INTRODUCTION TO HYDROCARBON EXPLOITATION Development Phase
Introduction to Hydrocarbon Exploitation Development Phase Well Heads
©2005 Abalt Solutions Limited. All rights reserved
Abalt
Solutions
Introduction
Drilling Engineering - Wellhea ds
All Surface equipment topping off the architecture of a well. It consists of Hangers, Christmas tree and all other hardware suspended with respect to safety and reliability of a well.
©2005 Abalt Solutions Limited. All rights reserved
Abalt
©abalt solutions limited - 2005
Solutions
September – October 2005
INTRODUCTION TO HYDROCARBON EXPLOITATION Development Phase
Drilling Eng inee ring - We llhead s
Introduction
©2005 Abalt Solutions Limited. All rights reserved
Abalt
Solutions
Drilling Engineering - Wellhea ds
Changes in Wellhead Changes in wellhead during a drilling operation are described based on the following Drilling 17 ½” Hole Casing 13 3/8” Drilling 12 ¼” Hole Casing 9 5/8” Drilling 8 ½” Hole Casing 7” Drilling 6” Hole Completions
©2005 Abalt Solutions Limited. All rights reserved
Abalt
©abalt solutions limited - 2005
Solutions
September – October 2005
INTRODUCTION TO HYDROCARBON EXPLOITATION Development Phase
Drilling Eng inee ring - We llhead s
Drilling 17 ½” Hole The initial architecture of well consists of bell nipple or conductor. Only if there is shallow gas-Diverter is used Surface casing is run in and cemented right to the surface. Wait on Cement and then mount the Casinghead housing. Diverter – Its an annular type BOP . – Working pressure is low – Functions to divert any blow out to a flare. ©2005 Abalt Solutions Limited. All rights reserved
Abalt
Solutions
Drilling 17 ½” Hole
Drilling Engineering - Wellhea ds
Casing Head Housing – First Component screwed, welded or forged to surface casing. – In the event casing string gets stuck on the way down, connection can be made only after pipe is cut off and welded. – Bore in upper part of housing can be cylindrical or tapered to support casing hangers and seals for next casing string. – The surface casing and housing support all the casings and BOPs anticipated.
©2005 Abalt Solutions Limited. All rights reserved
Abalt
©abalt solutions limited - 2005
Solutions
September – October 2005
INTRODUCTION TO HYDROCARBON EXPLOITATION Development Phase
Drilling 17 ½” Hole
Drilling Eng inee ring - We llhead s
Assembling BOP – The Wellhead is complete for this drilling phase with mud cross and Operator’s recommended BOP. – Wear bushing locked with locking flange and radial threaded rods inside casing head housing to protect bore from erosion. ©2005 Abalt Solutions Limited. All rights reserved
Abalt
Solutions
Drilling 17 ½” Hole
Drilling Engineering - Wellhea ds
Pressure Tests – Wellhead must be pressure tested Whenever anything is assembled Whenever anything is dismantled Periodically according to Operator All valves and pair of pipe rams are tested by pumping into annulus via kill line
– Tested using Tester cup – Tool screwed on to end of DP and to 10 to 30m into casing. – All valves and pipe rams are tested
Tester plug – Plug with O rings are rested in casing head – Pipe rams, annular and accessories can be tested. ©2005 Abalt Solutions Limited. All rights reserved
Abalt
©abalt solutions limited - 2005
Solutions
September – October 2005
INTRODUCTION TO HYDROCARBON EXPLOITATION Development Phase
Drilling Eng inee ring - We llhead s
Drilling 12 ¼” Hole Drilling with 12 ¼” bit. 9 5/8” casing is run and then cemented up to desired height from shoe. Wear bushing is removed from casing-head housing. Casing tensioned and anchored placing weight of 9 5/8” on casing spider and disconnecting flanges between mud cross and CHH. Lift BOP Structure. Place Casing Hangers in between 9 5/8” casing and bore of the casing head housing.
©2005 Abalt Solutions Limited. All rights reserved
Abalt
Solutions
Drilling 12 ¼” Hole Casing Hangers
Drilling Engineering - Wellhea ds
– Devices to anchor and hang casing strings in the CHH. – Each has slips to hang the casing into tapered section of CHH. – Contains rubber ring sealing assembly. – Types Separate Packers and Hangers Hangers and incorporated packers Automatic hangers. ©2005 Abalt Solutions Limited. All rights reserved
Abalt
©abalt solutions limited - 2005
Solutions
September – October 2005
INTRODUCTION TO HYDROCARBON EXPLOITATION Development Phase
Drilling 12 ¼” Hole Casing Head Spools
Drilling Eng inee ring - We llhead s
– Also supports casing strings. – 2 Flanges of different sizes and working pressures Lower flange-same dimension and working pressure as casing-head housing. It has a cylindrical bore and seal system. Upper part-cylindrical or tapered to accommodate casing hangers of next string
©2005 Abalt Solutions Limited. All rights reserved
Abalt
Solutions
Drilling 8 ½” Hole
Drilling Engineering - Wellhea ds
Principle is same as preceding phase Casing string anchored after wear bushing has been removed. Casing cut-off according to the components that will be assembled on top of 7” string. Testing/Pack-off flange is connected
©2005 Abalt Solutions Limited. All rights reserved
Abalt
©abalt solutions limited - 2005
Solutions
September – October 2005
INTRODUCTION TO HYDROCARBON EXPLOITATION Development Phase
Drilling 8 ½” Hole Tubing Head Spools
– Identical to double flanged casing-head spools and suspend tubing.
Tubing Hangers
Drilling Eng inee ring - We llhead s
– Consist of threaded hanger with seal on tapered outside part which corresponds to tubing head. – Held by screws on upper flange of tubing head. – Length of tubing is screwed on to upper female part of hanger. – For dual completions, special tubing head must be used.
©2005 Abalt Solutions Limited. All rights reserved
Abalt
Solutions
Drilling Engineering - Wellhea ds
Drilling 8 ½” Hole
Dual tubing hanger connection
Well head for 6 ½” Drilling ©2005 Abalt Solutions Limited. All rights reserved
Abalt
©abalt solutions limited - 2005
Solutions
September – October 2005
INTRODUCTION TO HYDROCARBON EXPLOITATION Development Phase
Drilling Eng inee ring - We llhead s
Drilling 8 ½” Hole
Courtesy:ABB ©2005 Abalt Solutions Limited. All rights reserved
Abalt
Solutions
Drilling 6” Hole
Drilling Engineering - Wellhea ds
The 7”casing is run in hole and cemented at top of pay zone. Producing layer is drilled and completed by running 5” liner anchored in the 7” casing. Casing is perforated and production packer set. Tubing & hanger are run in. After BOPs are dismantled, an adapter flange fitting on the tubing head & supporting lower part of master valves completes wellhead. ©2005 Abalt Solutions Limited. All rights reserved
Abalt
©abalt solutions limited - 2005
Solutions
September – October 2005
INTRODUCTION TO HYDROCARBON EXPLOITATION Development Phase
Blowout Preventers
Drilling Eng inee ring - We llhead s
Pressure control devices that hold and maintain pressure during drilling operations. Designed to: – Seal off the well when formations are encountered that contain pressure>hydrostatic pressure of drilling mud. – Allow mud circulation & density adjustment according to formation fluids under pressure. Characterized by: – Make – Type – Nominal size – Working pressure ©2005 Abalt Solutions Limited. All rights reserved
Abalt
Solutions
Blowout Preventers Characteristics for each Preventer: – Maximum opening diameter allowing drilling bits to pass through. – Opening & closing ratios; ratio between pressure prevailing in well when the Preventer is closed or opened) and hydrostatic pressure required to close or open) the preventers.
Drilling Engineering - Wellhea ds
Working pressure
– 1000;2000;3000;5000;10,000;15,000 & 20,000
Nominal diameters
– 30”,29 ”,21 ¼”,20 ¾”,18 ¾”,16 ¾”,13
5/8 ”,11 ”
&7
1/6”
Make – – – –
Cameron Shaffer Hydril Vetco Gray
©2005 Abalt Solutions Limited. All rights reserved
Abalt
©abalt solutions limited - 2005
Solutions
September – October 2005
INTRODUCTION TO HYDROCARBON EXPLOITATION Development Phase
Types of BOPs Ram type preventers
Drilling Eng inee ring - We llhead s
– Pipe rams – Blind rams – Shear rams
Annular type preventers Rotating preventers Inside preventers
©2005 Abalt Solutions Limited. All rights reserved
Abalt
Solutions
Types of BOPs Ram preventers – Pipe Rams
Drilling Engineering - Wellhea ds
Semi circular openings which match diameter of pipe sizes for which designed. If more than one size of drill pipe is used, additional preventers must be used on stack.
– Blind rams Designed to close when no pipe is used. Will flatten drill pipe if inadvertently closed with drill string in hole, but will not stop flow from well.
– Shear rams Designed to shear drill string. Will cause drill string to drop in hole & stop flow from well. Used mainly when all pipe rams and annular preventers have failed.
Courtesy :Cameron
©2005 Abalt Solutions Limited. All rights reserved
Abalt
©abalt solutions limited - 2005
Solutions
September – October 2005
INTRODUCTION TO HYDROCARBON EXPLOITATION Development Phase
Types of BOPs
Drilling Eng inee ring - We llhead s
Pipe rams
Shear rams
Blind rams ©2005 Abalt Solutions Limited. All rights reserved
Abalt
Solutions
Types of BOPs
Drilling Engineering - Wellhea ds
Annular Preventer – Sometimes called bag-type Preventer – Stops flow from well using a ring of synthetic rubber that contracts in the fluid passage. – Rubber packing conforms to shape pf pipe – Working pressures: 2000 psi 5000 psi 10,000 psi
©2005 Abalt Solutions Limited. All rights reserved
Abalt
©abalt solutions limited - 2005
Solutions
September – October 2005
INTRODUCTION TO HYDROCARBON EXPLOITATION Development Phase
Types of BOPs
Drilling Eng inee ring - We llhead s
Rotating Preventer – This type of Preventer allows the drill string to be rotated & run in or out. – Placed above normal preventers and used for drilling under pressure when low density mud is required. – Used for drilling with air or gas as fluid
©2005 Abalt Solutions Limited. All rights reserved
Abalt
Solutions
Different BOP Stack combinations According to IADC:
Drilling Engineering - Wellhea ds
Duty
Working Pressure (psi)
Stack
Light
2000
2-Ram or 1 Bag type
Low Pressure
3000
2-Ram and 1 Bag type
Medium Pressure
5000
2-Ram and 1 Bag type
High Pressure
10,000
3-Ram and 1 Bag type-5000 psi
Very High Pressure
15,000
3-Ram and 1 Bag type-10,000 psi
©2005 Abalt Solutions Limited. All rights reserved
Abalt
©abalt solutions limited - 2005
Solutions
September – October 2005
INTRODUCTION TO HYDROCARBON EXPLOITATION Development Phase Different BOP Stack combinations
Drilling Eng inee ring - We llhead s
??????
??????
??????
©2005 Abalt Solutions Limited. All rights reserved
Abalt
Solutions
BOP Hydraulic Control Systems
Drilling Engineering - Wellhea ds
Principles – All Bops and wellhead valves are hydraulically actuated & operated. – There is always one line on opening side & one on closing side. – Volume of fluid required to carry out a given number of emergency open/close functions should be specified by operator. – Pressure must be exerted to get a good seal. – Time required to close all BOPs must be calculated.
©2005 Abalt Solutions Limited. All rights reserved
Abalt
©abalt solutions limited - 2005
Solutions
September – October 2005
INTRODUCTION TO HYDROCARBON EXPLOITATION Development Phase
BOP Hydraulic Control Systems Several Air/Oil accumulators Set of hydraulic pumps Direct control manifold Remote controlled manifold
Drilling Eng inee ring - We llhead s
©2005 Abalt Solutions Limited. All rights reserved
Abalt
Solutions
BOP Hydraulic Control Systems
Drilling Engineering - Wellhea ds
Operation – Hydraulic fluid discharged by pumps to accumulators compress a bladder filled with Nitrogen. – Pressure equilibrium between gas & fluid in accumulator. – Gas acts as a spring that expels the oil when circuit is opened by means of one of four way valves that selects the functions. – Hydraulic pumps start & stop automatically and main circuit is regulated at 1500 psi.
©2005 Abalt Solutions Limited. All rights reserved
Abalt
©abalt solutions limited - 2005
Solutions
September – October 2005
View more...
Comments