Time and Money Claim Provisions FIDIC

July 23, 2019 | Author: Tharaka Kodippily | Category: General Contractor, Employment, Insurance, Cost, Economics
Share Embed Donate


Short Description

Time and Money Claim Provisions FIDIC are addressed in this report. international federation of consulting engineers...

Description

BE-4605 Claims Management

Provisions for Time and Money Claims in FIDIC Red Book 1999

1. Introduction FIDIC Red Book of 1999 edition has included various provisions for time and money claims for both Employer and for the Contractor. As quantity surveyors it is important to clearly identify the Clauses which give entitlement for Claims. Such provisions are listed and briefly explained below.

2. The Contractor’s Claims Most claims are made by the Contractor and may be claim for extension of time for completion of  Works and/or reimbursement of money that has been spent or will be spent. Claim for additional time most commonly result in a Claim for additional money as well, which shall be submitted as a separate Claim. Sub Clause Nr

1.9

Clause Title

Provisions for Time and/or Money

Delayed Drawings

If the Contractor suffers delay and/or incurs Cost as a result of  or  a failure of the Engineer to issue the notified drawing or 

Instructions

instruction within a time which is reasonable and is specified in the notice with supporting details, the Contractor shall give a further notice to the Engineer and shall be entitled subject to Sub-Clause 20.1 [Contractor’s [ Contractor’s Claims] Claims] to: (a) an extension of time for any such delay, if completion is or  will be delayed, under Sub-Clause 8.4 [ Extension [ Extension of Time for  Completion], Completion], and (b) payment of any such Cost plus reasonable profit, which shall be included in the Contract Price.

2.1

Right of Access

If the Contractor suffers delay and/or incurs Cost as a result of 

to the Site

a failure by the Employer to give any right or possession within such time, the Contractor shall give notice to the Engineer and shall be entitled subject to Sub-Clause 20.1 [Contractor’s Claims] Claims] to: a) an extension of time for any such delay, if completion is or  will be delayed, under Sub-Clause 8.4 [ Extension [ Extension of Time for  Completion], Completion], and (b) payment of any such Cost plus reasonable profit, which shall be included in the Contract Price.

4.6

Co-operation

Department of Building Economics

The Contractor shall, as specified in the Contract or as 1

BE-4605 Claims Management

Sub Clause Nr

Provisions for Time and Money Claims in FIDIC Red Book 1999

Clause Title

Provisions for Time and/or Money

instructed by the Engineer, allow appropriate opportunities for  carrying out work to: (a) the Employer’s Personnel, (b) any other contractors employed by the Employer, and (c) the personnel of any legally constituted public authorities, who may be employed in the execution on or near the Site of  any work not included in the Contract. Any such instruction shall constitute a Variation if and to the extent that it causes the Contractor to incur Unforeseeable Cost. Services for these  personnel and other contractors may include the use of  Contractor’s Equipment, Tempo 4.7

Setting Out

If the Contractor suffers delay and/or incurs Cost from executing work which was necessitated by an error in these items of reference, and an experienced contractor could not reasonably have discovered such error and avoided this delay and/or Cost, the Contractor shall give notice to the Engineer  and shall be entitled subject to Sub- Clause 20.1 [ Contractor’s Claims] to: (a) an extension of time for any such delay, if completion is or  will be delayed, under Sub-Clause 8.4 [ Extension of Time for Completion], and (b) payment of any such Cost plus reasonable profit, which shall be included in the Contract Price.

4.12

Unforeseeable

If and to the extent that the Contractor encounters physical

Physical

conditions which are Unforeseeable, gives such a notice, and

Conditions

suffers delay and/or incurs Cost due to these conditions, the Contractor shall be entitled subject to Sub-Clause 20.1 [Contractor’s Claims] to: (a) an extension of time for any such delay, if completion is or  will be delayed, under Sub-Clause 8.4 [ Extension of Time for  Completion], and (b) payment of any such Cost, which shall be included in the Contract Price.

Department of Building Economics

2

BE-4605 Claims Management

Sub Clause Nr

4.24

Provisions for Time and Money Claims in FIDIC Red Book 1999

Clause Title

Fossils

Provisions for Time and/or Money

The Contractor shall, upon discovery of any such finding,  promptly give notice to the Engineer, who shall issue instructions for dealing with it. If the Contractor suffers delay and/or incurs Cost from complying with the instructions, the Contractor shall give a further notice to the Engineer and shall  be entitled subject to Sub-Clause 20.1 [Contractor’s Claims] to: (a) an extension of time for any such delay, if completion is or  will be delayed, under Sub-Clause 8.4 [ Extension of Time for  Completion], and (b) payment of any such Cost, which shall be included in the Contract Price.

7.4

Testing

If the Contractor suffers delay and/or cost from complying with Engineer’s instructions or as a result of a delay for which the Engineer is responsible, the Contractor shall give the notice to the Engineer and shall be entitled subject to Sub-Clause 20.1 [Contractor’s Claims] and after receiving this notice, the Engineer shall proceed in accordance with Sub-Clause 3.5 [Determination] to agree or determine these matters.

8.4

Extension Time Completion

of  If the Contractor considers himself to be entitled to an for  extension of the Time for Completion, the Contractor shall give notice to the Engineer in accordance with Sub-Clause 20.1 [Contractor’s Claims].

8.5

Delays Caused by If the following conditions apply, namely: Authorities

(a) the Contractor has diligently followed the procedures laid down by the relevant legally constituted public authorities in the Country, (b) these authorities delay or disrupt the Contract or’s work, and (c) the delay or disruption was Unforeseeable, then this delay or disruption will be considered as a cause of  delay under subparagraph (b) of Sub-Clause 8.4 [ Extension of  Time for Completion].

8.9

Consequences of If the Contractor suffers delay and/or incurs Cost from

Department of Building Economics

3

BE-4605 Claims Management

Sub Clause Nr

Provisions for Time and Money Claims in FIDIC Red Book 1999

Clause Title

Suspension

Provisions for Time and/or Money

complying with the Engineer’s instructions under Sub -Clause 8.8 [Suspension of Work ] and/or from resuming the work, the Contractor shall give notice to the Engineer and shall be entitled subject to Sub-Clause 20.1 [Contractor’s Claims] to: (a) an extension of time for any such delay, if completion is or  will be delayed, under Sub-Clause 8.4 [ Extension of Time for  Completion], and (b) payment of any such Cost, which shall be included in the Contract Price.

8.11

Prolonged

Contractor may ,by giving notice to the Engineer, treat the

Suspension

suspension as an omission under clause 13[Variation and Adjustment] of the affected part of the work  If the suspension affects the whole of the works, contractor  may give notice of termination under Sub Clause 16.2 [Termination by Contractor]

10.2

Taking Over of  If the Contractor incurs Cost as a result of the Employer taking Parts

of

Works

the over and/or using a part of the Works, other than such use as is specified in the Contract or agreed by the Contractor, the Contractor shall (i) give notice to the Engineer and (ii) be entitled subject to Sub-Clause 20.1 [Contractor’s Claims] to  payment of any such Cost plus reasonable profit, which shall  be included in the Contract Price.

10.3

Interference with If the Contractor suffers delay and/or incurs Cost as a result of  Tests Completion

on this delay in carrying out the Tests on Completion, the Contractor shall give notice to the Engineer and shall be entitled subject to Sub-Clause 20.1 [Contractor’s Claims] to: (a) an extension of time for any such delay, if completion is or  will be delayed, under Sub-Clause 8.4 [ Extension of Time for  Completion], and (b) payment of any such Cost plus reasonable profit, which shall be included in the Contract Price.

11.8

Contractor Search

Department of Building Economics

to The Contractor shall, if required by the Engineer, search for the cause of any defect, under the direction of the Engineer. Unless 4

BE-4605 Claims Management

Sub Clause Nr

Provisions for Time and Money Claims in FIDIC Red Book 1999

Clause Title

Provisions for Time and/or Money

the defect is to be remedied at the cost of the Contractor under  Sub-Clause 11.2 [Cost of Remedying Defects], the Cost of the search plus reasonable profit shall be agreed or determined by the

Engineer

in

accordance

with

Sub-Clause

3.5

[ Determinations] and shall be included in the Contract Price. 12.4

Omissions

Whenever the omission of any work forms part (or all) of a Variation, the value of which has not been agreed, if: (a) the Contractor will incur (or has incurred) cost which, if the work had not been omitted, would have been deemed to be covered by a sum forming part of the Accepted Contract Amount; (b) the omission of the work will result (or has resulted) in this sum not forming part of the Contract Price; and (c) this cost is not deemed to be included in the evaluation of  any substituted work; then the Contractor shall give notice to the Engineer  accordingly, with supporting particulars. Upon receiving this notice, the Engineer shall proceed in accordance with SubClause 3.5 [ Determinations] to agree or determine this cost, which shall be included in the Contract Price.

13.2

Value

If a change of design which occurred due to value engineering

Engineering

results in a reduction in the contract value of this part, the Engineer shall proceed in accordance with Sub-Clause 3.5 [ Determinations] to agree or determine a fee, which shall be included in the Contract Price. This fee shall be half (50%) of  the difference between the following amounts: (i) such reduction in contract value, resulting from the change, excluding adjustments under Sub-Clause 13.7 [ Adjustments for  Changes in Legislation] and Sub-Clause 13.8 [ Adjustments for  Changes in Cost ], and (ii) the reduction (if any) in the value to the Employer of the varied works, taking account of any reductions in quality,

Department of Building Economics

5

BE-4605 Claims Management

Sub Clause Nr

Provisions for Time and Money Claims in FIDIC Red Book 1999

Clause Title

Provisions for Time and/or Money

anticipated life or operational efficiencies. 13.7

Adjustments for 

If the Contractor suffers (or will suffer) delay and/or incurs (or 

Changes

will incur) additional Cost as a result of these changes in the

in

Laws or in such interpretations, made after the Base Date, the

Legislation

Contractor shall give notice to the Engineer and shall be entitled subject to Sub-Clause 20.1 [Contractor’s Claims] to: (a) an extension of time for any such delay, if completion is or  will be delayed, under Sub-Clause 8.4 [ Extension of Time for Completion], and (b) payment of any such Cost, which shall be included in the Contract Price. 14.8

Delayed Payment

Contractor shall be entitled to receive financing charges compounded monthly on the amount on the amount unpaid during the period of delay. The financing charges shall be calculated at the central bank in the country of the currency of payment. *The contractor shall be entitled to this payment without formal notice or certification and without prejudice to any other  right or remedy.

16.1

Contractor’s Entitlement Suspend

If the Contractor suffers delay and/or incurs Cost as a result of  to suspending work (or reducing the rate of work) in accordance the

Works

with this Sub-Clause, the Contractor shall give notice to the Engineer and shall be entitled subject to Sub-Clause 20.1 [Contractor’s Claims] to: (a) an extension of time for any such delay, if completion is or  will be delayed, under Sub-Clause 8.4 [ Extension of Time for  Completion], and (b) payment of any such Cost plus reasonable profit, which shall be included in the Contract Price.

17.4

Consequences of  If the Contractor suffers delay and/or incurs Cost from Employer’s Risks

rectifying this loss or damage, the Contractor shall give a further notice to the Engineer and shall be entitled subject to Sub-Clause 20.1 [Contractor’s Claims] to:

Department of Building Economics

6

BE-4605 Claims Management

Sub Clause Nr

Clause Title

Provisions for Time and Money Claims in FIDIC Red Book 1999

Provisions for Time and/or Money

(a) an extension of time for any such delay, if completion is or  will be delayed, under Sub-Clause 8.4 [ Extension of Time for  Completion], and (b) payment of any such Cost, which shall be included in the Contract Price. In the case of sub-paragraphs (f) and (g) of  Sub-Clause 17.3 [ Employer’s Risks], reasonable profit on the Cost shall also be included. 19.4

Consequences of  If the Contractor is prevented from performing any of his Force Majeure

obligations under the Contract by Force Majeure of which notice has been given under Sub-Clause 19.2 [ Notice of Force  Majeure], and suffers delay and/or incurs Cost by reason of  such Force Majeure, the Contractor shall be entitled subject to Sub-Clause 20.1 [Contractor’s C laims] to: (a) an extension of time for any such delay, if completion is or  will be delayed, under Sub-Clause 8.4 [ Extension of Time for  Completion], and (b) if the event or circumstance is of the kind described in sub paragraphs (i) to (iv) of Sub-Clause 19.1 [ Definition of Force  Majeure] and, in the case of subparagraphs (ii) to (iv), occurs in the Country, payment of any such Cost.

Department of Building Economics

7

BE-4605 Claims Management

Provisions for Time and Money Claims in FIDIC Red Book 1999

3. The Employer’s Claims Previous FIDIC contracts did not include procedures for claim by the Employer. In practice the Employer probably deducted any money he thought he was entitled to claim and the Contractor had to submit a claim to recover the deduction. This situation inevitably caused problems and disputes, thus  procedures for claims are now given in Sub-Clause 2.5. Sub Clause Nr

4.19

Clause Title

Electricity,

Provisions for Time and/or Money

water  Charges for the use of power, water, gas and other se rvices

and Gas 4.2

Employer's

If the Contractor uses Employer's equipment, materials

equipment, and

free

issue

materials 7.5

Rejection

If the rejection and retesting cause the Employer to incur  additional cost

7.6

Remedial work

If the Contractor fails to comply with Engineer's instruction to comply with the requirement set in the contract (remove from site or replace plant/equipment, execute work)

8.6

Rate of progress

If revised method of execution cause the Employer to incur  additional costs

8.7

Delay damage

If the Contractor fails to comply with time for completion sub-clause 8.2 (liquidated damage)

9.4

Failure to pass test

If the Works, or a Section, fail to pass the Tests on

on

Completion repeated under Sub-Clause 9.3 [Retesting], and

completion

the Employer takes over the project, the reduced value of work 

11.3

Extension

of  If and to the extent that the Works, Section or a major item of 

Defect

Plant (as the case may be, and after taking over) cannot be

notification period

used for the purposes for which they are intended by reason taking over) cannot be used for the purposes for which they are intended by reason of a defect or by reason of damage attributable to the Contractor 

11.4

Failure to remedy

Department of Building Economics

If the Contractor fails to remedy the defects or damage by the

8

BE-4605 Claims Management

Sub Clause Nr

Provisions for Time and Money Claims in FIDIC Red Book 1999

Clause Title

Provisions for Time and/or Money

defects

notified date and this remedial work was to be executed of the cost of the contractor 

15.4

Payment after 

After Termination by employer, the costs of execution,

termination

completion and remedying of any defects, damages for delay in completion

18.1

General Insurance

If the contractor fails to effect and keep in force an insurance which is available and which it is required to effect and maintain under the contract, and the Employer neither  approves omissions nor effect insurance for the coverage relevant to this default, any money which should have been recoverable under this insurance

18.2

Insurance

for  If, more than 1 year after the Base date, the insurance cover 

works

for the damage to or loss of the works which is attributable to

and Contractor's

the use or occupation by the Employer, ceases to be available

Equipment

at commercially reasonable terms, the amount equivalent as the Contractor should have expected to have paid

Department of Building Economics

9

View more...

Comments

Copyright ©2017 KUPDF Inc.
SUPPORT KUPDF