RISK ASSESSMENT SHEET Installation of HVAC Duct REF. NO. RA-AC-001
Project Title: Town Square Development Dubai – Zahra Breeze No:
1
2
Category/Activity
Grinding & Cutting
Working at height
Potential Hazards
Probability/ Likelihood
Damage to eye, face and body parts. Electrical shock
3
Body injuries, Personnel fall down, Falling object (Material or tools)
3
Severity/ Impact
3
3
Risk Value (Before Control Measure)
9 Medium Risk
9 Medium Risk
Control Measures
Use proper PPE & Clothing should be proper, grinder to be checked before use. Check all the cable must be double insulated and should be good condition, connection toin power supply should be proper. Use only approved scaffolding erected by trained scaffolders under competent supervision. Full body harness to be used while working at height and anchored and to secure location. Barricade the area, secure the material properly, ensure ensure “toe boards” and hand rails are installed, use proper PPE. Proper tagging and proper inspection
Probability/ Likelihood (After Control Measures)
Severity/ Impact (After Control Measures)
2
3
2
3
Risk Value (After Control Measures)
6 Low Risk
6 Low Risk
Remarks or References
RISK ASSESSMENT SHEET Installation of HVAC Duct REF. NO. RA-AC-001
3
4
5
6
Insufficient Lighting & Poor House Keeping
Working environment Risk
Slip, Trip and Fall hazards, Hit with stationary or moving objects/ Materials/ Machineries.
Heat Stress
Power Tools
Damaged cable or plug, Broken disk, Electrocution Improper changing of disk Noise, Spark
Chemical Hazard
Inhalant of chemical & spillage, Skin irritation
3
3
4
3
4
3
4
3
12 Medium Risk
9 Medium Risk
16 High Risk
9 Medium Risk
Provide sufficient Lightings, Safety vests. Maintain good housekeeping and do visual inspection of workplace starting the work.
Conduct tool box talk on heat stress, Drink Plenty of Pure water (Min 6 liter a day) and rehydration drinks. Shaded rest area to be provided. Periodic inspection of power tools Training on proper replacing of grinding disk proper cable management and cable should be placed away from wet ground Ear plugs used by all workers constantly exposed to grinding noise Spark containment utilized Proper gloves and face mask provided. Color coded.
Conduct tool box talk, Provision of proper PPE, Adequate ventilation and First aid facilities. Only competent person use the sealant gun. Proper housekeeping and segregation of hazardous waste and placed on hazardous waste storage area.
2
4
8 Low Risk
2
3
6 Low Risk
2
4
8 Low Risk
2
3
6 Low Risk
RISK ASSESSMENT SHEET Installation of HVAC Duct REF. NO. RA-AC-001
7
8
Hand Tools
Manual handling, Lifting, Duct work Insulation
Damaged hand tools and Homemade hand tools being used
Back injury and hernia, Skin irritation
4
3
4
4
16 High Risk
Periodic inspection of hand tools. Homemade hand tools are not allowed in the site. Color coded
2
4
8 Low Risk
12 Medium Risk
Use proper technique while doing manual handling, Tool box talk and proper PPE provision. Control of Substances Hazardous to health, Provision of mask, all machineries including chain block should be third party certified. Proper hazardous waste disposal.
2
3
6 / Low Risk
Assessment Prepared By: Safety Engineer (Al Muhanad / Conversion)
Assessment Approved By: Project Manager (Al Muhanad/Conversion)
Signature:
Signature:
Date:
Date:
RISK ASSESSMENT SHEET Installation of HVAC Duct REF. NO. RA-AC-001
y ti il
5
10
15
2 20 0
25
4
8
12
16
20
3
6
9
12
15
2
4
6
8
10
1
2
3 Severity
4
5
b a b o r P
Likelihood (Probability)
Consequences (Impact)
5. Almost Certain
5. Fatality
4. Probable
4. Major Injury, resulting in disability
3. Possible
3.Injury Requires, Doctor’s or Hospital attendance attendance
2. Possible (under unfortunate circumstances)
2. Minor Injury, 1st Aid required
1. Rare
1. Minor Injury, 1st Aid not required
RISK ASSESSMENT SHEET Installation of HVAC Duct REF. NO. RA-AC-001 Assessed Risk Level
Description of Risk Level
Low
If an incident were to occur, there would be some chance that an injury requiring First Aid would result or not.
Actions
Additional controls may be needed.
y t r
i
Medium Medium v
e e S
High High
If an incident were to occur, it would be likely that an injury requiring medical treatment would result.
Controls will need to be in place before the activity is undertaken.
If an incident were to occur, it would be likely that a permanent, debilitating injury or death would result.
Consider alternatives to doing the activity. Significant control measures will need to be implemented to ensure safety.
PTW- PERMIT TO WORK JSA- JOB SAFETY ANALYSIS PPE- PERSONAL PROTECTIVE EQUIPMENT