Standard Installation on RRU

XL Axiata Project www.huawei.com By : QC team

HUAWEI TECHNOLOGIES CO., LTD.

content 1. Installation on top Antenna  RRU  CPRI , Power and grounding cable on top 

2. Installation on bottom CPRI, power and grounding cable on bottom

HUAWEI TECHNOLOGIES CO., LTD.

Page 2

Installation on top Antenna 1. Water Proof Installation

Metode 1. 3x electrical tape 2. 3x rubber 3. 3x electrical Tape 4. Tie wrap with black ties

HUAWEI TECHNOLOGIES CO., LTD.

Page 3

Installation on top Antenna 2. Coloring label Installation

HUAWEI TECHNOLOGIES CO., LTD.

Page 4

Installation on top Antenna 2. Coloring label Installation

Add white color label near connector

HUAWEI TECHNOLOGIES CO., LTD.

Page 5

Installation on top 1. RRU placement

RRU

a. RRU on new mounting bellow antenna

Add new 3 mounting bellow antenna

HUAWEI TECHNOLOGIES CO., LTD.

Page 6

Installation on top 1. RRU placement

RRU

b. RRU On the mounting antenna installation

HUAWEI TECHNOLOGIES CO., LTD.

Page 7

Installation on top 1. RRU placement

RRU

c. RRU On the leg tower Installation

HUAWEI TECHNOLOGIES CO., LTD.

Page 8

Installation on top 1. RRU placement

RRU

d. RRU On the Bracing tower Installation (Guide mash type)

HUAWEI TECHNOLOGIES CO., LTD.

Page 9

Installation on top 2. RRU position

RRU

a. Installing the RRU on a Pole one or more RRUs can be installed on a pole.

HUAWEI TECHNOLOGIES CO., LTD.

Page 10

Installation on top 2. RRU position

RRU

b. Installing the RRU on a Pole one or more RRUs can be installed on a pole.

HUAWEI TECHNOLOGIES CO., LTD.

Page 11

Installation on top 2. RRU position

RRU

c. Installing the RRU on U-steel and Angle Steel This section describes the procedure and precautions for installing the RRU on U-steel and angel steel. U-steel and Angle Steel can be installed either on the ground or a tower and only one RRU can be installed on a piece of U-steel and Angle Steel. An RRU on U-steel and Angle Steel is installed in standard mode by default.

HUAWEI TECHNOLOGIES CO., LTD.

Page 12

Installation on top 2. RRU position

RRU

d. Installing the RRU on a Wall This section describes the procedure and precautions for installing the RRU on a wall. An RRU on a wall is installed in standard mode by default.

HUAWEI TECHNOLOGIES CO., LTD.

Page 13

Installation on top 2. RRU position

RRU

e. Installing RRU on an IFS06 This section describes the procedure and precautions for installing an RRU on an IFS06.

HUAWEI TECHNOLOGIES CO., LTD.

Page 14

Installation on top 2. RRU position

RRU

f. Installing the RRU on a Wall This section describes the procedure and precautions for installing the RRU on a wall. An RRU on a wall is installed in standard mode by default.

HUAWEI TECHNOLOGIES CO., LTD.

Page 15

Installation on top RRU 3. RRU installation with filter

Installation filter On

Use iron clamp

Leg Tower

HUAWEI TECHNOLOGIES CO., LTD.

Page 16

Installation on top RRU 3. RRU installation with filter Tx Rx Label on Jumper

FILTER

HUAWEI TECHNOLOGIES CO., LTD.

Page 17

Installation on top CPRI , Power and grounding cable on top 1. CPRI cable

CPRI cable connect to CPRI port 0

HUAWEI TECHNOLOGIES CO., LTD.

Page 18

Installation on top CPRI , Power and grounding cable on top 2. Power cable

To make shield layer power cable RRU measure from reverse RRU cover

HUAWEI TECHNOLOGIES CO., LTD.

Page 19

Installation on top CPRI , Power and grounding cable on top 3. Grounding cable

Grounding cable Install on RRU connect to grounding bar existing

HUAWEI TECHNOLOGIES CO., LTD.

Page 20

Installation on top CPRI , Power and grounding cable on top 4. label

Color ring & Print label standard for jumper cable & CPRI

HUAWEI TECHNOLOGIES CO., LTD.

Page 21

Installation on top CPRI , Power and grounding cable on top 4. label

Max 1 m

Label CPRI and power cable RRU max 1 M before bending cable on horizontal cable tray  Label must be installed as close as possible to the connector

HUAWEI TECHNOLOGIES CO., LTD.

Page 22

Installation on top CPRI , Power and grounding cable on top 5. Grounding clip Install grounding clip on power cable RRU before bending between vertical tray and horizontal tray

HUAWEI TECHNOLOGIES CO., LTD.

Page 23

Installation on top CPRI , Power and grounding cable on top 5. Grounding clip Install grounding clip on power cable RRU before bending between vertical tray and horizontal tray

HUAWEI TECHNOLOGIES CO., LTD.

Page 24

Installation on top CPRI , Power and grounding cable on top 6. Routing cable

Vertical Clamp

Horizontal Clamp

Power and CPRI cable install with clam 150 cm or each cable tray step, at horizontal and vertical tray. Power Cable Type : 300V, UL2464, 3.31mm^2,2x12AWG, Black Jacket (2 Cores: Blue, Black), 30A, Shielded Outdoor Cable

HUAWEI TECHNOLOGIES CO., LTD.

Optical Cable Type : DLC/UPC, DLC/UPC, Single-mode, GYFJH 2B1.3 (LSZH), 60m, 7.0mm, 2 Cores, 0.03m/0.34m, 2mm, Outdoor Protected Branch Cable

Page 25

Installation on top CPRI , Power and grounding cable on top 6. Routing cable

Vertical Clam

Horizontal Clam

Power and CPRI cable install with clam 150 cm or each cable tray step, at horizontal and vertical tray. Cable Fastener : Antenna Feeder Accessories, One Fastener for Fixing Six 3.3 mm^2,4 mm^2, and 8.2 mm^2 Power Cable and Optical Fibers, Stainless Steel, RRU

HUAWEI TECHNOLOGIES CO., LTD.

Page 26

Installation on bottom CPRI , Power and grounding cable on bottom 1. Routing cable outdoor BTS 3900A and DBS 3900

HUAWEI TECHNOLOGIES CO., LTD.

Page 27

Installation on bottom CPRI , Power and grounding cable on bottom 1. Routing cable outdoor BTS 3900A and DBS 3900

1 1. -

2 Power cable rectifier to BTS grounding cable BTS to main busbar signal cable E1/T1, FE/GE, optical alarm cable

2. - Jumper cable - CPRI cable - RRU power cable

HUAWEI TECHNOLOGIES CO., LTD.

Page 28

Installation on bottom CPRI , Power and grounding cable on bottom 2. RRU Power cable out door BTS 3900A and DBS 3900



Must be use MCB with capacity minimum 32A each RRU



Must be used cable 25mm if need additional MCB on Rectifier outdoor

*Note: power cable RRU direct to rectifier if not DCDU 12B yet HUAWEI TECHNOLOGIES CO., LTD.

Page 29

Installation on bottom CPRI , Power and grounding cable on bottom 2. RRU Power cable outdoor BTS 3900A add new DCDU 12B



Must be connected to Load0, Load1 & Load2

HUAWEI TECHNOLOGIES CO., LTD.

Page 30

Installation on bottom CPRI , Power and grounding cable on bottom 2. RRU Power cable outdoor BTS 3900A add new DCDU 12B 1. MCB on Rectifier must be 125A or 1x 80A or 2X80A for connected to DCDU-12B depend on design customer

1 2

2. Power connection to DCDU 12B use 1 port or 2 port

4

3 BTS 3900A cabinet

Rectifier outdoor cabinet

HUAWEI TECHNOLOGIES CO., LTD.

Page 31

Installation on bottom CPRI , Power and grounding cable on bottom 2. RRU Power cable outdoor BTS 3900A add new DCDU 12B 3. Routing power cable from right or left side BTS use anaconda conduit

1 2

4. Sticking a cable claw onto the right side of the DCDU-12B and grounding cable

4

3 BTS 3900A cabinet

Rectifier outdoor cabinet

HUAWEI TECHNOLOGIES CO., LTD.

Page 32

Installation on bottom CPRI , Power and grounding cable on bottom 2. RRU Power cable outdoor BTS 3900A DBS 3900 add new DCDU 12B



Please install ground clip RRU power cable and routing in BTS cabinet as picture above

HUAWEI TECHNOLOGIES CO., LTD.

Page 33

Installation on bottom CPRI , Power and grounding cable on bottom 3. CPRI cable routing outdoor BTS 3900A

CPRI cable from RRU

HUAWEI TECHNOLOGIES CO., LTD.

CPRI cable from RRU

Page 34

Installation on bottom CPRI , Power and grounding cable on bottom 3. CPRI cable routing DBS 3900

CPRI cable from RRU

HUAWEI TECHNOLOGIES CO., LTD.

CPRI cable from RRU

Page 35

Installation on bottom CPRI , Power and grounding cable on bottom 3. CPRI cable routing outdoor BTS 3900A and DBS 3900 spare CPRI cable 1. Redundant optic cable place to inside BTS

2. Redundant optic cable place on vertical bottom tray

*note= split each redundant optic cable per sector with ties cable and color label

HUAWEI TECHNOLOGIES CO., LTD.

Page 36

Installation on bottom CPRI , Power and grounding cable on bottom 4. Routing cable indoor BTS 3900L, BTS 3900 and DBS 3900

When Power and CPRI cable insert to the room must install with rubber boot (3 hole) in/outlet, block closely and with good bending for water drift.

HUAWEI TECHNOLOGIES CO., LTD.

Page 37

Installation on bottom CPRI , Power and grounding cable on bottom 4. Routing cable indoor BTS 3900L, BTS 3900 and DBS 3900

HUAWEI TECHNOLOGIES CO., LTD.



Power, CPRI and grounding cable no need white conduit.



Cable lay at tray with tie wrap or clamp

Page 38

Installation on bottom CPRI , Power and grounding cable on bottom 4. Routing cable indoor BTS 3900L, BTS 3900 and DBS 3900 1. Grounding cable, Power cable DCDU and RRU in duct cable

1

2. CPRI, signal and alarm cable in duct cable.

2 1

2

HUAWEI TECHNOLOGIES CO., LTD.

Page 39

Installation on bottom CPRI , Power and grounding cable on bottom 5. Power cable RRU outdoor BTS 3900 L add new DCDU 12B



Must be connected to Load0, Load1 & Load2

HUAWEI TECHNOLOGIES CO., LTD.

Page 40

Installation on bottom CPRI , Power and grounding cable on bottom 5. Power cable RRU indoor BTS 3900L add new DCDU 12B 1. MCB on Rectifier must be 125A or 1x 80A or 2X80A for connected to DCDU-12B depend on design customer

3

1 2. Power connection to DCDU use 1 port or 2 port

2 4

Rectifier indoor cabinet

BTS 3900L cabinet

HUAWEI TECHNOLOGIES CO., LTD.

Page 41

Installation on bottom CPRI , Power and grounding cable on bottom 5. Power cable RRU indoor BTS 3900L add new DCDU 12B 3. Routing power cable from left side BTS use duct cable and ties cable on horizontal tray

3

1 4. Sticking a cable claw onto the right side of the DCDU-12B and grounding cable

2 4

Rectifier indoor cabinet

BTS 3900L cabinet

HUAWEI TECHNOLOGIES CO., LTD.

Page 42

Installation on bottom CPRI , Power and grounding cable on bottom 5. Power cable RRU indoor BTS 3900L add new DCDU 12B



RRU power cable routing from left side in duct cable and rout to right side to DCDU 12B

HUAWEI TECHNOLOGIES CO., LTD.

Page 43

Installation on bottom CPRI , Power and grounding cable on bottom 6. CPRI cable routing indoor BTS 3900L CPRI cable from RRU

CPRI cable routing from right side in duct cable to BBU

HUAWEI TECHNOLOGIES CO., LTD.

Page 44

Installation on bottom CPRI , Power and grounding cable on bottom 6. CPRI cable routing outdoor BTS 3900L and DBS 3900 spare CPRI cable

1. Redundant optic cable place to inside BTS

3. Redundant optic cable place on vertical bottom tray

2. Redundant optic cable place to horizontal tray (indoor type)

HUAWEI TECHNOLOGIES CO., LTD.

*note= split each redundant optic cable per sector with ties cable and color label

Page 45

Installation on bottom CPRI , Power and grounding cable on bottom 7. label  Label must be installed as close as possible to the connector use print label: CPRI cable, RRU Power cable, MCB, grounding cable