Short Circuit Calculation Report

November 23, 2018 | Author: jigyesh | Category: Transmission Line, Electrical Impedance, Transformer, Electronic Engineering, Electricity
Share Embed Donate


Short Description

SCR...

Description

The content of this document remains the full property of Larsen & T oubro. The document may neither be reproduced nor co mmunicated to third party in any form, nor used for own purpose, particularly for the execution of what is herein represented, without the written authorisation of Larsen & Toubro.

DRAWING ISSUED FOR  APPROVAL REFERENCE/INFORMATION CONSTRUCTION DISTRIBUTION

0

04.04.2016

Rev.

Date

First Submission. JS Prepared

PCP Checked

Remarks/Reasons for Revision

CLIENT :

HINDUSTAN ZINC LIMITED

CONSULTANT :

DEVELOPMENT DEVELOPMENT CONSULTANTS CONSULTANTS PVT. LTD.

TITLE :

SHORT CIRCUIT CALCULATION

PLANT : 1.5 MTPA LEAD-ZINC BENEFICIATION PLANT AT S.K.MINES, RAJASTHAN L&T DOC. No.

PCP Approved

Larsen & Toubro Limited

PROJECT: S.K.Mines(Mill) Dariba CUSTOMER: : HINDUSTAN ZINC LIMITED

Short Circuit Calculation Report The short circuit calculation report is generated with ETAP 11.1.1 version. Short circuit calculation is worked out considering the following conditions: 1. We have considered 1000MVA as source fault level of grid as IS 2026-I,1977 2. Cables are not considered, however this will reduce further SC level. 3. Lumped load at 0.415kV bus is derived from Latest load list. 4. SC calculations are done in accordance with IEC 60909 Detailed short circuit calculation result for each bus is indicated as below:

Sr. No.

1 2

Bus levels

6.6kV, {with 33 kV I/C-2 open &6.6kV us coupler closed} 6.6kv {with 33kV I/C -2 Closed & 6.6kV us coupler open}

Rated Fault level (RMS)

40 40

L&T Document No.:

Rev. No. 0

PREPARED BY

REVIEWED BY

Type of Fault

Symmetrical 3 phase Symmetrical 3 phase

Attained Fault Level as per calculation 23.16 KA

20.9 KA

One-Line Diagram - OLV1 (Short-Circuit Analysis) U4 1000 MVAsc

U3 1000 MVAsc

Case-2 33kV I/ C-2closed

 2  0.  V  3  8 k  9  26.

333.19 kV

, wit h 6.6kV bus coupler open

Open

33 kV

3.19

 T10 20 MVA

 T14 20 MVA

Open 6.6 kV 0.512 0. 512

 V  0  0 k

15.96 0.512 0. 512

0.512 0. 512

0.327 0. 327

0.601 0. 601

fl oat air blower -1

750 kW

2.25 2. 25

ball

0.303 0. 303

6.6 kV

2  0  .9  k   A -  84   .7 

mil l

regrind mil l 2850 kW 375 kW

Seconda Secondar ryy ccone one crusher cr usher

200 kW  TR#4 2 MVA  TR#1

 TR#7 2 MVA MVA

 TR#2 2 MVA  TR#3

2 MVA

 TR# TR#8 2 MVA

 TR#6 2 MVA

 TR#5 2 MVA

BusDuct15 BusDuct15

2 MVA

BusDuct12

BusDuct11

BusDuct14

BusDuct10 BusDuct7

BusDuct8

BusDuct9

0.433 kV 0.433 kV 7.8

0.433 kV Open

7.8

 2  1.  V 4  7  k  0 0.

0.433 kV

0.433 kV

Open

7.8 7.8

 2  1.  V 4  7 k  0  0.

PMCC- 1 MAIN PROCESS-EPR

0.433 kV 0.433 kV Open Open

7.8

Lump2 0. 5 MVA

Lump3 0. 5 MVA

PMCC- 2

Lump4 1. 5 MVA

0.433 kV

0.433 kV 4.99 4.99

0.433 kV Open

7.8 Lump1 1. 5 MVA

Float air blower-2 Float 750 kW

 2  1.  V 4  7  k  0  0.

 2  V 4  k  040.433  0.

kV

0.433 kV

MAIN PROCESS -ECR PMCC-3 SER/TER HOUSE

Lump5 1. 5 MVA

Lump6 0. 5 MVA

Lump7 0. 5 MV MVA A

Lump8 Lump8 1. 5 MVA

Lump9 900 kVA

Lump10 900 kVA

One-Line Diagram - OLV1 (Short-Circuit Analysis) U4 1000 MVAsc

U3 1000 MVAsc

Case-2 33kV I/ C-2closed

 2  0.  V  3  8 k  9  26.

333.19 kV

, wit h 6.6kV bus coupler open

Open

33 kV

3.19

 T10 20 MVA

 T14 20 MVA

Open 6.6 kV 0.512 0. 512

 V  0  0 k

15.96 0.512 0. 512

0.512 0. 512

0.327 0. 327

0.601 0. 601

fl oat air blower -1

750 kW

2.25 2. 25

ball

0.303 0. 303

6.6 kV

2  0  .9  k   A -  84   .7 

mil l

regrind mil l 2850 kW 375 kW

Seconda Secondar ryy ccone one crusher cr usher

200 kW  TR#4 2 MVA  TR#1

 TR#7 2 MVA MVA

 TR#2 2 MVA  TR#3

2 MVA

 TR# TR#8 2 MVA

 TR#6 2 MVA

 TR#5 2 MVA

Float air blower-2 Float 750 kW

BusDuct15 BusDuct15

2 MVA

BusDuct12

BusDuct11

BusDuct14

BusDuct10 BusDuct7

BusDuct8

BusDuct9

0.433 kV 0.433 kV 7.8

0.433 kV Open

7.8

0.433 kV

 2  1.  V 4  7  k  0 0.

0.433 kV

Open

7.8 7.8

 2  1.  V 4  7 k  0  0.

PMCC- 1 MAIN PROCESS-EPR

0.433 kV 0.433 kV Open Open

7.8

Lump1 1. 5 MVA

Lump2 0. 5 MVA

Lump3 0. 5 MVA

PMCC- 2

Lump4 1. 5 MVA

0.433 kV 4.99 4.99

0.433 kV Open

7.8 0.433 kV

 2  1.  V 4  7  k  0  0.

 2  V 4  k  040.433  0.

kV

0.433 kV

MAIN PROCESS -ECR PMCC-3 SER/TER HOUSE

Lump5 1. 5 MVA

page 1

11:40:44

Apr 05, 2016

Project: Location:

Lump6 0. 5 MVA

Lump7 0. 5 MV MVA A

Lump8 Lump8 1. 5 MVA

Lump9 900 kVA

Lump10 900 kVA

Project File: SK Mines HZL

SC calculation SK Mines

ETAP 11.1.1C

Contract: Engineer:

Jigyesh Sharma

Filename:

SK Mines HZL

Study Case:  CASE-1

Electrical Transient Analyzer Program

Short-Circuit Analysis

IEC 60909 Standard 3-Phase, LG, LL, & LLG Fault Currents

Page:

1

Date:

04-05-2016

SN:

LARTOUMUM

Revision:

Base

Config.:

 Normal

Project: Location:

ETAP

SC calculation

11.1.1C

SK Mines

Contract: Engineer:

Jigyesh Sharma

Filename:

SK Mines HZL

Study Case:  CASE-1

Page:

1

Date:

04-05-2016

SN:

LARTOUMUM

Revision:

Base

Config.:

 Normal

Electrical Transient Analyzer Program

Short-Circuit Analysis

IEC 60909 Standard 3-Phase, LG, LL, & LLG Fault Currents

 Number of Buses:

 Number of Branches:

 Number of Machines:

Swing

V-Control

Load

Total

 2

 0

 15

 17

XFMR2

XFMR3

Reactor 

Line/Cable

Impedance

Tie PD

Total

 10

 0

 0

 0

 0

 5

15

Synchronous Generator 

Power  Grid

Synchronous Motor

Induction Machines

Lumped Load

Total

 0

 2

0

 5

 10

 17

System Frequency:

50.00 Hz

Unit System:

English

Project Filename:

SK Mines HZL

Output Filename:

C:\ETAP 1111\SK Mines HZL\Untitled.SI2

Project: Location:

ETAP

SC calculation

11.1.1C

SK Mines

Contract: Engineer:

Jigyesh Sharma

Filename:

SK Mines HZL

Study Case:  CASE-1

Adjustments Apply

Individual

Adjustments

/Global

Transformer Impedance:

Yes

Individual

Reactor Impedance:

Yes

Individual

Overload Heater Resistance:

 No

Transmission Line Length:

 No

Cable Length:

 No

Tolerance

Percent

Apply

Individual

Adjustments

/Global

Transmission Line Resistance:

Yes

Global

 20

Cable Resistance:

Yes

Global

 20

Temperature Correction

Degree C

Page:

2

Date:

04-05-2016

SN:

LARTOUMUM

Revision:

Base

Config.:

 Normal

Project: Location:

ETAP

SC calculation

11.1.1C

SK Mines

Contract: Engineer:

Jigyesh Sharma

Filename:

SK Mines HZL

Study Case:  CASE-1

Bus Input Data

Bus ID

Type

Bus20

SWNG

Bus22

Load

Bus24

SWNG

Bus25

Initial Voltage  Nom. kV

Base kV

Sub-sys

 %Mag.

Ang.

33.000

 33.000

1

100.00

0.00

6.600

 6.600

1

100.00

-30.00

33.000

 33.000

2

100.00

0.00

Load

6.600

 6.600

1

100.00

-30.00

Bus26

Load

0.433

 0.433

1

100.00

0.00

Bus27

Load

0.433

 0.433

1

100.00

0.00

Bus28

Load

0.433

 0.433

1

100.00

0.00

Bus29

Load

0.433

 0.433

1

100.00

0.00

Bus30

Load

0.433

 0.433

1

100.00

0.00

Bus31

Load

0.433

 0.433

1

100.00

0.00

Bus32

Load

0.433

 0.433

1

100.00

0.00

Bus33

Load

0.433

 0.433

1

100.00

0.00

Bus34

Load

0.433

 0.433

1

100.00

0.00

Bus35

Load

0.433

 0.433

1

100.00

0.00

Bus36

Load

0.433

 0.433

1

100.00

0.00

Bus37

Load

0.433

 0.433

1

100.00

0.00

T14~

Load

6.600

 6.600

0

100.00

0.00

17 Buses Total All voltages reported by ETAP are in % of bus Nominal kV. Base kV values of buses are calculated and used internally by ETAP.

Page:

3

Date:

04-05-2016

SN:

LARTOUMUM

Revision:

Base

Config.:

 Normal

Project:

ETAP

SC calculation

Location:

11.1.1C

SK Mines

Contract: Engineer:

Jigyesh Sharma

Filename:

SK Mines HZL

Study Case:  CASE-1

Page:

4

Date:

04-05-2016

SN:

LARTOUMUM

Revision:

Base

Config.:

 Normal

 2-Winding Transformer Input Data

Transformer ID T10

Rating MVA

Prim. kV

Sec. kV

Z Variation %Z

X/R

% Tap Setting

+ 5%

- 5%

% Tol.

Prim.

Sec.

Adjusted

Phase Shift

%Z

Type

Angle

20.000

33.000

6.600

10.00

20.00

0

0

0

0

0

10.0000

Dyn

30.000

TR#1

2.000

6.600

0.433

6.25

6.00

0

0

0

0

0

6.2500

Dyn

-30.000

TR#2

2.000

6.600

0.433

6.25

6.00

0

0

0

0

0

6.2500

Dyn

-30.000

TR#3

2.000

6.600

0.433

6.25

6.00

0

0

0

0

0

6.2500

Dyn

-30.000

TR#4

2.000

6.600

0.433

6.25

6.00

0

0

0

0

0

6.2500

Dyn

-30.000

TR#5

2.000

6.600

0.433

6.25

6.00

0

0

0

0

0

6.2500

Dyn

-30.000

TR#6

2.000

6.600

0.433

6.25

6.00

0

0

0

0

0

6.2500

Dyn

-30.000

TR#7

2.000

6.600

0.433

6.25

6.00

0

0

0

0

0

6.2500

Dyn

-30.000

TR#8

2.000

6.600

0.433

6.25

6.00

0

0

0

0

0

6.2500

Dyn

-30.000

20.000

33.000

6.600

10.00

20.00

0

0

0

0

0

10.0000

Dyn

-30.000

T14

2-Winding Transformer Grounding Input Data Grounding Transformer ID T10

Rating MVA

Prim. kV

Conn. Sec. kV

Type

Primary Type

kV

Secondary Amp

Ohm

Type

kV

Amp

Ohm

20.000

33.000

6.600

D/Y

Solid

TR#1

2.000

6.600

0.433

D/Y

Resistor 

3.3

75.00000

TR#2

2.000

6.600

0.433

D/Y

Resistor 

3.3

75.00000

TR#3

2.000

6.600

0.433

D/Y

Resistor 

3.3

75.00000

TR#4

2.000

6.600

0.433

D/Y

Resistor 

TR#5

2.000

6.600

0.433

D/Y

Resistor 

TR#6

2.000

6.600

0.433

D/Y

Resistor 

75.00000

TR#7

2.000

6.600

0.433

D/Y

Resistor 

75.00000

TR#8

2.000

6.600

0.433

D/Y

Resistor 

20.000

33.000

6.600

D/Y

Solid

T14

75.00000 3.3

3.3

75.00000

75.00000

Project:

ETAP

SC calculation

Location:

11.1.1C

SK Mines

Contract: Engineer:

Jigyesh Sharma

Filename:

SK Mines HZL

Study Case:  CASE-1

Page:

5

Date:

04-05-2016

SN:

LARTOUMUM

Revision:

Base

Config.:

 Normal

Branch Connections

CKT/Branch ID

Connected Bus ID Type

From Bus

% Impedance, Pos. Seq., 100 MVAb To Bus

R

X

Z

T10

2W XFMR 

Bus20

Bus22

2.46

49.23

49.30

TR#1

2W XFMR 

Bus22

Bus26

49.42

296.51

300.60

TR#2

2W XFMR 

Bus25

Bus30

49.42

296.51

300.60

TR#3

2W XFMR 

Bus22

Bus28

49.42

296.51

300.60

TR#4

2W XFMR 

Bus22

Bus31

49.42

296.51

300.60

TR#5

2W XFMR 

Bus25

Bus32

49.42

296.51

300.60

TR#6

2W XFMR 

Bus25

Bus34

49.42

296.51

300.60

TR#7

2W XFMR 

Bus22

Bus36

49.42

296.51

300.60

TR#8

2W XFMR 

Bus25

Bus37

49.42

296.51

300.60

T14

2W XFMR 

T14~

Bus25

61.54

1230.86

1232.40

CB66

Tie Breakr 

Bus30

Bus27

CB69

Tie Breakr 

Bus30

Bus29

CB71

Tie Breakr 

Bus32

Bus33

CB73

Tie Breakr 

Bus32

Bus35

CB82

Tie Breakr 

Bus22

Bus25

 Y

Project: Location:

ETAP

SC calculation

11.1.1C

SK Mines

Contract: Engineer:

Jigyesh Sharma

Filename:

SK Mines HZL

Study Case:  CASE-1

Page:

6

Date:

04-05-2016

SN:

LARTOUMUM

Revision:

Base

Config.:

 Normal

Power Grid Input Data

Power Grid

Connected Bus

ID

ID

% Impedance 100 MVA Base

Rating MVASC

kV



X"

Grounding R/X"

Type

U3

Bus20

1000.000

33.000

0.71247

9.97459

 0.07

Wye - Solid

U4

Bus24

1000.000

33.000

0.71247

9.97459

 0.07

Wye - Solid

Total Connected Power Grids ( = 2 ): 2000.000 MVA

Project:

ETAP

SC calculation

Location:

11.1.1C

SK Mines

Contract: Engineer:

Jigyesh Sharma

Filename:

SK Mines HZL

Study Case:  CASE-1

Page:

7

Date:

04-05-2016

SN:

LARTOUMUM

Revision:

Base

Config.:

 Normal

Induction Machine Input Data

Induction Machine ID

Connected Bus Type

Qty

Rating

ID

HP/kW

PosSeqImp (Mtr Base)

kVA

kV

Amp

PF

%R

% X"

R/X"

Grounding Conn.

Type

mFact. Amp

MW/PP

loat air blower -1

Motor

1

Bus22

750.00

867.66

6.600

 75.90

92.37

2.16

13.72

0.16

Wye

Open

0.38

all mill

Motor

1

Bus22

2850.00

3253.59

6.600

 284.61

92.92

1.49

13.81

0.11

Wye

Open

1.43

egrind mill

Motor

1

Bus22

375.00

436.83

6.600

 38.21

92.09

2.62

13.64

0.19

Wye

Open

0.19

Float air blower-2

Motor

1

Bus25

750.00

867.66

6.600

 75.90

92.37

2.16

13.72

0.16

Wye

Open

0.38

Secondary cone crusher

Motor

1

Bus25

200.00

234.44

6.600

 20.51

91.83

3.12

13.53

0.23

Wye

Open

0.10

Total Connected Induction Machines ( = 5 ): 5660.2 kVA

Lumped Load Input Data Motor Loads Lumped Load Lumped Load ID

% Impedance

Rating kVA

kV

% Load

Loading

Amp

% PF

MTR

STAT

kW

kvar  

Machine Base R

X"

Grounding

R/X"

Conn.

Type

 mFact. Amp

MW/PP

Lump1

1500.0

0.433

2000.06

85.00

70

30

892.50

553.12

6.46

15.37

0.42

Delta

0.89

Lump2

500.0

0.433

666.69

85.00

70

30

297.50

184.37

6.46

15.37

0.42

Delta

0.30

Lump3

500.0

0.433

666.69

85.00

70

30

297.50

184.37

6.46

15.37

0.42

Delta

0.30

Lump4

1500.0

0.433

2000.06

85.00

70

30

892.50

553.12

6.46

15.37

0.42

Delta

0.89

Lump5

1500.0

0.433

2000.06

85.00

70

30

892.50

553.12

6.46

15.37

0.42

Delta

0.89

Lump6

500.0

0.433

666.69

85.00

70

30

297.50

184.37

6.46

15.37

0.42

Delta

0.30

Lump7

500.0

0.433

666.69

85.00

70

30

297.50

184.37

6.46

15.37

0.42

Delta

0.30

Lump8

1500.0

0.433

2000.06

85.00

70

30

892.50

553.12

6.46

15.37

0.42

Delta

0.89

Lump9

900.0

0.433

1200.04

85.00

70

30

535.50

331.87

6.46

15.37

0.42

Delta

0.54

Lump10

900.0

0.433

1200.04

85.00

70

30

535.50

331.87

6.46

15.37

0.42

Delta

0.54

Total Connected Lumped Loads ( = 10 ): 9800.0 kVA

Project:

ETAP

SC calculation

Location:

11.1.1C

SK Mines

Contract: Engineer:

Jigyesh Sharma

Filename:

SK Mines HZL

Study Case:  CASE-1

Page:

8

Date:

04-05-2016

SN:

LARTOUMUM

Revision:

Base

Config.:

 Normal

SHORT- CIRCUIT REPORT

Fault at bus:  Nominal kV Voltage c Factor 

Bus22 =  6.600 = 1.10 (Maximum If)

Contribution From Bus ID

3-Phase Fault To Bus

%V

kA

ID

From Bus

Symm. rms

Positive & Zero Sequence Impedances Looking into "From Bus"

Line-To-Ground Fault % Voltage at From Bus Va

kA Symm. rms

Vb

Vc

Ia

3I0

% Impedance on 100 MVA base R1

X1

R0

X0

Bus22

Total

0.00

23.162

0.00

104.37

100.85

21.986

21.986

4.67E+000

4.13E+001

2.37E+000

4.73E+001

Bus20

Bus22

81.76

15.959

91.64

100.12

91.22

17.245

21.140 *

3.25E+000

6.02E+001

2.46E+000

4.92E+001

Bus26

Bus22

15.98

0.512

66.38

100.56

62.11

0.327

0.000

6.64E+002

1.76E+003

Bus28

Bus22

15.98

0.512

66.38

100.56

62.11

0.327

0.000

6.64E+002

1.76E+003

Bus31

Bus22

15.98

0.512

66.38

100.56

62.11

0.327

0.000

6.64E+002

1.76E+003

Bus36

Bus22

10.23

0.327

64.16

100.60

60.53

0.209

0.000

1.07E+003

2.74E+003

float air blower -1

Bus22

100.00

0.601

100.00

100.00

100.00

0.364

0.000

2.49E+002

1.58E+003

 ball mill

Bus22

100.00

2.254

100.00

100.00

100.00

1.367

0.000

4.59E+001

4.24E+002

regrind mill

Bus22

100.00

0.303

100.00

100.00

100.00

0.169

0.000

6.00E+002

3.12E+003

Bus30

Bus25

11.24

0.360

64.55

100.59

60.79

0.230

0.000

9.72E+002

2.49E+003

Bus32

Bus25

11.24

0.360

64.55

100.59

60.79

0.230

0.000

9.72E+002

2.49E+003

Bus34

Bus25

15.98

0.512

66.38

100.56

62.11

0.327

0.000

6.64E+002

1.76E+003

Bus37

Bus25

10.23

0.327

64.16

100.60

60.53

0.209

0.000

1.07E+003

2.74E+003

T14~

Bus25

0.00

0.000

58.23

60.26

100.66

0.282

0.846 *

6.15E+001

1.23E+003

Float air blower-2

Bus25

100.00

0.601

100.00

100.00

100.00

0.364

0.000

2.49E+002

1.58E+003

Secondary cone crusher 

Bus25

100.00

0.162

100.00

100.00

100.00

0.090

0.000

1.33E+003

5.77E+003

Bus25

Bus22

0.00

2.312

0.00

104.37

100.85

1.721

0.846

Bus27

Bus30

11.24

2.742

64.55

100.59

60.79

1.520

0.000

Bus29

Bus30

11.24

2.742

64.55

100.59

60.79

1.520

0.000

Bus33

Bus32

11.24

2.742

64.55

100.59

60.79

1.520

0.000

Bus35

Bus32

11.24

2.742

64.55

100.59

60.79

1.520

0.000

Project:

ETAP

SC calculation

Location:

11.1.1C

SK Mines

Contract: Engineer:

Jigyesh Sharma

Filename:

SK Mines HZL

Study Case:  CASE-1

Page:

9

Date:

04-05-2016

SN:

LARTOUMUM

Revision:

Base

Config.:

 Normal

(Cont.)

Fault at bus:  Nominal kV Voltage c Factor 

Bus22 =  6.600 = 1.10 (Maximum If)

Contribution From Bus ID

3-Phase Fault To Bus

%V

kA

ID

From Bus

Symm. rms

3-Phase

Positive & Zero Sequence Impedances Looking into "From Bus"

Line-To-Ground Fault % Voltage at From Bus Va L-G

Vb

kA Symm. rms

Vc L-L

Ia

% Impedance on 100 MVA base

3I0

R1

L-L-G

Initial Symmetrical Current (kA, rms)

:

 23.162

 21.986

 19.852

 22.975

Peak Current (kA), Method C

:

 57.414

 54.500

 49.209

 56.952

Breaking Current (kA, rms, symm)

:

 21.986

 19.852

 22.975

Steady State Current (kA, rms)

:

 21.986

 19.852

 22.975

 15.959

# Indicates a fault current contribution from a three-winding transformer  * Indicates a zero sequence fault current contribution (3I0) from a grounded Delta- Y transformer 

X1

R0

X0

Project: Location:

ETAP

SC calculation

11.1.1C

SK Mines

Contract: Engineer:

Jigyesh Sharma

Filename:

SK Mines HZL

Study Case:  CASE-1

Page:

10

Date:

04-05-2016

SN:

LARTOUMUM

Revision:

Base

Config.:

 Normal

Short-Circuit Summary Report 3-Phase, LG, LL, LLG Fault Currents

Bus ID Bus22

3-Phase Fault kV 6.600

I"k 23.162

Line-to-Ground Fault

ip 57.414

Ik 15.959

All fault currents are in rms kA. Current ip is calculated using Method C. * LLG fault current is the larger of the two faulted line currents.

Line-to-Line Fault

*Line-to-Line-to-Ground

I"k

ip

Ib

Ik

I"k

ip

Ib

Ik

21.986

54.500

21.986

21.986

19.852

49.209

19.852

19.852

  I"k 22.975

ip   56.952

Ib

Ik

22.975

22.975

 

Project: Location:

ETAP

SC calculation

11.1.1C

SK Mines

Contract: Engineer:

Jigyesh Sharma

Filename:

SK Mines HZL

Study Case:  CASE-1

Page:

11

Date:

04-05-2016

SN:

LARTOUMUM

Revision:

Base

Config.:

 Normal

Sequence Impedance Summary Report

Bus ID Bus22

P os it iv e S eq. I mp . (o hm) kV 6.600

Ne ga ti ve S eq . I mp . (o hm)

Zero Seq. Imp. (ohm)

Fault Zf (ohm)

Resistance

Reactance

Impedance

Resistance

Reactance

Impedance

Resistance

Reactance

Impedance

Resistance

Reactance

Impedance

0.02036

0.17982

0.18097

0.02019

0.18364

0.18474

0.01031

0.20622

0.20647

0.00000

0.00000

0.00000

Project: Location:

ETAP

SC calculation

11.1.1C

SK Mines

Contract: Engineer:

Jigyesh Sharma

Filename:

SK Mines HZL

Study Case:  CASE-1

Page:

1

Date:

04-05-2016

SN:

LARTOUMUM

Revision:

Base

Config.:

 Normal

Electrical Transient Analyzer Program

Short-Circuit Analysis

IEC 60909 Standard 3-Phase, LG, LL, & LLG Fault Currents

 Number of Buses:

 Number of Branches:

 Number of Machines:

Swing

V-Control

Load

Total

 2

 0

 14

 16

XFMR2

XFMR3

Reactor 

Line/Cable

Impedance

Tie PD

Total

 10

 0

 0

 0

 0

 4

14

Synchronous Generator 

Power  Grid

Synchronous Motor

Induction Machines

Lumped Load

Total

 0

 2

0

 5

 10

 17

System Frequency:

50.00 Hz

Unit System:

English

Project Filename:

SK Mines HZL

Output Filename:

C:\ETAP 1111\SK Mines HZL\Untitled.SI2

Project: Location:

ETAP

SC calculation

11.1.1C

SK Mines

Contract: Engineer:

Jigyesh Sharma

Filename:

SK Mines HZL

Study Case:  CASE-1

Adjustments Apply

Individual

Adjustments

/Global

Transformer Impedance:

Yes

Individual

Reactor Impedance:

Yes

Individual

Overload Heater Resistance:

 No

Transmission Line Length:

 No

Cable Length:

 No

Tolerance

Percent

Apply

Individual

Adjustments

/Global

Transmission Line Resistance:

Yes

Global

 20

Cable Resistance:

Yes

Global

 20

Temperature Correction

Degree C

Page:

2

Date:

04-05-2016

SN:

LARTOUMUM

Revision:

Base

Config.:

 Normal

Project: Location:

ETAP

SC calculation

11.1.1C

SK Mines

Contract: Engineer:

Jigyesh Sharma

Filename:

SK Mines HZL

Study Case:  CASE-1

Bus Input Data

Bus ID

Type

Bus20

SWNG

Bus22

Load

Bus24

SWNG

Bus25

Initial Voltage  Nom. kV

Base kV

Sub-sys

 %Mag.

Ang.

33.000

 33.000

1

100.00

0.00

6.600

 6.600

1

100.00

-30.00

33.000

 33.000

2

100.00

0.00

Load

6.600

 6.600

2

100.00

30.00

Bus26

Load

0.433

 0.433

1

100.00

0.00

Bus27

Load

0.433

 0.433

2

100.00

60.00

Bus28

Load

0.433

 0.433

1

100.00

0.00

Bus29

Load

0.433

 0.433

2

100.00

60.00

Bus30

Load

0.433

 0.433

2

100.00

60.00

Bus31

Load

0.433

 0.433

1

100.00

0.00

Bus32

Load

0.433

 0.433

2

100.00

60.00

Bus33

Load

0.433

 0.433

2

100.00

60.00

Bus34

Load

0.433

 0.433

2

100.00

60.00

Bus35

Load

0.433

 0.433

2

100.00

60.00

Bus36

Load

0.433

 0.433

1

100.00

0.00

Bus37

Load

0.433

 0.433

2

100.00

60.00

16 Buses Total All voltages reported by ETAP are in % of bus Nominal kV. Base kV values of buses are calculated and used internally by ETAP.

Page:

3

Date:

04-05-2016

SN:

LARTOUMUM

Revision:

Base

Config.:

 Normal

Project:

ETAP

SC calculation

Location:

11.1.1C

SK Mines

Contract: Engineer:

Jigyesh Sharma

Filename:

SK Mines HZL

Study Case:  CASE-1

Page:

4

Date:

04-05-2016

SN:

LARTOUMUM

Revision:

Base

Config.:

 Normal

 2-Winding Transformer Input Data

Transformer ID

Rating MVA

Prim. kV

Sec. kV

Z Variation %Z

X/R

% Tap Setting

+ 5%

- 5%

% Tol.

Prim.

Sec.

Adjusted

Phase Shift

%Z

Type

Angle

T10

20.000

33.000

6.600

10.00

20.00

0

0

0

0

0

10.0000

Dyn

30.000

T14

20.000

33.000

6.600

10.00

20.00

0

0

0

0

0

10.0000

Dyn

-30.000

TR#1

2.000

6.600

0.433

6.25

6.00

0

0

0

0

0

6.2500

Dyn

-30.000

TR#2

2.000

6.600

0.433

6.25

6.00

0

0

0

0

0

6.2500

Dyn

-30.000

TR#3

2.000

6.600

0.433

6.25

6.00

0

0

0

0

0

6.2500

Dyn

-30.000

TR#4

2.000

6.600

0.433

6.25

6.00

0

0

0

0

0

6.2500

Dyn

-30.000

TR#5

2.000

6.600

0.433

6.25

6.00

0

0

0

0

0

6.2500

Dyn

-30.000

TR#6

2.000

6.600

0.433

6.25

6.00

0

0

0

0

0

6.2500

Dyn

-30.000

TR#7

2.000

6.600

0.433

6.25

6.00

0

0

0

0

0

6.2500

Dyn

-30.000

TR#8

2.000

6.600

0.433

6.25

6.00

0

0

0

0

0

6.2500

Dyn

-30.000

2-Winding Transformer Grounding Input Data Grounding Transformer ID

Rating MVA

Prim. kV

Conn. Sec. kV

Type

Primary Type

kV

Secondary Amp

Ohm

Type

kV

Amp

Ohm

T10

20.000

33.000

6.600

D/Y

Solid

T14

20.000

33.000

6.600

D/Y

Solid

TR#1

2.000

6.600

0.433

D/Y

Resistor 

3.3

75.00000

TR#2

2.000

6.600

0.433

D/Y

Resistor 

3.3

75.00000

TR#3

2.000

6.600

0.433

D/Y

Resistor 

3.3

75.00000

TR#4

2.000

6.600

0.433

D/Y

Resistor 

TR#5

2.000

6.600

0.433

D/Y

Resistor 

TR#6

2.000

6.600

0.433

D/Y

Resistor 

75.00000

TR#7

2.000

6.600

0.433

D/Y

Resistor 

75.00000

TR#8

2.000

6.600

0.433

D/Y

Resistor 

75.00000 3.3

3.3

75.00000

75.00000

Project:

ETAP

SC calculation

Location:

11.1.1C

SK Mines

Contract: Engineer:

Jigyesh Sharma

Filename:

SK Mines HZL

Study Case:  CASE-1

Page:

5

Date:

04-05-2016

SN:

LARTOUMUM

Revision:

Base

Config.:

 Normal

Branch Connections

CKT/Branch ID

Connected Bus ID Type

From Bus

% Impedance, Pos. Seq., 100 MVAb To Bus

R

X

Z

T10

2W XFMR 

Bus20

Bus22

2.46

49.23

49.30

T14

2W XFMR 

Bus24

Bus25

2.46

49.23

49.30

TR#1

2W XFMR 

Bus22

Bus26

49.42

296.51

300.60

TR#2

2W XFMR 

Bus25

Bus30

49.42

296.51

300.60

TR#3

2W XFMR 

Bus22

Bus28

49.42

296.51

300.60

TR#4

2W XFMR 

Bus22

Bus31

49.42

296.51

300.60

TR#5

2W XFMR 

Bus25

Bus32

49.42

296.51

300.60

TR#6

2W XFMR 

Bus25

Bus34

49.42

296.51

300.60

TR#7

2W XFMR 

Bus22

Bus36

49.42

296.51

300.60

TR#8

2W XFMR 

Bus25

Bus37

49.42

296.51

300.60

CB66

Tie Breakr 

Bus30

Bus27

CB69

Tie Breakr 

Bus30

Bus29

CB71

Tie Breakr 

Bus32

Bus33

CB73

Tie Breakr 

Bus32

Bus35

 Y

Project: Location:

ETAP

SC calculation

11.1.1C

SK Mines

Contract: Engineer:

Jigyesh Sharma

Filename:

SK Mines HZL

Study Case:  CASE-1

Page:

6

Date:

04-05-2016

SN:

LARTOUMUM

Revision:

Base

Config.:

 Normal

Power Grid Input Data

Power Grid

Connected Bus

ID

ID

% Impedance 100 MVA Base

Rating MVASC

kV



X"

Grounding R/X"

Type

U3

Bus20

1000.000

33.000

0.71247

9.97459

 0.07

Wye - Solid

U4

Bus24

1000.000

33.000

0.71247

9.97459

 0.07

Wye - Solid

Total Connected Power Grids ( = 2 ): 2000.000 MVA

Project:

ETAP

SC calculation

Location:

11.1.1C

SK Mines

Contract: Engineer:

Jigyesh Sharma

Filename:

SK Mines HZL

Study Case:  CASE-1

Page:

7

Date:

04-05-2016

SN:

LARTOUMUM

Revision:

Base

Config.:

 Normal

Induction Machine Input Data

Induction Machine ID

Connected Bus Type

Qty

Rating

ID

HP/kW

PosSeqImp (Mtr Base)

kVA

kV

Amp

PF

%R

% X"

R/X"

Grounding Conn.

Type

mFact. Amp

MW/PP

loat air blower -1

Motor

1

Bus22

750.00

867.66

6.600

 75.90

92.37

2.16

13.72

0.16

Wye

Open

0.38

all mill

Motor

1

Bus22

2850.00

3253.59

6.600

 284.61

92.92

1.49

13.81

0.11

Wye

Open

1.43

egrind mill

Motor

1

Bus22

375.00

436.83

6.600

 38.21

92.09

2.62

13.64

0.19

Wye

Open

0.19

Float air blower-2

Motor

1

Bus25

750.00

867.66

6.600

 75.90

92.37

2.16

13.72

0.16

Wye

Open

0.38

Secondary cone crusher

Motor

1

Bus25

200.00

234.44

6.600

 20.51

91.83

3.12

13.53

0.23

Wye

Open

0.10

Total Connected Induction Machines ( = 5 ): 5660.2 kVA

Lumped Load Input Data Motor Loads Lumped Load Lumped Load ID

% Impedance

Rating kVA

kV

% Load

Loading

Amp

% PF

MTR

STAT

kW

kvar  

Machine Base R

X"

Grounding

R/X"

Conn.

Type

 mFact. Amp

MW/PP

Lump1

1500.0

0.433

2000.06

85.00

70

30

892.50

553.12

6.46

15.37

0.42

Delta

0.89

Lump2

500.0

0.433

666.69

85.00

70

30

297.50

184.37

6.46

15.37

0.42

Delta

0.30

Lump3

500.0

0.433

666.69

85.00

70

30

297.50

184.37

6.46

15.37

0.42

Delta

0.30

Lump4

1500.0

0.433

2000.06

85.00

70

30

892.50

553.12

6.46

15.37

0.42

Delta

0.89

Lump5

1500.0

0.433

2000.06

85.00

70

30

892.50

553.12

6.46

15.37

0.42

Delta

0.89

Lump6

500.0

0.433

666.69

85.00

70

30

297.50

184.37

6.46

15.37

0.42

Delta

0.30

Lump7

500.0

0.433

666.69

85.00

70

30

297.50

184.37

6.46

15.37

0.42

Delta

0.30

Lump8

1500.0

0.433

2000.06

85.00

70

30

892.50

553.12

6.46

15.37

0.42

Delta

0.89

Lump9

900.0

0.433

1200.04

85.00

70

30

535.50

331.87

6.46

15.37

0.42

Delta

0.54

Lump10

900.0

0.433

1200.04

85.00

70

30

535.50

331.87

6.46

15.37

0.42

Delta

0.54

Total Connected Lumped Loads ( = 10 ): 9800.0 kVA

Project:

ETAP

SC calculation

Location:

11.1.1C

SK Mines

Contract: Engineer:

Jigyesh Sharma

Filename:

SK Mines HZL

Study Case:  CASE-1

Page:

8

Date:

04-05-2016

SN:

LARTOUMUM

Revision:

Base

Config.:

 Normal

SHORT- CIRCUIT REPORT

Fault at bus:  Nominal kV Voltage c Factor 

Bus22 =  6.600 = 1.10 (Maximum If)

Contribution From Bus ID

3-Phase Fault To Bus

%V

kA

ID

From Bus

Symm. rms

Positive & Zero Sequence Impedances Looking into "From Bus"

Line-To-Ground Fault % Voltage at From Bus Va

kA Symm. rms

Vb

Vc

Ia

% Impedance on 100 MVA base

3I0

R1

X1

R0

X0

Bus22

Total

0.00

20.897

0.00

102.58

100.30

20.302

20.302

4.22E+000

4.59E+001

2.46E+000

4.92E+001

Bus20

Bus22

81.76

15.959

91.41

100.11

91.07

17.194

20.302 *

3.25E+000

6.02E+001

2.46E+000

4.92E+001

Bus26

Bus22

15.98

0.512

65.47

100.49

61.67

0.334

0.000

6.64E+002

1.76E+003

Bus28

Bus22

15.98

0.512

65.47

100.49

61.67

0.334

0.000

6.64E+002

1.76E+003

Bus31

Bus22

15.98

0.512

65.47

100.49

61.67

0.334

0.000

6.64E+002

1.76E+003

Bus36

Bus22

10.23

0.327

63.20

100.52

60.12

0.214

0.000

1.07E+003

2.74E+003

float air blower -1

Bus22

100.00

0.601

100.00

100.00

100.00

0.372

0.000

2.49E+002

1.58E+003

 ball mill

Bus22

100.00

2.254

100.00

100.00

100.00

1.398

0.000

4.59E+001

4.24E+002

regrind mill

Bus22

100.00

0.303

100.00

100.00

100.00

0.172

0.000

6.00E+002

3.12E+003

3-Phase

L-G

L-L

L-L-G

Initial Symmetrical Current (kA, rms)

:

 20.897

 20.302

 17.937

 20.831

Peak Current (kA), Method C

:

 52.917

 51.412

 45.421

 52.751

Breaking Current (kA, rms, symm)

:

 20.302

 17.937

 20.831

Steady State Current (kA, rms)

:

 20.302

 17.937

 20.831

 15.959

# Indicates a fault current contribution from a three-winding transformer  * Indicates a zero sequence fault current contribution (3I0) from a grounded Delta- Y transformer 

Project: Location:

ETAP

SC calculation

11.1.1C

SK Mines

Contract: Engineer:

Jigyesh Sharma

Filename:

SK Mines HZL

Study Case:  CASE-1

Page:

9

Date:

04-05-2016

SN:

LARTOUMUM

Revision:

Base

Config.:

 Normal

Short-Circuit Summary Report 3-Phase, LG, LL, LLG Fault Currents

Bus ID Bus22

3-Phase Fault kV 6.600

I"k 20.897

Line-to-Ground Fault

ip 52.917

Ik 15.959

All fault currents are in rms kA. Current ip is calculated using Method C. * LLG fault current is the larger of the two faulted line currents.

Line-to-Line Fault

*Line-to-Line-to-Ground

I"k

ip

Ib

Ik

I"k

ip

Ib

Ik

20.302

51.412

20.302

20.302

17.937

45.421

17.937

17.937

  I"k 20.831

ip   52.751

Ib

Ik

20.831

20.831

 

Project: Location:

ETAP

SC calculation

11.1.1C

SK Mines

Contract: Engineer:

Jigyesh Sharma

Filename:

SK Mines HZL

Study Case:  CASE-1

Page:

10

Date:

04-05-2016

SN:

LARTOUMUM

Revision:

Base

Config.:

 Normal

Sequence Impedance Summary Report

Bus ID Bus22

P os it iv e S eq. I mp . (o hm) kV 6.600

Ne ga ti ve S eq . I mp . (o hm)

Zero Seq. Imp. (ohm)

Fault Zf (ohm)

Resistance

Reactance

Impedance

Resistance

Reactance

Impedance

Resistance

Reactance

Impedance

Resistance

Reactance

Impedance

0.01837

0.19974

0.20059

0.01813

0.20337

0.20418

0.01072

0.21447

0.21473

0.00000

0.00000

0.00000

View more...

Comments

Copyright ©2017 KUPDF Inc.
SUPPORT KUPDF