Risk Register

February 22, 2018 | Author: Alhad Panwalkar | Category: Tunnel, Risk, General Contractor, Emergency Management, Clean Water Act
Share Embed Donate


Short Description

Risk Register...

Description

REGION/PROJECT:

Bay Tunnel

CONTRACTOR:

MJC-JV

Bay Tunnel Project ID Number PROJECT RISK REGISTER Award: $215,294,530 - NTP: 4/1/2010

Bob Mues (Phone: 206-818-7353)

PROJECT CM: CM CONSULTANT:

B

Jacobs Engineering

C

Risk Category

001

002

Printed 9/28/2012 9:45 PM

Technical

Technical

Risk Description (Hazard/Risk Scenario)

Differing soil condition results in chimney to bottom of the Bay, blow-in to TBM, lose tunnel, submerge shaft and start over.

Encounter reaches of squeezing ground causing TBM to get stuck.

Bob Mues

Prepared Date:

10/8/2010 N/A

Approved Date:

D

E

CURRENT ASSESSMENT F

G

H

I

J

K

L

M

Location

Tunnel

Tunnel

Cause

Effect

Unplanned hyperbaric intervention, and results in loss of pressure Unrecoverable to face of EPB loss of tunnel TBM, which and shaft. cannot be recovered due to nature of the material.

Differing site conditions (highly plastic TBM gets stuck clay) of the San in these Antonio reaches, and formation in impacts excess to those Contractor or at other production rate. locations than those expected from GBR.

Risk Plan Owner

Wong, Johanna

Wong, Johanna

Risk Status

Open

Open

Trigger Date

7/12/2011

7/12/2011

Expiration Date

9/12/2013

9/12/2013

Probability of Occurrence (P)

1 - Rare

2 - Unlikely

Impact to Costs, $ (S_cost)

3 - Moderate

4 - Major

O

P

Q

Impact to Costs, $

Impact to Schedule, Risk Min. Time, days Calendar Days Score (R) (S_schedule)

5 - Catastrophic 5 - Catastrophic

N/A

MITIGATION

For PPPCM use only

N

Severity of Impact (S)

Risk ID

Baseline Risk Register

Prepared By:

Approved By:

RISK IDENTITY & CAUSE A

Status Update:

15

14

520

19.5

Most Likely Time, days

520

58.5

Page 1 of 7

Max. Time, days

520

97.5

Min. Cost, $

75,000,000

1,312,350

Most Likely Cost, $

112,500,000

3,937,050

Max. Cost, $

150,000,000

6,561,750

R

S

T

U

Mitigation Action Items

Scoring Rationale

Catastrophic event loss of completed work and extensive delay in starting over.

CM/SFPUC 9 FTE @ $150.00/hr = $10,800/day and CS 8 FTE @ $100/hr = $6,400 + office @ $100/day = $6,500/day . Total Daily Rate = $17,300. Add for loss of productivity for half of 75% of the tunnel = 9,750' - 10%, 20% & 50% reduction in progress at average of $1,000 per LF.

Strategy

Mitigate

Mitigate

Risk Plan

Action Items

Action Owner

Require maintenance of TBM driving parameters (spoil removal rate records) against theoretical earth volume to be removed, and Mues, Bob tail grout quantity placed per ring of TBM advance, to verify possible "over excavation"). Verify that Contractor's remedial plan for this Maintain full-time CM condition is in place with QA inspection on the initial tunnel submittals, and TBM when tunneling that the equipment/materials Mues, Bob (per Spec 02311 noted are available and requirements). Assure functional throughout Contractor maintains tunneling. Require additional adequate off-shift remedial grouting or refill monitoring of pressure where necessary. chamber and heading, esp at high risk areas. Verify the requirements of Specification 02311 for inspections and interventions into the pressure chamber of the EPB TBM are met Mues, Bob (Pressurized Face Tunneling Plans, Method Statements, Procedures, Tunnel Safety Plans).

Verify that the TBM On-going check of thrust and thrust is at least as lubrication data from TBM as Mues, Bob specified and that the progressing. shield lubrication (bentonite injection port/injection system) Assure TBM maintenance is are functioning, performed as specified or lubrication material more (if needed), particularly Hogan, Tom mixing and supply system are functioning prior to entering squeezing ground regions. and ready, and that TBM maintenance is current.

Actual Completion

Action Status

Action Start

Action End

7/12/2011

9/12/2013

Proposed

8/1/2010

9/12/2013

Proposed

8/1/2010

9/12/2013

Active

7/12/2011

9/12/2013

Proposed

7/12/2011

9/12/2013

Proposed

RR Bay Tunnel - 2010 10 8 (DRAFT2)R2 3 pt estimates 11 12 10

REGION/PROJECT:

Bay Tunnel

CONTRACTOR:

MJC-JV

Bay Tunnel Project ID Number PROJECT RISK REGISTER Award: $215,294,530 - NTP: 4/1/2010

Bob Mues (Phone: 206-818-7353)

PROJECT CM: CM CONSULTANT:

B

Jacobs Engineering

C

Risk Category

Risk Description (Hazard/Risk Scenario)

Technical

Unforeseen ground conditions between the Franciscan Formation and San Antonio Formation interface.

003

004

Technical

005

006

Security

Regulatory

Printed 9/28/2012 9:45 PM

Hitting unforseen Franciscan Formation in reaches not surveyed in the GBR

D

E

Location

Tunnel

Tunnel

Cause

F

Effect

Interface Control of the between San tunnel (vertical/ horizontal) Antonio Formation alignment (softer ground) between the San and Franciscan Antonio Formation Formation and

Differing site conditions.

Breach in Vandalism to site or Ravenswoo perimeter fence construction d/ Newark or bypass of property, damage Shafts guard station.

Unanticipated presence of endangered species.

Bob Mues

Prepared Date:

10/8/2010 N/A

Approved Date: CURRENT ASSESSMENT G

H

I

J

K

L

M

Additional hyperbaric interventions needed to change cutterhead; productivity loss; TBM not designed for great lengths of hard ground.

Risk Plan Owner

Wong, Johanna

Wong, Johanna

Replacement or repair to finished permanent works, safety Contractor hazard to "intruders" or perpetrators.

Contractor delayed from starting work at Protected Newark and/or species NewarkShaf additional encountered t restrictions to during surveys site or construction. implemented during site activities.

Wong, Johanna

Risk Status

Open

Open

Trigger Date

3/1/2013

7/12/2011

Expiration Date

7/5/2013

3/12/2013

Probability of Occurrence (P)

Impact to Costs, $ (S_cost)

4 - Likely

0 - Contractor Risk

2 - Unlikely

3 - Moderate

O

P

Q

Impact to Costs, $

Impact to Schedule, Risk Min. Time, days Calendar Days Score (R) (S_schedule)

3 - Moderate

N/A

MITIGATION

For PPPCM use only

N

Severity of Impact (S)

Risk ID

Baseline Risk Register

Prepared By:

Approved By:

RISK IDENTITY & CAUSE A

Status Update:

0

3 - Moderate

0

10

Most Likely Time, days

0

15

Max. Time, days

0

20

Min. Cost, $

0

673,000

Most Likely Cost, $

0

1,009,500

R

S

Max. Cost, $

Scoring Rationale

Risk Plan

Action Items

Assure Contractor submittals Although this subsurface discontinuity are in on schedule and is well defined in the properly reviewed and Mitigate GBR, assure that approved.with any Assist Contractor Contractor's EPB TBM other special measures design includes a needed. suitable guidance

0

1,346,000

Strategy

Open

6/1/2010

3/1/2011

5/15/2015

5/15/2015

5 - Frequent

2 - Unlikely

0 - Contractor Risk

2 - Minor

2 - Minor

2 - Minor

0

5

0

20

0

40

Page 2 of 7

0

60

0

766,000

0

1,532,000

U

CM/SFPUC 9 FTE @ $150.00/hr = $10,800/day and CS 8 FTE @ $100/hr = $6,400 + office @ $100/day = $6,500/day . Total daily cost = $17,300. Add for loss of productivity using $50,000 per day X the additional days to accomplish the work.

Assure that the Contractor has planned to perform maintenance Assure Contractor submittals interventions prior to are in on schedule and Mitigate each reach with properly reviewed and geotechnical data approved. "gaps"; assure that back-up equipment and supplies are available.

0

2,298,000

Contractor Risk

CM/SFPUC 9 FTE @ $150.00/hr = $10,800/day and CS 8 FTE @ $100/hr = $6,400 + office @ $100/day = $6,500/day + Standby Costs @ $21,000/day = $32,500. Total daily rate = $38,300/day. Standby costs include equipment, security, core crew costs, tunnel lighting & ventilation, equipment maintenance, etc.

Mitigate

Mitigate

Monitor and implement safety and security plan.

Actual Completion

Action Status

Action Owner

Action Start

Action End

Mues, Bob

1/1/2013

7/5/2013

Proposed

Mues, Bob

1/1/2013

7/5/2013

Proposed

Mues, Bob

1/1/2013

7/5/2013

Proposed

6/1/2010

3/2/2015

Active

8/1/2010

5/15/2015

Active

On-going check of perimeter fencing integrity and site sign Hogan, Tom visibility. On-going check of security Wakefield, guard's presence on site Rick 24/7. Open

T

Mitigation Action Items

Work area lighting functional (include winter evenings).

Contractor

11/15/2010

12/31/2014

Proposed

Maintain and repair (if needed) fencing.

Contractor

8/1/2010

5/15/2015

Active

Lock-ups inside site and provide safety covers over potential hazards such as pipe trench at night.

Contractor

12/1/2010

5/15/2015

Proposed

1/1/2011

4/1/2011

Proposed

2/1/2011

3/1/2011

Proposed

2/1/2011

5/1/2011

Proposed

Coordinate with SFPUC BEM to ensure they obtain a Peterson, Section 2081 Take Megan Authorization from CDFG prior to working at Newark. Conduct preconstruction surveys prior to working at Work in a proactive Wilkerson, Newark and relocate CTS manner to anticipate Cullen and/or individuals, if found. Hand issues before they Craighead, become delays or cost excavate burrows during the Kim dry season if work begins changes. after May 1. Wilkerson, Cullen; Monitor installation of exclusion fencing and initial Craighead, Kim; ground-disturbing activities. Peterson, Eric

RR Bay Tunnel - 2010 10 8 (DRAFT2)R2 3 pt estimates 11 12 10

REGION/PROJECT:

Bay Tunnel

CONTRACTOR:

MJC-JV

Bay Tunnel Project ID Number PROJECT RISK REGISTER Award: $215,294,530 - NTP: 4/1/2010

Bob Mues (Phone: 206-818-7353)

PROJECT CM: CM CONSULTANT:

B

Jacobs Engineering

C

007

008

Risk Category

Regulatory

Regulatory

009

010

Printed 9/28/2012 9:45 PM

Safety

Safety

Risk Description (Hazard/Risk Scenario)

D

E

F

Location

Cause

Effect

Restrictions due to Protected birds nesting specialnesting in status shorebirds Contractor adjacent Ravenswoo (CA clapper rail, delayed due marshlands d/ Newark implementation black rail, least tern, during future Shafts etc.) moving into an of buffer zones. nesting active construction seasons. area.

Union Sanitary District prohibits discharge of construction water into their system

Handling of contaminated groundwater/soil at Newarks shaft site in excess of amount specified.

Injuries resulting from, or while working in, compressed air environment.

Bob Mues

Prepared Date:

10/8/2010 N/A

Approved Date: CURRENT ASSESSMENT G

H

I

J

K

L

M

Newark Shaft

Newark

Risk Plan Owner

Wong, Johanna

Contamination Additional is too high and permits, water Contractor does not comply treatment, or offwith USD hauling of water. requirements

Worker health & safety concerns if contaminated groundwater not Gravel lenses handled across site appropriately. causing greater Contractor may infiltration or be required to existing shut-down contaminant Contractor dewatering plume has operation (and different not be allowed constituents or to discharge by higher USD) if concentrations. contaminants not properly treated prior to disposal.

Work will stop, Exposure to compressed air worker must be Ravenswoo at face of TBM transported to Contractor surface and d Shaft during inspections and quickly treated in maintenance. decompression chamber or at

Risk Status

Open

Open

Open

Trigger Date

2/11/2011

3/1/2011

3/1/2013

Expiration Date

5/15/2015

8/1/2011

12/31/2013

Probability of Occurrence (P)

3 - Possible

3 - Possible

5 - Frequent

Impact to Costs, $ (S_cost)

2 - Minor

0 - Contractor Risk

0 - Contractor Risk

3 - Moderate

3 - Moderate

O

P

Q

Impact to Costs, $

Impact to Schedule, Risk Min. Time, days Calendar Days Score (R) (S_schedule)

2 - Minor

N/A

MITIGATION

For PPPCM use only

N

Severity of Impact (S)

Risk ID

Baseline Risk Register

Prepared By:

Approved By:

RISK IDENTITY & CAUSE A

Status Update:

9

0

0

40

0

0

Most Likely Time, days

80

0

0

Max. Time, days

160

0

0

Min. Cost, $

1,532,000

0

0

Most Likely Cost, $

3,064,000

0

0

7/12/2011

9/12/2013

3 - Possible

0 - Contractor Risk

3 - Moderate

0

0

0

Page 3 of 7

0

0

0

S

T

U

Mitigation Action Items

Max. Cost, $

6,128,000

0

0

Scoring Rationale

CM/SFPUC 9 FTE @ $150.00/hr = $10,800/day and CS 8 FTE @ $100/hr = $6,400 + office @ $100/day = $6,500/day + Standby Costs @ $21,000/day = $32,500. Total daily rate = $38,300/day. Standby costs include equipment, security, core crew costs, tunnel lighting & ventilation, equipment maintenance, etc.

Contractor Risk

Contractor Risk

Strategy

1/1/2011

4/1/2011

Proposed

2/1/2011

3/1/2015

Proposed

Peterson, Megan

2/1/2011

5/1/2015

Proposed

Contractor

2/1/2011

6/1/2011

Proposed

Contractor

12/1/2010

6/1/2011

Proposed

Contractor

12/1/2010

6/1/2010

Proposed

CM QA Inspectors to verify that Contractor has tested the water, and has a test plan in place to continually Hogan, Tom test and manage the water throughout the Newark shaft installation work.

3/1/2013

12/31/2013

Proposed

Verification by ECM, QA Inspectors assure that EIs, and QA Inspectors the shaft is sealed to avoid that Contractor has its contaminated water from plan, permits, disposal interfering with the tunnel site, and resources for Mitigate completion and installation of this contaminated water Hogan, Tom the final lining pipe into the in place prior to tunnel and shaft, and the commencement of the surface pipe Newark Shaft installation/connection to the installation. existing BDPL1.

3/1/2013

12/31/2013

Proposed

Peterson, Megan

3/1/2013

12/31/2013

Proposed

Mues, Bob

7/12/2011

9/12/2013

Proposed

Mues, Bob

5/1/2011

9/12/2013

Proposed

Look into the feasibility of alternative mitigation Peterson, measures as opposed to Megan implementing a buffer zone (e.g., barriers, etc.) Conduct preconstruction Wilkerson, surveys according to the Cullen and/or MMRP during the early Craighead, portion of the 2011, 2012, Kim 2013, 2014 and 2015 nesting seasons. Maintain an open dialog with regulatory agencies and take proactive steps to minimize delays.

Mitigate

0

Contractor Risk

Action Owner

Action Status

Action End

Continually monitor status of birds in the area and develop an initial strategy for managing this risk.

Action Items

Actual Completion

Action Start

Mitigate

Risk Plan

Initiate discussions with USD early, and prior to moving into NVL to understand the requirements/restrictions Obtain a NPDES VOC permit as a backup in the event Develop a water USD discharge is not discharge contingency allowed. plan Evaluate additional design techniques to limit the influx of groundwater into shaft and trench for tie-ins (e.g., extending Ranger's cut-off wall).

On-going verification that Contractor meets requirements of their Union Sanitary District discharge permit with dewatering operation.

Open

R

Ensure contractor On-going verification that provides the tools, Contractor's hyperbaric work equipment, and facilities are operational. Mitigate hyperbaric work Assure Contractor's facilities, and follows contingency planning is in required contingency place prior to the planning for carrying out interventions.

RR Bay Tunnel - 2010 10 8 (DRAFT2)R2 3 pt estimates 11 12 10

REGION/PROJECT:

Bay Tunnel

CONTRACTOR:

MJC-JV

Bay Tunnel Project ID Number PROJECT RISK REGISTER Award: $215,294,530 - NTP: 4/1/2010

Bob Mues (Phone: 206-818-7353)

PROJECT CM: CM CONSULTANT:

B

Jacobs Engineering

C

Risk Category

011

Safety

Technical

012

013

Community

Risk Description (Hazard/Risk Scenario)

Decompression sickness

Bob Mues

Prepared Date:

10/8/2010 N/A

Approved Date:

D

E

CURRENT ASSESSMENT F

G

H

I

J

K

L

M

Location

Tunnel

Blow-in through the forward pressure bulkhead of the EPB TBM (the bulkhead containing the face pressure monitoring Ravenswoo instruments beyond d Shaft which is the earth plug, water table pressure and the Bay trying to come in).

Cause

Effect

Risk Plan Owner

Work will stop, Exposure to worker must be compressed air transported to at face of TBM surface and Contractor during quickly treated in inspections and decompression chamber or at maintenance. hospital.

Unintended penetration of the EPBM pressure bulkhead.

Potential loss of EPB TBM and Contractor tunnel.

Contractor's Resident failure to comply Potential work complaints, and with noise and stoppage until irritation, with Ravenswoo vibration code complaints are construction noise, d requirements, or addressed and dust, lighting, mitigated. if compliant, vibration, etc. public irritation.

Contractor

Risk Status

Trigger Date

Expiration Date

Probability of Occurrence (P)

Impact to Costs, $ (S_cost)

N/A

MITIGATION

For PPPCM use only

N

Severity of Impact (S)

Risk ID

Baseline Risk Register

Prepared By:

Approved By:

RISK IDENTITY & CAUSE A

Status Update:

O

P

Q

Impact to Costs, $

Impact to Schedule, Risk Min. Time, days Calendar Days Score (R) (S_schedule)

Most Likely Time, days

Max. Time, days

Min. Cost, $

Most Likely Cost, $

014

015

Technical

Technical

Lack of sufficient power supply.

Water leakage around the perimeter seal or through the shaft floor slab (tremie concrete).

More abrasive

Printed 9/28/2012 9:45 PM

Wong, Johanna

Contractor does not follow Potentially have Ravenswoo specifications/ to replace shaft Contractor d Shaft Contractor floor slab. means & methods faulty.

Different subsurface

Excessive TBM head, face chamber, cutter, and screw conveyor wear

S

Max. Cost, $

Scoring Rationale

Strategy

Risk Plan

Action Items

Action Owner

Open

Open

7/12/2011

7/12/2011

7/1/2010

9/12/2013

9/12/2013

5/15/2015

3 - Possible

2 - Unlikely

3 - Possible

0 - Contractor Risk

0 - Contractor Risk

0 - Contractor Risk

3 - Moderate

5 - Catastrophic

2 - Minor

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

0

Open

Open

3/31/2011

11/15/2010

9/12/2013

6/1/2011

2 - Unlikely

2 - Unlikely

3 - Moderate

0 - Contractor Risk

3 - Moderate

2 - Minor

11

0

20

0

60

0

180

0

766,000

0

2,298,000

0

0

0

0

Contractor Risk

Contractor Risk

Contractor Risk

6,894,000

0

CM/SFPUC 9 FTE @ $150.00/hr = $10,800/day and CS 8 FTE @ $100/hr = $6,400 + office @ $100/day = $6,500/day + Standby Costs @ $21,000/day = $32,500. Total daily rate = $38,300/day. Standby costs include

Contractor Risk

CM/SFPUC 9 FTE @ $150.00/hr = $10,800/day and CS 8 FTE @ $100/hr = $6,400 + office @ $100/day = $6,500/day

Wong,

Page 4 of 7

U

Mitigate

Require expanded engineering controls for sound attenuation (mufflers/enclosures of loud Monitor site work to equipment). identify problem before Require increased distance (if possible) from sound recognized by the source or sound walls (if Mitigate public; provide required). proactive outreach to Remove/change out the community of upcoming source or noise emitter. activities.

4/12/2011

9/12/2013

Proposed

4/12/2011

9/12/2013

Proposed

4/12/2011

9/12/2013

Proposed

Mues, Bob

5/1/2011

9/12/2013

Proposed

Mues, Bob

5/1/2011

9/12/2013

Proposed

Mues, Bob

7/1/2010

5/15/2015

Active

Mues, Bob

7/1/2010

5/15/2015

Active

Mues, Bob

7/1/2010

5/15/2015

Active

Kerby, Christina

7/1/2010

5/15/2015

Active

4/1/2010

3/31/2011

Active

4/1/2010

3/31/2011

Active

9/15/2010

6/1/2011

Active

2/1/2011

6/1/2011

Proposed

2/1/2011

6/1/2011

Proposed

7/12/2011

9/12/2013

Proposed

Hold monthly coordination Wong, meetings with PG&E and Johanna Closely monitor Contractor to mitigate issues. progress of the Mitigate temporary construction Take appropriate steps to power installations by avoid any SFPUC caused Mues, Bob PG&E. delays.

Verify Contractor follows Mues, Bob submittals and method statements. Verify that Contractor Carefully inspect slab for follows specifications, Hogan, Tom leakage (following Mitigate places shaft floor slabs unwatering and cleaning). accordingly, inspect for If required, verify submittal of conformance. Contractor's remedial plan to Mues, Bob repair leaks and assure materials/methods are viable. Check to increase spare part inventory once condition is verified.

Action Status

Action End

Mues, Bob Compressed air "hyperbaric" work cannot commence before all plans and Require Contractor to adhere procedures are to decompression acceptable pursuant to procedures and hyperbaric Mues, Bob California labor safety work plans. codes and standards, Require Contractor to have including medical resources in place decompression for response, transport, and process, equipment, Mues, Bob care of decompression and tables. sickness, either on site of at nearby hospital or other qualified facilities.

Assure Contractor's plans and employee training Contractor's plans must specifically address high risk nature of work around the address the high risk of pressure bulkhead. any maintenance work around the pressure Mitigate bulkhead and the dangers of any penetration (separate Assure Contractor provides from the hyperbaric training of high risk work to intervention plans). any new workers involved in tunneling operation.

Actual Completion

Action Start

Require all equipment and systems for work under pressure be in place and tested prior to commencement of work

Open

T

Mitigation Action Items

Provide on-going updates to community via mailers, door hangers, blog of activities.

Delay to start of PG&E fails to tunneling with provide power insufficient Ravenswoo service when power supply for d required; PG&E TBM; loss of power failure. power during tunneling.

R

Mues, Bob

Assure that there are adequate spare parts

RR Bay Tunnel - 2010 10 8 (DRAFT2)R2 3 pt estimates 11 12 10

REGION/PROJECT:

Bay Tunnel

CONTRACTOR:

MJC-JV

Bay Tunnel Project ID Number PROJECT RISK REGISTER Award: $215,294,530 - NTP: 4/1/2010

Bob Mues (Phone: 206-818-7353)

PROJECT CM: CM CONSULTANT:

B

Jacobs Engineering

C

Risk Category

016

Technical

017

018

019

020

021

022

Safety

Regulatory

Regulatory

Regulatory

Regulatory

Risk Description (Hazard/Risk Scenario)

ground conditions than anticipated.

Damage to BDPLs 1& 2 or PG&E transmission lines due to crane tip over.

D

E

F

Location

Tunnel

Shafts

Cause

Effect

materials than and hyperbaric those presented maintenance of in the GBR. those parts that are exposed to ground pressure.

Unbalanced/ excessive load or unstable crane platform base during installation of diaphragm slurry wall rebar

G

H

I

J

K

L

Carelessness Inadvertantly and/or not injuring or killing an following project endangered, Ravenswoo requirements; threatened, or fully d/ Newark accidental collisions with protected species (SMHM, CTS, etc.) equipment; work in wetlands, etc.

Subsurface Easement is not obtained from Management Cargill, SamTrans, and Mid Peninsula Open Space District.

Tunnel

Tunnel

Terms of Agreement not acceptable to parties; Board of Supervisors reject purchase of subsurface easement.

Risk Status

Trigger Date

Expiration Date

Probability of Occurrence (P)

Impact to Costs, $ (S_cost)

Wong, Johanna

Open

7/12/2011

9/12/2013

3 - Possible

3 - Moderate

Wong, Johanna

Work stoppage by USFWS and/or CDFG until additional Contractor mitigation measures can be developed/ approved.

Additional time Additional and costs requirements incurred by imposed by Contractor and higher risk level Additional RWQCB CM team requirements as a under NPDES Ravenswoo associated with General result of risk d/Newark sampling, assessment prior to Construction monitoring and Stormwater Sept 2, 2011. reporting; Permit due to additional duration of RWQCB project. coordination. Various: BCDC want removal of BDPLs 1&2; BCDC may claim jurisdiction below the Bay; subsurface easements are

Risk Plan Owner

Electrocution, if PG&E transmission lines hit; power Contractor outage. Service outage, if BDPLs hit; damage requiring

Bay Margin is known to Unanticipated contain Work stoppage cultural or prehistoric and until the paleontological Ravenswoo paleontological resource can be properly discoveries during d/ Newark resources, but evaluated/ shaft excavation, construction tunneling, or tie-ins methods recovered. prevent surveys and monitoring

BCDC will not issue permit for tunneling under the Bay.

M

10/8/2010 N/A

Cannot start tunnel excavation.

Cannot start tunnel excavation.

Wong, Johanna

Wong, Johanna

Wong, Johanna

Open

Open

Open

Open

Open

Open

8/1/2010

8/1/2010

5/20/2010

5/20/2010

9/20/2010

9/20/2010

11/15/2010

5/15/2015

5/15/2015

5/15/2015

6/30/2011

6/30/2011

3 - Possible

2 - Unlikely

1 - Rare

4 - Likely

2 - Unlikely

2 - Unlikely

0 - Contractor Risk

2 - Minor

0 - Contractor Risk

1 - Insignificant

3 - Moderate

2 - Minor

4 - Major

1 - Insignificant

5 - Catastrophic 5 - Catastrophic

5 - Catastrophic 5 - Catastrophic

O

P

Q

Impact to Costs, $

Impact to Schedule, Risk Min. Time, days Calendar Days Score (R) (S_schedule) 2 - Minor

N/A

MITIGATION

For PPPCM use only

N

12

0

5

0

7

21

21

20

0

20

0

0

60

60

Max. Time, days

Min. Cost, $

Most Likely Cost, $

Max. Cost, $

30

40

1,346,000

2,019,000

2,692,000

0

40

0

0

120

120

0

60

0

0

240

240

0

766,000

0

50,000

1,488,000

1,488,000

0

1,532,000

0

100,000

2,976,000

2,976,000

0

2,298,000

0

250,000

Scoring Rationale

$100/day = $6,500/day . Total daily cost = $17,300. Add $1M, $1.5M & $2M for replacement parts, lost time for replacement and lost productivity.

Contractor Risk

CM/SFPUC 9 FTE @ $150.00/hr = $10,800/day and CS 8 FTE @ $100/hr = $6,400 + office @ $100/day = $6,500/day + Standby Costs @ $21,000/day = $32,500. Total Daily Rate = $38,300/day. Standby costs include equipment, security, core crew costs, tunnel lighting & ventilation, equipment

Contractor Risk

Additional SWPP requirements and monitoring. Estimated costs by PUC/CM Team.

S

T

U

Strategy

Mitigate

Mitigate

Mitigate

Risk Plan

adequate spare parts available at start and throughout tunneling.

Assure Contractor is well prepared with acceptable JHAs for each portion of slurry wall construction.

Action Status

Action Owner

Action Start

Action End

Issue field order for immediate spare parts procurement, if schedule (long lead item) becomes an issue.

Mues, Bob

7/12/2011

9/12/2013

Proposed

Check that Contractor has provided an adequate base for crane support.

Hogan, Tom

8/1/2010

12/1/2010

Active

Check that Contractor is following load limits and Hogan, Tom protocol as perscribed in the JHAs.

8/1/2010

12/1/2010

Active

Hire specialty archaeological and paleontological monitors in the event of discoveries.

Peterson, Megan

12/1/2010

2/1/2010

Completed

Peterson, Eric

4/1/2010

12/31/2014

Active

Peterson, Megan

4/1/2010

12/31/2014

Active

Peterson, Eric

4/1/2010

12/31/2014

Active

Peterson, Eric

4/1/2010

12/31/2014

Active

Peterson, Megan

12/1/2010

3/1/2011

Active

4/1/2010

5/31/2010

Completed

4/1/2011

10/30/2010

Active

5/20/2010

3/1/2015

Active

5/20/2010

5/1/2015

Active

Implement existing Ensure that worker training is procedures for conducted according to the unanticipated MMRP and specifications. discoveries and work quickly to mobilize Coordinate with the specialists to the field. Contractor in the event of a find to quickly assess the significance and possible need for work stoppage.

Implement requirements as specified in project Mitigate documents and develop comprehensive training program

Actual Completion

Action Items

Inspect the work area daily for any cover or other potential habitat. Train individuals on significance of "take" of the species.Conduct tailgate trainings prior to working in sensitive areas. Coordinate with SFPUC BEM to ensure the 2081for CTS is in hand prior to work beginning Newark

Design water treatment Host SWPPP workshop for plant to accommodate Bay Division Region to Peterson, new permit faciliate understanding of Megan requirements (e.g., requirements. modular system that Develop expandable can easily be Contractor modular WTP for expanded). Close Mitigate Ravenswood. coordination between CM team provides daily Peterson, CM team and environmental inspection to Eric and Contractor to help identify issues. Mirzad, Slay understand new Provide QSP to oversee site requirements and Contractor compliance with NPDES prepare risk permit. assessment/SWPPP

5,952,000

CM/SFPUC 9 FTE @ $150.00/hr = $10,800/day and CS 8 FTE @ $100/hr = $6,400 + office @ $100/day = $6,500/day + Standby Costs @ $7,500/day = $14,000/day. Total Daily Rate =

Avoid

Work with BCDC and City Attorney to get agreements in place well before the start of tunneling.

Work with BCDC. Enlist help from City Attorney to avoid BDCD claiming jurisdiction below the Bay.

Zhang, Yin Lan

9/20/2010

6/30/2011

Active

5,952,000

CM/SFPUC 9 FTE @ $150.00/hr = $10,800/day and CS 8 FTE @ $100/hr = $6,400 + office @ $100/day = $6,500/day + Standby Costs @ $7,500/day = $14,000/day. Total Daily Rate = $24,800/day. Standby costs include equipment, security,

Avoid

Work with property owners and City Attorney.

Finalize Agreement with Property Owners. Submit Agenda Item to the Board of Supervisors

Morelli, Brian

9/20/2010

30-Jun-11

Active

Check on-going monitoring of BDPLs and check that data is consistent with no movement.

Hnat, Steve

8/1/2010

5/15/2015

Active

CM/SFPUC 9 FTE @ $150.00/hr = $10,800/day and CS 8 FTE @ $100/hr = $6,400 + office @ Page 5 of 7

R

Mitigation Action Items

Most Likely Time, days

BDPLs will require owner repair, which

Printed 9/28/2012 9:45 PM

Bob Mues

Prepared Date:

Approved Date: CURRENT ASSESSMENT Severity of Impact (S)

Risk ID

Baseline Risk Register

Prepared By:

Approved By:

RISK IDENTITY & CAUSE A

Status Update:

Assure Contractor installs and monitors survey monuments

RR Bay Tunnel - 2010 10 8 (DRAFT2)R2 3 pt estimates 11 12 10

REGION/PROJECT:

Bay Tunnel

CONTRACTOR:

MJC-JV

Bay Tunnel Project ID Number PROJECT RISK REGISTER Award: $215,294,530 - NTP: 4/1/2010

Bob Mues (Phone: 206-818-7353)

PROJECT CM: CM CONSULTANT:

B

Jacobs Engineering

C

Risk Category

Risk Description (Hazard/Risk Scenario)

Operations

Failure of BDPL1 or 2 in vicinity of Ravenswood or Newark shafts.

023

024

Printed 9/28/2012 9:45 PM

Operations

Delay in shut-down schedule.

Bob Mues

Prepared Date:

10/8/2010 N/A

Approved Date:

D

E

CURRENT ASSESSMENT F

G

H

I

J

K

L

M

Location

Cause

Effect

Risk Plan Owner

owner repair, which may be problematic Possibly caused by regarding access Ravenswood/ non-construction and safety concerns Mazza, Paul means, such as age Newark with construction related joint failure. operations on-going nearby. May cause some delay.

Ravenswood

Potentially weeks of Failure of the delay while the contractor supplied submersible pumps pumps are either repaired or rental during disinfection units are located; it of the pipe within might also result in the tunnel. re-disinfecting, etc.

Contractor

Risk Status

Open

Open

Trigger Date

8/1/2010

9/1/2014

Expiration Date

5/15/2015

2/10/2015

Probability of Occurrence (P)

2 - Unlikely

2 - Unlikely

Impact to Costs, $ (S_cost)

3 - Moderate

0 - Contractor Risk

3 - Moderate

O

P

Q

Impact to Costs, $

Impact to Schedule, Risk Min. Time, days Calendar Days Score (R) (S_schedule)

2 - Minor

N/A

MITIGATION

For PPPCM use only

N

Severity of Impact (S)

Risk ID

Baseline Risk Register

Prepared By:

Approved By:

RISK IDENTITY & CAUSE A

Status Update:

11

0

10

0

Most Likely Time, days

20

0

Page 6 of 7

Max. Time, days

30

0

Min. Cost, $

483,000

0

Most Likely Cost, $

866,000

0

R

S

T

U

Mitigation Action Items

Max. Cost, $

1,249,000

0

Scoring Rationale

$6,400 + office @ $100/day = $6,500/day + Standby Costs @ $21,000/day = $32,500. Total Daily Rate = $38,300/day. Standby costs include equipment, security, core crew costs, tunnel lighting & ventilation,

Contractor Risk

Strategy

Mitigate

Mitigate

Risk Plan

monitors survey monuments on BDPLs throughout construction; consider contingency planning for Ops access in the event that BDPLs fail and need to be shut-down and repaired adjacent to construction.

Actual Completion

Action Status

Action Items

Action Owner

Action Start

Action End

Assure Contractor's means and methods are consistent with specifications for protection of existing improvements.

Mues, Bob

8/1/2010

5/15/2015

Active

Develop contingency plan in the event of BDPL 1 or 2 failure and need for Ops access and repair.

Mues, Bob

12/1/2010

5/15/2015

Proposed

Contractor

9/1/2014

2/10/2015

Proposed

Mues, Bob

9/1/2014

2/10/2015

Proposed

Assure Contractor's Check functioning of submersible submersible pumps are pumps before planned shut-down. functioning well before the start of shut-down; check that Check suppliers through Contractor supplies of back-up pumps to verify supply of available back-up are readily available (if pumps. needed).

RR Bay Tunnel - 2010 10 8 (DRAFT2)R2 3 pt estimates 11 12 10

REGION/PROJECT:

Bay Tunnel

CONTRACTOR:

MJC-JV

Bay Tunnel Project ID Number PROJECT RISK REGISTER Award: $215,294,530 - NTP: 4/1/2010

Bob Mues (Phone: 206-818-7353)

PROJECT CM: CM CONSULTANT:

B

Jacobs Engineering

C

Risk Category

025

Safety

026

027

Security

Operations

Printed 9/28/2012 9:45 PM

Risk Description (Hazard/Risk Scenario)

D

Location

Earthquake (Major) Bay Tunnel

Terrorism - Direct Impact

Bob Mues

Prepared Date:

10/8/2010 N/A

Approved Date:

E

CURRENT ASSESSMENT F

G

H

I

J

K

L

M

Cause

Effect

Risk Plan Owner

Risk Status

Trigger Date

Expiration Date

Probability of Occurrence (P)

Act of God

Temporary site facilities may be damaged. May have to reexcavate shaft and portions of the tunnel to reaccess. Integrity of shaft and tunnel possisbly compromised.

Wong, Johanna

Open

8/5/2010

3/2/2015

1 - Rare

Physical Bomb, projectile damage or of any kind, biological Bay Tunnel biological contamination to contamination SFPUC Water etc. System.

Failure to meet contractual shutBay Tunnel down schedule for BDPL1 and BDPL2

Operations or other projects don't allow shutdown to make tie in at appropriate time.

Unable to complete tie in of Bay Tunnel (BDPL5) to BDPLs 1 and 2.

Wong, Johanna

Wong, Johanna

Open

Open

8/5/2010

9/14/2014

3/2/2015

2/10/2015

1 - Rare

1 - Rare

Impact to Costs, $ (S_cost)

5 - Catastrophic 5 - Catastrophic

2 - Minor

2 - Minor

O

P

Q

Impact to Costs, $

Impact to Schedule, Risk Min. Time, days Calendar Days Score (R) (S_schedule)

5 - Catastrophic 5 - Catastrophic

N/A

MITIGATION

For PPPCM use only

N

Severity of Impact (S)

Risk ID

Baseline Risk Register

Prepared By:

Approved By:

RISK IDENTITY & CAUSE A

Status Update:

15

15

4

0

0

30

Max. Time, days

Min. Cost, $

Most Likely Cost, $

Max. Cost, $

Scoring Rationale

Strategy

Risk Plan

0

0

0

0

0

Contractor Risk

Accept

Implementation of Safety Plan.

60

Page 7 of 7

0

365

0

100,000

0

200,000

S

T

U

Mitigation Action Items

Most Likely Time, days

0

R

0

Contractor Risk

300,000

Possible de-mob/remob of contractor or shift work to another contractor if the window is missed and has to be rescheduled.

Action Items

Action Owner

Actual Completion

Action Status

Action Start

Action End

9/1/2013

2/10/2015

Proposed

9/1/2014

2/10/2015

Proposed

Ensure proper physical security elements (fencing, Mitigation and response barriers, gates, etc.) and through additional ACAMS (access control and security and improved monitoring system) are in emergency place at all critical facilities. Mitigate preparedness to avoid Communications (ensure any damage that might result from a terrorism safety plan, standard protcol) event.

Keep current with WSIP program shut-down Mitigate schedules, contingency plans, and any changes.

Work with Ops on contingency schedule (either before or after) the Wong, Johanna planned shut-down to see if alternate date can be found.

Assure Contractor has all required shut-down submittals in on schedule.

Mues, Bob

RR Bay Tunnel - 2010 10 8 (DRAFT2)R2 3 pt estimates 11 12 10

View more...

Comments

Copyright ©2017 KUPDF Inc.
SUPPORT KUPDF