ACTIVITY RISK ASSESSEMENT WORKSHEET GUIDELINES Assessment Team :
H02 BEACH VILLA ADDRESS - SECTOR 51, PLOT NO. 143 OFFICERS CLUB, ABU DHABI U.A.E.
Date : 25 Dec 12 Signature
Project Manager - Mr. Moataz Chaabi – 056 728 7403 Project Engineer – Mr. Anthony Arago – 050 140 2931 HSE officer/Engineer – Mr. Musadek Hussein – 050 848 8603 First Aider – Mr. Mohamed AbdelSabour Hussein – 055 825 7883
Approved By : GUIDANCE NOTES Risk AssessmentInitial Risk AssessmentProbabilitySeverity
Potential Risk One or more risk assessment workshop shall be held, which consider all potential project risks. Note that Liquidated Damages is not a Project Risk – It is consequences of an event, typically failure to meet project milestones. Neither should this be recorded as a risk, as it is too general, and arises due to one or more reasons. * Delay in selection of Vendor X; * Failure of Vendor Y to meet schedule; * Failure of Subcontractor Y to mobilize sufficient resources; * Etc. These are the potential risks which should be considered.
The likelihood that this potential risk will be realized on this project is classified as :
The consequences for the project of the potential risk being realized are classified as :
1. 2. 3. 4. 5.
1. 2. 3. 4. 5.
Very Unlikely Unlikely Possible Likely Very Likely
Using the simplified Risk Matrix below, the Probability and severity are considered together to give the Initial risk as : •
Low
•
Medium
•
High
PROBABILITY 3. Possible LOW
2. Unlikely
Mitigation Action •Low Risks are acceptable. These should be recorded to confirm that this risk has been considered, but no further action is required. •Medium Risks are Tolerable. Mitigation action shall be taken where practical to reduce the probability or the severity of the risk, and the risk reassessed. •High Risks are Unacceptable. Immediate mitigation action shall be taken to reduce the Probability or Severity of the Risk and the risk reassessed. Risk must be reduced to Medium or Low
4. Likely
LOW LOW
MEDIUM
This is the assessment of the risk, following successful implementation of mitigating action. Low Risks are considered as “Closed”. Medium & High Risks are considered as “Open” and must be actively managed.
5. Very Likely MEDIUM MEDIUM HIGH
Page 1 of 5HIGH
MEDIUM MEDIUM
Residual Risk Assessment
HIGH
RISK ASSESSMENT
Task
Step #
1
2
Description of Task Step
Arrival of personnel on site
Hazard
Hazard Description & Effect
1.1 Unfamiliar with local situation. 1.2 Unfamiliar with site rules.
Check work location for space and obstacles Handling / carrying tools and equipments
2.1 Insufficient space. 2.2 Obstacles present
4
Set up barriers and caution signs
5
Locate under ground cables / services by scanner
3
Initial Risk Who or What might be Harmed?
Control Measures
Consequen Risk Rating Probability ce Control Measures and / or Recovery Measures
Residual Risk Consequen Risk Rating Probability ce *Residual Risk Level (ALARP )
People
2M
4M
8M
1.1 Site Induction course by HSE.
2L
2L
4L
Low
People
2M
4M
8M
1.2 All personnel to be fully briefed on task and responsibilities together with the use of PPEs. 1.3 Control unauthorized personnel entry to plant by Tawazen .
2L
2L
4L
Low
2L
2L
4L
Low
People People
2L 2L
3L 3L
6L 6L
2.1 Cordon off area. 2.2 Have obstacles removed.
2L 2L
2L 2L
4L 4L
Low Low
Property
2L
3L
6L
2L
2L
4L
Low
People
2L
3L
6L
3.1 Use lift / equipments for heavy load. 3.2 Clear all tripping hazards and Use safe access.
2L
2L
4L
Low
4.1 Injury from blunt / defective hand tools / handling material.
People
2L
3L
6L
4.1 Use PPEs.
2L
2L
4L
Low
5.1 Tripping hazards 5.2 Damage to the equipment / scanner
People Property
3M 3M
3M 3M
9M 9M
5.1 Remove all tripping hazards. 5.2 Competent person to use the scanner / equipments for locating the U/G services.
3L 3L
2L 2L
6L 6L
Low Low
3.1 Injury from carrying heavy tools / loads. 3.2 Fall / trip while carrying hand tools.
Page 2 of 5
RISK ASSESSMENT
Task
Step #
6
7
Description of Task Step
Grinding
Lifting of Valve by Crane and Fit Up
Hazard
Hazard Description & Effect
Initial Risk Who or What might be Harmed?
Control Measures
Consequen Risk Rating Probability ce Control Measures and / or Recovery Measures
6.1 Flying objects – Eye injury 6.2 Puncture of run pipe 6.3 Electric shock
Property
3M
3M
9M
People People
3M 3M
3M 3M
9M 9M
6.4 Possible ignition of gas and cause fire at flanges / threaded connections.
People / Property
3M
3M
9M
7.1 Loose Ground
Property / People
5H
5H
25H
7.2 Exposed Live line
Property
5H
5H
25H
7.3 Positioning of crane inside fenced area
Property / People
4H
4H
7.4 Trailer arrive with valve
Property
2L
7.5 Off loading the valve
Property / People
7.6 Falling from crane
Property / People
14.1Eye protection & face shield to be worn. 14.2Follow WPS Procedures. 14.3Follow the requirements in Remarks. 14.4Cover the near by flanges / threaded connections with fire blankets and monitor gas leakage 24x24 hours. 16.1 Compact Ground before positioning the crane and place outrigger pads as per the safety requirement and perform load test on finished ground.
Residual Risk Consequen Risk Rating Probability ce *Residual Risk Level (ALARP )
3L
2L
6L
Low
3L 3L
2L 2L
6L 6L
Low Low
3L
2L
6L
Low
5M
2M
10M
Medium
16.2 Protect live line with barrier constructed with sand bags in front and on top of operating pipeline.
5M
2M
10M
Medium
16H
16.3 Use tested & Certified equipment / rigging gear.
3L
2L
6L
Low
3L
6L
16.4 Keep clear lifting zone during lifting.
3L
2L
L
Low
3M
3M
9M
16.5 Use only Competent Rigging group
2L
2L
4L
Low
4M
3M
12M
16.6Conduct Tool box talk and discuss risk assessment with team to identify all hazards and
1L
1L
1L
Low
Page 3 of 5
RISK ASSESSMENT mitigation measures. 7.7 Damaging to material or personnel injury
7.8 Lowering the valve to fit up location
7.9 Fit up of valve
Property / People
Property/ People
Property / People
4H
5H
5H
4H
4H
4h
16H
20H
20H
16.7Check weather condition and wind speed to confirm safe for lifting. 16.8Keep clear all unwanted / unauthorized personnel. 16.9After lifting the valve from the trailer, maintain a minimum distance (100 Millimeter approximately) of the valve from the ground level. 16.10 Slew the load to the fit up location in a slow and steady motion. 16.11 Lower the valve into the bell hole onto the fit up location slowly and carefully, maintaining minimum clearance from ground. 16.12 Monitor any change in the ground condition due to crane movement.
3L
2L
6L
Low
3M
3M
9M
Medium
5H
3H
15H
High
4M
3M
12M
Medium
3M
3M
9M
Medium
3M
3M
9M
Medium
Page 4 of 5
RISK ASSESSMENT
REMARKS: 1. 2. 3. 4. 5. 6.
Cables, Hoses, Fittings, Gauges, etc. shall be visually inspected on a daily basis before starting any work and it should be ensured that all is in good conditions. Wind Indicator shall be provided, people and vehicles shall stay upwind of the work location. Escape route clearly identified, understood & known to all personnel working inside the live plant. Escape route must be kept clear of any obstacle. EMERGENCY NUMBERS – Tawazen HOT LINE NUMBERS must be posted & know to all personnel. Any emergency drill conducted by Tawazen live plant operations must be attended according to Tawazen procedures.