Download Scheduling and Sequencing by Johnson Rule...
Description
SCHEDULING & SEQUENCING BY JOHNSON’S RULE GROUP MEMBERS Rajendra kumar Pratik Puneet Pintu
DEFINATION
Establishing the timing of the use of equipment, facilities and human activities in an organization Effective scheduling can produce:1) Cost savings 2) Increases in productivity
Scheduling Difficulties
Variability in
Setup times Processing times Interruptions Changes in the set of jobs
No method for identifying optimal schedule Scheduling is not an exact science Ongoing task for a manager
Minimizing Scheduling Difficulties
Set realistic due dates
Focus on bottleneck operations
Consider lot dividing of large jobs
SEQUENCING
JOHNSON’S RULE
SEQUENCING
Sequencing: Determine the order in which jobs at a work center will be processed. Workstation: An area where one person works, usually with special equipment, on a specialized job. Priority rules: Simple hierarchy used to select the order in which jobs will be processed. Job time: Time needed for setup and processing of a job. Everything is #1 Priority
Priority Rules
FCFS - first come, first served
LTR - Least time required
LAR/LOR – Least activity required/Fewest operations required
EDD - earliest due date
CRS - critical ratio scheduling
Top Priority
JOHNSON’S RULE
Technique for minimizing completion time for a group of jobs to be processed on two machines or at two work centers.
Minimizes total idle time
Several conditions must be satisfied
Johnson’s Rule Conditions
Job time must be known and constant
Job times must be independent of sequence
Jobs must follow same two-step sequence
Job priorities cannot be used
All units must be completed at the first work center before moving to second
Example Of Johnson’s Rule (Two Machines) Job No. A B C D E F G H I J
So we can say that by using Johnson’s rule of scheduling Time saved in this case is :150 – 140 = 10
Johnson’s Rule for Three Machines
Condition:-Largest time on M2 should be less than or equal to smallest time on M1 or M2 or both. If condition satisfied then we calculate:R1 = M1 + M2 R2 = M2 + M3 This whole can be understand by the help of following example:-
Job No. A B C D E F G H TOTAL
Time on M1
16 15 12 13 14 15 13 12
Time on M2
Time on M3
12 11 10 9 11 10 9 12
11 12 13 15 17 16 14 17
84
115
MC1
MC2
St. Time
St. Time
0 16 31 43 56 70 85 98
End Time
16 31 43 56 70 85 98 110
16 31 43 56 70 85 98 110
End Time
28 42 53 65 81 95 107 122
MC3
R1
R2
SEQUENCE
St. Time
M1+M2
M2+M3
(BY JOHNSON'S RULE)
28 42 54 67 82 99 115 129
End Time
39 54 67 82 99 115 129 146
28 26 22 22 25 25 22 24
23 23 23 24 28 26 23 29
C G D H F E A B
Idle time on Machine-2 is:122 – 84 = 38 Idle time on machine-3 is:146 – 115 = 31
SEQUENCE
MC1
MC2
MC3
(BY JOHNSON'S RULE)
St. Time
St. Time
St. Time
C G D H F E A B
0 12 25 38 50 65 79 95
End Time
12 25 38 50 65 79 95 110
12 25 38 50 65 79 95 110
End Time
22 34 47 62 75 90 107 121
22 35 49 64 81 97 114 125
End Time
35 49 64 81 97 114 125 137
Total time saved by Using Johnson’s rule Is:146 – 137 = 06
CONCLUSION
Thus we can say that by using Johnson’s rule we can do more better sequencing of machines and can save the time of production.
Thank you for interesting in our services. We are a non-profit group that run this website to share documents. We need your help to maintenance this website.