Substation Insulation Coordination Studies-Sparacino (1).pdf
Short Description
Download Substation Insulation Coordination Studies-Sparacino (1).pdf...
Description
Insulation Coordination Studies “The Selection of Insulation Strength”
March 25, 2014 Adam Sparacino
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES
Definition of Insulation Coordination1 • Insulation Coordination (IEEE) – The selection of insulation strength consistent with expected overvoltages to obtain an acceptable risk of failure. – The procedure for insulation coordination consists of (a) determination of the voltage stresses and (b) selection of the insulation strength to achieve the desired probability of failure. – The voltage stresses can be reduced by the application of surge‐ protective devices, switching device insertion resistors and controlled closing, shield wires, improved grounding, etc.
(1) IEEE Std 1313.1‐1996 “IEEE Standard for Insulation Coordination ‐ Definitions, Principles, and Rules. MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES
2
Four Basic Considerations • • • •
Understanding Insulation Stresses Understanding Insulation Strength Designing Methods for Controlling Stresses Designing Insulation Systems
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES
3
Four Basic Considerations • • • •
Understanding Insulation Stresses Understanding Insulation Strength Designing Methods for Controlling Stresses Designing Insulation Systems
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES
4
Definition of Overvoltages • Overvoltage – Abnormal voltage between two points of a system that is greater than the highest value appearing between the same two points under normal service conditions.2
• Overvoltages are the primary “metric” for “measuring” and “quantifying” power system transients and thus insulation stress.
(2) IEEE Std C62.22‐1991 ‐ IEEE Guide for the Application of Metal‐Oxide Surge Arresters for Alternating‐Current Systems, 1991. MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES
5
Vocabulary of Voltage
Peak line‐ground Voltage
RMS Voltage line‐ground = (Vpeak/√2)
Peak Voltage line‐ground = VL‐L_rms√2/√3
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES
6
Illustration of Overvoltages
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES
7
Four Basic Considerations • • • •
Understanding Insulation Stresses Understanding Insulation Strength Designing Methods for Controlling Stresses Designing Insulation Systems
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES
8
Electrical Insulation • Insulation can be expressed as a dielectric with a function to preserve the electrical integrity of the system. – The insulation can be “internal” (solid, liquid, or gaseous), which is protected from the effects of atmospheric conditions (e.g., transformer windings, cables, gas‐insulated substations, oil circuit breakers, etc.). – The insulation can be “external” (in air), which is exposed to atmospheric conditions (e.g., bushings, bus support insulators, disconnect switches, line insulators, air itself [tower windows, phase spacing], etc.).
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES
9
Insulation Strength Typical Volt Time Curve for Insulation Withstand Strength for Liquid Filled Transformers
Source: IEEE Std 62.22-1997, IEEE Guide for the Application of Metal-Oxide Surge Arresters for AC Systems MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES
10
Insulation Strength • Example for Transformers Windings – Normal system operating voltage • 345 kVL‐L_RMS (1.00 p.u.)
– Maximum continuous operating voltage (MCOV) • 362 kVL‐L_RMS (1.05 p.u.)
– Basic switching impulse insulation level (BSL) • 745/870/975 kVL‐N_Peak
– Basic lightning impulse insulation level (BSL) • 900/1050/1175 kVL‐N_Peak
– Chopped wave withstand (CWW) • 1035/1205/1350 kVL‐N_Peak
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES
11
Frequency of Different Events
10-20 minutes
seconds
Power System Control & Dynamics
Power Frequency
milliseconds
microseconds
Transients & Surges
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES
12
Four Basic Considerations • Understanding Insulation Stresses • Duty and Magnitude of applied voltage
• Understanding Insulation Strength • Ability to withstand applied stress
• Designing Methods for Controlling Stresses • Designing Insulation Systems
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES
13
Potential Overvoltage Mitigation 1. Surge Arresters –
Need to be sized and located properly to “clip” overvoltages.
2. Pre‐Insertion Resistors/Inductors –
Need to be sized according to equipment being switched (only help during breaker operation) to prevent excessive overvoltages from being initiated.
3. Synchronous‐Close/Open Control –
Need to use independent pole operated (IPO) breakers and program controller based on equipment being switched (only help during breaker operation) to prevent excessive overvoltages from being initiated.
4. Surge Capacitors –
Need to be sized and located to “slow” the front of incoming surges
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES
14
Four Basic Considerations • Understanding Insulation Stresses • Duty and Magnitude of applied voltage
• Understanding Insulation Strength • Ability to withstand applied stress
• Designing Methods for Controlling Stresses • Designing Insulation Systems
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES
15
Insulation Coordination Process 1. Specify the equipment insulation strength, the BIL and BSL of all equipment. 2. Specify the phase‐ground and phase‐phase clearances that should be considered. 3. Specify the need for, location, rating, and number of surge arresters.
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES
16
Insulation Coordination Studies 1. Very Fast Transients (VFT) Analysis (nanoseconds time frame) – – –
GIS disconnected switching. Quantify the overvoltages throughout the substation. Primary intent of determining location and number of surge arresters within the substation.
2. Lightning Surge Analysis (microseconds time frame) – –
Quantify the overvoltages throughout the substation. Primary intent of determining location and number of surge arresters within the substation.
3. Switching Overvoltage Analysis (milliseconds time frame) – – –
Quantify the overvoltages and surge arrester energy duties associated with switching events and fault/clear operations. Primary intent is to verify that transient overvoltage mitigating devices (e.g., surge arresters, pre‐insertion resistors, synchronous close control) are adequate to protect electrical equipment. Capacitor, Shunt Reactor, Transformer, and Line Switching Studies. MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES
17
Insulation Coordination Studies (cont.) 4. Temporary Overvoltage Analysis (seconds time frame) – – –
Quantify the overvoltages and surge arrester energy duties as produced by faults, resonance conditions, etc. Primary intent is to verify conditions that cause problems within the system and develop the necessary mitigation. Fault/Clear, load rejection, ferroresonance studies.
5. Steady State Analysis (minutes to hours time frame) – –
Quantify voltage during various system configurations. Power flow/stability studies.
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES
18
EXAMPLE APPLICATION STUDY FOR INSULATION COORDINATION LIGHTNING SURGE ANALYSIS
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES
19
500 kV LINE
Refer to Figure 2 for details of line terminations.
BML00
Refer to Figure 2 for details of line terminations.
BLU00
BML01
All lengths shown in meters.
BLU01
la = 30.70 lb = 25.66 lc = 21.76 la = 23.47 lb = 22.56 lc = 21.64
500 kV LINE
la = 21.19 lb = 20.74 lc = 23.64 la = 23.47 lb = 22.56 lc = 20.64
WEST 500 kV BUS GWB06
la,b,c = 8.323
la,b,c = 19.59
G752W
G952W
CB
CB
G752E
la = 26.42 lb = 25.51 lc = 24.59
la = 9.518 lb = 8.603 lc = 7.689
G762W
G962W
CB
CB G952E
CB
G762E
G772W
la = 12.47 lb = 11.55 lc = 10.64
EAST 500 kV BUS
CB
CB
G772E
G872E
GML00
la,b,c = 8.323
GEB06
la = 70.62 lb = 76.69 lc = 82.77
G972W
G872W
G4A00
DUMMY BUS (POSITION FOR FUTURE BREAKER)
XFMR
la,b,c = 5.634
CB
CB G962E
la,b,c = 19.59
G3A00
la,b,c = 8.323
la = 26.42 lb = 25.51 lc = 24.59
G972E
GLU00
la,b,c = 8.323
la,b,c = 5.634 la = 70.15 lb = 76.25 lc = 82.30
B3A01
B4A01
B3A00
B4A00
Refer to Figure 3 for details of XFMR terminations.
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES
XFMR
Refer to Figure 3 for details of XFMR terminations.
20
Example for Line/XFMR Termination 500 kV Line
Line Trap1
To Transformer
Surge Arrester
Gas-toAir Bushing
CCVT
To GIS Bay #6
Gas-to-Air Bushing 550 kV GIS
350 MCM Ground Lead (38’)
Surge Arrester
Notes
To GIS Bay 550 kV GIS
(1) Line traps only on phase A and C for 500 kV lines. In EMTP model, phase B has a 2.53 m section of conductor modeled in place of line trap.
350 MCM Ground Lead (38’)
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES
21
Detailed Analysis
Screening Analysis
Approach for Evaluation the Insulation Coordination of the 550 kV Gas‐Insulated Substation Step 1:
A severe voltage surge was injected into the substation for operating configurations to screen for maximum potential overvoltages.
Step 2:
The resulting overvoltages were compared to the Basic Lightning Impulse Insulation Level (BIL) of the equipment and the protective margin1 for the equipment was calculated.
Step 3:
If overvoltages resulted in less than a 20% protective margin in the initial screening analysis for cases with the full system in or N‐1 contingencies, a more detailed analysis was performed to identify the protective margins resulting from a reasonable upper bounds lightning surge based on the configuration of the substation and connected transmission lines. –
various
For the detailed analysis, specific details of the transmission lines such as conductor characteristics, shielding design, ground resistivity, keraunic level, etc. are considered to determine a reasonable upper bounds to place on the lightning surge impinging on the substation.
(1) Protective Margin = [ BIL / Vmaximum_peak – 1] x 100%
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES
22
Lightning Surge Incoming From 500 kV Line Phase‐to‐Ground Voltage of Incoming Lightning Surge
MLFULL_halfSRC>MLSRCA(Type 1)
4000
Peak = 3264 kV (1.2 x 2720 kV CFO) Time-to-peak = 0.5 microseconds.
Voltage (kV)
3000
2000 Lightning surge impinges substation from 500 kV Line.
1000 Lightning surge initiated at 1.0 microseconds.
0 0
5
10 Time (us) MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES
15
20
23
Lightning Surge Incoming From 500 kV Line Highest Phase‐to‐Ground Voltage Observed in GIS
MLFULLB>G752WB(Type 1)
2000
GIS Basic Impulse Insulation Level (BIL) = 1550 kV
Voltage (kV)
1500 Protective Margin = 40% ([1550/1109 – 1] x 100%)
Peak overvoltage = 1109 kV.
1000
500
0 0
5
10 Time (us) MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES
15
20
24
EXAMPLE APPLICATION STUDY FOR INSULATION COORDINATION TRANSMISSION LINE SWITCHING ANALYSIS
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES
25
Transmission Line Switching Analysis Potential Equipment Concerns • Excessive Transient Overvoltages and the Possibility of a Flashover During Energizing or Re‐Closing • Overvoltages Exceeding Guidelines Used to Develop Line Clearances Transmission line is energized (normal energizing or re-closing).
Applicable Criteria • •
Basic Switching Impulse Level (BSL) Probability of Flashovers
Potential Mitigation Techniques • • • •
Synchronous‐Close Control Pre‐Insertion Resistors/Inductors Surge Arresters Shunt Reactors
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES
26
Statistical Switching Methodology
Source-Side Voltage ¼ cycle window
Case simulated with 200-400 energizations 3 = ¼ cycle ÷ 2 = 2.08 ms Each pole can close at anytime within the ¼ cycle window centered around the closing time (Tclose) for each energization. Random closing times based on a normal (Gaussian) distribution Tclose Three poles closing centered around closing time (Tclose)
Sliding ¼ cycle window for pole closing shifted over a half cycle timeframe using a uniform distribution
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES
27
Electro‐Geometric Line Model Example 345 kV Transmission Line
14.5’
Shield Wire: Alumoweld 7#8 Outside diameter = 0.385” RDC = 2.40 Ohm/mi
14.5’
78’ (63’ at midpoint) B
C
A
27’
27’
54’ (24’ at midpoint) Center Line
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES
Phase Conductor: ACSR Lapwing 2/c Bundle 18” spacing Outside diameter = 1.504” RDC = 0.059 Ohm/mi Thick/Diam = 0.375
Line Length (total) = 85 mi Untransposed Ground resistivity = 37 Ohm‐m
28
Statistical Switching Overvoltage Strength Characteristics and SOV densities of the line
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES
29
Statistical Distr. Of Overvoltages Along 500 kV Line with NO Surge Arresters
Statistical Distribution of Overvoltages Along Line 110%
Statistical distribution based on the case‐peak method from IEEE Std 1313.2‐1999.
Probability to Exceed Overvoltage (%)
100% Estimated insulation withstand for the transmission line: CFO = 3.53 p.u., f/CFO =5%.
90% 80% 70%
Sending End
60%
1/4 Point
98% of the overvoltages along the line are ≤ 2.62 p.u. (1070 kV).
50% 40%
1/2 Point 3/4 Point
Highest overvoltage at the remote end of the line = 2.75 p.u. (1123 kV).
30% 20%
Remote End Example CFO
E2 is the value in which the overvoltages exceed 2% of the switching operations.
10% 0% 1.00
1.50
2.00
2.50
3.00
3.50
4.00
Peak Overvoltage (Per Unit on a 500 kV Base) MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES
30
Statistical Distr. Of Overvoltages Along 500 kV Line with Line End Surge Arresters
Statistical Distribution of Overvoltages Along Line 110%
Probability to Exceed Overvoltage (%)
100% Estimated insulation withstand for the transmission line: CFO = 3.53 p.u., f/CFO =5%.
90% 80%
Statistical distribution based on the case‐peak method from IEEE Std 1313.2‐1999.
70%
Sending End
60%
1/4 Point 98% of the overvoltages along the line are ≤ 2.16 p.u. (882 kV).
50%
1/2 Point 3/4 Point
40%
Remote End 30%
Example CFO
20%
Highest overvoltage along the line = 2.21 p.u. (902 kV).
E2 is the value in which the overvoltages exceed 2% of the switching operations.
10% 0% 1.00
1.50
2.00
2.50
3.00
3.50
4.00
Peak Overvoltage (Per Unit on a 500 kV Base) MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES
31
EXAMPLE APPLICATION STUDY FOR INSULATION COORDINATION SHUNT CAPACITOR SWITCHING ANALYSIS
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES
32
Shunt Capacitor Switching Analysis
Capacitor bank is energized and transient inrush currents flow through capacitor bank breaker and voltage surges propagate into the system.
Potential Equipment Concerns • Contact Wear from Excessive Inrush Current Duty • Excessive Transient Overvoltages • Induced Voltages and Currents in Control Circuits • Step and Touch Potentials During Switching Applicable Criteria • ANSI/IEEE Inrush Current Limits • Basic Switching Impulse Level (BSL) • Breaker Capability Beyond Standards • IEEE Std 80 for grounding Potential Mitigation Techniques • Current‐Limiting Reactors • Synchronous‐Close Control • Pre‐Insertion Resistors/Inductors • Surge Arresters MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES
33
Capacitor Bank Re‐Strike During De‐Energization Current Through Switching Device High frequency current is interrupted
First restrike occurs and current is re‐ established
Second restrike occurs and current is re‐established
Voltage on Each Side of Switching Device Peak overvoltage from 1st restrike
Voltage on system side of switching device
Current is interrupted Voltage on capacitor bank side of switching device (DC trapped charge) Peak overvoltage from 2nd restrike
MITSUBISHI ELECTRIC POWER PRODUCTS, INC. POWER SYSTEM ENGINEERING SERVICES
34
Voltage Magnification • When a shunt capacitor bank is energized with a nearby capacitor at a lower voltage, the potential for voltage magnification may exist when the following condition is true: 1
1
2
2
• Furthermore, when C1>>C2, and L1
View more...
Comments