THIS SUBMISSION IS DECLARED TO BE STRICTLY IN ACCORDANCE WITH THE REQUIREMENTS OF THE CONTRACT
PH10-1C-10-15-P002
CLIENT NAME
STAMP:
QATAR TRANSMISSION SYSTEM EXPANSION – PHASE 10 SUBSTATIONS PACKAGE S5 & S8 CONSULTANT NAME
SUBSTATION NAME / CIRCUIT NAME
COMMON
B
02 Oct, 13
ISSUED FOR CONSTRUCTION
T.G. PARK
S.T.M
S.Y.SUNG
A
B
16 June, 13
ISSUED FOR CONSTRUCTION
T.G. PARK
S.T.M
S.Y.SUNG
0
B
24 APR, 13
ISSUED FOR COMMENTS
T.G. PARK
S.T.M
S.Y.SUNG
REV.
STAT.
DESCRIPTION
DRAWN
CHECK.
APPRO.
DATE
CONTRACTOR NAME
MANUFACTUTRE NAME
MANUFACTUTRE DRAWING NUMBER
NA
NA
DRAWING / DOCUMENT TITLE
SAT PROCEDURE AND TEST FORMS FOR 11KV SWGR SUBSTATIONS: 220/66/11kV 220/66/11kV New Doha-B Super S/S, 220/66/11kV Abu Hamur Super S/S, 220/66/11kV Ain Khalid Super S/S, Lusail Development super 3 S/S, 66/11KV Ain Khalid North S/S, 66/11KV Al Wadi West S/S SCALE
DESCRIPTION Visual and Dimension check Power Frequency Withstand Voltage Test 2.1.Insulation Resistance Measurement 2.2.High Voltage AC Test Measurement of Insulation Resistance for Auxiliary circuit Vacuum Circuit Breaker Test 4.1 Insulation Resistance Measurement 4.2 Coil Resistance Measurement 4.3 Contact Resistance Measurement 4.4 Closing Coil And Tripping Coil Pickup(Operation) Test 4.5 Breaker Timing Test 4.6 Electrical & Mechanical Operation checks Measurement of Contact Resistance for Main Circuit Current Transformer Test 6.1. Incomer Feeder 6.1.1 General Checks 6.1.2 Insulation Resistance Measurement 6.1.3 Polarity Test 6.1.4 Winding Resistance Measurement 6.1.5 Knee Point Voltage Measurement 6.1.6 Ratio Test 6.2.Bus-Section 6.2.1 General Checks 6.2.2 Insulation Resistance Measurement 6.2.3 Polarity Test 6.2.4 Winding Resistance Measurement 6.2.5 Knee Point Voltage Measurement 6.2.6 Ratio Test 6.3.Outgoing Feeder 6.3.1 General Checks 6.3.2 Insulation Resistance Measurement 6.3.3 Polarity Test 6.3.4 Winding Resistance Measurement 6.3.5 Knee Point Voltage Measurement 6.3.6 Ratio Test 6.4.Station Transformer Feeder 6.4.1 General Checks 6.4.2 Insulation Resistance Measurement 6.4.3 Polarity Test 6.4.4 Winding Resistance Measurement 6.4.5 Knee Point Voltage Measurement
6.4.6 Ratio Test Voltage Transformer Test 7.1.Incomer Feeder 7.1.1. General Check 7.1.2. Insulation Resistance Measurement 7.1.3. Polarity Test 7.1.4. Winding Resistance Measurement 7.1.5. Ratio Test 7.2.Bus VT & Outgoing Feeders 7.2.1. General Check 7.2.2. Insulation Resistance Measurement 7.2.3. Polarity Test 7.2.4. Winding Resistance Measurement 7.2.5. Ratio Test Meter Calibration test 8.1. Ammeter Calibration Test 8.2. Voltmeter Calibration Test CT Secondary Injection Test VT Secondary Injection Test CT Primary Injection Test
Name Plate Inspection Check each nameplate according to drawing Space Heater Check and breaking of wires of heater of HV and LV compartment Check setting of thermostat Others 3.1. Check doors closing completely 3.2. Check earthing state of doors and frame 3.3. Check all indication lamps of local panel 3.4. Check wiring condition 3.5. Check any joint in middle of wire 3.6. Check terminal block cover 3.7. Check the door limit switches 3.8. Check phase marks 3.10. Check construction and inspection of operating mechanism After self test and official test check interlock lever’s set-up and it’s smooth operation Check cable number tag at cables Check the proper dressing at wire duct Check the cable proper glanding at the panel Check insulation cover on CT&AC/DC supply terminals Conformity of power/control cable connection and identification labels. Check the power/control cable connection and tightness. Check of component pad lock facilities. All TB are numbered at both sides.
2. POWER FREQUENCY WITHSTAND VOLTAGE TEST HYOSUNG Signature: Name: Date:
Test procedure: 1. Carry out Insulation Resistance Test (Before HV). 2. Carry out HV Test. 3. Carry out Insulation Resistance Test (After HV). Pre-conditions: 1. Check and confirm the CT circuits should be shorted and earthed. 2. Check and confirm Bus and line VT are isolated. 3. Check and confirm Switchboard is earthed. 4. Check all VT Fuse Removed. 5. CVD contact shorted at front of Display terminals in each phase of HV test. (Note: CVD indications to be tested at 6KV AC during the HV test.) Safety Procedures: (i)During the HV test 11kv SWGR Room all the access points are should be closed and locked, No-one not permitted to remain with in the 11KV SWGR room during testing. (ii) All the energize component will be barricaded off with rigid safety fencing. (iii) 11KV SWGR room and basement as well as all access points are shall be locked. 2.1. IR value measurement: Measure insulation resistance at 5000V DC before and after HV test. R – YBE in GΩ
Y-RBE in GΩ
B-RYE in GΩ
Before HV Test After HV Test
2.2. HVAC test. This test is to be carried out on each of the phases with respect to earth. AC voltage at 50Hz equal to 80% FAT value i.e 22.4kV since this test was carried out at Factory 2.5 times of the line voltage i.e 28 kV for 1 minute was applied to the conductor with respect to ground. The leakage current is recorded and noted as mentioned in the below table. (Note: Since this test is carried out in factory. 80% of the 28kV i.e. 22.4 kV shall be applied in site test.) Test Result: HV Test @ 22.4 kV AC for 1 Minutes Leakage current in mA 0 Sec
30 Sec
1 min
R–YBE Y-RBE B-RYE
Criteria: Shall be withstood. HYOSUNG Signature: Name: Date:
2.2. PARTIAL DISCHARGE TEST DURING HV TEST (i) All secondary circuit of CT’s must be shorted. (ii) Ground the other two phases through the bus bar at cable chamber and also at the CVD display on the chamber. (iii) For the selected phases apply 1.1 x E/1.732 Voltage (7.6KV) (iv) Note down the PD value for each panel at the applied voltage. (v) Repeat same procedure for all phases and all the feeders. S.NO
BAY NO
Test voltage (kV)
1
A190
6.9KV
2
A170
6.9KV
3
A150
6.9KV
4
A130
6.9KV
R-PH
Measured values Y-PH B-PH
Result
Criteria: Should be less than 15 db 2.3. VT RATIO TEST AT RATED VOLTAGE: For Incomer: Test Results VT Designation
2.4.CVD INDICATOR TEST: CVD Indicator test have been tested with 6 kv single phase, check the all condition with individual Phases. CVD indications tested at 6KV AC VOLTAGE
: OK/NOT OK
Remarks:
3. MEASUREMENT OF INSULATION RESISTANCE FOR AUXILIARY CIRCUIT Insulation Resistance Measurement The insulation resistance between Auxiliary circuit and earth shall be measured with 1kV Megger. Contents
Measured value of Insulation Resistance
Result
Between the Auxiliary Circuit and Earth
Criteria: >2MΩ Remarks:
4. VACUUM CIRCUIT BREAKER TEST Name Plate Details HYOSUNG Signature: Name: Date: