13

01AUG13

-25

FSB-0029

FSB 118- Finishing & Handover

1

1

0 03AUG13

03AUG13

-25

Contract Close-out Close-out Inspections

CCO-0001

Prefinal Inspection & Correction

10

10

0 11AUG13

21AUG13

-22

CCO-0002

Final Inspection

3

3

0 22AUG13

25AUG13

-22

CCO-0003

Final Acceptance & Handover

1

1

0 26AUG13

26AUG13

-22

 As-Bui lt Drawi ngs

CCO-0004

Submit As-Built Drawings

CCO-0005

Approved As-Built Drawing by AED

6

6

0 04AUG13

09AUG13

-30

14

14

0 10AUG13

23AUG13

-30

O&M Manuals & Training

CCO-0006

Submit O&M Manual

7

7

0 04AUG13

10AUG13

-24

CCO-0007

Approved O&M Manual by AED

7

7

0 11AUG13

17AUG13

-24

Start Date Finish Date Data Date Run Date

26J UL11 05SEP13 01APR13 13APR13 10:10

Early Bar Progress Bar Critical Activity

PS19

FCEC UIProjects J V W5J 9J R-10-D-0005-0006 ANA Gardez Project Management Layout

Sheet 37 of 38 Date

Revision

Checked

Approved

View more...

Comments

Copyright ©2017 KUPDF Inc.
SUPPORT KUPDF