Solid Waste Management of Iligan City - STATUS REPORT of the Central Material Recovery and Composting Facility (CMRCF) - as of December 2012
Short Description
The Central Material Recovery and Composting Facility (CMRCF) is located at Sitio Bangko in Barangay Bonbonon, Iligan Ci...
Description
Republic of the Philippines City of Iligan Office of the City Mayor Iligan City Solid Waste Management Office
STATUS REPORT
Prepared by: ENGR. BENJAMIN W. QUITOS JR. Project Manager-PMU
As of December 2012
1
TABLE OF CONTENTS
TITLE
PAGE
Title Page
1
I. Project Brief/ Description …………………………………….……………………………..
3
II By Project Components ……………………………..………………………….……………
5
1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11.
Site Development Access Road Development Building and Other Infrastructure Agri.-Demo MRF & Composting Facility (Goods , Bins & Remaining Works) Garbage Collection And Fencing of PSD Special & Hazardous Waste Facility Dumpsite Closure & Rehabilitation Installation of Transformer & Accessories Iligan City Solid Waste Mgt. System (IEC &LDM) Iligan Solid Waste Mgt. Code/Ordinance
III. Summary of Accomplishment…………………………………………..…………..…
9
IV. Photos………………………………………………………………………………….
10
1. 2. 3. 4. 5. 6.
InfrastructureDevelopment MRF Eqipments Information Education Campaign Livelihood Closure and Rehabilitation of Brgy. Santiago Dumpsite Agri-Demo
2
Project Brief I. PROJECT
Iligan City Solid Waste Management System
II. PROJECT SITE / LOCATION
The Central Material Recovery and Composting Facility (or CMRCF) is located at Sitio Bangko, Barangay Bonbonon, Iligan City with a land area of 12.27 hectares of which only five (5) hectares is used for the CMRCF will be operated by the City Government.
III. TIME FRAME/PROPONENT
Scheduled to be completed on or before December 2011
IV. PROJECT COMPONENTS
The solid waste management system is composed of two major components; the infrastructure development and the institutionalization program. The infrastructure development is composed of site development, access road development, and the construction of the following buildings; namely, materials recovery and composting facility, special waste and hazardous facility, administration building, warehouses, guardhouse, motor pool, and agri-demo farm. Closure and rehabilitation of the existing dumpsite. The institutionalization program aims to strengthen the Iligan City Solid Waste Management Board, ICSWM-Project Management Office and the Barangay Solid Waste Management Committees. The barangays covered in this program are the barangays along the coastal area and Brgy. Bonbonon as the host barangay of CMRCF. The program provides technical skills to BSWM committees through capability – building seminar workshop, trainers’ training in IEC, livelihood and enforcements, IEC policies and advocacies. It also includes provision of alternative livelihood to the affected families of Brgy. Santiago and Brgy. Bonbonon. Implementation of the project is city-wide and barangay-based activities. Further, the program also addresses the existing garbage collection system by rehabilitating the 7 units and the purchase of additional 6 brand new units. As part of the social responsibilities to the affected families of Barangay Santiago and Bonbonon, alternative livelihoods are provided to them. 3
V. FUNDING
The source of fund for the project is a loan from Development Bank of the Philippines amounting to P163,638.00 million and a city equity of P25 million. The loan is being funded by 90% KfW CLSWM (156.1 M) and 10% DBP fund (P7.538 M). Release of fund is by tranche; to wit: First: P62.440 KfW portion; P7.538 DBP portion, after Collateral Appraisal Unit (CAU) verification of equity infusion of not less that P10.03 M Second: P78.050M after CAU verification of prior release and equity infusion of not less than P15.548M Final: P15.610 M after CAU verification of prior releases and equity infusion of not less that P25 M.
VI. PROJECT PROPONENT Contact Persons:
City Government of Iligan Hon. Lawrence Ll. Cruz City Mayor Buhanginan Hills, Iligan City Hon. Chonilo O. Ruiz City Councilor Chairman, Committee on Environment Vice-Chairman, Iligan City Solid Waste Mgt. Board Engr. Benjamin W. Quitos, Jr. Project Manager ICSWM-Project Management Unit
VII. PURPOSE / OBJECTIVE
The purpose of the project is to establish a financially viable and environmentally sustainable solid waste management system for the benefit of the people of Iligan City, to be operated within the carrying capacity of the supporting ecosystem, and at the same time satisfy the requirements of intergenerational equity and social justice.
VIII. TARGET BENEFICIARIES
Present and future residents of Iligan City and neighboring areas. 4
By Project Components Project Description 1. Site Development-Sitio Bangko, Bry. Bonbonon a. CMRCF Drainage b. Roads, Retaining Wall & Riprapping for MRF c. Site Development(Earthwork) for CMRCF d. Electrical Installation of Perimeter lighting e. Water Supply for CMRCF f. Tress Buffer Zone (Tree Growing)
Status a. 100% b. 100% c. 100% d. 100% e. 100% f. 100%
2. Access Road Development- Sitio Bangko, Bry. Bonbonon a. *Improvement and widening of access road *Opening of Diversion Road
a.* 36% b.* 60%
b. Installation of lighting on access road and diversion road
a. 100%
3. Building and Other Infrastructure- Sitio Bangko, Bry. Bonbonon a. CMRCF Buildings b. Subsurface Soil Investigation c. Agri. Demo Nursery
a. 100% b. 100% c. 100%
4. Agri.-Demo- Sitio Bangko, Bry. Bonbonon a. Agri Crop Demonstration b. Nursery Propagation
a. Continuing b. Continuing
5. MRF & Composting Facility (Goods & Bins)- Sitio Bangko, Bry. Bonbonon a. Facility Equipment b. Composting Bins c. Completion of Remaining Works
6. Garbage Collection And Fencing of PSD a. Repair and Upgrade of Garbage Trucks b. Garbage Trucks (NEW) with Registration c. Construction and Fencing of PSD shed
a. 100% b. 100% c. 100%
a. 100% b. 100% c. 100%
5
7. Special & Hazardous Waste Facility- Sitio Bangko, Bry. Bonbonon a. SH Facility Equipment - Custom Built Transport Vehicle - Autoclave b. Waste Vaults
a. -For procurement -dob. 100% completed
8. Dumpsite Closure & Rehabilitation-Brgy. Santiago a. Phase I b. Phase II
a. 100% b. 71.26% completed
9. Installation of Transformer & Accessories- Sitio Bangko, Bry. Bonbonon 10. Iligan City Solid Waste Mgt. System – Prjt. Mgt. Staff: a. Information Education Communcation Campaign
I.
100%
Evacuation Centers – S WM Orientation 1. Sta. Felomina
-
Jan. 26, 2012
2. San Roque
-
Jan. 26, 2012
3. IBJT Tambo
-
Jan. 27, 2012
4. Upper Hinaplanon Elem. School
-
Jan. 27, 2012
5. Luinab Elem. School
-
Jan. 30, 2012
6. Ubaldo Elem. School
-
Jan. 31, 2012
7. VillaVerde Gym
-
Jan. 31, 2012
8. Tubod, Laville Gym
-
Feb. 1, 2012
9. Tambacan Elem. School
-
Feb. 1, 2012
10. Pala-o Elem. S:chool
-
Feb.3, 2012
11. Santiago Gym
-
Feb.3, 2012
12. Upper Hinaplanon Gym
-
March 1, 2012
13. Ubaldo Gym
-
March 7, 2012
6
14. Del Carmen, Bunkhouse
-
July 30, 2012
Sta. Felomina Cluster 16. Luinab, Siao Shelter Box
-
Aug. 30, 2012
VillaVerde Cluster 17. All Camp Manager
-
Sept. 3, 2012 Sept. 12, 2012
(Evacuation centers) 18. Sta. Elena, Tambacan Cluster
-
Sept. 26, 2012
-
Nov. 12, 2012
1. Buruun
-
July 25, 2012
2. Suarez
-
Aug. 9, 2012
3. Ubaldo
-
Aug. 15, 2012
4. Pugaan
-
Aug. 16 – 17, 2012
5. Mandulog
-
Aug. 23, 2012
6. Upper Hinaplanon
-
Aug. 24, 2012
7. Kiwalan
-
Aug. 28, 2012
8. Mahayahay
-
Sept. 4, 2012
9. Tomas Cabili
-
Sept. 5, 2012
10. Del Carmen
-
Sept. 6, 2012
11. Hinaplanon
-
Sept. 7, 2012
12. Santiago
-
Sept. 12, 2012
15. Luinab, Siao Shelter Box
19. Amakan evacuation center , near ICSWMBO II.
III.
4 P’s - SWM Orientation
ACF / Cash for Work - SWM Orientation
7
IV.
V.
1. Santiago , Brgy Gym
-
Aug. 24, 2012
2. Hinaplanon, Brgy Hall
-
Aug. 24, 2012
3. San Roque, Rosal
-
Sept. 24, 2012
4. San Roque, Fire Tree
-
Sept. 26, 2012
5. Sta. Felomina, Riverside
-
Oct. 1, 2012
6. Sta. Felomina, Mauswagon A
-
Oct. 2, 2012
7. Sta, Felomina, Mauswagon B
-
Oct. 3, 2012
8. Upper Hinaplanon, Prk. Linanggongan -
Oct. 8, 2012
9. Upper Hinaplanon, Prk Cabaro
-
Oct. 9, 2012
10. Upper Hinaplanon, Prk. Wago
-
Oct. 10, 2012
11. Sta. Elena, Cluster 1 evacuation center -
Oct. 15, 2012
12. Sta. Elena, Cluster 2 evacuation center -
Oct. 16, 2012
13. Sta. Elena Cluster 3 evacuation center
-
Oct. 17, 2012
14. BOnbonon, Purok 1
-
Oct. 22, 2012
15. Bonbonon, Purok 2
-
Oct. 23, 2012
16. Bonbonon, Purok 3 & 13
-
Oct. 24, 2012
Other Organization - SWM Orientation 1. CSWD PES Orientation, Brgy. Tomas Cabili
-
July 23, 2012
2. Day Care Center, Brgy. Mahayahay
-
Sept. 21, 2012
-
April 10, 2012 June 14, 2012
School Orientation 1. Tubaran National High School Mandulog, Iligan City 2. Pugaan High School
8
(Room to Room) 3. Sgt. Miguel Canoy Central School
-
Oct. 23, 2012
(Jamboree – GSP) VI.
VII.
Purok to Purok Orientation 1. Purok 1, Brgy. Tipanoy
-
May 5, 2012
2. Purok 5, Brgy. Hinaplanon
-
June 23, 2012
3. Purok Anthurium , Brgy. San Roque-
June 14, 2012
4. Purok Sampaguita, Brgy. San Roque-
June 14, 2012
5. Purok 1, Brgy. Abuno
-
July 27, 2012
6. Purok 2, Brgy. Abuno
-
July 27, 2012
7. Purok 1 C, Brgy. Pugaan
-
Aug. 11,2012
8. Purok 1, Brgy. Tambacan
-
Aug. 4, 2012
9. Purok Sampaguita, Brgy. VillaVerde-
Sept. 21, 2012
10. Purok 15, Pala-o
Sept. 27, 2012
Review / Evaluation of BSWPM Plan 1. Suarez
VIII.
IX.
-
-
Feb. 24, 2012
TWG / Technical Working Group Seminar 1. Suarez
-
June 1, 2012
2. Saray
-
July 16, 2012
3. Poblacion
-
Aug. 31, 2012
IEC – BSWM Trainor’sTraining
9
1. Upper Tominobo
-
March 22, 2012
2. Tipanoy
-
May 12, 2012
3. Suarez
-
July 27, 2012
b. Livelihood and Marketing The livelihood team are still extending their trainings to the interested barangays and to the evacuation centers. The barangays that has evacuation centers are; Brgy. Santiago, Brgy. Palao, Brgy. Ubaldo, Brgy. San Roque & Brgy.Upper Hinaplanon. c. Other activities conducteds: c.1 Recycling c.2 Tree Growing c.3 Organic fertilizer processing and vermin composting c.3 Nursery propagation c.4 Barangay Assistance and monitoring thru attendance to their council meetings c.5 Assists walk in clients c.6 Conduct regular meetings with the ICSWM Board c.7 Coordination with DENR/ DILG c.8 Attendance to seminars related to Solid Waste Management
11. Iligan Solid Waste Mgt. Code/Ordinance The garbage fee collections will start on January 2013.The barangays are oblige to have a tax mapping to their respective area for the said collections.
10
Summary of Accomplishment a. Building and Other Infrastructure By Brima b. Package A-undertaken by DACODECO
Status 100%
98.9583%
Date Started: May 10,2010 1. MRF Composting Bins and other facilities 2. Completion of Remaining Work (Concreting of Roads, Riprap Works) to include Wash Rack 3. Improvement & Widening of Access Road 4. Installation of Street Lighting along Access Road 5. Special/Hazardous Waste Vaults 6. Supply and Installation of 3units -167 KVA Transformer Date Started: May 10,2010 c. Package B-undertaken by LACTO ASIA (CMRCF Equipments)
d. Information Education i. ii. iii. iv.
Communication Campaign
Review/ Evaluation of Barangays Solid Waste Mgt. Plan Submitted Barangays Solid Waste Mgt. Plan Conducted TWG Planning Workshop Conducted Trainor’s Training
100 %
On-going 30 Brgys. 31 Brgys. 26 Brgys. 15 Brgys.
e. Closure and Rehabilitation of Brgy. Santiago Dumpsite
71.2% Rehab.
f. Site Development
100%
11
Photos
1. InfrastructureDevelopment Brgy. Bonbonon, Sitio Bangko
7 4
6
3
2
1 5
1
2
Admin Bldg.
Warehouse Bldg.
as of 2012
3
MRF Buildings
4
Motor Pool Bldg.
12
7
6
Waste Vaults
Composting Bins
Transformer Pedestal
2
Warehouse Bldg.
5
Guard House
Opening-Access Road
13
2. MRF Equipments
14
3. Information Education Campaign
TWG-Bagong Silang, April 13, 2011
Evaluation of BSWMP - Tibanga, April 14, 2011
TWG-Tibanga, May 5, 2011
Evaluation of BSWMP -Mahayahay, April 15, 2011
TWG-Dalipuga, April 12, 2011
TWG-San Miguel, May 4, 2011
15
TWG - Sto. Rosario, May 10, 2011
TWG – Tomas Cabili, May 6, 2011
TWG – Hinaplanon, May 20, 2011
TWG - Luinab, May 9, 2011
TWG – Mahayahay, June 8, 2011
TWG – Acmac, May 18, 2011
16
TWG – Sta. Filomena, May 13, 2011
TWG – Villaverde, May 12, 2011
TWG – Upper Hinaplanon, May 30, 2011
TWG – Ubaldo Laya, May 25, 2011
Trainers Training – Ubaldo Laya, Nov 18, 2011
IEC – Urban Poor- Nov 30, 2011
17
3. Livelihood-Recycling Class
18
19
20
5. Closure and Rehabilitation of Brgy. Santiago Dumpsite
Phase 1
Phase 2
21
6. Agri-Demo
Virmi
Gumbo
Anthurium
Ilang-Ilang
Bitter Gourd
Angels Trumpet
22
View more...
Comments