Double Click on SAP LOGON Icon Select development server of SAP 4.6C Select Client 250 Enter User id & Password
Master Data Requirements
Controlling Area Company Code Business Area Plant Cost Center Activity Type Cost Element GL Account Purchasing Organisation Purchasing Group Material Group Profit Center
Project Definition creation WBS Creation Network & Activity creation Component Planning Plant Approval Corporate Planning Approval Budget Creation Board Approval Budget Release WBS Release Purchase order release Procurement cycle starts Production cycle starts Labour hour confirmation Settlement of Cost WBS completion AUC converts to Asset
TATA TECHNOLOGIES
Page 2 of 41 Version2: Arpita 20.01.2005
SAP: Project System
General Login Information
Double Click on SAP LOGON Icon Select development server of SAP 4.6C Select Client 250 Enter User id & Password
Master Data Requirements
Controlling Area Company Code Business Area Plant Cost Center Activity Type Cost Element GL Account Purchasing Organisation Purchasing Group Material Group Profit Center
Project Definition creation WBS Creation Network & Activity creation Component Planning Plant Approval Corporate Planning Approval Budget Creation Board Approval Budget Release WBS Release Purchase order release Procurement cycle starts Production cycle starts Labour hour confirmation Settlement of Cost WBS completion AUC converts to Asset
TATA TECHNOLOGIES
Page 2 of 41 Version2: Arpita 20.01.2005
SAP: Project System
Project Definition T h e p r o j e c t d e f i n i t io io n i s t h e b i n d i n g f r a m e w o r k f o r a l l o r g a n i za za t io io n a l e l em em e n t s w i t h i n a p r o j e c t . Yo Yo u c a n a l s o d e f i n e n o n - b i n d i n g s t a r t a n d f i n i s h d a t e s f o r t h e p r o j e c t
Menu Path: Logistics -> Project System -> Project -> Special Maintenance Functions -> Structure Planning -> Work Breakdown Structure -> Project Definition -> Create Transaction: CJ01 This transaction is carried out for the creation of Project Definition by the Coordinator or the NPI office after he receives the approved proposals from the respective cost centers. Person Responsible: Coordinator / NPI Office
Refer to the Project Coding Mask for TATA Motors as explained below
TATA TECHNOLOGIES
Page 3 of 41 Version2: Arpita 20.01.2005
SAP: Project System
T.00.X1X2X3.000.000.00.00 T 00 X1 X2 X 3
Represents projects in Tata Motors Year of Project Commencement e.g. 03 ,04 X1 : C = CVBU ; M = MUV ; K = CAR X2 : A = HCV ; B = MCV ; C = LCV ; D = SUB FOUR TONNE-CUB ; E = BUS-HCV ; F = BUS-MCV ; G = BUS-LCV ; H = ENGINES ; I = TRANSMISSION ; J = AXLE ; K = CAB ; L = SUMO/SPACIO ; M = SAFARI ; N = 207 ; O = INDICA ; P = SEDAN ; Q = ESTATE
000
000
00
X3 : N = NEW GENERATION ; D = DERIVATIVE ; E = ENHANCEMENT ; F = FACELIFT ; U = UPGRADE ; V = VERSION Running Serial number for given project category 001 to 500 = PCBU & CAR 501 to 999 = CVBU Level 1 WBS element serial number – number – to to be standardized as follows: Characters
Work breakdown
(alternate characters)
001 002 003 004 005 006 007 008 009
ERC(Inhouse) ERC(Outsource) PE (Inhouse) PE(Outsource) SQIG /ADD Plant and Machinery PO,PP Trials Marketing(Launch) Others(not known)
ERI ERO PET PEO SQI and ADD PAM TRI MKT MSC
Level 2 WBS element serial number to be standardized as follows (for PE toolings only) : Characters
0
Activity (alternate characters) (Toolings reqd for) 01 ENGINE AE 02 GEAR BOX AG 03 BIW AB 04 PRESS/FRAME AF 05 VEH ASSY AV 06 STEERING AS 07 AXLE AA 08 PAINT AP Level 3 WBS element serial number to be standardized as follows (for PE toolings only) : Characters Activity (alternate characters) (Toolings reqd for) 1 Non Foundry toolings N 8 Foundry toolings F
All projects for TATA Motors will be defined as per above coding mask. mask. In TATA Motors WBS can be created up to level 4.
TATA TECHNOLOGIES
Page 4 of 41 Version2: Arpita 20.01.2005
SAP: Project System
Field Definitions: Field Name
Mandatory
Remarks
Project def
Yes
Project Profile
Yes
Template
Optional
Enter new project number System help is available to search next available number , using ‘OPEN NUMBER’ Push Button Profile determines which kind of project it is and based on settings fields are displayed on the screen Data will be copied from reference template
TATA TECHNOLOGIES
Page 5 of 41 Version2: Arpita 20.01.2005
SAP: Project System
Project Definition Details Screen: Basic Data Tab:
Click here to see the Project Status
Field Definitions: Field Name
Mandatory
Remarks
Description Start
Yes Yes
End
Yes
Controlling Area Company Code Business Area Plant
Yes
Enter Project Description Enter Start Date of overall project Enter End Date of overall project Use '0100' for Tata Motors Use '0100' for Tata Motors Based on Location select BA from drop down box Based on Location select
Yes Yes Optional
TATA TECHNOLOGIES
Page 6 of 41 Version2: Arpita 20.01.2005
SAP: Project System
Plant from drop down box Profit Center Yes Enter the Correct Profit Center from drop down box Mask ID Optional Free field helps you to search project Factory Optional Select calendar for Calendar location where work is going to get exceeded Enter in all the relevant data.
TATA Motors TAB:
Field Name
Mandatory
Remarks
Market Classification Project Type Launch Date
Yes
Select from Drop Down
No No
Select from Drop Down Enter Launch date
TATA TECHNOLOGIES
Page 7 of 41 Version2: Arpita 20.01.2005
SAP: Project System
NPV IRR EVA Life Cycle Volume Pay Back
No No No No
To be put by User To be put by User To be put by User To be put by User
No
To be put by User
Project Status Management: The current status of a project or an object in a project determines which business t r a n s ac t i o n s c a n b e e x e c u t e d . S t at u s e s d o c u m e n t t h e c u r r e n t p r o c e s s i n g s t a g e o f a n object
When the different stages of the project are completed, the relevant gate status is ticked by the project office.
TATA TECHNOLOGIES
Page 8 of 41 Version2: Arpita 20.01.2005
SAP: Project System
Work Breakdown Structure I t i s t h e f u n c t i o n a l b a s i s f o r f u r t h e r p l a n n i n g s t e p s i n a p r o j e c t , f o r e x am p l e , f o r p r o c e s s p l a n n i n g , c o s t p l a n n i n g , s c h e d u l i n g , c a p ac i t y p l a n n i n g o r c o s t i n g a s w e l l a s p r o j e c t s con trol. It gives you a clear picture of the project and facilitates the coo rdination and i m p l e m e n t a t io n o f t h e p r o j e c t f r o m a m a n a g e m e n t s t a n d p o i n t .
Menu Path: Logistics -> Project Systems -> Project -> Special Maintenance Functions -> Structure Planning -> Change Project Transaction: CJ20 This transaction is carried out by the Project Planner, Coordinator / NPI Office, Department Head for creating WBS for each cost center. Person Responsible: Project Planner, Coordinator / NPI Office, Department Head
Field Name
Mandatory
Remarks
Project def
Yes
Use drop down menu to select existing project number
TATA TECHNOLOGIES
Page 9 of 41 Version2: Arpita 20.01.2005
SAP: Project System
Press ‘Enter’.
TATA TECHNOLOGIES
Page 10 of 41 Version2: Arpita 20.01.2005
SAP: Project System
Short Cut: Use ' “.01 ‘ to generate new WBS. Field Name
Mandatory
Remarks
WBS element
Yes
Description Short id
Yes No
Based on Masking system allows to create running WBS number Enter WBS description You can change default number to identify WBS by different name
Note: To Create a lower level WBS change the level to ‘2’ instead of ‘1’ and follow the same steps as that of creating the first level wbs element.
TATA TECHNOLOGIES
Page 11 of 41 Version2: Arpita 20.01.2005
SAP: Project System
D o u b l e C l i c k o n W B S E l e m e n t f o r D e t ai l s S c r e en : Tata Motor s Tab:
Field Name
Supply Source Basis of Estimate Primary Category Secondary Category Aggregate Business Unit Inv. Classification NPI Process WBS Element description
Mandatory
Remarks
Yes Yes Yes No No Yes Yes Yes Yes
Select from drop down box Select from drop down box Select from drop down box Select from drop down box Select from drop down box Select from drop down box Select from drop down box Select from drop down box Appropriate description to be put
Go to next tab ‘WBS Basic Data’
TATA TECHNOLOGIES
Page 12 of 41 Version2: Arpita 20.01.2005
SAP: Project System
WBS Basic Data:
Field Name
Mandatory
Project type Priority Responsibl e Person Resp. Cost Center Req. Cost Center Billing Element
No
Select from drop down box
No No
Select from drop down box Select from drop down box
Yes
Cost Center where asset will be capitalised Who is going to consume
No Optional
User Status System Status
Remarks
If WBS is billable to customer then check this option Detail explanation on another page System based on different business transaction maintains different statuses
Go to next tab ‘Dates’. TATA TECHNOLOGIES
Page 13 of 41 Version2: Arpita 20.01.2005
SAP: Project System
Dates Tab:
Field Name
Mandatory
Remarks
Basic Start Date Duration Basic End Date Forecast Start Forecast End Calendar
Yes
Plan Start date
Yes No
Duration of the activity Plan End date
No No Yes
Select Calendar
TATA TECHNOLOGIES
Page 14 of 41 Version2: Arpita 20.01.2005
SAP: Project System
A d d i t i o n o f P S T ex t t o a W B S E l em e n t
In the CJ20 Screen go to Details -> PS texts as shown below:
This will give the following screen:
TATA TECHNOLOGIES
Page 15 of 41 Version2: Arpita 20.01.2005
SAP: Project System
Select the type of PS text like in the example ‘Z1’ has been selected and give a Description and press Enter which will give the following screen where one can enter the text in detail.
TATA TECHNOLOGIES
Page 16 of 41 Version2: Arpita 20.01.2005
SAP: Project System
Back and Save.
TATA TECHNOLOGIES
Page 17 of 41 Version2: Arpita 20.01.2005
SAP: Project System
NETWORK A n e t w o r k c a n r e p r e s en t t h e s e q u e n c e o f a c t i v i t i e s i n a p r o j e c t o r t h e s e q u e n c e o f a s i n g l e a c t i v it y w i t h i n a p r o j e c t .
Menu Path: Logistics -> Project Systems -> Project -> Special Maintenance Functions -> Network -> Create Transaction: CJ20 This Transaction is carried out by the Planner who creates separate Network activities for each WBS. Person Responsible: Project Planner Select the WBS element and click on ‘Activity Data’ Tab. This will bring us to the detail screen for creating Network Activity.
Click on Activity data tab
TATA TECHNOLOGIES
Page 18 of 41 Version2: Arpita 20.01.2005
SAP: Project System
Type: Internal Activity (Mainly for Internal Labor us age)
Field Name
Mandatory
Remarks
Activity Description Duration Unit Plan Duration Work Center
Yes No No Yes Yes
Plant
Yes
Activity type
Yes
System defaults number Activity Description E.g. Hours/ Day Plan Duration Resource group within Cost Center Facility where activity is going to be perform Skill set from cost center / Work Center
For selecting the Activity Type, follow the process wherein the dates for the activity are to be put in. Double click on activity and then go to Dates tab where the dates can be put in. Save.
TATA TECHNOLOGIES
Page 19 of 41 Version2: Arpita 20.01.2005
SAP: Project System
This will enable us to select the relevant Activity Type.
TATA TECHNOLOGIES
Page 20 of 41 Version2: Arpita 20.01.2005
SAP: Project System
Type: External A ctivity (Mainly fo r Material)
Select the Activity and click on the Component Overview icon
External Activity can be ‘Material’ and ‘Services’. For Components: Select Activity and click on the Component Overview Icon to go to the component overview screen.
TATA TECHNOLOGIES
Page 21 of 41 Version2: Arpita 20.01.2005
SAP: Project System
C o m p o n e n t O v e r v i e w S c r ee n :
If Material was procured before or if it is Stock item then select material code from drop down list else for new Capital Material procurement use Generic material ‘CAPITAL_DOM’ for domestic procurement and ‘CAPITAL_IMP’ for imports. Double click on the item number and enter the price for the component.
TATA TECHNOLOGIES
Page 22 of 41 Version2: Arpita 20.01.2005
SAP: Project System
Click here for Invoice Plan.
TATA TECHNOLOGIES
Page 23 of 41 Version2: Arpita 20.01.2005
SAP: Project System
Invoic e Plan:
Click on the Button ‘Invoice Plan’ as shown above to get the following screen:
Enter the Details as shown
Save. Field Name
Mandatory
Activity Yes Description No Purchasing Org No Cost Element Vendor
Yes No
Material Group Price
Yes
Activity Qty
Yes
TATA TECHNOLOGIES
Remarks
System defaults number Description of the activity Who is going to perform procurement activity Where cost to get booked Required at the time of WBS release Required at the time of WBS release Expected price of the material Plan Quantity
Page 24 of 41 Version2: Arpita 20.01.2005
SAP: Project System
Type: External Activ ity (Mainly fo r Services)
Tick the Services Box for creation of Service
Select ‘Service’ tab & enter description of activity. Press Enter to get to the next screen.
TATA TECHNOLOGIES
Page 25 of 41 Version2: Arpita 20.01.2005
SAP: Project System
Enter the Contract number where relevant. If Service is coded then pick up number from drop down else enter short text manually. Enter all the relevant info including Qty and Price and press F3 twice.
TATA TECHNOLOGIES
Page 26 of 41 Version2: Arpita 20.01.2005
SAP: Project System
Type: Primary Cos t Activ ity (Mainly General Expenses)
Field Name
Activity Description Amount Currency Cost Element
Mandatory
Remarks
Yes No Yes Yes Yes
System defaults number Description of the activity Total Plan amount While using search, put ‘TATA’ in the chart of accounts.
Press Enter to fill up Details.
TATA TECHNOLOGIES
Page 27 of 41 Version2: Arpita 20.01.2005
SAP: Project System
Save after having filled up the details in the respective Tabs.
TATA TECHNOLOGIES
Page 28 of 41 Version2: Arpita 20.01.2005
SAP: Project System
WBS Status Management The current status of a project or an object in a project determines which bu siness t r a n s ac t i o n s c a n b e e x e c u t e d . S t at u s e s d o c u m e n t t h e c u r r e n t p r o c e s s i n g s t a g e o f a n object
To check the WBS Status Select the WBS Element or the Activity and the click on the Status Button
TATA TECHNOLOGIES
Page 29 of 41 Version2: Arpita 20.01.2005
SAP: Project System
Based on Status certain business transactions will be allowed: Draft Capex: By Default WBS will have this status. Deferred Capex: If the WBS is not approved, it is put on hold and this status is set. (Plant Head / Corporate Planning) Project Manager Approved: This Status is set by Project Manager Project Office Approved: This Status is set by Project Office HO Clarification requested: This status is set when the Head Office asks for any clarification. (Corporate Planning) Management Approved: When Management Approves the Budget, this status is set. (Corporate Planning) Budget Closed: In case the work was dropped in the middle and the budget is no longer required then this status is set. (Planner) Budget Not Required: This status is set in case planner wants to return approved budget. Budget Carry Forward: This Status is set in case the excess budget for the year is to be carried forward to the next financial year. (Corporate Planning)
TATA TECHNOLOGIES
Page 30 of 41 Version2: Arpita 20.01.2005
SAP: Project System
To use Template for creating new proposals. For including Standard Network as an activity set in the WBS Element. Go to Activity screen – then go to menu Network -> Include Std. Network which will give the following screen.
Select a Standard Network from the List and press Enter
TATA TECHNOLOGIES
Page 31 of 41 Version2: Arpita 20.01.2005
SAP: Project System
Standard Network has been included which contains these three activities
TATA TECHNOLOGIES
Page 32 of 41 Version2: Arpita 20.01.2005
SAP: Project System
To attach a document to a WBS Element Select the WBS and then click on the ‘Services for object’ button -> Create -> Create attachment as shown below.
Click here and follow the path
TATA TECHNOLOGIES
Page 33 of 41 Version2: Arpita 20.01.2005
SAP: Project System
Which then gives us the option of selecting which ever document we want to attach from the directory as needed.
TATA TECHNOLOGIES
Page 34 of 41 Version2: Arpita 20.01.2005
SAP: Project System
Create Standard Network Menu Path: Logistics -> Project Systems -> Basic Data -> Templates -> Standard Network Transaction: CN01 This transaction is carried out by the Project Planner, Coordinator / NPI Office, or Corporate Planning for creating Standard Network. Person Responsible: Project Planner, Coordinator / NPI Office, Corporate Planning
To be left blank – system generated number
Fill up the Profile and press Enter.
TATA TECHNOLOGIES
Page 35 of 41 Version2: Arpita 20.01.2005
SAP: Project System Click on Activities Button
Field Name
Mandatory
Remarks
Network Usage Planner Group Network Status Std. WBS Element Predefined Plant
No No No No
Select from drop down Select from Match Code Select from drop down Select from Match Code
No
Select from Match Code
Click on activities button to go to the next screen.
TATA TECHNOLOGIES
Page 36 of 41 Version2: Arpita 20.01.2005
SAP: Project System
Click on the External Activities Tab and create the Activity as follows:
Press Enter to go to the details screen.
TATA TECHNOLOGIES
Page 37 of 41 Version2: Arpita 20.01.2005
SAP: Project System
Field Name
Mandatory
Work Center / Yes Plant Material Group Yes Purchasing Yes Group Purchase No Organisation Net Price No
TATA TECHNOLOGIES
Remarks
Select from Match code Select from Match Code Select from Match Code Select from Match Code Enter the Price of the Component
Page 38 of 41 Version2: Arpita 20.01.2005
SAP: Project System
Click on the Internal Activities Tab and creat e the Activity as follows:
Press Enter to go to the Details Screen.
TATA TECHNOLOGIES
Page 39 of 41 Version2: Arpita 20.01.2005
SAP: Project System
Field Name
Mandatory
Work Center / Yes Plant Work No
Remarks
Select from Match code No. of days to be filled up
Click on tick which takes you back to the previous screen and save the internal number gets generated as shown below.
Thank you for interesting in our services. We are a non-profit group that run this website to share documents. We need your help to maintenance this website.