Sample of a Project Proposal - Water System Project

October 14, 2017 | Author: rolandtrojas | Category: Drinking Water, Water Supply Network, Project Management, Poverty, Poverty & Homelessness
Share Embed Donate


Short Description

Sample of a Project Proposal for a Water System Project...

Description

PROJECT PROPOSAL I. Description A. Project Title Rehabilitation of Water System B. Project Location Bote, Bato, Catanduanes

C. Brief Summary of the Project The project primarily intends to decrease the poverty incidence in the barangay, in line with the thrust of the National Government which is directed towards poverty reduction. It will provide 221 HHs in the barangay an access to clean and safe water. It also seeks to eliminate the incidence of water-borne diseases in the barangay which was recorded at 55 cases of skin diseases during the preceding year. As the more serious sickness which may be brought about by unsafe water will drain the budget of the family, availability of safe drinking water is a must to every household. Easy access to safe water will also result to savings in time of family members which will pave way for the accomplishment of other profitable undertakings. Although 90.5% percent of the households have water connections provided by the barangay, it failed to provide them with sufficient supply of clean and potable water. As such, there is a necessity to tap the appropriate water source in the barangay through the SALINTUBIG program of the DILG. The project will augment LGU’s undertaking in improving the water system of the barangay through its Economic Development Fund. Barangay Bote has also spent part of its development fund for the said water system, accomplishing the construction of the existing water tank that has a capacity of 21.6 cu. m and laying of the existing pipelines of the barangay water system.

D. Project Goals and Objectives In general, the project is aimed at reducing the poverty threshold of the barangay from 80% to 65%. Specifically, it will provide the 1,105 individuals in 221 households in the barangay an access to safe drinking water. It will also promote good health and cause the eradication of water-borne diseases; and will reduce the time allotted by family members in fetching water, thus savings in time would provide for the accomplishment of other lucrative activities.

E. Total Project Cost

Table 1. Total Project Cost and percentage of contribution Source of Fund Amount Department of the Interior and Local 900,000.00 Government Municipal Government of Bato, Catanduanes 90,000.00 (direct counterpart) 41,500.00 (fund provision to other activities) Beneficiaries 21,000.00 (in-kind)

% Share 85.5% 12.5%

2%

F. Target Beneficiaries The beneficiaries of the project are the whole residence of Barangay Bote. With proper management, it will give them abundant supply of safe and clean water which will also prevent them from being afflicted by diseases caused by contaminated water. The easy access to a potable water supply will also result to savings in time in fetching drinking water, therefore, would give time to residents to accomplish other profitable tasks.

G. Project Partners In the barangay level, the direct partner during the construction phase is the Barangay Council. Other organizations in the barangay such as the purok, youth and women’s organization will contribute to labor component of project construction. Once operational, the Barangay Bote Water and Sanitation Association with the assistance of the Barangay Council and the Municipal Government will take charge in the operation and maintenance of the project.

H. Technical Evaluation The proposed water tank will be constructed within the mountainous terrain having an elevation of 73.24 meters and distance of 3.069 kilometers from the service area. With slopes ranging from 8-15 percent and soil components primarily made of Luciana clay, the site is not susceptible to landslide and erosion. Also, the proposed site is not susceptible to excessive surface run-off or flooding, not located near an active fault line, and will not disturb any historical and monumental markers.

II. Project Components and Implementation Schedule Table 2. Time table of Activities Activities 1. Creation of Municipal Water and Sanitation (WATSAN) Council and Water and Sanitation (WATSAN) Team or Project Management Unit 2. Authorization of the Mayor to enter into a MOA through

Date April 10, 2014

Responsible Agency / Office Office of the Mayor

April 14, 2014

Office of the Sangguniang Bayan

SB Resolution 3. Conduct of community consultation 4. Water sources inventory

April 21, 2014

WATSAN, Barangay Council

April-May, 2014

WATSAN, Barangay Council, Municipal Engineering Office WATSAN, Barangay Council

5. Organization/Reactivation of April, 2014 Barangay Bote Water and Sanitation Association 6. Preparation, submission and April – September, 2014 approval of the required documents and other necessary materials 7. MOA signing and transfer of October, 2014 fund

8. Project Implementation a. Procurement and October, 2014 Delivery of Supplies and Materials b. Construction of Water October-December, 2014 Tank and Pipe Laying

c. Liquidation of Expenses December, 2014 through preparation and submission of Statement of Expenditures (SOE) and Receipt of Disbursement d. Inauguration and December, 2014 Transfer of Project Management to Bote Water and Sanitation Association e. Project Monitoring October 2014 onwards

WATSAN, DILG Provincial Office, DILG Regional Office No. 5 Office of the Mayor, DILG Provincial Office, DILG Regional Office No. 5, WATSAN BAC, GSO

Municipal Engineering Office, Barangay Council, People’s Organization (Purok, Youth and Women), WATSAN (Bote and MLGU) WATSAN, Municipal Treasurer, Municipal Accountant, Auditor, DILG Provincial Office, DILG Regional Office No. 5 Office of the Mayor, Barangay Council, Bote Water and Sanitation Association, LGUWATSAN Project Management Unit / LGU-WATSAN

III. Work and Financial Plan Table 3. Work and Financial Plan Project Component / Particular A. Pre-Implementation Phase 1. Creation of Municipal Water and Sanitation (WATSAN) Council and Water and Sanitation (WATSAN) Team or Project Management Unit (PMU) 2. Authorization of the Mayor to enter

Physic al Target

Cost per Item 1,000.00

Financial Requirements Beneficiary Equity

LGU-Bato 1,000.00

DILG

Total 1,000.00

into a MOA through SB Resolution 3. Conduct of community consultation 4. Water sources inventory (including salaries/wages of permanent/casual employees) 5. Organization/Reactivation of Barangay Bote Water and Sanitation Association 6. Preparation, submission and approval of the required documents and other necessary materials (including water permit) 7. MOA signing and transfer of fund Sub-Total B. Implementation Phase 1. Procurement and Delivery of Supplies and Materials 2. Construction of filtration tank, reservoir, water impounding structure and pipe laying (Materials, Labor and Contigencies) 3. Liquidation of Expenses through preparation and submission of Statement of Expenditures (SOE) and Receipt of Disbursement 4. Inauguration and Transfer of Project Management to Bote Water and Sanitation Association Subtotal C. Project Monitoring / Post Implementation Phase 1. Project Monitoring Sub-Total TOTAL PROJECT COST Project Share (%)

3,000.00 12,000.00

1,000.00

3,000.00 12,000.00

3,000.00 12,000.00

1,000.00

10,000.00

5,000.00 1,000.00

20,000.00 (in-kind: labor)

1,000.00 10,000.00

10,000.00

5,000.00 31,000.00

5,000.00 32,000.00

90,000.00

900,000.00

1,010,000.00

500.00

500.00

500.00

5,000.00

5,000.00

5,000.00

20,000.00

95,500.00

1,015,500.00

21,000.00 2%

5,000.00 5,000.00 131,500.00 12.5%

5,000.00 5,000.00 1,052,500.00

5,000.00

900,000.00 85.5%

IV. Project Management The Municipal Water and Sanitation Council shall be the over-all in-charged in ensuring the sound implementation of the Project. The Municipal Water and Sanitation Team shall function as the Project Management Unit. They shall oversee the project in its construction phase and shall be directly accountable in the imposition of proper on-and-post project management scheme, internal monitoring and evaluation procedures.

V. Project Sustainability Once completed, the project shall be turned over to the Bote Water and Sanitation Association and shall be directly responsible for the operation and management of the project. Water fee shall be imposed at the rate of P20.00 per household to cover monthly operational expenses and to cover future repair and replacement of pipes and other materials and facilities.

View more...

Comments

Copyright ©2017 KUPDF Inc.
SUPPORT KUPDF