SFRA - Theory and Method - Standards_120911

May 24, 2018 | Author: gnpr_10106080 | Category: Transformer, Electrical Impedance, Hertz, Resonance, Inductance
Share Embed Donate


Short Description

sweep frequency response...

Description

Sweep Frequency Response Analysis

Advanced Transformer Testing 2012

Transformer Diagnostics 

Transformer Diagnostics is about acquiring accurate measurement data and other information in order to make the correct decision about what to do with the actual unit

TTR

SFRA

WRM FDS

Advanced Transformer Testing 2012

SFRA testing basics 

Off-line test



The transformer is seen as a complex impedance circuit



[Open] (“magnetization impedance”) and [Short] (“short-circuit impedance”) responses are measured over a wide frequency range and the results are presented as magnitude response





(transfer function) in dB Changes in the impedance/transfer function can be detected and compared over time, between test objects or within test objects The method is unique in its ability to detect a variety of winding faults, core issues and other electromechanical faults in one test Advanced Transformer Testing 2012

Réponse et analyse d’un balayage en SFRA mathematics basics… fréquence

Generator test voltage

Measured voltage

Phase, °

Gain, dB

 Vout   V   in 

G (dB)  20 log10 

Advanced Transformer Testing 2012

Sweep Frequency Response Analysis Standards Summary

Advanced Transformer Testing 2012

SFRA Standards and Recommendations 

Frequency Response Analysis on Winding Deformation of Power Transformers, DL/T 911-2004, The Electric Power Industry Standard of People‟s Republic of China



Mechanical-Condition Assessment of Transformer Windings Using Frequency Response Analysis (FRA), CIGRE report 342, 2008



IEC 60076-18 , Power2012 transformers – Part 18: Measurement of frequency response,



IEEE PC57.149™, Guide for the Application and Interpretation of Frequency Response Analysis for Oil Immersed Transformers, 2012



Internal standards by transformer manufacturers, e.g. ABB FRA Standard v.5

Advanced Transformer Testing 2012

SFRA - Theory and method

Advanced Transformer Testing 2012

FRA definitions 

Frequency response • The amplitude ratio and phase difference between voltages measured at two terminals of the test object over a range of frequencies when one of the terminals is excited by a voltage source. The frequency response measurement result is a series of amplitude ratios and phase differences at specific frequencies over a range of frequency. • As Vout/Vin varies over a wide range, it is expressed in decibels (dB). The relative voltage response in dB is calculated as 20 x log (V /V )



Frequency response analysis (FRA)

10

out

in

• The technique used to detect damage by the use of frequency response measurements.

Advanced Transformer Testing 2012

FRA history 

1960: Low Voltage Impulse Method. First proposed by W. Lech & L. Tyminski in Poland for detecting transformer winding deformation.



1966: Results Published; “Detecting Transformer Winding Damage - The Low Voltage Impulse Method”, Lech & Tyminsk, The Electric Review, UK



1978: “Transformer Diagnostic Testing by Frequency Response Analysis”, E.P. Dick & C.C. Erven, Ontario Hydro, IEEE Transactions of Power Delivery



1980 - 1990‟s : Proving trials by utilities and OEM‟s, the technology cascades internationally via CIGRE, and many other conferences and technical meetings



2004: First SFRA standard, ” Frequency Response Analysis on Winding Deformation of Power Transformers”, DL/T 911-2004, is published by The Electric Power Industry Standard of People‟s Republic of China



2008: CIGRE report 342, ”Mechanical-Condition Assessment of Transformer Windings Using Frequency Response Analysis (FRA)” is published



2012: IEC60076-18 and IEEE PC57.149 are released

Advanced Transformer Testing 2012

Transformer mechanics basics 



A transformer is designed to handle certain (high!) mechanical forces. Design limits can be exceeded due to • Excessive mechanical impact – Transportation – Earthquakes

• Over currents caused by – Through faults – Tap-changer faults – Faulty synchronization 

Mechanical strength weakens as the transformer ages • Less capability to handle high stress/forces • Increased risk of mechanical problems • Increased risk for insulation problems

Advanced Transformer Testing 2012

Why assess the mechanical condition? 

To detect core displacement and winding deformation due to e.g. 

Large electromagnetic forces from fault current



Transformer transportation and relocation



If these faults or arethermal not detected they may develop into dielectric faults which normally results in the loss of the transformer 

Periodic testing is essential!

Advanced Transformer Testing 2012

Detecting Faults with SFRA 







Winding faults 

Deformation



Displacement



Shorts

Core related faults 

Movements



Grounding



Screens

Mechanical faults/changes 

Clamping structures



Connections

And more... Advanced Transformer Testing 2012

SFRA measurement circuitry

Advanced Transformer Testing 2012

SFRA – How does it work (1) 

A large number of low voltage signals with varying frequencies are applied to the transformer



The input and output signals are measured in amplitude and phase



The ratio of the two signals gives the frequency



response or transfer function of the transformer From the (complex) transfer function you can derive a number of entities as function of frequency e.g. 

Magnitude



Phase



Impedance/admittance



Correlation

Advanced Transformer Testing 2012

SFRA – How does it work (2) 

The RLC network has different impedance at different frequencies.



The transfer function for all frequencies is the measure of the effective impedance of the RLC network.



A geometrical deformation, changes the RLC network, which in turn changes the impedance/transfer function at different frequencies.



These changes gives an indication of damage within a transformer.

Advanced Transformer Testing 2012

SFRA results – Frequency regions 

Transformer issues can be detected in different frequency ranges • “Low” frequencies – Core problems – Shorted/open windings

Winding and tap

– Bad connections/increased resistance – Short-circuit impedance changes

leads Winding interaction and deformation

• “Medium” frequencies – Winding deformations

Core + windings

– Winding displacement

• “High” frequencies – Movement of winding and tap leads

Advanced Transformer Testing 2012

Frequency regions by IEC and IEEE 10 0 -10 -20

Winding structure influence

Core influence

B d -30 , e d tu -40 i n g a -50 M

-60 -70 -80 -90 1 10

A phase B phase C phase 2

10

Earthing leads influence

Interaction between windings

3

10

4

10 Frequency, Hz

5

10

6

10

Advanced Transformer Testing 2012

7

10

SFRA measurement frequency ranges – IEC60076-18 Category

Low frequency limit High frequency limit

Power transformers, Uw < 72.5 kV

< 20 Hz

> 2 MHz

Power transformers, Uw > 72.5 kV

< 20 Hz

> 1 MHz

Comparing older measurements and/or methods/practices not following IEC method 1 (CIGRE 342) standard for signal shield grounding

< 20 Hz

500 kHz

Advanced Transformer Testing 2012

SFRA measurement frequency ranges – Examples ”Standard”

Low frequency limit High frequency limit

Eskom standard

20 Hz

2 MHz

ABB standard

10 Hz

2 MHz

“Japan” (impedance) DL/T-911 2004

100 Hz

1 MHz 1 kHz

1 MHz

Typical instrument default values are 20 Hz – 2 MHz

Advanced Transformer Testing 2012

Comparative tests Transformer A

Design based

Time based

Transformer B

Transformer A

Type based

Advanced Transformer Testing 2012

Comparisons 

Time Based  







The most reliable test Deviations between curves are easy to detect

Type Based 

(Tests performed on the same transformer over time)

(Tests performed on transformer of same design)

Requires knowledge about test object/versions Small deviations are not necessarily indicating a problem

Design based

(Tests performed on winding legs and bushings of

identical design)  

Requires knowledge about test object/versions Small deviations are not necessarily indicating a problem

Advanced Transformer Testing 2012

SFRA Measurement philosophy New measurement = Reference measurement

Back in Service New measurement ≠ Reference measurement

Further Diagnostics Required Advanced Transformer Testing 2012

Reference measurements 

When transformer is new • Capture reference data at commissioning of new transformers



When transformer is in known good condition • Capture reference data at a scheduled routine test (no issues found)



Save for future reference



Start Your Reference Measurements ASAP!

Advanced Transformer Testing 2012

SFRA measurements – When? 

Manufacturing tests   

    

Quality check during manufacturing Proofing the transformer after short-circuit test Before shipping

Installation/commissioning Relocation After a significant through-fault event Part of routine diagnostic test Catastrophic events • Earth quakes • Hurricanes/tornadoes



Trigger based test/transformer alarms • Buchholz • DGA • High temperature



Before-after maintenance

Advanced Transformer Testing 2012

Transformer fault detection

Advanced Transformer Testing 2012

Detection of Winding Movement (1)



Prior to SFRA the mechanical integrity of the transformer was assessed with the following standard methods: 





Winding capacitance Excitation current



Leakage reactance measurements

Each of these methods have drawbacks

26

Detection of Winding Movement (2) 





Winding Capacitance 

Successful only if reference data is available



Limited sensitivity for some failure modes

Excitation Current 

Excitation current is an excellent means of detecting turn-to-turn failure as a result of winding movement



If a turn-to-turn failure is absent, winding movements can remain undetected.

Leakage Reactance 

Per phase leakage reactance measurements generally shows no or little correlation between the phases and nameplate



Discrepancies from nameplate value of 0,5 % to 3 % can be a reason for concern



The range of defect detection is to large for an accurate assessment 27

Comparing diagnostic techniques (CIGRE) Diagnostic technique

Advantages

Magnetizing (exciting) current

Requires relatively simple equipment. Can detect core damage

Disadvantages

Not sensitive to winding deformation. Measurement strongly affected by core residual magnetism Impedance (leakage reactance) Traditional method currently specified in Very small changes can be significant. short-circuits test standards. Limited sensitivity for some failure modes Reference (nameplate) values are (best for radial deformation) available Frequency Response of Stray Losses Can be more sensitive than impedance Not a standard use in the industry (FRSL) measurement. Almost unique to detect short circuits between parallel strands Winding capacitance Can be more sensitive than impedance Limited sensitivity for some failure modes measurements. (best for radial deformation). Standard equipment available Relevant capacitance may not be measurable (e.g. Between series/common/tap windings for auto transformers) Low Voltage Impulse (LVI) (time domain) Recognized as very sensitive Specialist equipment required. Difficult to achieve repeatability. Difficult to interpret Better repeatability than LVI with the Standardization of techniques required. Frequency Response Analysis same sensitivity. Guide to interpretation required Easier to interpret than LVI (frequency instead of time domain). Increasing number of users

Advanced Transformer Testing 2012

Comparing SFRA and other traditional transformer measurements 

End-to-End [Open], (Open Circuit Self Admittance] • •



End-to-End [short], (Short Circuit Self Admittance) • •



Example: 1U - 1N [open] Excitation current as function of frequency Example: 1U – 1N [short] Leakage reactance/short-circuit impedance as function of frequency (compare IEEE 62 measurements at 50/60 Hz)

• FRSL, Frequency Response of Stray Losses (SFRA 20 – 600 Hz) Input Impedance • •

Measurement of impedance to ground for a certain configuration (Japanese ”standard”, common in South America, common in China before DL/T 911) Can be performed for grounded objects with the active impedance probe



Capacitive Inter-winding [Inter-Winding]



Inductive Inter-winding [Transfer Admittance]

• • •

Capacitance as a function of frequency Turn-ratio measurement (voltage ratio) as a function of frequency Possible to perform at various impedances with the active voltage probe

Advanced Transformer Testing 2012

SFRA vs Excitaion current Example; U1 - N1 [open]  Excitation current as function of frequency 

SFRA

Please note that excitation current is voltage dependent! • At low voltages the inductance is low and increasing with voltage • At high voltages the core gets saturated and the inductance decreases • Non-linear phenomena...

Advanced Transformer Testing 2012

SFRA vs short-circuit impedance/leakage reactance Example; U1 – N1 [short] 

Short-circuit impedance/Leakage reactance as a function of frequency (IEEE – 50/60 Hz @ 200 V) • Leakage reactance is not voltage dependent. However, in certain configurations the magnetizing impedance can influence the results at lower test voltages



FRSL, Frequency Response of Stray Losses (”SFRA” 20 – 600 Hz @ ~200 V)

Advanced Transformer Testing 2012

Frequency Response of Stray Losses (FRSL) 

End-to-End (short-circuit), [Short Circuit Self Admittance] • Impedance changes may be caused by; – Inductance changes e.g winding movement – Resistance change (DC) due to bad contacts, soldering issues etc – Resistance change at higher frequencies (Rstray) due to stray losses caused by; – Winding deformation – Shorts between parallel strands Ref: L. BOLDUC, et. Al ”DETECTION OF TRANSFORMER WINDING DISPLACEMENT BY THE FREQUENCY RESPONSE OF STRAY LOSSES (FRSL), CIGRE session, 2000.

Advanced Transformer Testing 2012

FRSL – 160 MVA t ransformer with contact resistance problem

HV [short], Transformer G2-1

HV [short], Transformers G2-1 and 3

Advanced Transformer Testing 2012

FRA Methods  

Sweep Frequency Response Impulse

Advanced Transformer Testing 2012

Impulse FRA vs. SweepFRA 



Impulse FRA

Impulse FRA 

Injects a pulse signal and measure response



Convert Time Domain to Frequency Domain using Fast Fourier Transform (FFT) algorithm



Low resolution in lower frequencies

SFRA 

Injects a single frequency signal



Measures response at the same frequency



No conversion



High resoultion at all frequencies Advanced Transformer Testing 2012

Comparing Impulse & SweepFRA 

SFRA (Sweep frequency response analysis) provides good detail data in all frequencies Black = Imported Impulse measurement (Time domain converted to Frequency Domain) Red = SFRA Measurement

Deviations Low Frequency = Method Deviation High Frequency = Cable practice Advanced Transformer Testing 2012

Zoom View of impulse vs. SFRA Impulse instrument sample rate limts frequency resolution to 2kHz.

Advanced Transformer Testing 2012

SFRA Measurement Technique, part 1 - Measurement setups

Advanced Transformer Testing 2012

SFRA test setup

Advanced Transformer Testing 2012

FRAX measurement circuitry

Advanced Transformer Testing 2012

Test types – End-to-end (open) 

Test signal is applied to one end of a winding and the transmitted signal is measured at the other end



Magnetizing impedance of the transformer is the main parameter characterizing the low-frequency response



(below first resonance) in this configuration Commonly used because of its simplicity and the possibility to examine each winding separately

Advanced Transformer Testing 2012

End-to-end (open) - Example 

Low frequencies • May vary between measurements pending magnetization • Typical “dubbel-dip” response • B-phase should be below A and C-phase (Y)

Advanced Transformer Testing 2012

Test types – End-to-end short-circuit 

The test is similar to the end-to-end measurement, but with a winding on the same phase being short-circuited



The influence of the core is removed below about 10-20 kHz because the low-frequency response is characterized by the short-circuit impedance/leakage reactance instead of the magnetizing inductance



Response at higher frequencies is similar to end-to-end (open) measurements

Advanced Transformer Testing 2012

End-to-end (short) - Example 

Low frequencies • All phases should be very similar. > 0.25 dB difference may indicate leakage reactance/winding resistance/connection/tap-changer problems

Advanced Transformer Testing 2012

Test types – Capacitive inter-winding (IW) 

Test signal is applied to one end of a winding and the response is measured at one end of another winding on the same phase (not connected to the first one)



The response using this configuration is dominated at low frequencies by the inter-winding capacitance

Advanced Transformer Testing 2012

Test types – Inductive inter-winding (TA) 

The signal is applied to a terminal on the HV side, and the response is measured on the corresponding terminal on the LV side, with the other end of both windings being grounded



The low-frequency range of this test is determined by the winding turns ratio

Advanced Transformer Testing 2012

Inter-winding measurements - Example 

IW (red) is capacitive at low frequencies



TA (black) reflects turn ratio at low frequencies (135 MVA, 160/16 Dd0)



Similar response at high frequencies

Advanced Transformer Testing 2012

SFRA Measurement Technique, part 2 - How to achieve high quality results

Advanced Transformer Testing 2012

Test results – always comparisons

Core NOT grounded Core grounded

Repeatability is of utmost importance! Advanced Transformer Testing 2012

Example of repeatability 

105 MVA, Single phase Generator Step-up (GSU) transformer



SFRA measurements with FRAX 101 before and after a severe short-circuit in the generator • Two different test units • Tests performed by two different persons • Test performed at different dates

Advanced Transformer Testing 2012

Before (2007-05-23) and after fault (2007-08-29)

LV winding

HV winding

Advanced Transformer Testing 2012

105 MVA, Single phase GSU 

Measurements “before” and “after” were virtually identical



Very good correlation between reference and “after fault”

 

Conclusion: No indication of mechanical changes in the transformer



Transformer can safely be put back in service

Advanced Transformer Testing 2012

Potential compromising factors   

Measurement signal connection quality Shield grounding practice Instrument dynamic range/internal noise floor



Understanding core in lower frequencies in property “open” - influence circuit SFRA measurements

Advanced Transformer Testing 2012

Bad connection 

Bad connection can affect the curve at higher frequencies

Advanced Transformer Testing 2012

Good connection 

After proper connections were made

Advanced Transformer Testing 2012

FRAX C-Clamp – ensuring connection quality 

C-Clamp ensures good contact quality



Penetrates non conductive layers



Solid connection to round or flat busbars/bushings 

Provides strain relief for cable



Separate connector for single or multible ground braids

Advanced Transformer Testing 2012

Proper ground connection ensures repeatability at high frequencies

Good grounding practice; use shortest braid from cable shield to bushing flange.

Poor grounding practice

Advanced Transformer Testing 2012

Shield grounding influence

C. Homagk et al, ”Circuit design for reproducible on-site measurements of transfer function on large power transformers using the SFRA method”, ISH2007

Advanced Transformer Testing 2012

FRAX cable set and grounding

Always the same ground-loop inductance on a given bushing

Advanced Transformer Testing 2012

Instrument performance 

Transformers have high impedance/large attenuation at first resonance



Internal instrument noise is most often the main limiting source, not substation noise



Test your instruments noise floor bynot running a sweep with “open cables” (Clamps connected to transformer)

Advanced Transformer Testing 2012

Internal noise level – ”Noise floor”

”Open”/noise floor measurements Red = Other brand Green = FRAX 101

Advanced Transformer Testing 2012

Example of internal noise problem

H1 – H2 (open & short) measurements Black = Other brand Red = FRAX 101

Advanced Transformer Testing 2012

Why you need at least -100 dB...

Westinghouse 40 MVA, Dyn1, 115/14 kV, HV [open]

Advanced Transformer Testing 2012

Influence of core 



Try to minimize the effect, however, some differences are still to be expected and must be accepted (magnetic viscosity). Preferably:  perform SFRA measurements prior to winding



resistance measurements (or demagnetize the core prior to SFRA measurements) use same measurement voltage in all SFRA measurements

Advanced Transformer Testing 2012

Run winding resistance test after SFRA!

H1-H2 [open] After winding resistance test

After demagnetization

Advanced Transformer Testing 2012

Core magnetization by Doble…

Trace A shows the fingerprint response of the transformer and trace B shows the response as a result of magnetized core (caused by WRM measurements)

66

Magnetization status over time

Lachman et al, “Frequency Response Analysis of Transformers and Influence of Magnetic Viscosity”, Doble 2012

67

Effect of applied measurement voltage

H1-H0 [open] 0.1 V peak-to-peak

10V peak-to peak Influence of applied voltage is more pronounced on LV windings

Advanced Transformer Testing 2012

Measurement voltage by Tettex…

69

Measurement voltage effect – in practice

2.8 V Omicron

10 V FRAX, Doble and others

Advanced Transformer Testing 2012 70

FRAX101 has adjustable output voltage!

Omicron (2.8 V)

FRAX, 2.8 V

Advanced Transformer Testing 2012 71

Influence of tap changers 

The tap windings in a transformer add in one section at a time - affecting the low frequency (magnetization impedance) response and the mid-frequency (winding) response



Tap lead responses will be seen at higher frequencies than the tap windings. They are less organized but are still repeatable



Some tap-changers have a neutral position which is “more different” than the difference between consecutive taps. Avoid using the neutral position as reference measurement

Advanced Transformer Testing 2012

Distribution transformer with 5 HV taps

Tap winding Low frequency effect

73

Tap changer measurements by Doble…

Tap leads

Low frequency effect

Tap winding

74

System integrity test

Field verification unit with known frequency response is recommended in CIGRE and other standards to verify instrument and cables before starting the test Advanced Transformer Testing 2012

Summary – Measurement quality and repeatability 



The basis of SFRA measurements is comparison and repeatability/reproducibility is of utmost importance To ensure high repeatability; • Select a high quality, high accuracy instrument with high dynamic range and input/output impedance matched to the coaxial cables (e.g. 50 Ohm) • Make sure to get good signal connection and connect the shields of coaxial cables to flange of bushing using shortest braid technique • Use the same applied voltage in all SFRA measurements • Be careful about WRM testing and other tests that can magnetize the core. Perform after SFRA or demagnetize prior to SFRA • Make good documentation, e.g. make photographs of connections and note tap settings Advanced Transformer Testing 2012

SFRA Analysis

Advanced Transformer Testing 2012

Detecting Faults with SFRA 







Winding faults 

Deformation



Displacement



Shorts

Core related faults 

Movements



Grounding



Screens

Mechanical faults/changes 

Clamping structures



Connections

And more... Advanced Transformer Testing 2012

SFRA analysis tools Visual/graphical analysis





Starting dB values



The expected shape of star and delta configurations



Comparison of fingerprints from;

• 



The same transformer

– –

A sister transformer Symmetric phases

New/missing resonance frequencies

Correlation analysis • DL/T 911 2004 standard • Customer/transformer specific

Advanced Transformer Testing 2012

Typical response from a healthy transformer HV [short] identical between phases LV [open] as expected for a ΔY tx

Very lowphases deviation between for all tests – no winding defects HV [open] as expected for a ΔY tx ”Double dip” and mid phase response lower

80

Transformer with serious issues...

Large deviations between phases for LV [open] at low frequencies indicates changes in the magnetic circuit/core defects

Large deviations between phases at mid and high frequencies indicates winding faults

81

Transformer with winding shorted turn 

Easiest fault to recognize with SFRA



Typically produced by a through current fault



Adjacent turns lose paper and weld together resulting in a solid loop around the core



SFRA gives clear and unambiguous diagnosis of a shorted turn



SFRA response for the shorted phase may be identified without reference results since the variation at low frequencies gives a clear fault signature

Advanced Transformer Testing 2012

Shorted turn (IEEE) Frequency Range 20 Hz – 10 kHz

5 kHz – 100 kHz

Winding Turn-to-Turn Short Circuit Assuming no other failure modes exist: Open Circuit Tests: The short circuit failure mode removes the effect of the core‟s reluctance from the open circuit FRA results. The FRA open circuit trace assumes a similar behavior as short circuit test. The affected winding will show the greatest change. This failure mode will also affect the FRA responses from all other windings, but not as much. Short Circuit Tests: The results will not compare well against previous data or amongst phases. The affected winding is generally offset. Open Circuit and Short Circuit Tests: This range can shift or produce new resonance peaks and valleys. The changes will be greater on the affect phase.

50 kHz – 1 MHz

Open Circuit and Short Circuit Tests: This range can shift or produce new resonance peaks and valleys. The changes will be greater on the affect phase.

> 1 MHz

Open Circuit and Short Circuit Tests: This range can shift or produce new resonance peaks and valleys. The changes will be greater on the affect phase.

83

Transformer with shorted turn 10

100

1000

10000

100000

1000000

0 -10 -20 ) s B -30 d ( e s -40 n o p s e -50 R

-60 -70 -80 Freque ncy (Hz)

HV [open]; B phase (red) should have lower response compared to A and C phase but has instead higher magnitude/lower impedance

84

Shorted turn by Doble…

• •

Responses of the HV and LV winding of the same transformer Significant difference in the white phase due to imbalance in the reluctance on one of the core limbs (white phase) as a result of shorted turns

85

Shorted turn by IEEE… Large impedance decrease at low frequencies in open circuit test

Impedance decrease at low frequencies in HV shortcircuit test (only if short is on HV side)

86

Radial winding deformation – ”Hoop buckling” (IEEE) Frequency Range

Radial Winding Deformation Assuming, no other failure modes exist:

20 Hz – 10 kHz

Open Circuit Tests: This region (core region) is generally unaffected during radial winding deformation. Short Circuit Tests: Results in an increase in impedance. The FRA trace for the affected phase generally exhibits slight attenuation within the inductive roll-off portion.

5 kHz – 100 kHz

Open Circuit and Short Circuit Tests: The bulk winding range can shift or produce new resonance peaks and valleys depending of the severity of the deformation. However, this change is minimal and difficult identify. The changes will be greater on the affect winding, but it is still possible to have the effects transferred to the opposing winding. The response in the bulk region should be used as secondary evidence to support the analysis.

50 kHz – 1 MHz

Open Circuit and Short Circuit Tests: Radial winding deformation is most obvious in this range. It can shift or produce new resonance peaks and valleys depending of the severity of the deformation. The changes will be greater on the affect winding, but it is still possible to have the effects transferred to the opposing winding.

> 1 MHz

Open Circuit and Short Circuit Tests: This range is generally unaffected in this range. However, severe deformation can extend into this range.

Advanced Transformer Testing 2012

Radial winding deformation by IEEE...

Resonance changes at mid- and high frequencies in open circuit test

Small but significant impedance increase at low frequencies in short-circuit test

Advanced Transformer Testing 2012

Axial winding deformation – ”Telescoping” (IEEE) Frequency Range

Axial Winding Deformation Assuming, no other failure modes exist:

20 Hz – 10 kHz

Open Circuit Tests: This region (core region) is generally unaffected during axial winding deformation. Short Circuit Tests: Results in a change in impedance. The FRA trace for the affected winding causes a difference between phases or previous results in the inductive roll-off portion.

5 kHz – 100 kHz

Open Circuit and Short Circuit Tests: Axial winding deformation is most obvious in this range. The bulk winding range can shift or produce new resonance peaks and valleys depending of the severity of the deformation. The changes will be greater on the affect winding, but it is still possible to have the effects transferred to the opposing winding. Open Circuit and Short Circuit Tests: Axial winding deformation can shift or produce new resonance peaks and valleys depending of the severity of the deformation. The changes will be greater on the affect winding, but it is still possible to have the effects transferred to the opposing winding.

50 kHz – 1 MHz

> 1 MHz

Open Circuit and Short Circuit Tests: The response to axial winding deformation is unpredictable.

Advanced Transformer Testing 2012

Axial winding deformation by IEEE...

Resonance changes at mid- and high frequencies in open circuit test

Small but significant iImpedance increase at low frequencies in short-circuit test

Advanced Transformer Testing 2012

Core defects Core defects failures cause changes to the core‟s magnetic circuit 

Burnt core laminations



Shorted core laminations



Multiple/unintentional core grounds Lost core ground and joint dislocations.



Advanced Transformer Testing 2012

Core defects (IEEE) Frequency Range 20 Hz – 10 kHz

5 kHz – 100 kHz

Core Defects Assuming, no other failure modes exist: Open Circuit Tests: These types of failures will affect the lower frequency regions generally below 10 kHz. Core defects often change the primary core resonance shape. Less weight should be placed on shifting, because identifying core defects can sometimes be masked by the effects of core residual magnetization. If the open circuit core appears to be loaded, (looking closer to a short circuit response), this could indicated a core defect. Short Circuit Tests: This region is generally unaffected during bulk winding movement. All phases should be similar. Open Circuit and Short Circuit Tests: This range can shift or produce new resonance peaks and valleys.

50 kHz – 1 MHz

Open Circuit and Short Circuit Tests: Generally this range remains unaffected. However, if the fault is due to a core ground issue, changes to the CL capacitance can cause resonance shifts in the upper portion of this range.

> 1 MHz

Open Circuit and Short Circuit Tests: If the fault is due to a core ground issue, changes to the CL capacitance can cause resonance shifts.

Advanced Transformer Testing 2012

Core defects – Example

Significant (and unexpected) differencies between phases at low frequencies in LV [open] test

No differencies between phases at high frequencies – No winding defetcts...

Advanced Transformer Testing 2012

Core defects by IEEE...

Significant changes in the magnetic circuit at first resonance in open circuit test

Advanced Transformer Testing 2012

SFRA analysis – dB and Impedance

dB-scale • Magnitude = 20*log(Meas/Ref) • Phase = Phase (Meas/Ref) Impedance scale (Admittance Y = 1/Z) • |Z| = |U/I| = 50*(Ref – Meas)/Mea. • Phase = Phase (Z)

Advanced Transformer Testing 2012

SFRA standard magnitude response in dB

Advanced Transformer Testing 2012

Magnitude (dB) and Admittance (S) Second resonance ”decreased” on LV... Second resonance looks ”normal” on LV...

Advanced Transformer Testing 2012

Magnitude (dB) and Impedance (Ω)

Low resolution on LV magnitude High resolution with LV impedance

Advanced Transformer Testing 2012

Admittance (S) and Impedance (Ω)

Advanced Transformer Testing 2012

Magnitude response or Impedance/Admittance? 





Magnitude response (dB) •

Most established and standardized



Most pubished results are in dB



Common file format e.g. *.xfra supports magnitude

Impedance (Ω) •

More ”engineering”, most power engineers are familiar with transformer impedance in ohms



Improved resolution for low impedance circuits (< about 100 Ω) e.g. LV windings on distribution transformers



Impedance representation makes it possible to discriminate between resistive and inductive parts

Admittance (S) •

Improved resolution for low impedance circuits (< about 100 Ω) e.g. LV windings on distribution transformers



Same ”shape” as Magnitude

Advanced Transformer Testing 2012

FRAX The Features And Benefits

101

FRAX 101 – Frequency Response Analyzer

Advanced Transformer Testing 2012

FRAX101 – Frequency Response Analyzer Power Input 11-16VDC, internal battery (FRAX 101) USB Port On all models Bluetooth On FRAX101

Rugged Extruded Aluminum Case

Most feature rich and accurate SFRA unit in the world! Generator, reference and measure connectots – All panel mounted

Active probe connector on FRAX101

Advanced Transformer Testing 2012

SFRA test setup

Easy to connect shortest braid cables

Optional Internal Battery Over 8h effective run time

Industrial grade class 1 Bluetooth (100m) USB for redundancy

Advanced Transformer Testing 2012

Search Database Feature Data

files stored in XML format

Index

function stores all relevant data in a small database

Search

function can list and sort files in different locations

Advanced Transformer Testing 2012

Import formats

Advanced Transformer Testing 2012

Fast testing Less points where it takes time to test and where high frequency resolution is not needed

More points where higher frequency resolution is useful Traditional test about 2 min vs. FRAX fast test < 40 seconds

Advanced Transformer Testing 2012

Decision support with correlation analysis

Advanced Transformer Testing 2012

Unlimited analysis 

Unlimited graph control



Lots of available graphs



Ability to create custom calculation models using any mathematic formula measured data from and all the channels



Turn on and off as needed



Compare real data with calculated model data

Advanced Transformer Testing 2012

FRAX150

As FRAX-101 except: 

Internal PC/stand-alone



No internal battery option



No Bluetooth

Advanced Transformer Testing 2012

FRAX99

As FRAX 101 except: 

No internal battery option



No Bluetooth



Dynamic range > 115 dB



Fixed output voltage



9 m cable set



No active probes

Advanced Transformer Testing 2012

FRAX product summary          

Light weight Rugged Battery operated (FRAX101) Wireless communication (FRAX101) Accuracy & Dynamic Range/Noise floor Cable Practice Easy-to-use software Export & Import of Data Complies with all SFRA standards and recommendations Only unit that is compatible with all other SFRA instruments Advanced Transformer Testing 2012

Sweep Frequency Response Analysis Application Examples

Advanced Transformer Testing 2012

Time Based Comparison - Example

 



1-phase generator transformer, 400 kV SFRA measurements before and after scheduled maintenance Transformer supposed to be in good condition and ready to be put in service…

Advanced Transformer Testing 2012

Time Based Comparison - Example

”Obvious distorsion” as byDL/T911-2004 standard (missing core ground)

Advanced Transformer Testing 2012

Time Based Comparison – After repair

”Normal” as by DL/T911-2004 standard (core grounding fixed) Advanced Transformer Testing 2012

Type Based Comparisons (twin-units) Some parameters for identifying twin-units: 

Manufacturer



Factory of production



Original customer/technical specifications

 

No refurbishments or repair Same year of production or +/-1 year for large units



Re-order not later than 5 years after reference order



Unit is part of a series order (follow-up of ID numbers)



For multi-unit projects with new design: “reference” transformer should preferably not be one of the first units produced

Advanced Transformer Testing 2012

Type Based Comparison - Example





 



Three 159 MVA, 144 KV single-phase transformers manufactured 1960 (shell-form) Put out of service for maintenance/repair after DGA indication of high temperatures

“Identical” units SFRA testing and comparing the two transformers came out OK indicating that there are no electromechanical changes/problems in the transformers Short tests indicated high resistance in one unit (confirmed by WRM) Advanced Transformer Testing 2012

Type Based Comparison – 3x HV [open]

Advanced Transformer Testing 2012

Type Based Comparison – 3x LV [open]

Advanced Transformer Testing 2012

Type Based Comparison – 3x HV [short]

Advanced Transformer Testing 2012

Design Based Comparisons 

Power transformers are frequently designed in multi-limb assembly. This kind of design can lead to symmetric electrical circuits



Mechanical defects in transformer windings usually generate non-symmetric displacements



Comparing FRA results of separately tested limbs can be an appropriate method for mechanical condition assessment



Pending transformer type and size, the frequency range for design-based comparisons is typically limited to about 1 MHz Advanced Transformer Testing 2012

Design Based Comparison - Example

    



40 MVA, 114/15 kV, manufactured 2006 Taken out of service to be used as spare No known faults No reference FRA measurements from factory SFRA testing, comparing symmetrical phases came out OK The results can be used as fingerprints for future diagnostic tests

Advanced Transformer Testing 2012

Designed Based Comparison – HV [open]

Advanced Transformer Testing 2012

Designed Based Comparison – HV [short]

Advanced Transformer Testing 2012

Designed Based Comparison – LV [open]

Advanced Transformer Testing 2012

Design Based Comparison – After Suspected Fault 







Power transformer, 25MVA, 55/23kV, manufactured 1985 By mistake, the transformer was energized with grounded low voltage side After this the transformer was energized again resulting in tripped CB (Transformer protection worked!) Decision was taken to do diagnostic test

Advanced Transformer Testing 2012

Design Based Comparison – After Suspected Fault 10

100

1000

10000

100000

0 -10 -20 ) s B -30 d ( e s -40 n o p s e -50 R

-60 -70 -80 Freque ncy (Hz)

 

HV-0, LV open A and C phase OK, large deviation on B-phase (shorted turn?) Advanced Transformer Testing 2012

1000000

Design Based Comparison – After Suspected Fault 10

100

1000

10000

100000

1000000

0

-10

) -20 s B d ( e s -30 n o p e s R-40

-50

-60 Frequency (Hz)

 

HV-0 (LV shorted) A and C phase OK, deviation on B-phase

Advanced Transformer Testing 2012

And how did the mid-leg look like…?

Core limb Insulation cylinder

LV winding

Advanced Transformer Testing 2012

Réponse et analyse d’un balayage en fréquence SFRA for testing filter circuits (Line traps)

Advanced Transformer Testing 2012

Réponse et analyse d’un balayage en Typical line trap circuit fréquence



The filter circuit is an RLC network

Advanced Transformer Testing 2012

Réponse et analyse d’un balayage en Measurement principle fréquence

Generator signal

Measurement signal

Attenuation, dB

Phase shift, °

G (dB)

V   20 log10  out   Vin 

Advanced Transformer Testing 2012

Réponse et analyse d’un balayage en fréquence

225 kV line trap



225kV, 850A, 17mH



Verification of cut-off frequency

Advanced Transformer Testing 2012

Réponse et analyse d’un balayage en No capacitors connectedfréquence

0

-10

-20

-30 B e

-40

n g a M

-50

-60

-70

-80

100

k

1

k 10 Frequency (Hz)

k

100

M

1

[A-a1 [open]]

Advanced Transformer Testing 2012

Réponse et analyse d’un balayage en One capacitor connected fréquence

0

-5

-10

-15 B e u -20 n a M

-25

-30

-35

-40

100

k

1

k 10 Frequency (Hz)

k

100

M

1

[C-c1 [open] (2)]

Advanced Transformer Testing 2012

Réponse et analyse d’un balayage en Two capacitors connected fréquence

0

-10

B -20 e u n a M

-30

-40

-50 100

k

1

k 10 Frequency (Hz)

k

100

M

1

[C-c1 [open] (4)]

Advanced Transformer Testing 2012

Sweep Frequency Response Analysis Standards

Advanced Transformer Testing 2012

SFRA Standards and Recommendations 

Frequency Response Analysis on Winding Deformation of Power Transformers, DL/T 911-2004, The Electric Power Industry Standard of People‟s Republic of China



Mechanical-Condition Assessment of Transformer Windings Using Frequency Response Analysis (FRA), CIGRE report 342, 2008



IEEE PC57.149™/D4, Draft Guidefor forOil the Application and Interpretation of Frequency Response Analysis Immersed Transformers, 2011



IEC 60076-18, Power transformers – Part 18: Measurement of frequency response, 2011 (for voting)



Internal standards by transformer manufacturers, e.g. ABB FRA Standard v.5

Advanced Transformer Testing 2012

SFRA Standards – Short summary Standard

Dynamic range

Accuracy

Signal cable grounding

Self-test

EPIS PRC DL/T 911

-100 to +20 dB

± 1 dB @ -80 dB

Wire, shortest length to transformer core grounding

not stated

CIGRE brochure 342

-100 to +20 dB (measurement range)

± 1 dB @ -100 dB

Shortest braid principle

Test circuit with a known response Shorted leads test

"Sufficient dynamic range to IEEE PC57.149/D9 (draft)

accommodate most transformer test objects"

IEC 60076-18

-90 to +10 dB min 6 dB S/N (-96 to +10 dB)

ABB FRA Technical Standard

Better than -100 to +40 dB (measurement range)

"Calibrated to an

Grounded at both ends.

acceptable standard"

"Precise, repeatable and documented" procedure

Standard test object with a known response

± 0.3 dB @ -40 dB ± 1 dB @ -80 dB

Three methods described: Standard test object with 1. Same as CIGRE (2 MHz) a known response 2. "Old" method (500 kHz) Shorted/open leads test 3. "Inversed CIGRE" (2 MHz)

± 1 dB @ -100 dB

Condition control of FRA device, including coaxial cables, is strongly recommended

Shortest braid principle

Advanced Transformer Testing 2012

Instrumentation  

Frequency range – All major brands are OK Dynamic range 





Accuracy 



First transformer circuit resonance gives typically a -90 dB response. Smaller transformers may have a first response at -100 dB or lower Note that CIGRE recommends measurement range down to -100 dB. This implies a “dynamic range”/noise floor at about -120 dB. ± 1 dB at -100 dB fulfills all standards.

All FRAX instruments fulfills all standards for dynamic range and accuracy!

Advanced Transformer Testing 2012

Why you need at least -100 dB...

Westinghouse 40 MVA, Dyn1, 115/14 kV, HV [open]

Advanced Transformer Testing 2012

Measurement voltage and internal noise Measurement voltage and internal noise/dynamic range for common SFRA test sets 20.00

0.00

-20.00

1 -40.00

-60.00

0 -1 X A R F

0 5 -1 X A R F

9 -9 X A R F

A 5 9 1 4 P H

A 5 9 3 4 P H

0 0 0 1 5 M e l b o D

0 0 2 5 M e l b o D

0 0 0 3 5 M e l b o D

0 0 0 4 5 M e l b o D

r e l z y a n A R F

0 1 3 5 x te t e T

Dynamic range Measuring voltage p-p

-80.00

-100.00

-120.00

-140.00

Advanced Transformer Testing 2012

Measurement range comparison

-100 dB measurement (CIGRE standard) Black – FRAX-101 Red – Other SFRA

Internal noise (open) measurements Green – FRAX-101 Blue – Other SFRA

Advanced Transformer Testing 2012

Cable grounding practice  

The “shortest wire/braid”-practice is now generally accepted All European equipment manufacturers have adapted to this practice

Recommended grounding practice (CIGRE)

Bad grounding practice (CIGRE)

Advanced Transformer Testing 2012

Instrumentation verification 

Verification of instrument including cables • Measurement with “open” cables (at clamp) should give a response close to the noise floor of the instrument (at lower frequencies, pending cable length) • Measurement with “shorted” cables (at clamp) should give close to 0 dB response (pending cable length) • External test device with known response (FTB-101 included in FRAX standard kit)



Calibration at recommended interval • FRAX; Minimum every 3 years, calibration set and SW available

Advanced Transformer Testing 2012

Field Verification Unit

Field verification unit with known frequency response is recommended in CIGRE and other standards to verify instrument and cables before starting the test Advanced Transformer Testing 2012

FRAX - Benchmarking

Advanced Transformer Testing 2012

Measurement voltage and internal noise Measurement voltage and internal noise/dynamic range for common SFRA test sets 20.00

0.00

-20.00

1 -40.00

-60.00

0 -1 X A R F

0 5 -1 X A R F

9 -9 X A R F

A 5 9 1 4 P H

A 5 9 3 4 P H

0 0 0 1 5 M e l b o D

0 0 2 5 M e l b o D

0 0 0 3 5 M e l b o D

0 0 0 4 5 M e l b o D

r e l z y a n A R F

0 1 3 5 x te t e T

Dynamic range Measuring voltage p-p

-80.00

-100.00

-120.00

-140.00

Advanced Transformer Testing 2012

FRAX 101 has the highest dynamic range, -130 dB!

Westinghouse 40 MVA, Dyn1, 115/14 kV, HV [open]

Advanced Transformer Testing 2012

Internal noise (dynamic range)

Internal noise (open) measurements Green – FRAX-101 Red – Other SFRA 1 Blue – Other SFRA 2

Advanced Transformer Testing 2012

Measurement range

-100 dB measurement (CIGRE standard) Black – FRAX-101 Red – Other SFRA 1

Internal noise (open) measurements Green – FRAX-101 Blue – Other SFRA 1

Advanced Transformer Testing 2012

Field verification test (FTB101)

Blue = Other brand Black = FRAX101

Advanced Transformer Testing 2012

Dynamic Range – Comparison (1)

End-to-end open Green – FRAX-101 Blue – Other SFRA 1

Neutral to capacitive tap Red – FRAX-101 Black – Other SFRA 1

Advanced Transformer Testing 2012

Dynamic Range – Comparison (2)

H1 – H2 (open) measurements Red – FRAX-101 Grey – Other SFRA

Advanced Transformer Testing 2012

Dynamic Range – Measurements at first resonance

Blue – FRAX Purple – Other SFRA 3 Red – Other SFRA 1

Jiri Velek, “CEPS SFRA Market Research”, October 2006

Advanced Transformer Testing 2012

FRAX - Compatibility

Advanced Transformer Testing 2012

FRAX vs Doble (1) 5 MVA, Dyn, H2-H3 measurement

Blue – Doble Orange – Frax

Advanced Transformer Testing 2012 158

FRAX vs Doble (2) YNd, H1-H0 measurement

Blue – Doble Orange – Frax

Advanced Transformer Testing 2012 159

FRAX vs Tettex and Doble H1-H0 (short) measurement

Blue – FRAX Purple – Tettex Red – Doble (Doble high frequency deviation due to different grounding practice)

Jiri Velek, “CEPS SFRA Market Research”, October 2006

Advanced Transformer Testing 2012 160

Frax-101, 2.8 vs 10 V meas voltage

2.8 V

10 V

Advanced Transformer Testing 2012 161

Frax (2.8V) vs FRAnalyzer

Omicron (2.8 V)

PAX, 2.8 V

Advanced Transformer Testing 2012 162

Summary - conclusions 







SFRA is an established methodology for detecting electromechanical changes in power transformers Collecting reference curves on all mission critical transformers is an investment! Ensure repeatability by selecting good instruments and using standardized measurement practices Select FRAX from Megger, the ultimate Frequency Response Analyzer!

Advanced Transformer Testing 2012

Additional IEC slides

Advanced Transformer Testing 2012

IEC connection picture A

B C

D

50 Vin

B C D

Ω

Vout

50

Ω

reference lead response lead earth connection

Advanced Transformer Testing 2012

IEC – FRA condition assessment

Some examples of conditions that FRA can be used to assess are: 

Damage following a through fault or other high current event (including short-circuit testing),

 

Damage following a tap-changer fault, Damage during transportation, and



Damage following a seismic event.



Damage caused by short-circuit tests

Advanced Transformer Testing 2012

IEC – Test object conditions – Factory and site 

The test object shall be fully assembled as for service complete with all bushings.



Liquid or gas filled transformers and reactors shall be filled with liquid or gas of the same type as in service conditions



Busbars or other system or test connections shall be removed and there shall be no connections to the test object other than those being used for the specific measurement



If internal current transformers are installed but not connected to a protection or measurement system, the secondary terminals shall be shorted and earthed.



The core and frame to tank connections shall be complete and the tank shall be connected to earth.



Measurements should be performed at ambient temperature

Advanced Transformer Testing 2012

IEC – Test object conditions – Site 

The test object shall be disconnected from the associated electrical system at all winding terminals and made safe for testing.



Line, neutral and any tertiary line connections shall be disconnected but tank earth, auxiliary equipment and current transformer service connections shall remain connected.



In the case where two connections to one corner of a delta winding are brought out, the transformer shall be measured with the delta closed (see also 4.4.4).



In instances where it is impossible to connect directly to the terminal, then the connection details shall be recorded with the measurement data since the additional bus bars connected to the terminals may impact on the measurement results.

Advanced Transformer Testing 2012

IEC – Instrument performance check 1.

Connect the source, reference and response channels of the instrument together using suitable low loss leads, check that the measured amplitude ratio is 0 dB  0,3 dB across the whole frequency range. Connect the source and reference channels together and leave the response terminal open circuit, check that the measured amplitude ratio is less than -90 dB across the whole frequency range.

2.

The performance of the instrument may be checked by measuring the response of a known test object (test box) and checking that the measured amplitude ratio matches the expected response of the test object. The test object shall have a frequency response that covers the attenuation range -10 dB to -80 dB.

3.

The correct operation of the instrument may be checked using a performance check procedure provided by the instrument manufacturer. This performance check procedure shall verify that the instrument is operating at least over an attenuation range of -10 dB to -80 dB over the whole frequency range. Advanced Transformer Testing 2012

IEC – Measurement connection check 

Measurement connection and earthing •



The continuity of the main and earth connections shall be checked at the instrument end of the coaxial cable before the measurement is made. Poor connections can cause significant measurement errors, attention must be paid to the continuity of the main and earth connections. In particular, connections to bolts or flanges shall be verified to ensure that there is a good connection to the winding or the test object tank.

Zero-check measurement •

If specified, a zero-check measurement shall be carried out as an additional measurement. Before measurements commence, all the measuring shall be connected to one of the highest voltage terminals and earthed usingleads the normal method. A measurement is then made which will indicate the frequency response of the measurement circuit alone. The zero check measurement shall also be repeated on other voltage terminals if specified.

• 

The zero-check measurement can provide useful information as to the highest frequency that can be relied upon for interpretation of the measurement.

Repeatability check •

On completion of the standard measurements the measurement leads and earth connections shall be disconnected and then the first measurement shall be repeated and recorded.

Advanced Transformer Testing 2012

IEC – Measurement configuration – with OLTC 

For transformers and reactors with an on-load tap-changer (OLTC), the standard measurement on the tapped winding shall be • on the tap-position with the highest number of effective turns in circuit, and • on the tap-position with the tap winding out of circuit.



Other windings with a fixed number of turns shall be measured on the tap-position for the highest number of effective turns in the tap winding.



Additional measurements may be specified at other tappositions.



For neutral or change-over positions, the direction of movement of the tap-changer shall be in the lowering voltage direction unless otherwise specified. The direction of movement (raise or lower) shall be recorded.

Advanced Transformer Testing 2012

IEC – Measurement configuration – Auto with OLTC 

For auto-transformers with a line-end tap-changer, the standard measurements shall be: • on the series winding with the minimum number of actual turns of the tap-winding in circuit (the tapping for the highest LV voltage for a linear potentiometer type tapping arrangement or the change-over position for a reversing type tapping arrangement, or the tapping for the lowest LV voltage in a linear separate winding tapping arrangement), • on the common winding with the maximum number of effective turns of the tap-winding in circuit (the tapping for the highest LV voltage), and • on the common winding with the minimum number of actual turns of the tap-winding in circuit (the tapping for the lowest LV voltage for a linear potentiometer or separate winding type tapping arrangement or the change-over position for a reversing type tapping arrangement).

Advanced Transformer Testing 2012

IEC – Measurement configuration – DECT and OLTC 

For transformers with both an OLTC and a de-energised tapchanger (DETC), the DETC shall be in the service position if specified or otherwise the nominal position for the measurements at the OLTC positions described in this Clause.



For transformers fitted with a DETC, baseline measurements shall also be made on each position of the DETC with the



OLTC (if fitted) on the position for maximum effective turns. It is not recommended that the position of a DETC on a transformer that has been in service is changed in order to make a frequency response measurement, the measurement should be made on the „as found‟ DETC tap position. It is therefore necessary to make sufficient baseline measurements to ensure that baseline data is available for any likely service („as found‟) position of the DETC. Advanced Transformer Testing 2012

IEC – Frequency range and measurement points 

The lowest frequency measurement shall be at or below 20 Hz.



The minimum highest frequency measurement for test objects with highest voltage > 72,5 kV shall be 1 MHz.



The minimum highest frequency measurement for test objects with highest voltage of ≤ 72,5 kV shall be 2 MHz.



Below 100 Hz, measurements shall be made at intervals not exceeding 10 Hz Above 100 Hz, a minimum of 200 measurements approximately evenly spaced on either a linear or logarithmic scale shall be made in each decade of frequency.



Advanced Transformer Testing 2012

IEC – Measurement equipment specification (1) 

Dynamic range • The minimum dynamic range of the measuring instrument shall be +10 dB to -90 dB of the maximum output signal level of the voltage source at a minimum signal to noise ratio of 6 dB over the whole frequency range.



Amplitude measurement accuracy • The accuracy of the measurement of the ratio between Vin and Vout shall be better than  0,3 dB for all ratios between +10 dB and -40 dB and  1 dB for all ratios between -40 dB and -80 dB over the whole frequency range.



Phase measurement accuracy • The accuracy of the measurement of the phase difference between Vin and Vout shall be better than  1º at signal ratios between +10 dB and 40 dB, over the whole frequency range.



Frequency range • The minimum frequency range shall be 20 Hz to 2 MHz.

Advanced Transformer Testing 2012

IEC – Measurement equipment specification (2) 

Frequency accuracy • The accuracy of the frequency (as reported in the measurement record) shall be better than  0,1 % over the whole frequency range.



Measurement resolution bandwidth • For measurements below 100 Hz, the maximum measurement resolution bandwidth (between -3 dB points) shall be 10 Hz; above 100 Hz, it shall be less than 10 % of the measurement frequency or half the interval between adjacent measuring frequencies whichever is less.



Operating temperature range • The instrument shall operate within the accuracy and other requirements over a temperature range of 0 to +45 °C.



Smoothing of recorded data • The output data recorded to fulfil the requirements of this standard shall not be smoothed by any method that uses adjacent frequency measurements, but averaging or other techniques to reduce noise using multiple measurements at a particular frequency or using measurements within the measurement resolution bandwidth for the particular measurement frequency are acceptable.

Advanced Transformer Testing 2012

IEC – Measurement records 

Test object identifier



Date



Time



Test object manufacturer



Test object serial number



Measuring equipment



The peak voltage used for the measurement.



Reference terminal



Response terminal

 

Terminals connected together Earthed terminals



OLTC tap positions, current and previous



DETC position



Test object temperature



Fluid filled, yes or no.



Comments, free text to be used to state the condition of the test object



Measurement result (the frequency in Hz, the amplitude in dB and the phase in degrees) for each measurement frequency

Advanced Transformer Testing 2012

IEC – Test records (1) 

Test object data • •

Manufacturer

• • •

Manufacturer‟s serial number Highest continuous rated power of each winding

• • •

Short circuit impedance between each pair of windings

• •

Number of phases (single or three-phase) Transformer or reactor type (e.g. GSU, phase shifter, transmission, distribution, furnace, industrial, railway, shunt, series, etc.)



Transformer configuration (e.g. auto, double wound, buried tertiary, etc.)



Transformer or reactor construction (e.g core form, shell form), number of legs (3 or 5-leg), winding type, etc.



Load tap-changer (OLTC): number of taps, range and configuration (linear, reversing, coarse-fine, line-end, neutral-end, etc.)



De-Energized Tap Changer (DETC): number of positions, range, configuration, etc.

Year of manufacture

Rated voltage for each windings Rated frequency Vector group, winding configuration / arrangement

Advanced Transformer Testing 2012

IEC – Test records (2) 

Organisation owning the test object • •







Test object identification (as given by the owner if any) Any other information that may influence the result of the measurement

Location data • •

Location (e.g. site name, test field, harbour, etc.)

• •

Notable surrounding conditions (e.g. live overhead line or energized busbars nearby)

Bay identification reference if applicable Any other special features

Measuring equipment data • • • •

Working principle of device (sweep or impulse)

• •

Calibration date

Equipment name and model number Manufacturer Equipment serial number Any other special features of the equipment

Test organization data •

Company



Operator

Advanced Transformer Testing 2012

IEC – Test records (3) 

Measurement set-up data • Remanence of the core: was the measurement carried out immediately following a resistance or switching impulse test, or was it deliberately demagnetised? • Whether the tank was earthed • Measurement type (e.g. open circuit, short circuit, etc.) • Length of braids used to ground the cable shields • Length of coaxial cables



Reason for measurement (e.g. routine, retest, troubleshooting, commissioning new transformer, commissioning used transformer, protection tripping, recommissioning, acceptance testing, warranty testing, bushing replacement, OLTC maintenance, fault operation, etc.)



Additional information



Photographs of the test object as measured showing the position of the bushings and connections

Advanced Transformer Testing 2012

IEC – Measurement lead connction. Method 1 

The central conductor of the coaxial measurement leads shall be connected directly to the test object terminal using the shortest possible length of unshielded conductor.



The shortest possible connection between the screen of the measuring lead andshall the flange at the base of the bushing be made using braid. A specific clamp arrangement or similar is required to make the earth connection as short as possible



In general this method may be expected to give repeatable measurements up to 2 MHz

A B C D E F G H I J

connection clamp unshielded length to be made as short as possible measurement cable shield central conductor shortest braid bushing earth connection earth clamp tank smallest loop

Advanced Transformer Testing 2012

IEC – Measurement lead connction. Method 2 

Method 2 is identical to method 1 except that the earth connection from the measurement leads to the flange at the base of the terminal bushing may be made using a fixed length wire or braid, so that the connection is not the shortest possible.



The position of the excess earth conductor length in relation to the bushing may affect amplitude (dB) measurements above 500 kHz and resonant frequencies above 1 MHz

Advanced Transformer Testing 2012

IEC – Measurement lead connction. Method 3 

In a method 3 connection, the screen of the coaxial measurement lead is connected directly to the test object tank at the base of the bushing and an unshielded conductor is used to connect the central conductor to the terminal at the top of the bushing.



If a method 3 connection is used for the response lead connection only then the results are comparable with method 1. This connection may be the most practical option if an external shunt (measuring impedance) is used



If a common conductor is used for the signal and reference connections then the conductor is included in the measurement which will therefore differ from a method 1 measurement

A B C D E F G

connection clamp shortest braid or wire measurement cable shield central conductor earth clamp tank smallest loop

Advanced Transformer Testing 2012

IEC – Frequency response comparison 

In order to interpret a measured frequency response, a comparison is made between • The measured response and a previous baseline measurement (time based comparison) • With the response measured on a twin transformer, a transformer made to the same drawings from the same manufacturer (type based comparisons). Careful attention should be given when using responses from sister transformers (transformers with the same specification but with possible differences in winding configuration the same manufacturer) comparison. and changes even to thefrom transformer design may havefor been introducedImprovements by a manufacturer over a period of time to outwardly similar units and this may cause different frequency responses

• For three-phase transformers, comparisons can also be made between the responses of the individual phases (design based comparisons). When comparing phases of the same transformer quite significant differences are considered “normal” and could be due to different internal lead lengths, different winding inter-connections and different proximities of the phases to the tank and the other phases

Advanced Transformer Testing 2012

IEC – Comparisons of frequency responses The comparison of frequency response measurements is used to identify the possibility of problems in the transformer. Problems are indicated by the following criteria: 

Changes in the overall shape of the frequency response;



Changes in the number of resonances (maxima) and antiresonances (minima);



Shifts in the position of the resonant frequencies.

The confidence in the identification of a problem in the transformer based on the above criteria will depend on the magnitude of the change when compared with the level of change to be expected for the type of comparison being made (baseline, twin, sister or phase).

Advanced Transformer Testing 2012

IEC – Typical frequency response

Influence regions: A core B interaction between windings C winding structure D measurement setup and lead (including earthing connection)

Advanced Transformer Testing 2012

IEC – Influence of tertiary delta connections 10 0 -10 -20

B d-30 , e d u-40 itl p-50 m A

-60 -70

delta open delta cl ose d

-80 -90 1 10

10

2

10

3

4

10 Frequency, Hz

10

5

10

6

Advanced Transformer Testing 2012

IEC – Influence of star neutral connections 0 -5 -10 B-15 d , e-20 d u litp-25 m A-30

-35 neutrals open neutrals jo ined

-40 -45 1 10

10

2

10

3

4

10 Frequency, Hz

10

5

10

6

Advanced Transformer Testing 2012

IEC – Influence of measurment direction (example) 0 -10 -20 B-30 d , e-40 d tu i l -50 p m A-60

-70 HV to N N to HV

-80 -90 1 10

10

2

10

3

4

10 Frequency, Hz

10

5

10

6

Advanced Transformer Testing 2012

IEC – Influence of oil -20 -30 -40 B d , e-50 d tu li -60 p m A

-70 Full oil Without oil

-80 -90 1 10

10

2

10

3

4

10 Frequency, Hz

10

5

10

6

Advanced Transformer Testing 2012

IEC – Influence of DC injection (magnetization) 10 0 -10 B-20 d , e-30 d tu i l -40 p m A-50

-60 Before DC After DC

-70 -80 1 10

10

2

10

3

4

10 Frequency, Hz

10

5

10

6

Advanced Transformer Testing 2012

IEC – Influence of bushings 0

-20 B d , e d u t li p m A

-40

-60

-80

oil/SF 6/air bushing oil/SF 6 bushing

-100 1 10

10

2

10

3

4

10 Frequency, Hz

10

5

10

Advanced Transformer Testing 2012

6

IEC – Influence of temperature (minor efftect) -20 -30 B-40 d , e d u t -50 lip m A-60

32 C

-70

80 C -80 1 10

10

2

10

3

4

10 Frequency, Hz

10

5

10

6

Advanced Transformer Testing 2012

IEC – Bad measurements… -40 -60 B d -80 , e d tu li -100 p m A

-120

HV to N (good measurement ) HV to N with bad co nnection at N Hv to N with bad connection at HV

-140 -160 1 10

10

2

10

3

4

10 Frequency, Hz

10

5

10

Advanced Transformer Testing 2012

6

Additional IEEE slides

Advanced Transformer Testing 2012

IEEE – When to perform FRA measurements 

Factory short-circuit testing



Installation or relocation



After a significant through-fault event



As part of routine diagnostic measurement protocol



After a transformer alarm (i.e. sudden pressure, gas detector, Buchholz)



After a major change in on-line diagnostic condition (i.e. a sudden increase in combustible gas, etc.)



After a change in electrical test conditions (i.e. a change in winding capacitance)



System Modeling Purposes

Advanced Transformer Testing 2012

IEEE – FRA base line measurement 

Quality assurance



Required by Customer Specification



To provide a standard of comparison for future diagnostic FRA measurements

Advanced Transformer Testing 2012

IEEE – FRA base line measurement 

Quality assurance



Required by Customer Specification



To provide a standard of comparison for future diagnostic FRA measurements

Advanced Transformer Testing 2012

IEEE – FRA diagnostic application 

Verification that no damage occurred during a short circuit test



Relocation and commissioning validation



Post incident verification : lightning, external throughfault, internal short circuit, seismic event etc

 

Routine diagnostic purposes Condition assessment of older transformers



Evaluation of used or spare transformers

Advanced Transformer Testing 2012

IEEE – SFRA instrument specification 

Calibrated to an acceptable standard.



The output power of the excitation source should provide adequate power over the entire frequency range to allow for consistent measurement of the transfer function across the frequency range.



The test set should be capable of measuring sufficient dynamic range, over the frequency range in order to accommodate most transformer test objects



The test set should be capable of collecting a minimum of 200 measurements per decade, either spaced linearly or logarithmically.



The test system (set and leads) should provide a known and constant characteristic impedance. 

A three lead system, signal, reference and test, should be used to reduce effect of leads in the measurement.



Test leads should be coaxial cables of the same length, within 1 cm, and less then 30 m (100 ft) long. Shielded test leads should have the ability to be grounded at either end.



Both the Magnitude and Phase of the measured transfer function should be presented. Advanced Transformer Testing 2012

IEEE – Measurement type; Open circuit 



An open circuit measurement is made from one end of a winding to another with all other terminals floating. The Open Circuit test can be applied to both single phase and three phase transformers. Open Circuit tests generally fall into five winding categories: High Voltage, Low Voltage, Tertiary, Series, and Common. The Series and Common categories are applied to autotransformers. Open Circuit tests are primarily influenced by the core properties at or around the fundamental power frequency. The Open Circuit tests can be used in conjunction with exciting current tests in determining failure modes that affect the magnetic circuit of the transformer.

Advanced Transformer Testing 2012

IEEE – Measurement type; Short circuit 

The short circuit measurement is made from one end of a high voltage winding to another while the associated low voltage winding is shorted. For repeatability purposes, it is recommended that all low voltage windings are shorted on three phase transformers to create a three phase equivalent short circuit model. This ensures all three phase are similarly shorted to give consistent impedance. Any available neutral connections should not be included in the shorting process.



The Short Circuit test isolates the winding impedance from the core effects properties at or around the fundamental power frequency. The Short Circuit results should produce similar and comparable diagnostic information as seen in both leakage reactance and DC winding resistance measurements.

Advanced Transformer Testing 2012

IEEE – Measurement type; Capacitive inter-winding 

The capacitive inter-winding measurement also known as the inter-winding measurement is performed between two electrically isolated windings. A Capacitive Inter-Winding measurement is made from one end of a winding and measuring the signal through one of the terminals of another winding, with all other terminals floating. Capacitive InterWinding measurements . These measurements exhibit a are highcapacitive impedanceinatnature low frequencies (
View more...

Comments

Copyright ©2017 KUPDF Inc.
SUPPORT KUPDF