SAUDI ARAMCO SCAFFOLD INSPECTION GUIDE 9

(38" - 45")

0.95m - 1.15m

12

10

11 7

TUBES: Must not be bent, split, distorted or corroded. PLANKS: Must not be split more than 300mm (12”), warped or damaged. LADDERS: (1) Must be supported on both feet. (2) Must extend 0.9m (3’) above landing point. (3) External ladder must be inclined at an angle of 75o(4 vertical to 1 horizontal). (4) Both side rails of ladder to be secured.

4 8

2m (6'6") max. (typical)

13

H

3

5 8

FIG 1 SUPPORT SPACING FOR PLANKS (BOARDS) 38MM (11/2”) THICK

75o

6

150mm (6")

2 1.2m(4ft)

1

W

Note: Couplers are not shown

1 SILLS (SOLE BOARDS) used to support scaffold posts on soft surfaces. Minimum size 765mm (30”) long, 225mm (9”) wide and 38mm (11/2”) thick. 2 BASE PLATE min. size 150mm x 150mm x 6mm and installed below all posts (standards). 3 POSTS (STANDARDS) must be plumb, straight, on firm ground, and not near the edge of any excavation. Distances between posts will depend on the loading. For tube and coupler scaffolds, the maximum allowable distances between posts is as follows: DUTY

MAXIMUM LOAD

LIGHT

120 kg/m2 (25 lbs/sq.ft) 240 kg/m2 (50 lbs/sq.ft)

MEDIUM

MAX. DISTANCE BETWEEN POSTS ACROSS WIDTH ALONG LENGTH

1.2m (4’)

2.7m (9’)

1.2m (4’)

1.8m (6’)

4 BEARERS (TRANSOMS) run across the width of the scaffold on each row of posts and are spaced vertically nor more than 2m (6’6”) apart. For tube and coupler scaffolds, bearers are to be fixed on top of the runners (not underneath) and extend at least 100mm (4”) beyond supporting runners. 5 RUNNERS (LEDGERS) run along the length of the scaffold on each row of posts and are spaced vertically at not more than 2m (6’6”) apart. 6 BASE LIFT (KICKER LIFT) is positioned about 150mm (6”) above the ground.

SAUDI

7 WOOD SCAFFOLD PLANKS (BOARDS) to be at least 38mm (11/2”) thick and 225mm (9”) wide, and - gaps between planks on platforms shall not be wider than 25mm (1”) - 38mm (11/2”) thick planks to be supported by bearers or board bearers spaced not more than 1.5m (5’) apart (see Fig. 1) - 50mm (2”) thick planks to be supported by bearers or board bearers spaced not more than 2.4m (8’) apart. - planks to overhang their end support by at least 150mm (6”) and not more than 300mm (12”). (see Fig. 2) 8 BRACING Scaffold is vertically braced for the full height across the width and along the length to provide structural stability. All braces must be attached as close as possible to the post/runner/bearer intersection. 9 TOPRAIL is the top horizontal rail of the guardrail system, to be 0.95m 1.15m (38” - 45”) above the platform. 10 MIDRAIL is the horizontal rail installed midway between the toprail and platform. 11 TOEBOARD of a minimum size 100mm (4”) high x 25mm (1”) thick. General note to 9, 10 and 11: Toprails, midrails and toeboards are installed on the inside of support posts on all open sides and ends of platforms. 12 SELF-CLOSING DROP BAR to be installed inside posts whenever there is a step-through opening in the guardrails. 13 SUPPORTED SCAFFOLDS with a height (H) of over four times the minimum base dimension (W) must be restrained from tipping by ties or equivalent means.

OLD SCAFF PECTION S IN D E PASS

L SPECIA ) (50 PSF NKED MEDIUM TOTAL PLA OR #: ATION ) LD LOC (25 PSF SCAFFO ING: LIGHT #4 NG ection RAT LOAD : WORKI # 3 Insp LEVELS ection MAX # # 2 Insp ISOR* ection ERV Insp LD SUP on # 1 Inspecti SCAFFO ly Bi-week NAME PRINT URE SIGNAT # on # 4 PHONE Inspecti CATE # on # 3 CERTIFI Inspecti * on # 2 Inspecti PECTOR LD INS on # 1 Inspecti SCAFFO ly eek Bi-w NAME PRINT URE Y SIGNAT M/D/ Y # M/D/ PHONE on # 4 Y Inspecti CATE # M/D/ on # 3 CERTIFI Y Inspecti M/D/ on # 2 DATE Inspecti CTION NEXT on # 1 INSPE Inspecti DATE OF 00) NEXT TION 0-407UNTIL -00 INSPEC #21 LID F: DS TAG VA .S. RE TAG VOI (S.A.M ION GREEN GREEN LD OR ARY ACT Scaffold CIPLIN SCAFFO r and T TO DIS fold Superviso GI 8.001. TION OF . Scaf ALTERA YOU SUBJEC fold per (20') high ial Scaf ORISED MAKE than 6m if Spec UNAUTH AND WILL is less high or 419 old I (20') scaff than 6m REF STS THIS TAG shall sign if

FIG 2 PLANK OVERLAP AND OVERHANG

SCAFFTAG® Safety Management Systems

CO

ARAM

r is more Superviso sign if scaffold *Scaffold both r shall Inspecto ETRAK

© SCAFF

/// SAF TAG ®

® TEL:

(0)1446

721029

SCAFFTAG® is a registered trade name of SCAFFTAG Limited. SCAFFTAG® is not the generic word or name for labels, tags, inserts or their holders designed to be attached to scaffolding, and on no account should be so used. As the manufacturer SCAFFTAG Limited recommend that in operation it is the responsibility of the scaffold user to ensure the equipment is showing “Fit for Use” and within the inspection dates. We reserve the right to alter without prior notice any specification of our products. SCAFFTAG® Systems and Products are registered and copyright protected.

View more...

Comments

Copyright ©2017 KUPDF Inc.
SUPPORT KUPDF