Summer Training Report Civil Engineering

March 24, 2017 | Author: sdashiv | Category: N/A
Share Embed Donate


Short Description

summer training report civil engineering...

Description

SUMMER TRAINING REPORT ( CIV 435) A PROJECT REPORT Submitted by

LOVE MALIK in partial fulfillment for the award of the degree of

BACHELOR OF TECHNOLOGY IN CIVIL ENGINEERING

Under the guidance of

Submitted by

Mr. Ankit Bansal

Love Malik

Assistant Professor

11304009

UID No:

Lovely Professional University Phagwara-144401, Punjab (India) 1

LOVELY PROFESSIONAL UNIVERSITY CERTIFICATE Certified that this project report entitled "Summer Training Report (CIV 435)" submitted by "LOVE MALIK", registration number 11304009, student of Civil Engineering Department, Lovely Professional University, Phagwara, Punjab who carried on the project work under my supervision. This report has not been submitted to any other university or institution for the award of any degree.

SIGNATURE

SIGNATURE

HEAD OF DEPART MENT

SUPERVISOR

(School of Civil Engineering)

2

(School of Civil Engineering)

LOVELY PROFESSIONAL UNIVERSITY DECLARATION I certify that a) The work contained in the thesis is original and has been done by myself under the guidance of my supervisor b) The work has not been submitted to any other Institute for any degree or diploma. c) I have followed the guidelines provided by the Institute in preparing the thesis. d) Whenever I have used materials (data, theoretical analysis, figures, and text) from other sources, I have given due credit to them by citing them in the text of the thesis and giving their details in the reference.

Signature Date: Love Malik Registration no.: 11304009

3

TABLE OF CONTENTS DESCRIPTION

PAGE NO

Title page

i

Certificate

ii

Declaration

iii

List of tables

vi

List of figures

vi

Acknowledgement

vii

Abstract

viii

CHAPTER 1: INTRODUCTION

9 to 10

1.1 Introduction ........................................................................................................9 1.2 Objectives of the training ....................................................................................9 1.3 Scope of the study ................................................................................................9 CHAPTER 2: UNDERTAKEN CONSTRUCTION PROJECTS 2.1 Construction of U-type storm drains

11-20

2.1.1 List of officers ..............................................................................12 2.1.2 Detailed work ................................................................................13 2.1.3 Specifications ................................................................................13 2.1.4 Rate Analysis .................................................................................14 2.1.5 Details of Measurement .................................................................16 2.1.6 Bill of Quantity ...............................................................................19 2.2 Repair work and Whitewash 2.2.1 List of officers .................................................................................22 2.2.2 Detailed work ..................................................................................23 2.2.3 Specifications ..................................................................................23 2.2.4 Rate Analysis ...................................................................................24 2.2.5 Details of Measurement ...................................................................25 2.2.6 Bill of Quantity .................................................................................29

4

CHAPTER 3 : CONCLUSIONS 3.1 Conclusions ...............................................................................................30 3.2 Drawbacks .................................................................................................30 3.3 Future scope ...............................................................................................30

5

LIST OF TABLES DESCRIPTION

PAGE NO.

Table 2.1 List of engineers in charge at site

12

Table2.2 Rate analysis for U-type storm drain

14

Table 2.3 Details of measurement table for U-type storm drain

16

Table 2.4 Table for bill of quantity for U-type drain

19

Table 2.5 List of engineers for the project

22

Table 2.6 Rate of analysis for the project

24

Table 2.7 Details of measurement for Repair work

25

Table 2.8 Table for bill of quantity for Repair work

29

LIST OF FIGURES

None Included...................................................

6

Acknowledgement I take this opportunity to express my profound gratitude and deep regards to my guide Asst.Prof. Ambika Thakur, School of Civil Engineering for her exemplary guidance, monitoring and constant encouragement throughout the course of this thesis. The blessing, help and guidance given by her time to time shall carry me a long way in the journey of life on which I am about to embark. I am highly indebted to School of Civil Engineering, Lovely Professional University for their guidance and constant supervision as well as for providing necessary information regarding the project & also for their support in completing the project. Lastly, I thank Almighty, my parents, brother, sister and friends for their constant encouragement without which this assignment would not be possible.

7

Abstract This report describes two small scale construction projects namely, construction of U-type storm drain and repair work and whitewash. The main aim of constructing a U-type storm drain was to regulate the flow of water through and across the road . The roads were surveyed and the measurements were taken accordingly. The dimensions were recorded for estimating the total cost of constructing the U-type storm drain. The Earth was first excavated at the site to a depth of 60 cms and the bottom surface was plastered with 10 cms thick C.C (1:4:8). The brick drainwalls each of height 45 cms and of width 23 cms and 35 cms were respectively constructed. The Exposed inner surfaces were lined with 15 cms thick plaster (1:4) plaster and the exposed outer surfaces were lined with 5 cms thick P.C.C (1:1.5:3) plaster. In the second construction project, the existing coat of color was first scraped out and all the voids existing were covered with white cement. The surface was allowed to air dry and then watered to add moisture. The walls were then coated with a layer of oil-bound washable distemper. For repairing the walls the old plaster was first raked out and cleaned with sand paper for making the surface smooth. The repair work was done as patches of area 2.5 sqm, of thickness 12 mm to 20 mm with cement mortar (1:4).

8

Chapter 1 : INTRODUCTION 1.1 INTRODUCTION Lok Nirman Vibhag popularly known as P.W.D. has a legacy of more than 130 years. P.W.D. is responsible for construction, maintenance and planning of roads, bridges and Govt. Buildings. In view of strategic location of Uttarakhand bordering China & Nepal, the responsibility of P.W.D. becomes of much more attentive from defense point of view. As part of graduation requirements, all the undergraduates, the third year and forth year students, who take bachelor of Civil Engineering in LPU will undergo industrial training programme for a duration of six weeks. This industrial training is a course for undergraduates that gives them an opportunity to expose themselves in the real career world so as to they will learn how to relate theoretical learning before and real practical in working’s environment. Besides that, in future, they will be having good preparation and understanding for their field of profession.

1.2 THE OBJECTIVE OF INDUSTRIAL TRAINING: 

Undergraduates have an opportunity to expose themselves in working’s environment of their field of profession respectively.



For obtaining working’s experience in the industry which is relating to their field of current study.



Using knowledge which is obtained from industrial training for their study after finishing training and continuing study at university afterwards.



Training them to be capable in communication and interaction b e t w e e n w o r k e r s a n d s u p e r i o r.



Training them to be able to prepare a technical report which is related to industrial training they do.

1.3 THE SCOPE OF INDUSTRIAL TRAINING: 

Observing the whole operation of this industry.



Doing operation’s work that is involved in unit production by either using machine or tool.



Work that involving installment and fabrication of tool. 9



Visual inspection and quality control on the final product.



Repairing an y damaged tool if it still can use, or buying a new tool to replace it.



Discussion and meeting with superior.

2.1: CONSTRUCTION OF U-TYPE STORM DRAIN

10

Name of Circle :

9th Circle , P.W.D, Dehradun

Name of Constituency :

Dehradun

Name of Construction Site :

Raipur

Name of Department :

Construction Division, P.W.D, Dehradun

Lok Sabha/Vidhan Sabha :

Haridwar/Dharampur Detailed Estimate

Name of the task:

Construction of storm drains along Pratap Road, Guru Nanak Road, and Bhagat Singh Road in Subhash Nagar,

Dehradun.

Estimated Cost of the Project :

11

66.56 lakhs/-

2.1.1 LIST OF OFFICERS

Sr. No

Name of Officer

Designation

1.

Er. Y.N. Rajvanshi

Executive Engineer

2.

Er. Ravindra Kumar

Assistant Engineer

3.

Er. Shah Alam

Junior Engineer

4.

Er. Archana Bisht

Junior Engineer

table 2.1 List of Officers in charge at construction site

12

2.1.2 Detailed work : For the mentioned work, from C.C Road and Pratap road to Puri General Store (1150 mts), from Guru Nanak Road to Manav Kendra (1500 mts), from Bhagat Singh Road to Arun Sharma's residence (700 mts and 300 mts); provided U-type storm drain as per the specifications. The pre-existing U-type drain which had undergone damage was repaired to prevent the water from standing still and getting stagnant. The provision for providing the Utype drain was most appropriate as it provided 'reverse grade' to the water. Therefore, U-type drains were suggested to be provided.

2.1.3 Specifications : All the works were carried out as per Detailed Specifications of PWD Uttarakhand and as directed by Engineer in Charge and Circulars issued by Chief Engineer (level-I) from time to time.

13

2.1.4 RATE ANALYSIS Sr. No 1. I

SOR No. 11-1

Ii

16-16

iii

11-5-2

iv

17-8-C

v

9-13

2.

11-7

14

Item of work Construction of deep drain (0.45 x 0.45) Earthwork in excavation for structures as per drawing and technical specifications. Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal up to a lead of 50 mts, dressing of sides and bottom and backfilling in trenches with excavated material. Concreting with cement, coarse sand and 40 mm gauge stone ballast in proportion 1:4:8 in foundations and floors including supply of all material, labor and T&P etc. required for proper completion of the work. (Based on PWD specifications) Brick masonry work in cement mortar in foundation complete excluding pointing and plastering as per drawing and technical specifications (Clause 600,1202 & 1203). Brick masonry in 1:4 cement mortar. Plain/Reinforced Cement Concrete in open foundation complete as per drawing and technical specifications. PCC grade M20 (1:1.5:3) using concrete mixer. Plastering with cement mortar (1:4), 15 mm thick on brickwork in substructure as per technical specification (Clauses 613.4 & 1204) Supplying, fitting and placing HYSD bar reinforcement in foundation complete as per drawings and technical specifications. (Clauses 1000 and 1202).(As per MORD specification no.1002.1 and IS 1786:2008 clause no. 1,6). Steel shall be procured from original/primary steel producers only and no re-rolled steel shall be used. The following Primary Steel Producers have been approved for PWD Uttarakhand: 1. Steel Authority of India Limited (SAIL) 2. Rashtriya Ispaat Nigam Limited (RAIL)

Rate

Rs. 180.30 per cum

Rs. 3760.60 per cum

Rs. 4834.60 per cum

Rs. 5009.20 per cum

Rs. 107.70 per sqm

Rs. 6057.24 per qtl

3. Tata Steel 4. Shyam Steel Industries Limited table 2.2 Rate analysis for U-type drain

15

2.1.5 DETAILS OF MEASUREMENT Sr.no

Particulars of item

i

Earthwork in excavation for structures as per drawing and technical specifications. Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal up to a lead of 50 mts, dressing of sides and bottom and backfilling in trenches with excavated material.

Ii

Iii

No.

L

B

H

Quantity

1x1 1x1 1x1 1x1 1x2 total

900 900 600 150 168

1.05 1.05 1.05 1.05 1.05

0.6 567.00 cum 0.6 567.00 cum 0.6 378.00 cum 0.6 94.50 cum 0.6 211.50 cum 1818.18 cum

1x1 1x1 1x1 1x1 1x2 total

900 900 600 150 168

1.05 1.05 1.05 1.05 1.05

0.1 0.1 0.1 0.1 0.1 303.03 cum

1x1 1x1 1x1 1x1 1x1 1x1 1x1

900 900 900 900 600 600 150

0.23 0.35 0.23 0.35 0.23 0.35 0.23

Concreting with cement, coarse sand and 40 mm gauge stone ballast in proportion 1:4:8 in foundations and floors including supply of all material, labor and T&P etc. required for proper completion of the work. (Based on PWD specifications) 94.50 cum 94.50 cum 63.00 cum 15.75 cum 35.28 cum

Brick masonry work in cement mortar in foundation complete excluding pointing and plastering as per drawing and technical specifications (Clause 600,1202 & 1203). Brick masonry in 1:4 cement mortar.

16

0.45 0.45 0.45 0.45 0.45 0.45 0.45

93.15 cum 141.75 cum 93.15 cum 141.75 cum 62.1 cum 94.5 cum 15.525 cum

1x1 1x2 1x2 total Iv

v

150 168 168

0.35 0.23 0.35

0.45 23.625 cum 0.45 34.776 cum 0.45 52.92 cum 753.25 cum

Plain/Reinfor ced Cement Concrete in open foundation complete as per drawing and technical specifications . PCC grade M20 (1:1.5:3) using concrete mixer. 1x1 1x1 1x1 1x1 1x1 1x1 1x1 1x1 1x1 1x1 1x1 1x1 1x1 1x2 1x2 total

900 900 900 900 900 900 600 600 600 150 150 150 168 168 168

0.23 0.35 0.45 0.23 0.35 0.45 0.23 0.35 0.45 0.23 0.35 0.45 0.23 0.35 0.45

0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 0.05 148.63 cum

10.35 cum 15.75 cum 20.25 cum 10.35 cum 15.75 cum 20.25 cum 6.90 cum 10.50 cum 13.50 cum 1.725 cum 2.625 cum 3.375 cum 3.86 cum 5.88 cum 7.56 cum

1x2 1x2 1x2

900 900 600

-

0.45 0.45 0.45

810 sqm 810 sqm 540 sqm

Plastering with cement mortar (1:4), 15 mm thick on brickwork in substructure as per technical specification (Clauses 613.4 & 1204)

17

1x2 2x2 total 2.

Supplying, fitting and placing HYSD bar reinforcem ent in foundation complete as per drawings and technical specificatio ns. (Clauses 1000 and 1202).(As per MORD specificatio n no.1002.1 and IS 1786:2008 clause no. 1,6). Steel shall be procured from original/pri mary steel producers only and no re-rolled steel shall be used. The following Primary 18

150 168

-

0.45 135 sqm 0.45 302.40 sqm 2597.40 sqm

Steel Producers have been approved for PWD Uttarakhan d: 1. Steel Authority of India Limited (SAIL) 2. Rashtriya Ispaat Nigam Limited (RAIL) 3. Tata Steel 4. Shyam Steel Industries Limited [email protected]%= 0.33 x 78.5 = 25.91 qtl Total table 2.3 Details of measurement table for U-type storm drain

19

2.1.6 BILL OF QUANTITY Sr. No 1. i

Particulars of item Earthwork in excavation for structures as per drawing and technical specifications. Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal up to a lead of 50 mts, dressing of sides and bottom and backfilling in trenches with excavated material. Concreting with cement, coarse sand and 40 mm gauge stone ballast in proportion 1:4:8 in foundations and floors including supply of all material, labor and T&P etc. required for proper completion of the work. (Based on PWD specifications) Brick masonry work in cement mortar in foundation complete excluding pointing and plastering as per drawing and technical specifications (Clause 600,1202 & 1203). Brick masonry in 1:4 cement mortar. Plain/Reinforced Cement Concrete in open foundation complete as per drawing and technical specifications. PCC grade M20 (1:1.5:3) using concrete mixer. Plastering with cement mortar (1:4), 15 mm thick on brickwork in substructure as per technical specification (Clauses 613.4 & 1204) Supplying, fitting and placing HYSD bar reinforcement in foundation complete as per drawings and technical specifications. (Clauses 1000 and 1202).(As per MORD specification no.1002.1 and IS 1786:2008 clause no. 1,6). Steel shall be procured from original/primary steel producers only and no re-rolled steel shall be used. The following Primary Steel Producers have been approved for PWD Uttarakhand: 1. Steel Authority of India Limited (SAIL)

Ii

Iii

Iv

V

2

20

Quantity

Rate 180.30 per cum

Amount Rs. 327817.85

3760.60 per cum

Rs. 1139574.62

Rs. 3641643.11

753.25 cum

4834.60 per cum

Rs. 744512.39

148.63 cum

5009.20 per cum

Rs. 279739.98

2597.40 sqm

107.70 per sqm 6057.24 per qtl

Rs. 156912.80

1818.18 cum

303.03 cum

25.91 qtl

2. Rashtriya Ispaat Nigam Limited (RAIL) 3. Tata Steel 4. Shyam Steel Industries Limited Sub Total Contractor Profit (3%) + Supervision (1%)

Rs. 2,55,000 Grand Total

table 2.4 Table for bill of quantity for U-type drain

21

Rs. 64,01,255.00

Rs. 66,56,255.00

2.2 CONSTRUCTION PROJECT ON REPAIR WORK

Name of Circle : 9th Circle , P.W.D, Dehradun Name of Constituency : Dehradun Name of Construction Site : Raipur Name of Department : Construction Division, P.W.D, Dehradun Lok Sabha/Vidhan Sabha : Haridwar/Dharampur Detailed Estimate Name of the task:

Repair work and white wash of Minister's Guest House situated in Race Course, Dehradun.

Estimated Cost of the Project :

22

5.52 lakhs/-

2.2.1 LIST OF OFFICERS

Sr. No

Name of Officer

Designation

1.

Er. Y.N. Rajvanshi

Executive Engineer

2.

Er. Ravindra Kumar

Assistant Engineer

3.

Er. Shah Alam

Junior Engineer

4.

Er. Archana Bisht

Junior Engineer

table 2.5 List of Officers in charge at construction site

23

2.2.2 Detailed work : For the mentioned work, , the existing coat of color was first scraped out and all the voids existing were covered with white cement. The surface was allowed to air dry and then watered to add moisture. The walls were then coated with a layer of oil-bound washable distemper. For repairing the walls the old plaster was first raked out and cleaned with sand paper for making the surface smooth. The repair work was done as patches of area 2.5 sqm, of thickness 12 mm to 20 mm with cement mortar (1:4).

2.2.3 Specifications : All the works were carried out as per Detailed Specifications of PWD Uttarakhand and as directed by Engineer in Charge and Circulars issued by Chief Engineer (level-I) from time to time.

24

2.2.4 RATE ANALYSIS Sr. No

SOR No.

1.

1-14-43

Rate

Removing white or colour wash by scrapping and sand preparing the surface smooth including necessary repairs to scratches tec. completely. 1-13-41-1 Distempering with oil-bound washable distemper of approved brand and manufacture to give an even shade. New work (two or more coats) including priming coat with cement primer. 1-14-54 Painting with synthetic enamel paint of approved brand and manufacture of required colour to give an even shade: two coats on old work 1-14-1-1 Repairs to plaster of thickness 12 mm to 20 mm in patches of area 2.5 sqm with cement mortar (1:4). 1-15-56 Dismantling old plaster or skirting and raking out joints and cleaning the surface for plaster including disposal of rubbish to the dumping ground within 50 mts lead. 1-13-2-2 15 mm cement plaster on rough side of single or half brick wall of mix 1:6 1-13-21 Extra for providing and mixing water proofing material in cement plaster work in proportion recommended by the manufacturers. 1-9-51-2 Providing and fixing fly proof galvanized M.S wire gauge to windows and clerestory with 12 mm M.S beading. 1-17-11 White vitreous china clay Orissa pattern W.C pan of size 580x440 mm with integral type each foot rests. table 2.6 Rate analysis for U-type drain

2.

3.

4. 5.

6. 7.

8.

9.

Sr. no

Item of work

Particulars of the work Removing white or colour wash by scrapping and sand preparing the surface smooth including necessary repairs to scratches tec. completely. 25

No.

L

B

H

Rs.5.40 per sqm

Rs. 93 per sqm

Rs. 48.60 per sqm

Rs. 223.20 per sqm Rs. 13.70 per sqm

Rs. 156.30 per sqm Rs. 39.00 per sqm

Rs. 550.20 per sqm

Rs. 4855.50 each

Quantity

Drawing room

Offset Lobby

Bedroom

Office

Toilet

Store

Shelves

Washroom

Deduction for windows Kitchen

Deduction doors Add partitions

2.

Distempering with oil-bound washable distemper of approved brand and manufacture to give an even shade. New work (two or more coats) 26

15x1 3.21 15x2 3.21 15x2 3.45 15x1 0.11 15x1 2.57 15x1 2.66 15x2 3.75 15x2 4.00 15x1 4.00 15x2 4.22 15x2 5.50 15x1 5.50 15x2 3.40 15x2 1.50 15x1 1.50 15x2 2.33 15x2 2.48 15x1 2.48 15x2 1.34 15x2 0.80 15x2 2.48 15x2 1.25 15x2 0.76 15x1 1.35 15x4 2.22 15x1 2.22 15x2 1.45 15x2 0.58 15x1 2.37 15x1 2.47 15x2 2.37 15x2 1.15 15x1 6.00 15x3 0.62 Total Quantity:

3.45 3.00 3.00 2.67 0.110 3.75 3.00 3.00 4.22 3.00 3.00 3.40 3.00 3.00 2.33 0.56 1.34 3.00 3.00 0.59 0.59 0.59 0.59 0.59 1.45 0.55 0.56 0.88 2.47 2.85 2.85 1.45 0.59 0.64 4566.98 sqm

including priming coat with cement primer. Quantity same as 1. 3.

Painting with synthetic enamel paint of approved brand and manufacture of required colour to give an even shade: two coats on old work Drawing rooms Wire mesh Windows Wire mesh Wire mesh grill Grill Door Lobby door Wire mesh door Wire mesh Grill Bedroom door Window Grill

4.

5.

15x2 15x1.6 15x1 15x2 15x1 15x1 15x1 15x2.2 15x2.2 15x2.2 15x1.6 15x1 15x1 15x2.2 15x2 15x1 Total

0.87 0.87 1.18 1.13 1.18 0.92 0.92 0.89 0.90 0.77 0.90 0.75 0.75 0.75 1.02 1.02 900.26 sqm

1x1 Total

50 125 sqm

2.50

9x1 8x1 Total

2.85 2.50 94.08 sqm

3.20 0.60

Repairs to plaster of thickness 12 mm to 20 mm in patches of area 2.5 sqm with cement mortar (1:4).

Dismantling old plaster or skirting and raking out joints and cleaning the surface for plaster including disposal of rubbish to the dumping ground within 50 mts lead.

27

6.

7.

8.

9.

15 mm thick cement plaster on rough side of single or double brick wall of mix 1:6 Quantity same as Item 5 Extra for providing and mixing water proofing material in cement plaster work in proportion recommended by the manufacturers. Quantity same as Item 6 Providing and fixing fly proof 1x11 0.60 galvanized M.S wire gauge to windows and clerestory with 12 mm M.S beading. White vitreous china clay Orissa 1x2 pattern W.C pan of size 580x440 mm with integral type each foot rests. table 2.7 details of measurement table

28

0.45

2.97 sqm

2.00

2.1.6 BILL OF QUANTITY Sr. No 1.

2.

3.

4.

5.

6.

7.

8.

9.

Particulars of item Quantity Rate Amount Removing white or colour wash by 5.40 per Rs. 24661.69 scrapping and sand preparing the surface 4566.98 sqm smooth including necessary repairs to sqm scratches tec. completely. Distempering with oil-bound washable 93.oo per Rs. 424729.14 distemper of approved brand and sqm 4566.98 manufacture to give an even shade. New sqm work (two or more coats) including priming coat with cement primer. Painting with synthetic enamel paint of 48.60 per Rs. 43752.64 approved brand and manufacture of sqm 900.26 sqm required colour to give an even shade: two coats on old work Repairs to plaster of thickness 12 mm to 223.20 Rs. 27900.00 20 mm in patches of area 2.5 sqm with sqm 125.00 sqm cement mortar (1:4). Dismantling old plaster or skirting and 13.70 per Rs. 1288.90 raking out joints and cleaning the sqm 94.08 sqm surface for plaster including disposal of rubbish to the dumping ground within 50 mts lead. 15 mm thick cement plaster on rough 94.08 sqm 6057.24 Rs. 14704.70 side of single or double brick wall of per qtl mix 1:6 Extra for providing and mixing water 94.08 sqm 39.00 per Rs. 3669.12 proofing material in cement plaster work sqm in proportion recommended by the manufacturers. Providing and fixing fly proof 2.97 sqm 550.20 per Rs. 1634.09 galvanized M.S wire gauge to windows sqm and clerestory with 12 mm M.S beading. White vitreous china clay Orissa pattern 2.00 units 4855.50 Rs. 9711.00 W.C pan of size 580x440 mm with per sqm integral type each foot rests. Grand Total Rs. 5,52,051.28 table 2.4 Table for bill of quantity for U-type drain

29

table 2.8 bill of quantity for the work

Chapter 3: CONCLUSION 3.1 Conclusion The 6 weeks training that I received at PWD was great experience for me not only on technical terms but also in terms of interaction with other workers. I learnt a great deal on applying the knowledge I have gained at the University. Learning something from books and lectures is nothing like having firsthand experience. At Loadstar I got to apply my Civil Engineering knowledge. The company gives the full freedom for the trainee to get a sufficient training. The trainees are allowed to ask and do anything relevant to the training. Engineers are always very enthusiastic on giving us the best training experience. The employees do not think of their designation but only on the work to be done. Teamwork has been excellent and all of them are like best friends, even with lower ranked employees like Drivers, Office aids. And also they are most often at the sites with all kinds of employees. Everyone was friendly from top to bottom. Employees are busy with their work but they always help us to improve our knowledge. 3.2 Drawbacks during the training A drawback I see in PWD is that it has many health hazards. Employees are exposed to large amounts of dust. When inhaled, these particles can cause serious lung disease. Even though there is a rule to wear protective masks, employees do not do so most of the time. They should be urged to wear protective gear and lectured on negative consequences of not wearing them. Also unlike in CEB where the safety is measured by the number of accidents in a given time period, in Loadstar, it is the number of deaths that is shown. I attached the copy of the Certificate obtained by PWD. 3.3 Future Scope As an undergraduate of the Lovely professional University I would like to say that this training program is an excellent opportunity for us to get to the ground level and experience the things that we would have never gained through going straight into a job. I am grateful to Lovely professional University and PWD for giving us this wonderful opportunity. The main objective of the industrial training is to provide an opportunity to undergraduates to identify, observe and practice 30

how engineering is applicable in the real industry. It is not only to get experience on technical practices but also to observe management practices and to interact with fellow workers. It is easy to work with sophisticated machines, but not with people. The only chance that an undergraduate has to have this experience is the industrial training period. I feel I got the maximum out of that experience. Also I learnt the way of work in an organization, the importance of being punctual, the importance of maximum commitment, and the importance of team spirit. The training program having three destinations was a lot more useful than staying at one place throughout the whole six weeks. In my opinion, I have gained lots of knowledge and experience needed to be successful in a great engineering challenge, as in my opinion, Engineering is after all a Challenge, and not a Job.

31

View more...

Comments

Copyright ©2017 KUPDF Inc.
SUPPORT KUPDF