LEVEL 1 - RISK REGISTER

Example Project

Project Name:

DIST- EA

Risk Identification Status

ID #

Type

Category

Active

160

Threat

Design

Active

161

Threat

Active

162

Threat

R/W

Active

163

Threat

Construction

Active

164

Threat

Title Survey File

Environmental Challenge to EIR

Design

Active

165

Threat

Active

166

Threat

R/W

Active

167

Threat

Construction

Delay of R/W Acquisition

Buried Objects

Supplemental EIR

Environmental Nesting birds

Additional R/W

Hazardous Materials

08-1234

Project Manager

Risk Rating Risk Statement

Current status/assumptions

Inaccuracies or incomplete information in the survey file could lead to rework of the design. Potential lawsuits may challenge the environmental report, delaying the start of construction or threatening loss of funding. Due to the large number of parcels and businesses, may have to use the condemnation process to acquire R/W, which could delay start of construction by up to one year, increasing construction costs and extend the time for COS. Unanticipated buried man-made objects uncovered during construction require removal and disposal resulting in additional costs. A design change that is outside of the parameters contemplated in the Environmental Document triggers a supplemental EIR which causes a delay due to the public comment period. Nesting birds, protected from harassment under the Migratory Bird Treaty Act, may delay construction during the nesting season. Due to the complex nature of the staging, additional right of way or construction easements may be required to complete the work as contemplated, resulting in additional cost to the project. Hazardous materials encountered during construction will require an onsite storage area and potential additional costs to dispose

Level 1 Risk Register

Priority Rating

Rationale for Rating

PM Person Risk Response

Strategy

Response Actions

Risk Owner

Updated

Medium

Mitigate

Verify that the survey file is accurate and complete

Sam Owner

10/12/2012

Low

Mitigate

Address concerns of stakeholders and public during environmental process

EIR Person

11/23/2012

High

Accept

R/W Person

11/23/2012

Medium

Accept

Include a Supplemental Work item to cover this risk.

PM

11/24/2012

Low

Avoid

Monitor design changes against ED to avoid reassessment of ED unless the opportunity outweighs the threat

Design Manager

11/24/2012

Low

Mitigate

Schedule contract work to avoid the nesting season or remove nesting habitat before starting work.

PM/RE

11/24/2012

Low

Mitigate

Re-sequence the work to enable R/W Certification

R/W Person

11/24/2012

Medium

Accept

Ensure storage space will be available

PM

11/24/2012

Example Project

Project Name:

LEVEL 2 - RISK REGISTER

DIST- EA

08-1234

Probability

Cost Impact

Project Manager

Risk Identification Status

ID #

Type

Category

Active

160

Threat

Design

Active

161

Threat

Active

162

Threat

R/W

Active

163

Threat

Construction

Title Survey File

Environmental Challenge to EIR

Active

164

Threat

Design

Active

165

Threat

Active

166

Threat

R/W

Active

167

Threat

Construction

Delay of R/W Acquisition

Buried Objects

Supplemental EIR

Environmental Nesting birds

Additional R/W

Hazardous Materials

Risk Statement Inaccuracies or incomplete information in the survey file could lead to rework of the design. Potential lawsuits may challenge the environmental report, delaying the start of construction or threatening loss of funding. Due to the large number of parcels and businesses, may have to use the condemnation process to acquire R/W, which could delay start of construction by up to one year, increasing construction costs and extend the time for COS. Unanticipated buried man-made objects uncovered during construction require removal and disposal resulting in additional costs. A design change that is outside of the parameters contemplated in the Environmental Document triggers a supplemental EIR which causes a delay due to the public comment period. Nesting birds, protected from harassment under the Migratory Bird Treaty Act, may delay construction during the nesting season. Due to the complex nature of the staging, additional right of way or construction easements may be required to complete the work as contemplated, resulting in additional cost to the project. Hazardous materials encountered during construction will require an onsite storage area and potential additional costs to dispose

PM Person

Risk Assessment Current status/assumptions

Cost Score Time Impact

Risk Response

Time Score

Rationale

Strategy

Response Actions

Risk Owner

Updated

Sam Owner

10/12/2012

EIR Person

11/23/2012

R/W Person

11/23/2012

3-Moderate

2 -Low

6

4 -Moderate

12

Mitigate

Verify that the survey file is accurate and complete

1-Very Low

4 -Moderate

4

8 -High

8

Mitigate

Address concerns of stakeholders and public during environmental process

3-Moderate

4 -Moderate

12

8 -High

24

Accept

3-Moderate

4 -Moderate

12

4 -Moderate

12

Accept

Include a Supplemental Work item to cover this risk.

PM

11/24/2012

3-Moderate

4 -Moderate

12

8 -High

24

Avoid

Monitor design changes against ED to avoid reassessment of ED unless the opportunity outweighs the threat

Design Manager

11/24/2012

2-Low

2 -Low

4

8 -High

16

Mitigate

Schedule contract work to avoid the nesting season or remove nesting habitat before starting work.

PM/RE

11/24/2012

3-Moderate

8 -High

24

8 -High

24

Mitigate

Re-sequence the work to enable R/W Certification

R/W Person

11/24/2012

2-Low

2 -Low

4

1 -Very Low

2

Accept

Ensure storage space will be available

PM

11/24/2012

Level 2 Risk Register

LEVEL 3 - RISK REGISTER

Example Project

Project Name:

DIST- EA

Project Manager

08-1234

PM Person

Risk Assessment Risk Identification Status

ID #

Category

Active

160

Design

Active

161

Active

162

R/W

Active

163

Construction

Title Survey File

Environmental Challenge to EIR

Active

164

Design

Active

165

Active

166

R/W

Active

167

Construction

Delay of R/W Acquisition

Buried Objects

Supplemental EIR

Environmental Nesting birds

Additional R/W

Hazardous Materials

Risk Statement Inaccuracies or incomplete information in the survey file could lead to rework of the design. Potential lawsuits may challenge the environmental report, delaying the start of construction or threatening loss of funding. Due to the large number of parcels and businesses, may have to use the condemnation process to acquire R/W, which could delay start of construction by up to one year, increasing construction costs and extend the time for COS. Unanticipated buried man-made objects uncovered during construction require removal and disposal resulting in additional costs. A design change that is outside of the parameters contemplated in the Environmental Document triggers a supplemental EIR which causes a delay due to the public comment period. Nesting birds, protected from harassment under the Migratory Bird Treaty Act, may delay construction during the nesting season. Due to the complex nature of the staging, additional right of way or construction easements may be required to complete the work as contemplated, resulting in additional cost to the project. Hazardous materials encountered during construction will require an onsite storage area and potential additional costs to dispose

Probability Current status/assumptions

Low

Cost Impact ($) Low

High

Most likely

40

60

$

100,000

0

10

$

500,000

$

40

60

$

500,000

$

20

40

$

200,000

10

30

$

100,000

0

20

$

150,000

40

60

$

500,000

20

40

$

100,000

$

$

Time Impact (days) High

Probable

Low

Most likely

High

Risk Response

Rationale Probable

Strategy

Risk Owner

Updated

Mitigate

Verify that the survey file is accurate and complete

Sam Owner

10/12/2012

Address concerns of stakeholders and public during environmental process

EIR Person

11/23/2012

R/W Person

11/23/2012

PM

11/24/2012

$

300,000

$

100,000

800,000

$

1,200,000

$

42,000

60

150

5

Mitigate

750,000

$

2,000,000

$

542,000

180

365

136

Accept

$

400,000

$

90,000

$

400,000

$

47,000

0

60

$

300,000

$

23,000

0

30

$

1,000,000

$

$

300,000

$

200,000

750,000

Level 3 Risk Register

Response Actions

Accept

Include a Supplemental Work item to cover this risk.

6

Avoid

Monitor design changes against ED to avoid reassessment of ED unless the opportunity outweighs the threat

2

Mitigate

Schedule contract work to avoid the nesting season or remove nesting habitat before starting work.

375,000

Mitigate

60,000

Accept

Design Manager 11/24/2012

PM/RE

11/24/2012

Re-sequence the work to enable R/W Certification

R/W Person

11/24/2012

Ensure storage space will be available

PM

11/24/2012

Rating -->

Very Low

Impact Definitions Low Moderate

High

Insignificant cost increase

3 months improvement 60–99%

8 High

16 Very High