Section.21.(QCS.electrical)

Share Embed Donate


Short Description

Qatar Construction Specification (Electrical)...

Description

QCS 2007

Section 21

Part 1

General Provisions for Electrical Installation

Page 1

1.

GENERAL PROVISIONS FOR ELECTRICAL INSTALLATION.....................2

1.1.1 1.1.2 1.1.3 1.1.4 1.1.5 1.1.6 1.1.7 1.1.8 1.1.9 1.1.10 1.1.11 1.1.12 1.1.13 1.1.14 1.1.15 1.1.16 1.1.17 1.1.18 1.1.19 1.1.20 1.1.21 1.1.22 1.1.23 1.1.24 1.1.25 1.1.26 1.1.27

Scope Regulations Existing Services Contract Drawings Shop Drawings Progress Drawings As built drawings Builders Work Programme Equipment and Materials Approval Fire and Safety Precautions Protection Quality of Staff/Personnel Climatic Conditions Samples Quality of Materials Equipment Duties and Ratings Workmanship Labels/Circuit Lists/Cable Identification Segregation of Services Electricity Supply Polarity Safety Interlocks Spare Parts Protection of Excavation Supply of materials Special Requirements

Qatar General Organization for Standards and Metrology QCS 2007, 3rd Edition

2 2 3 3 3 5 5 5 5 6 6 7 7 8 8 9 9 9 10 11 12 12 13 13 14 14 15

QCS 2007

Section 21

Part 1

General Provisions for Electrical Installation

Page 2

1.

GENERAL PROVISIONS FOR ELECTRICAL INSTALLATION

1.1.1

Scope

1

The Electrical Installation Contractor, herein referred to as the 'Contractor' within this part and all other Section 21 parts of this specifications shall carry out all electrical works complete in accordance with the requirements of the Project Documentation.

2

The scope of work shall include but not be limited to: (a)

(b) (c) (d) (e) (f) (g) (h)

the supply and installation of all services, equipment, components, accessories and fittings required for the operation of the facility to the extent specified and detailed on the Drawings and Specifications including 400 days maintenance after provisional handover builder's work in connection with the Electrical Installations, including supply, necessary inserts and sleeves any work which can be reasonably inferred as necessary for the safe, satisfactory operation of each system, whether such work is specified or shown on drawings or not the supply and installation of cables, conduits, boxes and termination points, for the motors, starters, controls and the like for the Process Equipment, Heating, Ventilation and Air-conditioning and Plumbing services arranging for installation of permanent Electrical supply by the Qatar General Electricity and Water Corporation (QGEWC), including submission of all necessary documents to the QGEWC, and carrying all necessary approvals and obtaining consumption meters attending upon the Supply Authority installing mains power supply and carrying out primary and secondary injection tests arranging and carrying out all necessary approvals with Q-TEL for the Telephone System arranging and carrying out all necessary approvals with the Qatar Civil Defence Department for the Fire Alarm System, extinguishing and protection systems.

1.1.2

Regulations

1

All supplies and services offered in response to this specification shall conform to the latest standards.

2

The design, equipment and installation requirements shall comply with the standards and recommendations laid down by the following : (a) (b) (c) (d) (e) (f) (g)

3

Regulations for Electrical Installations as issued by the Qatar General Electricity and Water Corporation (QGEWC) Qatar Regulations for Electrical Installations as issued by the Institution of Electrical Engineers (I.E.E.), London (for points not included in QGEWC Regulations) Recommendations for Lighting Installations as issued by QGEWC and the Chartered Institute of Building Services, London Standards relating to Electrical Installations and equipment as issued by International Electrotechnical Commission (I.E.C.) and British Standards Institute (BSI) Regulations for telephone system installation as issued by Q-TEL National Electrical Code issued by National Fire Protection Association (NFPA), Boston, U.S.A Rules of the Qatar Civil Defence Department for Fire Alarm Installations.

Where two or more applicable standards and/or the Specifications are in conflict, the most stringent shall apply.

Qatar General Organization for Standards and Metrology QCS 2007, 3rd Edition

QCS 2007

Section 21

Part 1

General Provisions for Electrical Installation

Page 3

1.1.3

Existing Services

1

The contractor is deemed to have visited and inspected the site to familiarise himself with the existing site conditions and services at tender stage.

2

The contractor shall obtain the existing services record drawings from QGEWC and various utility services departments (i.e. Q-TEL, CDD etc).

3

Co-ordination between shop drawings, work on site and existing services shall be carried out by the Contractor.

4

The Contractor shall be fully responsible for any damages to the existing services including repairs, and penalties imposed by the concerned parties etc and for removing any site obstacles such as underground cables, pipes, civil works etc. which is obstructing his work on site.

5

The Contractor shall also be responsible for liaison with QGEWC, Q-TEL and all other government utility departments to disconnect or divert the existing services supply to the existing site prior to demolishing.

1.1.4

Contract Drawings

1

The indication and/or description of any item on the Drawings or in the Specification, unless otherwise specifically stated, implies an instruction to supply and fix such items.

2

Notes on Drawings referring to individual items of work take precedence over the Specification.

3

Drawings show the general run of cables, raceways, etc. and the approximate location of equipment and utilities; symbols and schematic diagrams are of no dimensional significance. Obtain from the Engineer dimensions not shown on, or which cannot be determined from Drawings. Do not scale drawings to obtain locations.

4

Notify the Engineer of conflicting requirements. Where departures from the drawings are deemed necessary, details of such departure and reasons thereupon shall be submitted to the Engineer for approval.

5

No such departure shall be made without prior written approval of the Engineer.

1.1.5

Shop Drawings

1

The term 'shop drawings' includes fabrication, erection, layout and setting out drawings; manufacturer's standard drawings, schedules; descriptive literature, illustrations, catalogues and brochures; performance and test data; wiring and control diagrams and other drawings and descriptive data pertaining to materials, equipment, raceway systems, control systems and methods of construction as required to show that materials, equipment and systems and position thereof, conform to the Contract Documents. The term 'manufactured' applies to standard units usually mass produced. The term 'fabricated' means items specifically assembled or made out of selected materials to meet individual design requirements.

2

Shop drawings shall establish actual detail of all manufactured or fabricated items, indicate proper relation to adjoining work, amplify design details of electrical equipment in proper relation to physical spaces in the structure, and incorporate minor changes of design or construction to suit actual conditions.

3

The Contractor shall submit for approval, and obtain in due time to conform to the Contract Program, all shop and installation drawings based on the design drawings approved by the QGEWC and all other relevant Municipality and Government Authorities.

Qatar General Organization for Standards and Metrology QCS 2007, 3rd Edition

QCS 2007

Section 21

Part 1

General Provisions for Electrical Installation

Page 4

4

The Contractor, immediately after being awarded the said Contract, shall prepare and submit shop drawings. Shop drawings shall be submitted with such promptness as to cause no delay in his own work nor to any other Contractor. No extensions of time will be granted because of failure to have shop drawings submitted in ample time to allow for processing, in accordance with the submittals schedule outlined in Section 9, Part 1, Clause 1.1.4.

5

Provide shop drawings, to a scale not smaller than the corresponding layout drawings, showing the following and obtain approval before commencing work: (a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k)

exact runs and sizes of conduits, ducts, cables, cable trays and trunking layout drawings for each separate electrical installation showing the actual locations of points, suitably identified, the locations of switchgears, switchboards, motor control centres and distribution boards, details and types of fittings plans showing the equipment assembly, space requirements, clearances and locations for cable entrances and anchor bolts elevations showing all parts, devices, components and nameplates, positions and arrangements of the equipment. Show as many elevations as necessary to clearly depict component and device arrangements schedules of points, indicating how the various outlets are connected to the distribution boards, size of circuit wiring, the rating of the protective device and the type and size of appliance of fitting schematic diagram of connections of distribution boards, and equipment to main switchboards showing sizes of feeders, etc schematic and elementary wiring diagrams, of each unit of each equipment, showing numbered terminal points, numbered wires and numbered interconnections to other equipment and remote devices connection wiring diagrams, of each unit of each equipment, showing numbered terminal points, numbered wires and numbered interconnections to other equipment and remote devices complete catalogue information of all parts and components of electrical equipment all cable routings and layouts for the different electrical services, feeders and branch circuits showing routes, sizes and types of cables any other data necessary for the proper maintenance of the installations.

6

Drawings shall be ISO standard size A1. Lettering shall be stencilled. Shop drawings and samples shall be properly identified with the name of the Project, the Contractor, the SubContractor and the date, and signed by Contractors Authorised Engineers.

7

Final co-ordination of electrical works with mechanical, structural and architectural work shall be carried out from complete shop drawings and sufficient time shall be allowed for coordination and checking of shop drawings and calculations after shop drawings are submitted.

8

Individual shop drawings shall be submitted following the distribution of the co-ordination drawings and shall bear a stamp indicating that the work has been co-ordinated with other trades.

9

The Engineer's review and approval of shop drawings submitted by and approved by the Contractor is for general conformance with the design concept and information given in the Contract Documents and shall not relieve the Contractor from responsibility for any deviations from the requirements of the Contract Documents. The Engineer's review and approval shall not be construed as a complete check nor shall it relieve the Contractor from responsibility for error of any sort in shop drawings or schedules, or from the necessity of furnishing any work required by the Contract Documents which may have been omitted on the shop drawings. The Engineer's review and approval of a component item shall not indicate review and approval of the complete assembly in which it functions.

10

The Engineer or the supervising consultant shall forward electrical drawings and specifications which are to be submitted for approval to QGEWC, when appropriate. However, it shall be the Contractors responsibility to obtain written approval from QGEWC for all such drawings and specifications appertaining to the work carried out under the contract.

Qatar General Organization for Standards and Metrology QCS 2007, 3rd Edition

QCS 2007

Section 21

Part 1

General Provisions for Electrical Installation

Page 5

QGEWC approvals may take a considerable time to obtain and the contractor should make allowance for this and be available for liaising with and pursuing approvals with QGEWC. 1.1.6

Progress Drawings

1

Provide and keep on the job at all times, one complete and separate set of blackline prints of the electrical work on which shall be clearly, neatly and accurately noted, promptly as the work progresses, all architectural and electrical changes, revisions and additions to the work. Whatever work is installed otherwise than as shown on the Contract Drawings, such changes shall be noted.

2

Indicate daily progress on these prints by colouring in the various conduit, ducts, trunking, cable trays, fixtures, apparatus and associated installation works erected.

1.1.7

As built drawings

1

The contractor shall provide the as built drawings, as approved by the engineers, in DXF format or AutoCAD DWG format, either in floppy diskettes or in CD-ROM, as per the Project Documentation requirement. The drawings shall be submitted not later than 2 months after completion of the Project, or putting into operation, whichever is earlier. An addition, 3 sets of hard copy of all relevant drawings, which will be required for operation and maintenance, shall be supplied in bound book forms immediately after the commissioning of the Project. The quality of these drawings shall be consistent with the standard of QGEWC. Diary sheets for Work completed shall not be authorised until such records have been presented to the Engineer and accepted.

2

The contractor shall supply, 3 sets of all operation and maintenance manuals in original, from the manufacturer in bound book forms, at least 2 weeks prior to commissioning of the equipment. These shall also be supplied, in computer diskettes, based on popular Microsoft window based publishing software programmes, along with the as built drawings as mentioned above, as specified in the Project Documentation.

1.1.8

Builders Work

1

Lay electrical works in advance of pouring concrete slabs and construction of walls. Obtain Engineer's approval before commencing builder's work in connection with electrical installation. Related co-ordinated shop-drawings shall be submitted for approval as per the related clause 1.1.5 of this section. Materials approval shall be obtained as per procedure detailed in clause 1.1.9 below. The contractor shall make it certain that drawings properly coordinated with other works are submitted immediately after signing of the contract and approval of drawings and the materials are obtained at least one month prior to the commencement date of the construction.

2

Check with other trades to ensure equipment and material can be installed in space provided.

3

Provide other trades with information necessary for them to execute their work.

4

Details on drawings which are specific regarding dimensions and locations, are for information purposes. Co-ordinate with other trades to ensure work can be installed as indicated.

1.1.9

Programme

1

The Contractor shall produce a work programme based on CPM or Bar-chart form indicating the time required for various operations to complete the Project in time. The following points shall be highlighted in the programme: (a) (b) (c)

mobilisation drawings/submittals approvals

Qatar General Organization for Standards and Metrology QCS 2007, 3rd Edition

QCS 2007 (d) (e) (f) (g) (h) (i) (j) (k)

Section 21

Part 1

General Provisions for Electrical Installation

Page 6

equipment deliveries including delivery periods from supply sources external to the State of Qatar first fix cabling main/sub-main distribution equipment second fix fixing of light fittings testing commissioning and handing over.

2

The Contractor is responsible for all liaison with QGEWC in respect of programming the installation and commissioning of complete electrical system. The Contractor shall ensure that QGEWC are at all times kept informed of the current progress of the electrical works on site and that his approved electricity supply subcontractor programs the cable laying works in the specified sequence in accordance with the approved programme.

1.1.10

Equipment and Materials Approval

1

Approval of materials and equipment shall be based on latest manufacturer's published data.

2

Complete and detailed information of all materials and equipment to be incorporated in the work shall be submitted. Submit detailed description and specifications, catalogues cuts, installation data, diagrams, dimensions, controls and any other data required to demonstrate compliance with the Contract Documents. Each item submitted shall be referenced to the applicable paragraph in the Specification.

3

At the request of the Engineer, submit a sample of any equipment or material for further study before approval. Where samples are required by the Engineer, the period required to obtain the sample will be taken into account when scheduling approvals.

4

Only approved materials shall be employed at the site. All materials installed which are not approved shall be removed and reinstated by approved ones.

5

Time periods for equipment and materials approvals shall be as outlined in Section 9, Part 1, Clause 1.1.4.

1.1.11

Fire and Safety Precautions

1

Establish from Architectural Drawings where fire and smoke barriers exist, and make adequate provision of fire and smoke barriers in and around trunking, conduits, cables, etc., where they pass through floors and fire rated walls, and where protection systems are installed pack space between wiring and sleeve full with Fire Retardant Material and seal with caulking.

2

The Contractor shall ensure that this work is carried out such that the integrity of any such fire barrier is properly maintained where pierced by electrical services.

3

For each switchboard the Contractor shall supply the following equipment: (a) (b) (c)

4

1 no. electrical grade rubber mat to BS 921 1000 mm wide extending the full length of the switchboard 1 no. pair of electrical grade rubber gloves to BS 697. The hand glove should have the date of test stamped on it. 1 no. notice in English and Arabic advising treatment for a person suffering from electrical shock.

The contractor shall put the notice for electrical shock treatment in details with sketches and instructions as per standard procedures. The notice shall comply with the requirement of the QGEWC in content and format. However, this should include the following as a minimum,

Qatar General Organization for Standards and Metrology QCS 2007, 3rd Edition

QCS 2007

Section 21

Part 1

General Provisions for Electrical Installation

Page 7

ACT IMMEDIATELY (i)

Safeguard Yourself

(ii)

Switch off current or break electric circuit

(iii)

Use or stand on some dry non-conducting material to remove the CASUALTY from cable or source of electricity.

(iv)

Start artificial respiration and call for Medical Aid

TREATMENT FOR ELECTRIC SHOCK ARTIFICIAL RESPIRATION (KISS OF LIFE, MOUTH TO MOUTH METHOD) (v)

Lay the casualty on back and if possible on a table

(vi)

Kneel or stand near to the casualty’s head

(vii)

Remove any obstruction from the mouth

(viii)

Support the nape of the neck and press top of the head so that it is tilted backwards

(ix)

Open your mouth and take a deep breath, pinch the casualty’s nostrils with your fingers. Seal your lips round his mouth and blow into his lungs until the chest rises.

(x)

Remove your mouth and watch the chest falls

(xi)

Repeat and continue inflation at your natural rate of breathing. Continue to give artificial respiration until natural breathing is restored or until the medical aid arrives

(xii)

When the casualty is breathing, place in recovery position, lying and resting on the side. Remain with and watch casualty closely.

1.1.12

Protection

1

The Contractor shall be responsible for his work and equipment until finally inspected, tested and accepted. Materials and equipment which are not immediately installed after delivery to site shall be stored carefully. Close open ends of work with temporary covers or plugs during construction to prevent entry of obstructing material.

2

Protect work and material of other trades from damage that might be caused by his work or workmen and make good damage thus caused.

3

Protect exposed live equipment during construction for personnel safety.

4

Shield and mark live parts "LIVE 240 VOLTS" or with appropriate voltage in English and Arabic.

5

Arrange for installation of temporary doors for room containing electrical distribution equipment. Keep these doors locked except when under direct supervision of an electrician.

1.1.13

Quality of Staff/Personnel

1

The electrical services installation shall be carried out in a professional manner by experienced and qualified personnel.

2

Electrical contractor shall be to the classifications required by QGEWC and shall carry a valid licence.

3

Prior to the commencement of works the Contractor shall notify the Engineer of his intended site staffing levels.

Qatar General Organization for Standards and Metrology QCS 2007, 3rd Edition

QCS 2007

Section 21

Part 1

General Provisions for Electrical Installation

Page 8

4

The Contractor shall appoint one graduate Electrical Engineer full time with 5 years experience in similar works and qualified staff/personnel for the supervision of the Electrical Installation Works.

5

The name, qualifications and experience of the nominated engineers shall be submitted to the engineer for approval within 15 days of the receipt of the order to commence the works.

6

An Electrical Foreman of 10 years experience in similar projects should be full time available on site for direct follow up and implementation of the electrical works.

7

Qualified and Experienced Electricians shall be available on site to carry out the works in accordance with the programme.

8

The Engineer reserves the right to require the Contractor to provide information and documentation as may be necessary to establish the validity of any individual persons proficiency and effect their removal from site should they prove to be unsatisfactory.

1.1.14

Climatic Conditions

1

The climate in Qatar in the summer months is hot and humid and a humidity of 100 % at 30 °C has been recorded. (a) (b)

violent sand and dust storms of several hours duration occur and even on comparatively still days, fine dust is carried in suspension in the atmosphere. all apparatus and equipment shall, therefore, be so designed and constructed that they operate satisfactorily and without any deleterious effect for prolonged and continuous periods in the conditions stated above and at the following ambient temperature conditions: (i) maximum sun radiation temperature in summer 84 °C (ii) maximum ambient temperature in summer 52 °C (iii) average max. ambient temperature in summer 45 °C (iv) minimum ambient temperature in winter 0 °C (v) the altitude of Qatar may be taken as sea level.

2

The temperatures quoted above make no allowance for heat generated from equipment itself or from any other equipment in the vicinity

3

The capacity and ratings of all electrical equipment and materials given are, unless otherwise indicated, for Qatar climatic conditions. Provide the basis of the derating factors applied in each case

4

Where specific sizes are indicated e.g. cable sizes, due allowances have been made in the design for the climatic conditions of Qatar and derating has been applied

5

Where no ratings or sizes are indicated for components and other accessories, supply equipment which will give trouble free service in the ambient conditions stated above.

1.1.15

Samples

1

The term ‘samples’ includes natural materials, fabricated items, equipment, devices, appliances, or parts thereof as specified and other samples as may be required to determine whether kind, quality, construction, workmanship, finish, colour and other characteristics of materials conform to requirements of the Contract Documents.

2

Samples shall establish kind, quality and other required characteristics of various parts of the work. Indicate details of construction, dimensions, capacities, weights and electrical performance characteristic of equipment or material.

3

Samples and sample board should be prepared and identified by the manufacturer and stamped/engraved with make, type, Cat No. and size marking should be indelible and legible.

Qatar General Organization for Standards and Metrology QCS 2007, 3rd Edition

QCS 2007

Section 21

Part 1

General Provisions for Electrical Installation

Page 9

1.1.16

Quality of Materials

1

Manufacturers shall provide their standard guarantees for products furnished under this Contract. However, such guarantees shall be in addition to and not in lieu of all other liabilities which manufacturers and the Contractor may have by law or by other provisions of the Contract Documents.

2

All materials, items of equipment and workmanship furnished under this Contract shall carry standard warranty against all defects in materials and workmanship. Any faults due to defective or improper material, equipment, workmanship or Contractor's design which develop shall be made good, forthwith, by and at the expense of the Contractor, including all other damage done to areas, materials and other systems resulting from this failure.

3

Guarantee that all elements of the systems are of sufficient capacity to meet the specified performance requirements as set forth herein or as indicated.

4

Upon receipt of notice from the Engineer, of failure of any part of system or equipment during the period of maintenance, the affected parts shall be replaced.

1.1.17

Equipment Duties and Ratings

1

Power ratings shown for the proposed equipment are in accordance with the best information available to the Engineer and are to be considered as minimum ratings. In the event equipment items proposed by the Contractor should require motors with different power rating than shown, it shall be the Contractor’s responsibility to furnish circuit breaker, starting equipment, feeder and branch circuits, conduits, and accessories etc. as required to comply with the electrical code and prevent excessive voltage drop without added cost to the Client.

2

Where equipment to be furnished is installed in an existing enclosure or adjacent to existing equipment, the Contractor shall field check the dimensions of existing equipment, location of conduits, etc., and shall familiarise himself with all existing conditions and difficulties to be encountered in performing such work.

3

Degree of protection for all electrical equipment shall be as follows: IP 54, for indoor equipment IP 55, for outdoor equipment IP 68, for submersible equipment

4

All external equipment to be of metallic construction.

5

The equipment shall be located generally as indicated on the drawings and the contractor shall ensure that the equipment is suitably constructed to permit installation as shown. The equipment shall where necessary be constructed in modular form to permit access into the buildings and facilitate ease of erection at site.

6

The equipment arrangements and single line diagram are for guidance only and show a practical arrangement that would be acceptable. The contractor may propose an alternative arrangement which meets the requirements of the specification.

7

All equipment performing similar duties shall be of a single type and make and be fully interchangeable in order to limit the stock of spare parts required. This is to apply particularly to such items as motors, switchgear, instruments, controls, relays, etc.

1.1.18

Workmanship

1

The entire work provided in this specification shall be constructed and finished in every respect in a workmanlike and substantial manner. The Contractor shall provide the system in accordance with the best trade practice and to the satisfaction of the Engineer.

Qatar General Organization for Standards and Metrology QCS 2007, 3rd Edition

QCS 2007

Section 21

Part 1

General Provisions for Electrical Installation

Page 10

2

Keep others fully informed as to the shape, size and position of all openings required for apparatus and give full information sufficiently in advance of the work so that all openings may be built in advance. Provide and install all sleeves, supports, etc., hereinafter specified or required.

3

Obtain detailed information from the manufacturers of apparatus as to the proper method of installing and connecting same. Obtain all information from others which may be necessary to facilitate work and the completion of the whole Project.

4

Provide the services of an experienced foreman, who shall be continuously in charge of the erection of the electrical work, together with all necessary skilled workmen, helpers and labourers, required to properly unload, transfer, erect and connect up, adjust, start, operate and test the system.

5

Before installing any work, verify that it does not interfere with clearance required for other work. Notice of adverse conditions shall be forwarded in writing to the Engineer before any work in question is installed. If notification is not made, and work installed causes interference with the contemplated design, make such changes in his work as directed by the Engineer to permit the installation of all work of the Project, at no additional cost to the Client.

6

Raceways shall be run as straight and direct as possible in general forming right angles with or parallel with walls or piping and neatly spaced, with risers erected plumb and true, maintain a clearance of at least 25 mm between finished coverings and adjoining work. Approved ceiling height shall be obtained from Architectural Drawings.

7

All equipment and accessories shall operate without objectionable noise or vibration. Should operation of any of the equipment or systems produce noise or vibration which is, in the opinion of the Engineer objectionable, make change in equipment and do all work necessary to eliminate the objectionable noise or vibration at no additional cost to the Client.

8

Wherever possible services shall not cross expansion joints. Where this is unavoidable the services shall accommodate the design movement without damage, by use of approved expansion couplings/flexible conduit arrangement.

9

All MV, HV and EHV works shall be carried out by a contractor or sub-contractor pre-qualified and approved by QGEWC. Proof of such approval shall be required in writing prior to the works commencing on site and the name of any sub–contractor to be used shall be entered in the relevant form of tender when the tender is submitted. All cable jointers to be used on the Contract shall be required to undertake and pass a trade test conducted by QGEWC at the Contractor’s expense.

1.1.19

Labels/Circuit Lists/Cable Identification

1

For substations, switchgears, switchboards, motor control centres and panel boards: (a)

2

For Distribution Boards and Circuit Breakers: (a) (b)

3

engraved lamacoid name plates, black with minimum 6 mm high white lettering.

where individually enclosed or in substations, switchgears, switchboards, motor control centres and panel boards without doors : engraved lamacoid nameplates, black with 3 mm high white lettering. in panel boards with doors : directories mounted inside transparent plastic covers in metal frames.

Wiring Identification: (a) (b) (c)

identify wiring with permanent indelible, identifying markings, either numbered or coloured, heat shrinkable tube or ferrules, on both ends of phase conductors of feeders and branch circuit wiring. maintain phase sequence and colour coding throughout colour code to standards above as specified elsewhere

Qatar General Organization for Standards and Metrology QCS 2007, 3rd Edition

QCS 2007 (d) 4

(c) (d)

(b) (c)

colour code conduits and metallic sheathed cables code with plastic sleeve or paint end points where conduit or cable enters wall, ceiling or floor and also at 15 m intervals along its length. colours to be 25 mm wide prime colour and 20 mm wide auxiliary colour to standards above number code, per Circuit Schedule, all feeder and branch circuit cables at both connection points and in manholes, handholes, pull-boxes and junction boxes with fibre or non-ferrous metal tags, fastened with non-ferrous wire.

for Device Plates of local toggle switches, toggle switch type motor starters, pilot lights and the like, whose junction is not readily apparent : plates to be engraved with 3 mm high letters describing equipment controlled or indicated.

phase identification letters shall be stamped into the metal of the busbars of each phase of the main buses in each substation, switchgear, switchboards, motor control centre and panel board in addition to colour identification Letters shall be visible without disassembling current carrying supporting elements. busbars shall be sleeved for phase identification by using high temperature grade heat shrinkable coloured PVC sleeving throughout its length. In no circumstances will any kind of wrapping tape be accepted on busbars.

where switchboard rooms, cable chambers, metal screened spaces and the like contain electric power cables, bus bars or equipment operating at voltages exceeding 600 V : enamelled sheet metal, red on white, reading "Danger - High Voltage".

For Rooms: (a)

9

use colour coded wires in communication cables, matched throughout system.

For Doors: (a)

8

Page 11

For Busbars: (a)

7

General Provisions for Electrical Installation

Device Plates: (a)

6

Part 1

Conduit and Cable Identification: (a) (b)

5

Section 21

to switchboard rooms, electric closets, metal screened spaces assigned to electrical equipment, and the like : enamelled sheet metal, red on white, reading "Electrical Equipment Room - No Storage Permitted".

Languages: (a)

nameplates with directional, operational or warning labels shall be in Arabic and English.

1.1.20

Segregation of Services

1

Electrical services shall be segregated as specified throughout the installation to obviate the following; (a) (b) (c) (d) (e) (f)

electrical interference from one circuit to another a fault on one circuit affecting another unnecessary fire damage difficulties in circuit identification voltage limits for general safety difficulties in removal and/or maintenance.

2

All raceways shall be kept clear of other services except where intentionally earthed or bonded. Generally, raceways shall be kept 150 mm away from and above hot water and 75 mm away from other services.

3

Unless specifically indicated otherwise, normal, emergency, low voltage cables and wiring shall be segregated throughout the installation generally in the following manner:

Qatar General Organization for Standards and Metrology QCS 2007, 3rd Edition

QCS 2007 (a)

(b)

4

Section 21

Part 1

General Provisions for Electrical Installation

Page 12

armoured and sheathed cables: Where more than one tray has been specified or is necessary to accommodate the number of cables on a run, where practical, segregation shall be achieved by dedicating each tray to either normal or emergency services. Where normal and emergency cables have to run together in trays, ducts or trenches, they shall be formed in two groups, one normal and one emergency insulated conductors: Insulated conductor circuits shall, where possible, be segregated throughout by enclosing in separate conduits, trunking or trunking compartments.

Fire Alarms: (a)

fire alarm cables shall be segregated from other services throughout and be either armoured and sheathed cable, or insulated conductors enclosed in conduit or trunking, as indicated on the drawings.

1.1.21

Electricity Supply

1

The Supply Authority will make available, at the incoming terminals of each Main Switchboard (Medium Voltage Panel) a 3 phase + Neutral, 4 wire, 415 V, 50 Hz supply of adequate capacity and having the following tolerances: (a) (b)

voltage frequency

±6% ± 0.1 Hz (short term ± 0.15 Hz for a duration of only a few seconds)

2

Phase rotation of supply to BS 158.

3

Neutral: Solidly earthed at transformer location

4

Earthing system: TNS

5

Obtain fault level and fault duration time from the Supply Authority (QGEWC).

6

Obtain confirmation from the Supply Authority of the size and number of cables they will provide to Main Switchboards. Allow for adequate and appropriate cable glands, lugs and boxes.

7

After inspection and approval of the contractor’s installation, QGEWC will permit energisation of the feeder cables to the installation.

8

QGEWC will only inspect the contractor's installation and permit energisation of the power supply after receiving a written request to do so from the contractor.

9

The contractor will be responsible for any delay caused by omission to make the request in good time.

10

The contractor shall provide a generator of adequate capacity to carry out all precommissioning tests. Per-commissioning tests may be carried out using mains electricity if this is available.

1.1.22

Polarity

1

The polarity of all apparatus used for the Works specified shall be arranged as follows when apparatus is viewed from the front: (a) (b)

for two pole apparatus the phase or “live” pole at the top (or left hand side) and the '“neutral or earthed” pole at the bottom (or right hand side). On plug and socket outlets the polarity shall conform to BS 196, BS 546, or BS 1363 as appropriate for three or four pole apparatus the phases in order red, yellow, blue and neutral reading from top to bottom or left to right in the case of vertical and horizontal layouts respectively.

Qatar General Organization for Standards and Metrology QCS 2007, 3rd Edition

QCS 2007

Section 21

Part 1

General Provisions for Electrical Installation

Page 13

2

All cables shall be so connected between main switchboards, distribution boards, plant and accessories so that the correct sequence of phase colours is preserved throughout the system.

3

All cable cores shall be identified with phase colours. Where more than one phase is incorporated on a common system in one room then the live cores shall be red, yellow, blue, as appropriate, and fittings and switch accessories shall be permanently labelled and segregated in accordance with I.E.E. Regulations.

1.1.23

Safety Interlocks

1

A complete system of interlocks and safety devices shall be provided as necessary for the safe and continuous operation of the plant in order to provide for the following: (a) (b) (c)

safety of personnel engaged on operation and maintenance of the plant correct sequence of operation of the plant during start up and shut down safety of the plant when operating under normal or emergency conditions.

2

Interlocks shall be preventive and not corrective

3

The Contractor shall be responsible for the preparation of interlocking schemes for the approval of the Engineer.

4

Locks for interlocking purposes shall be of the figure lock type.

5

No spare or master key shall be provided, unless specified.

6

Device items are to be arranged to ensure that there is no danger of interchange with existing locks on other units.

1.1.24

Spare Parts

1

General: (a) (b) is (c)

2

Main Low Tension Boards: (a) (b) (c) (d)

3

2 % spare moulded case circuit breakers of all different frame sizes, but in any case not less than 2 nos. circuit breaker of each size 5 % spare indicating lamps for each indicating lamp in the switchgear one set of tools required for switchgear maintenance provide complete spare parts as recommended by the manufacturer for different sizes of ACB.

Switchboards, Motor Control Centres and Distribution Boards: (a) (b) (c) (d) (e)

4

provide sufficient spare parts as follows. Submit to the Engineer a list of all spare parts to be required for a further two years operation from the date of issue of the Maintenance Certificate spare parts required include but not necessarily limited to those listed below, provided specified in the Project Documentation or where quantities for each item or equipment recommended by the manufacturer spare parts to be delivered to central stores.

5 % spare combination magnetic motor starters 5 % spare circuit breakers for each rating of each MCCB 5 % spare HRC fuses for each rating 5 % spare of load break switch (isolators) of each size 5 % spare of current operated ELCB of each size

Disconnecting Switches: (a)

5 % spare switch of each size.

Qatar General Organization for Standards and Metrology QCS 2007, 3rd Edition

QCS 2007 5

(b) (c) (d)

General Provisions for Electrical Installation

Page 14

plug fuses - furnish ten percent (10%) of the number of each size and type of fuses installed, but in any case not less than six fuses of each sizes wall switches - provide five percent (5%) of the number of each size and type of wall switch installed socket outlets - provide five percent (5%) of the number of each size and type installed lamps - provide five percent (5%) lamps of each size and type for indicating panels and pilot lights installed for different systems.

Lighting Fixtures: (a)

7

Part 1

Circuit Accessories: (a)

6

Section 21

for lighting fixtures provide the following spare parts: (i) 2 % of the total quantity of each type of lighting fixture. This quantity shall not be less than one fixture of each type (ii) additional diffusers for 5 % of the total quantity of each type of lighting fixture provided with acrylic, plastic or glass enclosures. Diffusers shall be identical to those of the installed fixtures. This quantity shall not be less than two diffusers of each type (iii) 10 % spare lamps of each wattage of different type (iv) 5 % of the total quantity of controlgear (ballast) of each type and size but in no case less than (6) ballast of each size and type.

Emergency Generating Sets: (a)

complete itemised list of different spares to be included and priced by the tenderers. For emergency generator, furnish by the generator supplier to maintain it for two years.

8

The tenderer shall submit with his offer detail prices of the spare parts he is required to provide under the Contract indicating the quantity and the unit rate of each item.

1.1.25

Protection of Excavation

1

The Contractor shall comply with all requirements of the Police Department for marking, lighting and protecting excavations. It is the responsibility of the Contractor to ascertain the requirements of Police Department and to comply fully with these requirements. No additional payments will be authorised under any circumstances for marking, lighting or protecting excavations.

2

Where carriageway works and road crossings are performed the Contractor shall provide steel plates of sufficient size and quality to permit the safe passage of traffic and the plate shall be so placed (if necessary fixed) to permit reasonable traffic flow.

3

All doorways, gates and entrances shall be kept clear with full access. Where excavations impede pedestrian access, crossings boards shall be provided. Crossing boards shall be 1250mm wide with a hand rail on both sides 1 metre high and guard rails on both sides at vehicular access to premises etc. Ducts will not be installed at entrances to premises unless instructed by the Engineer.

4

Materials excavated shall be placed so as to prevent nuisance or damage. Where this is not possible, the material shall be removed from site and returned for backfilling on completion of cable laying at the Contractor’s expense. In cases where the excavated material is not to be used for backfilling trenches it must be removed from site on the same day as it is excavated. Surplus material shall only be disposed of at Government approved sites. At the time of Contract award the Contractor shall contact the Ministry of Municipal Affairs and Agriculture to ascertain the approved sites and route.

1.1.26

Supply of materials

1

Where materials are to be supplied by the Contractor, the following shall apply: (a)

Materials shall be ordered in accordance with the Specifications issued by QGEWC.

Qatar General Organization for Standards and Metrology QCS 2007, 3rd Edition

QCS 2007 (b) (c)

Section 21

Part 1

General Provisions for Electrical Installation

Page 15

Specifications and details of the proposed supplier shall be submitted to QGEWC before a firm order being placed. On delivery of materials from outside of Qatar, QGEWC inspectors shall be given the opportunity to inspect the materials prior to their use.

1.1.27

Special Requirements

1

The Contractor shall consult the public utility authorities not less than one month before it is proposed to commence work to ascertain whether any underground installations will be affected by the proposed work, in which event the Contractor shall make all necessary arrangements with the public utility authorities to safeguard the installation.

2

The Contractor shall give at least one week’s notice in writing to the public utility authorities of the dates upon which it is intended to operate plant or equipment or carry out any work for which permission has been given in writing by the public utility authorities: such operations of work shall only be carried out in the presence of the public utility authorities unless notice has been obtained in writing from the public utility authorities that they do not require to be present.

3

The public utility authorities may require work to be executed on their installation during the period of the Contract: the Contractor shall afford all facilities to the public utility authorities’ contractors or workmen until their diversion work is complete. The Contractor shall co ordinate the work of the public utility authorities and his own activities and when necessary shall amend his programme of working to suit all requirements of the department in connection with their diversion work and shall keep the Engineer informed of all arrangements made.

4

The Contractor shall locate and mark with suitable posts all the public utility authorities underground installations that are within the area of the Works and shall ensure that such markers are maintained in their correct positions at all times; the Contractor shall advise the public utility authorities of any installation not found where shown on the Drawings, or found but not shown or found damaged or subsequently damaged. END OF PART

Qatar General Organization for Standards and Metrology QCS 2007, 3rd Edition

QCS 2007

Section 21

Part 2

MV Factory Built Assemblies (FBA’s)

Page 1

2.

MV FACTORY BUILT ASSEMBLIES (FBA’S) ............................................... 2

2.1

GENERAL ...................................................................................................... 2

2.1.1 2.1.2 2.1.3 2.1.4 2.1.5

Scope General Reference References Submissions Quality Assurance

2.2

PRODUCTS ................................................................................................... 4

2.2.1 2.2.2 2.2.3 2.2.4

Cubicle Switchboards Motor Control Centres MCCB Panel Boards Distribution Boards

2.3

INSTALLATION............................................................................................ 20

2.3.1 2.3.2

General Earth Bonding

Qatar General Organization for Standards and Metrology QCS 2007, 3rd Edition

2 2 2 3 3 4 16 19 20 20 21

QCS 2007

Section 21

Part 2

MV Factory Built Assemblies (FBA’s)

Page 2

2.

MV FACTORY BUILT ASSEMBLIES (FBA’S)

2.1

GENERAL

2.1.1

Scope

1

This Part shall include all labour, materials and accessories for the complete performance of all MV Cubicle Switchboards, Main Switchboards, Submain Switchboards, Motor Control Centres, MCCB panel boards, distribution boards in accordance with the Specifications and Drawings.

2

Related Parts and Sections are as follows: This Section Part 1 Part 6 Part 7 Part 8 Part 9 Part 16

General Provisions for Electrical Installation Cables and Small Wiring Conduits Trunking Cable Trays Power factor correction capacitors

3

Factory built assemblies of switchgear and control gear (MCCs) shall be suitable for operation under the ambient and service conditions specified. They shall comply with all local regulations and requirements. The contractor shall be responsible for making himself aware of any special conditions which apply to the installation.

4

The Contractor shall be responsible for ensuring that all details relating to the construction and protection systems are fully compliant with the latest requirements of QGEWC and construction shall not commence until QGEWC approval has been obtained. The Contractor shall provided all protection relays, interlocks and devices deemed necessary by QGEWC.

2.1.2

General Reference

1

The work of this Part is integral with the whole of the Project Documentation and is not intended to be interpreted outside that context.

2

Co-ordinate the work with all other services affecting the work of this Part.

2.1.3

References

1

The following standards are referred to in this Section: BS 88, BS EN 60127 BS 142 BS 159, BS EN 60439-2 BS 7354, BS EN 60439, BS EN 6094 BS 7626, IEC 185 BS 4794, Pt. 2 IEC 337-2 BS 37 Pt. 1 BS 89, IEC 51 BS 5685, IEC 521 BS EN 60529, IEC 529 BS 4752, IEC 157-1, BS EN 60439 BS EN 60947-3, IEC 408 BS EN 60947-4 IEC-1 & 1A BS 5472, BS EN 60439 BS 6231 BS EN 60439, IEC 439

Qatar General Organization for Standards and Metrology QCS 2007, 3rd Edition

Cartridge fuses Electrical protective relays Busbar and connection Electrical power switchgear Current transformers Control devices Electricity meters general Direct acting indicating electrical measuring instruments Electric meters Degree of protection of enclosures Switchgear and control-gear Air break switches Contactors Low voltage switchgear and control-gear PVC insulated cables for switchgear Factory built assemblies LV

QCS 2007

Section 21

Part 2

MV Factory Built Assemblies (FBA’s)

BS EN 60073

Basic and safety principles for man-machine interface, marking and identification coding principles for indicators and actuators

2.1.4

Submissions

1

Shop Drawings: All submittals in accordance with Part 1: (a)

2

Page 3

submit dimensional drawings of all the switchgears, switchboards and motor control centres, including sections and elevations, showing the following: (i) arrangement of all components, instruments, indication and dimensions of all busbars (ii) positions and method of fixing cables and boxes (iii) location of terminal blocks (iv) single line diagram of the circuits showing the rating of all components, the type and size of the incoming and outgoing feeders (v) schematic and elementary wiring diagrams, for each control unit, showing numbered terminal points, numbered wires and numbered interconnections to other equipment and remote devices (vi) connection wiring diagrams, for each control unit, showing numbered terminal points, numbered wires and numbered interconnections to other equipment and remote devices (vii) complete catalogue information for all components (viii) a complete list of parts, with prices, that would be necessary to maintain and/or modify the equipment (ix) other relevant data.

Product Data: (a) (b) (c)

full specifications of the enclosures and the components of the switchgear, switchboards and motor control centres, with relevant sheets of manufacturer’s catalogues type test certificates of all components and whole assembled MCCs from an internationally recognised testing authority or from independent testing lab in accordance with IEC 439 confirmation that the switchgears, switchboards and motor control centres comply with the relevant specification as mentioned in this Section.

2.1.5

Quality Assurance

1

The switchgear manufacturer must have a previous record of satisfactory service in Qatar for at least 3 years.

2

All new and refurbished Motor Control Centres shall be subject to routine tests to detect faults and workmanship in accordance with BSEN 60439-1 clause 8.3.1. Standard assemblies and/or products used within the assembly shall also be subject to tests at the manufacture’s works who supplied the products. Routine tests shall include: (a)

(b) (c)

(d)

the effectiveness of mechanical actuating elements, interlock, locks etc. shall be checked. The conductors and cables shall be checked for proper laying and the devices for proper mounting. A visual inspection is also necessary to ensure that the prescribed degree of protection, creepage and clearances are maintained. all termination types and connections especially screwed connections shall be checked for adequate contact. factory built assemblies such as motor control centres for pumping stations and treatment plants, unit mounted stand alone control panels etc. shall be inspected thoroughly and tested at the manufacturer's works to verify the electrical operation in accordance with the control philosophy by simulating the site conditions. the manufacturer shall submit the process flow diagram together with cause and effects for the assemblies involving complex control schemes and complicated interlock, sequence controls, etc.

Qatar General Organization for Standards and Metrology QCS 2007, 3rd Edition

QCS 2007 (e) (f) (g)

(h) (i) (j) (k)

Section 21

Part 2

PRODUCTS

2.2.1

Cubicle Switchboards

1

General:

(b)

(c)

(d) (e)

(f) (g) (h)

Page 4

the tests so conducted on the assembly at manufacturer's works shall be repeated as integrated tests on site with all field devices and interfaces present. the manufacturer shall submit in advance, the testing procedure to the Engineer for approval prior to conducting the tests. Motor Control Centres shall be subjected to dielectric tests as described in BSEN 60439-1 clause 8.3.2. All electrical components of the assembly shall be connected for the test, excluding those designed for lower test voltage and currents e.g. measuring instruments. anti-interference capacitors installed between the live and exposed conductive parts shall be capable of withstanding the test voltage without being disconnected from the circuit. the protective measures with regard to protection against direct and indirect contact shall be checked as per BSEN 60439-1 clause 8.3.3 Motor Control Centres shall be Totally Type Tested to BSEN 60439-1 clause 8.2. ASTA/KEMA type test certificate together with test report including reports/terms under (k) shall be submitted to the Engineer for approval. following is a list of verifications and tests to be performed on a Totally Type Tested Assembly according to Table 7 clause 8.2 of BSEN 60439-1. A test report shall be submitted to the Engineer (i) temperature rise limits (ii) dielectric properties (iii) short circuit withstand strength (iv) effectiveness of protective circuit • effective connection between the exposed conductive parts of the assembly and the protective circuits. • short circuit withstand strength of the protective circuit (v) clearances and creepage distances (vi) mechanical operation (vii) degree of protection

2.2

(a)

MV Factory Built Assemblies (FBA’s)

M.V. cubicle switchboards shall be of indoor construction, purpose made, floor standing, totally enclosed, cellular cubicle type, dust protected, vermin proof and of clean and modern appearance containing the main components shown on the Drawings and/or specified the switchboards shall be fabricated, assembled, wired, checked, tested and co-ordinated at the factory by one manufacturer using the same make for all internal switchgear components and shall be constructed in accordance with BS EN 60439 or IEC 439 the switchboard shall be equipped with Air Circuit Breakers, moulded case circuit breakers, relays, instruments, transformers, ancillary devices necessary for operation protection or measurement purposes and Auto Transfer Switch with Manual by pass arrangement as indicated on the Drawings the normal components, fittings and accessories required for safe and proper operation of switchgear shall be provided, whether specifically mentioned herein or not to withstand thermal and mechanical stresses set up by short circuit conditions in accordance with the fault through current of the feeding transformer. In general fault breaking capacities for main switchboards shall be as stipulated in QGEWC regulations spare ways indicated on the Single Line Diagram shall be fully equipped all FBA’s should have a manufacturers name plate indicating busbar rating, fault current, year of manufacture, serial no., etc. the MCCs shall be designed, manufactured and tested to IP54 in compliance with the requirements of IEC 60529.

Qatar General Organization for Standards and Metrology QCS 2007, 3rd Edition

QCS 2007 (i)

(j)

(k) (l) (m)

(n) (o) (p)

(q) (r)

(s)

(t) (u)

(v) (w) (x)

Section 21

Part 2

MV Factory Built Assemblies (FBA’s)

Page 5

equipment such as Variable Frequency Drives (VFD), UPS and others with large watt loss, if specifically mentioned in the particular requirements to be included in the MCC, that require forced ventilation by employing external fan and louvers as recommended by the manufacturer, the degree of protection (IP rating) shall be reduced to IP43 from IP54. the MCCs shall be designed and type tested to withstand a fault current of 44 kA for 3 seconds symmetrical. Additionally the MCCs shall be type tested for safe containment of an internal arcing fault, which will check the capability of the steel structure to withstand the forces associated with the arc, and ensure safety and integrity of the assembly for continuous use. This is to establish that the enclosure of MCCs together with internal partitions and/or barriers withstands the pressure and temperature arising from internal arcing with short circuit current and thus provides protection for persons in front of or within the close proximity of the MCCs in the event of internal arcing. the test certificate must show that the neutral bar has been tested with the full fault current and for the full time specified. separate test certificates for incoming sections will be acceptable. the MCCs shall be designed and equipped with properly sized circuit breakers and/or fused disconnect switches, having a minimum factor of safety of capacity 1.5 taking into account the connected load and its diversity, with provision for selective shortcircuit co-ordination so that faults are cleared without disturbing other circuits. the MCCs shall be designed for indoor installation except where specified for outdoor installation. the MCCs shall be designed to operate satisfactorily in an ambient air temperature of +50° C and RH exceeding 90%. unless otherwise specified temperature up to +70° C and RH up to 100% shall apply during transport, storage and installation. Equipment subjected to these extreme service conditions without being operated shall not suffer irreversible damage when operated under normal specified conditions. the altitude of the site installation shall not exceed 100 meters. the MCCs shall normally be located indoors in service conditions as specified above. However some parts of the MCCs such as sensors, field instruments and pilot devices may require installation in highly corrosive gaseous environments. Gases such as hydrogen sulfide and methane may adversely affect the functions of the components and devices. In such application environments, special measure shall be adopted to prevent corrosion and the subsequent rise in resistance leading to temporary or permanent interruption in control or power circuits. the temperature rise in MCCs shall not be allowed to damage the components, connectors, wires, terminals etc. With the equipment in normal service condition, no live part shall become subjected to high temperature causing overheating that increases the risk of internal arcing accidents. extreme care shall be taken while designing the MCCs to ensure external surface temperature is maintained within the specified limits. the clearances and creepage distances in the MCCs shall be based on rated impulse withstand voltage in accordance with BS EN 60439-1 to ensure that the equipment designed is capable of withstanding the specified voltage without failure under specified test conditions. the equipped MCC must confirm to the clearance and creepage distances and withstand voltages explicitly by taking into account the specified service conditions. the maximum height of assemblies shall be 2400 mm above the finished floor level. site consideration including safety and maintenance shall be taken into account in the design of assemblies. These considerations shall include: (i) clear floor space of at least 900 mm shall be provided in front of the MCC from the free edge of the doors in the open position. Clear floor space of 900mm shall be provided behind the MCC when the doors are in the open position if the MCC is less than 4000mm long. If the MCC is 4000mm or longer the space provided shall be 1200mm. The clear floor space behind the MCC is not required when a true front access assembly is provided. (ii) in order to provide an unobstructed exit route a clear path of not less than 900 mm shall be provided at each end of the MCC. (iii) provision of sufficient space to allow for doors to open fully without fouling other items of equipment or other open doors.

Qatar General Organization for Standards and Metrology QCS 2007, 3rd Edition

QCS 2007

Section 21 (iv) (v)

2

Part 2

MV Factory Built Assemblies (FBA’s)

Page 6

limiting the size and weight of assembly sections to those imposed by transportation, site access and permitted levels of site floor loading. clear floor space of at least 1000 mm shall be provided from the sides of all MCCs in order to allow possible future extension.

Construction: (a) (b) (c)

(d) (e)

(f) (g) (h)

(i) (j) (k) (l) (m) (n) (o) (p)

unless specified otherwise in the Project Documentation, main switchboards for general purpose indoor uses shall be constructed to comply with the requirements of BS EN 60439-1 (IEC 439) Form 4 Type 3 or Type 7 and conform with GAMBICA. switchboard shall be factory built, totally enclosed, and have provision for rear access. Size, rating arrangements shall be as indicated on the Drawings the switchboard shall consist of standard cubicles assembled together on continuous base channels to form a rigid in line flush fronted free standing continuous switchboard assembly. For small installations where particularly specified, true front access MCCs must be provided. For all other cases front and rear access MCCs must be provided. MCCs shall be constructed such that doors and covers are flush with one another and aligned to a common vertical plane; manufactured out of mild steel coated with Alu Zinc having the following thickness: Plinth/bed frame - 3.00 mm Frames - 2.00 mm Covers and Doors - 2.00 mm Mounting plate - 3.00 mm Gland Plate - 3.00 mm a separate cubicle section shall be provided for the main incoming circuit breaker and cable glands shall be provided for the incoming cables in accordance with the QGEWC regulations. each cubicle shall be divided into segregated busbar section and circuit section. The circuit section shall be further divided into segregated compartments for housing main and emergency circuit breakers and other devices. Access to internal components of any compartment must be feasible by isolating its particular switch. The hinged door shall be mechanically interlocked with the switch in such a manner that the door can be opened only in the ‘OFF’ position the switchboards shall be totally enclosed, all hinged doors, covers shall be gasketed to provide protection against dust cabinet shall have adequate means of lifting and shall be capable of being rolled or moved into the installation position and bolted directly to the floor the switchboards shall be provided with suitable cable glands to suit the type, size and number of cables as indicated on the Drawings. The cable glands or bracket where required shall be adequately mounted inside the switchboard. The switchboards shall be provided with the proper cable fixing clamps and terminal lugs for incoming and outgoing cables as well as earth bonding connections after fabrication, steel work shall be cleaned, zinc sprayed and stove enamelled with one prime coat, two under-coats and one finishing coat, the surface being rubbed down after each coat the finish of all parts shall be entirely suitable for the climatic conditions on site. the equipment shall be finished with at least two coats of undercoat and two coats of high grade acrylic stove enamel or approved equivalent. Cubicle interiors shall be completely painted white, however this is not essential for the rear of the door. any damage caused to the finish during transportation and erection shall be returned to the manufacturer for repair if it cannot be perfectly repaired on site. The exterior shall be green to BS 4800, shade 14E53. all plastic parts used within the assembly shall be of flame-retardant, self extinguishing type and halogen free. MCCs shall have internal separation by means of metallic or non-metallic partitions or barriers. all internal components within the compartment /cubicle shall be provided with the degree of protections to IP 2X as minimum whereas the degree of Protection to IP4X shall be provided to adjacent functional units preventing contact with live parts.

Qatar General Organization for Standards and Metrology QCS 2007, 3rd Edition

QCS 2007 (q)

(r)

(s)

(t)

(u)

(v) (w) (x)

(y)

(z)

(aa) (bb)

(cc) (dd)

(ee) (ff) (gg)

(hh) (ii) (jj)

Section 21

Part 2

MV Factory Built Assemblies (FBA’s)

Page 7

electrical continuity between the exposed conductive parts of MCCs and protective circuits of the installation shall be ensured to provide protection against indirect contact by using protective circuits. the protective circuits throughout the installation shall be so designed that it is impossible to break the protective path with the removal of any component from the MCC. all outgoing circuit’s protective conductors shall have a separate terminal of adequate size duly identified in accordance with the Identification Section explained elsewhere in QCS. MCCs must be designed by giving highest importance to accessibility especially when in service/fully powered, allowing easy viewing for inspection and operation, replacement of fuses and extension of additional functional units etc. floor mounted assembles shall either be provided with an integral plinth or a separate rolled mild steel channel bed frame, at least 50 mm high. Fixing shall be by not less than four holding down bolts per assembly section, located around the periphery of the section. The fixing shall not be visible from outside the section, but shall be readily accessible from within. fixings for wall and pole mounted enclosures shall be provided outside the enclosure. The back of the enclosure shall not be drilled to accept fixings. the type of cubicle construction shall be multi-compartment type unless specified otherwise. compartments containing switchfuses, starters, control sections, distribution boards, busbars, downdroppers and similar equipment shall be fully segregated. There shall be no aperture large enough to admit a 1mm diameter wire between any two adjacent compartments. Each cubicle/compartment shall have its own door. interconnecting cables between adjacent compartments shall not proceed directly from one to the other but shall pass through a vertical wall into a cabling compartment before re-entering. Holes for interconnecting cables shall be of the minimum size necessary. All such holes shall be filled with insulating grommets. all cubicles shall be provided with a means of ensuring that equipment can be adequately isolated for maintenance purposes without interrupting essential loads which may continue to operate whilst maintenance is being undertaken. distribution sections shall be fully insulated to allow safe operation by non-engineering personnel. doors shall be adequately sized to accommodate readily and neatly all mounted equipment, open at least 120 degrees, be rigidly constructed, suitably braced and provided with at least two substantial hinges which shall be captive when the door is closed. Doors shall be provided with stays to prevent over opening. each door shall be provided with non-rusting metalic ‘T’ type handles at least one of, which shall be lockable. the doors shall be fixed to the frame by substantial single knuckle non-rusting type, or internal concealed type hinges. Hinges shall be on the left hand side of the door. Hinges shall not be welded to either the door or frame. Substantial continuous stainless steel type hinges over the whole height of the door may be considered if the manufacturer can provide evidence of long continuous service of this type of hinge on his product. locking combinations shall be provided as specified. Three keys for each key type shall be provided on individual key rings having a nametag showing identify details. where the need of padlocking facilities is identified by the engineer/employer, the padlocks shall be supplied and fitted. equipment shall not be mounted on covers. Covers shall not weigh more than 30 kg, and any cover over 7.5 kg shall be provided with a means of supporting the lower edge when its securing bolts are being inserted or removed. removable back covers shall be provided. each door shall be provided with an internal welded earthing stud, and shall be bonded to the assembly main earth bar. every incomer, starter, feeder, etc. shall have an individual terminal/gland box. Control compartments and small power and lighting distribution boards must also have independent gland boxes but these may be common to more than one circuit.

Qatar General Organization for Standards and Metrology QCS 2007, 3rd Edition

QCS 2007 (kk)

(ll)

(mm)

(nn) (oo) (pp) (qq)

(rr) (ss) (tt) (uu) (vv)

(ww) (xx)

(yy) (zz)

(aaa)

(bbb) (ccc) (ddd) (eee) (fff)

Section 21

Part 2

MV Factory Built Assemblies (FBA’s)

Page 8

terminal/gland boxes may be externally mounted on the rear of the MCC or internal. Terminal/gland boxes shall not inhibit access to or maintenance of any part of the MCC. outgoing main and control cables shall be glanded at the compartment so as to ensure a full earth screen to each compartment and shall also be glanded at plinth level to make the complete MCC vermin-proof. Compartment gland plates shall be a minimum of 300mm above the plinth level gland plate. gasket material used for sealing panel doors and covers and for door mounted instruments shall be of highest quality and should not be subject to deterioration by temperature, UV, hydrogen sulphide and methane. doors and covers giving access to potentially live conductors shall be provided with prominent warning labels, in English and Arabic. doors on outdoor assemblies shall be retained in the open position by the provision of adequately fixed stays. each cubicle/compartment shall be provided with a removable steel components mounting plate located clear of the cubicle rear panel. all components, other than door mounted, shall be located on the component mounting plate by bolting into tapped holes or by using self-tapping screws. Nuts used for securing components shall be captive. rail type fixings may be used where appropriate. Components shall not be mounted on any other surface. no components shall be located within the assembly at a height greater than 2000 mm or less than 500 mm above finished floor level. it shall be possible to replace and maintain any component without first removing other components. bolts and nuts for cover fixing shall be captive and provided with protective washers to prevent damage to paintwork. unless specified otherwise control supplies shall be 110V a.c. derived from a transformer within the control compartment or in a separate compartment, fused on its primary circuit. Neutral shall be earthed with a removable link. Individual compartments shall be fed through a fused tapping next to the main 110v bus adjacent to the transformer. Proper fuse coordination to be achieved to avoid one section fault from affecting the other section. Transformer shall be rated for at least 150% of the maximum loading for long service life. auxiliary supplies such as 24 V AC/DC, 240 V AC etc. are specified in the relevant individual component’s specifications. each compartment shall be provided with a separately fixed compartment heater rated 110 Volts AC. Apart from those in motor starter compartments the heaters shall be controlled by means of individual “OFF/AUTO” switches. Auto operation shall be by means of adjustable panel mounted humidistat covering the range of humidity envisaged. MCCs shall be designed for ready extension at each end. all terminals for outgoing connections shall be located at a low level in the compartment adjacent to the cable gland trays. Adequate space shall be provided the installation and dressing of site cables. It should be noted that site cables are frequently oversized to allow for high ambient temperatures and long cable routes. Direct termination on equipment such as Distribution Board Fuses or Miniature Circuit Breakers (MCB’s) shall not be permitted. all main switches shall be arranged such that a minimum distance of 700mm exists between the glandplate and the bottom of the circuit breaker or terminals, whichever is the less. all live terminals shall be fully shrouded by using high-grade high temperature material. all cable entries shall be affected using brass cable glands to IP rating as specified. all cable glands shall be provided with earth tags. cables shall enter assemblies through detachable steel or aluminum/brass (for single core cables); gland plates fitted at least 200 mm above finished floor level. gland plates shall be rust proofed and provided with a welded and bonded earthing stud, and adequately sized to accommodate present and known future cabling requirements. Access to both sides of each gland plate when it is in position shall be possible from within the assembly. Cables shall enter at the top or bottom of assemblies as specified and/or as shown on the relevant drawings where applicable.

Qatar General Organization for Standards and Metrology QCS 2007, 3rd Edition

QCS 2007

Section 21

Part 2

MV Factory Built Assemblies (FBA’s)

Page 9

(ggg) cableways shall be provided to ensure that apart from inter-connections no cable

routed to one cubicle shall pass through any other cubicle. 2

(hhh) for cable sizes 300mm and above insulated glands shall be fitted. (iii) provision for accommodation of rising armored cables shall be provided with adequate

cable supports and a form of cable entry via approved cable glands secured to a steel glanding plate. (jjj) space shall be provided to accommodate cable glands of appropriate size for incoming and outgoing circuits. All gland plates and trays shall be adequately earthed. (kkk) cable disconnecting links shall be provided where specified and shall be used for maintenance purposes only. The links shall be fitted to the bus bar risers immediately before the cable terminations and shall be easily accessible. The links shall be labeled ‘ISOLATING LINK’ and the circuit or cable reference shall be quoted. (lll) within each assembly, all metal parts of equipment supplied, other than those forming part of an electric circuit, shall be bonded to the earth bar. Metalwork may be used for this purpose provided that earth continuity conductors are fitted at all joints and other discontinuities and those connections to metal work are made using a welded or bolted stud. (mmm) the following metal parts must be provided with equipotential bonding connected to an earth busbar system by using yellow/green earth cable of at least 6.0 mm square. (i) gland plates (ii) gland covers (iii) side sheets (iv) top barriers (v) intermediate barriers (vi) top covers (vii) end covers (viii) rear Covers (ix) front covers (x) cable Boxes (xi) doors and bolted front covers (xii) horizontal busbar barriers. (nnn) each compartment shall be provided with a smoke detector. In addition to this a heat sensitive cable shall be run throughout the MCC passing through each compartment. Both shall be connected to the fire alarm panel and shall additionally be arranged to open the main supply circuit breaker and inhibit the start up of the standby generator. 3

Labels: (a)

(b) (c)

(d) (e) (f)

(g) (h) (i) (j)

provide identification on all equipment e.g. control panels, MCC, controllers, raceways, boxes and conductors, devices etc in accordance with BS 61346, BS 61666, BS 61175 and BS 60445 standards or latest edition of other applicable standards to the approval of the Engineer. all labels shall be permanent, and be machine generated. NO HANDWRITTEN OR NON-PERMANENT LABELS SHALL BE ALLOWED. prior to making any label or nameplate for the purpose of identification, submit a detailed schedule indicating nameplate size, lettering size, color, material and actual nameplate information for the Engineer's review and approval. all external labels, nameplates, operational and warning signs shall be provided in English. material used in making the engraved labels shall be of highest quality suitable for the environmental and climatic conditions as specified in the relevant section. critical devices such as disconnect switches; service feeders and branch circuit protective feeders shall be legibly labeled to indicate its purpose and point of origin. The legibility distance shall not be less than 2.0 meters. identification nameplates shall be provided in addition to the manufacturer's equipment nameplates as required by NEMA, BS, IEC or UL. warning signs and instruction labels wherever needed shall be provided in accordance with all applicable local regulations. the contractor shall clearly show locations and fixing arrangements of nameplates and labels on layout drawings. the contractor shall comply with the following requirements for labels:

Qatar General Organization for Standards and Metrology QCS 2007, 3rd Edition

QCS 2007

Section 21 (i)

(ii) (iii)

(iv) (v) (vi) (vii) (viii) (ix) (x) (xi) (xii) (xiii) (xiv) (xv) (xvi) (xvii) (xviii) 4

Part 2

MV Factory Built Assemblies (FBA’s) Page 10

provide equipment identification labels for all electrical equipment including, but not limited to switchgear, control panels, switchboards, transfer switches, disconnect switches, transformers, generators, power factor capacitors, fixed equipment, motor starters, MCCs etc. provided sub-classification label for all emergency power system, junction boxes and pull boxes. external labels: Clear Perspex back engraved, in black letters on white backgorund in English with chamfered edges fixed with stainless steel screws with nuts and flat & lock washers. The letters should be filled in white and the rear surface painted black. internal labels: Multi-layered plastic to an approved design engraved in English, and fixed with stainless steel screws. Alternatively special purpose made DIN rail may be used for fixing labels as approved by the engineer. all labels shall be screw or rivet fixed and adhesive labels shall not be permitted under any circumstances. internal components labels shall have circuit designations correlated with the drawings. labels shall not be attached to trunking covers or other readily removable items. electrical equipment enclosures, vaults, doors and fences shall be provided with "DANGER KEEP OUT" warning sign, showing proper voltage. disconnect switches and emergency devices shall have "CAUTION" warning signs as directed by the Engineer. fuse and MCB distribution boards shall be provided with internal, screw fixed, engraved circuit labels. Ink on paper, ink on plastic, printed paper, printed plastic, plastic film or any kind of adhesive labels shall not be permitted. provide a main Title Label all for electrical distribution and all other control equipment, panels etc. provide a Function Label for door mounted components. every internal component - Identification Label. provide a Identification Label for Protective devices - ( e.g. fuse/mcb type, rating). provide a Title Label for Communication equipment. compartments with doors and covers not electrically interlocked to an isolator, external label - “ DANGER, LIVE TERMINALS ” with flash and voltage in red letters on white background in Arabic and English. provide a function description Label for group of terminal blocks. letter size shall be to the approval of the Engineer

Switchboard Wiring: (a)

(b) (c) (d)

(e)

(f) (g)

wiring shall generally be of the multi-stranded high temperature to minimum 105° C flexible PVC insulated, 600/1000V single core stranded copper type cable to BS EN 6231. Where it is proposed to use alternative high temperature, double insulated or other special cable or insulated flexible laminated bus bar this should be brought to the attention of the Engineer for his approval. wiring shall be supported in insulated cleats or cable trunking. Adhesive type cleats or mounts shall not be used unless augmented by screw fixings. busbar chambers shall not be used as trunking for small wiring. wiring shall be neatly laid and run in limited compression insulated cleats, insulated straps or, where more than ten wires follow the same route, in plastic slotted-sided trunking with clip-on covers. Where trunking is used, the effective overall crosssectional area of cables shall not be greater than 70% of the trunking cross sectional area. wiring to items of equipment mounted on hinged doors or subject to movement shall run in plastic sleeving or flexible conduit, being securely anchored at both ends; leaving ample slack to prevent wiring strain, arranged so that they are subject to torsion rather than bending. holes in steelwork through which cables pass shall be protected using grommets or bushes, suitable for the size of hole. cables used for control, extra low voltage and instrument signal transmission, likely to be affected by interference, shall be screened and/or spaced from each other and from

Qatar General Organization for Standards and Metrology QCS 2007, 3rd Edition

QCS 2007

(h) (i) (j) (k) (l)

(m)

Section 21

Part 2

MV Factory Built Assemblies (FBA’s) Page 11

heavy current power cables. The separation distance shall ensure that the resultant electrical noise is insufficient to cause any form of malfunction of associated equipment or give false readings. a sufficient number of terminal connections including 15 % spare terminals shall be provided for all control and instrument wiring. all wiring shall be identified at each end by means of glossy plastic ferrules showing the wire number as on the schematic diagrams. Ferrules shall be color coded, ‘Z’ type and indelibly marked. where single core cable is to be accommodated, a non-magnetic gland plate shall be provided. For cable size 300 mm Sq. and above insulated glands shall be fitted. undrilled gland plates shall be provided for the reception of conduits and threaded glands. Boxes and glands shall be within the cubicles except where otherwise approved. single strand wire shall not be used. The minimum cross sectional area of the wire 2 2 used shall be 1.0 mm (multi strand flexible) for control circuit and 2.5 mm for power circuit. Both ends of every wire shall be fitted with a white cable marker as described above. Clip on type cable markers shall not be used. Color-coding shall be: Red - Red phase Yellow - Yellow phase Blue - Blue phase Black - Neutral Green and Yellow - Earth/Protective conductors Grey - 110V a.c White - 60 D.C Purple -
View more...

Comments

Copyright ©2017 KUPDF Inc.
SUPPORT KUPDF