Standard Specification for Hot Insulation (Piping & Equipment)
April 17, 2017 | Author: Wade Coleman | Category: N/A
Short Description
Download Standard Specification for Hot Insulation (Piping & Equipment)...
Description
DOC NO . : QPS-PI-HI-101
STANDARD SPECIFICATION F0R HOT INSULATION
SHEET
PROCESS SOLUTIONS PVT. LTD.
:
I
REV
: 0
DATE
: 21.11.10
STANDARD SPECIFICATION FOR HOT INSULATION (PIPING & EQUIPMENT)
0
21.11.10
Issued As Standard
S R Patil
PID
BKD
REV.
DATE
DESCRIPTION
PREPARED
REVIEWED
APPROVED
BY
BY
BY
NO.
DOC NO . : QPS-PI-HI-101
STANDARD SPECIFICATION F0R HOT INSULATION
PROCESS SOLUTIONS PVT. LTD.
SHEET
:
II
REV
: 0
DATE
: 21.11.10
INDEX SECTION
TITLE
NO.
PAGE NO.
1.0
GENERAL
1
2.0
DESIGN BASIS
2
3.0
EXTENT OF INSULATION ON PIPING SYSTEM
3
4.0
EXTENT OF INSULATION OF EQUIPMENT
4
5.0
MATERIALS GENERAL
5
6.0
INSULATION MATERIAL FIBROUS MATERIAL (ROCK & GLASS WOOL)
6
7.0
INSULATION MATERIAL (CELLULAR GLASS )
9
8.0
WEATHER PROTECTION JACKET
11
8.1 FIBROUS MATERIAL (ROCK & GLASS WOOL) 8.2 REGID MATERIAL (CELLUAR GLASS) 8.3 ANCILLIAR MATERIALS 9.0
APPLICATION METHODS (GENERAL)
13
10.0
PIPING
15
11.0
HORIZONTAL EQUIPMENT
20
12.0
VERTICAL EQUIPMENT
22
13.0
FLANGE, NOZZLE, CHANNEL, COVER, MANWAY AND HANDHOLE FLANGED COVER.
23
14.0
IRREGULAR SURFACES SUCH AS PUMP, COMPRESSOR, TURBINE ETC.
24
15.0
VERTICAL STORAGE TANK
25
16.0
INSULATION FINISH (CARBON SETEEL)
27
16.1 PIPING 16.2 EQUIPMENT 16.3 VERTICAL STORAGE TANK 17.0
ANNEXURE – I
31
17.1 OWNER’S OBLIGATIONS 17.2 CONTRACTORS CONDITIONS 18.0
ANNEXURE – II
32
INSULATION THICKNESS FOR HOT INSULATION (IH) 19.0
ANNEXURE – III INSULATION THICKNESS FOR PERSONAL INSULATION (IS)
33
DOC NO . : QPS-PI-HI-101
STANDARD SPECIFICATION F0R HOT INSULATION
SHEET
PROCESS SOLUTIONS PVT. LTD.
:
III
REV
: 0
DATE
: 21.11.10
STANDARD SKETCHES FOR HOT INSULATION STANDARD OF VESSELS, PIPING AND EQUIPMENT FIG. NO.
DESCRIPTION
SHEET
01
FIBROUS AND APPLICATION
02
METHOD OF STAGGERING OF SECTION FOR PIPE INSULATION
35
03
FIBROUS MATTRESS INSULATION - DETAILS SPACER RINGS FOR CLADDING SUPPORT (FOR HORIZONTAL PIPE)
36
04
DETAIL OF SPACER RING FOR FIBROUS INSULATION (MATTRESS)
37
05
BOLTED-ON INSULATION SUPPORT FOR VERTICAL PIPE
38
06
INSULATION DETAILS FOR PIPES, BENDS & ELBOWS
39
07
INSULATION DETAILS FOR BENDS & ELBOWS
40
08
INSULATION DETAILS FOR PIPE BRANCHES AND REDUCERS
41
09
INSULATED REMOVABLE COVERS FOR VALVES
42
10
INSULATED REMOVABLE COVERS FOR FLANGED JOINTS
43
11
INSULATED DETAILS FOR LINES ON SHOE
44
12
INSULATION OF STEAM TRACED PIPING
45
13
INSULATION FOR HORIZONTAL EQUIPMENT
46
14
INSULATION FOR EQUIPMENT HORIZONTAL HEADS
47
15
USE OF FLEXIBLE INSULATION IN COMBINATION WITH RIGID INSULATION TO COMPENSATE FOR VESSEL EXPANSION
48
16
INSULATION DETAILS FOR VERTICAL VESSELS
49
17
INSULATION DETAILS FOR VERTICAL VESSEL HEADS
50
18
INSULATION DETAILS FOR VERTICAL VESSEL (`J’ & `S’ CLIPS)
51
19
INSULATION DETAILS FOR VERTICAL STORAGE TANKS
52
20
INSULATION SUPPORTS FOR STORAGE TANKS
53
21
INSULATION SUPPORTS FOR STORAGE TANKS (DETAILS FOR ROOF)
54
22
FIRE PROOFING AND INSULATION SUPPORT FOR VERTICAL VESSEL
55
23
MACHINERY INSULATION
56
24
INSULATION ENCLOUSERS FOR CONTROL VALVES & OTHER IN-LINE INSTRUMENTS
57
25
INSULATIN FOR LEVEL GAUGES
58
26
INSULATION SUPPORTS FOR HORIZONTAL VESSEL
59
REGID
INSULATION
DETAILS
FOR
HORIZONTAL
PIPE
34
STANDARD SPECIFICATION FOR HOT INSULATION
PROCESS SOLUTIONS PVT. LTD.
PIPING AND EQUIPMENT
DOC NO . : QPS-PI-HI-101 SHEET
: 1 OF 59
REV
: 0
DATE
: 21.11.10
1.0 GENERAL: SCOPE 1.1
This specification covers design and material requirements for above ground, external insulation of piping and equipment operating between ambient temperature and 550 °C for the purpose of heat conservation, process stabilization, temperature maintenance, personnel protection and fire protection. Wherever necessary this specification indicates the basis for selecting a criterion.
1.2
This specification is suitable for use in out door service with normal process plant atmospheres. Alternative designs and materials would be specified if necessary for corrosive atmosphere of potential leaks and spills of chemicals.
1.3
This specification does not cover cold service insulation. For cold services QPS Specification QPS-PI-CI-101 is applicable.
1.4
This specification does not cover insulation for boiler or fired heaters and associated air heaters, economizers, fuel ducting and air ducting.
1.5
Piping, equipment, storage tanks and vessels requiring insulation shall normally be specified on the following project documents. a) Process and Instrument Diagrams (P&IDs) and Line List. b) Piping General Arrangement Drawings & Isometrics. c) Instrument Piping Details and Schedules. d) Vessel, Exchanger, Storage Tank & sphere documents and Insulation Schedules e) Equipment supplier’s General Arrangement Drawing for equipment items in package plant.
STANDARD SPECIFICATION FOR HOT INSULATION
PROCESS SOLUTIONS PVT. LTD.
PIPING AND EQUIPMENT
DOC NO . : QPS-PI-HI-101 SHEET
: 2 OF 59
REV
: 0
DATE
: 21.11.10
2.0 DESIGN BASIS: CRITERIA 2.1
Heat Conservation Insulation is designed for economic thickness and to limit cold surface temperatures below 65 °C with 20 °C ambient temperature in still air conditions.
2.2
Internally refractory lined piping and equipment and any other items for which heat loss is essential shall not be insulated. (See para 4.6-D)
2.3
Insulation is not required for piping and equipment for which heat loss is desired - excepting for personnel protection or to avoid thermal stress problems.
2.4
Insulation is required for any of the following purposes, as indicated in P&IDs and line lists: a) Heat conservation. b) Process stabilization to assist process control. c) Steam tracing. d) Electric tracing. e) Hot water of solvent tracing (liquid). f)
Hot Oil tracing.
g) Steam jacketing. h) Hot water or liquid jacketing. i)
Hot Oil jacketing.
j)
Fire hazard protection to prevent fast boil off of liquid.
k) Personnel protection. Applicable where exposed surface temperature exceeds 65°C in normal or short-term operating conditions. Over internally insulated piping and equipment, provide open mesh metal guards and for surfaces which are not internally insulated provide insulation on that part of surfaces with which operating and maintenance personnel may come in contact while performing routine duties. The intent of P&IDs, Line classification lists and engineering drawings etc. which designate insulation for personnel protection is to call attention only to the eligibility of such service. The actual extent of insulation shall be determined by Field Construction Personnel and/or operating personnel using the following
criteria: Exposed surfaces operating above 65 °C and
located within 600 mm horizontally or 2100mm vertically of a normal access, walkway of work area. 2.5
Instruments and associated piping subject to operating flow and/or temperature conditions prevailing in the connected piping or equipment shall be insulated to the same requirements as that of piping or equipment.
STANDARD SPECIFICATION FOR HOT INSULATION
PROCESS SOLUTIONS PVT. LTD.
PIPING AND EQUIPMENT
DOC NO . : QPS-PI-HI-101 SHEET
: 3 OF 59
REV
: 0
DATE
: 21.11.10
3.0 EXTENT OF INSULATION ON PIPING SYSTEM: 3.1
Insulated piping systems shall have straight pipe, bends, tees and pipe fittings completely insulated.
3.2
All valves and flanged joints shall be completely insulated only on in steam, condensate service, hot oil lines and in lines which are steam trace heated or jacketed to maintain temperature.
3.3
For bucket and float type traps, the inlet piping and trap shall be insulated.
3.4
Insulation on inlet piping to thermostatic and thermodynamic steam traps shall terminate at approximately 500mm before the trap.
3.5
Steam trap outlet piping other than closed condensate recovery system shall not be insulated except for personnel protection reasons.
3.6
Instrumentation to be insulated, such as level gages, level controllers, level switches, DP cells, shall have their fluid containing sections and the associated piping completely insulated, including pipes, valves and fittings.
3.7
Insulation shall not be applied to the following, unless otherwise specified. a) Piping which becomes hot intermittently, such as relief valves, vents, steam-out and snuffing steam systems flare and blow-down systems. b) Supports for piping, excluding pipe hangers to the extent covered by insulation. c) Steam Traps (except as noted in paragraph 3.3). d) Valves, including control valves and flanges in process piping systems (except as noted in 3.2 and 3.8). However, personnel protection insulation for these items shall be applied, as required. e) Pipe Union fittings. f)
Thermowell bosses and pressure tappings.
g) Expansion joints, hinged joints and hose. h) Sight flow indicators. 3.8
Insulation shall be designed to provide an absolute minimum clearance of 25mm between the outside surface of any insulation finishing material and adjacent surfaces.
3.9
Where insulated horizontal piping is supported on steel shoes, the height of the shoe shall be such that the underside of the insulation finishing material is clear of the supporting structures upon which the shoe rests by 25mm minimum.
STANDARD SPECIFICATION FOR HOT INSULATION
PROCESS SOLUTIONS PVT. LTD.
PIPING AND EQUIPMENT
DOC NO . : QPS-PI-HI-101 SHEET
: 4 OF 59
REV
: 0
DATE
: 21.11.10
4.0 EXTENT OF INSULATION ON EQUIPMENT: 4.1
Support skirts of insulated vertical vessel greater than 1200mm diameter shall be insulated both internally and externally for a minimum distance of 600mm below the bottom tangent line. The insulation shall terminate not less than 300mm above the support concrete or steel work.
4.2
Support skirts of insulated vertical vessels of 1200mm and less shall be insulated externally only, as described in Para 4.1 above.
4.3
Bottom heads of insulated vertical vessels enclosed by a support skirt shall be insulated without finishing material and shall be insulated only when the vessel outside diameter is greater than 1200mm.
4.4
Turbines and steam ends of reciprocating pump shall be insulated for heat conservation.
4.5
Liquid ends of pumps shall be insulated when heat traced or jacketed.
4.6
Insulation shall not be applied to the following unless otherwise specified. a) Pumps with operating temperature below 200 °C unless pumped fluid has a pour point above minimum design ambient temperature. b) Fans, compressors, blowers or other rotating or reciprocating requirement. c) Liquid ends of pumps except as noted in the Para 4.5 above. d) Internally insulated or refractory lined equipment unless specially designed for metal temperature control. e) Heads of vessels enclosed by support skirts with vessel diameters 1200mm and less. f)
Internal surfaces of insulated vessel support skirts with vessel diameter 1200mm or less.
g) Turbine casings to be insulated shall exclude shaft seal caps, shaft bearing housings, throttle valves, governors and supports. h) Exchanger channel and covers; shell and channel flanges & Exp. Joints. i)
Nozzles, manholes and hand holes and flanges of equipment.
j)
Surfaces of coolers and condensers.
k) Nameplates of all equipment items. l)
Thermowell bosses and pressure tappings.
STANDARD SPECIFICATION FOR HOT INSULATION
PROCESS SOLUTIONS PVT. LTD.
PIPING AND EQUIPMENT
DOC NO . : QPS-PI-HI-101 SHEET
: 5 OF 59
REV
: 0
DATE
: 21.11.10
5.0 MATERIALS GENERAL: 5.1
All material shall be of high quality and good appearance. This specification covers three materials - Rock wool, Glass Wool and cellular glass.
5.2
Insulation materials shall be of low chloride content, chemically inert, non-sulphurous, rot proof, vermin proof, impervious to hot water and steam, non-injurious to health and noncorrosive to steel and aluminum (even if soaked in water at ambient temperatures for extended periods).
5.3
The use of insulation or finishing materials containing ASBESTOS in any form is not permitted.
5.4
Insulation and jacketing material backed with paper or other flammable material is not acceptable.
5.5
Many common flammable liquids such as oil, butanol, diethanolamine and hexanol will react and start fires when they leak into inorganic absorbent insulation. Such absorbent insulation can store large quantities of combustible liquids should a leak occur. This could be a decisive factor when specifying and evaluating alternative materials and are taken care of by QUANTA / CLIENT while specifying project insulation specifications.
5.6
Insulation materials have been classified into two categories – i) water absorbing ii) nonwater absorbing. Non-water absorbing insulates like cellular glass is recommended for services upto 125 °C. Water absorbing insulation lake fibrous insulation and calcium silicate can be used for all temperatures except for electrically traced pipe. But for low temperature (i.e. upto 125 °C) services a suitable moisture barrier shall be used since the substrata is at too low temperature to evaporate moisture, rain or water.
STANDARD SPECIFICATION FOR HOT INSULATION
PROCESS SOLUTIONS PVT. LTD.
PIPING AND EQUIPMENT
DOC NO . : QPS-PI-HI-101 SHEET
: 6 OF 59
REV
: 0
DATE
: 21.11.10
6.0 INSULATION MATERIAL: FIBROUS MATERIAL (ROCK & GLASS WOOL) 6.1
Shall be a performed insulation and shall be of long fiber rock or glass material processed from a molten state into fibrous form bonded operational temp. range from ambient to 550 °C. Slag wool is not acceptable.
6.2
Unless otherwise specified herein, insulation material shall strictly conform to all the requirements of quality standards listed below : • Performed pipe insulation.
- IS : 9842 : Latest issue
• Metal-mesh covered
- IS : 8183 : Latest issue for piping & equipment.
bonded mineral fibre
Faced on one side with 20mm galvanised No. 22 SWG. Wire
blanket & blanket type
Mesh, Stitched through with 22 SWG. galvanised lacing wire
pipe insulation.
: Mattress for Lined covdrs shall be faced on one side with 20mm galvanised 22 SWG wire mesh stitched through with 22 SWG galvanised lacing wire.
• Mineral Fibre blocks &
- IS : 8183 : Latest issue
board thermal insulation. 6.3
Insulation shall conform to following requirement and shall be tested and test certificate on representative samples furnished to PURCHASER as per IS : 8183 / IS : 9842 (latest issue) for conformance of each of the following requirements. • Density
- 140 to 150 kg/m3 (Density shall be within this range and density test shall be as per IS:5688/ IS : 3144 (Latest issue)
• Shot Content
- Shot shall not be more than 5mm in any dimensions, shot
(IS : 3144)
content, when sieved as follows, shall not exceed as per below : IS Sieve Shot Content, Percent (IS:460 by Mass (Max.) (Latest issue).
• Moisture content and
500 micron
5
250 micron
15
- Not more than 2 %
moisture absorption (IS : 3144) • Incombustibility
- Incombustible; Loss in weight not more then 5 %
(IS : 3144) • Thermal Conductivity (IS : 3346)
DOC NO . : QPS-PI-HI-101
STANDARD SPECIFICATION FOR HOT INSULATION
PROCESS SOLUTIONS PVT. LTD.
PIPING AND EQUIPMENT
* Mean Temperature
SHEET
: 7 OF 59
REV
: 0
DATE
: 21.11.10
Thermal / Conductivity mw/cm °C
°C 50
0.43
100
0.52
150
0.62
200
0.68
250
0.80
300
0.90
* Mean Temperature is Hot Face Temp. + Cold face Temperature. 2 - Not more then 0.6 percent. • Sulphur Content (IS : 3144) • Liner Shrinkage (IS : 3144)
- Not more then 2 percent when subjected to soaking conditions of soaking heat at the stated max. temp. of use (550 °C) for 24 hours.
Heat Resistance (IS : 3144)
- When heated to max. temp. (550 °C), sample shall maintain its general form and shall not suffer visible deformation of the fibrous structure.
• Compressive Strength
- 120 kg/m2
(Average) min. at 10 % deformation • Recovery after compression (IS : 8183-
- After compression to 75 % of the original thickness, recovery shall not be less than 90% of thickness.
Appendix ‘A’ IS : 9842Appendix ‘A’) • Alkalinity (IS : 8183 Appendix ‘B’ / IS : 9842
- pH of the solution of the material shall be between 7.0 and 10.0
Appendix ‘B’) • Chloride Content
- Not to exceed 20 ppm
( IS : 3144 ) • Dimension
- PIPE SECTION : Hollow cylinder, split length wise on one or both sides of the cylindrical axis. Thickness Length
: 25, 40, 50, 60 & 75mm Tolerance in : ± 3 mm Tolerance in
Thickness : ± 3 mm When installed on the pipe of the specified size, sections shall
STANDARD SPECIFICATION FOR HOT INSULATION
PROCESS SOLUTIONS PVT. LTD.
PIPING AND EQUIPMENT
DOC NO . : QPS-PI-HI-101 SHEET
: 8 OF 59
REV
: 0
DATE
: 21.11.10
fit snugly and shall have tight longitudinal and circumferential joint. - BLANKET : Unless otherwise specifically required, standard width shall be 600mm to 1200mm, standard length 1500mm to 2400mm Thickness
: 25, 30, 40, 50, 60 & 75 mm
Tolerance on thickness : Positive
: 3mm
Negative
: -3mm
- BLOCK AND BOARDS ( IS : 8183 ) : Lengths
: 1000mm to 1400mm
widths
: 500mm to 1000mm
Tolerance : ± 3mm Thickness : ± 3mm
STANDARD SPECIFICATION FOR HOT INSULATION
PROCESS SOLUTIONS PVT. LTD.
PIPING AND EQUIPMENT
DOC NO . : QPS-PI-HI-101 SHEET
: 9 OF 59
REV
: 0
DATE
: 21.11.10
7.0 INSULATION MATERIAL (CELLULAR GLASS): Cellular Glass foamed and fused into unicellular form can be used upto a temperature of 425 °C. But in view of high thermal conductivity, its use is limited in this specification to 125 °C only as it has been included essentially for its non-water absorbing nature. Insulation shall conform to following requirements and test certificates on representative samples shall be furnished to PURCHASER as per ASTM C552 for conformance to each of the following requirements: Density 110 to 150 kg/m3
: Test as per ASTM C303 except that on drying will be necessary. Determine the No. of specimens as per ASTM C390.
Thermal conductivity (average max.) Mean Temp. °C
W/m°k
10
0.058
24
0.060
38
0.062
93
0.073
149
0.086
Test thermal conductivity as per ASTM C240, C177 and C518. Test shall be at least for 3 specimens. Compressive Strength : 517 kPa (average min.) Test method as per ASTM C240 and Recommended Practice ASTM C165. Test shall be at least for 4 specimens. Flexural strength average min. 414 kPa. Test method as per ASTM C240 and clause ASTM 3.4 C203. Determine the method of test specimens as per method given in ASTM C390. Water absorption, volume % (average max.) 0.5. Test method as per ASTM C240. Test shall be at least for 3 specimens. Water vapour transmission (average max.) metric perm-cm of grains/24 h.m2 mm Hg. cm of thickness at 26.7 °C : 0.0084. Test method as per ASTM E96. Test shall be at least for 2 specimens.
DOC NO . : QPS-PI-HI-101
STANDARD SPECIFICATION FOR HOT INSULATION
PROCESS SOLUTIONS PVT. LTD.
PIPING AND EQUIPMENT
SHEET
: 10 OF 59
REV
: 0
DATE
: 21.11.10
Dimensions: Flat Blocks: Shall be rectangular sections and shall be true to form and dimensions, the corners square and the sides parallel. Size and thickness shall be as follows: Width (mm)
Length (mm)
300
450
450
600
Pipe Sections : Shall be supplied as hollow cylindrical shapes split in half lengthwise (in a plane including the cylindrical axis) or as curved segments. Upto 350mm Ø size, only pipe sections split in half lengthwise shall be used. The insulation shall be supplied in sections of segments in lengths of 450mm or 600mm to fit standard of pipe. Insulation for pipes upto 150mm Ø size shall be furnished in 600mm length, and for pipe above 150mm Ø nom. size in 450mm length. Thickness for both pipe sections and flat blocks shall be 25, 30, 40, 50, 60 & 75mm. Dimensional Tolerance shall be as follows: Block
Pipe
Length
± 1.6 mm
± 3 mm
Width
± 1.6 mm
--
Thickness
± 1.6 mm
± 3 mm
GENERAL: Periodical checks for density, thickness, shape and size as per above requirements shall be repeated at site, as per norms and frequency decided at site as per the directions of PROJECT Site-in-Charge. Special attention is required for fibrous material as its installed thickness could be reduced due to compression affecting performance. a) All the codes mentioned shall be the latest issue. b) PURCHASER shall have right to inspect any or all the test conducted on insulation material by manufacturer at his shop or at any laboratory.
DOC NO . : QPS-PI-HI-101
STANDARD SPECIFICATION FOR HOT INSULATION
PROCESS SOLUTIONS PVT. LTD.
PIPING AND EQUIPMENT
SHEET
: 11 OF 59
REV
: 0
DATE
: 21.11.10
8.0 WEATHER PROTECTION JACKET: Aluminium jacketing shall be used as weather protection over insulation unless otherwise specified and shall be ASTM B209 alloy 3003 H16 or IS : 737 designation 31000 (Old NS3 ) condition H3 for flat sheets and H4 for corrugated sheets. Cladding shall be coated on the side in contact with the insulation with a bitumen anti-corrosive paint.
8.1 FIBROUS MATERIAL (ROCK & GLASS WOOL): a)
For shells of vertical Storage, Tanks & Vessels
: 0.71mm (22 SWG) corrugated
b)
For tanks Roofs
: 1.22mm (18 SWG) Flat
c)
For Horizontal vessels shell and heads; vertical
: 0.71mm (22 SWG) Flat
vessel heads. d)
For removable cover
: 1.22mm (18 SWG) Flat
e)
For all piping, other than grade piping in off-
: 0.71mm (22 SWG) Flat
sites. f)
For grade piping in off-sites
: 0.56mm (24 SWG) galvanised steel, per IS : 277 class I
8.2 RIGID MATERIAL (CELLULAR GLASS): a)
Piping, Horizontal Vessel, Vessel head & Tanks
: 0.56mm (24 SWG) Flat
Roof b)
Vertical Vessel Shells & Vertical portion of
: 0.56mm (24 SWG) corrugated
Storage Tanks c)
Removable covers
: 1.22mm (18 SWG) Flat
8.3 ANCILLARY MATERIALS: 8.4
Aluminium Foil to protect Stainless Steel surfaces shall be 0.19mm (36 SWG) thick per ASTM B209 Alloy 3003 H16 or IS : 737 designation 31000 (old NS3) condition H3.
8.5
Securement Bands / Wires
8.6
If material is Aluminium, then specification shall be ASTM B209 Alloy 3003 H16 or IS : 737 designation 31000 (old NS3) condition H3; If Stainless Steel, it shall be 18/8.
8.7
For securing Aluminium foil on Stainless Steel surfaces : Band, 24 SWG thick X 20mm wide, Aluminium.
8.8
For Securing Fibrous Insulation a) On Piping. b) Band, 24 SWG thick X 12mm (min.) wide, Aluminium. c) On Equipments. d) Band, 24 SWG thick X 20 wide, Aluminium.
STANDARD SPECIFICATION FOR HOT INSULATION
PROCESS SOLUTIONS PVT. LTD.
PIPING AND EQUIPMENT
DOC NO . : QPS-PI-HI-101 SHEET
: 12 OF 59
REV
: 0
DATE
: 21.11.10
e) On Vertical Storage Tanks. f) 8.9
Band, glavanised steel, 40mm wide X 3mm thk. galvanising per IS : 277 class-2.
For Securing Rigid Insulation: a) On Piping upto 16” OD. Wire, annealed galvanised steel, 16 SWG, galvanised per class 2 (heavy coating of zinc, nominal 600 g/m2) per IS : 227. b) On Piping 18” OD and Larger. Band, galvanised steel, 20 wide X 24 SWG thk., galvanising per above (same as for piping upto 16” OD). c) On Vertical & Horizontal Vessels. Band, galvanised steel, 20 wide X 24 SWG thk, galvanising per above (same as for piping upto 16” OD).
8.10 For Securing Cladding On Insulation (Both Fibrous And Rigid): a) For Piping: Band, Aluminium 12 mm (min.) wide X 24 SWG thk. b) On Equipment: Band, Aluminium, 20 mm wide X 24 SWG thk. c) On Vertical Storage Tanks: Band, Stainless Steel, 25 mm wide X 24 SWG thk. 8.11 Rivets: Rivets required for metal jacket securement shall be the expanding Aluminium “POP” blind eye type, 9.5mm long X 5mm Ø. 8.12 Screws: Screws required for metal jacket securement shall be cadmium plated steel, self tapping type A No. 8mm Ø X 12mm long to BS 4176 complete with neoprene washers under the head. 8.13 ‘S’ and ‘J’ clips - Formed from 25mm wide stainless steel banding. 8.14 To ensure prefect water proofing, all the cladding joints shall be packed with sealing materials which may either be in the from of a elastomeric sealing compound or fiber based bituminous felt strips.
STANDARD SPECIFICATION FOR HOT INSULATION
PROCESS SOLUTIONS PVT. LTD.
PIPING AND EQUIPMENT
DOC NO . : QPS-PI-HI-101 SHEET
: 13 OF 59
REV
: 0
DATE
: 21.11.10
9.0 APPLICATION METHODS (GENERAL): 9.1
The application methods, given in this Standard are general in nature. The Contractor is responsible for applying an insulating system that will give a satisfactory operational performance and the requirement given herein shall be regarded as the acceptable minimum. The Contractor shall carryout the work in accordance with the best practices of insulation application with the minimum of waste and debris and the final job shall have a neat, efficient and work a like appearance.
9.2
All hydrostatic tests on piping and equipment, including steam tracing systems, shall be carried out before insulating material is applied. The insulation Contractor shall only insulate those sections of the plant that has been specifically released for such work by the engineer-in-charge. If insulation must be installed before pressure test, then all welds and flanged joints in the pipe shall be left uncovered till successful completion of pressure test. Then insulation shall be completed.
9.3
Surfaces to be insulated shall be thoroughly cleaned, dried and made free from loose scale, oil or grease. It shall be the Contractor’s responsibility to remove loosely adhering scale and dirt before applying insulation.
9.4
Corrosion Prevention: Carbon steel and low alloy piping and equipment with normal operating temp. of 125 °C and below shall be protected against corrosion by painting with a 20 microns (min.) dry film thickness of heat resistant Aluminium paint suitable for the above temperature. While for equipments (Vessels, Exchangers and Tanks), this coating shall be provided by equipment fabricator, for piping, it shall be provided by insulation contractor or equipment and piping painting contractor.
9.5
Insulation cement shall not be used on stainless steel piping or equipment.
9.6
All insulated austentic stainless steel piping and equipment insulated with Rock or Glass Wool shall be protected against chloride attack as follows: For operating temperatures upto 450 °C, the surfaces shall be wrapped with 0.19mm thick Aluminium foil with 50mm overlap at longitudinal and circumferential joints before application of insulation. All joints of the Aluminium foil shall have barium chromate primer interposed. Aluminium foil shall be firmly secured on the stainless steel surfaces by Aluminium bands at a pitch of 500mm. Care shall be taken while applying Aluminium foil to ensure that the foil is not punctured at any place during wrapping and clamping with Aluminium bands. For operating temperature above 450 °C, the stainless steel surfaces shall be painted with two coats of heat resistant silicon Aluminium paint as follows :
STANDARD SPECIFICATION FOR HOT INSULATION
PROCESS SOLUTIONS PVT. LTD.
PIPING AND EQUIPMENT
DOC NO . : QPS-PI-HI-101 SHEET
: 14 OF 59
REV
: 0
DATE
: 21.11.10
Type
: Single
Composition
: Silicon resin based with Aluminium flakes as pigment
Dry Film Thickness
: 20 microns/coat (min.)
Other requirements
: It should be suitable to withstand temperature upto 600 °C; when the paint becomes dry, the painted surfaces shall show no discontinuity.
9.7
The insulation contractor shall not carryout any welding or drilling on plant equipment and piping.
9.8
Insulation shall be finished, beveled and weatherproofed at all terminal points where it is required to remove bolts etc. without damage to the insulation.
9.9
Equipment name plates shall remain visible after insulation has been applied by beveling back the insulating material and carefully sealing the exposed edges to prevent ingress of moisture.
9.10 All projections, such as lifting lugs, trunnions and stiffeners on piping and equipment (i.e. vacuum rings) shall be insulated with the same thickness of insulation as specified for the equipment item or pipeline. 9.11 Thermowell bosses, pressure tappings and weep-hole nipples shall not be insulated in but left accessible. 9.12 Double layer insulation shall be required when the insulation thickness is greater than 75mm. Insulation installed in two or more layers shall be staggered joint construction and each layer shall be secured in place and details of securement shall be the same for each layer. 9.13 Wet or Damage Insulation shall not be used under any Circumstances. Insulation material to be applied shall not be kept over bare ground to avoid water absorption. Installed material awaiting its protective cover shall be adequately protected from damage, rain and contamination, and shall be covered with cladding at a minimum loss of time. 9.14 A minimum clearance of 25mm between outside surface of any insulation finish and adjacent equipment, pipe or structural members shall be maintained. 9.15 Insulation supports shall not project out of the insulation outer surface and shall be given sufficient coverage of insulating material to avoid hot spots on the metallic cover at support positions.
STANDARD SPECIFICATION FOR HOT INSULATION
PROCESS SOLUTIONS PVT. LTD.
PIPING AND EQUIPMENT
DOC NO . : QPS-PI-HI-101 SHEET
: 15 OF 59
REV
: 0
DATE
: 21.11.10
10.0 PIPING: 10.1
MATERIAL:
10.2
FIBROUS MATERIAL (ROCK OR GLASS WOOL): a) Can be used for all piping other than electrical traced pipes upto 125 °C. b) Can be used for all temperatures. c) Shall be in performed pipe section in 2 halves for sizes upto which manufactured and at least for all pipes with outside diameter over insulation of 500mm. In bigger sizes, multisegments are preferable if manufactured, otherwise, blankets are acceptable. d) Pieces of insulation with crushed and damaged ends shall not be used.
10.3
CELLULAR GLASS: a) Can be used for all piping including electrically traced piping for service temperatures below 125 °C (with electrical and steam tracing the maximum metal temperature reached by tracer in order to conduct the requisite heat into the pipe shall be the deciding factor).
b) In-situ foaming may be allowed by engineering-charge after discussions with client and head-office.
10.4
CORROSION PROTECTION BEFORE APPLYING INSULATION (All Insulation Materials) : a) For operating temperature Upto 125 °C, on carbon and alloy steel piping, provide painting as per 9.4. b) For austentic stainless steel piping, provide Aluminium harrier, as per Clause 9.6.
10.5
APPLICATION METHODS (General) : Insulation material shall be applied to fit snugly against the contours and shaped only where necessary to achieve this requirement. The insulation shall be carried out with the least number of material pieces as possible and all unavoidable gaps, cavities, and voids suitably filled with compatible loose fill material.
10.6
Pipe Section / Molded Blocks / Segments: a) End joints of adjacent blocks shall be staggered one half of the length of the block. b) Included angle between segments shall not be less than 30° for both single and double layer insulation, c) Further, minimum arc length of segments should meet following staggering requirements.
STANDARD SPECIFICATION FOR HOT INSULATION
PROCESS SOLUTIONS PVT. LTD.
PIPING AND EQUIPMENT
DOC NO . : QPS-PI-HI-101 SHEET
: 16 OF 59
REV
: 0
DATE
: 21.11.10
d) When double layer is applied, both longitudinal and circumferential joints shall be staggered. The arc between the longitudinal seam lines of the inside and outside layers of insulation shall have an angle of over 15° or the longitudinal joints staggered at least by one layer thickness, whichever is more stringent. Circumferential seams of the inside and outside layers shall be at least 100mm apart.
10.7
MATTRESS (Fibrous insulation - Rock or Glass Wool): Shall be applied over the surface with joints tightly butted and laced together with 1 mm dia galvanised lacing wire.
10.8
INSULATION SECUREMENT (All Insulation Materials): a) Each layer of insulation shall be secured firmly in place with at least 3 loops of binding wire/ band, one loop to be placed not more than 75 from each end and at least one loop to be equally spaced between end loops, for each section. Binding wire shall be drawn about the insulation with ends tightly twisted together, bent under & pressed into the surface of insulation. Bands or wires in no case are spaced more than 200mm apart. b) For all joints shall be sealed with insulating of same composition as the molded block. c) For Cellular glass and polyisocyanurate, joints shall be sealed with suitable compatible material. d) Each layer of insulation shall be secured by the same method as above.
10.9
FRAME WORK FOR SUPPORTING CLADDING: FIBROUS INSULATION (See Fig. 3 And 4): This is not necessary for rigid material. This is required only for horizontal pipe runs provided with fibrous insulation, in blanket forms; vertical piping provided with fibrous materials need not be provided with this. Piping provided with fibrous resin bonded pipe sections also need not be provided with this framework. Spacer rings shall be fabricated out of 25 X 3mm M.S. Flats. The outside diameter of these rings shall be equivalent to the outside diameter of the insulation. Spacer rings shall be riveted to ‘Z’ shaped stays, fabricated from the same sized MS Flats. These rings shall be suitably painted for corrosion protection. Stays shall be provided at intervals of not more than 300mm long the circumference of the insulation, subject to a minimum of 3 stays. Spacer rings shall be provided at every approx. 900mm distance. To minimize direct heat conduction through the stays, a packings of 2 sheets of 3mm thick asbestos mill board shall be provided at the joints of the stays and pipes. Joints between MS Spacer ring and stays shall be riveted by 6mm Ø M.S. rivets with 2 sheets of 3mm thick asbostos mill board interposed.
STANDARD SPECIFICATION FOR HOT INSULATION
PROCESS SOLUTIONS PVT. LTD.
PIPING AND EQUIPMENT
DOC NO . : QPS-PI-HI-101 SHEET
: 17 OF 59
REV
: 0
DATE
: 21.11.10
10.10 VERTICAL PIPE (All Insulation Materials) (See Fig. 5): a) Insulation on vertical or near vertical piping (i.e. greater than 45 °C angle from horizontal) shall be supported by bolted on metal collars. Metal collars shall be of 6mm thk. M.S. or alloy steel bar (to suit piping materials). b) Outside diameter of collar shall be around 12mm less than OD of insulation. Where multi-layer insulation is used, support collar shall be extended to provide for each layer. c) Support positions shall be at no greater distance apart than the following : Piping Operating Temp.
Support Spacing
Upto 400 °C
4500mm
400 to 500 °C
3500mm
500 to 550 °C
2500mm
d) Expansion Joints (Both vertical and horizontal piping. All insulation materials) (See Fig. 3) e) Expansion joint shall be provided at regular intervals as below :
f)
Temp. °C
Spacing (Meter)
Upto 200
Not required
200 to 300
10
300 to 350
8
350 to 400
6
400 to 450
5
Expansion joint shall be formed by a 25mm space between the pipe insulation sections and the space shall be filled by compressed mineral rock fibers. Expansion joints in each layer shall be offset at least 150 from each other in case of multilayer insulation. Expansion joint for first layer for vertical pipe shall preferably be just below insulation support collars.
10.11 ELBOWS AND BENDS (All insulation materials) (See Fig. 6 and Fig. 7): Insulation material shall be mitered and shall be same as that of pipe. Insulation securement band / wire shall be same as that for equivalent dia pipe. Each mitered section
STANDARD SPECIFICATION FOR HOT INSULATION
PROCESS SOLUTIONS PVT. LTD.
PIPING AND EQUIPMENT
DOC NO . : QPS-PI-HI-101 SHEET
: 18 OF 59
REV
: 0
DATE
: 21.11.10
shall be secured with minimum 2 wires / bands. For bends/ elbows of nom. pipe size 6” & below, due to lack of space, for all insulation materials, insulation shall be secured by spiral wound 16 SWG galvanised steel wire for hard materials & 10 SWG galvanised steel wire for soft materials. Insulation joints of block material shall be suitably sealed with adhesive for isocyanurate/ callular glass. 10.12 TEE (All insulation materials) (See Fig. 8): Preformed pipe sections or segments shall be carefully cut and shaped around ‘Tee’ junctions and the insulation material of the tangential pipe shall be carefully and neatly cut to mate upto the material applied to the parent pipe without the creation of voids or gaps, at the junction insulation shall be adequately secured by wire/ band of same specification as that of same size pipe. 10.13 FLANGED JOINTS OR VALVES (All insulation materials) (See Fig. 9 and Fig. 10): a) Flanged Joints or valves, if to be insulated, shall be insulated with prefabricated removable Aluminium covers, lined with pipe sections/ lags/ slabs. b) Welded valves, if insulated, shall be insulated with oversized pipe sections or lags, cut and shaped to fit around the body of the valve. Insulated valves shall be cut and shaped around the valve stem and kept clear of the stuffing box gland. 10.14 INSULATION FLASHING (All insulation materials): Insulation shall be stopped short of flanged joints and unions by a sufficient distance to permit easy removal of the flange nuts and bolts or breaking of the unions to take place without disturbance or damage to the insulating material. At these positions the insulation shall be bevelled and sealed with a metal closure which inturn shall be sealed with waterproof sealing material. 10.15 PIPE SUPPORTS (All insulation materials) (See Fig. 11): Insulation at solid welded or clamped supports shall be cut and shaped to fit around the support and banded securely to enable the insulation to be carried with the pipe movement. When the pipe hangers pass through insulation on piping outdoor, metal hoods packed with a waterproof sealing material shall be furnished and installed. Upper bolts of the hanger clamps are not to be covered with insulation.
10.16 STEAM TRACED PIPING (All insulation materials) (See Fig. 12): Steam traced piping and fittings shall be installed with oversized sections to allow accommodation of both parent pipe and tracer without damage or deformation of the insulation. Traced instrument line and fittings shall be totally enclosed by the insulation in a
STANDARD SPECIFICATION FOR HOT INSULATION
PROCESS SOLUTIONS PVT. LTD.
PIPING AND EQUIPMENT
DOC NO . : QPS-PI-HI-101 SHEET
: 19 OF 59
REV
: 0
DATE
: 21.11.10
similar manner and the designed warm air annulus maintained throughout the tracer pipe length. Insulation supports for vertical pipe shall have suitable clearance for tracer pipe. Suitable pulley or cement shall be used to improve the contact between pipe and tracers, throughout length of tracers. 10.17 ELECTRICAL TRACED PIPING (Polyisocyanurate / Cellular Glass): Electrical traced piping shall be provided with the same size insulation as would be provided if the piping were not electrically traced.
STANDARD SPECIFICATION FOR HOT INSULATION
PROCESS SOLUTIONS PVT. LTD.
PIPING AND EQUIPMENT
DOC NO . : QPS-PI-HI-101 SHEET
: 20 OF 59
REV
: 0
DATE
: 21.11.10
11.0 HORIZONTAL EQUIPMENT: 11.1
MATERIAL
11.2
FIBROUS MATERIALS (Rock or Glass Wool): a) Can be used for all temperatures. b) Shells
- Preferably performed pipe or multi pipe segments or slabs cut and shaped to fit. Alternately, blanket may be accepted.
c) Heads
- Preformed blocks and slabs cut and shaped to fit. Alternatively blanket may be accepted.
11.3
CELLULAR GLASS: a) Can be used on all surfaces. b) Temperature limitation for each shall be as per 7.0 c) Curved segments/ blacks, miter cut and shaped to fit.
11.4
CORROSION PROTECTION BEFORE APPLYING INSULATION (All insulation materials): For stainless steel surfaces, provide same protection as for piping per Clause 10.4
11.5
APPLICATION (All materials):
11.6
Following, Provided by the vessel fabricator for insulator/ cladding support/ securement, as indicated in enclosed Fig. No. 13, 16 & 19 shall be verified for their presence by the insulation contractor, before commencing insulation work : For vessels of diameter 2000mm and above are provided with insulation support at horizontal center line as also vertically at tangent lines. Ring support at tangent lines are provided with 6mm Ø holes. These are to be used for insulation securement. At vessel heads above 600mm outside diameter are provided with flats having 6mm Ø holes. The flats are for insulation support and holes provided in them are to be used for insulation securement. Also provided on either head is a central ring made of 10mm Ø glavanised steel rod. For vessels which do not have central nozzle, these rings shall not be provided by vessel fabricator. For such vessels, insulation contractor shall provide these rings. Boot of vessel, if any is provided with circular support ring with holes, as indicated in Fig. No. 26.
11.7
Blanket shall be applied over the surface with joints tightly butted and laced together with 1mm Ø galvanised lacing wire. Other block insulation shall be applied with the longer dimension parallel to the axis of the vessel or equipment. When blocks are applied in multiple layers, all joints in successive layers shall be parallel to the long axis, shall be staggered and sealed with insulating
STANDARD SPECIFICATION FOR HOT INSULATION
PROCESS SOLUTIONS PVT. LTD.
PIPING AND EQUIPMENT
DOC NO . : QPS-PI-HI-101 SHEET
: 21 OF 59
REV
: 0
DATE
: 21.11.10
cement for calcium silicate or suitable adhesive for others. In all cases, the insulation is to fit the contour of the vessel or equipment, so that the use of a leveling coat of insulating cement should not be normally necessary to get an acceptable smooth exterior.
11.8
INSULATION SECUREMENT (All insulation materials) (See Fig. 13 and 14): a) Each layer of insulation on shell of equipment shall be secured by bands at every 225 mm centers. Each band shall be machine stretched and tensioned to remove slack only. b) Each layer of insulation on vessel heads shall be secured as follows : Band shall be in radial direction connecting the head central floating ring and shell girth ring. The radial bends shall be placed at not more than 150mm centers for regid and 300mm for fibrous insulation, measured at the girth ring. These bands shall be machine stretched and sealed. Outermost layer of insulation shall also be supported by drawing and securing 16 SWG annealed steel wire through the 6mm diameter holes provided in the shell grith ring as also the flats provided on heads. The wire shall be drawn through every hole and it shall be secured to the ring with a knot.
STANDARD SPECIFICATION FOR HOT INSULATION
PROCESS SOLUTIONS PVT. LTD.
PIPING AND EQUIPMENT
DOC NO . : QPS-PI-HI-101 SHEET
: 22 OF 59
REV
: 0
DATE
: 21.11.10
12.0 VERTICAL EQUIPMENT: 12.1
MATERIAL:
12.2
Fibrous material shall be same as specified for horizontal equipment.
12.3
Calcium silicate, Polyisocyanurate and cellular glass shall be same as for horizontal equipment.
12.4
Corrosion protection shall be applied before applying insulation (All insulation materials) Corrosion prevention before applying insulation for stainless steel surfaces shall be same as specified for horizontal equipment.
12.5
Application (All insulation materials) (Fig. 13 & 14): Application details on shell, top and bottom heads shall be similar to that of horizontal equipment. Insulation shall be laid on insulation support rings provided by the fabricator. See enclosed sketch (Fig. No. 22).
12.6
INSULATION SECUREMENT (All insulation materials) (Fig. 13, 14 & 15): a) Bottom and top head insulation shall be supported by 16 SWG annealed galvanised steel wire drawn through holes in the insulation supports provided by the fabricator.
b) Top head insulation shall be secured by floating ring/ bands provided by vessel fabricator similar to head or horizontal vessel.
c) Shell insulation shall be supported by bands at every 225mm centres on the cylindrical portion and the bands shall be kept horizontal.
d) Insulation Securement for Bottom head for vessel supported on legs shall be identical to that of Top head.
e) For insulation securement of bottom heads inside skirt no floating rings/ bands need be provided; Firm securement should be ensured just by 16 SWG annealed wire drawn over insulation tightly and through the holes on support rings provided by the fabricator.
12.7
EXPANSION JOINTS (All insulation materials): Expansion joints shall be provided every 4000mm (max.) The joint shall be provided at insulation support rings. It shall be a 25mm space between the top of the insulation and the bottom of the support ring. The space shall be filled up by compressed Rock-wool fiber.
STANDARD SPECIFICATION FOR HOT INSULATION
PROCESS SOLUTIONS PVT. LTD.
PIPING AND EQUIPMENT
DOC NO . : QPS-PI-HI-101 SHEET
: 23 OF 59
REV
: 0
DATE
: 21.11.10
13.0 FLANGE, NOZZLE, CHANNEL COVER, MAN-WAY AND HANDHOLE FLANGED COVER (All insulation materials): a) Where insulation is required, these shall be insulated with lined removable prefabricated covers secured with bands or quick release toggle clips.
b) Otherwise, insulation shall be stopped short of uninsulated flanges and nozzle etc., a sufficient distance to permit withdrawal of bolts without disturbing the rem inder of the insulation. Insulation shall be weather proofed and sealed at these locations.
STANDARD SPECIFICATION FOR HOT INSULATION
PROCESS SOLUTIONS PVT. LTD.
PIPING AND EQUIPMENT
DOC NO . : QPS-PI-HI-101 SHEET
: 24 OF 59
REV
: 0
DATE
: 21.11.10
14.0 IRREGULAR SURFACES SUCH AS PUMPS, COMPRESSORS, TURBINE ETC: 14.1
Corrosion Protection: For SS surfaces at all temperatures, provide same protection as indicated for piping, Clause 10.4
14.2
Application:
14.3
Fibrous Material : Material, application and insulation sacrament: This shall be prefabricated removable aluminum covers, lined with mineral rock / glass wool pipe sections / lags/ slabs / mattresses.
STANDARD SPECIFICATION FOR HOT INSULATION
PROCESS SOLUTIONS PVT. LTD.
PIPING AND EQUIPMENT
DOC NO . : QPS-PI-HI-101 SHEET
: 25 OF 59
REV
: 0
DATE
: 21.11.10
15.0 VERTICAL STORAGE TANK (Carbon Steel): 15.1
MATERIAL:
15.2
FIBROUS MATERIAL (ROCK / GLASS WOOL): Shall be in the blanket form.
15.3
APPLICATION:
15.4
SUPPORTING RINGS / SPIKES (RODS) FOR SUPPORTING INSULATION / CLADDING:
15.5
SHELL: Refer Fig.No. 20 & 21 This Standard indicates the extent of insulation/cladding supporting/ sacrament details provided by tank fabricator. Insulation contractor shall check for its presence before insulation application work. Following is provided by tank fabricator. a) Water Shed At the junction of shell and roof, water shed is provided to act as top covering for the shell insulation as shown in Fig. No.-20 & 21. b) Insulation Support will consist of 5mm Ø steel rods provided at 400mm Ø diamond pitch. Length of these lugs is 3mm less than insulation thickness. c) Cladding Support form tank top, horizontal rings shall be provided at every 1175mm on tank shell.
15.6
TANK ROOF: Tank roof shall be provided as per Fig. No. 21.
15.7
INSULATION LAYING AND SECUREMENT:
15.8
SHELL: Application of fibrous insulation: Insulation shall be applied between rings in horizontal mode. Mattress insulation shall be applied with joints tightly butted and laced together with 1mm Ø galvanised lacing wire. Matts shall be impaled to the 5mm rod and speed washers fixed and pressed home for intimate contact of the insulation. In the case of multiple layers, speed washers are necessary only over the final layers, (upto and including 150mm). Rods and speed washers of spring steel should be selected to suit each other. While rods are provided by tank fabricator, speed washers shall be furnished by insulation contractor. Insulation shall be further secured by bands spaced centrally between insulation supports.
15.9
ROOF (for all materials): Application of both fibrous and polyisocyanurate shall be similar to that as for shell. Insulation supports from 5mm Ø MS lugs shall be exactly same as in shell.
15.10 INSULATION FINISH (TANK): 15.11 GENERAL:
STANDARD SPECIFICATION FOR HOT INSULATION
PROCESS SOLUTIONS PVT. LTD.
PIPING AND EQUIPMENT
DOC NO . : QPS-PI-HI-101 SHEET
: 26 OF 59
REV
: 0
DATE
: 21.11.10
15.12 MOISTURE BARRIER: On all surfaces provided with fibrous materials and calcium solicate for surface upto 125 ºC, apply a breathing type moisture barrier as below. A 3mm thick coating of mastic shall be applied to the surface of the insulation as soon as possible, after erection, to reduce the time the insulation is exposed to the weather, to a minimum. Whilst this coat is still wet, glass cloth shell be laid over the surface and embedded in thd mastic. Care shall be taken to ensure that the glass cloth is laid smooth and free from wrinkles and that no pockets of air are trapped beneath the surface. At junctions in the glass cloth, the overlap shall not be less than 75mm. A second 3mm thick coat of mastic shall be applied after approximate 12 hrs. When dry this coating shall be a minimum of 1.50mm thick. Care must be taken, however to ensure that the individual coats are not greater than 3mm (especially corners) otherwise some cracking of dried coat may be result the mastic shall not be applied over wet insulation or until the adhesive is dry. During the drying time, the insulation shall be protected from the weather by “Alkathene” film type tarpailin or similar materials approved by Engineer-in-Charge.
STANDARD SPECIFICATION FOR HOT INSULATION
PROCESS SOLUTIONS PVT. LTD.
PIPING AND EQUIPMENT
DOC NO . : QPS-PI-HI-101 SHEET
: 27 OF 59
REV
: 0
DATE
: 21.11.10
16.0 INSULATION FINISH (PIPING): The insulation finish shall provide a weatherproof and mechanical damage resistant covering over the whole of the insulation areas and be applied and fitted in such a manner as to provide a close fitting assembly without gaps.
16.1
PIPING (For all materials): a) Straight pipe shall have metal jacketing cut and machine rolled, (approx. 1 meter long) wrapped around, with 50mm minimum overlaps on both longitudinal and circumferential overlaps. All laps shall be arranged to shed water. b) A single bend shall be made on all overlaps to ensure tight metal-to-metal water tight arrangement. Self-tapping screws, at every 150mm, shall be provided at all longitudinal overlaps for both horizontal & vertical piping. c) At all operating temperature the seams at overlap positions shall be rendered watertight per clause 8.14 to ensure that insulation remains dry and unwetted, whether the possible water impingement is from rain, hose or fire sprinklers. d) The metal coverings shall be secured tightly around the insulation pipe and held in place with hands on a maximum of 300mm centers. One bend shall be located on each circumferential lap and the distance. Between laps divided at equal bend spacings. The bend securing seals shall be kept neatly in line the positioned away from viewing angles as much as is possible. e) Vertical overlaps on vertical or near vertical piping shall be staggered to provide overlaps at ‘North’ and ‘South’ positions in alternate sections of covering. f)
Each section of metal covering on vertical piping with insulation outside dia. larger than 250mm shall be supported from the next lower section each two ‘S’ clips, fabricated form banding material. The ‘S’ clip shall be of sufficient length to allow the minimum overlap of 50mm.
g) On vertical piping with O.D. of 600mm and larger, the securing bends shall be supported by ‘J’ clips, fabricated from banding material. The ‘J’ clip spacing shall be minimum of two per band All ‘J’ clips shall be screwed into position and secured. h) Insulation bends and elbows in piping 80mm and larger, shall be metalled with ‘lobster back’ segments using 10mm minimum ball swage to assist shaping. The metal bands shall be screwed with self-tapping screws and metal sealants are to provide to get a completely waterproofed arrangement. i)
Insulation bends and elbows in piping smaller than 80mm may use complete pressed humped back flat metal elbows or fabricated ‘stove pipe’ elbows.
STANDARD SPECIFICATION FOR HOT INSULATION
PROCESS SOLUTIONS PVT. LTD.
j)
PIPING AND EQUIPMENT
DOC NO . : QPS-PI-HI-101 SHEET
: 28 OF 59
REV
: 0
DATE
: 21.11.10
The practice of locating all joints in the top portion of elevated horizontal pipes for the sake-of-good-appearance when looking up from grade shall be strongly discouraged. The joints shall be located to shed water.
16.2
EQUIPMENT (All materials): a) The metal jacket over vertical vessel shells shall be constructed of sheet metal panels with the weight of the panel taken on the equipment insulation support rings, via angle brackets bolted to the panel. Refer Fig. No. 22 for details. b) The panels shall be applied commencing at the bottom of the vessel. Each circumferential ring of panels shall be tensioned by means of tensioning bands until the final joint is screwed tight. ‘S’ clips shall be used as sheeting support at unscrewed circumferential overlaps. c) The panels shall be held tight over the vessel insulation by means of circumferential bands and sealed per. 8.14 the bands shall be positioned on all horizontal overlaps and at 450 mm centers. Bands shall be held in their relative positions with ‘J’ clips and be machining stretched and sealed to remove slack only. Those bands, which are not supported by ‘j’ clips, shall be held in position on cladding by providing pop rivets every 2 meter centers. d) The panels shall have a minimum overlap of one corrugation on vertical joints and 80mm on horizontal joints. The overlaps shall be arranged to shed water at all times. e) The vertical and horizontal overlaps shall be secured with self tapping screws at 150mm pitch except the horizontal overlaps pre-selected to act as expansion joints, these shall be constructed with a 150 mm overlap and shall remain unscrewed and left free to permit expansion. All overlaps shall be rendered watertight as per 8.14. f)
All equipment projections such as nozzles shall have the jacketing sealed using a metal flashing, cut to fit the projection and extending above the jacket at least 80mm. The seal between the flashing and jacket shall be made watertight by use of self-tapping screws and sealing mastic.
g) Horizontal cylindrical equipment shall be furnished with flat metal jacket arranged in circumferential bands with the edge of the sheets, with the longer dimension applied around the circumference of the equipment insulation. h) The panels shall have a minimum of 80mm overlap on both longitudinal and circumferential edges, both overlaps being finished with a simple ball swage and rendered watertight as detailed in clause 8.14. i)
Horizontal overlaps shall be secured with No. 8 X 12mm long self-tapping set in the overlap at 150mm intervals, and shall be so arranged that staggered bands of paneling
STANDARD SPECIFICATION FOR HOT INSULATION
PROCESS SOLUTIONS PVT. LTD.
PIPING AND EQUIPMENT
DOC NO . : QPS-PI-HI-101 SHEET
: 29 OF 59
REV
: 0
DATE
: 21.11.10
encircle the equipment. Vertical overlaps shall not be screwed for horizontal equipment. j)
The metal finish shall be banded and sealed at 450mm centers.
k) The insulated heads of vertical and horizontal equipment shall be fabricated from flat metal, in an “Orange peel” construction with all radial seams overlapping a minimum of 50 mm and secured with self-tapping screws at 150mm centers. All overlaps shall be ball swaged and be rendered water tight per 8.14. l)
Projections from the heads shall be sealed using metal flashings, neatly cut to fit around the projections and extending above the jacket for a minimum of 80mm. The seal between flashing and jacket shall be weatherproofed with self-tapping screws and mastics.
m) Insulation at bottom heads of fully skirted equipment does not require weatherproofing. n) Heads of equipment's 24” OD and smaller shall be finished and waterproofed with square ended fabricated covers.
16.3
VERTICAL STORAGE TANKS:
16.4
Cladding Applications and Securement:
16.5
Shell (Fig. No. 19, 20 & 21): Cladding is applied over the system of horizontal rings as follows: a) Overlaps in the vertical joints will be one corrugation. b) Overlaps in the horizontal joints shall be 50mm (min.) c) Cladding to cladding fastening, at both horizontal and vertical overlaps shall be alternately by “POP” Rivets & self-tapping screws at 150mm (min.). d) Cladding shall be secured to support ring by bolting. Bolts are provided by tank fabricator at 300mm centers on angles provided at every 1175 centers vertically. Cladding is secured as indicated in Fig.No. 20 & 21 Felt washer, aluminium washer and nut shall be supplied by insulation contractor for all bolted connections at shell, roof and curb angle. e) Insulation shall be tucked into the skirt portion of the curb angle. Shell cladding and extended roof cladding shall be secured to curb angle by bolting as per Fig.No. 20 & 21 every 1500mm. f)
Horizontal stainless steel, steel bands over cladding to be provided every 800mm and also to coincide at every horizontal cladding overlaps. Bands shall be tightened, locked and lock fastened featuring stainless steel fastening systems. In order to prevent sliding of the bands downwards, the bands shall be secured to the cladding using POP rivets at horizontal pitch not over 2 meters.
STANDARD SPECIFICATION FOR HOT INSULATION
PROCESS SOLUTIONS PVT. LTD.
16.6
PIPING AND EQUIPMENT
DOC NO . : QPS-PI-HI-101 SHEET
: 30 OF 59
REV
: 0
DATE
: 21.11.10
ROOF: a) All cladding joints shall be sealed by electrometric metal sealants. b) Min. 75mm overlap shall be ensured at all joints. c) At all joints, cladding-to-cladding securement shall be provided by self-tapping screws and proprivets alternately, every 150mm centers. d) Cladding shall be secured by bolting at every 300mm provided by tank fabricator. For details of cladding arrangement and bolting, see Fig.No. 20 & 21.
STANDARD SPECIFICATION FOR HOT INSULATION
PROCESS SOLUTIONS PVT. LTD.
PIPING AND EQUIPMENT
DOC NO . : QPS-PI-HI-101 SHEET
: 31 OF 59
REV
: 0
DATE
: 21.11.10
17.0 ANNEXURE – I: 17.1
OWNER’S OBLIGATIONS: Following free facilities shall be provided near the work site. a) Open space for storing contractor’s materials shall be provided. b) Water and Electricity supply. c) Supply of cement.
17.2
CONTRACTOR’S CONDITIONS: a)
Mode of measurement will be as per IS : 7413-1981 & IS:7240-1981.
b) Contractor should submit the copy of the contract labour license to the personnel Dept. before starting up the work. c) Contractor has to maintain certain registers under the contract & the same shall be shown to the personnel department as and when asked for. d) Contractor has to maintain certain register under contract labour act. e) Contractors should comply with ESIS rules and challan of ESI payment should be submitted regularly during the tenure of the contract. f)
Transportation for contractor’s crew and their accommodation, food etc. will be arranged by the contractor’s.
g) The rates quoted by the contractor’s must be inclusive of the following : •
Handing and transportation of all items at site.
•
Consumable materials.
DOC NO . : QPS-PI-HI-101
STANDARD SPECIFICATION FOR HOT INSULATION
PROCESS SOLUTIONS PVT. LTD.
PIPING AND EQUIPMENT
SHEET
: 32 OF 59
REV
: 0
DATE
: 21.11.10
18.0 ANNEXURE – II: HOT INSULATION (IH): Recommended thickness in various temperatures for mineral wool. Density of Mineral wool 120 kg/m³. Conductivity 0.039 kcal/hr. m ° C. Insulation Thickness Pipe Size NB
Thickness in mm
(mm)
60 °C TO 100 °C
100 °C TO 140 °C
140 °C TO 180 °C
180 °C TO 210 °C
15
25
25
40
50
20
25
40
50
50
25
25
40
50
50
40
40
40
50
65
50
40
50
65
65
65
50
50
65
65
80
50
65
65
75
100
65
65
75
100
125
65
75
75
100
150
75
75
75
100
200
75
75
100
100
Flat Sur.
75
75
100
100
DOC NO . : QPS-PI-HI-101
STANDARD SPECIFICATION FOR HOT INSULATION
PROCESS SOLUTIONS PVT. LTD.
PIPING AND EQUIPMENT
SHEET
: 33 OF 59
REV
: 0
DATE
: 21.11.10
19.0 ANNXURE – III: TYPE OF INSULATION (IS): 1. Bonded Mineral Wool Pipe Section. 2. Bonded Mineral Wool Mattress. Insulation Thickness in mm OPERATING TEMPERATURE ° C Nom. Dia.
≥ 125
(mm)
Pipe O.D. (mm)
126 TO 150
151 TO 200
201 TO -32.0
15
21
25
25
25
25
20
27
25
25
25
25
25
34
25
25
25
25
40
48
25
25
25
25
50
60
25
25
25
25
80
89
25
25
25
25
100
114
25
25
25
25
150
168
25
25
25
25
200
219
25
25
25
40
250
273
25
25
25
40
300
324
25
25
25
40
350
356
25
25
25
40
400
406
25
25
25
40
450
457
25
25
25
40
25
25
25
40
25
25
25
40
500 & Above Flat Sur.
View more...
Comments