SAP PP Product Conversion (CS14)
Short Description
Get this material from http://sapdocs.info/sap/production-planning/sap-r3-ecc-6-0-pp-end-user-guides/...
Description
Testing: Unit Testing / User Manual
Module: Production & Planning
ENVIRONMENT SYSTEM
: SAP R/3 ECC 6.0
CLIENT
: 200
UNIT TESTING SCENARIO SCENARIO NUMBER
: PP - 07
DESCRIPTION
: Product Conversion
PURPOSE
: To convert from one FG model to another FG Model
PREPARED BY NAME Helped by
: S Narayanaswamy : Avtar Singh/G. Sivakumar
DATE
:
TEAM
: Production Planing
APPROVED & TESTED BY NAME
: Nanhe Babu (PwC)
DATE
:
TEAM
: Production Planing
Page 1 of 19
Testing: Unit Testing / User Manual
Module: Production & Planning
1.0 Transaction Code/ Path Enter the menu path of the transaction code, which is going to be tested by the user. Menu Path
Logistics Production Master Bill Of Material Report BOM Comparison – CS14
T.Code
CS14
Input Data 1. Enter the Input FG Code, Plant & Usage No in Primary BOM 2. Enter the to be converted FG Code, Plant & Usage No in Secondary BOM Click on
button
Page 2 of 19
Testing: Unit Testing / User Manual
Module: Production & Planning
You will get this comparison screen :
Export this data to Excel sheet and arrive the net requirements and Primary FG which is to be converted in the list as mentioned below. 2.0
Create conversion BOM from the above table
2.1
Then create routing master as standard practice
Page 3 of 19
Testing: Unit Testing / User Manual
Module: Production & Planning
3.0 Create Conversion Production Order – T.CODE ZPC1 Order type : ZC01
Press enter and select Routing by double clicking on the routing No. Create Production conversion order Delete auto generated Sl. No. Release the Prdn. Order & Save (note down the prdn. order No.) 4.0 Create Manual reservation to FG Only for Matl stagging : T.Code MB21 Mvmt Type : 311
Page 4 of 19
Testing: Unit Testing / User Manual
Module: Production & Planning
Click Ok
Save the reservation Go to MB1B MOVEMENT TYPE:311
Page 5 of 19
Testing: Unit Testing / User Manual
Module: Production & Planning
Enter Ok button
Select ‘M’ – Movement allowed and save the reservation
Go to MB1A – Mvmt: type : 261
Page 6 of 19
Testing: Unit Testing / User Manual
Module: Production & Planning
Click To Reservation and enter the Reservation No. and press enter
Go to MB1A – Mvmt Type 261
Page 7 of 19
Testing: Unit Testing / User Manual
Module: Production & Planning
Click To reservation and provide reservation no. and attach Eng. Sl. No and save. The Serial Number of Engine gets consumed.
Material Staging – MF60
Page 8 of 19
Testing: Unit Testing / User Manual
Module: Production & Planning
Enter Order in Production/process orders tab, remove date from 'Selection period for rqmts'. Click global setting Missing parts calculation: if there are multiple orders open for same header item, in order to capture total requirements of all open order & depending upon stock lying at WiP, once needs to Select 'Include all requirements'. Replenishment options: Since reservation no. needs to be generated for Stock Transfer, Tick 'Stock transfer res.' field. Display: Click all four fields. Units of measure: if 'Unit of issue' is different then Unit of stock keeping, select '1 Priority 1(highest)', accordingly quantity will be calculated & displayed in MF60 screen.
Page 9 of 19
Testing: Unit Testing / User Manual
Module: Production & Planning
Select
all or deselect
depending upon all components, to be staged. Click 'Replenishment Elements'. Then Click 'Replenishment proposal', following screen will be seen. Select the lines & Click Stage. Click
for saving the
posting reservation.
Using the reservation no. generated, MF65 T Code will stage the material by reservation as standard process
Page 10 of 19
Testing: Unit Testing / User Manual
Module: Production & Planning
5. Sl. No control for the Conversion Assign Eng. Sl.no of Old FG to New FG Menu Path
Logistics Production Master Bill Of Material Engine Sl. No Change – IQ02
T.Code
IQ02
Page 11 of 19
Testing: Unit Testing / User Manual
Module: Production & Planning
Enter old FG Model No. and press Sl.No. List
Select the Engine Sl. No & Click Ok Button
To remove the Old Engine Sl. No from the old model go to IQ02 :
Page 12 of 19
Testing: Unit Testing / User Manual
Module: Production & Planning
Page 13 of 19
Testing: Unit Testing / User Manual
Module: Production & Planning
Input the New Material No. and save. Now the Sl. No. will be allotted to the New Matl. No.
Select the Structure Tab and change the Old FG No to New FG No.
Page 14 of 19
Testing: Unit Testing / User Manual
Module: Production & Planning
Click Save button to save the entry
Page 15 of 19
Testing: Unit Testing / User Manual
Module: Production & Planning
6 Material Staging Posting for Reservation No. generated from MF60. 6.1 Go to MB25, enter Production order
After entering the order and executing MB25 T Code, one needs to Set filter on MvT Type, keeping it 311.
6.2 Go to MF65, enter the Reservation No.
Page 16 of 19
Testing: Unit Testing / User Manual
Select all lines using
Module: Production & Planning
button, depending upon Stock Availability in the Storage Location, & one
defined in EP Location (Set in Stock Determining Group), remaining Stock will remain open. Upon availability of Stock, same reservation no. will be used for transfer posting of items. 7.Goto Co11n and do the production order confirmations
Page 17 of 19
Testing: Unit Testing / User Manual
Description of the Field Order
Module: Production & Planning
Nature of the Field Mandatory
Operation
Mandatory
Yield
Optional
Value of the Field Enter your Order No. Enter your Operation No. 0010,0020,... Enter the no. item that one want to confirm
'Posting date' will be date on which Confirmation will be posted 'Reason for Var.',the reason for deviation of Confirmed Quantity to Planned Quantity. Plant wise reason codes are provided as F4 values. Shift, Down time, Actual time taken & Actual Work Centre can be set. Once the confirmation of all operations are done, next step of Goods Receipt needs to be done. 8.Goto MB31 and do the Goods Receipt movement type : 101 attach Eng.Sl.No & save
Enter Order, Plant & Storage Location, Click Adopt / Adopt + Details, following screen will be displayed.
Page 18 of 19
Testing: Unit Testing / User Manual
Module: Production & Planning
Click 'Enter', depending upon Quality Setup, Click Enter twice, following screen is displayed.
Select the Serial number, by clicking in the box next to the Serial number After selecting the Serial numbers,
needs to be clicked.
Above screen will be displayed. Once the screen is displayed, click
, in order to post records.
In production order header screen, quantity confirmed will appear as 'DLV' 9.Now the Engine will convert from old Model to New MODEL with Same Sl. No. 10.Engine route card to be printed again with the converted Model
NARAYANASWAMY-PP *Note – BOM comparison, copying & creating conversion BOM is manual, setting up control will be checked & then in corporated in the manual.
Page 19 of 19