Standard Document

March 29, 2023 | Author: Anonymous | Category: N/A
Share Embed Donate


Short Description

Download Standard Document...

Description

 

 

TANGGUH EXPANSION

PROJECT DEFINE

LNG FEE

PRELIMINARY SIL VERIFICATION REPORT

Code Description A

Proceed - No comment

B

Proceed - With comment

C

Do Not Proceed - Revise & Resubmit

D

Cancelled

E

Received as information

Signature:

A01 Rev

Issued for Review Reason for Issue

Enza Fiore/ Ganda Himawan Author

! This document is copyright and shall not be reproduced without the permission of BP

23-Oct-15 Date

Niccolo Gerrosa/ Jumriani Checked

23-Oct-15 Date

Marco D’Amico  D’Amico  Approver

23-Oct-15 Date

Document Number

Contractor Doc Number

TEP-900-RPT-HS-BP4-0004

870300-PTS-900-LPE-REP-12004 Document Class

© BP p.l.c. Security Classification: BP Confidential  Confidential 

2

 

Tangguh Expansion Project – LNG FEED Preliminary SIL Verification Report

Table of Contents 1  1.1  1.2  1.3  1.4  1.5  1.6 

Introdu Intr oducti ction on ............................................................. ...................................... ............................................ .................................... ............... 5   Project Overview ..........................................................................................................5  Scope Scop e .................................. .................................................. ................................. .................................. ................................. ................................. .......................5 ......5  Owner and Contractual Standards ..............................................................................22  International Standards ...............................................................................................22  Contractor Document .................................................................................................22  Order of Precedence ..................................................................................................22 



Symbols, Abbreviations and Definitions ....................................................... 23 



Method Met hodolo ology gy.................... ......................................... ........................................... ........................................... ............................... .......... 24 

3.1  Gener General al ............................... ................................................ .................................. .................................. .................................. ................................. ....................24 ....24  3.2  Probability Requirements ............................................................................................24  3.2.1  Genera Generall .................................................................. ................................................................................................... ...............................................................2 ..............................24 4  3.2.2  PFD Formulas Formulas ............................... .................................................................. ...................................................................... .....................................................25 ..................25 

3.3  Hardware Fault Tolerance ...........................................................................................28 

4  4.1  4.2  4.3  4.4 

Reliab Rel iabili ility ty Data Data ..................................................... ................................ .......................................... ...................................... ................. 31  General ............................... General ................................................ .................................. .................................. .................................. ................................. ....................31 ....31  Sensors Sens ors .................................. .................................................. ................................. ................................. .................................. .................................. .................32 .32  Logic Logi c Solver Solver (SIS)....................................... ....................................................... .................................. .................................. ...............................3 ...............32 2  Final Elements ............................................................................................................32 

4.5  PFD Calculation Chart .................................................................................................32  4.6  Architectural Constraints.............................................................................................32 



SIL Ve Verifi rificat cation ion Results Results ....................... ............................................ .......................................... ................................... .............. 34 



Conclusions and Recommendations ............................................................ 36 

Append App endix ix A

PFD Ca Calcu lculat lation ion She Sheet et .................... ......................................... ............................................ ......................... .. 42 

Append App endix ix B

HFT Com Compli plianc ance e Shee Sheett ................... ........................................ ............................................ ......................... .. 43 

List of Table Table 1 – Allocation Results and SIL Verification Scope of Work ............................................................ 5   Table 2 – SIFs to be verifi verified ed ........................... ............................................................. .................................................................... ................................................... ................. 21  Table 3 – Probability of failure on demand for SIL levels (Low Demand Mode)..................................... 24  Table 4 – Minimum hardware fault tolerance of sensors and final elements ........................................ 28   Table 5 – Minimum hardware fault tolerance of PE logic solvers.......................................................... 29   Table 6 – Maximum allowable SIL for a SIF carried out by a type A safety-related element or subsystem ................................................................. .............................. ..................................................................... ..................................................................... ........................................................ ..................... 30  Table 7 – Maximum allowable SIL for a SIF carried out by a type B safety-related element or subsystem ................................................................. .............................. ..................................................................... ..................................................................... ........................................................ ..................... 30 

Table 8 – Reli Reliabili ability ty Data for Compo Components nents ......................................... ........................................................................... .................................................. ................ 3 31 1  TEP-900-RPT-HS-BP4-0004 © BP p.l.c.

Page 2 of 43

Rev: A01 BP Confidential

 

Tangguh Expansion Project – LNG FEED Preliminary SIL Verification Report

Table 9 – SIL satisfied based on SFF and redundancy............................ ............................................................... .............................................. ........... 33  Table 10 – SIL verifi verification cation result results s ............................................................................ ........................................................................................................ ............................ 34  Table 11 – USVE Reli Reliabili ability ty Data................. Data.................................................. ................................................................... ........................................................ ...................... 36  Table 12 – Recommenda Recommendations tions Table ............................................ .............................................................................. ........................................................ ...................... 36  List of Figures Figure 1 – Block diagram, diagram, votin voting g logi logic c 1oo1................................. .................................................................... ........................................................ ..................... 25  Figure 2 – Block diagram, diagram, voting logic 1oo2................................. .................................................................... ........................................................ ..................... 26  Figure 3 – Block diagram, diagram, votin voting g logi logic c 2oo2................................. .................................................................... ........................................................ ..................... 27  Figure 4 – Block diagram, voting logic valid for 1oo3, 2oo3 and 3oo3 ................................................... 27 

TEP-900-RPT-HS-BP4-0004 © BP p.l.c.

Page 3 of 43

Rev: A01 BP Confidential

 

Tangguh Expansion Project – LNG FEED Preliminary SIL Verification Report

Revision History Amendment Date

Revision Number

Amender Name

Amendment

OMS references OMS section ref 3.3 5.2

OMS section title

Relevant section of this document

Process Safety Design and Construction

Related documents Document number

Document name

Description of Content

Stakeholders Name A. Muldoon - Engineering Lead

Date Reviewed

I. Musthafa - Process Safety Lead A. Daya Wiguna – Process Lead A. Witjaksono – I and C Lead

TEP-900-RPT-HS-BP4-0004 © BP p.l.c.

Page 4 of 43

Rev: A01 BP Confidential

 

Tangguh Expansion Project – LNG FEED Preliminary SIL Verification Report

1  Introduction 1.1 

Project Overview

BP Berau Ltd., hereafter known as COMPANY, is the operator of Tangguh LNG, a two train natural gas (NG) liquefaction facility in Bintuni Bay, Papua, Indonesia. The facility includes associated onshore infrastructure, two offshore platforms, pipelines and twelve wells. These facilities are the Trains 1 and 2 developments at Tangguh. COMPANY has initiated the Tangguh Expansion Project to commercialize the incremental resource into high margin gas markets based on a single LNG (liquefied natural gas) train expansion (Train 3). Tangguh Expansion Project will consist of new offshore facilities, including wellhead platforms and pipelines, and onshore development on the existing Tangguh brownfield site. The new onshore facilities will include one additional natural gas liquefaction train of a similar design and capacity to the existing trains, an onshore receiving facility (ORF), new LNG and condensate loading berth, additional boil off gas (BOG) recovery, utilities, flares and the infrastructure to support logistics and the associated increase in the temporary and permanent workforce. The Tangguh Expansion Project comprises of the following new facilities:

                     









[New] Onshore Receiving Facility (ORF) [New] LNG Train 3 [New] Condensate Stabilization Train 3 [New/Interconnection] Plant Utility Facilities















[New] Condensate LNG LoadingLoading SystemSystem [New] [Expansion] Integrated Control and Safety System (ICSS) [Expansion] Telecommunication System [New] Trestle Jetty Structure [Expansion] Onshore Infrastructure Hazardous and Non-hazardous Waste Management Ma nagement System

1.2 

Scope

The objective of the SIL verification activity is to confirm that the analyzed automatic protection loops meet the SIL requirements, assigned by means of LOPA analysis, both from probability of failure on demand (according to equations described in IEC 61508-6) and architectural constrains. The LOPA was conducted by a BP-approved Atkins Leader and was attended by a multi-disciplinary team which included representatives from the Contractor A TEP FEED team, representatives from the BP embedded team and Tangguh LNG operations team members. The LOPA was held over two weeks from 3rd August to the 15th August 2015 in Alamanda Tower, Jakarta, Indonesia. The present document describes methodology and reports the results of the SIL verification process. SIL verification has been performed for SIF Loops Allocated as reported in the LOPA Report. The complete list of LOPA scenario and related allocation results is reported in following Table 1, together with identified SIF, if any, and the relevant SIL requirements. For each SIL rated item of the table it is indicated if included in SIL Verification process Scope of Work, taking into account if a SIF is associated to the scenario. Table 1

Allocation Results and SIL Verification Scope of Work LOPA Report Results Hazardous Scenario

No.

SIF to be verified

LOPA Result

-

SIL 0

Consequences

1

043-E-31002 shellside high pressure

TEP-900-RPT-HS-BP4-0004 © BP p.l.c.

Page 5 of 43

SIL Verification Notes

Scope of Work  Work  Not SIL rated, not included in Preliminary SIL Verification

Rev: A01 BP Confidential

 

Tangguh Expansion Project – LNG FEED Preliminary SIL Verification Report

LOPA Report Results No.

Hazardous Scenario Consequences

SIF to be verified

SIL Verification

LOPA Result

Scope of Work  Work 

Notes Report

-

SIL 1

Not included in Preliminary SIL Verification Report since < SIL 2

053-C-31001 discharge high pressure

053-PAHH-31187

SIL 3

Included in Preliminary SIL Preliminary Verification Report

043-T-31001 high 043-T-31001 pressure

043-PAHH-31032

SIL 2

Included in Preliminary SIL Verification Report

2

043-E-31003 shellside high pressure

3

4

5

043-E-31001 shell side high pressure

6

043-E-31001 tube side high pressure (warm tube bundle feed gas)

053-PAHH-31858

-

SIL 2

Upon close out of Recommendation #64 from the Critical P&ID Review an additional SIF may be considered (e.g. high pressure trip)

Included in Preliminary SIL Verification Report

Not included Preliminary SIL Verification Report since < SIL 2 and no SIF d efined in LOPA

SIL 1

LPG reinjection high

Included in Preliminary SIL

7

pressure

043-PAHH-31726

SIL 2

Verification Report

8

053-D-31007 high pressure

053-PAHH-31487

SIL 2

Included in Preliminary SIL Verification Report

9

LNG rundown line low t emper emperature ature

-

-

10

LNG rundown line high temperature

-

SIL 0

Sudden contraction will not lead to LOPC. LOPC is only considered credible due to a bowing effect (i.e. liquid LNG introduced into line).

No SIF defined in LOPA, scenario not included in Preliminary SIL Verification Report Not SIL rated, not included in Preliminary SIL Verification Report

Upon close out of Recommendation #19 from the Critical P&ID Review an additional IPL may be considered for Causes 1 to 4.

No SIF defined in LOPA, scenario not included in Preliminary SIL Verification Report

11

043-E-31004 tube side low temperature

-

SIL 3

12

043-T-31001 low 043-T-31001 level

043-LAHH-31044 043-LAHH-310 44

SIL 2

Included in Preliminary SIL Verification Report

13

043-E-31004 tube side high pressure

-

SIL 1

Not included in Preliminary SIL Verification Report since < SIL 2 and no SIF defined in LOPA

14

071-TK-1001/2 high pressure

043-TAHH-31258

-

Existing systems were not part of the critical P&ID review and hence not considered in LOPA as the LOPA calculations need to consider causes in existing facilities which were not included in the Critical P&ID review. Therefore if a LOPA was conducted, it would be

SIL to be defined in EPC phase. SIF not included in Preliminary SIL Verification Report

incomplete. 15

LNG rundown line

TEP-900-RPT-HS-BP4-0004 © BP p.l.c.

-

SIL 0

Page 6 of 43

Not SIL rated, not included in

Rev: A01 BP Confidential

 

Tangguh Expansion Project – LNG FEED Preliminary SIL Verification Report

LOPA Report Results No.

Hazardous Scenario Consequences

SIF to be verified

SIL Verification

LOPA Result

Notes

bowing.

16

Scope of Work  Work  Preliminary SIL Verification Report

043-E-31001 tube side high pressure (middle and cold tube bundles - LNG product)

-

Not included in Preliminary SIL Verification Report since < SIL 2 and no SIF d efined in LOPA

SIL 1

SIL 4+

Upon close out of Recommendation #21 from the Critical P&ID Review an additional SIF may be considered.

No SIF defined in LOPA, scenario not included in Preliminary SIL Verification Report

043-PAHH-31273

SIL 4+

Upon close out of Recommendation #150 from the Critical P&ID Review this hazard may be removed.

No SIL Verification required since hazard has been removed following Company approval of Recommendation #150 implementation

-

SIL 1

Not included in Preliminary SIL Verification Report since < SIL 2 and no SIF defined in LOPA

17

043-T-31002 high 043-T-31002 level

18

043-T-31003 feed 043-T-31003 line high temperature

19

MP steam condensate flash drum high pressure

20

043-T-31002 low 043-T-31002 level

043-LALL-31285 043-LALL31285

SIL 2

Included in Preliminary SIL Verification Report

21

043-T-31002 high 043-T-31002 pressure

043-PAHH-31273

SIL 2

Included in Preliminary SIL Verification Report

22

053-C-31002 discharge high pressure

053-PAHH-31487

SIL 2

Included in Preliminary SIL Verification Report

23

-

074-TK-1001 high level

-

-

Existing systems were not part of the critical P&ID review and hence not considered in LOPA as the LOPA calculations need to consider causes in existing facilities which were not included in the Critical P&ID review. Therefore if a LOPA was conducted, it would be

SIL to be defined in EPC phase. SIF not included in Preliminary SIL Verification Report

incomplete.

24

C2 transfer line high temperature

-

SIL 4+

25

043-E-31006 shell side high pressure

-

SIL 1

26

043-T-31003 high 043-T-31003 level

043-LAHH-31434 043-LAHH-314 34

SIL 3

27

043-T-31003 high 043-T-31003 pressure

043-PAHH-31423

SIL 3

28

043-T-31004 feed 043-T-31004 line high temperature

-

SIL 4+

TEP-900-RPT-HS-BP4-0004 © BP p.l.c.

Upon close out of Recommendation #39 from the Critical P&ID Review this hazard may be removed.

No SIL Verification required since hazard has been removed following Company approval of Recommendation #39 implementation Not included in Preliminary SIL Verification Report since < SIL 2 and no SIF defined in LOPA

Upon close out of Recommendation #24 from the Critical P&ID Review an additional SIF may be considered.

Included in SIL Verification Report

Included in SIL Verification Report Upon close out of Recommendation #26 from the Critical P&ID

Page 7 of 43

Hazard has been removed following Company approval of Recommendation #26

Rev: A01 BP Confidential

 

Tangguh Expansion Project – LNG FEED Preliminary SIL Verification Report

LOPA Report Results No.

Hazardous Scenario Consequences

SIF to be verified

SIL Verification

LOPA Result

Notes Review this hazard may be removed.

29

043-T-31003 low 043-T-31003 level

30

074-TK-1002A/B high level

31

C3 transfer line high pressure

32

043-LALL-31434 043-LALL31434

-

053-PAHH-31359

SIL 1

043-T-31004 043-T-3100 4 high

-

Existing systems were not part of the critical P&ID review and hence not considered in LOPA as the LOPA calculations need to consider causes in existing facilities which were not included in the Critical P&ID review. Therefore if a LOPA was conducted, it would be incomplete.

043-T-31004 high 043-T-31004 pressure

34

C2 liquid for LPG reinjection pipework high pressure

35

C2 vapour for LPG reinjection pipework high pressure

36

C3 liquid for LPG reinjection pipework high pressure

37

Dilution gas line high pressure

SIL to be defined in EPC phase. SIF not included in SIL Verification Report

Not included in Preliminary SIL Verification Report since < SIL 2 and no SIF defined in LOPA No SIF defined in LOPA, scenario not included in

SIL 3

leve

33

implementation Included in SIL Verification Report

SIL 2

-

Scope of Work  Work 

Preliminary SIL Verification Report 043-PAHH-31573

SIL 4+

SIF consider ed outstandin outstanding g

-

Due to close out of Recommendation #48 this consequence has been removed.

Hazard has been removed following Company approval of Recommendation #48 implementation

-

Due to close out of Recommendation #48 this consequence has been removed.

Hazard has been removed following Company approval of Recommendation #48 implementation

-

-

Due to close out of Recommendation #48 this consequence has been removed.

Hazard has been removed following Company approval of Recommendation #48 implementation

-

-

Due to close out of Recommendation #52 this consequence has been removed.

Hazard has been removed following Company approval of Recommendation #52 implementation

Upon close out of Recommendation #93 from the Critical P&ID Review an additional IPL may be considered.

Hazard has been removed following Company approval of Recommendation #93 implementation

-

-

38

043-E-31012 shell side high pressure

-

SIL 1

39

043-E-31001 tube side high pressure (warm, middle and cold tube bundles LPG reinjection)

-

SIL 1

Not included in Preliminary SIL Verification Report since < SIL 2 and no SIF defined in LOPA

40

N2 system high pressure

053-PDALL-31469

SIL 2

Included in SIL Verification Report

41

053-C-31003 suction low pressure

TEP-900-RPT-HS-BP4-0004 © BP p.l.c.

-

-

Due to close out of

Hazard has been removed

Recommendation #67 this consequence has been removed.

following Company approval of Recommendation #67 implementation

Page 8 of 43

Rev: A01 BP Confidential

 

Tangguh Expansion Project – LNG FEED Preliminary SIL Verification Report

LOPA Report Results No.

Hazardous Scenario Consequences

42

053-C-31002 discharge low temperature

43

053-C-31003 discharge high temperature

44

SIF to be verified

-

SIL Verification

LOPA Result

SIL 3

Notes Upon close out of Recommendation #93 from the Critical P&ID Review this hazard may

Scope of Work  Work 

Hazard has been removed following Company approval of Recommendation #93 implementation

be removed. 053-TAHH-31578 053-TAHH-315 78

SIL 4+

053-C-31002 excess nitrogen flow

-

SIL 0

Not SIL rated, not included in Preliminary SIL Verification Report

45

053-C-31003 excess nitrogen flow

053-TAHH-31578 053-TAHH-315 78

SIL 0

Not SIL rated, not included in Preliminary SIL Verification Report

46

053-C-31004 excess nitrogen flow

053-TAHH-31638 053-TAHH-316 38

SIL 0

Not SIL rated, not included in Preliminary SIL Verification Report

47

053-C-31004 discharge high temperature

053-TAHH-31638 053-TAHH-316 38

SIL 4+

SIF considered outstanding

48

053-C-31002 discharge high temperature

053-TAHH-31489 053-TAHH-314 89

SIL 2

Included in Preliminary SIL Verification Report

49

053-C-31003 discharge high pressure

053-PAHH-31576

SIL 2

Included in Preliminary SIL Verification Report

50

053-C-31004 suction low pressure

51

053-C-31003 discharge low temperature

-

SIL 3

52

053-C-31004 discharge high pressure

053-PAHH-31636

SIL 2

-

-

SIF considered outstanding

Due to close out of Recommendation #67 this consequence has been removed.

Hazard has been removed following Company approval of Recommendation #67 implementation

Upon close out of Recommendation #71 from the Critical P&ID Review this hazard may be removed.

Hazard has been removed following Company approval of Recommendation #71 implementation Included in Preliminary SIL Verification Report

Upon close out of Recommendation #71 from the Critical P&ID Review this hazard may be removed.

Hazard has been removed following Company approval of Recommendation #71 implementation

53

053-C-31004 discharge low temperature

54

053-E-31007 shell side high pressure

-

SIL 2

No SIF defined in LOPA, scenario not included in Preliminary SIL Verification Report

55

053-E-31008 shell side high pressure

-

SIL 1

Not included in Preliminary SIL Verification Report since < SIL 2 and no SIF defined in LOPA

56

053-E-31009 shell side high pressure

-

SIL 1

Not included in Preliminary SIL Verification Report since < SIL 2 and no SIF defined in LOPA

57

053-E-31010 shell side high pressure

-

SIL 1

Not included in Preliminary SIL Verification Report since < SIL 2 and no SIF defined in LOPA

TEP-900-RPT-HS-BP4-0004 © BP p.l.c.

-

SIL 3

Page 9 of 43

Rev: A01 BP Confidential

 

Tangguh Expansion Project – LNG FEED Preliminary SIL Verification Report

LOPA Report Results No.

58

59

Hazardous Scenario Consequences

SIF to be verified

053-E-31009 shell side low temperature

-

053-E-31010 shell side low temperature

-

SIL Verification

LOPA Result

SIL 3

SIL 3

Notes Upon close out of Recommendation #75 from the Critical P&ID Review this hazard may be removed. Upon close out of Recommendation #75 from the Critical P&ID Review this hazard may be removed. Existing systems were not part of the critical P&ID review and hence not considered in LOPA as the LOPA calculations need to consider causes in existing facilities which were not included in the Critical P&ID review. Therefore if a LOPA was conducted, it would be incomplete.

Scope of Work  Work 

Hazard has been removed following Company approval of Recommendation #75 implementation Hazard has been removed following Company approval of Recommendation #75 implementation

SIL to be defined in EPC phase. SIF not included in Preliminary SIL Verification Report

60

074-TK-1001 high pressure

-

-

61

043-E-31001 tube side high pressure (warm and middle tube bundles - MR liquid)

-

SIL 1

Not included in Preliminary SIL Verification Report since < SIL 2 and no SIF defined in LOPA

62

043-E-31001 tube side high pressure (middle and cold tube bundles - MR lquid)

-

SIL 1

Not included in Preliminary SIL Verification Report since < SIL 2 and no SIF defined in LOPA

63

053-C-31001 suction high pressure

64

053-C-31001 discharge high temperature

65

053-C-31001 excess nitrogen flow

66

053-D-31004 high pressure

No SIF defined in LOPA, scenario not included in Preliminary SIL Verification Report

-

SIL 4+

053-TAHH-31189 053-TAHH-311 89

SIL 3

Included in Preliminary SIL Verification Report

-

SIL 0

Not SIL rated, not included in Preliminary SIL Verification Report

SIL 3

No SIF defined in LOPA, scenario not included in Preliminary SIL Verification Report

-

67

053-D-31006 low 053-D-31006 pressure

-

SIL 3

68

053-P-31006 high pressure

053-PAHH-31359

SIL 1

TEP-900-RPT-HS-BP4-0004 © BP p.l.c.

Upon close out of Recommendation #86 from the Critical P&ID Review 053-PSV- 31151 on the HP C3 Compressor Suction Drum may be considered as an additional IPL.

Upon close out of Recommendation #97 from the Critical P&ID Review additional IPLs may be considered.

Page 10 of 43

No SIF defined in LOPA, scenario not included in Preliminary SIL Verification Report Not included in Preliminary SIL Verification Report since < SIL 2 and no SIF defined in LOPA

Rev: A01 BP Confidential

 

Tangguh Expansion Project – LNG FEED Preliminary SIL Verification Report

LOPA Report Results No.

Hazardous Scenario Consequences

SIF to be verified

SIL Verification

LOPA Result

Notes

Scope of Work  Work 

69

053-D-31006 high level

-

SIL 3

No SIF defined in LOPA, scenario not included in Preliminary SIL Verification Report

70

023-D-31004 low 023-D-31004 level

-

SIL 1

Not included in Preliminary SIL Verification Report since < SIL 2 and no SIF defined in LOPA

71

023-D-31008 low 023-D-31008 water level

023-LALL-31057 023-LALL31057

SIL 1

Not included in Preliminary SIL Verification Report since < SIL 2

72

023-D-31008 low 023-D-31008 condensate condensat e level

023-LALL-31056 023-LALL31056

SIL 1

Not included in Preliminary SIL Verification Report since < SIL 2

73

023-E-31005 shell side high pressure

-

SIL 1

Not included in Preliminary SIL Verification Report since < SIL 2 and no SIF defined in LOPA

74

033-E-31001 shell side high pressure

-

SIL 1

Not included in Preliminary SIL Verification Report since < SIL 2 and no SIF defined in LOPA

75

033-D-310 033-D-31001 01 low condensate condensat e level

033-LALL-31054 033-LALL31054

SIL 1

Not included in Preliminary SIL Verification Report since < SIL 2

76

033-D-31001 low 033-D-31001 water level

033-LALL-31055 033-LALL31055

SIL 1

Not included in Preliminary SIL Verification Report since < SIL 2

77

78

033 Regeneration gas circuit high pressure (Fire/VCE)

071 BOG compressor discharge high pressure

-

SIL 3

Upon close out of Recommendation #103 from the Critical P&ID Review Cause 8 may be changed to ‘PV fails closed during start-up’. start- up’. OG compressor is not part of the critical P&ID review and hence not considered in LOPA as the LOPA calculations need to consider causes

-

-

in existing facilities and other parts of the project facilities not included in the Critical P&ID review. Therefore if a LOPA was conducted, it would be incomplete. Upon close out of Recommendation #101 from the Critical P&ID Review this hazard may be removed.

No SIF defined in LOPA, scenario not included in Preliminary SIL Verification Report

SIL to be defined in EPC phase. SIF not included in Preliminary SIL Verification Report

Hazard has been removed following Company approval of Recommendation #101 implementation

79

033-E-31006 shell side high temperature

-

SIL 3

80

053-D-31103 high pressure

-

SIL 0

Not SIL rated, not included in Preliminary SIL Verification Report

81

033-E-31005 shell side high pressure

-

No further risk reduction required.

Not SIL rated, not included in Preliminary SIL Verification Report

82

033-E-31006 shell side high pressure

-

No further risk reduction

Not SIL rated, not included in Preliminary SIL Verification

TEP-900-RPT-HS-BP4-0004 © BP p.l.c.

Page 11 of 43

Rev: A01 BP Confidential

 

Tangguh Expansion Project – LNG FEED Preliminary SIL Verification Report

LOPA Report Results No.

Hazardous Scenario Consequences

SIF to be verified

(Jet Fire)

83

SIL Verification

LOPA Result required.

033-E-31006 shell side high pressure

-

Scope of Work  Work 

Notes Report

No SIF defined in LOPA, scenario not included in Preliminary SIL Verification Report

SIL 3

(Fire/VCE) Fuel gas system is not part of the critical P&ID review and hence not considered in LOPA as the LOPA calculations need to consider causes in other parts of the project facilities not included in the Critical P&ID review. Therefore if a LOPA was conducted, it would be incomplete.

SIL to be defined in EPC phase. SIF not included in Preliminary SIL Verification Report

84

HP fuel gas turbines 033-TAHH-31454 high temperature

85

033-D-31003 low 033-D-31003 water level

86

033-D-31003 low 033-D-31003 condensate condensat e level

-

risk reduction required.

Preliminary SIL Verification Report

87

023-T-31001 low 023-T-31001 amine level

023-LALL-31084 023-LALL31084

SIL 2

Included in Preliminary SIL Verification Report

88

023-T-31001 low 023-T-31001 condensate condensat e level

-

SIL 2

No SIF defined in LOPA, scenario not included in Preliminary SIL Verification Report

89

023-D-31001 high pressure

023-PAHH-31128

No further risk reduction required

Not SIL rated, not included in Preliminary SIL Verification Report

90

023-D-31001 low 023-D-31001 amine level

023-LALL-31139 023-LALL31139

SIL 0

Not SIL rated, not included in Preliminary SIL Verification Report

033-LALL-31502 033-LALL31502

-

SIL 0

Not SIL rated, not included in Preliminary SIL Verification Report

No further

Not SIL rated, not included in

Upon close out of Recommendation #101

No SIF defined in LOPA,

91

023-D-31009 high pressure

-

SIL 1

92

023-D-31001 low 023-D-31001 condensate condensat e level

-

SIL 0

93

023-P31001A/B/C/D suction high pressure

023-FALL-31099 023-FALL31099

SIL 4+

SIF considered outstanding

94

023-T-31002 high 023-T-31002 pressure

023-FALL-31099 023-FALL-31 099

SIL 4+

SIF considered outstanding  /Same as SIF 93

95

023-D-31002 high pressure

023-PAHH-31215

SIL 1

Not included in Preliminary SIL Verification Report since < SIL 2

No further

Not SIL rated, not included in

96

017-D-31004 inlet piping high pressure

97

017-D-31004 high

-

risk reduction required

017-PAHH-31258

No further

TEP-900-RPT-HS-BP4-0004 © BP p.l.c.

from the Critical P&ID Review an additional IPL may be considered.

Page 12 of 43

scenario not included in SIL SIL Verification Report Not SIL rated, not included in Preliminary SIL Verification Report

Preliminary SIL Verification Report Not SIL rated, not included in

Rev: A01 BP Confidential

 

Tangguh Expansion Project – LNG FEED Preliminary SIL Verification Report

LOPA Report Results No.

Hazardous Scenario Consequences

SIF to be verified

pressure

98

017-D-31004 high

SIL Verification

LOPA Result

Notes

risk reduction required 017-LAHH-31252 017-LAHH-312 52

Preliminary SIL Verification Report Not included in Preliminary SIL Verification Report since < SIL 2

SIL 1

level

99

LP fuel gas circuit high pressure

-

-

100

017-D-31004 low 017-D-31004 condensate condensat e level

017-LAHH-31252

No further risk reduction required

Scope of Work  Work 

Fuel gas system is not part of the critical P&ID review and hence not considered in LOPA as the LOPA calculations need to consider causes in other parts of the project facilities not included in the Critical P&ID review. Therefore if a LOPA was conducted, it would be incomplete.

SIL to be defined in EPC phase. SIF not included in Preliminary SIL Verification Report

Not SIL rated, not included in Preliminary SIL Verification Report Produced water system is

101

Produced water tank high pressure

102

Recovered oil tank high pressure

103

011-T-31001 inlet 011-T-31001 piping high pressure

-

-

-

-

011-PAHH-31013

No further risk reduction required

not part of the critical P&ID review and hence not considered in LOPA as the LOPA calculations SIL to be defined in EPC need to consider causes phase. SIF not included in SIL in other parts of the Verification Report project facilities not included in the Critical P&ID review. Therefore if a LOPA was conducted, it would be incomplete. Recovered oil system is not part of the critical P&ID review and hence not considered in LOPA as the LOPA calculations SIL to be defined in EPC need to consider causes phase. SIF not included in SIL in other parts of the Verification Report project facilities not included in the Critical P&ID review. Therefore if a LOPA was conducted, it would be incomplete. Not SIL rated, not included in Preliminary SIL Verification Report Upon close out of Recommendation #117 from the Critical P&ID Review an additional IPL may be considered for Cause 3.

Not included in Preliminary SIL Verification Report since < SIL 2

104

011-T-31001 high 011-T-31001 pressure

011-PAHH-31013

SIL 1

105

011-T-31001 high 011-T-31001 level

-

SIL 1

Not included in Preliminary SIL Verification Report since < SIL 2 and no SIF defined in LOPA

106

011-T-1001A/B inlet piping high pressure

011-PAHH-31013

SIL 0

Not SIL rated, included in Preliminary SIL not Verification Report

TEP-900-RPT-HS-BP4-0004 © BP p.l.c.

Page 13 of 43

Rev: A01 BP Confidential

 

Tangguh Expansion Project – LNG FEED Preliminary SIL Verification Report

LOPA Report Results No.

Hazardous Scenario Consequences

SIF to be verified

SIL Verification

LOPA Result

Notes

Scope of Work  Work 

Existing systems were not part of the critical P&ID review and hence not considered in LOPA as the LOPA calculations need to consider causes in existing facilities which were not included in the Critical P&ID review. Therefore if a LOPA was conducted, it would be incomplete.

SIL to be defined in EPC phase. SIF not included in SIL Verification Report

107

011-T-1001A/B high level

-

108

011-E-31001 shell side high pressure

-

No further risk reduction required.

Not SIL rated, not included in Preliminary SIL Verification Report

109

017-D-31008 high pressure

-

SIL 0

Not SIL rated, not included in Preliminary SIL Verification Report

110

011-P-31001A/B suction low pressure

-

No further risk reduction required.

Not SIL rated, not included in Preliminary SIL Verification Report

111

112

113

114

115

116

017-D-31001A low condensate condensat e level

017-D-31001A low water level

017-D-31001B low condensate condensat e level

017-D-31001B low water level

017-LALL-31057 017-LALL31057

017-LALL-31060 017-LALL31060

017-LALL-31107 017-LALL31107

017-LALL-31110 017-LALL-31110

-

016-PAHH-XXXX (2oo3)

TEP-900-RPT-HS-BP4-0004 © BP p.l.c.

Included in Preliminary SIL Verification Report

SIL 3

Upon close out of Recommendation #152 from the Critical P&ID Review additional IPLs may be considered.

Included in Preliminary SIL Verification Report

SIL 3

Upon close out of Recommendation #152 from the Critical P&ID Review additional IPLs may be considered.

Included in Preliminary SIL Verification Report

Upon close out of Recommendation #152

017-V-31305 high pressure

016-D-1006 high 016-D-1006 pressure (HIPPS)

SIL 3

Upon close out of Recommendation #152 from the Critical P&ID Review additional IPLs may be considered.

SIL 3

-

from the Critical P&ID Review additional IPLs may be considered. This system is not part of the critical P&ID review and hence not considered in LOPA as the LOPA calculations need to consider causes in other parts of the project facilities not included in the Critical P&ID review. Therefore if a LOPA was conducted, it would be incomplete. Existing systems were not part of the critical P&ID review and hence

-

not considered in LOPA as the LOPA calculations need to consider causes in existing facilities which

Page 14 of 43

Included in Preliminary SIL Verification Report

SIL to be defined in EPC phase. SIF not included in Preliminary SIL Verification Report

SIL to be defined in EPC phase. SIF not included in Preliminary SIL Verification Report

Rev: A01 BP Confidential

 

Tangguh Expansion Project – LNG FEED Preliminary SIL Verification Report

LOPA Report Results No.

Hazardous Scenario Consequences

SIF to be verified

SIL Verification

LOPA Result

Notes

Scope of Work  Work 

were not included in the Critical P&ID review. Therefore if a LOPA was conducted, it would be incomplete. Existing systems were not part of the critical P&ID review and hence not considered in LOPA as the LOPA calculations need to consider causes in existing facilities which were not included in the Critical P&ID review. Therefore if a LOPA was conducted, it would be incomplete.

SIL to be defined in EPC phase. SIF not included in Preliminary SIL Verification Report

117

016-D-1006 high 016-D-1006 pressure (PSV + Trip)

016-PAHH-XXXX

-

118

017-D-31006 low 017-D-31006 level

017-LALL-31203 017-LALL31203

SIL 1

Not included in Preliminary SIL Verification Report since < SIL 2

017-PAHH-31308

SIL 0

Not SIL rated, not included in Preliminary SIL Verification Report

017-LALL-31302 017-LALL31302

SIL 0

Not SIL rated, not included in Preliminary SIL Verification Report

119

017-D-31005 high pressure

120

121

017-D-31005 high level

017-D-31009 low 017-D-31009 level

017-LALL-31357

-

The coalescer is not part of the critical P&ID review and hence not considered in LOPA as the LOPA calculations need to consider causes in other parts of the project facilities not included in the Critical P&ID review. Therefore if a LOPA was conducted, it would be incomplete

017-D-31005 017-D-310 05 low

SIL to be defined in EPC phase. SIF not included in Preliminary SIL Verification Report

Not SIL rated, not included in

122

level

017-LALL-31305 017-LALL-31305

SIL 0

123

017-D-31005 low 017-D-31005 condensate condensat e level

017-LALL-31302

No further risk reduction required

124

ORF high pressure (HIPPS)

017-PAHH-31152 (2oo3)

SIL 4+

SIF consider ed outstanding

125

ORF high pressure (PSV + Trip)

017-PAHH-31152 (1oo1)

SIL 2

Included in Preliminary SIL Verification Report

126

017-TK-31001 high 017-TK-31001 pressure

TEP-900-RPT-HS-BP4-0004 © BP p.l.c.

-

-

Open Recommendation Recommendation

SIL Verification Report Not SIL rated, not included in Preliminary SIL Verification Report

Produced water system is not part of the critical P&ID review and hence not considered in LOPA as the LOPA calculations need to consider causes in other parts of the project facilities not included in the Critical P&ID review. Therefore if a LOPA was conducted, it would be incomplete.

Page 15 of 43

SIL to be defined in EPC phase. SIF not included in Preliminary SIL Verification Report

Rev: A01 BP Confidential

 

Tangguh Expansion Project – LNG FEED Preliminary SIL Verification Report

LOPA Report Results No.

Hazardous Scenario Consequences

SIF to be verified

SIL Verification

LOPA Result

Scope of Work  Work 

Notes Existing systems were not part of the critical P&ID review and hence not considered in LOPA

127

128

129

130

016-TK-31001 high 016-TK-31001 pressure

-

087-TK-1004 high pressure

-

LNG loading arms sudden flow increase

-

LNG tanker high level

-

-

-

SIL to be defined in EPC phase. SIF not included in Preliminary SIL Verification Report

-

This scenario is not considered in LOPA as the team has insufficient information to decide on its credibility. Discuss when detailed drawings and documentation for loading arm package are available (during EPC).

SIL to be defined in EPC phase. SIF not included in Preliminary SIL Verification Report

-

This scenario is not considered in LOPA as the team has insufficient information to identify safeguards on the tankers at this stage of the project. Discuss when detailed information for the LNG tankers are available (during EPC).

072-D-31002 high level

132

LNG loading arms bowing / thermal shock

-

SIL 2

133

LNG loading line low pressure

-

No further risk reduction required.

134

LNG loading line high pressure

TEP-900-RPT-HS-BP4-0004 © BP p.l.c.

-

SIL to be defined in EPC phase. SIF not included in Preliminary SIL Verification Report

Existing systems were not part of the critical P&ID review and hence not considered in LOPA as the LOPA calculations need to consider causes in existing facilities which were not included in the Critical P&ID review. Therefore if a LOPA was conducted, it would be incomplete.

131

072-LAHH-31204 072-LAHH-312 04

as the LOPA calculations need to consider causes in existing facilities which were not included in the Critical P&ID review. Therefore if a LOPA was conducted, it would be incomplete.

Report

Not included in Preliminary SIL Verification Report since < SIL 2

SIL 1

SIL 2

SIL to be defined in EPC phase. SIF not included in Preliminary SIL Verification

Upon close out of Recommendation #154 this hazard may be removed or an additional IPL may be considered.

No SIF defined in LOPA, scenario not included in SIL SIL Verification Report Not SIL rated, not included in Preliminary SIL Verification Report

Upon close out of Recommendation #124 from the Critical P&ID Review, cause 2 may be removed.

Page 16 of 43

No SIF defined in LOPA, scenario not included in SIL Verification Report

Rev: A01 BP Confidential

 

Tangguh Expansion Project – LNG FEED Preliminary SIL Verification Report

LOPA Report Results No.

Hazardous Scenario Consequences

135

LNG vapour return line high pressure

136

072-P-31008 discharge pipework high pressure

137

LNG loading/circulation line bowing

138

Circulation line surge

139

LNG loading line surge

140

SIF to be verified

N2 system low temperature

SIL Verification

LOPA Result

Notes

Scope of Work  Work 

SIL 1

Upon close out of Recommendation #123 from the Critical P&ID Review.

Hazard has been removed following Company approval of Recommendation #123 implementation

-

SIL 2

Upon close out of Recommendation #139 from the Critical P&ID Review, cause 4 may be removed.

No SIF defined in LOPA, scenario not included in Preliminary SIL Verification Report

-

SIL 0

Not SIL rated, not included in Preliminary SIL Verification Report

-

SIL 2

No SIF defined in LOPA, scenario not included in Preliminary SIL Verification Report

-

SIL 1

Not included in Preliminary SIL Verification Report since < SIL 2 and no SIF defined in LOPA

-

Not included in Preliminary SIL -

SIL 1

Verification Report since < SIL 2 and no SIF defined in LOPA Upon close out of Recommendation #126 from the Critical P&ID Review an additional IPL may be considered.

Not included in Preliminary SIL Verification Report since < SIL 2 and no SIF defined in LOPA

141

Jetty 1 circulation line high flow

-

SIL 1

142

Jetty 2 circulation line high flow

-

SIL 1

Not included in Preliminary SIL Verification Report since < SIL 2 and no SIF defined in LOPA

143

LNG circulation line low pressure

-

No further risk reduction required.

Not SIL rated, not included in Preliminary SIL Verification Report

144

LNG circulation line high pressure

145

146

LNG tanker high pressure

LNG storage tank low pressure

-

-

-

No SIF defined in LOPA, scenario not included in Preliminary SIL Verification Report

SIL 2

-

-

This scenario is not considered in LOPA as the team has insufficient information to identify safeguards on the tankers at this stage of the project. Discuss when detailed information for the LNG tankers are available (during EPC). Existing systems were not part of the critical P&ID review and hence not considered in LOPA as the LOPA calculations need to consider causes in existing facilities which

SIL to be defined in EPC phase. SIF not included in Preliminary SIL Verification Report

SIL to be defined in EPC phase. SIF not included in Preliminary SIL Verification Report

were not included in the Critical P&ID review. Therefore if a LOPA was

TEP-900-RPT-HS-BP4-0004

Page 17 of 43

Rev: A01

© BP p.l.c.

BP Confidential

 

Tangguh Expansion Project – LNG FEED Preliminary SIL Verification Report

LOPA Report Results No.

Hazardous Scenario Consequences

SIF to be verified

SIL Verification

LOPA Result

Notes

Scope of Work  Work 

conducted, it would be incomplete. Existing systems were

147

148

LNG storage tank high pressure

LNG vapour return line bowing

-

-

-

SIL 1

149

Tankage flare low pressure

150

Vapour return arm/line high pressure (asphyxiation)

-

SIL 2

151

LNG loading arm high pressure

-

No further risk reduction required.

-

-

not part of theand critical P&ID review hence not considered in LOPA as the LOPA calculations need to consider causes in existing facilities which were not included in the Critical P&ID review. Therefore if a LOPA was conducted, it would be incomplete.

SIL to be defined in EPC phase. SIF not included in Preliminary SIL Verification Report

Upon close out of Recommendation #132 from the Critical P&ID Review, cause 1 may be removed.

Not included in Preliminary SIL Verification Report since < SIL 2 and no SIF defined in LOPA

The tankage flare is not part of the critical P&ID review and hence not considered in LOPA as the LOPA calculations need to consider causes in other parts of the project facilities not included in the Critical P&ID review. Therefore if a LOPA was conducted, it would be incomplete.

SIL to be defined in EPC phase. SIF not included in Preliminary SIL Verification Report

No SIF defined in LOPA, scenario not included in Preliminary SIL Verification Report Not SIL rated, not included in Preliminary SIL Verification Report Scenario not considered credible as cooldown facilities have not yet been provided for 072-P31008 (design error).

152

072-P-31008 uncontrolled cooldown

-

-

153

072-D-31002 low 072-D-31002 pressure

-

SIL 0

Not SIL rated, not included in Preliminary SIL Verification Report

154

072-D-31002 high pressure

-

SIL 0

Not SIL rated, not included in Preliminary SIL Verification Report

155

072-D-31002 rapid 072-D-31002 cooldown

-

SIL 1

Not included in Preliminary SIL Verification Report since < SIL 2 and no SIF defined in LOPA

156

Condensate loading line surge

-

SIL 1

Not included in Preliminary SIL Verification Report since < SIL 2 and no SIF defined in LOPA

157

Condensate tanker high level

-

-

TEP-900-RPT-HS-BP4-0004

This scenario is not considered in LOPA as the team has insufficient

Page 18 of 43

No SIF defined in LOPA, not included in preliminary SIL Verification Report

SIL to be defined in EPC phase. SIF not included in Preliminary SIL Verification

Rev: A01

© BP p.l.c.

BP Confidential

 

Tangguh Expansion Project – LNG FEED Preliminary SIL Verification Report

LOPA Report Results No.

Hazardous Scenario Consequences

SIF to be verified

SIL Verification

LOPA Result

Scope of Work  Work 

Notes information to identify Report safeguards on the tankers at this stage of the project. Discuss when detailed information for the condensate tankers are available (during EPC). This scenario is not considered in LOPA as the team has insufficient information to identify safeguards on the tankers at this stage of the project. Discuss when detailed information for the condensate tankers are available (during EPC).

SIL to be defined in EPC phase. SIF not included in Preliminary SIL Verification Report

158

Condensate tanker high pressure

-

-

159

Condensate loading line low pressure

-

SIL 0

Not SIL rated, not included in Preliminary SIL Verification Report

160

Condensate loading arm low pressure

-

No further risk reduction required.

Not SIL rated, not included in Preliminary SIL Verification Report

161

Condensate loading line high pressure

-

SIL 0

Not SIL rated, not included in Preliminary SIL Verification Report

162

076-P-31004 inlet piping low pressure

-

No further risk reduction required.

Not SIL rated, not included in Preliminary SIL Verification Report

163

162-D-31001A high level

162-LAHH-31682 162-LAHH-316 82

SIL 2

Included in SIL Verification Report

164

162-D-31001B high level

162-LAHH-31722 162-LAHH-317 22

SIL 2

Included in SIL Verification Report

165

LP steam header high pressure

-

SIL 1

Not included in Preliminary SIL Verification Report since < SIL 2 and no SIF defined in LOPA

166

167

LP steam header high temperature

LP steam header hammering

-

-

SIL 3

Upon close out of Recommendation #146 from the Critical P&ID Review an IPL may be considered.

No SIF defined in LOPA, scenario not included in SIL SIL Verification Report

SIL 3

Upon close out of Recommendation #153 from the Critical P&ID Review, this hazard may be removed or additional IPLs may be considered.

No SIF defined in LOPA, scenario not included in SIL SIL Verification Report

Upon close out of Recommendation #147 from the Critical P&ID Review, this hazard may be removed or additional IPLs may be considered.

No SIF defined in LOPA, scenario not included in Preliminary SIL Verification Report

168

MP steam header high temperature

-

SIL 2

169

MP steam header high pressure

-

SIL 1

TEP-900-RPT-HS-BP4-0004

Page 19 of 43

Not included in Preliminary SIL Verification Report since < SIL 2 and no SIF defined in LOPA

Rev: A01

© BP p.l.c.

BP Confidential

 

Tangguh Expansion Project – LNG FEED Preliminary SIL Verification Report

LOPA Report Results No.

170

Hazardous Scenario Consequences

MP steam header hammering

SIF to be verified

162-TALL-31486 162-TALL31486

SIL Verification

LOPA Result

SIL 3

Notes Upon close out of Recommendation #153 from the Critical P&ID Review, this hazard may

Scope of Work  Work 

Included in Preliminary SIL Verification Report

be removed or additional IPLs may be considered.

171

172

HP steam header hammering

Oxygen scavenger tank high level

-

-

SIL 3

-

Upon close out of Recommendation #153 from the Critical P&ID Review, this hazard may be removed or additional IPLs may be considered. This tank is not part of the critical P&ID review and hence not considered in LOPA as the LOPA calculations need to consider causes in other parts of the project facilities not included in the Critical P&ID review. Therefore if a LOPA was

No SIF defined in LOPA, scenario not included in Preliminary SIL Verification Report

SIL to be defined in EPC phase. SIF not included in Preliminary SIL Verification Report

conducted, it would be incomplete. This tank is not part of the critical P&ID review and hence not considered in LOPA as the LOPA calculations need to consider causes in other parts of the project facilities not included in the Critical P&ID review. Therefore if a LOPA was conducted, it would be incomplete.

SIL to be defined in EPC phase. SIF not included in Preliminary SIL Verification Report

173

Neutralization amine tank high level

-

-

174

162-D-31001A high pressure

-

SIL 0

Not SIL rated, not included in Preliminary SIL Verification Report

175

162-D-31001B high pressure

-

SIL 0

Not SIL rated, included in Preliminary SIL not Verification Report

176

De-emulsfier storage drum high pressure

-

-

This tank is not part of the critical P&ID review and hence not considered in LOPA as the LOPA calculations need to consider causes in other parts of the project facilities not included in the Critical P&ID review. Therefore if a LOPA was conducted, it would be incomplete.

SIL to be defined in EPC phase. SIF not included in Preliminary SIL Verification Report

Analysing the above table and excluding all scenario not associated t a specific SIF, a total of 57 SIFs have been identified, distributed as follows: 7 SIFs rated SIL 4+;  

TEP-900-RPT-HS-BP4-0004

Page 20 of 43

Rev: A01

© BP p.l.c.

BP Confidential

 

Tangguh Expansion Project – LNG FEED Preliminary SIL Verification Report

 

9 SIFs rated SIL 3;

 

17 SIFs rated SIL 2;

 

11 SIFs rated SIL 1;

 

8 SIFs rated SIL 0;

 

5 SIFs not rated (No further risk reduction required).











The Preliminary SIL verification has been performed for all the loops requiring SIL level 2 or SIL 3. However outstanding since further investigation is required, for SIL 4+ rated loops it has been investigated the maximum achievable SIL according to actual SIF design considered during LOPA analysis. In Table 2 the list of 33 SIFs to be subjected to FEED SIL Verification process. SIL 1 loops, not considered critical  critical will not be included in the Preliminary SIL verification report.

Table 2 – SIFs to be verified No.

SIF to be verified

SIL

3

053-PAHH-31187

SIL 3

4

043-PAHH-31032

SIL 2

5

053-PAHH-31858

SIL 2

7

043-PAHH-31726

SIL 2

8

053-PAHH-31487

SIL 2

12

043-LAHH-31044

SIL 2

20

043-LALL-31285

SIL 2

21

043-PAHH-31273

SIL 2

22

053-PAHH-31487

SIL 2

26

043-LAHH-31434

SIL 3

27

043-PAHH-31423

SIL 3

29

043-LALL-31434

SIL 2

33

043-PAHH-31573

SIL 4+

40

053-PDALL-31469

SIL 2

43

053-TAHH-31578

SIL 4+

47

053-TAHH-31638

SIL 4+

48

053-TAHH-31489

SIL 2

49

053-PAHH-31576

SIL 2

52

053-PAHH-31636

SIL 2

TEP-900-RPT-HS-BP4-0004

Page 21 of 43

Rev: A01

© BP p.l.c.

BP Confidential

 

Tangguh Expansion Project – LNG FEED Preliminary SIL Verification Report

No.

SIF to be verified

SIL

64

053-TAHH-31189

SIL 3

87

023-LALL-31084

SIL 2

93

023-FALL-31099

SIL 4+

023-FALL-31099

SIL 4+

111

017-LALL-31057

SIL 3

112

017-LALL-31060

SIL 3

113

017-LALL-31107

SIL 3

114

017-LALL-31110

SIL 3

124

017-PAHH-31152 (2oo3)

SIL 4+

125

017-PAHH-31152 (1oo1)

SIL 2

163

162-LAHH-31682

SIL 2

164

162-LAHH-31722

SIL 2

170

162-TALL-31486

SIL 3

94 (same as 93)

1.3 

Owner and Contractual Standards

GP 30-75

Safety Instrumented Systems (SIS) - Management of the Safety Lifecycle

GP 30-80

Safety Instrumented Systems (SIS) – Specification and Implementation

GP 48-06

Layer of Protection Analysis (LOPA).

1.4 

International Standards

IEC 61508

Functional Safety: Safety Related Systems

IEC 61511

Functional Safety: Safety instrumented systems for the process industry sector.

1.5 

Contractor Document

TEP-930-RPT-HS-BP4-0019

1.6 

LOPA WORKSHOP REPORT

Order of Precedence

1.  National or local regulatory standards where the work is being performed and/or where the facilities are to be installed; 2.  Contractual Requirements and Specifications, Datasheets etc.)

Project

Specific

Requirements

or

Standards

(e.g.

3.  BP Group Practice (GP); 4.  COMPANY Guidelines, Manuals and Procedures; International Regulations, Codes and Standards.

TEP-900-RPT-HS-BP4-0004

Page 22 of 43

Rev: A01

© BP p.l.c.

BP Confidential

 

Tangguh Expansion Project – LNG FEED Preliminary SIL Verification Report

2  Symbol Symbols, s, Abbreviations and Defini Definitions tions Abbreviations  BOG

Boil Off Gas.

EPC

Engineering, Procurement, and Construction.

FEED

Front End Engineering Design

HFT

Hardware Fault Tolerance

IEC

International Electrotechnical Commission

IPL

Independent Protection Layer

PFD

Probability of Failure on Demand

LNG

Liquefied Natural Gas.

LOPA

Layer of Protections Analysis

LPG

Liquefied Petroleum Gas.

NFPA

National Fire Protection Association.

PFDs

Process Flow Diagrams

P&IDs

Piping and Instrumentation Diagram

ORF

Onshore Receiving Facilities.

SIF

Safety Instrumented Function

SIL

Safety Integrity Level 

SIS

Safety Instrumented Function

TMR

Triple modular redundancy

TEP

Tangguh Expansion Project – LNG FEED

1oo1

Voting logic: 1 out of 1

1oo2

Voting logic: 1 out of 2

1oo3

Voting logic: 1 out of 3

2oo3

Voting logic: 2 out of 3

3oo3

Voting logic: 3 out of 3

Description

Definitions

Description

COMPANY

BP Berau Ltd.

CONTRACTOR

A selected company who has agreed to perform the work on the terms and conditions contained in the respective FEED and/or EPC contract.

Shall

Mandatory

Should/May

Discretional, but COMPANY approval to be sought for deviation.

TEP-900-RPT-HS-BP4-0004

Page 23 of 43

Rev: A01

© BP p.l.c.

BP Confidential

 

Tangguh Expansion Project – LNG FEED Preliminary SIL Verification Report

3  Methodology Methodology    3.1 

General

According to IEC 61508/61511, for each Safety Integrity Level, there is a corresponding probability of failure on demand that the system must not exceed. For the classification the greater the potential consequences and the expected frequency of demand are, the more reliable the loop must be. SIL levels and their associated target probabilities are shown in Table 3. For the target PFD, it has been considered the upper limit of each SIL requirement (as no margin requirements have been specified during the SIL Allocation) considering that literature data are conservatively used for the reliability calculation. Table 3 – Probability of failure on demand for SIL levels (Low Demand Mode) SIL

Probability of Failure on Demand

1

10-1÷10-2

2

10-2÷10-3

3

10-3÷10-4

4

10-4÷10-5

After the SIL required for a SIF has been identified by means of LOPA sessions, the SIF must be verified in order to check its adequacy both for the maximum required PFD and for architectural constrains (hardware fault tolerance). As per good engineering practice, loop testing frequency for PFD calculation has been assumed one year (8760 hours). The methodology for SIL verification is given by IEC 61508/61511 and is summarized in this document. Therefore two different requirements are given for each SIF in order to achieve the compliance to the standard: both probability performance and hardware fault tolerance (HFT) must be satisfied. No continuous mode of operation SIFs have been identified during the allocation activity.

3.2 

Probability Requirements

3.2.1 

General

The protection loops (SIF) are considered to be composed by the following items: 

     



The sensing element(s) The logic solver (SIS) The final element(s).

The average probability of failure on demand of the safety related system is determined by calculating and combining the average probability of failure on demand for all the subsystems which provide protection against a hazardous event. This is expressed by the following relationship:  PFD  PF D AVG

  PF    PF  PFD D SE      PFD D LS    PFD PFD FE 

 

where,

 

PFDAVG is the average probability of failure on demand of the safety-related system

 

PFDSE is the probability of failure on demand of the sensing element(s)

 

PFDLS is the probability of failure on demand of the logic system element

 

PFDFE is the probability of failure on demand of final element(s)

 

 

TEP-900-RPT-HS-BP4-0004

Page 24 of 43

Rev: A01

© BP p.l.c.

BP Confidential

 

Tangguh Expansion Project – LNG FEED Preliminary SIL Verification Report

To determine the probability of failure on demand of each of the components (i.e. sensors, logic system and final elements), the following procedure should be adhered to: 1.  Consider the block diagram showing the system input elements, logic solver or system output elements and represent each set of elements as 1oo1, 1oo2, 2oo2, 2oo3, 1oo3, 3oo3. Only the final elements that are critical for the protection function shall be considered in the evaluation of PFDFE, in fact critical is intended the action that protect the system against the deviation controlled by the SIF loop analyzed. Not all action foreseen by the C&E diagram are to be considered part of SIF (critical). 2.  For each sub-system element, select the parameters relevant to:  

probability of failure per hour, λ , for the element;   diagnostic coverage (DC);   the common cause β-factor;   proof test interval.

3.  Obtain the probability of failure on demand. The complete verification tables summarizing calculation reports for each analysed function are reported in Appendix A.

3.2.2 

PFD Formulas

In this paragraph the equations used for the SIL verification (i.e. for calculating the probability of failure on demand) are described per each architecture. Only reliability block diagrams present in actual design have been considered and used in the calculation reported in Appendix A. Voting logic 1oo1 This architecture consists of a single element, where any dangerous failure will prevent a valid alarm signal from being correctly processed.

Figure 1

Block diagram, voting logic 1oo1

Probability of failure can be calculated using the following formulas:

   DU    D         DD

:

 

(REF. IEC 61508-6 B.3.2.2.1) 

 

(REF. IEC 61508-6 B.3.2.2.1)

  1   DC      DU      D

(REF. IEC 61508-6 B.3.2.2.1)

  DD       D DC  

(REF. IEC 61508-6 B.3.2.2.1) 

TEP-900-RPT-HS-BP4-0004

D

Page 25 of 43

Rev: A01

© BP p.l.c.

BP Confidential

 

Tangguh Expansion Project – LNG FEED Preliminary SIL Verification Report

The value of device equivalent mean down time can be obtained as follows:

t CE 



  DU   T 1        MTTR    DD  MTTR     D   2     D

(REF. IEC 61508-6 B.3.2.2.1) 

Average probability of failure on demand can then be evaluated:

 P  PF FD AVG

    DU         DD t   CE   

(REF. IEC 61508-6 B.3.2.2.1). 

Voting logic 1oo2 This architecture consists of two elements connected in parallel, such that either element can command a shutdown output. Thus, there would have to be a dangerous failure in both elements in order for a valid alarm signal not to be correctly processed. It is assumed that any diagnostic testing would only report the faults and would not change any output states or the output voting.

Figure 2

Block diagram, voting logic 1oo2

To evaluate average probability of failure on demand, system equivalent mean down time (tGE) shall be defined, using the following formula:

T  t GE 

 DU  1  DD  MTTR         3   MTTR            D  D

(REF. IEC 61508-6 B.3.2.2.2).

Average probability of failure on demand can then be evaluated:

 PFD  PF D AVG

 2 1       1      

2

 D

 DD

 DU 

 

t CE  t    GE 

       D

 DD

   T   MTTR        2

 MTTR        DU  

1

(REF. IEC 61508-6 B.3.2.2.2) D.

TEP-900-RPT-HS-BP4-0004

Page 26 of 43

Rev: A01

© BP p.l.c.

BP Confidential

 

Tangguh Expansion Project – LNG FEED Preliminary SIL Verification Report

Voting logic 2oo2 This architecture has two channels connected in parallel so that both channels need to demand the safety function before it can take place. It is assumed that any diagnostic testing would only report the faults and would not change any output states or the output voting.

Figure 3

Block diagram, voting logic 2oo2

Average probability of failure on demand can then be evaluated:

 PF  PFD AVG    2     D t CE   

(REF. IEC 61508-6 B.3.2.2.3) 

Voting logic 2oo3 This architecture consists of three elements connected in parallel with a majority voting arrangement for the output signals, such that the output state is not changed if only one channel demands the safety function to intervene. It is assumed that any diagnostic testing would only report the faults and would not change any output states or the output voting.

Figure 4

Block di diagram, agram, voting logic valid for 1oo3, 2oo3 and 3oo3

Average probability of failure on demand can then be evaluated:  PFD  PF D AVG

 6 1        1       D

 DD

 DU 

2

 

t CE  t  GE 

       D

 DD

   T   MTTR        2

 MTTR        DU  

1

(REF. IEC 61508-6 B.3.2.2.5). 

TEP-900-RPT-HS-BP4-0004

Page 27 of 43

Rev: A01

© BP p.l.c.

BP Confidential

 

Tangguh Expansion Project – LNG FEED Preliminary SIL Verification Report

Voting logic 1oo3 This architecture consists of three channels connected in parallel with a voting arrangement for the output signals, such that the output state follows 1oo3 voting. It is assumed that any diagnostic testing would only report the faults found and would not change any output states or change the output voting. The average probability of failure on demand for the architecture is:  PFD  PF D AVG

 61       1     

3

 D

 DD

t G 2 E 

 DU 



 

t CE t GE   t G 2 E 

      D

       MTTR       4    

  DU   T 1

 DD

 D

   T   MTTR        2

 MTTR       DU    DD

1

 MTTR  

 D

(REF. IEC 61508-6 B.3.2.2.6). Voting logic 3oo3 This architecture has three channels connected in parallel so that all the three channels need to demand the safety function before it can take place. It is assumed that any diagnostic testing would only report the faults and would not change any output states or the output voting. Average probability of failure on demand has been evaluated considering the structure of 2oo2 equation:  PF  PFD AVG    3     D t CE 

3.3 

 

Hardware Fault Tolerance

Safety instrumented functions, may need to have a minimum Hardware Fault Tolerance (HFT) requirements based on the SIL level allocated. It is important to note that the Hardware Fault Tolerance represents the minimum component or subsystem redundancy requirements. In particular, hardware fault tolerance is the capability of a component or subsystem to continue to be able to function with one or more dangerous faults in the hardware. A Hardware Fault Tolerance equal to 1 means that there are for example two devices and the architecture is such that the dangerous failure of one of the two components or subsystems does not prevent the safety action from occurring on demand. A Hardware Fault Tolerance equal to 2 means that there are for example three devices and the architecture is such that the dangerous failure of two of the three components or subsystems does not prevent the safety action from occurring on demand. Requirements related to HFT foreseen by IEC 61511 are shown in the following Table 4 for each level. Table 4 – Minimum hardware fault tolerance of sensors and final elements SIL

Minimum Hardware Fault Tolerance

1

0

2

1

3

2

4

Special requirements apply - see IEC-61508

TEP-900-RPT-HS-BP4-0004

Page 28 of 43

Rev: A01

© BP p.l.c.

BP Confidential

 

Tangguh Expansion Project – LNG FEED Preliminary SIL Verification Report

If elements are not fail safe, above requirements have to be increased by 1 order. Vice versa, HFT can be reduced by 1 order if the following requirements are satisfied:

 

the hardware of the device is selected on the basis of prior use;

 

the device allows adjustment of process-related parameters only, e.g., measuring range, upscale or downscale failure direction;

 

the adjustment of the process-related parameters of the device is protected, e.g., jumper, password;

 

the function has a SIL requirement less than 4.

 





Above approach applies to sensors and final elements only. Logic solver HTF follows only the requirements given in IEC-61511 part 1 clauses 11.4.2 to 11.4.4, based on SFF, as reported in Table 5. Table 5 – Minimum hardware fault tolerance of PE logic solvers Minimum Hardware Fault Tolerance SIL

SFF < 60

SFF 60

to 90

SFF > 90

1

1

0

0

2

2

1

0

3

3

2

1

4

Special requirements apply - see IEC 61508

According to IEC-61508, IEC-61508, redundancies can be evaluated following the SFF approach, if vendor’s certifications are available. Elements and subsystems are divided in two categories, type A and type B, as defined: An element can be regarded as type A if, for the components required to achieve the safety function: a.  the failure modes of all constituent components are well defined; and b.  the behaviour of the element under fault conditions can be completely determined; and c.  there is sufficient dependable failure data to show that the claimed rates of failure for detected and undetected dangerous failures are met. Instead an element shall be regarded as type B if, for the components required to achieve the safety function: a.  the failure mode of at least one constituent component is not well defined; or b.  the behaviour of the element under fault conditions cannot be completely determined; or c.  there is insufficient dependable failure data to support claims for rates of failure for detected and undetected dangerous failures. For each type of elements and subsystems IEC-61508 lists the architectural requirements as per following tables (Table 6 and Table 7).

TEP-900-RPT-HS-BP4-0004

Page 29 of 43

Rev: A01

© BP p.l.c.

BP Confidential

 

Tangguh Expansion Project – LNG FEED Preliminary SIL Verification Report

Table 6 – Maximum allowable SIL for a SIF carried out by a type A safety-related element or subsystem Safe failure fraction of an element

Hardware fault tolerance 0

1

2

< 60 %

SIL 1

SIL 2

SIL 3

60 % – < 90 %

SIL 2

SIL 3

SIL 4

90 % – < 99 %

SIL 3

SIL 4

SIL 4

SIL 3

SIL 4

SIL 4

 99

%

Table 7 – Maximum allowable SIL for a SIF carried out by a type B safety-related element or subsystem Safe failure fraction of an element

Hardware fault tolerance 0

1

2

< 60 %

Not Allowed

SIL 1

SIL 2

60 % – < 90 %

SIL 1

SIL 2

SIL 3

90 % – < 99 %

SIL 2

SIL 3

SIL 4

SIL 3

SIL 4

SIL 4

 99

%

TEP-900-RPT-HS-BP4-0004

Page 30 of 43

Rev: A01

© BP p.l.c.

BP Confidential

 

Tangguh Expansion Project – LNG FEED Preliminary SIL Verification Report

4  Reliability Data 4.1 

General

Reliability data used during the verification activity, relating to each component of the SIF, are presented in the following Table 8. The following information are shown per single subsystem: 

   

instrument code as per SIL verification sheet; reliability data;

 

subsystem Type, as per IEC 61508;

 

β factor;

 

MTTR as per contractual requirements;

 

references.









According to project phase, barriers, QEV, aut similia are not considered in this report. A general β factor of 5% has been considered in PFD calculation. As per contractual requirement, a minimum of SFF=60% is consider for all subsystems, even though differently reported in relevant databank reference.

Table 8 – Reliability Data for Components λ  

Component

Code

Failure rate [oc/hr]

Level transmitter (radar)

Generic Pressure Transmitter

λ D 

Dangerous failure rate [oc/hr]

DC [-]

β 

[-]

MTTR

SFF

[hr]

[-]

Type

Reference

Exida FMEDA LT

PT

1,60E-06

1,30E-06

1,60E-06

8,00E-07

86%

60%

5%

5%

8

8

91%

75%

B

Report No.: Rosemount 08/02-17 R005

B

Item 5.1.3 "Reliability Data for Safety Instrumented Systems", SINTEF PDS Data Handbook, 2010 Edition

Generic Temperature Transmitter

TT

2,00E-06

7,00E-07

60%

5%

8

86%

B

Item 5.1.5 "Reliability Data for Safety Instrumented Systems", SINTEF PDS Data Handbook, 2010 Edition

SIS Logic Solver

SIS

--

--

--

--

--

>99 %

B

PFD=1.0E-04 (Average data from Vendors)

A

Item 5.3.4 "Reliability Data for Safety Instrumented Systems", SINTEF PDS Data Handbook, 2010 Edition

Solenoid Valve

SIS/XV including actuator

SY

XV

3,00E-06

5,30E-06

1,10E-06

3,00E-06

30%

0%

5%

5%

(excluding pilot)

TEP-900-RPT-HS-BP4-0004

72

72

74%

43%

A

Item 5.3.1 "Reliability Data for Safety Instrumented Systems", SINTEF PDS Data Handbook, 2010 Edition

Page 31 of 43

Rev: A01

© BP p.l.c.

BP Confidential

 

Tangguh Expansion Project – LNG FEED Preliminary SIL Verification Report

λ  

Component

USVE valve

Code

USVE

Failure rate

λ D 

[oc/hr]

Dangerous failure rate [oc/hr]

8,30E-06

4,10E-06

DC

β 

MTTR

SFF

[-]

[-]

[hr]

[-]

0%

5%

72

51%

Type

A

Reference

Combined value from solenoid valve and XV valve.

As specific reliability data provided from vendors are not available, generic figures, referenced in international hand books has been used to perform the reliability assessment. When available, the reliability data of Vendor will be verified and used for the next Verification calculations. According to the equations described in IEC 61508, β factor listed in Table 8 doesn’t have any effect if not redundant NooN architecture are used (e.g. 1oo1, 2oo2); if redundant NooM (N99%.

4.4 

Final Elements

Final elements are mainly represented by valve closure/opening and machine trips actions and are generally considered the weak part of the SIF. In order to calculate the PFD related to the final elements the analysis has been focused only on the final elements considered critical for the evaluated function, i.e. those final elements that actually provide a protection for the concerned process deviation as defined summaries during the enclosed allocationinmeetings. calculation the report.Moreover these critical end modules are shown in the The probabilities of failure on demand have been obtained on the basis of the failure rates values, DC and β factor shown in Table 8. Probability of failure on demand for final elements has been calculated on the basis of an initial proof test period of 8760 hours and of the equations described in relevant paragraph.

4.5 

PFD Calculation Chart

Considering the abovementioned assumptions, methodology and reliability data, for each subsystem the following PFD values apply, according to relevant architecture.

4.6 

Architectural Constraints

Based on component reliability (i.e. SFF), it is possible to identify which safety integrity level can be achieved based on the loop architecture provided; for each type of component, according to its SFF, maximum SIL level for each redundancy (HFT) is shown in the following Table 9.

TEP 900 RPT HS BP4 0004

Page 32 of 43

Rev: A01

© BP p.l.c.

BP Confidential

 

Tangguh Expansion Project – LNG FEED Preliminary SIL Verification Report

Table 9

SIL satisfied based on SFF and redundancy Component

Code

Flow transmitter

FT

Level transmitter transmitter

Type

HFT=0

HFT=1

HFT=2

84%

B

SIL 1

SIL 2

SIL 3

LT

81%

B

SIL 1

SIL 2

SIL 3

Generic Pressure Transmitter

PT

75%

B

SIL 1

SIL 2

SIL 3

Generic Temperature Transmitter

TT

86%

B

SIL 1

SIL 2

SIL 3

SIS Logic Solver

SIS

>99%

B

SIL 3

SIL 4

SIL 4

Motor failure to trip/start

MT

60%

A

SIL 3

SIL 4

SIL 4

Blowdown valve (excluding pilot)

USVD

33%

A

SIL 2

SIL 3

SIL 4

X-tree valve (excluding pilot)

ESV

45%

A

SIL 1

SIL 2

SIL 3

SIS/XV including actuator (excluding pilot)

XV

43%

A

SIL 1

SIL 2

SIL 3

Solenoid Valve

SY

74%

A

SIL 2

SIL 3

SIL 4

Control valve

CV

68%

A

SIL 2

SIL 3

SIL 4

UZV valve

USVE

60%

A

SIL 2

SIL 3

SIL 4

(*) Outside BIDDER Scope of Work

SFF [

]

TEP 900 RPT HS BP4 0004

Page 33 of 43

Rev: A01

© BP p.l.c.

BP Confidential

 

Tangguh Expansion Project – LNG FEED Preliminary SIL Verification Report

5  SIL Verificatio Verification n Results The SIL verification has been performed for all the loops requiring SIL level 2 or higher, as specified in par. 1.2.. For all safety functions classified as SIL 2 and SIL 3, it has been verified if the specific reliability requirement is satisfied in terms of both probability of failure on demand (PFD) and architectural constraints (HFT). For SIL 4+ considered outstanding sinceSIL further investigation is required, it hasduring been indicated in rated Notesloops, column the maximum achievable according to SIF design considered LOPA analysis. SIL Verification has been performed considering actual SIF arrangement, as modified incorporating recommendations from Critical P&ID Review. The summary of the results of the SIL verification for all SIL rated functions are reported in Table 10, together with relevant remarks indicating the necessary improving actions in order to fulfil SIL requirements, both in terms of PFD and HFT, for all SIFs not positively verified. Test interval used during verification study is equal to 8760 h (1 year). Detailed calculations for each SIF is given in following attachments:

 

A – PFD SIL Verification Sheets

 

B – HFT SIL Verification Sheets





Table 10 – SIL verification results N.

SIF

3

Compliance

SIL

Notes

target

PFD

HFT

SIL

053-P 053-PIT-31187-HH IT-31187-HH

3

NO

NO

NO

Refer to Table 12

4

043-P 043-PIT-31032-HH IT-31032-HH

2

NO

NO

NO

Refer to Table 12

5

053-P 053-PIT-31858-HH IT-31858-HH

2

NO

NO

NO

Refer to Table 12

7

043-P 043-PIT-31726-HH IT-31726-HH

2

NO

NO

NO

Refer to Table 12

8

053-P 053-PIT-31487-HH IT-31487-HH

2

NO

NO

NO

Refer to Table 12

12

043-LIT-31 043-LIT-31044-LL 044-LL

2

NO

NO

NO

Refer to Table 12

20

043-LIT-31 043-LIT-31285-LL 285-LL

2

NO

NO

NO

Refer to Table 12

21

043-PIT-31273-HH 043-PIT-31273-HH

2

NO

NO

NO

Refer to Table 12

22

053-PIT-31487-HH 053-PIT-31487-HH

2

NO

NO

NO

Refer to Table 12

26

043-LIT-31434-HH 043-LIT-31434-HH

3

NO

NO

NO

Refer to Table 12

27

043-PIT-31423-HH 043-PIT-31423-HH

3

NO

NO

NO

Refer to Table 12

29

043-LIT-31 043-LIT-31434-LL 434-LL

2

NO

NO

NO

Refer to Table 12

33

043-PIT-31573-HH 043-PIT-31573-HH

4+

--

--

--

Refer to Table 12

40

053-PDIT-31469-LL 053-PDIT-31469-LL

2

NO

NO

NO

Refer to Table 12

43

053-TIT-31578-HH 053-TIT-31578-HH

4+

--

--

--

Refer to Table 12

47

053-TIT-31638-HH 053-TIT-31638-HH

4+

--

--

--

Refer to Table 12

48

053-TIT-31489-HH 053-TIT-31489-HH

2

NO

NO

NO

Refer to Table 12

TEP-900-RPT-HS-BP4-0004

Page 34 of 43

Rev: A01

© BP p.l.c.

BP Confidential

 

Tangguh Expansion Project – LNG FEED Preliminary SIL Verification Report

N.

SIF

49

Compliance

SIL

Notes

target

PFD

HFT

SIL

053-PIT-31576-HH 053-PIT-31576-HH

2

NO

NO

NO

Refer to Table 12

52

053-PIT-31636-HH 053-PIT-31636-HH

2

NO

NO

NO

Refer to Table 12

64

053-TIT-31189-HH 053-TIT-31189-HH

3

NO

NO

NO

Refer to Table 12

87

023-LIT-31 023-LIT-31084-LL 084-LL

2

NO

NO

NO

Refer to Table 12

93

023-FIT-31 023-FIT-31099-LL 099-LL

4+

--

--

--

Refer to Table 12

94

Same as 93

Same as 93

Same as 93

Same as 93

Same as 93

Same as 93

111

017-LIT-31 017-LIT-31057-LL 057-LL

3

NO

NO

NO

Refer to Table 12

112

017-LIT-31 017-LIT-31060-LL 060-LL

3

NO

NO

NO

Refer to Table 12

113

017-LIT-31 017-LIT-31107-LL 107-LL

3

NO

NO

NO

Refer to Table 12

114

017-LIT-31 017-LIT-31110-LL 110-LL

3

NO

NO

NO

Refer to Table 12

124

017-PIT-31152A/B/C-HH 017-PIT-31152A/B/CHH

4+

--

--

--

Refer to Table 12

125

017-PIT-31152 017-PIT-31152

2

NO

NO

NO

Refer to Table 12

163

162-LI-31682-HH 162-LI-31682-HH

2

NO

NO

NO

Refer to Table 12

164

162-LI-31722-HH 162-LI-31722-HH

2

NO

NO

NO

Refer to Table 12

170

162-TI162-TI-31486-LL 31486-LL

3

NO

NO

NO

Refer to Table 12

NOTES:

 

YES:

SIL achieved

 

NO:

SIL not achieved





TEP-900-RPT-HS-BP4-0004

Page 35 of 43

Rev: A01

© BP p.l.c.

BP Confidential

 

Tangguh Expansion Project – LNG FEED Preliminary SIL Verification Report

6  Conclusions and Recommendations In this section conclusions/recommendations arisen after verification step for each SIF are presented; when a SIF doesn’t satisfy SIL requirements (refer to  Table 10), a specific recommendation applicable to the mention subsystem has been issued and listed in Table 12.

Regarding USVE valves, consisting of a system including solenoid and XV valve body, in order to support valves vendors selection in Table 11 it has been indicated reliability data to fulfil SIL 2 requirement, without redundancy. This value shall be considered as a the maximum reliability requirement to be considered in EPC phase, in case redundancy for sensors in SIL 2 loop will be not applied.

Table 11 – USVE Reliability Data λ  

Component

USVE valve

Failure rate [oc/hr]

Dangerous failure rate [oc/hr]

1,00E-06

4,00E-07

Code

USVE

λ D 

DC

β 

MTTR

SFF

[-]

[-]

[hr]

[-]

0%

5%

72

60%

Type

Reference

A

According to GP 30-80, par. 9.5, bullet m., for SIL 3 a minimum of 2 final element shall be utilized, consequently final element should have a redundancy.

Table 12 – Recommendations Table N.

3

4

5

SIF

053-P 053-PAHH-31187 AHH-31187

043-PIT-31032-HH 043-PIT-31032-HH

053-PIT-31858-HH

SIL Target

Involved Subsystems

Proposed Recommendation

053-PAHH-31187

For sensor a redundancy (i.e. voting 1oo2 or 2oo3) shall be applied unless on market transmitter certified for SIL 3 application is available

053-USVE-31222 (Trip HP FG to 053-CG-31001)

For valve and its components (e.g. solenoid, actuator, body, et other applicable) a redundancy (i.e. voting 1oo2) shall be applied (ref. BP 30-80)

043-PIT-31032-HH

Sensor to be certified suitable to SIL 2 application (HFT=0), otherwise a redundancy (i.e. voting 1oo2 or 2oo3) shall be applied

043-USVE-31062

Valve and its components (e.g. solenoid, actuator, body, et other applicable) to be provided with minimum reliability data as per Table 11 and certified suitable to SIL 2 application (HFT=0), otherwise a redundancy (i.e. voting 1oo2) shall be applied

3

2

2

053-PIT-31858-HH

Sensor to be provided certified suitable to SIL 2 application (HFT=0), otherwise a redundancy (i.e. voting 1oo2 or 2oo3) shall be applied

TEP-900-RPT-HS-BP4-0004

Page 36 of 43

© BP p.l.c.

Rev: A01 BP Confidential

 

Tangguh Expansion Project – LNG FEED Preliminary SIL Verification Report

N.

7

8

SIF

043-PIT-31726-HH 043-PIT-31726-HH

053-PIT-31487-HH 053-PIT-31487-HH

SIL Target

Involved Subsystems

053-USVE-31990/31951 31989/31988

Valve and its components (e.g. solenoid, actuator, body, other applicable) to be provided with minimum reliability data as per Table 11 and certified suitable to SIL 2 application (HFT=0), otherwise a redundancy (i.e. voting 1oo2) shall be applied

043-PIT-31726-HH

Sensor to be provided certified suitable to SIL 2 application (HFT=0), otherwise a redundancy (i.e. voting 1oo2 or 2oo3) shall be applied

043-USVE31085/31725/31866/3186 7/31868

Valve and its components (e.g. solenoid, actuator, body, et other applicable) to be provided with minimum reliability data as per Table 11 and certified suitable to SIL 2 application (HFT=0), otherwise a redundancy (i.e. voting 1oo2) shall be applied

053-PIT-31487-HH

Sensor to be provided certified suitable to SIL 2 application (HFT=0), otherwise a redundancy (i.e. voting 1oo2 or 2oo3) shall be applied

2

2

Valve and its components (e.g. solenoid, actuator, body, et other applicable) to be 053-USVE-31464

12

043-LIT-31044-LL 043-LIT-31044-LL

Proposed Recommendation

provided with minimum reliability data as per Table 11 and certified suitable to SIL 2 application (HFT=0), otherwise a redundancy (i.e. voting 1oo2) shall be applied

043-LIT-31044-LL

Sensor to be provided certified suitable to SIL 2 application (HFT=0), otherwise a redundancy redundan cy (i.e. voting 1oo2 o r 2oo3) shall be applied

043-USVE-31047

Valve and its components (e.g. solenoid, actuator, body, et other applicable) to be provided with minimum reliability data as per Table 11 and certified suitable to SIL 2 application (HFT=0), otherwise a redundancy (i.e. voting 1oo2) shall be applied

2

043-LIT-31285-LL

Sensor to be provided certified suitable to SIL 2 application (HFT=0), otherwise a redundancy (i.e. voting 1oo2 or 2oo3) shall be applied

20

21

043-LIT-31285-LL 043-LIT-31285-LL

043-PIT 043-PIT-31273-HH -31273-HH

2 043-USVE-31288

Valve and its components (e.g. solenoid, actuator, body, et other applicable) to be provided with minimum reliability data as per Table 11 and certified suitable to SIL 2 application (HFT=0), otherwise a redundancy (i.e. voting 1oo2) shall be applied

043-PIT-31273-HH

Sensor to be provided certified suitable to SIL 2 application (HFT=0), otherwise a redundancy (i.e. voting 1oo2 or 2oo3) shall be applied

043-USVE31293/31277/31047

Valve and its components (e.g. solenoid, actuator, body, et other applicable) to be provided with minimum reliability data as per Table 11 and certified suitable to SIL 2

2

053-USVE-31885

application (HFT=0), otherwise a redundancy (i.e. voting 1oo2) shall be applied

TEP-900-RPT-HS-BP4-0004

Page 37 of 43

Rev: A01

© BP p.l.c.

BP Confidential

 

Tangguh Expansion Project – LNG FEED Preliminary SIL Verification Report

N.

SIF

SIL Target

Involved Subsystems

053-PIT-31487-HH

22

053-PIT 053-PIT-31487-HH -31487-HH

2

27

29

33

40

43

043-LIT 043-LIT-31434-HH -31434-HH

043-PIT 043-PIT-31423-HH -31423-HH

043-LIT-31434-LL 043-LIT-31434-LL

043-PIT 043-PIT-31573-HH -31573-HH

053-PDIT 053-PDIT-31469-LL -31469-LL

053-TIT 053-TIT-31578-HH -31578-HH

Sensor to be provided certified suitable to SIL 2 application (HFT=0), otherwise a redundancy (i.e. voting 1oo2 or 2oo3) shall be applied Valve and its components (e.g. solenoid, actuator, body, et other applicable) to be

053-USVE-31522 (Trip HP FG to 053-CG-31002)

26

Proposed Recommendation

provided with minimum reliability data as per Table 11 and certified suitable to SIL 2 application (HFT=0), otherwise a redundancy (i.e. voting 1oo2) shall be applied

043-LIT-31434-HH

For sensor a redundancy (i.e. voting 1oo2 or 2oo3) shall be applied unless on market transmitter certified for SIL 3 application is available

043-USVE-31441/31288

For valve and its components (e.g. solenoid, actuator, body, et other applicable) a redundancy (i.e. voting 1oo2) shall be applied (ref. BP 30-80)

043-PIT-31423-HH

For sensor a redundancy (i.e. voting 1oo2 or 2oo3) shall be applied unless on market transmitter certified for SIL 3 application is available

043-USVE31452/31441/31288

For valves and its components (e.g. solenoid, actuator, body, et other applicable) a redundancy (i.e. voting 1oo2) shall be applied (ref. BP 30-80)

043-LIT-31434-LL

Sensor to be provided certified suitable to SIL 2 application (HFT=0), otherwise a redundancy (i.e. voting 1oo2 or 2oo3) shall be applied

043-USVE-31437

Valve and its components (e.g. solenoid, actuator, body, et other applicable) to be provided with minimum reliability data as per Table 11 and certified suitable to SIL 2 application (HFT=0), otherwise a redundancy (i.e. voting 1oo2) shall be applied

043-PIT-31573-HH

SIF to be further investigate investigated. d.

043-USVE-31602/31437

Maximum achievable SIL: 2 according to SIF design analyzed during LOPA. In this case the recommendation are the same as for other SIL 2 rated SIFs

053-PDIT-31469-LL

Sensor to be provided certified suitable to SIL 2 application (HFT=0), otherwise a redundancy (i.e. voting 1oo2 or 2oo3) shall be applied

053-USVE-31466

Valve and its components (e.g. solenoid, actuator, body, et other applicable) to be provided with minimum reliability data as per Table 11 and certified suitable to SIL 2 application (HFT=0), otherwise a redundancy (i.e. voting 1oo2) shall be applied

053-TIT-31578-HH

SIF to be further investigate investigated. d.

053-USVE-31522 (Trip HP FG to 053-CG-31002)

Maximum achievable SIL: 2 according to SIF design analyzed during LOPA. In this case the recommendation are the same as for other SIL 2 rated SIFs

3

3

2

4+

2

4+

TEP-900-RPT-HS-BP4-0004

Page 38 of 43

Rev: A01

© BP p.l.c.

BP Confidential

 

Tangguh Expansion Project – LNG FEED Preliminary SIL Verification Report

N.

47

48

49

52

64

87

93

SIF

053-TIT 053-TIT-31638-HH -31638-HH

053-TIT 053-TIT-31489-HH -31489-HH

053-PIT 053-PIT-31576-HH -31576-HH

053-PIT 053-PIT-31636-HH -31636-HH

053-TIT 053-TIT-31189-HH -31189-HH

023-LIT-31084-LL 023-LIT-31084-LL

023-FIT-31099- LL

SIL Target

4+

Involved Subsystems

Proposed Recommendation

053-TIT-31638-HH

SIF to be further investigate investigated. d.

053-USVE-31222 (Trip HP FG to 053-CG-31001)

Maximum achievable SIL: 2 according to SIF design analyzed during LOPA. In this case the recommendation are the same as for other SIL 2 rated SIFs

053-TIT-31489-HH

Sensor to be provided certified suitable to SIL 2 application (HFT=0), otherwise a redundancy (i.e. voting 1oo2 or 2oo3) shall be applied

053-USVE-31522 (Trip HP FG to 053-CG-31002)

Valve and its components (e.g. solenoid, actuator, body, et other applicable) to be provided with minimum reliability data as per Table 11 and certified suitable to SIL 2 application (HFT=0), otherwise a redundancy (i.e. voting 1oo2) shall be applied

053-PIT-31576-HH

Sensor to be provided certified suitable to SIL 2 application (HFT=0), otherwise a redundancy (i.e. voting 1oo2 or 2oo3) shall be applied

053-USVE-31522 (Trip HP FG to 053-CG-31002)

Valve and its components (e.g. solenoid, actuator, body, et other applicable) to be provided with minimum reliability data as per Table 11 and certified suitable to SIL 2 application (HFT=0), otherwise a redundancy (i.e. voting 1oo2) shall be applied

053-PIT-31636-HH

Sensor to be provided certified suitable to SIL 2 application (HFT=0), otherwise a redundancy (i.e. voting 1oo2 or 2oo3) shall be applied

053-USVE-31222 (Trip HP FG to 053-CG-31001)

Valve and its components (e.g. solenoid, actuator, body, et other applicable) to be provided with minimum reliability data as per Table 11 and certified suitable to SIL 2 application (HFT=0), otherwise a redundancy (i.e. voting 1oo2) shall be applied

053-TIT-31189-HH

For sensor a redundancy (i.e. voting 1oo2 or 2oo3) shall be applied unless on market transmitter certified for SIL 3 application is available

053-USVE-31222 (Trip HP FG to 053-CG-31001)

For valves and its components (e.g. solenoid, actuator, body, et other applicable) a redundancy (i.e. voting 1oo2) shall be applied (ref. BP 30-80)

023-LIT-31084-LL

Sensor to be provided certified suitable to SIL 2 application (HFT=0), otherwise a redundancy redundan cy (i.e. voting 1oo2 o r 2oo3) shall be applied

023-USVE-31103

Valve and its components (e.g. solenoid, actuator, body, et other applicable) to be provided with minimum reliability data as per Table 11 and certified suitable to SIL 2 application (HFT=0), otherwise a redundancy (i.e. voting 1oo2) shall be applied

023-FIT-31099- LL

SIF to be further investigate investigated. d.

2

2

2

3

2

4+

TEP-900-RPT-HS-BP4-0004

Page 39 of 43

Rev: A01

© BP p.l.c.

BP Confidential

 

Tangguh Expansion Project – LNG FEED Preliminary SIL Verification Report

N.

94

111

112

SIF

Same as 93

017-LIT 017-LIT-31057-LL -31057-LL

017-LIT 017-LIT-31060-LL -31060-LL

SIL Target

Same as 93

Involved Subsystems

Proposed Recommendation

023-USVE-31101

Maximum achievable SIL: 2 according to SIF design analyzed during LOPA. In this case the recommendation are the same as for other SIL 2 rated SIFs

Same as 93

Same as 93

017-LIT-31057-LL

For sensor a redundancy (i.e. voting 1oo2 or 2oo3) shall be applied unless on market transmitter certified for SIL 3 application is available

017-USVE-31064

For valves and its components (e.g. solenoid, actuator, body, et other applicable) a redundancy (i.e. voting 1oo2) shall be applied (ref. BP 30-80)

017-LIT-31060-LL

For sensor a redundancy (i.e. voting 1oo2 or 2oo3) shall be applied unless on market transmitter certified for SIL 3 application is available

3

3 017-USVE-31065

For valves and its components (e.g. solenoid, actuator, body, et other applicable) a redundancy (i.e. voting 1oo2) shall be applied (ref. BP 30-80)

113

114

124

125

017-LIT 017-LIT-31107-LL -31107-LL

017-LIT 017-LIT-31110-LL -31110-LL

017-PIT-31152A/B/ 017-PIT-31152A/B/C-HH C-HH

017-PIT 017-PIT-31152-HH -31152-HH

017-LIT-31107-LL

For sensor a redundancy (i.e. voting 1oo2 or 2oo3) shall be applied unless on market transmitter certified for SIL 3 application is available

017-USVE-31114

For valves and its components (e.g. solenoid, actuator, body, et other applicable) a redundancy (i.e. voting 1oo2) shall be applied (ref. BP 30-80)

017-LIT-31110-LL

For sensor a redundancy (i.e. voting 1oo2 or 2oo3) shall be applied unless on market transmitter certified for SIL 3 application is available

017-USVE-31115

For valves and its components (e.g. solenoid, actuator, body, et other applicable) a redundancy (i.e. voting 1oo2) shall be applied (ref. BP 30-80)

017-PIT-31152A/B/C-H H

SIF to be further investigate investigated. d.

017-USVE-31156

Maximum achievable SIL: 2 according to SIF design analyzed during LOPA. In this case the recommendation are the same as for other SIL 2 rated SIFs

017-PIT-31152-HH

Sensor to be provided certified suitable to SIL 2 application (HFT=0), otherwise a redundancy (i.e. voting 1oo2 or 2oo3) shall be applied

3

3

4+

2 017-USVE-31156

Valve and its components (e.g. solenoid, actuator, body, et other applicable) to be provided with minimum reliability data as per Table 11 and certified suitable to SIL 2 application (HFT=0), otherwise a redundancy (i.e. voting 1oo2) shall be applied

TEP-900-RPT-HS-BP4-0004

Page 40 of 43

© BP p.l.c.

Rev: A01 BP Confidential

 

Tangguh Expansion Project – LNG FEED Preliminary SIL Verification Report

N.

SIF

SIL Target

Involved Subsystems

162-LI-31682-HH

163

162-LI162-LI-31682-HH 31682-HH

2

162-LI-31722-HH

162-LI162-LI-31722-HH 31722-HH

Sensor to be provided certified suitable to SIL 2 application (HFT=0), otherwise a redundancy (i.e. voting 1oo2 or 2oo3) shall be applied Currently under BPCS. It shall be moved to SIS

162-XV-31690

164

Proposed Recommendation

Valve and its components (e.g. solenoid, actuator, body, et other applicable) to be provided with minimum reliability data as per Table 11 and certified suitable to SIL 2 application (HFT=0), otherwise a redundancy (i.e. voting 1oo2) shall be applied Sensor to be provided certified suitable to SIL 2 application (HFT=0), otherwise a redundancy (i.e. voting 1oo2 or 2oo3) shall be applied Currently under BPCS. It shall be moved to SIS

2 162-XV-31722

Valve and its components (e.g. solenoid, actuator, body, et other applicable) to be provided with minimum reliability data as per Table 11 and certified suitable to SIL 2 application (HFT=0), otherwise a redundancy (i.e. voting 1oo2) shall be applied

170

162-TI162-TI-31486-LL 31486-LL

162-TI-31486-LL

For sensor a redundancy (i.e. voting 1oo2 or 2oo3) shall be applied u nless on market transmitter certified for SIL 3 application is available

162-USVE-31845

For valves and its components (e.g. solenoid, actuator, body, et other applicable) a redundancy (i.e. voting 1oo2) shall be applied (ref. BP 30-80)

3

TEP-900-RPT-HS-BP4-0004

Page 41 of 43

© BP p.l.c.

BP Confidential

 

Tangguh Expansion Project – LNG FEED Preliminary SIL Verification Report

Appendix A SIL Verification Report_Att. 1.pdf  Report_Att.

Rev: A01

 

PFD Calculati Calculation on Sheet

TEP-900-RPT-HS-BP4-0004

Page 42 of 43

© BP p.l.c.

BP Confidential

 

Tangguh Expansion Project – LNG FEED Preliminary SIL Verification Report

Appendix B

SIL Verification Report_Att. 2.pdf  Report_Att.

Rev: A01

 

HFT Compliance Sheet

View more...

Comments

Copyright ©2017 KUPDF Inc.
SUPPORT KUPDF