Training Plan Tile Setting Nc II

October 12, 2017 | Author: efs | Category: Tile, Stairs, Safety, Nature
Share Embed Donate


Short Description

training plan...

Description

Training Materials, tools and equipments for Tile Setting NC II TOOLS QTY. ITEM

EQUIPMENT QTY. ITEM

MATERIALS QTY. ITEM Glazed wall tiles (20 25 boxes cm x 20 cm) Vitrified floor tiles (20 25 boxes cm x 20 cm) Mosaic tiles (12” x 150 pcs. 12”)

5 pcs.

Notched trowel

2 pcs.

Angle grinder

2 pcs.

Tile cutter

25 sets

PPE

25 pcs.

Pull- push Rule

5 pcs.

Tile Nipper

15m

Level Hose

5 pcs.

Plumb bob

1 bag

5 pcs.

Spirit level

1 pcs.

5 pcs.

Tri-square (12”)

25 pcs

30 kilos

Tile adhesive Cement Tile plastic spacer Sanding Stone(Carburandum) Pencil

5 pcs.

Rubber squeegee

25 pcs.

5 pcs.

Rubber mallet

10 pcs.

10 pcs

Pointing trowel

5 rolls 1 roll

Tile grout (match with the tiles) Foam Tile trim(color match with wall tiles) Nylon string # 50 Nylon string # 12

1 kilo

Cotton rags

5 pcs.

Water pail assorted 3”and 4” Concrete Nail 1” CWN

5 kilos

5 pcs

Diamond Cutting Disc Cold Chisel

5 pcs

Claw Hammer

2 pcs

½ kls 1/4kls

NOTE: The number of cement or adhesive and tiles and its sizes (for floor and wall tile) will depend on the actual number needed for the target output plus the tiles needed for assessment. PPE includes: 1. Hand gloves ( rubber) ung ginagamit pagnaglalaba 2. Goggles 3. Hard hat ( if available) 4. Dust Mask

Trainees’ Training Requirements Basic Competency

Training Activity/Task

TRAINING PLAN Qualification: TILE SETTING NC II Nominal Duration: 82hrs Facilities/To Mode of Staff/Person ols and Training Concerned Equipment

Venue

Assessment Method

Date and Time 18hr s

Common Competency

24hr s

CORE COMPETENCY

40hr s

1. LAY AND REPAIR WALL AND FLOOR TILES

32 hrs

1.1 Plan and 1.1 Secured and prepare for interpreted Work work instruction in line with job requirements

1.2 Identified Safety and quality requirements in line with Occupational Safety and Health Standards (OSHS) and company standard operating procedures

Self-pace Individualize training method Group Structured training method

Trainer (Efren G. Gayanes) Trainees

Module on blue print reading; CBLM; PPT, Blue Print

Contextual Observation learning with oral area/Lear Questioning ning resource area

Self-pace/ Industry immersion Individualize training method

Trainer (Efren G. Gayanes) Trainees

PPT,CBLM, other reference materials/

Contextual learning area workplace On site (constructi on site)

Observation with oral questioning/ demonstration

1.2 Lay out tiling job

1.3 identified Material tiles, tools and equipment in accordance with job requirements

Self-pace/ Industry immersion Individualize training method Group Structured training method

Trainer (Efren G. Gayanes) Trainees

CBLM; PPT; other reference materials/ actual tools and equipment illustration

Contextual learning area

2.1 checked Area(s) to be tiled in line with job requirements

Self-pace Individualize training method Group Structured training method Demonstration Self-pace Individualize training method Group Structured training method Self-pace Individualize training method Group Structured training method

Trainer (Efren G. Gayanes) Trainees

Module on Lay outing CBLM, PPT, Lay outing Tools

Workplace Demonstration area/ On /observation site with oral questioning

Trainer (Efren G. Gayanes) Trainees

Module on Tile laying procedures, CBLM, PPT, Tile laying Tools

Working area/ On site

Demonstration /observation with oral questioning

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT, Tools for mixing

Working area/ On site

Demonstration /observation with oral questioning

Self-pace Individualize

Trainer (Efren G. Gayanes)

CBLM, PPT, Video clip,

Working area / On

Demonstration /observation

2.2 Laid out Tiles in line with specifications

1.3 Install wall tiles

3.1 Prepared Cement or cement based adhesive according to manufacturer’s instructions or recommendation then applied to tile / wall surface 3.2 Prepared and installed Tiles with

Observation with oral questioning/ demonstration

guide / batterboard set to level alignment

training method Group Structured training method

Trainees

Tools for tile installation

site

with oral questioning

3.3 Checked Horizontal joint for straightness and checked tile edges and surface for alignment

Self-pace Individualize training method Group Structured training method

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT, Video clip

Working area/ On site

Demonstration /observation with oral questioning

3.4 Fixed Tiles to alignment retaining designed pattern to specifications

Self-pace Individualize training method Group Structured training method

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

3.5 Shown even margins are around openings, frames and fittings, where applicable

Self-pace Individualize training method Group Structured training method

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

3.6 Installed Special cut tile to create a square corner in accordance with drawings and specifications, where applicable

Self-pace Individualize training method Group Structured training method

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

1.4 Cut tiles

3.7 Finished Vertical tiles according to plumbness and square corner requirements

Self-pace Individualize training method

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

3.8 Maintained All joints straight and uniform in width considering allowance for tolerance of tile

Self-pace Individualize training method

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

3.9 Maintained Expansion gaps following specifications 3.10 Polished and cleaned Tiled surface is to Specifications and manufacturer’s recommendations 1.1 Cut Tiles according to required specifications

Self-pace Individualize training method

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT,

Working area/ On site

Self-pace Individualize training method

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning Demonstration /observation with oral questioning

Self-pace Individualize training method

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT, Cutting tools

Working area/ On site

4.2 Cut Recess hole or curve by hand or machine is in required tolerance

Self-pace Individualize training method

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT, Cutting tools

Working area/ On site

Trainer (Efren G. Gayanes)

CBLM, PPT,

Working area/ On

4.3 Prepared Miter joints, Self-pace retaining glazing on miter Individualize

Demonstration /observation with oral questioning Demonstration /observation with oral questioning Demonstration /observation

1.5 Grout space between tiles

with no chips and uniform in size

training method

Trainees

site

with oral questioning

4.4 Prepared Special cut tile in accordance with drawings and specifications, where applicable

Self-pace Individualize training method

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT, working plan

Working area/ On site

Demonstration /observation with oral questioning

4.5 Jolly-edged Tile to form a miter to prevent the tile body from being exposed at the joint

Self-pace Individualize training method

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT, Tile edging tools

Working area/ On site

Demonstration /observation with oral questioning

4.6Applied Safety precautions in line with Occupational Safety and Health Standards

Self-pace Individualize training method

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

5.1 Cleaned and prepared Joints for grouting following manufacturer's specifications

Self-pace Individualize training method

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT, tile cleaning tools

Working area/ On site

Demonstration /observation with oral questioning

5.2 Mixed and applied Grout according to manufacturer's specifications

Self-pace Individualize training method

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT, grout mixing tools

Working area/ On site

Demonstration /observation with oral questioning

5.3 Cleaned and polished Tiles to specifications, removing all dust from surface and joints

Self-pace Individualize training method

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

Self-pace Individualize training method

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

6.2 Made Adjustments to Self-pace ensure spacing is Individualize uniform training method and pattern and alignment are maintained

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT,

Working area/ On site

6.3 Finished area with mosaics level to line, if applicable, surface straight and flat and grout are finished to specifications

Self-pace Individualize training method

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

7.1 Selected Adhesive based on specifications, tile type and climatic condition

Self-pace Individualize training method

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

7.2 Cleaned Surface from residue and protrusions

Self-pace Individualize training method

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

1.6 Install 6.1 Fixed Paper-faced or vertical mosaic mesh-backed mosaics to sheets background with tile adhesive

1.7 Lay floor tiles

7.3 Mixed Adhesive following manufacturer's specifications

Self-pace Individualize training method

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT, mixing tools

Working area/ On site

7.4 Laid Tiles to manufacturer's specifications and expansion gaps maintained between walls and tiles

Self-pace Individualize training method

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT, tile laying tools

Working area/ On site

7.5 Mixed and applied Grout to clean joints and surface according to manufacturer's specifications

Self-pace Individualize training method

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT, grout application tools

Working area/ On site

Demonstration /observation with oral questioning

Self-pace Individualize training method

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT, tile cleaning tools

Working area/ On site

Demonstration /observation with oral questioning

Self-pace Individualize training method

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT,

Working area/ On site

Self-pace Individualize training method

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning Demonstration /observation with oral questioning

7.6 Polished and cleaned Finished tile work according to specifications and manufacturer recommendations 1.8 Tile treads, 8.1 Calculated and risers, steps determined Risers and and steps from concrete steps thresholds / stairs 8.2 Laid out Steps for uniform rise and take even cut on both side

Demonstration /observation with oral questioning Demonstration /observation with oral questioning

8.3 Placed Step riser packing or render support, where necessary, and installed riser tiles according to alignment

Self-pace Individualize training method

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

8.4 Installed Treads in line with the top edge of risers within the required tolerance

Self-pace Individualize training method

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

8.5 Applied Grout to wet joints and finished flush with tiles to a smooth finish.

Self-pace Individualize training method

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

8.6 Cleaned and polished finished tile work and free of pitted, chipped, cracked or scratched tile resulting from laying operation

Self-pace Individualize training method

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

8.7Polished and cleaned tiled surface is to specifications and manufacturer’s recommendations.

Self-pace Individualize training method

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

1.9 Repair damaged tile work

9.1 Performed Damaged tiles removal procedure following established / recommended practices

Self-pace Individualize training method

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT, tile removal tools

Working area/ On site

Demonstration /observation with oral questioning

9.2 Old bedding is cleaned and cleared for placement of replacement tile

Self-pace Individualize training method

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

9.3 Selected and cut replacement tiles, if necessary, following existing pattern and face recommendations.

Self-pace Individualize training method

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

9.4 Fitted and installed Tiles to maintain alignment with joints for uniform spacing

Self-pace Individualize training method

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

9.5 Performed grouting and cleaned tile face from dirt and other residues

Self-pace Individualize training method

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

9.6 Polished and cleaned Tiled surface to specifications and manufacturer’s

Self-pace Individualize training method

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

1.10 Clean up

10.1 Cleaned work area as per OSHS requirements

Self-pace Individualize training method

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT,

10.2 Disposed waste and unwanted materials following company standard operating procedure and OSH and environmental requirements

Self-pace Individualize training method

10.3 Stored / stacked unused materials are according to enterprise procedures 10.4 Cleaned and maintained tools and equipment are following manufacturer's specifications

Self-pace Individualize training method

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT,

Self-pace Individualize training method

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT,

Staff/Person Concerned

Facilities/To ols and Equipment

Trainees’ Training Requirements

Training Activity/Task

Trainer (Efren G. Gayanes) Trainees CBLM, PPT,

Mode of Training

Working area/ On site

Demonstration /observation with oral questioning

Working area/ On site

Demonstration /observation with oral questioning

Working area/ On site Working area/ On site

Venue

Demonstration /observation with oral questioning Demonstration /observation with oral questioning Assessment Method

2. TILE CORNER 2.1 Plan and prepare for work

1.1Secured and interpreted Work instruction in line with job requirements

Date and Time 4hrs

Self-pace Individualize training method

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

1.2.Identified Safety and quality requirements in line with Occupational Safety and Health Standards (OSHS) and company standard operating procedures 1.3 Identified Material tiles, tools and equipment in accordance with job requirements 2.2Tile external corners 2.3 Tile internal corners

2.1 Checked set out tiles for specified tolerance of + - 2 mm based on plumbness and levelness. 2.2 Checked external corners for flatness of surfaces and straightness of intersections. 2.3 Installed tile trim to maintain external returns and tile trim is fitted to both corners.

Self-pace Individualize training method

Self-pace Individualize training method

Self-pace Individualize training method

Self-pace Individualize training method

Self-pace Individualize training method

Trainer (Efren G. Gayanes) Trainees

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

Trainer (Efren G. Gayanes) Trainees

Trainer (Efren G. Gayanes) Trainees

Trainer (Efren G. Gayanes) Trainees

2.4 Installed tiles without voids in tile bed and fully bedded to maintain alignment to specifications 2.5 Maintained corners square and finished to specifications. 2.6 Polished and cleaned tiled surface to specifications and manufacturer’s recommendations. 3.1 Checked internal corners for flatness of surfaces and straightness of intersections. 3.2 Fitted and cut Tiles, where required and installed to one wall maintaining alignment to set out and specifications.

Self-pace Individualize training method

Self-pace Individualize training method Self-pace Individualize training method

Self-pace Individualize training method

Self-pace Individualize training method

Trainer (Efren G. Gayanes) Trainees

Trainer (Efren G. Gayanes) Trainees Trainer (Efren G. Gayanes) Trainees

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

Trainer (Efren G. Gayanes) Trainees

Trainer (Efren G. Gayanes) Trainees

3.3 Tiles are fitted and cut, where required and installed abutting adjacent wall tiles to line, set out and specifications. 3.4 Made joints for abutting tiles in accordance with designed margin for grouting or for expansion joint, where applicable to specifications. 3.5 Installed tiles to cove tiles or trim and finished to alignment and specifications. 3.6 Polished and cleaned tiled surface to specifications and manufacturer’s recommendations. 2.4 Clean up

4.1 Cleaned work area as per OSHS requirements

Trainer (Efren G. Gayanes) Trainees Self-pace Individualize training method

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

Trainer (Efren G. Gayanes) Trainees Self-pace Individualize training method

Self-pace Individualize training method

Self-pace Individualize training method Self-pace Individualize training method

Trainer (Efren G. Gayanes) Trainees Trainer (Efren G. Gayanes) Trainees

Trainer (Efren G. Gayanes) Trainees

4.2 Disposed waste and unwanted materials of following company standard operating procedure and OSHS requirements 4.3 Stored / stacked unused materials according to enterprise procedures 4.4Cleaned and maintained tools and equipment following manufacturer's specifications

Trainees’ Training Requirements

Training Activity/Task

Self-pace Individualize training method

Self-pace Individualize training method

Self-pace Individualize training method

Mode of Training

Trainer (Efren G. Gayanes) Trainees

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

Trainer (Efren G. Gayanes) Trainees

Staff/Person Concerned

CBLM, PPT,

Working area/ On site

Facilities/To ols and Equipment

Venue

Demonstration /observation with oral questioning

Assessment Method

3. TILE CURVED SURFACES 3.1 Plan and 1.1Secured and prepare for interpreted Work work instruction in line with job requirements

Date and Time 4hrs

Self-pace Individualize training method

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

1.2.Identified Safety and quality requirements in line with Occupational Safety and Health Standards (OSHS) and company standard operating procedures 1.3 Identified Material tiles, tools and equipment in accordance with job requirements 3.2 Tile curved wall and floor surfaces

2.1 Set out level line around the wall by intermediate marking using leveling equipment. 2.2 Set out location of tiles to determine balanced design and cutting requirements, if necessary.

Self-pace Individualize training method

Self-pace Individualize training method

Self-pace Individualize training method

Self-pace Individualize training method

2.3 Made template to form accurate curve line to tiled surface around the wall.

Self-pace Individualize training method

2.4 Determined method for installing tiles

Self-pace Individualize

Trainer (Efren G. Gayanes) Trainees

Trainer (Efren G. Gayanes) Trainees

Trainer (Efren G. Gayanes) Trainees

Trainer (Efren G. Gayanes) Trainees

Trainer (Efren G. Gayanes) Trainees Trainer (Efren G. Gayanes)

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

CBLM, PPT,

Working area/ On

Demonstration /observation

with identification of location of the first tile. 2.5 Prepared cementbased adhesive following manufacturer's specifications. 2.6 Installed guide board to level set out and template curve to specifications. 2.7 Maintained minimum voids in mortar tile beds and tiles are fixed, plumb (wall), and flush. 2.8 Laid floor tiles to set out grid with perimeter tiles marked and cut to fit curve wall. 2.9 Mixed tile grout with water and applied to joints according to specifications, to provide flush and smooth finish.

training method

Self-pace Individualize training method Self-pace Individualize training method

Self-pace Individualize training method

Self-pace Individualize training method

Self-pace Individualize training method

Trainees Trainer (Efren G. Gayanes) Trainees Trainer (Efren G. Gayanes) Trainees Trainer (Efren G. Gayanes) Trainees

Trainer (Efren G. Gayanes) Trainees

site

with oral questioning

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

Trainer (Efren G. Gayanes) Trainees

2.10 Polished and cleaned tiled surface to specifications and manufacturer’s recommendations. 3.3 Tile circular volume, wall and arches

3.1 Set out, cut, positioned and checked template to maintain conformity to tile surface for curve. 3.2 Positioned and installed guide board to line to maintain uniform spacing. 3.3 Marked and cut tiles, where applicable, installed into place to specifications. 3.4 Installed tiles on walls and plumb, maintaining levels and curvature of wall to specifications. 3.5 Installed tiles to archways, maintaining line and curvature to specifications.

Self-pace Individualize training method

Self-pace Individualize training method Self-pace Individualize training method Self-pace Individualize training method Self-pace Individualize training method

Self-pace Individualize training method

Trainer (Efren G. Gayanes) Trainees

Trainer (Efren G. Gayanes) Trainees

Trainer (Efren G. Gayanes) Trainees Trainer (Efren G. Gayanes) Trainees Trainer (Efren G. Gayanes) Trainees

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

CBLM, PPT,

Working area/ On site

CBLM, PPT,

Working area/ On site

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

Demonstration /observation with oral questioning Demonstration /observation with oral questioning

3.6 Mixed tile grout with water and applied to joints of tiled surfaces and tiled surface is finished to specifications. 3.7 Polished and cleaned tiled surface to specifications and manufacturer’s recommendations. 3.4 Install 4.1 Checked Surface mosaic tiles on from protrusions and a circular from plastering column imperfections. 4.2 Prepared Template for column tiling diameter to specifications. 4.3 Applied mortar evenly to the required tiling diameter thickness and finished to curve based on prepared template specifications.

Self-pace Individualize training method

Self-pace Individualize training method

Self-pace Individualize training method Self-pace Individualize training method

Trainer (Efren G. Gayanes) Trainees

Trainer (Efren G. Gayanes) Trainees

Trainer (Efren G. Gayanes) Trainees Trainer (Efren G. Gayanes) Trainees

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

Trainer (Efren G. Gayanes) Trainees Self-pace Individualize training method

4.4 Positioned and installed guide board to maintain level line.

3.5 Clean up

4.5 Mosaic tiles are installed to column maintaining even spacing and level finish to specifications. 4.6 Mixed tile grout with water and applied to tiled surface and tile surface is finished to specifications. 4.7 Polished and cleaned tiled surface to specifications and manufacturer’s recommendations 5.1 Cleaned work area as per OSHS requirements 5.2 Disposed waste and unwanted materials of following company standard operating procedure and OSHS requirements

Self-pace Individualize training method

Self-pace Individualize training method

Self-pace Individualize training method Self-pace Individualize training method Self-pace Individualize training method

Self-pace Individualize training method

Trainer (Efren G. Gayanes) Trainees Trainer (Efren G. Gayanes) Trainees

Trainer (Efren G. Gayanes) Trainees Trainer (Efren G. Gayanes) Trainees Trainer (Efren G. Gayanes) Trainees

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

Trainer (Efren G. Gayanes) Trainees

5.3 Stored / stacked unused materials according to enterprise procedures 5.4Cleaned and maintained tools and equipment following manufacturer's specifications

Self-pace Individualize training method

Self-pace Individualize training method

Trainer (Efren G. Gayanes) Trainees

Trainer (Efren G. Gayanes) Trainees

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

CBLM, PPT,

Working area/ On site

Demonstration /observation with oral questioning

Conformed: Training Supervisor

EFREN G. GAYANES Trainer

View more...