Time at Large
July 22, 2022 | Author: Anonymous | Category: N/A
Short Description
Download Time at Large...
Description
Time at large Time for completion completion of the Works Works is said to be “at large” large” when the Contractor’s obligation to complete the Works within the specied time or certied extended time is lost. That is to say, the Contractor is no longer bond by the contract pro!ision that he has to complete the Works by a certain date or extended date. The obligation of the Contractor is then to complete the Works Works within what is called “reasonable time”. Time for completion completion of the Works Works can be said to be, or or made, “at large” in the following !e sitations" (a) No time for completion is fixed in the contract; c ontract; (b) Improper administration or misapplication of the extension of time provision in the contract; (c) Waiver Waiver of time requirements; (d) The Employer’s interference in the certification process; (e) When the extension of time provision does not confer poer on the En!ineer"#rchitect"$%&% to extend the time for completion of the Wor's on the occurrence of event or events hich fall(s) ithin the obli!ation of the Employer%
The signicant conse#ence of time for completion b being eing at large is that that the li#idated damages clase in the contract becomes inoperati!e and the $mployer cannot rely on this li#idated damages clase to impose li#idated damages onto the Contractor.%& Contractor.%& The other signicance when time for completion is at large is that the original completion date or the contractally certied extended completion date no longer binds the Contractor Contractor.. The Contractor’s remaining obligation is to complete the Works within what is called “reasonable “reasonable time” the meaning of which we now trn. 1. NO TIME NOR DATE FIXED IN THE CONTRACT
Completion on time is important in modern construction contracts. If the project is late the Employers return on his investment is reduced and the Contractors costs frequently increased. Many construction contracts and Standard Forms of contract usually place an obligation on the contractor to complete the wors by a specified completion date or within a specified period. If no date or period is fi!ed by the contract then the objective intention of the parties must be ascertained. In the case of a contract under the Supply of "oods and Services #ct $%&'( if the date is not fi!ed by a course of dealing between the parties( a term will be implied that the contractors obligation is to complete within a reasonable time )Section $*)$++.
2. Time or Date Ceases to Apply
'any e!ents may pre!ent completion on time inclding ad!erse weather conditions, labor or material shortages, strikes or local distrbances, lack of information or plain hman error, and interference, hindrance or pre!ention by the $mployer. $mployer. The rights and remedies of the parties depend pon the apportionment of liability for the delay and the express terms of the contract which may limit the remedies otherwise a!ailable. (f part of the delay in completion is at the risk of the contractor, then to that extent the $mployer is entitled to damages for breach of the obligation to complete on time. (f the contract makes proper pro!ision for li#idated damages, then the measre of damages is the stated sms of li#idated damages. (f on the other hand the delay is at the risk of the $mployer then the contractor will be entitled to damages for breach of the particlar obligation casing the delay. delay. (f instead the risk e!ent was not cased by breach of contract then the contractors remedy will only be as stated in the contract. )tandard forms of contract apportion liability for delay throgh th rogh extension of time clases. (f the contractor is entitled to an extension of time for an expressly stated e!ent, then the $mployer carries the risk, otherwise it lies with the contractor. Which party carries the risk of the additional cost for the delay will depend pon the other terms of the contract. The wording of of the extension of time clase clase will determine determine when and the extent to which the risk of delay passes from the contractor to $mployer. $mployer. The description of the particlar e!ent is all important. (f notices and*or sbstantiation are a condition of an entitlement to an extension of time, then the risk will only pass to the $mployer if and*or when the contractor pro!ides that information. )ome e!ents that case delay are not nder the control of either party, sch as weather or local distrbances. They are netral e!ents. The e!ent may howe!er be cased by one of the parties. The $mployer may for instance order extra work or otherwise !ary the contract. The $mployer, in breach of contract, may not gi!e possession of the site or may not pro!ide information at a particlar date to allow the contractor time. The conse#ence maywhich be to wold so delay contractor thatto hecomplete is frtheron delayed by the netral e!ent, n not otthe ha!e occrred bt for the original delay. +oth the order of !ariations and the $mployers breaches of contract are acts of pre!ention that may delay the contractor. contractor. (f the extension of time clase does not entitle the contractor to ha!e the time for completion extended for delays actally cased by sch acts of pre!ention, then the contractor will no longer be nder an obligation to complete within the specied period. is obligation is instead only to complete within a reasonable period. Time is said to be at large. What is a reasonable time is a #estion of fact and all the factal circmstances mst be taken into accont.
(f the contract pro!ides for the dedction of li#idated damages shold the contractor o!errn the time for completion, then the pro!ision will no longer be enforceable when time is at large. There is no specic certain date from which li#idated damages can rn. The $mployer will then only be entitled to damages that he can pro!e in the normal way if he can establish that the contractor has not completed within a reasonable time. 4. Acts of Prevention
(n modern constrction contracts, extension of time clases are careflly drafted to entitle the contractor to extension of the period of completion for any acts of pre!ention by the $mployer. $mployer. The extension of time clases are for the benet of the $mployer.. They keep ali!e the contractors obligation to complete by a specied $mployer date and preser!e the $mployers right to dedct li#idated damages for breach of that obligation. (n order to protect the $mployers right to li#idated damages, $xtension of Time Clases need to pro!ide a contractal remedy for the expected range of acts of pre!ention by the $mployer. 5. Waiver or Election
Time may become become at large if if the original obligation obligation to complete is wai!ed. (n Charles Rickards td v !ppenheim "#$5%& , a -olls -oyce motor car was not bilt by the agreed deli!ery date, bt new dates agreed. $!entally, ppenheim ga!e written notice to -ickards stating that nless he recei!ed the car by a rm date, for weeks away, he wold not accept it. The car was not deli!ered within the time specied and was not completed ntil some months later when ppenheim refsed to accept it. The Cort of /ppeal held that he was 0stied in doing so. /fter wai!ing the initial stiplation as to time, ppenheim was entitled to gi!e reasonable notice making time of the essence again, and on the facts the notice was reasonable. This principle applies applies to constrction contracts. ((f, f, becase of wai!er, ttime ime becomes 1at large2, the $mployer can gi!e the contractor reasonable notice to complete within a xed reasonable time, ths making time of the essence againTaylor v 'ro(n "#)*$&. The $mployer will ha!e lost his right to li#idated damages so that if the contractor fails to complete by the re!ised agreed date the $mployer will be left with the remedy of general damages. (t is not clear whether the $mployer can make time of the essence, if it was not pre!iosly so. +. ,ail-re of Contract-al achinery
(f the time or date for completion is e3ected by e!ents which entitle the contractor to an extension of time, bt the contractal machinery can no longer operate, then time is at large. The circmstances will be rare
The principle of time at lar/ea
(n short, the common law principle of “time at large” is this" if a delay e!ent occrs that is the employer’s falt and the contract does not allow the completion date to be extended in that e!ent, the original completion date, and any liquidated damages regime, fall away and time is pt “at large”. This means that the contractor has a reasonable time to complete the works and the employer is no longer entitled to claim li#idated damages for delay 4althogh it may still be able to claim general damages5. (t is an application of the “pre!ention principle”, that a party may not insist on compliance with a contractal obligation in circmstances where it has itself pre!ented sch compliance. (f the works are delayed becase of e!ents for which the client is responsible 4an act of pre!ention5 or by agreed netral e!ents, the contracts will generally pro!ide for an extension of time to be granted, changing the completion date 4see rele!ant e!ents5. (f contracts did not allow the constrction period to be extended nder sch circmstances, then time wold be at large. The client client wold wold then not be able to claim li#idated damages damages from the contractor contractor as as there wold be no date against which they cold be calclated and the contractor contractor wold wold then only ha!e to complete the works in a 2reasonable2 time. The client client wold wold only be entitled to damages damages if they cold established that the contract was not n ot completed within a reasonable time.
Constrction contracts will contracts will sally inclde a date by which the works described in the contract shold be completed. This is generally the date by which practical completion mst completion mst be certied. The phrase 6time at large’ large’ describes the sitation where where there is no date for completion,, or where the date for completion has completion completion has become in!alid. The contractor contractor is is then no longer bond by the obligation to complete the works by a certain date. Time can become become at large becase becase there is no clear completion date specied date specied in the contract, or can be a sitation that arises as a reslt of e!ents 4typically by agreement of the parties or by failre of the contract 6machinery’5, or if the contract does not allow the constrction period to be extended. (t is not ncommon on constrction pro0ects that the works are not completed by the date for completion. completion. (f this is becase of delays for which the contractor contractor is is responsible, then then the contract will generally inclde a pro!ision for them to pay li#idated damages to damages to the client client.. These are pre7determined damages damages based based on a calclation of the actal loss that the client client is is likely to incr if the contractor contractor fails fails to meet the completion date. date. )ome contracts re#ire that a certicate of non7 completion is completion is issed as a pre7re#isite to dedcting li#idated damages. damages.
(f the works are delayed becase of e!ents for which the client client is is responsible 4an act of pre!ention5 or by agreed netral e!ents, the contracts will generally pro!ide for an extension of time to time to be granted, changing the completion date 4see date 4see rele!ant e!ents5. e!ents 5. (f contracts did not allow the constrction period to be extended nder sch circmstances, then time wold be at large. The client client wold wold then not be able to claim li#idated damages from damages from the contractor contractor as as there wold be no date against which they cold be calclated and the contractor contractor wold wold then only ha!e to complete the works in a 2reasonable2 time. The client client wold wold only be entitled to damages damages if if they cold established that the contract was not completed within a reasonable time. (t is important therefore that clases describing rele!ant e!ents co!er e!ents co!er all necessary e!entalities, otherwise if an e!ent occrs that is not co!ered, time will be at large. 8+ Constrction contracts generally contracts generally inclde a pro!ision re#iring that the contractor contractor proceeds proceeds 6reglarly 6reglarly and diligently’ diligently’ irrespecti!e of whether it is apparent that the completion date will date will be achie!ed. 8+ 8$C contracts refer contracts refer to 6compensation 6compensation e!ents’ e!ents’ rather than 6rele!ant 6rele!ant e!ents’. e!ents’. +oth parties mstshold gi!e early anything that may delay the works, or a!oid increase costs. They thenwarning h old an of hold early warning meeting to discss how to or mitigate impacts on the pro0ect. (n the case of a compensation e!ent, e!ent, if the contractor contractor fails fails to gi!e early warning of a possible delay to the works, or increase in costs, they will only be compensated for e3ects that wold ha!e remained e!en if they had gi!en early warning.
7.Reasonable Time
The question of hat duration of time is reasonable is one of fact not la% It is a question of fact ta'in! into consideration all relevant factors and circumstances obectively assessed% *e!rettably as it is this is one of the elastic concepts for hich there ill be no fixed anser% What constitute reasonable time has to be considered in relation to circumstances hich existed at the time the contract obli!ations are performed but excludin! circumstances hich are under the control of the party performin! those obli!ations normally the +ontractor in our case% c ase%
7. Reasonable Time
If time does become ,at lar!e- the contractor-s obli!ation is to complete ithin a reasonable time% What constitutes a reasonable time is a question of fact% The principles to be applied are those in .antland /ic' v *aymond 0 *eid 123456% What constitutes a reasonable time has to be considered in relation to circumstances hich existed at the time hen the contract obli!ations are performed but excludin! circumstances hich ere under the control of the contractor% con tractor% In 7ritish $teel +orporation v +leveland 7rid!e 0 En! +o 124326 897:*2 :ord
View more...
Comments