Test forms for SS

May 22, 2018 | Author: Rakesh Kumar | Category: N/A
Share Embed Donate


Short Description

SS test forms with standards...

Description

PROJECT DRAWING NUMBER

THIS SUBMISSION IS DECLARED TO BE STRICTLY IN ACCORDANCE WITH THE REQUIREMENTS OF THE CONTRACT

PH10-1C-10-15-P002

CLIENT NAME

STAMP:

QATAR TRANSMISSION SYSTEM EXPANSION – PHASE 10 SUBSTATIONS PACKAGE S5 & S8 CONSULTANT NAME

SUBSTATION NAME / CIRCUIT NAME

COMMON

B

02 Oct, 13

ISSUED FOR CONSTRUCTION

T.G. PARK

S.T.M

S.Y.SUNG

A

B

16 June, 13

ISSUED FOR CONSTRUCTION

T.G. PARK

S.T.M

S.Y.SUNG

0

B

24 APR, 13

ISSUED FOR COMMENTS

T.G. PARK

S.T.M

S.Y.SUNG

REV.

STAT.

DESCRIPTION

DRAWN

CHECK.

APPRO.

DATE

CONTRACTOR NAME

MANUFACTUTRE NAME

MANUFACTUTRE DRAWING NUMBER

NA

NA

DRAWING / DOCUMENT TITLE

SAT PROCEDURE AND TEST FORMS FOR 11KV SWGR SUBSTATIONS: 220/66/11kV 220/66/11kV New Doha-B Super S/S, 220/66/11kV Abu Hamur Super S/S, 220/66/11kV Ain Khalid Super S/S, Lusail Development super 3 S/S, 66/11KV Ain Khalid North S/S, 66/11KV Al Wadi West S/S SCALE

N/A

SIZE

SHEET 1 OF 105 SHEETS

A4

REV. B

PROJECT DRAWING NUMBER

PH10-1C-10-15-P002

PROJECT NAME: QATAR POWER TRANSMISSION SYSTEM EXPANSION PHASE 10 – SUBSTATIONS PACKAGE S5 & S8 CONTRACT NO.: GTC/371C/2010 DOC. NO.: PH10-1C-10-15-P002

PAGE: 2 OF 105 REV. B

TITLE:SAT PROCEDURE AND TEST FORMS FOR 11KV SWGR

DATE:

LIST OF CONTENTS SL. NO. 1 2 3 4

5 6

DESCRIPTION Visual and Dimension check Power Frequency Withstand Voltage Test 2.1.Insulation Resistance Measurement 2.2.High Voltage AC Test Measurement of Insulation Resistance for Auxiliary circuit Vacuum Circuit Breaker Test 4.1 Insulation Resistance Measurement 4.2 Coil Resistance Measurement 4.3 Contact Resistance Measurement 4.4 Closing Coil And Tripping Coil Pickup(Operation) Test 4.5 Breaker Timing Test 4.6 Electrical & Mechanical Operation checks Measurement of Contact Resistance for Main Circuit Current Transformer Test 6.1. Incomer Feeder 6.1.1 General Checks 6.1.2 Insulation Resistance Measurement 6.1.3 Polarity Test 6.1.4 Winding Resistance Measurement 6.1.5 Knee Point Voltage Measurement 6.1.6 Ratio Test 6.2.Bus-Section 6.2.1 General Checks 6.2.2 Insulation Resistance Measurement 6.2.3 Polarity Test 6.2.4 Winding Resistance Measurement 6.2.5 Knee Point Voltage Measurement 6.2.6 Ratio Test 6.3.Outgoing Feeder 6.3.1 General Checks 6.3.2 Insulation Resistance Measurement 6.3.3 Polarity Test 6.3.4 Winding Resistance Measurement 6.3.5 Knee Point Voltage Measurement 6.3.6 Ratio Test 6.4.Station Transformer Feeder 6.4.1 General Checks 6.4.2 Insulation Resistance Measurement 6.4.3 Polarity Test 6.4.4 Winding Resistance Measurement 6.4.5 Knee Point Voltage Measurement

HYOSUNG Signature: Name: Date:

LAHMEYER INTERNATIONAL Signature: Name: Date:

PAGE NO. 6 8 10 10

14 16

KAHRAMAA Signature: Name: Date:

PROJECT NAME: QATAR POWER TRANSMISSION SYSTEM EXPANSION PHASE 10 – SUBSTATIONS PACKAGE S5 & S8 CONTRACT NO.: GTC/371C/2010 DOC. NO.: PH10-1C-10-15-P002

PAGE: 3 OF 105 REV. B

TITLE:SAT PROCEDURE AND TEST FORMS FOR 11KV SWGR

DATE:

6.4.6 Ratio Test Voltage Transformer Test 7.1.Incomer Feeder 7.1.1. General Check 7.1.2. Insulation Resistance Measurement 7.1.3. Polarity Test 7.1.4. Winding Resistance Measurement 7.1.5. Ratio Test 7.2.Bus VT & Outgoing Feeders 7.2.1. General Check 7.2.2. Insulation Resistance Measurement 7.2.3. Polarity Test 7.2.4. Winding Resistance Measurement 7.2.5. Ratio Test Meter Calibration test 8.1. Ammeter Calibration Test 8.2. Voltmeter Calibration Test CT Secondary Injection Test VT Secondary Injection Test CT Primary Injection Test

7

8 9 10 11

44

54

56 80 105

Reference Drawings: S.NO

Description

Doc.No

Approval Status

1

Schematic for 11kV SWGR Incomer feeder

PH10-1C-10-15-3-001

A

2

Schematic for 11kV SWGR Bus section

PH10-1C-10-15-3-012

A

3

Schematic for 11kV SWGR Cable feeder

PH10-1C-10-15-3-008

A

4

Schematic for 11kV SWGR Aux transformer feeder

PH10-1C-10-15-3-007

A

5

Schematic for 11kV SWGR Capacitor feeder

PH10-1C-10-15-3-009

A

6

Schematic for 11kV SWGR Interlock Diagram

PH10-1C-10-15-3-010

I

7

Schematic for 11kv SWGR SYNCRO check

PH10-1C-10-15-3-011

B

8

Schematic for 11kv SWGR Bus1 CT Diagram

PH10-1C-10-15-3-002

I

9

Schematic for 11kv SWGR Bus2 CT Diagram

PH10-1C-10-15-3-006

I

10

Schematic for 11kv SWGR Bus Bar VT Diagram

PH10-1C-10-15-3-003

B

11

11KV SWGR General Arrangement Diagram

PH10-1C-10-15-2-002

B

12

11KV SWGR Name Plate Diagram

PH10-1C-10-15-5-001

I

13

11KV SWGR Outline & Foundation Diagram

PH10-1C-10-15-2-001

I

HYOSUNG Signature: Name: Date:

LAHMEYER INTERNATIONAL Signature: Name: Date:

KAHRAMAA Signature: Name: Date:

PROJECT NAME: QATAR POWER TRANSMISSION SYSTEM EXPANSION PHASE 10 – SUBSTATIONS PACKAGE S5 & S8 CONTRACT NO.: GTC/371C/2010 DOC. NO.: PH10-1C-10-15-P002

PAGE: 4 OF 105 REV. B

TITLE:SAT PROCEDURE AND TEST FORMS FOR 11KV SWGR

DATE:

LIST OF TEST INSTRUMENTS

S.NO

EQUIPMENT

MAKE/TYPE

SERIAL NUMBER

CALIBRATION DATE

CALIBRATION DUE DATE

1 2 3 Note: Calibration Certificates will be produced along with the Testing equipments at site during testing activities.

HYOSUNG Signature: Name: Date:

LAHMEYER INTERNATIONAL Signature: Name: Date:

KAHRAMAA Signature: Name: Date:

PROJECT NAME: QATAR POWER TRANSMISSION SYSTEM EXPANSION PHASE 10 – SUBSTATIONS PACKAGE S5 & S8 CONTRACT NO.: GTC/371C/2010 DOC. NO.: PH10-1C-10-15-P002

PAGE: 5 OF 105 REV. B

TITLE:SAT PROCEDURE AND TEST FORMS FOR 11KV SWGR

DATE:

1. VISUAL CHECK Equipment information DESCRIPTION

INCOMER

BUS SECTION

OUT GOING

SCHNEIDER

Make Type

INDOOR

Installation Serial no Rated current

2500 A

3150 A

630A

Rated frequency

50 Hz

50 Hz

50 Hz

Rated voltage

12 kV

12 kV

12 kV

40 KA for 3Sec

40 KA for 3 Sec

40 KA for 3 Sec

Control voltage

110 VDC

110 VDC

110 VDC

Auxiliary voltage

240 VAC

240 VAC

240 VAC

Short time withstand rating

Year of manufacture

HYOSUNG Signature: Name: Date:

LAHMEYER INTERNATIONAL Signature: Name: Date:

KAHRAMAA Signature: Name: Date:

PROJECT NAME: QATAR POWER TRANSMISSION SYSTEM EXPANSION PHASE 10 – SUBSTATIONS PACKAGE S5 & S8 CONTRACT NO.: GTC/371C/2010 DOC. NO.: PH10-1C-10-15-P002

Sl.No. 1 2

3

4 5 6 7 8 9 10 11 12

PAGE: 6 OF 105 REV. B

TITLE:SAT PROCEDURE AND TEST FORMS FOR 11KV SWGR

DESCRIPTION

DATE:

RESULTS

Name Plate Inspection Check each nameplate according to drawing Space Heater Check and breaking of wires of heater of HV and LV compartment Check setting of thermostat Others 3.1. Check doors closing completely 3.2. Check earthing state of doors and frame 3.3. Check all indication lamps of local panel 3.4. Check wiring condition 3.5. Check any joint in middle of wire 3.6. Check terminal block cover 3.7. Check the door limit switches 3.8. Check phase marks 3.10. Check construction and inspection of operating mechanism After self test and official test check interlock lever’s set-up and it’s smooth operation Check cable number tag at cables Check the proper dressing at wire duct Check the cable proper glanding at the panel Check insulation cover on CT&AC/DC supply terminals Conformity of power/control cable connection and identification labels. Check the power/control cable connection and tightness. Check of component pad lock facilities. All TB are numbered at both sides.

2. POWER FREQUENCY WITHSTAND VOLTAGE TEST HYOSUNG Signature: Name: Date:

LAHMEYER INTERNATIONAL Signature: Name: Date:

KAHRAMAA Signature: Name: Date:

PROJECT NAME: QATAR POWER TRANSMISSION SYSTEM EXPANSION PHASE 10 – SUBSTATIONS PACKAGE S5 & S8 CONTRACT NO.: GTC/371C/2010 DOC. NO.: PH10-1C-10-15-P002

PAGE: 7 OF 105 REV. B

TITLE:SAT PROCEDURE AND TEST FORMS FOR 11KV SWGR

DATE:

Test procedure: 1. Carry out Insulation Resistance Test (Before HV). 2. Carry out HV Test. 3. Carry out Insulation Resistance Test (After HV). Pre-conditions: 1. Check and confirm the CT circuits should be shorted and earthed. 2. Check and confirm Bus and line VT are isolated. 3. Check and confirm Switchboard is earthed. 4. Check all VT Fuse Removed. 5. CVD contact shorted at front of Display terminals in each phase of HV test. (Note: CVD indications to be tested at 6KV AC during the HV test.) Safety Procedures: (i)During the HV test 11kv SWGR Room all the access points are should be closed and locked, No-one not permitted to remain with in the 11KV SWGR room during testing. (ii) All the energize component will be barricaded off with rigid safety fencing. (iii) 11KV SWGR room and basement as well as all access points are shall be locked. 2.1. IR value measurement: Measure insulation resistance at 5000V DC before and after HV test. R – YBE in GΩ

Y-RBE in GΩ

B-RYE in GΩ

Before HV Test After HV Test

2.2. HVAC test. This test is to be carried out on each of the phases with respect to earth. AC voltage at 50Hz equal to 80% FAT value i.e 22.4kV since this test was carried out at Factory 2.5 times of the line voltage i.e 28 kV for 1 minute was applied to the conductor with respect to ground. The leakage current is recorded and noted as mentioned in the below table. (Note: Since this test is carried out in factory. 80% of the 28kV i.e. 22.4 kV shall be applied in site test.) Test Result: HV Test @ 22.4 kV AC for 1 Minutes Leakage current in mA 0 Sec

30 Sec

1 min

R–YBE Y-RBE B-RYE

Criteria: Shall be withstood. HYOSUNG Signature: Name: Date:

LAHMEYER INTERNATIONAL Signature: Name: Date:

KAHRAMAA Signature: Name: Date:

PROJECT NAME: QATAR POWER TRANSMISSION SYSTEM EXPANSION PHASE 10 – SUBSTATIONS PACKAGE S5 & S8 CONTRACT NO.: GTC/371C/2010 DOC. NO.: PH10-1C-10-15-P002

PAGE: 8 OF 105 REV. B

TITLE:SAT PROCEDURE AND TEST FORMS FOR 11KV SWGR

DATE:

2.2. PARTIAL DISCHARGE TEST DURING HV TEST (i) All secondary circuit of CT’s must be shorted. (ii) Ground the other two phases through the bus bar at cable chamber and also at the CVD display on the chamber. (iii) For the selected phases apply 1.1 x E/1.732 Voltage (7.6KV) (iv) Note down the PD value for each panel at the applied voltage. (v) Repeat same procedure for all phases and all the feeders. S.NO

BAY NO

Test voltage (kV)

1

A190

6.9KV

2

A170

6.9KV

3

A150

6.9KV

4

A130

6.9KV

R-PH

Measured values Y-PH B-PH

Result

Criteria: Should be less than 15 db 2.3. VT RATIO TEST AT RATED VOLTAGE: For Incomer: Test Results VT Designation

Phase

Terminal

Applied Primary Voltage in (V)

Calc Sec. Voltage in (V)

Measured Sec. Voltage in (V)

1r - 1nr R

2r - 2nr 3r - 3nr 1y - 1ny

Y

2y - 2ny 3y - 3ny 1b - 1nb

B

2b - 2nb 3b - 3nb

HYOSUNG Signature: Name: Date:

LAHMEYER INTERNATIONAL Signature: Name: Date:

KAHRAMAA Signature: Name: Date:

% Error

PROJECT NAME: QATAR POWER TRANSMISSION SYSTEM EXPANSION PHASE 10 – SUBSTATIONS PACKAGE S5 & S8 CONTRACT NO.: GTC/371C/2010 DOC. NO.: PH10-1C-10-15-P002

PAGE: 9 OF 105 REV. B

TITLE:SAT PROCEDURE AND TEST FORMS FOR 11KV SWGR

DATE:

For Bus VT & Outgoing Feeders: VT Designation

Phase

Terminal

R

1r - 1nr

Y

1y - 1ny

B

1b - 1nb

Applied Primary Voltage in (V)

Calc Sec. Voltage in (V)

Measured Sec.Voltage in (V)

% Error

2.4.CVD INDICATOR TEST: CVD Indicator test have been tested with 6 kv single phase, check the all condition with individual Phases. CVD indications tested at 6KV AC VOLTAGE

: OK/NOT OK

Remarks:

3. MEASUREMENT OF INSULATION RESISTANCE FOR AUXILIARY CIRCUIT Insulation Resistance Measurement The insulation resistance between Auxiliary circuit and earth shall be measured with 1kV Megger. Contents

Measured value of Insulation Resistance

Result

Between the Auxiliary Circuit and Earth

Criteria: >2MΩ Remarks:

4. VACUUM CIRCUIT BREAKER TEST Name Plate Details HYOSUNG Signature: Name: Date:

LAHMEYER INTERNATIONAL Signature: Name: Date:

KAHRAMAA Signature: Name: Date:

Remarks

PROJECT NAME: QATAR POWER TRANSMISSION SYSTEM EXPANSION PHASE 10 – SUBSTATIONS PACKAGE S5 & S8 CONTRACT NO.: GTC/371C/2010 DOC. NO.: PH10-1C-10-15-P002

PAGE: 10 OF 105 REV. B

TITLE:SAT PROCEDURE AND TEST FORMS FOR 11KV SWGR

Description

INCOMER

BUS SECTION

DATE:

OUT GOING

SCHNEIDER

Make HVX 12-40-31-E

HVX 12-40-31-E

HVX 12-40-31-E

Type INDOOR

Installation Serial no Rated current

2500 A

3150 A

800A

Rated frequency

50 Hz

50 Hz

50 Hz

Rated voltage

12 kV

12 kV

12 kV

Breaking rating

40 kA

40 kA

40 kA

Control voltage

110 VDC

110 VDC

110 VDC

Auxiliary voltage

240 VAC

240 VAC

240 VAC

O–0.3S-CO–3M-CO

O–0.3S-CO–3M-CO

O–0.3S-CO–3M-CO

Breaker operating sequence Year of manufacture

4.1. Insulation Resistance Measurement: Applied Voltage

R-PH(GΩ)

Y-PH(GΩ)

B-PH(GΩ)

Pole – Earth(Close)

5KV

Pole – Pole(Open)

Criteria: 500MΩ

4.2. Coil Resistance Measurement: Coil

Resistance in Ω

Trip Coil Close Coil

Criteria: 1.Closing Coil : 35.3 to 39.0 Ω 2. Opening Coil : 35.3 to 39.0 Ω

4.3. CB Closing & Opening check at reduced control voltage: CB

C .Voltage (110V)

A .Volt [Vdc]

Close

(85%)

93.5V

Open

(70%)

77V

Time (ms)

Result

Temperature :

4.4. Breaker Timing Test: HYOSUNG Signature: Name: Date:

LAHMEYER INTERNATIONAL Signature: Name: Date:

KAHRAMAA Signature: Name: Date:

ºC

PROJECT NAME: QATAR POWER TRANSMISSION SYSTEM EXPANSION PHASE 10 – SUBSTATIONS PACKAGE S5 & S8 CONTRACT NO.: GTC/371C/2010 DOC. NO.: PH10-1C-10-15-P002

PAGE: 11 OF 105 REV. B

Operation

TITLE:SAT PROCEDURE AND TEST FORMS FOR 11KV SWGR

R-PH (msec)

Y-PH (msec)

DATE:

B-PH( (msec)

Open Close Close – Open

Criteria: 1. Closing time : 20 to 50ms 2. Opening time: 15 to 35 ms

4.5. Contact Resistance Measurement: Measured Value (in μΩ)

Phase R-Phase Y-Phase B-Phase

Criteria: 1. For Incomer & Bus Section 2. For Outgoing feeder

: < 20 µΩ :
View more...

Comments

Copyright ©2017 KUPDF Inc.