Risk Analysis
Short Description
Download Risk Analysis...
Description
RISK RISK ANAL ANALYSIS YSIS
Presented By:GIRISH ARORA 74 Sec-B PGDM 2009-2011
Risk is a possibility of incurring loss or misfortune. Every project is linked with certain amount of risk. Research and development project is more risky than an expansion project. Thus a need arises for the calculation of the amount of risk concerned with the projects. Risk analysis comprises of various tools for determining determining the risk associated associated with project. No single technique or tool may be suggested as the best tool.
Risk is a possibility of incurring loss or misfortune. Every project is linked with certain amount of risk. Research and development project is more risky than an expansion project. Thus a need arises for the calculation of the amount of risk concerned with the projects. Risk analysis comprises of various tools for determining determining the risk associated associated with project. No single technique or tool may be suggested as the best tool.
The two broad categories of techniques used for risk analysis: ±
±
Technique considering considering stand alone risk of a project. project . Technique that considers co nsiders the risk of project in context to the firm and market.
Stand-Alone risk of project Various
techniques that consider stand alone risk of project are:±
Sensitivity analysis
±
Scenario analysis
±
Break-Even Break-Even analysis analys is
±
Hillier model
±
Simulation analysis
±
Decision tree analysis
SENSITIVITY ANALYSIS Future is uncertain, this leads to risk with a project. What a manager wants to know? ±
Manager wants to know the viability of the project when some variables like sales or investment deviates from their expected values.
Sensitivity analysis is thus a technique of systematically changing parameters in a model to determine the effect of such changes. This method is part of capital budgeting decisions.
Example solved 11.2 Prasanna chandra 6 th edition Financial manager of Naveen flour mills considers of setting up of new floor mill in Bangalore. The project staff has developed the following figures of cash flows. Determine the NPV of the project and find out the sensitivity analysis with the deviations in key variables from the expected values.
Sensitivity of NPV to variations RANGE(Rs in µ000) K ey Variable
Pessimistic
Expected
Optimistic
Investment
24000
20000
18000
Sales
15000
18000
21000
Variable Costs 70 as percent of sales
66.66
65
Fixed Costs
1000
80
1300
Discounting Rate=12%, n=10
Solution
RANGE(Rs in µ000) K ey Variable
Pessimistic
Expected
Optimistic
Investment
24000
20000
18000
Sales
15000
18000
21000
Variable Costs 70 as percent of sales
66.66
65
Fixed Costs
1000
80
Consider
1300
the case when Investment occurs in pessimistic time. Thus more investment would be required then the expected value. Now we change the value of investment to 24000 then 20000 keeping the other variables constant and determine the change in NPV of the project.
NPV= -24000000+4133000*5.65 NPV= -648550 Similarly, we calculate NPV when the investment is done under optimistic time and so on.
RANGE(Rs in µ000)
NPV
K ey Variabl e
Pessimisti c
Expected Optimis Pessimist Expecte Optimis tic ic d tic
Invest ment
24000
20000
18000
-648550
Sales
15000
18000
21000
-1166290 2600000 6367420
66.66
65
340452
Variabl 70 e Costs as percent of sales
2600000 4223936
2600000 3730621
Fixed 1300 1000 80 1470000 2600000 3353936 Costs Thus the effect, of varying the key variables, on NPV can be easily assessed. The financial manager thus gets to know whether to carry on with the project under different circumstances.
Example: unsolved question No. 1 prasanna chandra 6th edition you are financial manager of HEPL. HEPL is planning to set up an extrusion plant at Indore. Your project staff has developed the following cash flow forecast for the project.
Determine the NPV of the project and calculate the effect of variations in the values of underlying variables on NPV.
RANGE(Rs in million) Underlying Variable
Pessimistic
Expected
Optimistic
Investment
300
250
200
Sales
150
200
275
Variable Costs 65 as percent of sales
60
56
Fixed Costs
20
15
30
Cost of Capital=13%, n=10
Solution
NPV= -250+50*5.426 NPV= 21.312
RANGE(Rs in µ000)
NPV
K ey Variabl e
Pessimisti c
Expected Optimis Pessimist Expecte Optimis tic ic d tic
Invest ment
300
250
200
-20.95
21.31
63.55
Sales
150
200
275
-56.21
21.31
137.58
Variabl 65 e Costs as percent of sales
60
56
-17.46
21.31
52.31
Fixed Costs
20
15
-17.46
21.31
40.68
30
Thus it can be determined that situations with negative NPV are unfavorable situations for carrying out the project further.
Merits and Demerits of Sensitivity Analysis Merits ±
±
±
It shows the robustness of project to changes in underlying key variables. It indicates whether to carry on with the project. If the NPV is highly sensitive to changes then manager can explore the variability of key variable.
Demerits or shortcomings ±
±
Sensitivity analysis considers change in only one variable whereas in reality variables move together. It shows the effect on variable with change in key variable but does not depict the likely change in the variable.
SCENARIO ANALYSIS Sensitivity analysis assumes that variables are independent of each other. Whereas, variables are interrelated and they may change in combination. To examine the risk of investment one can analyze the impact of alternative combinations of variables, called Scenarios. Consider the following example where, Zen enterprises is evaluating a project for introducing a new product. Depending on the response of market, firm has formulated 3 scenarios, Scenario1: The product will have moderate appeal to customers at a moderate price. Scenario2: The product will have strong appeal to large segment which is highly price sensitive. Scenario3: The product appeals small segment which is willing to pay high for the product.
Consider the following example in which the initial investment is Rs 200 million, The 3 scenarios are considered as:Scenario1 Moderate demand of 20 million units and moderate selling price of product being Rs 25 per unit. Scenario2 High demand of 40 million units and low selling price of Rs 15 per unit, Scenario3 Low demand 0f 10 million units for a highly priced product of Rs 40 per unit.
The variable costs on three scenarios are 48%, 80%, 30% respectively. Taxes are paid at a rate of 50% Depreciation occurs at 10% and project life cycle is of 10 years and salvage value is 0. It is also given that the Discounting Rate is15%.
Scenario 1
Scenario 2
Scenario 3
Initial Investment Unit S.P(Rs) Demand(in units)
200 25 20
200 15 40
200 40 10
Revenues
500
600
400
Variable
240 (48% of sales)
480(80%)
120(30%)
Fixed costs
50
50
50
Depreciation(10%)
20
20
20
Pre-Tax profit
190
15
210
Tax@50%
95
25
105
Profit after Tax
95
25
105
Annual Cash flow
115
45
125
Net Present Value
377.2
25.9
427.4
costs
Thus scenario analysis helps to understand the effect on NPV when the variables change in correlation.
BEST AND WORST CASE ANALYSIS The scenarios developed in previous example are most commonly occurring situations where high selling price and low demand go hand in hand. But managers try another kinds of scenario analysis called the best and worst case analysis. These scenarios are as: Best Scenario: Best scenario is considered when the product has high demand, high selling price, low variable cost etc. Average scenario: has average demand, average selling price, average variable cost. Worst Scenario: The scenario is considered worst when the product has low demand, low selling price, high variable costs.
The objective of such scenario analysis is to determine what would happen if situation is most favorable and if the adverse situation arises.
Merits and Demerits of Scenario Analysis Merits: It is an improvement to Sensitivity analysis because it considers variations in several variables together as it happens in reality.
Demerits: It is based on assumption that there are few linear scenarios. If there are many changing key variables then it would be difficult to analyze a number of scenarios.
BREAK -EVEN ANALYSIS This method helps in determining how much should be produced and sold at the minimum to ensure no loss situation. The minimum quantity at which loss is avoided is called a Break-Even point. It is a no profit-no loss situation. Since profits are linked with cost and volumes. Hence, it is the cost-volume-profit relationship analysis.
The project breaks even in NPV terms when the present value of cash flows is equal to the initial investment. Formulas used for the calculation of Break Even sales: Contribution Margin=Total Sales-Total Variable Costs
Consider the previous example of Naveen Flour mills. Financial manager of the firm wants to know the break even sales.
Solution
For the project to break even, PV of cash flows should be equal to initial investment or NPV should be zero. Hence, 1.254*sales= 20 million Break Even Sales=Rs 15.95 million This implies that for the project to have a zero NP V, sales of the flour mill should be equal to 15.95 million.
Example: unsolved question No. 1 prasanna chandra 6th edition you are financial manager of HEPL. HEPL is planning to set up an extrusion plant at Indore. Your project staff has developed the following cash flow forecast for the project.
Determine the financial break even point of sales.
Solution
For the project to break even, PV of cash flows should be equal to initial investment or NPV should be zero. Hence, 1.614*sales-40.36 million= 250 million Break Even Sales= Rs 180 million
HILLIER MODEL F.S. Hillier analyzed that the expected cash flows have standard deviations. The more the certainty of cash flow less is the standard deviation. There are two cases for which analysis is done ±
There is no correlation among cash flows,
±
Cash
flows are perfectly correlated.
The cash flows for the project involving outlay of Rs 10000 are as follows: Year 1 Year 2 Year3 Net cash flow
Probabilit y
Net cash flow
Probabilit y
Net cash flow
Probabilit y
Rs 3000
.3
2000
.2
3000
.3
5000
.4
4000
.6
5000
.4
7000
.3
6000
.2
7000
.3
Calculate the NPV and (NPV) for the project when the risk free interest rate i=6%
Year 1
Year 2
Year3
Net cash flow
Probabilit y
Net cash flow
Probabilit y
Net cash flow
Probabilit y
Rs 3000
.3
2000
.2
3000
.3
5000
.4
4000
.6
5000
.4
7000
.3
6000
.2
7000
.3
At
5000
At
4000
At
5000
Question No. 3 unsolved exercise Prasanna chandra 6 th edition(projects) A project involving an initial outlay of Rs 10 million has the following benefits associated with it:
Year 1
Year 2
Year3
Net cash flow (Rs in mln)
Probabilit y
Net cash flow
Probabilit y
Net cash flow
Probabilit y
4
.4
5
.4
3
.3
5
.5
6
.4
4
.5
6
.1
7
.2
5
.2
Assume that the cash flows are independent. Calculate the expected NPV and standard deviation of NPV. Risk free interest rate=10%
Solution Year 1
Year 2
Year3
Net cash flow (Rs in mln)
Probabilit y
Net cash flow
Probabilit y
Net cash flow
Probabilit y
4
.4
5
.4
3
.3
5
.5
6
.4
4
.5
6
.1
7
.2
5
.2
At
4.7
At
5.8
At
3.9
The investment project has an initial outlay of Rs 10000. The mean and standard deviation of cash flows which are perfectly correlated are as,
Year
At
t
1
5000
1500
2
3000
1000
3
4000
2000
4
3000
1200
Determine the NPV and (NPV) of the project when the risk free interest rate=6%.
Example unsolved question No. 4 prasanna chandra 6 th edition ch. 11 Janakiram is considering an investment which requires a current outlay of Rs 25000. the expected value of cash flows and standard deviations of cash flows are:
Year
At
t
1
12000
5000
2
10000
6000
3
9000
5000
4
8000
6000
The cash flows are perfectly correlated. Calculate the expected value of NPV and standard deviation of NPV of this investment. Risk free interest rate is 8%.
View more...
Comments