TS1-OIL Rev. U
Short Description
tsi...
Description
TS1 OIL 16. February 2012
TS 1 Revion U
No
Audited Item
Open Item
Remark
Action by PT. INKA / Result
Status
Close have checked the √ (17032011) function and added in the report
1
Cheek sheet of components installation
- Number of speed sensor (TC1/TS1)
1 speed sensor miss to be checked
will be checked
2
Cheek sheet of components installation
- Ground contact
Not yet checked and must add to the check documentation
will be checked and added
have checked and added √ (21032011) to check sheet of Component Installation
3
Quality Plan Procedure (ITP)
- Create an Overview about routine test & type test are requested for total process
will be showed to HC
have added to Vehicle Record Book
4
Static test procedure
- Anti trap don't install
Don't list at the contract of project. Hamburg Consult state that there must Anti trap at the door (according to the international standard/state of art). Anti trap don't describes at the detail of contract.
see list of deviation in the √ (17032011) Vehicle record book
5
Static test procedure
- There is difference between Bogie number (Component identification number and Bogie Serial Number)
INKA use number of Bogie frame when bogie load test (July 2010), and use
update of document
√ (17032011)
6
Static test procedure
- Bogie number inspection Doc. number E0.20.402. Measurement value outside tolerance (Point 8 & 9)
Check of target value
clarification in the document
√ (24032011)
7
Static test procedure
- Some test only have Test Record, not yet for the Test Procedure
Test Procedure will be added
8
Static test procedure
- Create separate folder for Test Record and Test Procedure
will be created
9
Static test procedure
- Static tolerance of axle loads
The maximum difference of wheel loads of one wheel Repeat for the weight test set in leveled track more than 4% in relation to the average wheel loads for empty vehicles. The maximum differences between wheel loads of two related bogies shall not be more than 2%
carried out and balanced √ (04042011)
10
Static test procedure
- Check lubrication on Inspection Sheet Bogie Assembly Trailer Car (TC1/TS1)
Not yet checked, will describe which lubrication must will be checked be checked
have checked, inspected and recorded
√ (22032011)
11
Static test procedure
- E0 20-401 E020 08 005 (Bogie)
have checked, mistyped
√ (17032011)
12
Static test procedure
- Coupler measurement on TC1,M1,M2,TC2
Procedure how to filled up the coupler measurement check sheet.
Repeat the measurement
13
Static test procedure
- Inspection Sheet of Insulation test (Megger Tester 500V) (M2)
some test are missing
will be checked and measure
have measured the missing test
√ (17032011)
14
Static test procedure
- Check of Compresor preparation on (M2)
It can be changed/referred to another document
Delete the existing rows
The rows have been deleted and referred to another document
√ (21032011)
15
Static test procedure
- Actual time of lowering pantograph
write the value (seconds)
will be added
have added the value (in seconds)
√ (17032011)
16
TCMS
- Exchange of connector for the monitoring of Battery charger Over temperature & Charger failure.
INKA still waiting for new connector
335433966.xls
Check the value under crash load
Page 1 of 7
√ (24032011)
√ (16022012) existing
√ (04042011)
√ (26092011)
√ (22112012)
22.11.2012
No
Audited Item
Open Item
Remark
Action by PT. INKA / Result
Status Close
17 March 2011 17
List of drawing
- Add list of drawing (drawing number & version) in the Vehicle record book
Will add to the Vehicle record book
18
Test on safety related equipment
- Add test procedure for inspecting existing equipment (emergency hammer, extinguisher including checking label) and safety labeling
Will add to the Check Sheet of components installation and Inspect on the train
19
Curve test
- Add curve test (turn out test) procedure for coupled train
will check directly to the test track (min curve R = 80m)
the procedure have been √ (21032011) added to the curve test (on routine test)
20
Door emergency handle
- Door emergency handle not yet installed
will be installed
was installed. Please refer √ (31032011) also to List of deviation
21
Door leaves
- Door leaves can't close perfectly (there is small gap)
will re-adjust the door, check before dynamic test and add task to the dynamic test procedure at incoming inspection
Door rubbers are changed √ (16022012) to male/female design
22
Safety device label
- Safety device label (emergency window, fire extinguisher, door handle)
23
Interior & exterior
- Cleaning the interior & exterior
24
Interior & exterior
- Loud speaker screw (scratch paint)
25
Interior & exterior
26
Door emergency handle is listed at the document of contract.
Not complete installed.
to be reduced.
List of drawing have been √ (28032011) added to the Vehicle record book √ (04042011)
will install
√ (16022012)
will be cleaned before train sent to Jakarta
√ (22112012)
touch up the painting
have touch up
√ (22032011)
- Loud speaker cover (scratch paint)
touch up the painting
have touch up
√ (22032011)
Interior & exterior
- TC1 (right side) : damage of side wall over baggage rack
will be repaired and repainting
have repaired and repainted
√ (22032011)
27
Interior & exterior
- Spot welding area isn't clean
will be cleaned
√ (16022012)
28
Bogie and Carbody
- Safety mark of the screw/bolt are missing
the safety relevant bolt will be marked
√ (07062011)
29
Jumper cable coupler (on the roof)
- Jumper cable coupler will be inspected during dynamic test in Jakarta
The cable are to long.
Definition of the fixed length and reduce the cable
√ (07092011)
30
Flexible hose
- flexible hose touch against and chafe against the bogie frame
Hamburg Consult is accepted about flexible hose protector.
will give protector to flexible hose
√ (07062011)
31
Co-masinis chair
- TC1 : co-masinis chair (second chair) not yet installed
will be installed after dynamic test
is installed
√ (21032011)
22 March 2011 32
Door
- Adjustment of the exact door signal (open and close)
Safety relevant
33
Door
- Maintainability to the door mechanism is not given
the reason is LCD cover hit against the ceiling when the cover is opened. LCD is requested by DGR
335433966.xls
Page 2 of 7
re-adjusted and tested Check the design and define maintenance task
√ (24032011) √ (09082011) update maintenance manual later
22.11.2012
No 34
Audited Item Test Record car body shell
Open Item
Remark
- Clarification between under frame and car body number
Action by PT. INKA / Result will be clarified
has added in Vehicle record book, point number 9
on TS3
move to TS3
Status Close √ (22032011)
23 March 2011 35
Lifting ability test
- Can the train lift with the bogie
carrying out at type test
36
De-railment
- Procedure of re-alignment
add re-alignment procedure for the train to the maintenance manual/driver guide
37
Braking software
38
TCMS
- Updating software procedure for end customer.
39
TCMS
40
√ (09082011) update maintenance manual later
Doc. E0.20-406.2 page 5, target value of software version must be added
clarified Standard Operating Procedure how to update software from Bombardier to Customer
√ (28032011)
√ (25032011)
Clarification by BT
√ (10082011)
- What is the meaning Consist 1 & Consist 2 (Doc. 3EST000220-2673)
Clarification by BT
√ (10082011)
TCMS
- Explanation about (*) remark at TCMS routine test. Step 5.5.4 DX8C; 5.5.5 DX8D (Doc. 3EST000220-2673)
Clarification by BT
√ (22112012)
41
TCMS
- BVI test, Step 5.5.6 AX84 (Doc. 3EST0002202673)
Update Test Specification & Test Report document. Step 5.5.6 AX84 (Doc. 3EST000220-2670)
Clarification by BT
√ (22112012)
42
TCMS
- Verify/Check test point number 7 &8. Step 5.5.8 DX36 (Doc. 3EST000220-2673)
Verify test point number 7 & 8 after new connector installed
Clarification by BT
√ (22112012)
43
TCMS
- Update the document Step 5.6.6 AX84 (3EST000220-2670)
Test record must be updated as standard for the next Clarification by BT train set
√ (10082011)
44
TCMS
- Update the document Step 5.6.7 AX85 (3EST000220-2670)
Test record must be updated as standard for the next Clarification by BT train set
√ (10082011)
45
TCMS
- Add a note about the impact when updating software on document 3EST000220-2675.
Give remark (*) under the table Chapter 4.1
Clarification by BT
√ (10082011)
46
TCMS
- Update the Test Specification and Test Report
About document number 3EST0002202670/2671/2672/2673/2674/2675
Clarification by BT
√ (10082011)
47
TCMS
- BT will repeat the open item test (nb. item that need to be repeated and item that can't be checked at INKA)
Because the installation of new software version
Clarification by BT
√ (22112012)
48
Clarification of driver's procedure
- Add of additional test for Online test at Jakarta. Results are implemented at driver manual guide
Emergency brake handle is activated when the train move (standstill, 5 km/hr, 50 km/hr). What is the effect?
Completion of the Online test procedure (test at Jakarta)
√ (09082011)
49
Clarification of driver's procedure
- Add of additional test for Online test at Jakarta. Results are implemented at driver manual guide
Emergency door handle is activated when the train move (standstill, 5 km/hr, 50 km/hr). What is the effect?
Completion of the Online test procedure (test at Jakarta) /
√ (09082011)
50
Clarification of driver's procedure
- Simulation of the platform situation is to be added on Online test
Completion of the Online test
√ (22112012)
24 March 2011 51
Leveling of the train
- Procedure of leveling necessary
Add to the maintenance manual and sent preliminary formal letter to Dipo
- Procedure of lamp intensity test
Measurement condition (environment)
√ (09082011) update maintenance manual later
25 March 2011 52
Room lamp intensity test
335433966.xls
Page 3 of 7
update of the test procedure record sheet
√ (28032011)
22.11.2012
No
Audited Item
Open Item
Remark
53
Function test Air Conditioner
- Procedure of function test Air Conditioner
Add target value of humidity temperature
54
Function test Air Conditioner
- Measurement of Air Conditioner must be repeated on MC2
The humidity outside of tolerance
55
Pneumatic Static Test of braking sy
- Air supply equipment (item no 4), deviation between setting value and actual value
Confirmation/statement from KNORR request
Action by PT. INKA / Result update of the procedure and record sheet Will repeat the measurement and adjust the thermostat
Status Close √ (28032011)
thermostat has adjusted √ (07042011) & measurement repeated. Humidity inside the tolerance
Regarding to statement √ (29032011) from KNORR (dated 27 March 2011)
28 March 2011 56
List of standard
Will add to the Vehicle record book
√ (09082011)
57
Emergency Door opening cock
- protection cover not yet installed
protection against unauthorized installed according to PT INKA Door proposal
√ (07092011)
58
Driver Cabs equipment
- First Aid box not yet install for each cabin
install before start of dynamic test
√ (07062011)
59
Driver Cabs equipment
- Add in the check sheet (chapter "Safety Relegated Equipment")
60
List of safety relevant calculation & investigation
- Add summary of safety relevant calculation and investigation (FMECA) to type test folder
Amendment to the existing list, see list of deviations.
√ (09082011) will add the list to the folder type test
√ (22112012)
definition of solution
√ (07092011)
29 March 2011 61
Door lock from inside
- Function of each door is not given according to the technical specification point 9.4.2
safety operation is not given
62
Door lock from inside
- Label "Door Out Operation - Please use the next door")
63
Door switch on driver desk
- Push button for door system is not correct function
safety relegated issue
correction of installation
√ (07062011)
submit for information and file as safety related document
√ (22112012)
responsible by PT. KA
n.a.
Closed for PT. INKA
30 March 2011 64
Automatic Coupler
- certification of the absorption of the energy until 7 km/h without damage of the carbody structure is requested
result of first article inspection of coupler
65
Main lighting passenger room
- Type test of brightness of 200 lux at 200 mm above the aisle floor
compilation of the specification and measurement on train set 3
n.a.
√ (04042011)
31 March 2011 66
Pneumatic Static Test of the braking system
- Measurement of AW0 & AW3 outside of tolerance
repeat measurement & clarification of tolerance
67
Door emergency handle
- update of corresponding drawings
submission of change request no change request necessary
completion and identification of the change request
√ (16022012)
68
Ground contact
- ground contact cable are outside of the loading gauge
re-check of fitting and length correction
correction and check of loading gauge
√ (09082011)
69
Battery Box
- Lock system of the cover is too loose
Adjustment of the lock mechanism and check of the design
70
Car cover, rear ends
- aligning of the cover in the line
71
Filter box (door)
- draining hole missing
335433966.xls
√ (16022012)
√ (07062011) adjustment
water can not drain
Page 4 of 7
redesign
√ (07062011) modified
√ (12052011)
22.11.2012
No
Audited Item
Open Item
Remark
Action by PT. INKA / Result in progress
installed
Status Close √ (12052011)
72
Fitting of the main air pipe on the car
- retrofit of an additional bracket
73
Driver's desk
- door panel description, command left on the right side of the panel, command right on the left side of the panel
Design according to the drawing,
agreement and acceptance changed by PT. KAI necessary (deviation of Indonesia regulations)
√ (12052011)
74
Main switch box
- Isolated stick
Fitting in the box or definition another location
definition of fitting location
√ (07092011)
75
Main switch box
- Isolated stick
Add in the list of safety related equipment
compilation of the check sheet of components installation for TS1 as amendment (see also point 59)
√ (09082011)
- Loading gauge inspection
Check sheet of loading gauge move from complete to incomplete
- Paint fixed up the complete roof
Prepared surface too smooth or not rough
01 April 2011 76
Vehicle Record Book
please see point 68
√ (04042011)
04 April 2011 77
78
Roof : TC2, M2, M1, TC1
Roof : M2, M1
- Brake resistor
repainted (surface preparation with sand blasting according to the surface sample)
√ (07092011)
NCR missing (must add at vehicle record book) √ (07092011)
washer of the protection cover rusted clean, fitting screws and anti corrosion protection
79
Roof
- AC units
rusted location on the roof
clean, sealing and anti corrosion protection
√ (07092011)
check and repair
√ (21092012)
06 April 2011 80
Door TC2
- Right door (number 3) has noise when moving
81
Air Conditioner
- change request by Konvekta is requested
Currently, Konvekta exchange all fans. Konvekta has to notify the reason of measurement
requirement of changing request by Konvekta
Engineering
Dynamic test on 15.05.2011 (first test run) 82
Articulation area M1 - M2
- Tapping noise from the articulation area
surmise: ungreased joint of the permanent coupler
Check of the area and grease of the articulated joints and recheck of the noise
√ (07092011)
83
Emergency light
- function of the emergency light is not given.
Regarding to the Indonesia rules one lamp of each door must be also switched on in the emergency case. So in the KRL train must be switched on 6 lamps per car.
Investigation of the caution and re-inspection.
√ (16022012)
84
Condensed water in the passenger rooms
- Strong water condensation on the ceiling
check of the AC control system and adjust of the cooling curve. Monitoring during the dynamic tests.
√ (21092012)
85
Test of the thermal capacity on the brake pads
- Investigation of the influence of the brake temperature of the brake pads and the wheels is requested.
335433966.xls
The microstructure of the wheels may not change.
Page 5 of 7
Agreement with KNORR and evaluation of the results in the record sheets
22.11.2012
No
Audited Item Handrails and connection pieces of the stanchion
86
Open Item
Remark
Action by PT. INKA / Result
- edge particles and peeled surface film
Cleaning and exchange of damaged parts
- M1 middle door right: water drops via the door mechanism in the passenger room
investigation of the reason of strong water flow and optimize of the AC controlling.
Status Close √ (16022012)
Dynamic test on 16.05.2011 87
Condensed water on door mechanism
√ (03052012) monitoring during dynamic test (see point 105)
88
Journey time check
- Objective for the type test: to verify the ability of the vehicle to meet the specified running schedules and energy consumption
Recommendation: Carrying out during the multiple operation test
Implementation in to the type test procedure, carrying out and evaluation.
√ (07092011)
89
Air systems – compressor duty cycle
- Objective according to the vehicle specification point 11.1.3: to verify that the installed compressor/s can deliver the required amount of air to meet all system requirements
Recommendation: Carrying out during the type test of TS2
Implementation in to the type test procedure, carrying out and evaluation.
√ (07092011)
21 May 2011 90 Under frame area near the movable step.
- Using of overlong screws.
Regarding to the remarks during the inspection on Check the function and 31st of May, see also Email 110420-MZ-INKA-Anti_Skid screw material, shorten the repairing progress. screw and protect the surface.
√ (07092011)
91
Movable Step
- Corrosion of the shims (leveling of the steps).
Regarding to the remarks during the inspection on Repair. 31st of May, see also Email 110420-MZ-INKA-Anti_Skid repairing progress.
√ (07092011)
92
Inspection and Test plan
- Add the quality measures for the Anti Skid Painting on the roof.
Recommendation: Add the chapter 5.
PI-295-003-002, rev. B
√ (09082011)
At each track joint, the coupler head spring up (additional noise).
Recheck of the design.
√ (07092011)
Investigation of the function (check in procedure testing)
√ (09082011)
Dynamic test on 07.06.2011 93
Automatic Coupler
Vertical movement of the coupler head is very smooth-running.
94
Crawl Mode (Train Washing)
Reset function not clear described. (at switch off of the train washing button the function will be not released).
95 96
Functional Label (train washing) Passenger room
"i" letter Missing
97 98
Passenger room Passenger door
Door cover (TV)
99 100 101
Passenger room Passenger room Windows
102 103
Driver Cabs Door handle
104 105
lock of driver door roof
106
Cable isolation
Baggage rack
Sealing rubbers of the door windows are deformed ( e.g. M1, TC2) Inside the train
Change the label re-adjustment of the baggage racks are necessary in all adjusting the Level, repair cars crack and repainting short the screw could be serial failure surmise: high temperature variation
Change repainting
windows in TC2 sealing rubber is not correct installed Paint crack on door and at door panel
investigation and repairing
TC1 screw of handle missing Hole on the roof at M1 near pantograph
√ (16022012) √ (22112012)
monitoring, investigation (repair or change)
M1 door number 4 (LCD cover screws lost) door of panel in each car is crack (painting)
M1, M2 and TC2 rusted (screw and washer)
√ (16022012) √ (16022012)
√ (07092011) √ (16022012) √ (21092012)
repainting Change screw and washer
√ (16022012) √ (21092012)
Add screw Monitoring and Repainting
√ (07092011) √ (07092011)
Sealing and repair
√ (07092011)
Repair
√ (07092011)
Cable isolation in M1 damaged (on the roof) 107
Cable protection
335433966.xls
Shrinking hose of two cables are deformed and broken, near pantograph (M1) damage Page 6 of 7
22.11.2012
No
Audited Item
Open Item
Remark
Action by PT. INKA / Result
Status
Missing paint
exchange / repair roughness and re-painting
Close √ (07092011) √ (07092011)
110 Ground contact 03 August 2011 111 destination indicator (Tc1& TC2)
Retrofit of the brackets according to TS2
Modification
√ (16022012)
112
dynamic type test
add spec. Requirement 3.6.3: 8 car unit must push/pull away another 8 car unit
113
Check Sheet of Component Installation
equipment for manual lifting/lowering of pantograph is not mentioned and not install
114
Check Sheet of Component Installation
116
108 109
Cable brackets Roof driver's cab
Corrosion of the brackets
condense water inside
open item from Depok (June 2011)
investigation & monitor, NCR - add requirement in dynamic type test plan - add instructions to driver's manual
√ (07092011)
Spec. Chapter 10.1.2 INKA installed additional tank to lower / lift pantograph
tested on TS3
√ (07092011)
equipment for manual release of mechanical brake is not mentioned and not install
device available at each parking brake cylinder. Device on first and last bogie is mounted outside drivers cab
installation according specification
√ (22112012)
Complete Train
all pneumatic valves must be protected against unauthorized use
according to specification not necessary
protect with wire
√ (16022012)
117
preventive maintenance schedule
not available to consultant
submit preventive maintenance schedule
√ (11082011)
118
maintenance records
not available to consultant
submit existing maintenance records
√ (07092011)
Water from Aircon (and rain) is going uncontrolled down from roof. The existing rain gutter covers door only and is far too small for conditions in Indonesia
re-design rain drain
√ (03052012)
incoming water cannot go out because 1 (one) drainage tube (right side) is missing
check all trains and install missing drainage tube
√ (07092011)
the standard driver's key is too big to operate mechanical door lock
revise design or talk to PT KAI / KRL about using another key
defect
replace
04 November 2011 119 carbody TC2 and drivers cab
120
carbody TC2 door 3
13. February 2012 121 mechanical door lock
122
indicator lamp of parking brake
Open Item Train Open Item TOTAL Open Item closed/deleted open items
335433966.xls
√ (07092011)
122 69 191 117
Page 7 of 7
22.11.2012