INDUSTRIAL TRAINING AT
TENAGA NASIONAL BERHAD(DISTRIBUTION) PONTIAN JALAN PARIT MESJID, 82000 PONTIAN, JOHOR
18/4/2016 – 10/6/2016 BY: IZZAT IZZUDDIN BIN BADLEE SHAH 2014477676 DIPLOMA IN ELECTRICAL ENGINEERING (POWER)
TNB BACKGROUND
TNB is a public listed company with responsibilities: • To generate , transmit , distribute and sell energy to customer throughout Peninsular Malaysia • To plan , install , operate and maintain electricity installation for the generation , transmission and distribution of electricity TNB's core activities are: • Generation • Transmission • Distribution of electricity
VISION
To be among the leading corporation in energy and related businesses globally
MISION We are committed to excellence in our products and services
ORGANIZATION CHART ASSISITANCE ENGINEER NUR ANISAH HIGHEST TECHNICIAN KANG DENG SOON
FOREMAN SUBSTATION SUFUAN DAUD TECHNICIAN MOHD RAZALI MUSE MOHAMAD SALEH IDRIS SUBSTATION TEAM
FOREMAN CABLE NOR HAIZAN IDRIS
ASSISTANT TECHNICIAN ZUL EFFANDY HASHIM
TEST TECHNICIAN SHAHRIN A. RAZAK
TECHNICIAN SAVR MUHAMMAD FAHMI
JOINTER HT 1
SUPERVISOR SAVR V.R. BALAKRISHNAN
JOINTER HT 2
TEAM SAVR1
TEST
SUPERVISOR SAVR2 MOHD FARID TEAM SAVR 2
SUPERVISOR MAINTENANCE TECHNICIAN STREET LIGHTING HANAFI KEMIN WAN MOHD HAFIZI MUHAMMAD NAIM TEAM STREET LIGHTING MAINTENANCE TEAM
SUPERVISOR PPB MUHAMMAD SHAFIQ NOR MAALIF MOHD FAREEZ MUDA TEAM A TEAM B TEAM C TEAM D
DEPARTMENT • During
INDUSTRIAL TRAINING, I have learnt and with 6 department.
• Fault
Finder
• Substation • SAVR • Street
lighting
• Cable • Meter
& Service
FAULT FINDER CENTRE(PPB) CUSTOMER COMPLAINT
WALK IN
CALLED TNB PONTIAN
TECHNICIAN PBB
STANDBY TEAM
COMPLETE WORK
CALLED 15454
MOBILE FIELD FORCE AUTOMATION (MFFA)
EQUIPMENTS
NEUTRAL LINK FUSE (HRC , NH , BARREL)
CUT-OUT BASE LV TRACER
INTERNAL FAULT FAULT TYPE: •
SERVICE WIRE 1X16+25MM² AT NEUTRAL LINK LOOSE CONTACT CAUSED BY OXIDATION .
LOCATION: •
N0 4611 , KAMPUNG AIR PUTEH , KAMPUNG SAWAH , PEKAN NENAS , JOHOR.
SUBSTATION •A
set of equipment reducing the high voltage of electrical power transmission to that suitable for supply to consumers.
EQUIPMENTS IN SUBSTATION
TRANSFORMER (TX)
SWITCHGEAR
FEEDER PILLAR
SUBSTATIONS
INDOOR
H-POLE
OUTDOOR
COMPACT
SAVR is a state of work being conducted on low voltage with procedures , safety measures and the type of tools which is allowed by TNB's system . It provides voltage to users through overhead method and underground cable .
SAVR
EQUIPMENTS
DEAD END CLAMP
SUSPENSION CLAMP
J-HOOK
INSULATED PIERCING CONNECTER (IPC
STREET LIGHTING
EQUIPMENTS
PHOTOCELL & IGNITOR CHOKE
LATERN
CABLE • Carying
high voltage (11KV)
Have 2 type of cable: • XLPE • PILC
(new)
(old)
Equipment to find cable underground named Tracer • Transimited • Recieved
METER AND SERVICE • Make
installation of service cable and also install meter
• Connect
service cable from electric pole then pull to the house to get supply and also install meter to the house.
• Meter
have 2 types:
1)Single
phase meter 230V
2)Three
phase meter 415V
CONCLUSION •It
is beneficial practical session for the students •give a chance for students to adapt on working environment •learn how to communicate with working people
Thank you for interesting in our services. We are a non-profit group that run this website to share documents. We need your help to maintenance this website.