Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 1: D.O.C.K : OCT 2012 : F.O.O : K.M.M
COLUMN @ COLUMN TYPE C1 LEVEL 6
Basic Data Design to
BS 8110: 199
Grades Fy, Fyv, Fcu
460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 400 mm deep column βy : for 600 mm wide column Lc=3300
Top: Deep, Bottom: Deep Top: Deep, Bottom: Deep Lox=3300-(700+700)/2 Loy=3300-(600+600)/2
1.20 1.20 2600 2700
LEX=3120.0 MM, LEX/H=7.8, EXX=20.0 MM LEY=3240.0 MM, LEY/B=5.4, EYY=20.0 MM BI-AXIAL , SHORT, U NBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Part 1 of 2 with Mxx Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
777.7 k
.45x(600x400-2161)x25 + 0.95x2161.4x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-2161)x25 + 0.95x2161.4x460
OK Applied Moments (Mx1, Mx2) M nom=fn(N, exx) Design Moment
-183.6 kN.m, 180.1 kN.m 777.7 kN, 20.0 mm
3620.2 k OK 3352.7 k
X-X Moments 15.6 kN.m 183.6 kN.m
Y-Y Moments Applied Moments (My1, My2) Design Moment
-103.6 kN.m, 217.2 kN.m 217.2 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(183.6² + 217.2² ) atn(217.2/ 183.6)
284.4 kN.m 49.8 deg
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 2: D.O.C.K : OCT 2012 : F.O.O : K.M.M
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M12)
0.439, 716 mm, 600 mm, 314.66 mm, 80702 mm², 188.1 m 1 x 20, 634.7, -0.356, -437, -276.5, -137.3 1 x 20, 265.1, 0.055, 110, 93.1, 34.7 1 x 12, 514.1, -0.222, -437, -155.9, -49.4 1 x 12, 390.9, -0.085, -170, -32.6, -19.2 1 x 12, 576.7, -0.291, -437, -218.4, -49.4 1 x 12, 515.5, -0.223, -437, -157.3, -49.4 1 x 20, 451.4, -0.152, -304, -93.1, -95.5 1 x 20, 81.7, 0.259, 437, 276.5, 137.3 1 x 12, 325.6, -0.012, -24, 32.6, -2.7 1 x 12, 202.4, 0.125, 250, 155.9, 28.3 1 x 12, 200.9, 0.127, 253, 157.3, 28.6 1 x 12, 139.8, 0.195, 389, 218.4, 44.0 80702 x 0.45 x 25 -137+35-49-19-49-49-96+137-3+28+29+4 +908-777.7
Max Moment/Mu
907.9 x (716 / 2 - 188.1) 154.4 + (38.0+3.2+7.7+0.6+10.8+7.8+8.9+38.0 + (-0.1+4.4+4.5+9.6) 284.4 / 287.8
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
236.1 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
279.3 mm, 360 m
OK
38.0 3.2 7.7 0.6 10.8 7.8 8.9 38.0 -0.1 4.4 4.5 9.6 907.9
kN kN kN kN kN kN kN kN kN kN kN kN k
0.0
k OK 154.4 kN 287.8kN 0.98
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
NOMINAL LINKS BI-AXIAL , SHORT, U NBRACED, COLUMN DESIGN Critical Case : 1 : Dead plus Live Part 2 of 2: with Myy Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
777.7 k
.45x(600x400-2161)x25 + 0.95x2161.4x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-2161)x25 + 0.95x2161.4x460
OK Applied Moments (Mx1, Mx2) Design Moment
3620.2 k OK 3352.7 k
X-X Moments
-183.6 kN.m, 180.1 kN.m 183.6 kN.m
Y-Y Moments Applied Moments (My1, My2) M nom=fn(N, eyy) Design Moment
-103.6 kN.m, 217.2 kN.m 777.7, 20.0
15.6 kN.m 217.2 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(183.6² + 217.2² ) atn(217.2/ 183.6)
284.4 kN.m 49.8 deg
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F)
0.439, 716 mm, 600 mm, 314.66 mm, 80702 mm², 188.1 m 1 x 20, 634.7, -0.356, -437, -276.5, -137.3 1 x 20, 265.1, 0.055, 110, 93.1, 34.7 1 x 12, 514.1, -0.222, -437, -155.9, -49.4 1 x 12, 390.9, -0.085, -170, -32.6, -19.2
38.0 3.2 7.7 0.6
kN kN kN kN
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M12)
1 x 12, 576.7, -0.291, -437, -218.4, -49.4 1 x 12, 515.5, -0.223, -437, -157.3, -49.4 1 x 20, 451.4, -0.152, -304, -93.1, -95.5 1 x 20, 81.7, 0.259, 437, 276.5, 137.3 1 x 12, 325.6, -0.012, -24, 32.6, -2.7 1 x 12, 202.4, 0.125, 250, 155.9, 28.3 1 x 12, 200.9, 0.127, 253, 157.3, 28.6 1 x 12, 139.8, 0.195, 389, 218.4, 44.0 80702 x 0.45 x 25 -137+35-49-19-49-49-96+137-3+28+29+4 +908-777.7
Max Moment/Mu
907.9 x (716 / 2 - 188.1) 154.4 + (38.0+3.2+7.7+0.6+10.8+7.8+8.9+38.0 + (-0.1+4.4+4.5+9.6) 284.4 / 287.8
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
236.1 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
279.3 mm, 360 m
OK
: Job Ref : Sheet Ref / 3: D.O.C.K : OCT 2012 : F.O.O : K.M.M
10.8 7.8 8.9 38.0 -0.1 4.4 4.5 9.6 907.9
kN kN kN kN kN kN kN kN k
0.0
k OK 154.4 kN 287.8kN 0.98
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 4: D.O.C.K : OCT 2012 : F.O.O : K.M.M
COLUMN @ COLUMN TYPE C1 LEVEL 5
Basic Data Design to
BS 8110: 199
Grades Fy, Fyv, Fcu
460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 400 mm deep column βy : for 600 mm wide column Lc=3300
Top: Deep, Bottom: Deep Top: Deep, Bottom: Deep Lox=3300-(700+700)/2 Loy=3300-(600+600)/2
1.20 1.20 2600 2700
LEX=3120.0 MM, LEX/H=7.8, EXX=20.0 MM LEY=3240.0 MM, LEY/B=5.4, EYY=20.0 MM BI-AXIAL , SHORT, U NBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Part 1 of 2 with Mxx Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
1934.0 k
.45x(600x400-5730)x25 + 0.95x5730.3x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-5730)x25 + 0.95x5730.3x460
OK Applied Moments (Mx1, Mx2) M nom=fn(N, exx) Design Moment
5139.7 k OK 4876.1 k
X-X Moments
-157.0 kN.m, 134.9 kN.m 1934.0 kN, 20.0 mm
38.7 kN.m 157.0 kN.m
Y-Y Moments Applied Moments (My1, My2) Design Moment
36.4 kN.m, -52.9 kN.m 52.9 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(157.0² + 52.9² ) atn(52.9/ 157.0)
165.7 kN.m 18.6 deg
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar
0.582, 571 mm, 600 mm, 331.88 mm, 128465 mm², 189.7 m
Bar group1:M1 fn(bars,d,ε%,,la,F)
1 x 32, 489.6, -0.166, -333, -204.2, -267.5
54.6 kN
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp= 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M12)
: Job Ref : Sheet Ref / 5: D.O.C.K : OCT 2012 : F.O.O : K.M.M
1 x 32, 338.8, -0.007, -15, -53.5, -11.8 1 x 20, 445.0, -0.119, -239, -159.7, -75.0 1 x 20, 394.8, -0.066, -133, -109.4, -41.7 1 x 20, 405.6, -0.078, -155, -120.2, -48.8 1 x 20, 319.6, 0.013, 26, -34.3, 8.1 1 x 32, 231.8, 0.106, 211, 53.5, 169.8 1 x 32, 81.1, 0.264, 437, 204.2, 351.5 1 x 20, 175.9, 0.165, 329, 109.4, 103.4 1 x 20, 125.6, 0.218, 435, 159.7, 136.7 1 x 20, 251.0, 0.085, 171, 34.3, 53.6 1 x 20, 165.1, 0.176, 352, 120.2, 110.5 128465 x 0.45 x 25 -267-12-75-42-49+8+170+351+103+137+5 +111+1445-1934
Max Moment/Mu
1445.2 x (571 / 2 - 189.7) 138.2 + (54.6+0.6+12.0+4.6+5.9+-0.3+9.1 + (71.8+11.3+21.8+1.8+13.3) 165.7 / 344.7
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
81.2 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
27.4 mm, 360 m
OK
0.6 12.0 4.6 5.9 -0.3 9.1 71.8 11.3 21.8 1.8 13.3 1445.2
kN kN kN kN kN kN kN kN kN kN kN k
0.0
k OK 138.2 kN 344.7kN 0.48
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
NOMINAL LINKS BI-AXIAL , SHORT, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Part 2 of 2: with Myy Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
1934.0 k
.45x(600x400-5730)x25 + 0.95x5730.3x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-5730)x25 + 0.95x5730.3x460
OK Applied Moments (Mx1, Mx2) Design Moment
5139.7 k OK 4876.1 k
X-X Moments
-157.0 kN.m, 134.9 kN.m 157.0 kN.m
Y-Y Moments Applied Moments (My1, My2) M nom=fn(N, eyy) Design Moment
36.4 kN.m, -52.9 kN.m 1934.0, 20.0
38.7 kN.m 52.9 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(157.0² + 52.9² ) atn(52.9/ 157.0)
165.7 kN.m 18.6 deg
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F)
0.582, 571 mm, 600 mm, 331.88 mm, 128465 mm², 189.7 m 1 x 32, 489.6, -0.166, -333, -204.2, -267.5 1 x 32, 338.8, -0.007, -15, -53.5, -11.8 1 x 20, 445.0, -0.119, -239, -159.7, -75.0 1 x 20, 394.8, -0.066, -133, -109.4, -41.7
54.6 0.6 12.0 4.6
kN kN kN kN
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M12)
1 x 20, 405.6, -0.078, -155, -120.2, -48.8 1 x 20, 319.6, 0.013, 26, -34.3, 8.1 1 x 32, 231.8, 0.106, 211, 53.5, 169.8 1 x 32, 81.1, 0.264, 437, 204.2, 351.5 1 x 20, 175.9, 0.165, 329, 109.4, 103.4 1 x 20, 125.6, 0.218, 435, 159.7, 136.7 1 x 20, 251.0, 0.085, 171, 34.3, 53.6 1 x 20, 165.1, 0.176, 352, 120.2, 110.5 128465 x 0.45 x 25 -267-12-75-42-49+8+170+351+103+137+5 +111+1445-1934
Max Moment/Mu
1445.2 x (571 / 2 - 189.7) 138.2 + (54.6+0.6+12.0+4.6+5.9+-0.3+9.1 + (71.8+11.3+21.8+1.8+13.3) 165.7 / 344.7
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
81.2 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
27.4 mm, 360 m
OK
: Job Ref : Sheet Ref / 6: D.O.C.K : OCT 2012 : F.O.O : K.M.M
5.9 -0.3 9.1 71.8 11.3 21.8 1.8 13.3 1445.2
kN kN kN kN kN kN kN kN k
0.0
k OK 138.2 kN 344.7kN 0.48
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
Nominal links
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 7: D.O.C.K : OCT 2012 : F.O.O : K.M.M
COLUMN @ COLUMN TYPE C1 LEVEL 4
Basic Data Design to
BS 8110: 199
Grades Fy, Fyv, Fcu
460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 400 mm deep column βy : for 600 mm wide column Lc=3300
Top: Deep, Bottom: Deep Top: Deep, Bottom: Deep Lox=3300-(700+700)/2 Loy=3300-(600+600)/2
1.20 1.20 2600 2700
LEX=3120.0 MM, LEX/H=7.8, EXX=20.0 MM LEY=3240.0 MM, LEY/B=5.4, EYY=20.0 MM BI-AXIAL , SHORT, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Part 1 of 2 with Mxx Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
2986.6 k
.45x(600x400-4477)x25 + 0.95x4476.8x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-4477)x25 + 0.95x4476.8x460
OK Applied Moments (Mx1, Mx2) M nom=fn(N, exx) Design Moment
4606.0 k OK 4341.0 k
X-X Moments
-158.7 kN.m, 141.8 kN.m 2986.6 kN, 20.0 mm
59.7 kN.m 158.7 kN.m
Y-Y Moments Applied Moments (My1, My2) Design Moment
-14.1 kN.m, -14.1 kN.m 14.1 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(158.7² + 14.1² ) atn(14.1/ 158.7)
159.3 kN.m 5.1 deg
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F)
0.789, 452 mm, 600 mm, 356.05 mm, 177032 mm², 173.1 m 1 x 25, 385.9, -0.029, -59, -160.1, -28.8 1 x 25, 343.5, 0.012, 25, -117.8, 12.1 1 x 20, 374.3, -0.018, -36, -148.5, -11.3
4.6 kN -1.4 kN 1.7 kN
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M12)
: Job Ref : Sheet Ref / 8: D.O.C.K : OCT 2012 : F.O.O : K.M.M
1 x 20, 360.1, -0.004, -8, -134.4, -2.5 1 x 20, 293.5, 0.061, 123, -67.7, 38.6 1 x 20, 200.9, 0.153, 305, 24.9, 95.8 1 x 25, 108.0, 0.244, 437, 117.8, 214.5 1 x 25, 65.6, 0.285, 437, 160.1, 214.5 1 x 20, 91.4, 0.260, 437, 134.4, 137.3 1 x 20, 77.3, 0.274, 437, 148.5, 137.3 1 x 20, 250.7, 0.104, 207, -24.9, 65.1 1 x 20, 158.0, 0.195, 389, 67.7, 122.3 177032 x 0.45 x 25 -29+12-11-3+39+96+215+215+137+137+6 +122+1992-2986.6
Max Moment/Mu
1991.6 x (452 / 2 - 173.1) 104.9 + (4.6+-1.4+1.7+0.3+-2.6+2.4+25.3 + (34.4+18.4+20.4+-1.6+8.3) 159.3 / 215.0
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
53.1 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
4.7 mm, 360 m
OK
0.3 -2.6 2.4 25.3 34.4 18.4 20.4 -1.6 8.3 1991.6
kN kN kN kN kN kN kN kN kN k
0.0
k OK 104.9 kN 215.0kN 0.74
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
NOMINAL LINKS BI-AXIAL , SHORT, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Part 2 of 2: with Myy Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
2986.6 k
.45x(600x400-4477)x25 + 0.95x4476.8x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-4477)x25 + 0.95x4476.8x460
OK Applied Moments (Mx1, Mx2) Design Moment
4606.0 k OK 4341.0 k
X-X Moments
-158.7 kN.m, 141.8 kN.m 158.7 kN.m
Y-Y Moments Applied Moments (My1, My2) M nom=fn(N, eyy) Design Moment
-14.1 kN.m, -14.1 kN.m 2986.6, 20.0
59.7 kN.m 59.7 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(158.7² + 59.7² ) atn(59.7/ 158.7)
169.6 kN.m 20.6 deg
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F)
0.741, 586 mm, 600 mm, 434.02 mm, 182274 mm², 241.3 m 1 x 25, 507.8, -0.059, -119, -214.9, -58.4 1 x 25, 339.1, 0.077, 153, -46.2, 75.2 1 x 20, 453.9, -0.016, -32, -161.0, -10.1 1 x 20, 397.6, 0.029, 59, -104.8, 18.4 1 x 20, 421.6, 0.010, 20, -128.8, 6.3 1 x 20, 334.6, 0.080, 160, -41.7, 50.4
12.6 -3.5 1.6 -1.9 -0.8 -2.1
kN kN kN kN kN kN
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M12)
Job ref Sheet Made By Date Checked Approved
1 x 25, 246.7, 0.151, 302, 46.2, 148.3 1 x 25, 77.9, 0.287, 437, 214.9, 214.5 1 x 20, 188.1, 0.198, 397, 104.8, 124.6 1 x 20, 131.8, 0.244, 437, 161.0, 137.3 1 x 20, 251.1, 0.147, 295, 41.7, 92.7 1 x 20, 164.1, 0.218, 435, 128.8, 136.8 182274 x 0.45 x 25 -58+75-10+18+6+50+148+215+125+137+9 +137+2051-2986.6
Max Moment/Mu
2050.6 x (586 / 2 - 241.3) 105.7 + (12.6+-3.5+1.6+-1.9+-0.8+-2.1+6.9 + (46.1+13.1+22.1+3.9+17.6) 169.6 / 221.2
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
53.1 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
20 mm, 360 m
OK
: Job Ref : Sheet Ref / 9: D.O.C.K : OCT 2012 : F.O.O : K.M.M
6.9 46.1 13.1 22.1 3.9 17.6 2050.6
kN kN kN kN kN kN k
0.0
k OK 105.7 kN 221.2kN 0.76
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
Nominal links
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 10: D.O.C.K : OCT 2012 : F.O.O : K.M.M
Column @ COLUMN TYPE C1 Level 3
Basic Data Design to
BS 8110: 199
Grades Fy, Fyv, Fcu
460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 400 mm deep column βy : for 600 mm wide column Lc=3300
Top: Deep, Bottom: Deep Top: Deep, Bottom: Deep Lox=3300-(700+700)/2 Loy=3300-(600+600)/2
1.20 1.20 2600 2700
LEX=3120.0 MM, LEX/H=7.8, EXX=20.0 MM LEY=3240.0 MM, LEY/B=5.4, EYY=20.0 MM BI-AXIAL , SHORT, U NBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Part 1 of 2 with Mxx Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
3927.0 k
.45x(600x400-5730)x25 + 0.95x5730.3x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-5730)x25 + 0.95x5730.3x460
OK Applied Moments (Mx1, Mx2) M nom=fn(N, exx) Design Moment
5139.7 k OK 4876.1 k
X-X Moments
-162.7 kN.m, 137.0 kN.m 3927.0 kN, 20.0 mm
78.5 kN.m 162.7 kN.m
Y-Y Moments Applied Moments (My1, My2) Design Moment
70.6 kN.m, -47.0 kN.m 70.6 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(162.7² + 70.6² ) atn(70.6/ 162.7)
177.4 kN.m 23.5 deg
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F)
0.859, 606 mm, 600 mm, 520.10 mm, 214039 mm², 277.3 m 1 x 32, 521.6, -0.001, -2, -218.7, -1.6
0.4 kN
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M12)
: Job Ref : Sheet Ref / 11: D.O.C.K : OCT 2012 : F.O.O : K.M.M
1 x 32, 333.7, 0.125, 251, -30.8, 201.8 1 x 20, 464.5, 0.037, 75, -161.6, 23.5 1 x 20, 401.8, 0.080, 159, -99.0, 50.0 1 x 20, 440.8, 0.053, 107, -137.9, 33.5 1 x 20, 357.6, 0.109, 219, -54.7, 68.7 1 x 32, 272.1, 0.167, 334, 30.8, 268.5 1 x 32, 84.2, 0.293, 437, 218.7, 351.5 1 x 20, 203.9, 0.213, 426, 99.0, 133.7 1 x 20, 141.3, 0.255, 437, 161.6, 137.3 1 x 20, 248.1, 0.183, 366, 54.7, 115.0 1 x 20, 165.0, 0.239, 437, 137.9, 137.3 214039 x 0.45 x 25 -2+202+24+50+34+69+268+351+134+137+11 +137+2408-3927
Max Moment/Mu
2407.9 x (606 / 2 - 277.3) 61.7 + (0.4+-6.2+-3.8+-4.9+-4.6+-3.8+8.3 + (76.9+13.2+22.2+6.3+18.9) 177.4 / 184.4
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
41.4 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
18 mm, 360 m
OK
-6.2 -3.8 -4.9 -4.6 -3.8 8.3 76.9 13.2 22.2 6.3 18.9 2407.9
kN kN kN kN kN kN kN kN kN kN kN k
0.0
k OK 61.7 kN 184.4kN 0.96
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
NOMINAL LINKS BI-AXIAL , SHORT, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Part 2 of 2: with Myy Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
3927.0 k
.45x(600x400-5730)x25 + 0.95x5730.3x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-5730)x25 + 0.95x5730.3x460
OK Applied Moments (Mx1, Mx2) Design Moment
5139.7 k OK 4876.1 k
X-X Moments
-162.7 kN.m, 137.0 kN.m 162.7 kN.m
Y-Y Moments Applied Moments (My1, My2) M nom=fn(N, eyy) Design Moment
70.6 kN.m, -47.0 kN.m 3927.0, 20.0
78.5 kN.m 78.5 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(162.7² + 78.5² ) atn(78.5/ 162.7)
180.7 kN.m 25.8 deg
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F)
0.858, 621 mm, 600 mm, 532.64 mm, 214363 mm², 284.7 m 1 x 32, 535.6, -0.002, -4, -225.1, -3.1 1 x 32, 330.4, 0.133, 266, -19.9, 213.7 1 x 20, 472.6, 0.039, 79, -162.1, 24.8 1 x 20, 404.2, 0.084, 169, -93.7, 53.0 1 x 20, 456.6, 0.050, 100, -146.0, 31.4 1 x 20, 374.9, 0.104, 207, -64.4, 65.1
0.7 -4.2 -4.0 -5.0 -4.6 -4.2
kN kN kN kN kN kN
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M12)
1 x 32, 290.6, 0.159, 318, 19.9, 255.8 1 x 32, 85.5, 0.294, 437, 225.1, 351.5 1 x 20, 216.8, 0.208, 415, 93.7, 130.4 1 x 20, 148.5, 0.252, 437, 162.1, 137.3 1 x 20, 246.2, 0.188, 377, 64.4, 118.3 1 x 20, 164.5, 0.242, 437, 146.0, 137.3 214363 x 0.45 x 25 -3+214+25+53+31+65+256+351+130+137+11 +137+2412-3927
Max Moment/Mu
2411.6 x (621 / 2 - 284.7) 62.3 + (0.7+-4.2+-4.0+-5.0+-4.6+-4.2+5.1 + (79.1+12.2+22.3+7.6+20.0) 180.7 / 187.3
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
41.4 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
20 mm, 360 m
OK
: Job Ref : Sheet Ref / 12: D.O.C.K : OCT 2012 : F.O.O : K.M.M
5.1 79.1 12.2 22.3 7.6 20.0 2411.6
kN kN kN kN kN kN k
0.0
k OK 62.3 kN 187.3kN 0.96
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
Nominal links
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 13: D.O.C.K : OCT 2012 : F.O.O : K.M.M
COLUMN @ COLUMN TYPE C1 LEVEL 2
Basic Data Design to
BS 8110: 199
Grades Fy, Fyv, Fcu
460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 400 mm deep column βy : for 600 mm wide column Lc=5000
Top: Deep, Bottom: Deep Top: Deep, Bottom: Deep Lox=5000-(700+700)/2 Loy=5000-(600+600)/2
1.20 1.20 4300 4400
LEX=5160.0 MM, LEX/H=12.9, EXX=20.0 MM LEY=5280.0 MM, LEY/B=8.8, EYY=20.0 MM BI-AXIAL , SLENDER, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Part 1 of 2 with Mxx Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
5105.0 k
.45x(600x400-12596)x25 + 0.95x12596.2x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-12596)x25 + 0.95x12596.2x460
OK
8062.8 k OK 7807.0 k
X-X Moments
Applied Moments (Mx1, Mx2) -122.6 kN.m, 111.4 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (8063 - 5105)/(8063 - 1296) < 1 au = βa • K • h 0.083, 1.000, 400 Madd= N • au 5105 x 33.3 Mi=fn(Mx1, Mx2) -122.6 kN.m, 111.4 kN.m M2+Madd, M nom 292.5 kN.m, 102.1 kN.m M nom=fn(N, exx) 5105.0 kN, 20.0 mm Design Moment
1.00 33.3 mm 169.9 kN.m 49.0 kN.m 169.9 kN.m 292.5 kN.m
Y-Y Moments Applied Moments (My1, My2) 138.6 kN.m, -87.8 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (8063 - 5105)/(8063 - 598) < 1 au = βa • K • h 0.039, 1.000, 400 Madd= N • au 5105 x 23.2 Mi=fn(My1, My2) 138.6 kN.m, -87.8 kN.m M nom=fn(M2+Madd) 257.2 M nom=fn(N, eyy) 5105.0, 20.0 Design Moment
1.00 23.2 mm 118.6 kN.m 55.4 kN.m 0.0 kN.m 118.6 kN.m 257.2 kN.m
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 14: D.O.C.K : OCT 2012 : F.O.O : K.M.M
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(292.5² + 257.2² ) atn(257.2/ 292.5)
389.5 kN.m 41.3 deg
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Bar group13:M13 fn(bars,d,ε%,,la,F) Bar group14:M14 fn(bars,d,ε%,,la,F) Bar group15:M15 fn(bars,d,ε%,,la,F) Bar group16:M16 fn(bars,d,ε%,,la,F) Bar group17:M17 fn(bars,d,ε%,,la,F) Bar group18:M18 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M18)
0.775, 697 mm, 600 mm, 539.74 mm, 195184 mm², 300.6 m 1 x 32, 606.3, -0.043, -86, -258.0, -69.4 1 x 32, 294.6, 0.159, 318, 53.7, 255.7 1 x 32, 543.9, -0.003, -5, -195.6, -4.4 1 x 32, 481.6, 0.038, 75, -133.3, 60.6 1 x 32, 419.3, 0.078, 156, -71.0, 125.7 1 x 32, 356.9, 0.119, 237, -8.6, 190.7 1 x 25, 557.5, -0.012, -23, -209.2, -11.3 1 x 25, 506.4, 0.022, 43, -158.1, 21.2 1 x 25, 455.4, 0.055, 109, -107.1, 53.7 1 x 32, 402.0, 0.089, 179, -53.7, 143.7 1 x 32, 90.3, 0.291, 437, 258.0, 351.5 1 x 32, 339.7, 0.130, 259, 8.6, 208.7 1 x 32, 277.3, 0.170, 340, 71.0, 273.7 1 x 32, 215.0, 0.211, 421, 133.3, 338.7 1 x 32, 152.7, 0.251, 437, 195.6, 351.5 1 x 25, 241.2, 0.194, 387, 107.1, 190.0 1 x 25, 190.1, 0.227, 437, 158.1, 214.5 1 x 25, 139.1, 0.260, 437, 209.2, 214.5 195184 x 0.45 x 25 -69+256-4+61+126+191-11+21+54+144+35 +209+274+339+351+190+215+215+2196-5105
Max Moment/Mu
2195.8 x (697 / 2 - 300.6) 104.7 + (17.9+13.7+0.9+-8.1+-8.9+-1.6+2.4 + (-3.4+-5.8+-7.7+90.7+1.8+19.4+45.2 + (68.8+20.4+33.9+44.9) 389.5 / 429.1
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
57.3 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
50.4 mm, 360 m
OK
17.9 13.7 0.9 -8.1 -8.9 -1.6 2.4 -3.4 -5.8 -7.7 90.7 1.8 19.4 45.2 68.8 20.4 33.9 44.9 2195.8
kN kN kN kN kN kN kN kN kN kN kN kN kN kN kN kN kN kN k
0.1
k OK 104.7 kN
429.1kN 0.90
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
NOMINAL LINKS BI-AXIAL , SLENDER, U NBRACED, COLUMN DESIGN Critical Case : 1 : Dead plus Live Part 2 of 2: with Myy Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
5105.0 k
.45x(600x400-12596)x25 + 0.95x12596.2x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-12596)x25 + 0.95x12596.2x460
OK
8062.8 k OK 7807.0 k
X-X Moments
Applied Moments (Mx1, Mx2) -122.6 kN.m, 111.4 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (8063 - 5105)/(8063 - 1296) < 1 au = βa • K • h 0.083, 1.000, 400 Madd= N • au 5105 x 33.3 Mi=fn(Mx1, Mx2) -122.6 kN.m, 111.4 kN.m M2+Madd, M nom 292.5 kN.m, 0.0 kN.m M nom=fn(N, exx) 5105.0 kN, 20.0 mm Design Moment
1.00 33.3 mm 169.9 kN.m 49.0 kN.m 169.9 kN.m 292.5 kN.m
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
Job ref Sheet Made By Date Checked Approved
: Job Ref : Sheet Ref / 15: D.O.C.K : OCT 2012 : F.O.O : K.M.M
Y-Y Moments Applied Moments (My1, My2) 138.6 kN.m, -87.8 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (8063 - 5105)/(8063 - 598) < 1 au = βa • K • h 0.039, 1.000, 400 Madd= N • au 5105 x 23.2 Mi=fn(My1, My2) 138.6 kN.m, -87.8 kN.m M nom=fn(M2+Madd) 257.2 M nom=fn(N, eyy) 5105.0, 20.0 Design Moment
1.00 23.2 mm 118.6 kN.m 55.4 kN.m 102.1 kN.m 118.6 kN.m 257.2 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(292.5² + 257.2² ) atn(257.2/ 292.5)
389.5 kN.m 41.3 deg
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Bar group13:M13 fn(bars,d,ε%,,la,F) Bar group14:M14 fn(bars,d,ε%,,la,F) Bar group15:M15 fn(bars,d,ε%,,la,F) Bar group16:M16 fn(bars,d,ε%,,la,F) Bar group17:M17 fn(bars,d,ε%,,la,F) Bar group18:M18 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M18)
0.775, 697 mm, 600 mm, 539.74 mm, 195184 mm², 300.6 m 1 x 32, 606.3, -0.043, -86, -258.0, -69.4 1 x 32, 294.6, 0.159, 318, 53.7, 255.7 1 x 32, 543.9, -0.003, -5, -195.6, -4.4 1 x 32, 481.6, 0.038, 75, -133.3, 60.6 1 x 32, 419.3, 0.078, 156, -71.0, 125.7 1 x 32, 356.9, 0.119, 237, -8.6, 190.7 1 x 25, 557.5, -0.012, -23, -209.2, -11.3 1 x 25, 506.4, 0.022, 43, -158.1, 21.2 1 x 25, 455.4, 0.055, 109, -107.1, 53.7 1 x 32, 402.0, 0.089, 179, -53.7, 143.7 1 x 32, 90.3, 0.291, 437, 258.0, 351.5 1 x 32, 339.7, 0.130, 259, 8.6, 208.7 1 x 32, 277.3, 0.170, 340, 71.0, 273.7 1 x 32, 215.0, 0.211, 421, 133.3, 338.7 1 x 32, 152.7, 0.251, 437, 195.6, 351.5 1 x 25, 241.2, 0.194, 387, 107.1, 190.0 1 x 25, 190.1, 0.227, 437, 158.1, 214.5 1 x 25, 139.1, 0.260, 437, 209.2, 214.5 195184 x 0.45 x 25 -69+256-4+61+126+191-11+21+54+144+35 +209+274+339+351+190+215+215+2196-5105
Max Moment/Mu
2195.8 x (697 / 2 - 300.6) 104.7 + (17.9+13.7+0.9+-8.1+-8.9+-1.6+2.4 + (-3.4+-5.8+-7.7+90.7+1.8+19.4+45.2 + (68.8+20.4+33.9+44.9) 389.5 / 429.1
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
57.3 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
50.4 mm, 360 m
OK
17.9 13.7 0.9 -8.1 -8.9 -1.6 2.4 -3.4 -5.8 -7.7 90.7 1.8 19.4 45.2 68.8 20.4 33.9 44.9 2195.8
kN kN kN kN kN kN kN kN kN kN kN kN kN kN kN kN kN kN k
0.1
k OK 104.7 kN
429.1kN 0.90
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
Nominal links
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
Job ref Sheet Made By Date Checked Approved
: Job Ref : Sheet Ref / 16: D.O.C.K : OCT 2012 : F.O.O : K.M.M
COLUMN @ COLUMN TYPE C1 LEVEL 1
Basic Data Design to
BS 8110: 199
Grades Fy, Fyv, Fcu
460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 500 mm deep column βy : for 600 mm wide column Lc=5000
Top: Deep, Bottom: Shallow Top: Deep, Bottom: Shallow Lox=5000-(700+0)/2 Loy=5000-(600+0)/2
1.30 1.30 4650 4700
LEX=6045.0 MM, LEX/H=12.1, EXX=20.0 MM LEY=6110.0 MM, LEY/B=10.2, EYY=20.0 MM BI-AXIAL , SLENDER, UNBRACED, COLUMN DESIGN Critical Case : 1 : Dead plus Live Part 1 of 2 with Mxx Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
6465.5 k
.45x(600x500-14476)x25 + 0.95x14476.5x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x500-14476)x25 + 0.95x14476.5x460
OK Applied Moments (Mx1, Mx2) -59.4 kN.m, 98.6 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (9538 - 6466)/(9538 - 846) < 1 au = βa • K • h 0.073, 1.000, 500 Madd= N • au 6466 x 36.5 Mi=fn(Mx1, Mx2) -59.4 kN.m, 98.6 kN.m M2+Madd, M nom 334.9 kN.m, 129.3 kN.m M nom=fn(N, exx) 6465.5 kN, 20.0 mm Design Moment
9538.4 k OK 9217.1 k
X-X Moments 1.00 36.5 mm 236.3 kN.m 39.4 kN.m 236.3 kN.m 334.9 kN.m
Y-Y Moments Applied Moments (My1, My2) 85.3 kN.m, -140.2 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (9538 - 6466)/(9538 - 872) < 1 au = βa • K • h 0.052, 1.000, 500 Madd= N • au 6466 x 31.1 Mi=fn(My1, My2) 85.3 kN.m, -140.2 kN.m M nom=fn(M2+Madd) 341.3
1.00 31.1 mm 201.1 kN.m 56.1 kN.m 0.0 kN.m
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected], M nom=fn(N, eyy) Design Moment
: Job Ref : Sheet Ref / 17: D.O.C.K : OCT 2012 : F.O.O : K.M.M
6465.5, 20.0
201.1 kN.m 341.3 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(334.9² + 341.3² ) atn(341.3/ 334.9)
478.2 kN.m 45.5 deg
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Bar group13:M13 fn(bars,d,ε%,,la,F) Bar group14:M14 fn(bars,d,ε%,,la,F) Bar group15:M15 fn(bars,d,ε%,,la,F) Bar group16:M16 fn(bars,d,ε%,,la,F) Bar group17:M17 fn(bars,d,ε%,,la,F) Bar group18:M18 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M18)
0.811, 778 mm, 600 mm, 631.45 mm, 255828 mm², 346.2 m 1 x 32, 688.0, -0.031, -63, -298.7, -50.4 1 x 32, 351.0, 0.155, 311, 38.2, 250.0 1 x 32, 620.6, 0.006, 12, -231.3, 9.7 1 x 32, 553.2, 0.043, 87, -163.9, 69.8 1 x 32, 485.8, 0.081, 161, -96.6, 129.9 1 x 32, 418.4, 0.118, 236, -29.2, 189.9 1 x 32, 622.8, 0.005, 10, -233.6, 7.7 1 x 32, 557.7, 0.041, 82, -168.5, 65.8 1 x 32, 492.6, 0.077, 154, -103.3, 123.8 1 x 32, 427.4, 0.113, 226, -38.2, 181.9 1 x 32, 90.5, 0.300, 437, 298.7, 351.5 1 x 32, 360.1, 0.150, 301, 29.2, 242.0 1 x 32, 292.7, 0.188, 376, 96.6, 302.0 1 x 32, 225.3, 0.225, 437, 163.9, 351.5 1 x 32, 157.9, 0.262, 437, 231.3, 351.5 1 x 32, 285.9, 0.192, 383, 103.3, 308.1 1 x 32, 220.8, 0.228, 437, 168.5, 351.5 1 x 32, 155.6, 0.264, 437, 233.6, 351.5 255828 x 0.45 x 25 -50+250+10+70+130+190+8+66+124+182+35 +242+302+351+351+308+351+351+2878-6465.5
Max Moment/Mu
2878.1 x (778 / 2 - 346.2) 123.8 + (15.0+9.6+-2.2+-11.4+-12.5+-5.5 + (-1.8+-11.1+-12.8+-7.0+105.0+7.1 + (29.2+57.6+81.3+31.8+59.2+82.1) 478.2 / 537.3
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
51.8 mm, 300 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
52.8 mm, 360 m
OK
15.0 9.6 -2.2 -11.4 -12.5 -5.5 -1.8 -11.1 -12.8 -7.0 105.0 7.1 29.2 57.6 81.3 31.8 59.2 82.1 2878.1
kN kN kN kN kN kN kN kN kN kN kN kN kN kN kN kN kN kN k
0.1
k OK 123.8 kN
537.3kN 0.89
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
NOMINAL LINKS BI-AXIAL , SLENDER, U NBRACED, COLUMN DESIGN Critical Case : 1 : Dead plus Live Part 2 of 2: with Myy Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
6465.5 k
.45x(600x500-14476)x25 + 0.95x14476.5x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x500-14476)x25 + 0.95x14476.5x460
OK Applied Moments (Mx1, Mx2) -59.4 kN.m, 98.6 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (9538 - 6466)/(9538 - 846) < 1 au = βa • K • h 0.073, 1.000, 500 Madd= N • au 6466 x 36.5 Mi=fn(Mx1, Mx2) -59.4 kN.m, 98.6 kN.m
9538.4 k OK 9217.1 k
X-X Moments 1.00 36.5 mm 236.3 kN.m 39.4 kN.m
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected], M2+Madd, M nom M nom=fn(N, exx) Design Moment
: Job Ref : Sheet Ref / 18: D.O.C.K : OCT 2012 : F.O.O : K.M.M
334.9 kN.m, 0.0 kN.m 6465.5 kN, 20.0 mm
236.3 kN.m 334.9 kN.m
Y-Y Moments Applied Moments (My1, My2) 85.3 kN.m, -140.2 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (9538 - 6466)/(9538 - 872) < 1 au = βa • K • h 0.052, 1.000, 500 Madd= N • au 6466 x 31.1 Mi=fn(My1, My2) 85.3 kN.m, -140.2 kN.m M nom=fn(M2+Madd) 341.3 M nom=fn(N, eyy) 6465.5, 20.0 Design Moment
1.00 31.1 mm 201.1 kN.m 56.1 kN.m 129.3 kN.m 201.1 kN.m 341.3 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(334.9² + 341.3² ) atn(341.3/ 334.9)
478.2 kN.m 45.5 deg
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Bar group13:M13 fn(bars,d,ε%,,la,F) Bar group14:M14 fn(bars,d,ε%,,la,F) Bar group15:M15 fn(bars,d,ε%,,la,F) Bar group16:M16 fn(bars,d,ε%,,la,F) Bar group17:M17 fn(bars,d,ε%,,la,F) Bar group18:M18 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M18)
0.811, 778 mm, 600 mm, 631.45 mm, 255828 mm², 346.2 m 1 x 32, 688.0, -0.031, -63, -298.7, -50.4 1 x 32, 351.0, 0.155, 311, 38.2, 250.0 1 x 32, 620.6, 0.006, 12, -231.3, 9.7 1 x 32, 553.2, 0.043, 87, -163.9, 69.8 1 x 32, 485.8, 0.081, 161, -96.6, 129.9 1 x 32, 418.4, 0.118, 236, -29.2, 189.9 1 x 32, 622.8, 0.005, 10, -233.6, 7.7 1 x 32, 557.7, 0.041, 82, -168.5, 65.8 1 x 32, 492.6, 0.077, 154, -103.3, 123.8 1 x 32, 427.4, 0.113, 226, -38.2, 181.9 1 x 32, 90.5, 0.300, 437, 298.7, 351.5 1 x 32, 360.1, 0.150, 301, 29.2, 242.0 1 x 32, 292.7, 0.188, 376, 96.6, 302.0 1 x 32, 225.3, 0.225, 437, 163.9, 351.5 1 x 32, 157.9, 0.262, 437, 231.3, 351.5 1 x 32, 285.9, 0.192, 383, 103.3, 308.1 1 x 32, 220.8, 0.228, 437, 168.5, 351.5 1 x 32, 155.6, 0.264, 437, 233.6, 351.5 255828 x 0.45 x 25 -50+250+10+70+130+190+8+66+124+182+35 +242+302+351+351+308+351+351+2878-6465.5
Max Moment/Mu
2878.1 x (778 / 2 - 346.2) 123.8 + (15.0+9.6+-2.2+-11.4+-12.5+-5.5 + (-1.8+-11.1+-12.8+-7.0+105.0+7.1 + (29.2+57.6+81.3+31.8+59.2+82.1) 478.2 / 537.3
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
51.8 mm, 300 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
52.8 mm, 360 m
OK
15.0 9.6 -2.2 -11.4 -12.5 -5.5 -1.8 -11.1 -12.8 -7.0 105.0 7.1 29.2 57.6 81.3 31.8 59.2 82.1 2878.1
kN kN kN kN kN kN kN kN kN kN kN kN kN kN kN kN kN kN k
0.1
k OK 123.8 kN
537.3kN 0.89
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
Nominal links
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 19: D.O.C.K : OCT 2012 : F.O.O : K.M.M
COLUMN @ COLUMN TYPE C2 LEVEL 6
Basic Data Design to
BS 8110: 199
Grades Fy, Fyv, Fcu
460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 400 mm deep column βy : for 600 mm wide column Lc=3300
Top: Deep, Bottom: Deep Top: Deep, Bottom: Deep Lox=3300-(700+700)/2 Loy=3300-(600+600)/2
1.20 1.20 2600 2700
LEX=3120.0 MM, LEX/H=7.8, EXX=20.0 MM LEY=3240.0 MM, LEY/B=5.4, EYY=20.0 MM BI-AXIAL , SHORT, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Part 1 of 2 with Mxx Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
991.7 k
.45x(600x400-4398)x25 + 0.95x4398.2x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-4398)x25 + 0.95x4398.2x460
OK Applied Moments (Mx1, Mx2) M nom=fn(N, exx) Design Moment
310.0 kN.m, -331.6 kN.m 991.7 kN, 20.0 mm
4572.5 k OK 4307.5 k
X-X Moments 19.8 kN.m 331.6 kN.m
Y-Y Moments Applied Moments (My1, My2) Design Moment
0.0 kN.m, -8.6 kN.m 8.6 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(331.6² + 8.6² ) atn(8.6/ 331.6)
331.7 kN.m 1.5 deg
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 20: D.O.C.K : OCT 2012 : F.O.O : K.M.M
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Bar group13:M13 fn(bars,d,ε%,,la,F) Bar group14:M14 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M14)
0.452, 415 mm, 600 mm, 187.62 mm, 96682 mm², 88.3 m 1 x 20, 355.9, -0.314, -437, -148.2, -137.3 1 x 20, 343.4, -0.291, -437, -135.7, -137.3 1 x 20, 352.8, -0.308, -437, -145.1, -137.3 1 x 20, 349.7, -0.302, -437, -142.0, -137.3 1 x 20, 346.5, -0.296, -437, -138.8, -137.3 1 x 20, 261.3, -0.137, -275, -53.6, -86.4 1 x 20, 166.7, 0.039, 78, 41.0, 24.6 1 x 20, 72.0, 0.216, 431, 135.7, 135.5 1 x 20, 59.5, 0.239, 437, 148.2, 137.3 1 x 20, 68.9, 0.221, 437, 138.8, 137.3 1 x 20, 65.8, 0.227, 437, 142.0, 137.3 1 x 20, 62.6, 0.233, 437, 145.1, 137.3 1 x 20, 248.8, -0.114, -228, -41.0, -71.7 1 x 20, 154.1, 0.062, 125, 53.6, 39.3 96682 x 0.45 x 25 -137-137-137-137-137-86+25+135+137+13 +137+137-72+39+1088-991.7
Max Moment/Mu
1087.7 x (415 / 2 - 88.3) 129.9 + (20.3+18.6+19.9+19.5+19.1+4.6+1.0 + (18.4+20.3+19.1+19.5+19.9+2.9+2.1) 331.7 / 335.2
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
334.4 mm, 240 m
100 As/bd, vc, vc' As/Svreq, Sv, Links Asvreq, Asvpvd
2.14%, 0.85 N/mm², 0.85 N/mm² 0 mm, 225 mm, 3 no 8 mm legs 0 mm², 151 mm²
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
8.7 mm, 360 m
OK
20.3 18.6 19.9 19.5 19.1 4.6 1.0 18.4 20.3 19.1 19.5 19.9 2.9 2.1 1087.7
kN kN kN kN kN kN kN kN kN kN kN kN kN kN k
0.0
k OK 129.9 kN 335.2kN 0.98
X-X Shear Checks OK
links reqd. Link check
Nominal OK Y-Y Shear Checks OK
NOMINAL LINKS BI-AXIAL , SHORT, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Part 2 of 2: with Myy Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
991.7 k
.45x(600x400-4398)x25 + 0.95x4398.2x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-4398)x25 + 0.95x4398.2x460
OK Applied Moments (Mx1, Mx2) Design Moment
4572.5 k OK 4307.5 k
X-X Moments
310.0 kN.m, -331.6 kN.m 331.6 kN.m
Y-Y Moments Applied Moments (My1, My2) M nom=fn(N, eyy) Design Moment
0.0 kN.m, -8.6 kN.m 991.7, 20.0
19.8 kN.m 19.8 kN.m
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
Job ref Sheet Made By Date Checked Approved
: Job Ref : Sheet Ref / 21: D.O.C.K : OCT 2012 : F.O.O : K.M.M
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(331.6² + 19.8² ) atn(19.8/ 331.6)
332.2 kN.m 3.4 deg
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Bar group13:M13 fn(bars,d,ε%,,la,F) Bar group14:M14 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M14)
0.459, 435 mm, 600 mm, 199.91 mm, 97380 mm², 98.6 m 1 x 20, 373.8, -0.304, -437, -156.2, -137.3 1 x 20, 344.9, -0.254, -437, -127.3, -137.3 1 x 20, 366.5, -0.292, -437, -149.0, -137.3 1 x 20, 359.3, -0.279, -437, -141.7, -137.3 1 x 20, 352.1, -0.266, -437, -134.5, -137.3 1 x 20, 279.3, -0.139, -278, -61.7, -87.3 1 x 20, 184.8, 0.027, 53, 32.8, 16.7 1 x 20, 90.3, 0.192, 384, 127.3, 120.6 1 x 20, 61.4, 0.243, 437, 156.2, 137.3 1 x 20, 83.0, 0.205, 409, 134.5, 128.6 1 x 20, 75.8, 0.217, 435, 141.7, 136.5 1 x 20, 68.6, 0.230, 437, 149.0, 137.3 1 x 20, 250.4, -0.088, -177, -32.8, -55.5 1 x 20, 155.9, 0.077, 154, 61.7, 48.5 97380 x 0.45 x 25 -137-137-137-137-137-87+17+121+137+12 +137+137-55+48+1096-991.7
Max Moment/Mu
1095.5 x (435 / 2 - 98.6) 130.3 + (21.4+17.5+20.5+19.5+18.5+5.4+0.5 + (15.4+21.4+17.3+19.4+20.5+1.8+3.0) 332.2 / 332.3
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
334.4 mm, 240 m
100 As/bd, vc, vc' As/Svreq, Sv, Links Asvreq, Asvpvd
2.14%, 0.85 N/mm², 0.85 N/mm² 0 mm, 225 mm, 3 no 8 mm legs 0 mm², 151 mm²
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
20 mm, 360 m
OK
21.4 17.5 20.5 19.5 18.5 5.4 0.5 15.4 21.4 17.3 19.4 20.5 1.8 3.0 1095.5
kN kN kN kN kN kN kN kN kN kN kN kN kN kN k
0.1
k OK 130.3 kN 332.3kN 1.00
X-X Shear Checks OK
links reqd. Link check
Nominal OK Y-Y Shear Checks OK
Nominal links
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 22: D.O.C.K : OCT 2012 : F.O.O : K.M.M
COLUMN @ COLUMN TYPE C2 LEVEL 5
Basic Data Design to
BS 8110: 199
Grades Fy, Fyv, Fcu
460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 400 mm deep column βy : for 600 mm wide column Lc=3300
Top: Deep, Bottom: Deep Top: Deep, Bottom: Deep Lox=3300-(700+700)/2 Loy=3300-(600+600)/2
1.20 1.20 2600 2700
LEX=3120.0 MM, LEX/H=7.8, EXX=20.0 MM LEY=3240.0 MM, LEY/B=5.4, EYY=20.0 MM BI-AXIAL , SHORT, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Part 1 of 2 with Mxx Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
2014.6 k
.45x(600x400-3770)x25 + 0.95x3769.9x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-3770)x25 + 0.95x3769.9x460
OK Applied Moments (Mx1, Mx2) M nom=fn(N, exx) Design Moment
243.4 kN.m, -200.8 kN.m 2014.6 kN, 20.0 mm
4305.0 k OK 4039.3 k
X-X Moments 40.3 kN.m 243.4 kN.m
Y-Y Moments Applied Moments (My1, My2) Design Moment
-7.3 kN.m, 10.0 kN.m 10.0 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(243.4² + 10.0² ) atn(10.0/ 243.4)
243.6 kN.m 2.4 deg
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 23: D.O.C.K : OCT 2012 : F.O.O : K.M.M
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M12)
0.635, 424 mm, 600 mm, 269.40 mm, 138206 mm², 127.3 m 1 x 20, 364.0, -0.123, -246, -151.8, -77.2 1 x 20, 344.1, -0.097, -194, -131.9, -61.0 1 x 20, 357.3, -0.114, -228, -145.2, -71.8 1 x 20, 350.7, -0.106, -211, -138.6, -66.4 1 x 20, 269.4, 0.000, 0, -57.2, 0.0 1 x 20, 174.8, 0.123, 246, 37.4, 77.2 1 x 20, 80.2, 0.246, 437, 131.9, 137.3 1 x 20, 60.3, 0.272, 437, 151.8, 137.3 1 x 20, 73.6, 0.254, 437, 138.6, 137.3 1 x 20, 67.0, 0.263, 437, 145.2, 137.3 1 x 20, 249.5, 0.026, 52, -37.4, 16.2 1 x 20, 154.9, 0.149, 297, 57.2, 93.5 138206 x 0.45 x 25 -77-61-72-66+0+77+137+137+137+137+1 +93+1555-2014.6
Max Moment/Mu
1554.8 x (424 / 2 - 127.3) 132.0 + (11.7+8.0+10.4+9.2+0.0+2.9+18.1 + (20.8+19.0+19.9+-0.6+5.3) 243.6 / 256.9
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
120.8 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
5 mm, 360 m
OK
11.7 8.0 10.4 9.2 0.0 2.9 18.1 20.8 19.0 19.9 -0.6 5.3 1554.8
kN kN kN kN kN kN kN kN kN kN kN kN k
0.0
k OK 132.0 kN 256.9kN 0.94
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
Nominal links
BI-AXIAL , SHORT, UNBRACED, COLUMN DESIGN Critical Case : 1 : Dead plus Live Part 2 of 2: with Myy Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
2014.6 k
.45x(600x400-3770)x25 + 0.95x3769.9x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-3770)x25 + 0.95x3769.9x460
OK Applied Moments (Mx1, Mx2) Design Moment
4305.0 k OK 4039.3 k
X-X Moments
243.4 kN.m, -200.8 kN.m 243.4 kN.m
Y-Y Moments Applied Moments (My1, My2) M nom=fn(N, eyy) Design Moment
-7.3 kN.m, 10.0 kN.m 2014.6, 20.0
40.3 kN.m 40.3 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(243.4² + 40.3² ) atn(40.3/ 243.4)
246.7 kN.m 9.4 deg
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F)
0.621, 493 mm, 600 mm, 306.10 mm, 137745 mm², 160.5 m 1 x 20, 425.9, -0.137, -274, -179.6, -86.1 1 x 20, 346.9, -0.047, -93, -100.6, -29.3
15.5 kN 2.9 kN
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M12)
1 x 20, 399.6, -0.107, -214, -153.3, -67.2 1 x 20, 373.2, -0.077, -154, -126.9, -48.2 1 x 20, 332.5, -0.030, -60, -86.2, -19.0 1 x 20, 239.1, 0.077, 153, 7.2, 48.1 1 x 20, 145.7, 0.183, 367, 100.6, 115.2 1 x 20, 66.7, 0.274, 437, 179.6, 137.3 1 x 20, 119.4, 0.213, 427, 126.9, 134.1 1 x 20, 93.0, 0.244, 437, 153.3, 137.3 1 x 20, 253.5, 0.060, 120, -7.2, 37.8 1 x 20, 160.1, 0.167, 334, 86.2, 104.9 137745 x 0.45 x 25 -86-29-67-48-19+48+115+137+134+137+3 +105+1550-2014.6
Max Moment/Mu
1549.6 x (493 / 2 - 160.5) 133.0 + (15.5+2.9+10.3+6.1+1.6+0.3+11.6 + (24.7+17.0+21.0+-0.3+9.0) 246.7 / 252.9
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
120.8 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
20 mm, 360 m
OK
: Job Ref : Sheet Ref / 24: D.O.C.K : OCT 2012 : F.O.O : K.M.M
10.3 6.1 1.6 0.3 11.6 24.7 17.0 21.0 -0.3 9.0 1549.6
kN kN kN kN kN kN kN kN kN kN k
0.0
k OK 133.0 kN 252.9kN 0.97
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
Nominal links
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 25: D.O.C.K : OCT 2012 : F.O.O : K.M.M
COLUMN @ COLUMN TYPE C2 LEVEL 4
Basic Data Design to
BS 8110: 199
Grades Fy, Fyv, Fcu
460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 400 mm deep column βy : for 600 mm wide column Lc=3300
Top: Deep, Bottom: Deep Top: Deep, Bottom: Deep Lox=3300-(700+700)/2 Loy=3300-(600+600)/2
1.20 1.20 2600 2700
LEX=3120.0 MM, LEX/H=7.8, EXX=20.0 MM LEY=3240.0 MM, LEY/B=5.4, EYY=20.0 MM BI-AXIAL , SHORT, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Part 1 of 2 with Mxx Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
2928.0 k
.45x(600x400-5890)x25 + 0.95x5890.5x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-5890)x25 + 0.95x5890.5x460
OK Applied Moments (Mx1, Mx2) M nom=fn(N, exx) Design Moment
257.0 kN.m, -224.5 kN.m 2928.0 kN, 20.0 mm
5207.9 k OK 4944.5 k
X-X Moments 58.6 kN.m 257.0 kN.m
Y-Y Moments Applied Moments (My1, My2) Design Moment
-2.8 kN.m, 0.0 kN.m 2.8 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(257.0² + 2.8² ) atn(2.8/ 257.0)
257.0 kN.m 0.6 deg
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 26: D.O.C.K : OCT 2012 : F.O.O : K.M.M
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
0.742, 407 mm, 600 mm, 301.53 mm, 160874 mm², 137.3 m 1 x 25, 345.4, -0.051, -102, -142.1, -49.9 7.1 1 x 25, 340.1, -0.045, -90, -136.9, -44.0 6.0 1 x 25, 343.6, -0.049, -98, -140.4, -48.0 6.7 1 x 25, 341.9, -0.047, -94, -138.6, -46.0 6.4 1 x 25, 252.4, 0.057, 114, -49.1, 56.0 -2.8 1 x 25, 159.4, 0.165, 330, 43.9, 162.0 7.1 1 x 25, 66.4, 0.273, 437, 136.9, 214.5 29.4 1 x 25, 61.2, 0.279, 437, 142.1, 214.5 30.5 1 x 25, 64.6, 0.275, 437, 138.6, 214.5 29.7 1 x 25, 62.9, 0.277, 437, 140.4, 214.5 30.1 1 x 25, 247.1, 0.063, 126, -43.9, 62.0 -2.7 1 x 25, 154.2, 0.171, 342, 49.1, 167.9 8.2 160874 x 0.45 x 25 1809.8 -50-44-48-46+56+162+215+215+215+21+62+168+1810-2928 -0.1
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M12) Max Moment/Mu
1809.8 x (407 / 2 - 137.3) 119.3 + (7.1+6.0+6.7+6.4+-2.8+7.1+29.4+30.5 + (29.7+30.1+-2.7+8.2) 257.0 / 275.1
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
87.8 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
1 mm, 360 m
OK
kN kN kN kN kN kN kN kN kN kN kN kN k k OK 119.3 kN 275.1kN 0.93
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
Nominal links
BI-AXIAL , SHORT, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Part 2 of 2: with Myy Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
2928.0 k
.45x(600x400-5890)x25 + 0.95x5890.5x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-5890)x25 + 0.95x5890.5x460
OK Applied Moments (Mx1, Mx2) Design Moment
5207.9 k OK 4944.5 k
X-X Moments
257.0 kN.m, -224.5 kN.m 257.0 kN.m
Y-Y Moments Applied Moments (My1, My2) M nom=fn(N, eyy) Design Moment
-2.8 kN.m, 0.0 kN.m 2928.0, 20.0
58.6 kN.m 58.6 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(257.0² + 58.6² ) atn(58.6/ 257.0)
263.6 kN.m 12.8 deg
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F)
0.702, 523 mm, 600 mm, 367.62 mm, 162588 mm², 196.0 m 1 x 25, 450.9, -0.079, -159, -189.2, -77.8 1 x 25, 344.5, 0.022, 44, -82.8, 21.7 1 x 25, 415.4, -0.045, -91, -153.8, -44.7
14.7 kN -1.8 kN 6.9 kN
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M12)
Job ref Sheet Made By Date Checked Approved
1 x 25, 379.9, -0.012, -23, -118.3, -11.5 1 x 25, 360.2, 0.007, 14, -98.5, 6.9 1 x 25, 269.5, 0.093, 187, -7.9, 91.7 1 x 25, 178.8, 0.180, 359, 82.8, 176.4 1 x 25, 72.4, 0.281, 437, 189.2, 214.5 1 x 25, 143.4, 0.213, 427, 118.3, 209.6 1 x 25, 107.9, 0.247, 437, 153.7, 214.5 1 x 25, 253.8, 0.108, 217, 7.9, 106.4 1 x 25, 163.1, 0.195, 389, 98.5, 191.2 162588 x 0.45 x 25 -78+22-45-12+7+92+176+215+210+215+10 +191+1829-2928
Max Moment/Mu
1829.1 x (523 / 2 - 196.0) 120.2 + (14.7+-1.8+6.9+1.4+-0.7+-0.7+14.6 + (40.6+24.8+33.0+0.8+18.8) 263.6 / 272.6
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
87.8 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
20 mm, 360 m
OK
: Job Ref : Sheet Ref / 27: D.O.C.K : OCT 2012 : F.O.O : K.M.M
1.4 -0.7 -0.7 14.6 40.6 24.8 33.0 0.8 18.8 1829.1
kN kN kN kN kN kN kN kN kN k
0.0
k OK 120.2 kN 272.6kN 0.96
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
Nominal links
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 28: D.O.C.K : OCT 2012 : F.O.O : K.M.M
COLUMN @ COLUMN TYPE C2 LEVEL 3
Basic Data Design to
BS 8110: 199
Grades Fy, Fyv, Fcu
460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 400 mm deep column βy : for 600 mm wide column Lc=3300
Top: Deep, Bottom: Deep Top: Deep, Bottom: Deep Lox=3300-(700+700)/2 Loy=3300-(600+600)/2
1.20 1.20 2600 2700
LEX=3120.0 MM, LEX/H=7.8, EXX=20.0 MM LEY=3240.0 MM, LEY/B=5.4, EYY=20.0 MM U NI-AXIAL , SHORT, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
3736.0 k
.45x(600x400-7854)x25 + 0.95x7854.0x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-7854)x25 + 0.95x7854.0x460
OK M nom Design Moment
6043.8 k OK 5782.7 k
X-X Moments
74.7 257.0 kN.m
Moment Capacity Mu X-X Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp= 0
0.819, 400 mm, 600 mm, 327.49 mm, 176845 mm², 147.4 m 6 x 25, 60.5, 0.285, 437, 139.5, 1287.1 6 x 25, 339.5, -0.013, -26, -139.5, -75.6 2 x 25, 242.3, 0.091, 182, -42.3, 178.7 2 x 25, 157.7, 0.181, 363, 42.3, 356.4 176845 x 0.45 x 25 1287 - 76 + 179 + 356 + 1990 - 3736.0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M4) Max Moment/Mu
1989.5 x (400 / 2 - 147.4) 104.7 + (179.5+10.5+-7.6+15.1) 257.0 / 302.3
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
68.8 mm, 240 m
OK
179.5 10.5 -7.6 15.1 1989.5 0.0
kN kN kN kN k k OK 104.7 kN 302.3kN 0.85
X-X Shear Checks OK
Nominal links
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 29: D.O.C.K : OCT 2012 : F.O.O : K.M.M
COLUMN @ COLUMN TYPE C2 LEVEL 2
Basic Data Design to
BS 8110: 199
Grades Fy, Fyv, Fcu
460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 400 mm deep column βy : for 600 mm wide column Lc=5000
Top: Deep, Bottom: Shallow Top: Deep, Bottom: Deep Lox=5000-(700+700)/2 Loy=5000-(600+600)/2
1.30 1.20 4300 4400
LEX=5590.0 MM, LEX/H=14.0, EXX=20.0 MM LEY=5280.0 MM, LEY/B=8.8, EYY=20.0 MM SLENDER, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live
U NI-AXIAL ,
Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
4715.3 k
.45x(600x400-14205)x25 + 0.95x14204.7x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-14205)x25 + 0.95x14204.7x460
OK
8747.7 k OK 8493.6 k
X-X Moments
Applied Moments(M1, M2) -213.2 kN.m, 300.1 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (8748 - 4715)/(8748 - 1296) < 1 au = βa • K • h 0.098, 1.000, 400 Madd= N • au 4715 x 39.1 Initial Moment Mi=fn(M1,M2) -213.2 kN.m, 300.1 kN.m M2+Madd, M nom 484.3, 94.3 Design Moment
1.00 39.1 mm 184.2 kN.m 120.0 kN.m 484.3 kN.m
Moment Capacity Mu X-X Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F)
0.772, 400 mm, 600 mm, 308.80 mm, 166749 mm², 139.0 m 7 x 32, 64.0, 0.277, 437, 136.0, 2460.2 7 x 32, 336.0, -0.031, -62, -136.0, -347.2 2 x 25, 260.0, 0.055, 111, -60.0, 108.6
334.6 kN 47.2 kN -6.5 kN
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
2 x 25, 200.0, 0.123, 247, 0.0, 242.1 2 x 25, 140.0, 0.191, 383, 60.0, 375.7 166749 x 0.45 x 25 2460 -347 +109 +242 +376 +1876 -4715.3
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M5) Max Moment/Mu
1875.9 x (400 / 2 - 139.0) 114.5 + (334.6+47.2+-6.5+0.0+22.5) 484.3 / 512.3
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
102.7 mm, 240 m
OK
: Job Ref : Sheet Ref / 30: D.O.C.K : OCT 2012 : F.O.O : K.M.M
0.0 kN 22.5 kN 1875.9 k 0.0 k OK 114.5 kN 512.3kN 0.94
X-X Shear Checks OK
Nominal links
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
Job ref Sheet Made By Date Checked Approved
: Job Ref : Sheet Ref / 31: D.O.C.K : OCT 2012 : F.O.O : K.M.M
COLUMN @ COLUMN TYPE C2 LEVEL 1
Basic Data Design to
BS 8110: 199
Grades Fy, Fyv, Fcu
460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 500 mm deep column βy : for 600 mm wide column Lc=5000
Top: Shallow, Bottom: Shallow Top: Deep, Bottom: Shallow Lox=5000-(700+0)/2 Loy=5000-(600+0)/2
1.50 1.30 4650 4700
LEX=6975.0 MM, LEX/H=14.0, EXX=20.0 MM LEY=6110.0 MM, LEY/B=10.2, EYY=20.0 MM SLENDER, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live
U NI-AXIAL ,
Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
5486.0 k
.45x(600x500-12868)x25 + 0.95x12868.0x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x500-12868)x25 + 0.95x12868.0x460
OK
8853.5 k OK 8530.5 k
X-X Moments
Applied Moments(M1, M2) 175.9 kN.m, -283.7 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (8854 - 5486)/(8854 - 846) < 1 au = βa • K • h 0.097, 1.000, 500 Madd= N • au 5486 x 48.7 Initial Moment Mi=fn(M1,M2) 175.9 kN.m, -283.7 kN.m M2+Madd, M nom 550.6, 109.7 Design Moment
1.00 48.7 mm 266.9 kN.m 113.5 kN.m 550.6 kN.m
Moment Capacity Mu X-X Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu)
0.831, 500 mm, 600 mm, 415.39 mm, 224311 mm², 186.9 m 5 x 32, 64.0, 0.296, 437, 186.0, 1757.3 5 x 32, 436.0, -0.017, -35, -186.0, -139.7 2 x 32, 335.0, 0.068, 135, -85.0, 217.9 2 x 32, 250.0, 0.139, 279, 0.0, 448.3 2 x 32, 165.0, 0.211, 422, 85.0, 678.7 224311 x 0.45 x 25
326.9 26.0 -18.5 0.0 57.7 2523.5
kN kN kN kN kN k
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
F Equlibrum (Ft) + FC - Fapp = 0
1757 -140 + 218 + 448 + 679 + 2523 -5486
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M5) Max Moment/Mu
2523.5 x (500 / 2 - 186.9) 159.2 + (326.9+26.0+-18.5+0.0+57.7) 550.6 / 551.2
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
100.4 mm, 300 m
OK
: Job Ref : Sheet Ref / 32: D.O.C.K : OCT 2012 : F.O.O : K.M.M
0.0
k OK 159.2 kN 551.2kN 0.99
X-X Shear Checks OK
Nominal links
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 33: D.O.C.K : OCT 2012 : F.O.O : K.M.M
COLUMN @ COLUMN TYPE C3 LEVEL 6
Basic Data Design to
BS 8110: 199
Grades Fy, Fyv, Fcu
460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 400 mm deep column βy : for 600 mm wide column Lc=3300
Top: Shallow, Bottom: Shallow Top: Deep, Bottom: Deep Lox=3300-(700+700)/2 Loy=3300-(600+600)/2
1.50 1.20 2600 2700
LEX=3900.0 MM, LEX/H=9.8, EXX=20.0 MM LEY=3240.0 MM, LEY/B=5.4, EYY=20.0 MM BI-AXIAL , SHORT, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Part 1 of 2 with Mxx Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
598.9 k
.45x(600x400-4398)x25 + 0.95x4398.2x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-4398)x25 + 0.95x4398.2x460
OK Applied Moments (Mx1, Mx2) M nom=fn(N, exx) Design Moment
-165.2 kN.m, 191.9 kN.m 598.9 kN, 20.0 mm
4572.5 k OK 4307.5 k
X-X Moments 12.0 kN.m 191.9 kN.m
Y-Y Moments Applied Moments (My1, My2) Design Moment
-129.1 kN.m, 153.5 kN.m 153.5 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(191.9² + 153.5² ) atn(153.5/ 191.9)
245.7 kN.m 38.7 deg
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 34: D.O.C.K : OCT 2012 : F.O.O : K.M.M
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Bar group13:M13 fn(bars,d,ε%,,la,F) Bar group14:M14 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Max Moment/Mu
0.445, 687 mm, 600 mm, 305.98 mm, 77731 mm², 183.6 m 1 x 20, 605.6, -0.343, -437, -262.1, -137.3 1 x 20, 303.3, 0.003, 6, 40.3, 1.9 1 x 20, 530.0, -0.256, -437, -186.5, -137.3 1 x 20, 454.5, -0.170, -340, -110.9, -106.7 1 x 20, 378.9, -0.083, -167, -35.3, -52.4 1 x 20, 531.7, -0.258, -437, -188.1, -137.3 1 x 20, 457.8, -0.174, -347, -114.2, -109.1 1 x 20, 383.9, -0.089, -178, -40.3, -56.0 1 x 20, 81.5, 0.257, 437, 262.1, 137.3 1 x 20, 308.3, -0.003, -5, 35.3, -1.6 1 x 20, 232.7, 0.084, 168, 110.9, 52.7 1 x 20, 157.1, 0.170, 341, 186.5, 107.0 1 x 20, 229.4, 0.088, 175, 114.2, 55.1 1 x 20, 155.4, 0.172, 344, 188.1, 108.2 77731 x 0.45 x 25 -137+2-137-107-52-137-109-56+137-2+5 +107+55+108+874-598.9 874.5 x (687 / 2 - 183.6) 139.9 + (36.0+0.1+25.6+11.8+1.9+25.8+12.5 + (2.3+36.0+-0.1+5.8+20.0+6.3+20.4) 245.7 / 344.1
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
320.4 mm, 240 m
100 As/bd, vc, vc' As/Svreq, Sv, Links Asvreq, Asvpvd
2.14%, 0.85 N/mm², 0.85 N/mm² 0 mm, 225 mm, 3 no 8 mm legs 0 mm², 151 mm²
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
256.3 mm, 360 m
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M14)
OK
36.0 0.1 25.6 11.8 1.9 25.8 12.5 2.3 36.0 -0.1 5.8 20.0 6.3 20.4 874.5
kN kN kN kN kN kN kN kN kN kN kN kN kN kN k
0.0 k 139.9 kN 344.1kN 0.71
X-X Shear Checks OK
links reqd. Link check
Nominal OK Y-Y Shear Checks OK
NOMINAL LINKS BI-AXIAL , SHORT, UNBRACED, COLUMN DESIGN Critical Case : 1 : Dead plus Live Part 2 of 2: with Myy Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
598.9 k
.45x(600x400-4398)x25 + 0.95x4398.2x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-4398)x25 + 0.95x4398.2x460
OK Applied Moments (Mx1, Mx2) Design Moment
4572.5 k OK 4307.5 k
X-X Moments
-165.2 kN.m, 191.9 kN.m 191.9 kN.m
Y-Y Moments Applied Moments (My1, My2) M nom=fn(N, eyy) Design Moment
-129.1 kN.m, 153.5 kN.m 598.9, 20.0
12.0 kN.m 153.5 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(191.9² + 153.5² ) atn(153.5/ 191.9)
245.7 kN.m 38.7 deg
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
Job ref Sheet Made By Date Checked Approved
: Job Ref : Sheet Ref / 35: D.O.C.K : OCT 2012 : F.O.O : K.M.M
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Bar group13:M13 fn(bars,d,ε%,,la,F) Bar group14:M14 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Max Moment/Mu
0.445, 687 mm, 600 mm, 305.98 mm, 77731 mm², 183.6 m 1 x 20, 605.6, -0.343, -437, -262.1, -137.3 1 x 20, 303.3, 0.003, 6, 40.3, 1.9 1 x 20, 530.0, -0.256, -437, -186.5, -137.3 1 x 20, 454.5, -0.170, -340, -110.9, -106.7 1 x 20, 378.9, -0.083, -167, -35.3, -52.4 1 x 20, 531.7, -0.258, -437, -188.1, -137.3 1 x 20, 457.8, -0.174, -347, -114.2, -109.1 1 x 20, 383.9, -0.089, -178, -40.3, -56.0 1 x 20, 81.5, 0.257, 437, 262.1, 137.3 1 x 20, 308.3, -0.003, -5, 35.3, -1.6 1 x 20, 232.7, 0.084, 168, 110.9, 52.7 1 x 20, 157.1, 0.170, 341, 186.5, 107.0 1 x 20, 229.4, 0.088, 175, 114.2, 55.1 1 x 20, 155.4, 0.172, 344, 188.1, 108.2 77731 x 0.45 x 25 -137+2-137-107-52-137-109-56+137-2+5 +107+55+108+874-598.9 874.5 x (687 / 2 - 183.6) 139.9 + (36.0+0.1+25.6+11.8+1.9+25.8+12.5 + (2.3+36.0+-0.1+5.8+20.0+6.3+20.4) 245.7 / 344.1
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
320.4 mm, 240 m
100 As/bd, vc, vc' As/Svreq, Sv, Links Asvreq, Asvpvd
2.14%, 0.85 N/mm², 0.85 N/mm² 0 mm, 225 mm, 3 no 8 mm legs 0 mm², 151 mm²
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
256.3 mm, 360 m
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M14)
OK
36.0 0.1 25.6 11.8 1.9 25.8 12.5 2.3 36.0 -0.1 5.8 20.0 6.3 20.4 874.5
kN kN kN kN kN kN kN kN kN kN kN kN kN kN k
0.0 k 139.9 kN 344.1kN 0.71
X-X Shear Checks OK
links reqd. Link check
Nominal OK Y-Y Shear Checks OK
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 36: D.O.C.K : OCT 2012 : F.O.O : K.M.M
COLUMN @ COLUMN TYPE C3 LEVEL 5
Basic Data Design to
BS 8110: 199
Grades Fy, Fyv, Fcu
460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 400 mm deep column βy : for 600 mm wide column Lc=3300
Top: Shallow, Bottom: Shallow Top: Deep, Bottom: Deep Lox=3300-(700+700)/2 Loy=3300-(600+600)/2
1.50 1.20 2600 2700
LEX=3900.0 MM, LEX/H=9.8, EXX=20.0 MM LEY=3240.0 MM, LEY/B=5.4, EYY=20.0 MM BI-AXIAL , SHORT, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Part 1 of 2 with Mxx Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
1250.3 k
.45x(600x400-4398)x25 + 0.95x4398.2x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-4398)x25 + 0.95x4398.2x460
OK Applied Moments (Mx1, Mx2) M nom=fn(N, exx) Design Moment
-101.1 kN.m, 83.3 kN.m 1250.3 kN, 20.0 mm
4572.5 k OK 4307.5 k
X-X Moments 25.0 kN.m 101.1 kN.m
Y-Y Moments Applied Moments (My1, My2) Design Moment
-78.8 kN.m, 61.8 kN.m 78.8 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(101.1² + 78.8² ) atn(78.8/ 101.1)
128.2 kN.m 37.9 deg
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 37: D.O.C.K : OCT 2012 : F.O.O : K.M.M
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Bar group13:M13 fn(bars,d,ε%,,la,F) Bar group14:M14 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M14)
0.516, 684 mm, 600 mm, 352.89 mm, 104016 mm², 211.7 m 1 x 20, 602.9, -0.248, -437, -260.8, -137.3 1 x 20, 305.4, 0.047, 94, 36.8, 29.6 1 x 20, 528.6, -0.174, -348, -186.4, -109.5 1 x 20, 454.2, -0.100, -201, -112.0, -63.1 1 x 20, 379.8, -0.027, -53, -37.6, -16.8 1 x 20, 528.3, -0.174, -348, -186.1, -109.3 1 x 20, 453.6, -0.100, -200, -111.4, -62.8 1 x 20, 378.9, -0.026, -52, -36.8, -16.2 1 x 20, 81.4, 0.269, 437, 260.8, 137.3 1 x 20, 304.6, 0.048, 96, 37.6, 30.1 1 x 20, 230.2, 0.122, 243, 112.0, 76.5 1 x 20, 155.8, 0.195, 391, 186.4, 122.8 1 x 20, 230.7, 0.121, 242, 111.4, 76.1 1 x 20, 156.1, 0.195, 390, 186.1, 122.7 104016 x 0.45 x 25 -137+30-109-63-17-109-63-16+137+30+7 +123+76+123+1170-1250.3
Max Moment/Mu
1170.2 x (684 / 2 - 211.7) 152.6 + (35.8+1.1+20.4+7.1+0.6+20.3+7.0 + (0.6+35.8+1.1+8.6+22.9+8.5+22.8) 128.2 / 345.3
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
80.9 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
63 mm, 360 m
OK
35.8 1.1 20.4 7.1 0.6 20.3 7.0 0.6 35.8 1.1 8.6 22.9 8.5 22.8 1170.2
kN kN kN kN kN kN kN kN kN kN kN kN kN kN k
0.1
k OK 152.6 kN 345.3kN 0.37
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
NOMINAL LINKS BI-AXIAL , SHORT, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Part 2 of 2: with Myy Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
1250.3 k
.45x(600x400-4398)x25 + 0.95x4398.2x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-4398)x25 + 0.95x4398.2x460
OK Applied Moments (Mx1, Mx2) Design Moment
4572.5 k OK 4307.5 k
X-X Moments
-101.1 kN.m, 83.3 kN.m 101.1 kN.m
Y-Y Moments Applied Moments (My1, My2) M nom=fn(N, eyy) Design Moment
-78.8 kN.m, 61.8 kN.m 1250.3, 20.0
25.0 kN.m 78.8 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(101.1² + 78.8² ) atn(78.8/ 101.1)
128.2 kN.m 37.9 deg
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F)
0.516, 684 mm, 600 mm, 352.89 mm, 104016 mm², 211.7 m 1 x 20, 602.9, -0.248, -437, -260.8, -137.3 1 x 20, 305.4, 0.047, 94, 36.8, 29.6
35.8 kN 1.1 kN
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected], Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Bar group13:M13 fn(bars,d,ε%,,la,F) Bar group14:M14 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M14)
1 x 20, 528.6, -0.174, -348, -186.4, -109.5 1 x 20, 454.2, -0.100, -201, -112.0, -63.1 1 x 20, 379.8, -0.027, -53, -37.6, -16.8 1 x 20, 528.3, -0.174, -348, -186.1, -109.3 1 x 20, 453.6, -0.100, -200, -111.4, -62.8 1 x 20, 378.9, -0.026, -52, -36.8, -16.2 1 x 20, 81.4, 0.269, 437, 260.8, 137.3 1 x 20, 304.6, 0.048, 96, 37.6, 30.1 1 x 20, 230.2, 0.122, 243, 112.0, 76.5 1 x 20, 155.8, 0.195, 391, 186.4, 122.8 1 x 20, 230.7, 0.121, 242, 111.4, 76.1 1 x 20, 156.1, 0.195, 390, 186.1, 122.7 104016 x 0.45 x 25 -137+30-109-63-17-109-63-16+137+30+7 +123+76+123+1170-1250.3
Max Moment/Mu
1170.2 x (684 / 2 - 211.7) 152.6 + (35.8+1.1+20.4+7.1+0.6+20.3+7.0 + (0.6+35.8+1.1+8.6+22.9+8.5+22.8) 128.2 / 345.3
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
80.9 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
63 mm, 360 m
OK
: Job Ref : Sheet Ref / 38: D.O.C.K : OCT 2012 : F.O.O : K.M.M
20.4 7.1 0.6 20.3 7.0 0.6 35.8 1.1 8.6 22.9 8.5 22.8 1170.2
kN kN kN kN kN kN kN kN kN kN kN kN k
0.1
k OK 152.6 kN 345.3kN 0.37
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
Nominal links
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 39: D.O.C.K : OCT 2012 : F.O.O : K.M.M
COLUMN @ COLUMN TYPE C3 LEVEL 4
Basic Data Design to
BS 8110: 199
Grades Fy, Fyv, Fcu
460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 400 mm deep column βy : for 600 mm wide column Lc=3300
Top: Shallow, Bottom: Shallow Top: Deep, Bottom: Deep Lox=3300-(700+700)/2 Loy=3300-(600+600)/2
1.50 1.20 2600 2700
LEX=3900.0 MM, LEX/H=9.8, EXX=20.0 MM LEY=3240.0 MM, LEY/B=5.4, EYY=20.0 MM BI-AXIAL , SHORT, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Part 1 of 2 with Mxx Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
1830.3 k
.45x(600x400-5890)x25 + 0.95x5890.5x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-5890)x25 + 0.95x5890.5x460
OK Applied Moments (Mx1, Mx2) M nom=fn(N, exx) Design Moment
5207.9 k OK 4944.5 k
X-X Moments
-105.8 kN.m, 96.2 kN.m 1830.3 kN, 20.0 mm
36.6 kN.m 105.8 kN.m
Y-Y Moments Applied Moments (My1, My2) Design Moment
-77.8 kN.m, 73.9 kN.m 77.8 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(105.8² + 77.8² ) atn(77.8/ 105.8)
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar
0.566, 678 mm, 600 mm, 383.85 mm, 124462 mm², 229.8 m
131.3 kN.m 36.3 deg
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected], Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M12)
: Job Ref : Sheet Ref / 40: D.O.C.K : OCT 2012 : F.O.O : K.M.M
1 x 25, 593.1, -0.191, -382, -254.3, -187.3 1 x 25, 309.4, 0.068, 136, 29.5, 66.7 1 x 25, 498.5, -0.105, -209, -159.7, -102.7 1 x 25, 403.9, -0.018, -37, -65.1, -18.0 1 x 25, 518.2, -0.123, -245, -179.3, -120.3 1 x 25, 443.3, -0.054, -108, -104.4, -53.2 1 x 25, 368.4, 0.014, 28, -29.5, 13.9 1 x 25, 84.6, 0.273, 437, 254.3, 214.5 1 x 25, 273.8, 0.100, 201, 65.1, 98.5 1 x 25, 179.2, 0.187, 373, 159.7, 183.2 1 x 25, 234.4, 0.136, 272, 104.4, 133.8 1 x 25, 159.5, 0.205, 409, 179.3, 200.8 124462 x 0.45 x 25 -187+67-103-18-120-53+14+215+99+18 +134+201+1400-1830.3
Max Moment/Mu
1400.2 x (678 / 2 - 229.8) 152.7 + (47.6+2.0+16.4+1.2+21.6+5.6+-0.4 + (54.5+6.4+29.3+14.0+36.0) 131.3 / 386.7
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
57.8 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
42.5 mm, 360 m
OK
47.6 2.0 16.4 1.2 21.6 5.6 -0.4 54.5 6.4 29.3 14.0 36.0 1400.2
kN kN kN kN kN kN kN kN kN kN kN kN k
-0.2
k OK 152.7 kN 386.7kN 0.34
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
NOMINAL LINKS BI-AXIAL , SHORT, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Part 2 of 2: with Myy Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
1830.3 k
.45x(600x400-5890)x25 + 0.95x5890.5x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-5890)x25 + 0.95x5890.5x460
OK Applied Moments (Mx1, Mx2) Design Moment
5207.9 k OK 4944.5 k
X-X Moments
-105.8 kN.m, 96.2 kN.m 105.8 kN.m
Y-Y Moments Applied Moments (My1, My2) M nom=fn(N, eyy) Design Moment
-77.8 kN.m, 73.9 kN.m 1830.3, 20.0
36.6 kN.m 77.8 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(105.8² + 77.8² ) atn(77.8/ 105.8)
131.3 kN.m 36.3 deg
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F)
0.566, 678 mm, 600 mm, 383.85 mm, 124462 mm², 229.8 m 1 x 25, 593.1, -0.191, -382, -254.3, -187.3 1 x 25, 309.4, 0.068, 136, 29.5, 66.7 1 x 25, 498.5, -0.105, -209, -159.7, -102.7 1 x 25, 403.9, -0.018, -37, -65.1, -18.0 1 x 25, 518.2, -0.123, -245, -179.3, -120.3
47.6 2.0 16.4 1.2 21.6
kN kN kN kN kN
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
Job ref Sheet Made By Date Checked Approved
: Job Ref : Sheet Ref / 41: D.O.C.K : OCT 2012 : F.O.O : K.M.M
Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
1 x 25, 443.3, -0.054, -108, -104.4, -53.2 5.6 1 x 25, 368.4, 0.014, 28, -29.5, 13.9 -0.4 1 x 25, 84.6, 0.273, 437, 254.3, 214.5 54.5 1 x 25, 273.8, 0.100, 201, 65.1, 98.5 6.4 1 x 25, 179.2, 0.187, 373, 159.7, 183.2 29.3 1 x 25, 234.4, 0.136, 272, 104.4, 133.8 14.0 1 x 25, 159.5, 0.205, 409, 179.3, 200.8 36.0 124462 x 0.45 x 25 1400.2 -187+67-103-18-120-53+14+215+99+18+134+201+1400-1830.3 -0.2
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M12)
1400.2 x (678 / 2 - 229.8) 152.7 + (47.6+2.0+16.4+1.2+21.6+5.6+-0.4
+ (54.5+6.4+29.3+14.0+36.0)
Max Moment/Mu
kN kN kN kN kN kN kN k k OK 152.7 kN
386.7kN
131.3 / 386.7
0.34
OK App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
57.8 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
42.5 mm, 360 m
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
Nominal links
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 42: D.O.C.K : OCT 2012 : F.O.O : K.M.M
COLUMN @ COLUMN TYPE C3 LEVEL 3
Basic Data Design to
BS 8110: 199
Grades Fy, Fyv, Fcu
460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 400 mm deep column βy : for 600 mm wide column Lc=3300
Top: Shallow, Bottom: Shallow Top: Deep, Bottom: Deep Lox=3300-(700+700)/2 Loy=3300-(600+600)/2
1.50 1.20 2600 2700
LEX=3900.0 MM, LEX/H=9.8, EXX=20.0 MM LEY=3240.0 MM, LEY/B=5.4, EYY=20.0 MM BI-AXIAL , SHORT, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Part 1 of 2 with Mxx Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
2351.0 k
.45x(600x400-5890)x25 + 0.95x5890.5x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-5890)x25 + 0.95x5890.5x460
OK Applied Moments (Mx1, Mx2) M nom=fn(N, exx) Design Moment
5207.9 k OK 4944.5 k
X-X Moments
-88.2 kN.m, 83.6 kN.m 2351.0 kN, 20.0 mm
47.0 kN.m 88.2 kN.m
Y-Y Moments Applied Moments (My1, My2) Design Moment
-66.3 kN.m, 59.3 kN.m 66.3 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(88.2² + 66.3² ) atn(66.3/ 88.2)
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar
0.617, 680 mm, 600 mm, 419.75 mm, 144753 mm², 249.0 m
110.3 kN.m 36.9 deg
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected], Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M12)
Max Moment/Mu
: Job Ref : Sheet Ref / 43: D.O.C.K : OCT 2012 : F.O.O : K.M.M
1 x 25, 595.5, -0.147, -293, -255.4, -143.9 1 x 25, 307.7, 0.093, 187, 32.4, 91.7 1 x 25, 499.6, -0.067, -133, -159.5, -65.4 1 x 25, 403.7, 0.013, 27, -63.5, 13.2 1 x 25, 521.2, -0.085, -169, -181.1, -83.0 1 x 25, 446.9, -0.023, -45, -106.7, -22.2 1 x 25, 372.5, 0.039, 79, -32.4, 38.7 1 x 25, 84.7, 0.279, 437, 255.4, 214.5 1 x 25, 276.6, 0.119, 239, 63.5, 117.2 1 x 25, 180.7, 0.199, 399, 159.5, 195.7 1 x 25, 233.4, 0.155, 311, 106.7, 152.6 1 x 25, 159.1, 0.217, 435, 181.1, 213.4 144753 x 0.45 x 25 -144+92-65+13-83-22+39+215+117+196+15 +213+1628-2351
36.8 3.0 10.4 -0.8 15.0 2.4 -1.3 54.8 7.4 31.2 16.3 38.6 1628.5 -0.1
k OK 148.4 kN
1628.5 x (680 / 2 - 249.0) 148.4 + (36.8+3.0+10.4+-0.8+15.0+2.4+-1.3 + (54.8+7.4+31.2+16.3+38.6)
362.2kN
110.3 / 362.2
0.30
OK App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
37.5 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
28.2 mm, 360 m
kN kN kN kN kN kN kN kN kN kN kN kN k
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
NOMINAL LINKS BI-AXIAL , SHORT, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Part 2 of 2: with Myy Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
2351.0 k
.45x(600x400-5890)x25 + 0.95x5890.5x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-5890)x25 + 0.95x5890.5x460
OK Applied Moments (Mx1, Mx2) Design Moment
5207.9 k OK 4944.5 k
X-X Moments
-88.2 kN.m, 83.6 kN.m 88.2 kN.m
Y-Y Moments Applied Moments (My1, My2) M nom=fn(N, eyy) Design Moment
-66.3 kN.m, 59.3 kN.m 2351.0, 20.0
47.0 kN.m 66.3 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(88.2² + 66.3² ) atn(66.3/ 88.2)
110.3 kN.m 36.9 deg
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F)
0.617, 680 mm, 600 mm, 419.75 mm, 144753 mm², 249.0 m 1 x 25, 595.5, -0.147, -293, -255.4, -143.9 1 x 25, 307.7, 0.093, 187, 32.4, 91.7 1 x 25, 499.6, -0.067, -133, -159.5, -65.4 1 x 25, 403.7, 0.013, 27, -63.5, 13.2 1 x 25, 521.2, -0.085, -169, -181.1, -83.0
36.8 3.0 10.4 -0.8 15.0
kN kN kN kN kN
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected], Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M12)
Job ref Sheet Made By Date Checked Approved
1 x 25, 446.9, -0.023, -45, -106.7, -22.2 1 x 25, 372.5, 0.039, 79, -32.4, 38.7 1 x 25, 84.7, 0.279, 437, 255.4, 214.5 1 x 25, 276.6, 0.119, 239, 63.5, 117.2 1 x 25, 180.7, 0.199, 399, 159.5, 195.7 1 x 25, 233.4, 0.155, 311, 106.7, 152.6 1 x 25, 159.1, 0.217, 435, 181.1, 213.4 144753 x 0.45 x 25 -144+92-65+13-83-22+39+215+117+196+15 +213+1628-2351
Max Moment/Mu
1628.5 x (680 / 2 - 249.0) 148.4 + (36.8+3.0+10.4+-0.8+15.0+2.4+-1.3 + (54.8+7.4+31.2+16.3+38.6) 110.3 / 362.2
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
37.5 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
28.2 mm, 360 m
OK
: Job Ref : Sheet Ref / 44: D.O.C.K : OCT 2012 : F.O.O : K.M.M
2.4 -1.3 54.8 7.4 31.2 16.3 38.6 1628.5
kN kN kN kN kN kN kN k
-0.1
k OK 148.4 kN 362.2kN 0.30
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
Nominal links
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 45: D.O.C.K : OCT 2012 : F.O.O : K.M.M
COLUMN @ COLUMN TYPE C3 LEVEL 2
Basic Data Design to
BS 8110: 199
Grades Fy, Fyv, Fcu
460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 400 mm deep column βy : for 600 mm wide column Lc=5000
Top: Shallow, Bottom: Shallow Top: Deep, Bottom: Deep Lox=5000-(700+700)/2 Loy=5000-(600+600)/2
1.50 1.20 4300 4400
LEX=6450.0 MM, LEX/H=16.1, EXX=20.0 MM LEY=5280.0 MM, LEY/B=8.8, EYY=20.0 MM BI-AXIAL , SLENDER, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Part 1 of 2 with Mxx Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
2966.6 k
.45x(600x400-7144)x25 + 0.95x7144.0x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-7144)x25 + 0.95x7144.0x460
OK
5741.6 k OK 5479.6 k
X-X Moments
Applied Moments (Mx1, Mx2) -70.2 kN.m, 59.9 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (5742 - 2967)/(5742 - 1303) < 1 au = βa • K • h 0.130, 1.000, 400 Madd= N • au 2967 x 52.0 Mi=fn(Mx1, Mx2) -70.2 kN.m, 59.9 kN.m M2+Madd, M nom 224.5 kN.m, 59.3 kN.m M nom=fn(N, exx) 2966.6 kN, 20.0 mm Design Moment
1.00 52.0 mm 154.3 kN.m 28.1 kN.m 154.3 kN.m 224.5 kN.m
Y-Y Moments Applied Moments (My1, My2) -28.2 kN.m, 36.9 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (5742 - 2967)/(5742 - 1372) < 1 au = βa • K • h 0.039, 1.000, 400 Madd= N • au 2967 x 23.2 Mi=fn(My1, My2) -28.2 kN.m, 36.9 kN.m
1.00 23.2 mm 68.9 kN.m 14.8 kN.m
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected], M nom=fn(M2+Madd) M nom=fn(N, eyy) Design Moment
: Job Ref : Sheet Ref / 46: D.O.C.K : OCT 2012 : F.O.O : K.M.M
105.8 2966.6, 20.0
0.0 kN.m 68.9 kN.m 105.8 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(224.5² + 105.8² ) atn(105.8/ 224.5)
248.2 kN.m 25.2 deg
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M12)
0.667, 618 mm, 600 mm, 412.19 mm, 161112 mm², 238.1 m 1 x 32, 532.5, -0.102, -204, -223.6, -164.3 1 x 32, 331.2, 0.069, 138, -22.4, 110.6 1 x 25, 468.6, -0.048, -96, -159.7, -47.0 1 x 25, 401.5, 0.009, 18, -92.6, 8.9 1 x 25, 452.0, -0.034, -68, -143.1, -33.2 1 x 25, 369.9, 0.036, 72, -61.1, 35.2 1 x 32, 286.4, 0.107, 214, 22.4, 171.7 1 x 32, 85.2, 0.278, 437, 223.6, 351.5 1 x 25, 216.2, 0.166, 333, 92.6, 163.4 1 x 25, 149.1, 0.223, 437, 159.7, 214.5 1 x 25, 247.7, 0.140, 279, 61.1, 137.1 1 x 25, 165.7, 0.209, 419, 143.1, 205.5 161112 x 0.45 x 25 -164+111-47+9-33+35+172+351+163+21 +137+205+1813-2966.6
Max Moment/Mu
1812.5 x (618 / 2 - 238.1) 128.1 + (36.7+-2.5+7.5+-0.8+4.7+-2.2+3.8 + (78.6+15.1+34.3+8.4+29.4) 248.2 / 341.3
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
75.7 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
35.7 mm, 360 m
OK
36.7 -2.5 7.5 -0.8 4.7 -2.2 3.8 78.6 15.1 34.3 8.4 29.4 1812.5
kN kN kN kN kN kN kN kN kN kN kN kN k
-0.1
k OK 128.1 kN 341.3kN 0.72
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
NOMINAL LINKS BI-AXIAL , SLENDER, U NBRACED, COLUMN DESIGN Critical Case : 1 : Dead plus Live Part 2 of 2: with Myy Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
2966.6 k
.45x(600x400-7144)x25 + 0.95x7144.0x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-7144)x25 + 0.95x7144.0x460
OK
5741.6 k OK 5479.6 k
X-X Moments
Applied Moments (Mx1, Mx2) -70.2 kN.m, 59.9 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (5742 - 2967)/(5742 - 1303) < 1 au = βa • K • h 0.130, 1.000, 400 Madd= N • au 2967 x 52.0 Mi=fn(Mx1, Mx2) -70.2 kN.m, 59.9 kN.m M2+Madd, M nom 224.5 kN.m, 0.0 kN.m M nom=fn(N, exx) 2966.6 kN, 20.0 mm Design Moment
1.00 52.0 mm 154.3 kN.m 28.1 kN.m 154.3 kN.m 224.5 kN.m
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 47: D.O.C.K : OCT 2012 : F.O.O : K.M.M
Y-Y Moments Applied Moments (My1, My2) -28.2 kN.m, 36.9 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (5742 - 2967)/(5742 - 1372) < 1 au = βa • K • h 0.039, 1.000, 400 Madd= N • au 2967 x 23.2 Mi=fn(My1, My2) -28.2 kN.m, 36.9 kN.m M nom=fn(M2+Madd) 105.8 M nom=fn(N, eyy) 2966.6, 20.0 Design Moment
1.00 23.2 mm 68.9 kN.m 14.8 kN.m 59.3 kN.m 68.9 kN.m 105.8 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(224.5² + 105.8² ) atn(105.8/ 224.5)
248.2 kN.m 25.2 deg
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M12)
0.667, 618 mm, 600 mm, 412.19 mm, 161112 mm², 238.1 m 1 x 32, 532.5, -0.102, -204, -223.6, -164.3 1 x 32, 331.2, 0.069, 138, -22.4, 110.6 1 x 25, 468.6, -0.048, -96, -159.7, -47.0 1 x 25, 401.5, 0.009, 18, -92.6, 8.9 1 x 25, 452.0, -0.034, -68, -143.1, -33.2 1 x 25, 369.9, 0.036, 72, -61.1, 35.2 1 x 32, 286.4, 0.107, 214, 22.4, 171.7 1 x 32, 85.2, 0.278, 437, 223.6, 351.5 1 x 25, 216.2, 0.166, 333, 92.6, 163.4 1 x 25, 149.1, 0.223, 437, 159.7, 214.5 1 x 25, 247.7, 0.140, 279, 61.1, 137.1 1 x 25, 165.7, 0.209, 419, 143.1, 205.5 161112 x 0.45 x 25 -164+111-47+9-33+35+172+351+163+21 +137+205+1813-2966.6
Max Moment/Mu
1812.5 x (618 / 2 - 238.1) 128.1 + (36.7+-2.5+7.5+-0.8+4.7+-2.2+3.8 + (78.6+15.1+34.3+8.4+29.4) 248.2 / 341.3
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
75.7 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
35.7 mm, 360 m
OK
36.7 -2.5 7.5 -0.8 4.7 -2.2 3.8 78.6 15.1 34.3 8.4 29.4 1812.5
kN kN kN kN kN kN kN kN kN kN kN kN k
-0.1
k OK 128.1 kN 341.3kN 0.72
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
Nominal links
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 48: D.O.C.K : OCT 2012 : F.O.O : K.M.M
COLUMN @ COLUMN TYPE C3 LEVEL 1
Basic Data Design to
BS 8110: 199
Grades Fy, Fyv, Fcu
460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 400 mm deep column βy : for 600 mm wide column Lc=5000
Top: Shallow, Bottom: Shallow Top: Deep, Bottom: Shallow Lox=5000-(700+0)/2 Loy=5000-(600+0)/2
1.50 1.30 4650 4700
LEX=6975.0 MM, LEX/H=17.4, EXX=20.0 MM LEY=6110.0 MM, LEY/B=10.2, EYY=20.0 MM BI-AXIAL , SLENDER, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Part 1 of 2 with Mxx Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
3523.6 k
.45x(600x400-9651)x25 + 0.95x9651.0x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-9651)x25 + 0.95x9651.0x460
OK
6808.9 k OK 6549.8 k
X-X Moments
Applied Moments (Mx1, Mx2) -37.2 kN.m, 62.6 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (6809 - 3524)/(6809 - 1321) < 1 au = βa • K • h 0.152, 1.000, 400 Madd= N • au 3524 x 60.8 Mi=fn(Mx1, Mx2) -37.2 kN.m, 62.6 kN.m M2+Madd, M nom 276.9 kN.m, 70.5 kN.m M nom=fn(N, exx) 3523.6 kN, 20.0 mm Design Moment
1.00 60.8 mm 214.3 kN.m 25.0 kN.m 214.3 kN.m 276.9 kN.m
Y-Y Moments Applied Moments (My1, My2) -8.8 kN.m, 15.1 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (6809 - 3524)/(6809 - 1258) < 1
1.00
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected], au = βa • K • h Madd= N • au Mi=fn(My1, My2) M nom=fn(M2+Madd) M nom=fn(N, eyy) Design Moment
: Job Ref : Sheet Ref / 49: D.O.C.K : OCT 2012 : F.O.O : K.M.M
0.052, 1.000, 400 3524 x 31.1 -8.8 kN.m, 15.1 kN.m 124.7 3523.6, 20.0
31.1 mm 109.6 kN.m 6.0 kN.m 0.0 kN.m 109.6 kN.m 124.7 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(276.9² + 124.7² ) atn(124.7/ 276.9)
303.7 kN.m 24.2 deg
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M12)
0.679, 611 mm, 600 mm, 414.78 mm, 164477 mm², 238.1 m 1 x 32, 526.5, -0.094, -189, -220.9, -151.6 1 x 32, 332.6, 0.069, 139, -27.1, 111.5 1 x 32, 461.9, -0.040, -79, -156.3, -63.9 1 x 32, 397.3, 0.015, 30, -91.7, 23.8 1 x 32, 443.8, -0.025, -49, -138.3, -39.4 1 x 32, 361.2, 0.045, 90, -55.6, 72.8 1 x 32, 278.5, 0.115, 230, 27.1, 185.0 1 x 32, 84.6, 0.279, 437, 220.9, 351.5 1 x 32, 213.9, 0.170, 339, 91.7, 272.7 1 x 32, 149.3, 0.224, 437, 156.3, 351.5 1 x 32, 250.0, 0.139, 278, 55.6, 223.7 1 x 32, 167.3, 0.209, 418, 138.3, 335.9 164477 x 0.45 x 25 -152+111-64+24-39+73+185+351+273+35 +224+336+1850-3523.6
Max Moment/Mu
1850.4 x (611 / 2 - 238.1) 124.9 + (33.5+-3.0+10.0+-2.2+5.5+-4.0+5.0 + (77.6+25.0+54.9+12.4+46.4) 303.7 / 386.1
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
78.6 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
35.4 mm, 360 m
OK
33.5 -3.0 10.0 -2.2 5.5 -4.0 5.0 77.6 25.0 54.9 12.4 46.4 1850.4
kN kN kN kN kN kN kN kN kN kN kN kN k
0.0
k OK 124.9 kN 386.1kN 0.78
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
NOMINAL LINKS BI-AXIAL , SLENDER, U NBRACED, COLUMN DESIGN Critical Case : 1 : Dead plus Live Part 2 of 2: with Myy Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
3523.6 k
.45x(600x400-9651)x25 + 0.95x9651.0x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-9651)x25 + 0.95x9651.0x460
OK
6808.9 k OK 6549.8 k
X-X Moments
Applied Moments (Mx1, Mx2) -37.2 kN.m, 62.6 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (6809 - 3524)/(6809 - 1321) < 1 au = βa • K • h 0.152, 1.000, 400 Madd= N • au 3524 x 60.8 Mi=fn(Mx1, Mx2) -37.2 kN.m, 62.6 kN.m M2+Madd, M nom 276.9 kN.m, 0.0 kN.m M nom=fn(N, exx) 3523.6 kN, 20.0 mm
1.00 60.8 mm 214.3 kN.m 25.0 kN.m 214.3 kN.m
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 50: D.O.C.K : OCT 2012 : F.O.O : K.M.M
Design Moment
276.9 kN.m
Y-Y Moments Applied Moments (My1, My2) -8.8 kN.m, 15.1 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (6809 - 3524)/(6809 - 1258) < 1 au = βa • K • h 0.052, 1.000, 400 Madd= N • au 3524 x 31.1 Mi=fn(My1, My2) -8.8 kN.m, 15.1 kN.m M nom=fn(M2+Madd) 124.7 M nom=fn(N, eyy) 3523.6, 20.0 Design Moment
1.00 31.1 mm 109.6 kN.m 6.0 kN.m 70.5 kN.m 109.6 kN.m 124.7 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(276.9² + 124.7² ) atn(124.7/ 276.9)
303.7 kN.m 24.2 deg
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M12)
Max Moment/Mu
0.679, 611 mm, 600 mm, 414.78 mm, 164477 mm², 238.1 m 1 x 32, 526.5, -0.094, -189, -220.9, -151.6 1 x 32, 332.6, 0.069, 139, -27.1, 111.5 1 x 32, 461.9, -0.040, -79, -156.3, -63.9 1 x 32, 397.3, 0.015, 30, -91.7, 23.8 1 x 32, 443.8, -0.025, -49, -138.3, -39.4 1 x 32, 361.2, 0.045, 90, -55.6, 72.8 1 x 32, 278.5, 0.115, 230, 27.1, 185.0 1 x 32, 84.6, 0.279, 437, 220.9, 351.5 1 x 32, 213.9, 0.170, 339, 91.7, 272.7 1 x 32, 149.3, 0.224, 437, 156.3, 351.5 1 x 32, 250.0, 0.139, 278, 55.6, 223.7 1 x 32, 167.3, 0.209, 418, 138.3, 335.9 164477 x 0.45 x 25 -152+111-64+24-39+73+185+351+273+35 +224+336+1850-3523.6 1850.4 x (611 / 2 - 238.1) 124.9 + (33.5+-3.0+10.0+-2.2+5.5+-4.0+5.0 + (77.6+25.0+54.9+12.4+46.4)
33.5 -3.0 10.0 -2.2 5.5 -4.0 5.0 77.6 25.0 54.9 12.4 46.4 1850.4 0.0
k OK 124.9 kN 386.1kN
303.7 / 386.1
0.78
OK App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
78.6 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
35.4 mm, 360 m
kN kN kN kN kN kN kN kN kN kN kN kN k
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
Nominal links
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 51: D.O.C.K : OCT 2012 : F.O.O : K.M.M
COLUMN @ COLUMN TYPE C4 LEVEL 6
Basic Data Design to
BS 8110: 199
Grades Fy, Fyv, Fcu
460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 400 mm deep column βy : for 600 mm wide column Lc=3300
Top: Shallow, Bottom: Shallow Top: Deep, Bottom: Deep Lox=3300-(700+700)/2 Loy=3300-(600+600)/2
1.50 1.20 2600 2700
LEX=3900.0 MM, LEX/H=9.8, EXX=20.0 MM LEY=3240.0 MM, LEY/B=5.4, EYY=20.0 MM BI-AXIAL , SHORT, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Part 1 of 2 with Mxx Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
777.9 k
.45x(600x400-4398)x25 + 0.95x4398.2x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-4398)x25 + 0.95x4398.2x460
OK Applied Moments (Mx1, Mx2) M nom=fn(N, exx) Design Moment
-69.7 kN.m, 101.1 kN.m 777.9 kN, 20.0 mm
4572.5 k OK 4307.5 k
X-X Moments 15.6 kN.m 101.1 kN.m
Y-Y Moments Applied Moments (My1, My2) Design Moment
1.8 kN.m, -7.6 kN.m 7.6 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(101.1² + 7.6² ) atn(7.6/ 101.1)
101.4 kN.m 4.3 deg
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 52: D.O.C.K : OCT 2012 : F.O.O : K.M.M
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Bar group13:M13 fn(bars,d,ε%,,la,F) Bar group14:M14 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M14)
Max Moment/Mu
0.425, 444 mm, 600 mm, 188.73 mm, 88672 mm², 95.6 m 1 x 20, 381.7, -0.358, -437, -159.7, -137.3 1 x 20, 345.4, -0.291, -437, -123.5, -137.3 1 x 20, 372.6, -0.341, -437, -150.7, -137.3 1 x 20, 363.5, -0.324, -437, -141.6, -137.3 1 x 20, 354.5, -0.307, -437, -132.5, -137.3 1 x 20, 287.3, -0.183, -365, -65.3, -114.8 1 x 20, 192.9, -0.008, -15, 29.1, -4.8 1 x 20, 98.5, 0.167, 335, 123.5, 105.2 1 x 20, 62.2, 0.235, 437, 159.7, 137.3 1 x 20, 89.4, 0.184, 368, 132.5, 115.7 1 x 20, 80.3, 0.201, 402, 141.6, 126.3 1 x 20, 71.3, 0.218, 436, 150.7, 136.9 1 x 20, 251.0, -0.115, -231, -29.1, -72.5 1 x 20, 156.6, 0.060, 119, 65.3, 37.5 88672 x 0.45 x 25 -137-137-137-137-137-115-5+105+137+11 +126+137-73+37+998-777.9
21.9 16.9 20.7 19.4 18.2 7.5 -0.1 13.0 21.9 15.3 17.9 20.6 2.1 2.4 997.6 -0.1
k OK 126.0 kN
997.6 x (444 / 2 - 95.6) 126.0 + (21.9+16.9+20.7+19.4+18.2+7.5+-0.1 + (13.0+21.9+15.3+17.9+20.6+2.1+2.4)
323.9kN
101.4 / 323.9
0.31
OK App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
130 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
9.8 mm, 360 m
kN kN kN kN kN kN kN kN kN kN kN kN kN kN k
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
NOMINAL LINKS BI-AXIAL , SHORT, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Part 2 of 2: with Myy Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
777.9 k
.45x(600x400-4398)x25 + 0.95x4398.2x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-4398)x25 + 0.95x4398.2x460
OK Applied Moments (Mx1, Mx2) Design Moment
4572.5 k OK 4307.5 k
X-X Moments
-69.7 kN.m, 101.1 kN.m 101.1 kN.m
Y-Y Moments Applied Moments (My1, My2) M nom=fn(N, eyy) Design Moment
1.8 kN.m, -7.6 kN.m 777.9, 20.0
15.6 kN.m 15.6 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(101.1² + 15.6² ) atn(15.6/ 101.1)
102.3 kN.m 8.7 deg
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F)
0.443, 487 mm, 600 mm, 215.67 mm, 90135 mm², 117.5 m 1 x 20, 420.5, -0.332, -437, -177.2, -137.3
24.3 kN
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected], Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Bar group13:M13 fn(bars,d,ε%,,la,F) Bar group14:M14 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M14)
1 x 20, 346.8, -0.213, -426, -103.5, -133.7 1 x 20, 402.1, -0.302, -437, -158.8, -137.3 1 x 20, 383.7, -0.273, -437, -140.3, -137.3 1 x 20, 365.2, -0.243, -437, -121.9, -137.3 1 x 20, 326.9, -0.180, -361, -83.6, -113.4 1 x 20, 233.3, -0.029, -57, 10.0, -18.0 1 x 20, 139.8, 0.123, 246, 103.5, 77.4 1 x 20, 66.1, 0.243, 437, 177.2, 137.3 1 x 20, 121.4, 0.153, 306, 121.9, 96.2 1 x 20, 103.0, 0.183, 366, 140.3, 114.9 1 x 20, 84.6, 0.213, 426, 158.8, 133.7 1 x 20, 253.3, -0.061, -122, -10.0, -38.3 1 x 20, 159.7, 0.091, 182, 83.6, 57.1 90135 x 0.45 x 25 -137-134-137-137-137-113-18+77+137+9 +115+134-38+57+1014-777.9
Max Moment/Mu
1014.0 x (487 / 2 - 117.5) 127.5 + (24.3+13.8+21.8+19.3+16.7+9.5+-0.2 + (8.0+24.3+11.7+16.1+21.2+0.4+4.8) 102.3 / 319.4
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
130 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
20 mm, 360 m
OK
: Job Ref : Sheet Ref / 53: D.O.C.K : OCT 2012 : F.O.O : K.M.M
13.8 21.8 19.3 16.7 9.5 -0.2 8.0 24.3 11.7 16.1 21.2 0.4 4.8 1014.0
kN kN kN kN kN kN kN kN kN kN kN kN kN k
0.0
k OK 127.5 kN 319.4kN 0.32
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 54: D.O.C.K : OCT 2012 : F.O.O : K.M.M
COLUMN @ COLUMN TYPE C4 LEVEL 5
Basic Data Design to
BS 8110: 199
Grades Fy, Fyv, Fcu
460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 400 mm deep column βy : for 600 mm wide column Lc=3300
Top: Shallow, Bottom: Shallow Top: Deep, Bottom: Deep Lox=3300-(700+700)/2 Loy=3300-(600+600)/2
1.50 1.20 2600 2700
LEX=3900.0 MM, LEX/H=9.8, EXX=20.0 MM LEY=3240.0 MM, LEY/B=5.4, EYY=20.0 MM BI-AXIAL , SHORT, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Part 1 of 2 with Mxx Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
1580.7 k
.45x(600x400-3770)x25 + 0.95x3769.9x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-3770)x25 + 0.95x3769.9x460
OK Applied Moments (Mx1, Mx2) M nom=fn(N, exx) Design Moment
-14.5 kN.m, 7.7 kN.m 1580.7 kN, 20.0 mm
4305.0 k OK 4039.3 k
X-X Moments 31.6 kN.m 31.6 kN.m
Y-Y Moments Applied Moments (My1, My2) Design Moment
2.3 kN.m, 0.0 kN.m 2.3 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(31.6² + 2.3² ) atn(2.3/ 31.6)
31.7 kN.m 4.2 deg
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 55: D.O.C.K : OCT 2012 : F.O.O : K.M.M
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M12)
0.558, 442 mm, 600 mm, 246.94 mm, 120607 mm², 121.6 m 1 x 20, 380.4, -0.189, -378, -159.2, -118.9 1 x 20, 345.3, -0.139, -279, -124.1, -87.6 1 x 20, 368.7, -0.173, -345, -147.5, -108.4 1 x 20, 357.0, -0.156, -312, -135.8, -98.0 1 x 20, 286.0, -0.055, -111, -64.8, -34.8 1 x 20, 191.6, 0.078, 157, 29.6, 49.3 1 x 20, 97.2, 0.212, 425, 124.1, 133.4 1 x 20, 62.1, 0.262, 437, 159.2, 137.3 1 x 20, 85.5, 0.229, 437, 135.8, 137.3 1 x 20, 73.8, 0.245, 437, 147.5, 137.3 1 x 20, 250.9, -0.006, -11, -29.6, -3.5 1 x 20, 156.5, 0.128, 256, 64.8, 80.6 120607 x 0.45 x 25 -119-88-108-98-35+49+133+137+137+13 -4+81+1357-1580.7
Max Moment/Mu
1356.8 x (442 / 2 - 121.6) 135.2 + (18.9+10.9+16.0+13.3+2.3+1.5+16.5 + (21.9+18.6+20.2+0.1+5.2) 31.7 / 280.6
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
20 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
1.5 mm, 360 m
OK
18.9 10.9 16.0 13.3 2.3 1.5 16.5 21.9 18.6 20.2 0.1 5.2 1356.8
kN kN kN kN kN kN kN kN kN kN kN kN k
0.0
k OK 135.2 kN 280.6kN 0.11
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
NOMINAL LINKS BI-AXIAL , SHORT, UNBRACED, COLUMN DESIGN Critical Case : 1 : Dead plus Live Part 2 of 2: with Myy Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
1580.7 k
.45x(600x400-3770)x25 + 0.95x3769.9x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-3770)x25 + 0.95x3769.9x460
OK Applied Moments (Mx1, Mx2) Design Moment
4305.0 k OK 4039.3 k
X-X Moments
-14.5 kN.m, 7.7 kN.m 14.5 kN.m
Y-Y Moments Applied Moments (My1, My2) M nom=fn(N, eyy) Design Moment
2.3 kN.m, 0.0 kN.m 1580.7, 20.0
31.6 kN.m 31.6 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(14.5² + 31.6² ) atn(31.6/ 14.5)
34.8 kN.m 65.4 deg
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
Job ref Sheet Made By Date Checked Approved
: Job Ref : Sheet Ref / 56: D.O.C.K : OCT 2012 : F.O.O : K.M.M
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Max Moment/Mu
0.559, 712 mm, 600 mm, 398.05 mm, 120960 mm², 216.6 m 1 x 20, 635.2, -0.209, -417, -279.2, -131.0 1 x 20, 195.3, 0.178, 357, 160.8, 112.0 1 x 20, 488.6, -0.080, -159, -132.5, -50.0 1 x 20, 341.9, 0.049, 99, 14.1, 31.0 1 x 20, 595.8, -0.174, -348, -239.7, -109.2 1 x 20, 556.3, -0.139, -278, -200.2, -87.4 1 x 20, 516.8, -0.104, -209, -160.8, -65.6 1 x 20, 76.9, 0.282, 437, 279.2, 137.3 1 x 20, 370.2, 0.025, 49, -14.1, 15.4 1 x 20, 223.5, 0.153, 307, 132.5, 96.4 1 x 20, 155.8, 0.213, 426, 200.2, 133.8 1 x 20, 116.4, 0.248, 437, 239.7, 137.3 120960 x 0.45 x 25 -131+112-50+31-109-87-66+137+15+96+13 +137+1361-1580.7 1360.8 x (712 / 2 - 216.6) 189.8 + (36.6+18.0+6.6+0.4+26.2+17.5+10.5 + (38.3+-0.2+12.8+26.8+32.9) 34.8 / 416.3
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
9.2 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
20 mm, 360 m
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M12)
OK
36.6 18.0 6.6 0.4 26.2 17.5 10.5 38.3 -0.2 12.8 26.8 32.9 1360.8
kN kN kN kN kN kN kN kN kN kN kN kN k
0.0 k 189.8 kN 416.3kN 0.08
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
Nominal links
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 57: D.O.C.K : OCT 2012 : F.O.O : K.M.M
COLUMN @ COLUMN TYPE C4 LEVEL 4
Basic Data Design to
BS 8110: 199
Grades Fy, Fyv, Fcu
460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 400 mm deep column βy : for 600 mm wide column Lc=3300
Top: Shallow, Bottom: Shallow Top: Deep, Bottom: Deep Lox=3300-(700+700)/2 Loy=3300-(600+600)/2
1.50 1.20 2600 2700
LEX=3900.0 MM, LEX/H=9.8, EXX=20.0 MM LEY=3240.0 MM, LEY/B=5.4, EYY=20.0 MM BI-AXIAL , SHORT, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Part 1 of 2 with Mxx Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
2298.0 k
.45x(600x400-5890)x25 + 0.95x5890.5x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-5890)x25 + 0.95x5890.5x460
OK Applied Moments (Mx1, Mx2) M nom=fn(N, exx) Design Moment
-22.3 kN.m, 21.9 kN.m 2298.0 kN, 20.0 mm
5207.9 k OK 4944.5 k
X-X Moments 46.0 kN.m 46.0 kN.m
Y-Y Moments Applied Moments (My1, My2) Design Moment
3.9 kN.m, -3.1 kN.m 3.9 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(46.0² + 3.9² ) atn(3.9/ 46.0)
46.1 kN.m 4.9 deg
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 58: D.O.C.K : OCT 2012 : F.O.O : K.M.M
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M12)
0.629, 449 mm, 600 mm, 282.67 mm, 137916 mm², 139.4 m 1 x 25, 383.9, -0.125, -251, -159.3, -123.1 1 x 25, 343.4, -0.075, -150, -118.8, -73.8 1 x 25, 370.4, -0.109, -217, -145.8, -106.6 1 x 25, 356.9, -0.092, -184, -132.3, -90.2 1 x 25, 291.2, -0.011, -21, -66.6, -10.4 1 x 25, 198.6, 0.104, 208, 26.1, 102.2 1 x 25, 105.9, 0.219, 437, 118.8, 214.5 1 x 25, 65.4, 0.269, 437, 159.3, 214.5 1 x 25, 92.4, 0.236, 437, 132.3, 214.5 1 x 25, 78.9, 0.252, 437, 145.8, 214.5 1 x 25, 250.7, 0.040, 79, -26.1, 38.8 1 x 25, 158.1, 0.154, 309, 66.6, 151.5 137916 x 0.45 x 25 -123-74-107-90-10+102+215+215+215+21 +39+151+1552-2298
Max Moment/Mu
1551.6 x (449 / 2 - 139.4) 132.2 + (19.6+8.8+15.5+11.9+0.7+2.7+25.5 + (34.2+28.4+31.3+-1.0+10.1) 46.1 / 319.8
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
20 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
1.7 mm, 360 m
OK
19.6 8.8 15.5 11.9 0.7 2.7 25.5 34.2 28.4 31.3 -1.0 10.1 1551.6
kN kN kN kN kN kN kN kN kN kN kN kN k
0.0
k OK 132.2 kN 319.8kN 0.14
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
NOMINAL LINKS BI-AXIAL , SHORT, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Part 2 of 2: with Myy Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
2298.0 k
.45x(600x400-5890)x25 + 0.95x5890.5x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-5890)x25 + 0.95x5890.5x460
OK Applied Moments (Mx1, Mx2) Design Moment
5207.9 k OK 4944.5 k
X-X Moments
-22.3 kN.m, 21.9 kN.m 22.3 kN.m
Y-Y Moments Applied Moments (My1, My2) M nom=fn(N, eyy) Design Moment
3.9 kN.m, -3.1 kN.m 2298.0, 20.0
46.0 kN.m 46.0 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(22.3² + 46.0² ) atn(46.0/ 22.3)
51.1 kN.m 64.1 deg
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
Job ref Sheet Made By Date Checked Approved
: Job Ref : Sheet Ref / 59: D.O.C.K : OCT 2012 : F.O.O : K.M.M
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M12)
0.626, 714 mm, 600 mm, 447.14 mm, 140101 mm², 240.8 m 1 x 25, 633.6, -0.146, -292, -276.4, -143.3 1 x 25, 202.6, 0.191, 383, 154.6, 187.9 1 x 25, 489.9, -0.033, -67, -132.7, -32.9 1 x 25, 346.3, 0.079, 158, 10.9, 77.5 1 x 25, 593.0, -0.114, -228, -235.8, -112.1 1 x 25, 552.4, -0.082, -165, -195.2, -80.9 1 x 25, 511.8, -0.051, -101, -154.6, -49.7 1 x 25, 80.8, 0.287, 437, 276.4, 214.5 1 x 25, 368.1, 0.062, 124, -10.9, 60.7 1 x 25, 224.5, 0.174, 349, 132.7, 171.1 1 x 25, 162.0, 0.223, 437, 195.2, 214.5 1 x 25, 121.4, 0.255, 437, 235.8, 214.5 140101 x 0.45 x 25 -143+188-33+78-112-81-50+215+61+17 +215+215+1576-2298
Max Moment/Mu
1576.1 x (714 / 2 - 240.8) 183.4 + (39.6+29.0+4.4+0.8+26.4+15.8+7.7 + (59.3+-0.7+22.7+41.9+50.6) 51.1 / 481.0
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
9.7 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
20 mm, 360 m
OK
39.6 29.0 4.4 0.8 26.4 15.8 7.7 59.3 -0.7 22.7 41.9 50.6 1576.1
kN kN kN kN kN kN kN kN kN kN kN kN k
0.1
k OK 183.4 kN 481.0kN 0.10
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
Nominal links
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 60: D.O.C.K : OCT 2012 : F.O.O : K.M.M
COLUMN @ COLUMN TYPE C4 LEVEL 3
Basic Data Design to
BS 8110: 199
Grades Fy, Fyv, Fcu
460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 400 mm deep column βy : for 600 mm wide column Lc=3300
Top: Shallow, Bottom: Shallow Top: Deep, Bottom: Deep Lox=3300-(700+700)/2 Loy=3300-(600+600)/2
1.50 1.20 2600 2700
LEX=3900.0 MM, LEX/H=9.8, EXX=20.0 MM LEY=3240.0 MM, LEY/B=5.4, EYY=20.0 MM BI-AXIAL , SHORT, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Part 1 of 2 with Mxx Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
3709.9 k
.45x(600x400-5890)x25 + 0.95x5890.5x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-5890)x25 + 0.95x5890.5x460
OK Applied Moments (Mx1, Mx2) M nom=fn(N, exx) Design Moment
-43.4 kN.m, 13.8 kN.m 3709.9 kN, 20.0 mm
5207.9 k OK 4944.5 k
X-X Moments 74.2 kN.m 74.2 kN.m
Y-Y Moments Applied Moments (My1, My2) Design Moment
4.0 kN.m, 0.0 kN.m 4.0 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(74.2² + 4.0² ) atn(4.0/ 74.2)
74.3 kN.m 3.1 deg
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 61: D.O.C.K : OCT 2012 : F.O.O : K.M.M
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M12)
0.873, 432 mm, 600 mm, 377.03 mm, 194188 mm², 177.6 m 1 x 25, 368.0, 0.008, 17, -152.2, 8.2 1 x 25, 342.3, 0.032, 65, -126.4, 31.7 1 x 25, 359.5, 0.016, 33, -143.6, 16.0 1 x 25, 350.9, 0.024, 49, -135.0, 23.9 1 x 25, 275.2, 0.095, 189, -59.3, 92.8 1 x 25, 182.3, 0.181, 362, 33.5, 177.5 1 x 25, 89.5, 0.267, 437, 126.4, 214.5 1 x 25, 63.7, 0.291, 437, 152.2, 214.5 1 x 25, 80.9, 0.275, 437, 135.0, 214.5 1 x 25, 72.3, 0.283, 437, 143.6, 214.5 1 x 25, 249.4, 0.118, 237, -33.5, 116.3 1 x 25, 156.5, 0.205, 409, 59.3, 201.0 194188 x 0.45 x 25 8+32+16+24+93+177+215+215+215+215+11 +201+2185-3709.9
Max Moment/Mu
2184.6 x (432 / 2 - 177.6) 83.6 + (-1.2+-4.0+-2.3+-3.2+-5.5+6.0+27.1 + (32.6+29.0+30.8+-3.9+11.9) 74.3 / 200.8
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
20 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
1.1 mm, 360 m
OK
-1.2 -4.0 -2.3 -3.2 -5.5 6.0 27.1 32.6 29.0 30.8 -3.9 11.9 2184.6
kN kN kN kN kN kN kN kN kN kN kN kN k
0.0
k OK 83.6 kN 200.8kN 0.37
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
NOMINAL LINKS BI-AXIAL , SHORT, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Part 2 of 2: with Myy Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
3709.9 k
.45x(600x400-5890)x25 + 0.95x5890.5x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-5890)x25 + 0.95x5890.5x460
OK Applied Moments (Mx1, Mx2) Design Moment
5207.9 k OK 4944.5 k
X-X Moments
-43.4 kN.m, 13.8 kN.m 43.4 kN.m
Y-Y Moments Applied Moments (My1, My2) M nom=fn(N, eyy) Design Moment
4.0 kN.m, 0.0 kN.m 3709.9, 20.0
74.2 kN.m 74.2 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(43.4² + 74.2² ) atn(74.2/ 43.4)
86.0 kN.m 59.7 deg
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
Job ref Sheet Made By Date Checked Approved
: Job Ref : Sheet Ref / 62: D.O.C.K : OCT 2012 : F.O.O : K.M.M
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M12)
0.824, 720 mm, 600 mm, 592.96 mm, 200224 mm², 313.1 m 1 x 25, 637.1, -0.026, -52, -277.2, -25.6 1 x 25, 223.6, 0.218, 436, 136.3, 214.0 1 x 25, 499.3, 0.055, 111, -139.3, 54.3 1 x 25, 361.5, 0.137, 273, -1.5, 134.2 1 x 25, 590.1, 0.002, 3, -230.2, 1.6 1 x 25, 543.2, 0.029, 59, -183.3, 28.8 1 x 25, 496.2, 0.057, 114, -136.3, 56.1 1 x 25, 82.8, 0.301, 437, 277.2, 214.5 1 x 25, 358.4, 0.138, 277, 1.5, 135.9 1 x 25, 220.6, 0.220, 437, 139.3, 214.5 1 x 25, 176.7, 0.246, 437, 183.3, 214.5 1 x 25, 129.7, 0.273, 437, 230.2, 214.5 200224 x 0.45 x 25 -26+214+54+134+2+29+56+215+136+215+21 +215+2253-3709.9
Max Moment/Mu
2252.5 x (720 / 2 - 313.1) 105.5 + (7.1+29.2+-7.6+-0.2+-0.4+-5.3+-7.6 + (59.5+0.2+29.9+39.3+49.4) 86.0 / 298.9
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
11.7 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
20 mm, 360 m
OK
7.1 29.2 -7.6 -0.2 -0.4 -5.3 -7.6 59.5 0.2 29.9 39.3 49.4 2252.5
kN kN kN kN kN kN kN kN kN kN kN kN k
0.0
k OK 105.5 kN 298.9kN 0.28
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
Nominal links
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 63: D.O.C.K : OCT 2012 : F.O.O : K.M.M
COLUMN @ COLUMN TYPE C4 LEVEL 2
Basic Data Design to
BS 8110: 199
Grades Fy, Fyv, Fcu
460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 400 mm deep column βy : for 600 mm wide column Lc=5000
Top: Shallow, Bottom: Shallow Top: Deep, Bottom: Deep Lox=5000-(700+700)/2 Loy=5000-(600+600)/2
1.50 1.20 4300 4400
LEX=6450.0 MM, LEX/H=16.1, EXX=20.0 MM LEY=5280.0 MM, LEY/B=8.8, EYY=20.0 MM BI-AXIAL , SLENDER, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Part 1 of 2 with Mxx Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
3709.9 k
.45x(600x400-6872)x25 + 0.95x6872.2x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-6872)x25 + 0.95x6872.2x460
OK
5625.9 k OK 5363.6 k
X-X Moments
Applied Moments (Mx1, Mx2) -43.4 kN.m, 13.8 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (5626 - 3710)/(5626 - 1326) < 1 au = βa • K • h 0.130, 1.000, 400 Madd= N • au 3710 x 52.0 Mi=fn(Mx1, Mx2) -43.4 kN.m, 13.8 kN.m M2+Madd, M nom 236.3 kN.m, 74.2 kN.m M nom=fn(N, exx) 3709.9 kN, 20.0 mm Design Moment
1.00 52.0 mm 192.9 kN.m 20.5 kN.m 192.9 kN.m 236.3 kN.m
Y-Y Moments Applied Moments (My1, My2) 4.0 kN.m, 0.0 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (5626 - 3710)/(5626 - 864) < 1 au = βa • K • h 0.039, 1.000, 400 Madd= N • au 3710 x 23.2 Mi=fn(My1, My2) 4.0 kN.m, 0.0 kN.m M nom=fn(M2+Madd) 90.2
1.00 23.2 mm 86.2 kN.m 2.4 kN.m 0.0 kN.m
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected], M nom=fn(N, eyy) Design Moment
: Job Ref : Sheet Ref / 64: D.O.C.K : OCT 2012 : F.O.O : K.M.M
3709.9, 20.0
86.2 kN.m 90.2 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(236.3² + 90.2² ) atn(90.2/ 236.3)
253.0 kN.m 20.9 deg
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Bar group13:M13 fn(bars,d,ε%,,la,F) Bar group14:M14 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M14)
Max Moment/Mu
0.768, 588 mm, 600 mm, 451.49 mm, 190664 mm², 249.1 m 1 x 25, 509.5, -0.045, -90, -215.7, -44.2 1 x 25, 338.8, 0.087, 175, -44.9, 85.8 1 x 25, 466.8, -0.012, -24, -173.0, -11.7 1 x 25, 424.2, 0.021, 42, -130.3, 20.8 1 x 25, 381.5, 0.054, 109, -87.6, 53.3 1 x 25, 422.7, 0.022, 45, -128.8, 21.9 1 x 25, 335.8, 0.090, 179, -41.9, 88.1 1 x 25, 248.9, 0.157, 314, 44.9, 154.2 1 x 25, 78.1, 0.289, 437, 215.7, 214.5 1 x 25, 206.2, 0.190, 380, 87.6, 186.7 1 x 25, 163.5, 0.223, 437, 130.3, 214.5 1 x 25, 120.8, 0.256, 437, 173.0, 214.5 1 x 25, 251.9, 0.155, 309, 41.9, 151.9 1 x 25, 165.0, 0.222, 437, 128.8, 214.5 190664 x 0.45 x 25 -44+86-12+21+53+22+88+154+215+187+21 +215+152+215+2145-3709.9 2145.0 x (588 / 2 - 249.1) 96.0 + (9.5+-3.9+2.0+-2.7+-4.7+-2.8+-3.7 + (6.9+46.3+16.4+28.0+37.1+6.4+27.6)
9.5 -3.9 2.0 -2.7 -4.7 -2.8 -3.7 6.9 46.3 16.4 28.0 37.1 6.4 27.6 2145.0 0.0
k OK 96.0 kN 258.4kN
253.0 / 258.4
0.97
OK App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
63.7 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
24.3 mm, 360 m
kN kN kN kN kN kN kN kN kN kN kN kN kN kN k
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
NOMINAL LINKS BI-AXIAL , SLENDER, U NBRACED, COLUMN DESIGN Critical Case : 1 : Dead plus Live Part 2 of 2: with Myy Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
3709.9 k
.45x(600x400-6872)x25 + 0.95x6872.2x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-6872)x25 + 0.95x6872.2x460
OK
5625.9 k OK 5363.6 k
X-X Moments
Applied Moments (Mx1, Mx2) -43.4 kN.m, 13.8 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (5626 - 3710)/(5626 - 1326) < 1 au = βa • K • h 0.130, 1.000, 400 Madd= N • au 3710 x 52.0 Mi=fn(Mx1, Mx2) -43.4 kN.m, 13.8 kN.m M2+Madd, M nom 236.3 kN.m, 0.0 kN.m M nom=fn(N, exx) 3709.9 kN, 20.0 mm
1.00 52.0 mm 192.9 kN.m 20.5 kN.m 192.9 kN.m
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 65: D.O.C.K : OCT 2012 : F.O.O : K.M.M
Design Moment
236.3 kN.m
Y-Y Moments Applied Moments (My1, My2) 4.0 kN.m, 0.0 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (5626 - 3710)/(5626 - 864) < 1 au = βa • K • h 0.039, 1.000, 400 Madd= N • au 3710 x 23.2 Mi=fn(My1, My2) 4.0 kN.m, 0.0 kN.m M nom=fn(M2+Madd) 90.2 M nom=fn(N, eyy) 3709.9, 20.0 Design Moment
1.00 23.2 mm 86.2 kN.m 2.4 kN.m 74.2 kN.m 86.2 kN.m 90.2 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(236.3² + 90.2² ) atn(90.2/ 236.3)
253.0 kN.m 20.9 deg
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Bar group13:M13 fn(bars,d,ε%,,la,F) Bar group14:M14 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M14)
0.768, 588 mm, 600 mm, 451.49 mm, 190664 mm², 249.1 m 1 x 25, 509.5, -0.045, -90, -215.7, -44.2 1 x 25, 338.8, 0.087, 175, -44.9, 85.8 1 x 25, 466.8, -0.012, -24, -173.0, -11.7 1 x 25, 424.2, 0.021, 42, -130.3, 20.8 1 x 25, 381.5, 0.054, 109, -87.6, 53.3 1 x 25, 422.7, 0.022, 45, -128.8, 21.9 1 x 25, 335.8, 0.090, 179, -41.9, 88.1 1 x 25, 248.9, 0.157, 314, 44.9, 154.2 1 x 25, 78.1, 0.289, 437, 215.7, 214.5 1 x 25, 206.2, 0.190, 380, 87.6, 186.7 1 x 25, 163.5, 0.223, 437, 130.3, 214.5 1 x 25, 120.8, 0.256, 437, 173.0, 214.5 1 x 25, 251.9, 0.155, 309, 41.9, 151.9 1 x 25, 165.0, 0.222, 437, 128.8, 214.5 190664 x 0.45 x 25 -44+86-12+21+53+22+88+154+215+187+21 +215+152+215+2145-3709.9
Max Moment/Mu
2145.0 x (588 / 2 - 249.1) 96.0 + (9.5+-3.9+2.0+-2.7+-4.7+-2.8+-3.7 + (6.9+46.3+16.4+28.0+37.1+6.4+27.6) 253.0 / 258.4
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
63.7 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
24.3 mm, 360 m
OK
9.5 -3.9 2.0 -2.7 -4.7 -2.8 -3.7 6.9 46.3 16.4 28.0 37.1 6.4 27.6 2145.0
kN kN kN kN kN kN kN kN kN kN kN kN kN kN k
0.0
k OK 96.0 kN 258.4kN 0.97
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
Nominal links
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
Job ref Sheet Made By Date Checked Approved
: Job Ref : Sheet Ref / 66: D.O.C.K : OCT 2012 : F.O.O : K.M.M
COLUMN @ COLUMN TYPE C4 LEVEL 1
Basic Data Design to
BS 8110: 199
Grades Fy, Fyv, Fcu
460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 400 mm deep column βy : for 600 mm wide column Lc=5000
Top: Shallow, Bottom: Shallow Top: Deep, Bottom: Shallow Lox=5000-(700+0)/2 Loy=5000-(600+0)/2
1.50 1.30 4650 4700
LEX=6975.0 MM, LEX/H=17.4, EXX=20.0 MM LEY=6110.0 MM, LEY/B=10.2, EYY=20.0 MM BI-AXIAL , SLENDER, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Part 1 of 2 with Mxx Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
4253.7 k
.45x(600x400-10988)x25 + 0.95x10987.7x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-10988)x25 + 0.95x10987.7x460
OK Applied Moments (Mx1, Mx2) -39.0 kN.m, 65.2 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (7378 - 4254)/(7378 - 718) < 1 au = βa • K • h 0.152, 1.000, 400 Madd= N • au 4254 x 60.8 Mi=fn(Mx1, Mx2) -39.0 kN.m, 65.2 kN.m M2+Madd, M nom 323.9 kN.m, 85.1 kN.m M nom=fn(N, exx) 4253.7 kN, 20.0 mm Design Moment
7378.0 k OK 7120.4 k
X-X Moments 1.00 60.8 mm 258.7 kN.m 26.1 kN.m 258.7 kN.m 323.9 kN.m
Y-Y Moments Applied Moments (My1, My2) 1.2 kN.m, -1.5 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (7378 - 4254)/(7378 - 957) < 1 au = βa • K • h 0.052, 1.000, 400 Madd= N • au 4254 x 31.1 Mi=fn(My1, My2) 1.2 kN.m, -1.5 kN.m M nom=fn(M2+Madd) 133.8
1.00 31.1 mm 132.3 kN.m 0.6 kN.m 0.0 kN.m
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected], M nom=fn(N, eyy) Design Moment
Job ref Sheet Made By Date Checked Approved
: Job Ref : Sheet Ref / 67: D.O.C.K : OCT 2012 : F.O.O : K.M.M
4253.7, 20.0
132.3 kN.m 133.8 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(323.9² + 133.8² ) atn(133.8/ 323.9)
350.4 kN.m 22.5 deg
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Bar group13:M13 fn(bars,d,ε%,,la,F) Bar group14:M14 fn(bars,d,ε%,,la,F) Bar group15:M15 fn(bars,d,ε%,,la,F) Bar group16:M16 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M16)
0.726, 599 mm, 600 mm, 434.81 mm, 179009 mm², 244.5 m 1 x 32, 515.2, -0.065, -129, -215.8, -104.1 1 x 32, 335.0, 0.080, 161, -35.6, 129.3 1 x 25, 473.4, -0.031, -62, -174.0, -30.5 1 x 25, 428.3, 0.005, 10, -128.9, 5.1 1 x 25, 383.3, 0.041, 83, -83.9, 40.7 1 x 32, 452.4, -0.014, -28, -153.0, -22.8 1 x 32, 389.5, 0.036, 73, -90.1, 58.6 1 x 32, 326.7, 0.087, 174, -27.3, 140.0 1 x 32, 263.8, 0.138, 275, 35.6, 221.4 1 x 32, 83.6, 0.283, 437, 215.8, 351.5 1 x 25, 215.5, 0.176, 353, 83.9, 173.3 1 x 25, 170.5, 0.213, 426, 128.9, 208.9 1 x 25, 125.4, 0.249, 437, 174.0, 214.5 1 x 32, 272.1, 0.131, 262, 27.3, 210.6 1 x 32, 209.3, 0.182, 363, 90.1, 292.0 1 x 32, 146.4, 0.232, 437, 153.0, 351.5 179009 x 0.45 x 25 -104+129-30+5+41-23+59+140+221+351+17 +209+215+211+292+351+2014-4253.7
Max Moment/Mu
2013.8 x (599 / 2 - 244.5) 110.5 + (22.5+-4.6+5.3+-0.7+-3.4+3.5+-5.3 + (-3.8+7.9+75.9+14.5+26.9+37.3+5.7 + (26.3+53.8) 350.4 / 372.3
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
76.1 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
31.5 mm, 360 m
OK
22.5 -4.6 5.3 -0.7 -3.4 3.5 -5.3 -3.8 7.9 75.9 14.5 26.9 37.3 5.7 26.3 53.8 2013.8
kN kN kN kN kN kN kN kN kN kN kN kN kN kN kN kN k
0.0
k OK 110.5 kN
372.3kN 0.94
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
NOMINAL LINKS BI-AXIAL , SLENDER, U NBRACED, COLUMN DESIGN Critical Case : 1 : Dead plus Live Part 2 of 2: with Myy Nominal considered Axial Capacity Applied Axial N Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
.45x(600x400-10988)x25 + 0.95x10987.7x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-10988)x25 + 0.95x10987.7x460
OK Applied Moments (Mx1, Mx2) -39.0 kN.m, 65.2 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (7378 - 4254)/(7378 - 718) < 1 au = βa • K • h 0.152, 1.000, 400 Madd= N • au 4254 x 60.8 Mi=fn(Mx1, Mx2) -39.0 kN.m, 65.2 kN.m M2+Madd, M nom 323.9 kN.m, 0.0 kN.m M nom=fn(N, exx) 4253.7 kN, 20.0 mm Design Moment
4253.7 k 7378.0 k OK 7120.4 k
X-X Moments 1.00 60.8 mm 258.7 kN.m 26.1 kN.m 258.7 kN.m 323.9 kN.m
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
Job ref Sheet Made By Date Checked Approved
: Job Ref : Sheet Ref / 68: D.O.C.K : OCT 2012 : F.O.O : K.M.M
Y-Y Moments Applied Moments (My1, My2) 1.2 kN.m, -1.5 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (7378 - 4254)/(7378 - 957) < 1 au = βa • K • h 0.052, 1.000, 400 Madd= N • au 4254 x 31.1 Mi=fn(My1, My2) 1.2 kN.m, -1.5 kN.m M nom=fn(M2+Madd) 133.8 M nom=fn(N, eyy) 4253.7, 20.0 Design Moment
1.00 31.1 mm 132.3 kN.m 0.6 kN.m 85.1 kN.m 132.3 kN.m 133.8 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(323.9² + 133.8² ) atn(133.8/ 323.9)
350.4 kN.m 22.5 deg
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Bar group13:M13 fn(bars,d,ε%,,la,F) Bar group14:M14 fn(bars,d,ε%,,la,F) Bar group15:M15 fn(bars,d,ε%,,la,F) Bar group16:M16 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M16)
0.726, 599 mm, 600 mm, 434.81 mm, 179009 mm², 244.5 m 1 x 32, 515.2, -0.065, -129, -215.8, -104.1 1 x 32, 335.0, 0.080, 161, -35.6, 129.3 1 x 25, 473.4, -0.031, -62, -174.0, -30.5 1 x 25, 428.3, 0.005, 10, -128.9, 5.1 1 x 25, 383.3, 0.041, 83, -83.9, 40.7 1 x 32, 452.4, -0.014, -28, -153.0, -22.8 1 x 32, 389.5, 0.036, 73, -90.1, 58.6 1 x 32, 326.7, 0.087, 174, -27.3, 140.0 1 x 32, 263.8, 0.138, 275, 35.6, 221.4 1 x 32, 83.6, 0.283, 437, 215.8, 351.5 1 x 25, 215.5, 0.176, 353, 83.9, 173.3 1 x 25, 170.5, 0.213, 426, 128.9, 208.9 1 x 25, 125.4, 0.249, 437, 174.0, 214.5 1 x 32, 272.1, 0.131, 262, 27.3, 210.6 1 x 32, 209.3, 0.182, 363, 90.1, 292.0 1 x 32, 146.4, 0.232, 437, 153.0, 351.5 179009 x 0.45 x 25 -104+129-30+5+41-23+59+140+221+351+17 +209+215+211+292+351+2014-4253.7
Max Moment/Mu
2013.8 x (599 / 2 - 244.5) 110.5 + (22.5+-4.6+5.3+-0.7+-3.4+3.5+-5.3 + (-3.8+7.9+75.9+14.5+26.9+37.3+5.7 + (26.3+53.8) 350.4 / 372.3
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
76.1 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
31.5 mm, 360 m
OK
22.5 -4.6 5.3 -0.7 -3.4 3.5 -5.3 -3.8 7.9 75.9 14.5 26.9 37.3 5.7 26.3 53.8 2013.8
kN kN kN kN kN kN kN kN kN kN kN kN kN kN kN kN k
0.0
k OK 110.5 kN
372.3kN 0.94
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
Nominal links
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 69: D.O.C.K : OCT 2012 : F.O.O : K.M.M
COLUMN @ COLUMN TYPE C5 LEVEL 6
Basic Data Design to
BS 8110: 199
Grades Fy, Fyv, Fcu
460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 300 mm deep column βy : for 400 mm wide column Lc=3300
Top: Deep, Bottom: Deep Top: Shallow, Bottom: Shallow Lox=3300-(600+600)/2 Loy=3300-(600+600)/2
1.20 1.50 2700 2700
LEX=3240.0 MM, LEX/H=10.8, EXX=15.0 MM LEY=4050.0 MM, LEY/B=10.1, EYY=20.0 MM BI-AXIAL , SLENDER, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Part 1 of 2 with Mxx Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
314.2 k
.45x(400x300-2513)x25 + 0.95x2513.3x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(400x300-2513)x25 + 0.95x2513.3x460
OK Applied Moments (Mx1, Mx2) -78.6 kN.m, 59.7 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (2420 - 314)/(2420 - 608) < 1 au = βa • K • h 0.058, 1.000, 300 Madd= N • au 314 x 17.5 Mi=fn(Mx1, Mx2) -78.6 kN.m, 59.7 kN.m M2+Madd, M nom 84.1 kN.m, 4.7 kN.m M nom=fn(N, exx) 314.2 kN, 15.0 mm Design Moment
2420.0 k OK 2287.9 k
X-X Moments 1.00 17.5 mm 5.5 kN.m 31.4 kN.m 5.5 kN.m 84.1 kN.m
Y-Y Moments Applied Moments (My1, My2) -22.7 kN.m, 14.7 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (2420 - 314)/(2420 - 660) < 1 au = βa • K • h 0.051, 1.000, 300 Madd= N • au 314 x 20.5 Mi=fn(My1, My2) -22.7 kN.m, 14.7 kN.m M nom=fn(M2+Madd) 29.1
1.00 20.5 mm 6.4 kN.m 9.1 kN.m 0.0 kN.m
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected], M nom=fn(N, eyy) Design Moment
: Job Ref : Sheet Ref / 70: D.O.C.K : OCT 2012 : F.O.O : K.M.M
314.2, 20.0
6.4 kN.m 29.1 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(84.1² + 29.1² ) atn(29.1/ 84.1)
89.0 kN.m 19.1 deg
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
0.446, 414 mm, 400 mm, 184.74 mm, 42662 mm², 108.8 m 1 x 20, 340.6, -0.295, -437, -133.4, -137.3 1 x 20, 247.7, -0.119, -238, -40.4, -74.9 1 x 20, 294.1, -0.207, -415, -86.9, -130.2 1 x 20, 253.7, -0.131, -261, -46.5, -82.1 1 x 20, 166.8, 0.034, 68, 40.4, 21.4 1 x 20, 73.8, 0.210, 420, 133.4, 132.1 1 x 20, 120.3, 0.122, 244, 86.9, 76.7 1 x 20, 160.7, 0.045, 91, 46.5, 28.6 42662 x 0.45 x 25 -137-75-130-82+21+132+77+29+480-314.2
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M8) Max Moment/Mu
480.0 x (414 / 2 - 108.8) 47.2 + (18.3+3.0+11.3+3.8+0.9+17.6+6.7 + (1.3) 89.0 / 110.2
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
267.7 mm, 180 m
100 As/bd, vc, vc' As/Svreq, Sv, Links Asvreq, Asvpvd
2.60%, 0.98 N/mm², 0.98 N/mm² 0 mm, 225 mm, 3 no 8 mm legs 0 mm², 151 mm²
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
92.8 mm, 240 m
OK
18.3 3.0 11.3 3.8 0.9 17.6 6.7 1.3 480.0 0.0
kN kN kN kN kN kN kN kN k k OK 47.2 kN
110.2kN 0.80
X-X Shear Checks OK
links reqd. Link check
Nominal OK Y-Y Shear Checks OK
NOMINAL LINKS BI-AXIAL , SLENDER, U NBRACED, COLUMN DESIGN Critical Case : 1 : Dead plus Live Part 2 of 2: with Myy Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
314.2 k
.45x(400x300-2513)x25 + 0.95x2513.3x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(400x300-2513)x25 + 0.95x2513.3x460
OK Applied Moments (Mx1, Mx2) -78.6 kN.m, 59.7 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (2420 - 314)/(2420 - 608) < 1 au = βa • K • h 0.058, 1.000, 300 Madd= N • au 314 x 17.5 Mi=fn(Mx1, Mx2) -78.6 kN.m, 59.7 kN.m M2+Madd, M nom 84.1 kN.m, 0.0 kN.m M nom=fn(N, exx) 314.2 kN, 15.0 mm Design Moment
2420.0 k OK 2287.9 k
X-X Moments 1.00 17.5 mm 5.5 kN.m 31.4 kN.m 5.5 kN.m 84.1 kN.m
Y-Y Moments Applied Moments (My1, My2) -22.7 kN.m, 14.7 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (2420 - 314)/(2420 - 660) < 1
1.00
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected], au = βa • K • h Madd= N • au Mi=fn(My1, My2) M nom=fn(M2+Madd) M nom=fn(N, eyy) Design Moment
: Job Ref : Sheet Ref / 71: D.O.C.K : OCT 2012 : F.O.O : K.M.M
0.051, 1.000, 300 314 x 20.5 -22.7 kN.m, 14.7 kN.m 29.1 314.2, 20.0
20.5 mm 6.4 kN.m 9.1 kN.m 6.3 kN.m 6.4 kN.m 29.1 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(84.1² + 29.1² ) atn(29.1/ 84.1)
89.0 kN.m 19.1 deg
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
0.446, 414 mm, 400 mm, 184.74 mm, 42662 mm², 108.8 m 1 x 20, 340.6, -0.295, -437, -133.4, -137.3 1 x 20, 247.7, -0.119, -238, -40.4, -74.9 1 x 20, 294.1, -0.207, -415, -86.9, -130.2 1 x 20, 253.7, -0.131, -261, -46.5, -82.1 1 x 20, 166.8, 0.034, 68, 40.4, 21.4 1 x 20, 73.8, 0.210, 420, 133.4, 132.1 1 x 20, 120.3, 0.122, 244, 86.9, 76.7 1 x 20, 160.7, 0.045, 91, 46.5, 28.6 42662 x 0.45 x 25 -137-75-130-82+21+132+77+29+480-314.2
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M8) Max Moment/Mu
480.0 x (414 / 2 - 108.8) 47.2 + (18.3+3.0+11.3+3.8+0.9+17.6+6.7 + (1.3) 89.0 / 110.2
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
267.7 mm, 180 m
100 As/bd, vc, vc' As/Svreq, Sv, Links Asvreq, Asvpvd
2.60%, 0.98 N/mm², 0.98 N/mm² 0 mm, 225 mm, 3 no 8 mm legs 0 mm², 151 mm²
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
92.8 mm, 240 m
OK
18.3 3.0 11.3 3.8 0.9 17.6 6.7 1.3 480.0 0.0
kN kN kN kN kN kN kN kN k k OK 47.2 kN
110.2kN 0.80
X-X Shear Checks OK
links reqd. Link check
Nominal OK Y-Y Shear Checks OK
Nominal links
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 72: D.O.C.K : OCT 2012 : F.O.O : K.M.M
COLUMN @ COLUMN TYPE C5 LEVEL 5
Basic Data Design to
BS 8110: 199
Grades Fy, Fyv, Fcu
460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 300 mm deep column βy : for 400 mm wide column Lc=3300
Top: Deep, Bottom: Deep Top: Shallow, Bottom: Shallow Lox=3300-(600+600)/2 Loy=3300-(600+600)/2
1.20 1.50 2700 2700
LEX=3240.0 MM, LEX/H=10.8, EXX=15.0 MM LEY=4050.0 MM, LEY/B=10.1, EYY=20.0 MM BI-AXIAL , SLENDER, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Part 1 of 2 with Mxx Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
826.7 k
.45x(400x300-3770)x25 + 0.95x3769.9x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(400x300-3770)x25 + 0.95x3769.9x460
OK Applied Moments (Mx1, Mx2) -94.0 kN.m, 87.7 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (2955 - 827)/(2955 - 608) < 1 au = βa • K • h 0.058, 1.000, 300 Madd= N • au 827 x 17.5 Mi=fn(Mx1, Mx2) -94.0 kN.m, 87.7 kN.m M2+Madd, M nom 108.5 kN.m, 12.4 kN.m M nom=fn(N, exx) 826.7 kN, 15.0 mm Design Moment
2955.0 k OK 2824.3 k
X-X Moments 1.00 17.5 mm 14.5 kN.m 37.6 kN.m 14.5 kN.m 108.5 kN.m
Y-Y Moments Applied Moments (My1, My2) -46.3 kN.m, 39.9 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (2955 - 827)/(2955 - 682) < 1 au = βa • K • h 0.051, 1.000, 300 Madd= N • au 827 x 20.5 Mi=fn(My1, My2) -46.3 kN.m, 39.9 kN.m M nom=fn(M2+Madd) 63.2
1.00 20.5 mm 16.9 kN.m 18.5 kN.m 0.0 kN.m
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected], M nom=fn(N, eyy) Design Moment
: Job Ref : Sheet Ref / 73: D.O.C.K : OCT 2012 : F.O.O : K.M.M
826.7, 20.0
16.9 kN.m 63.2 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(108.5² + 63.2² ) atn(63.2/ 108.5)
125.6 kN.m 30.2 deg
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M12)
0.540, 461 mm, 400 mm, 248.92 mm, 57083 mm², 148.7 m 1 x 20, 381.3, -0.186, -372, -151.0, -117.0 1 x 20, 238.3, 0.015, 30, -7.9, 9.4 1 x 20, 333.6, -0.119, -238, -103.3, -74.9 1 x 20, 286.0, -0.052, -104, -55.6, -32.7 1 x 20, 328.4, -0.112, -223, -98.0, -70.2 1 x 20, 275.4, -0.037, -74, -45.0, -23.4 1 x 20, 222.4, 0.037, 75, 7.9, 23.4 1 x 20, 79.3, 0.238, 437, 151.0, 137.3 1 x 20, 174.7, 0.104, 209, 55.6, 65.6 1 x 20, 127.0, 0.171, 343, 103.3, 107.7 1 x 20, 185.3, 0.089, 179, 45.0, 56.2 1 x 20, 132.3, 0.164, 328, 98.0, 103.0 57083 x 0.45 x 25 -117+9-75-33-70-23+23+137+66+108+5 +103+642-826.7
Max Moment/Mu
642.2 x (461 / 2 - 148.7) 52.4 + (17.7+-0.1+7.7+1.8+6.9+1.1+0.2+20.7 + (3.6+11.1+2.5+10.1) 125.6 / 135.8
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
131.2 mm, 180 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
76.5 mm, 240 m
OK
17.7 -0.1 7.7 1.8 6.9 1.1 0.2 20.7 3.6 11.1 2.5 10.1 642.2
kN kN kN kN kN kN kN kN kN kN kN kN k
0.0
k OK 52.4 kN 135.8kN 0.92
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
NOMINAL LINKS BI-AXIAL , SLENDER, U NBRACED, COLUMN DESIGN Critical Case : 1 : Dead plus Live Part 2 of 2: with Myy Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
826.7 k
.45x(400x300-3770)x25 + 0.95x3769.9x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(400x300-3770)x25 + 0.95x3769.9x460
OK Applied Moments (Mx1, Mx2) -94.0 kN.m, 87.7 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (2955 - 827)/(2955 - 608) < 1 au = βa • K • h 0.058, 1.000, 300 Madd= N • au 827 x 17.5 Mi=fn(Mx1, Mx2) -94.0 kN.m, 87.7 kN.m M2+Madd, M nom 108.5 kN.m, 0.0 kN.m M nom=fn(N, exx) 826.7 kN, 15.0 mm Design Moment
2955.0 k OK 2824.3 k
X-X Moments 1.00 17.5 mm 14.5 kN.m 37.6 kN.m 14.5 kN.m 108.5 kN.m
Y-Y Moments Applied Moments (My1, My2) -46.3 kN.m, 39.9 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (2955 - 827)/(2955 - 682) < 1
1.00
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected], au = βa • K • h Madd= N • au Mi=fn(My1, My2) M nom=fn(M2+Madd) M nom=fn(N, eyy) Design Moment
Job ref Sheet Made By Date Checked Approved
: Job Ref : Sheet Ref / 74: D.O.C.K : OCT 2012 : F.O.O : K.M.M
0.051, 1.000, 300 827 x 20.5 -46.3 kN.m, 39.9 kN.m 63.2 826.7, 20.0
20.5 mm 16.9 kN.m 18.5 kN.m 16.5 kN.m 16.9 kN.m 63.2 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(108.5² + 63.2² ) atn(63.2/ 108.5)
125.6 kN.m 30.2 deg
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M12)
0.540, 461 mm, 400 mm, 248.92 mm, 57083 mm², 148.7 m 1 x 20, 381.3, -0.186, -372, -151.0, -117.0 1 x 20, 238.3, 0.015, 30, -7.9, 9.4 1 x 20, 333.6, -0.119, -238, -103.3, -74.9 1 x 20, 286.0, -0.052, -104, -55.6, -32.7 1 x 20, 328.4, -0.112, -223, -98.0, -70.2 1 x 20, 275.4, -0.037, -74, -45.0, -23.4 1 x 20, 222.4, 0.037, 75, 7.9, 23.4 1 x 20, 79.3, 0.238, 437, 151.0, 137.3 1 x 20, 174.7, 0.104, 209, 55.6, 65.6 1 x 20, 127.0, 0.171, 343, 103.3, 107.7 1 x 20, 185.3, 0.089, 179, 45.0, 56.2 1 x 20, 132.3, 0.164, 328, 98.0, 103.0 57083 x 0.45 x 25 -117+9-75-33-70-23+23+137+66+108+5 +103+642-826.7
Max Moment/Mu
642.2 x (461 / 2 - 148.7) 52.4 + (17.7+-0.1+7.7+1.8+6.9+1.1+0.2+20.7 + (3.6+11.1+2.5+10.1) 125.6 / 135.8
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
131.2 mm, 180 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
76.5 mm, 240 m
OK
17.7 -0.1 7.7 1.8 6.9 1.1 0.2 20.7 3.6 11.1 2.5 10.1 642.2
kN kN kN kN kN kN kN kN kN kN kN kN k
0.0
k OK 52.4 kN 135.8kN 0.92
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
Nominal links
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 75: D.O.C.K : OCT 2012 : F.O.O : K.M.M
COLUMN @ COLUMN TYPE C5 LEVEL 4
Basic Data Design to
BS 8110: 199
Grades Fy, Fyv, Fcu
460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 300 mm deep column βy : for 400 mm wide column Lc=3300
Top: Deep, Bottom: Deep Top: Shallow, Bottom: Shallow Lox=3300-(600+600)/2 Loy=3300-(600+600)/2
1.20 1.50 2700 2700
LEX=3240.0 MM, LEX/H=10.8, EXX=15.0 MM LEY=4050.0 MM, LEY/B=10.1, EYY=20.0 MM BI-AXIAL , SLENDER, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Part 1 of 2 with Mxx Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
1188.4 k
.45x(400x300-3848)x25 + 0.95x3848.5x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(400x300-3848)x25 + 0.95x3848.5x460
OK Applied Moments (Mx1, Mx2) -90.4 kN.m, 80.8 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (2988 - 1188)/(2988 - 608) < 1 au = βa • K • h 0.058, 1.000, 300 Madd= N • au 1188 x 17.5 Mi=fn(Mx1, Mx2) -90.4 kN.m, 80.8 kN.m M2+Madd, M nom 111.2 kN.m, 17.8 kN.m M nom=fn(N, exx) 1188.4 kN, 15.0 mm Design Moment
2988.5 k OK 2857.8 k
X-X Moments 1.00 17.5 mm 20.8 kN.m 36.2 kN.m 20.8 kN.m 111.2 kN.m
Y-Y Moments Applied Moments (My1, My2) -44.5 kN.m, 41.7 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (2988 - 1188)/(2988 - 654) < 1 au = βa • K • h 0.051, 1.000, 300 Madd= N • au 1188 x 20.5 Mi=fn(My1, My2) -44.5 kN.m, 41.7 kN.m M nom=fn(M2+Madd) 68.9
1.00 20.5 mm 24.4 kN.m 17.8 kN.m 0.0 kN.m
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected], M nom=fn(N, eyy) Design Moment
: Job Ref : Sheet Ref / 76: D.O.C.K : OCT 2012 : F.O.O : K.M.M
1188.4, 20.0
24.4 kN.m 68.9 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(111.2² + 68.9² ) atn(68.9/ 111.2)
130.8 kN.m 31.8 deg
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M10)
0.599, 466 mm, 400 mm, 278.79 mm, 68509 mm², 165.4 m 1 x 25, 382.4, -0.130, -260, -149.5, -127.7 1 x 25, 235.5, 0.054, 109, -2.6, 53.4 1 x 20, 311.0, -0.040, -81, -78.2, -25.4 1 x 20, 333.0, -0.068, -136, -100.1, -42.7 1 x 20, 282.2, -0.004, -9, -49.4, -2.7 1 x 25, 230.2, 0.061, 122, 2.6, 59.9 1 x 25, 83.3, 0.245, 437, 149.5, 214.5 1 x 20, 154.6, 0.156, 312, 78.2, 98.0 1 x 20, 183.4, 0.120, 239, 49.4, 75.2 1 x 20, 132.7, 0.183, 367, 100.1, 115.2 68509 x 0.45 x 25 -128+53-25-43-3+60+215+98+75+115+77 -1188.4
Max Moment/Mu
770.7 x (466 / 2 - 165.4) 52.0 + (19.1+-0.1+2.0+4.3+0.1+0.2+32.1 + (7.7+3.7+11.5) 130.8 / 132.5
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
93.6 mm, 180 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
57.9 mm, 240 m
OK
19.1 -0.1 2.0 4.3 0.1 0.2 32.1 7.7 3.7 11.5 770.7
kN kN kN kN kN kN kN kN kN kN k
0.0
k OK 52.0 kN 132.5kN 0.98
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
NOMINAL LINKS BI-AXIAL , SLENDER, U NBRACED, COLUMN DESIGN Critical Case : 1 : Dead plus Live Part 2 of 2: with Myy Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
1188.4 k
.45x(400x300-3848)x25 + 0.95x3848.5x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(400x300-3848)x25 + 0.95x3848.5x460
OK Applied Moments (Mx1, Mx2) -90.4 kN.m, 80.8 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (2988 - 1188)/(2988 - 608) < 1 au = βa • K • h 0.058, 1.000, 300 Madd= N • au 1188 x 17.5 Mi=fn(Mx1, Mx2) -90.4 kN.m, 80.8 kN.m M2+Madd, M nom 111.2 kN.m, 0.0 kN.m M nom=fn(N, exx) 1188.4 kN, 15.0 mm Design Moment
2988.5 k OK 2857.8 k
X-X Moments 1.00 17.5 mm 20.8 kN.m 36.2 kN.m 20.8 kN.m 111.2 kN.m
Y-Y Moments Applied Moments (My1, My2) -44.5 kN.m, 41.7 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (2988 - 1188)/(2988 - 654) < 1 au = βa • K • h 0.051, 1.000, 300 Madd= N • au 1188 x 20.5
1.00 20.5 mm 24.4 kN.m
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected], Mi=fn(My1, My2) M nom=fn(M2+Madd) M nom=fn(N, eyy) Design Moment
: Job Ref : Sheet Ref / 77: D.O.C.K : OCT 2012 : F.O.O : K.M.M
-44.5 kN.m, 41.7 kN.m 68.9 1188.4, 20.0
17.8 23.8 24.4 68.9
kN.m kN.m kN.m kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(111.2² + 68.9² ) atn(68.9/ 111.2)
130.8 kN.m 31.8 deg
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M10)
0.599, 466 mm, 400 mm, 278.79 mm, 68509 mm², 165.4 m 1 x 25, 382.4, -0.130, -260, -149.5, -127.7 1 x 25, 235.5, 0.054, 109, -2.6, 53.4 1 x 20, 311.0, -0.040, -81, -78.2, -25.4 1 x 20, 333.0, -0.068, -136, -100.1, -42.7 1 x 20, 282.2, -0.004, -9, -49.4, -2.7 1 x 25, 230.2, 0.061, 122, 2.6, 59.9 1 x 25, 83.3, 0.245, 437, 149.5, 214.5 1 x 20, 154.6, 0.156, 312, 78.2, 98.0 1 x 20, 183.4, 0.120, 239, 49.4, 75.2 1 x 20, 132.7, 0.183, 367, 100.1, 115.2 68509 x 0.45 x 25 -128+53-25-43-3+60+215+98+75+115+77 -1188.4
Max Moment/Mu
770.7 x (466 / 2 - 165.4) 52.0 + (19.1+-0.1+2.0+4.3+0.1+0.2+32.1 + (7.7+3.7+11.5) 130.8 / 132.5
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
93.6 mm, 180 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
57.9 mm, 240 m
OK
19.1 -0.1 2.0 4.3 0.1 0.2 32.1 7.7 3.7 11.5 770.7
kN kN kN kN kN kN kN kN kN kN k
0.0
k OK 52.0 kN 132.5kN 0.98
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
Nominal links
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 78: D.O.C.K : OCT 2012 : F.O.O : K.M.M
COLUMN @ COLUMN TYPE C5 LEVEL 3
Basic Data Design to
BS 8110: 199
Grades Fy, Fyv, Fcu
460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 300 mm deep column βy : for 400 mm wide column Lc=3300
Top: Deep, Bottom: Deep Top: Shallow, Bottom: Shallow Lox=3300-(600+600)/2 Loy=3300-(600+600)/2
1.20 1.50 2700 2700
LEX=3240.0 MM, LEX/H=10.8, EXX=15.0 MM LEY=4050.0 MM, LEY/B=10.1, EYY=20.0 MM BI-AXIAL , SLENDER, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Part 1 of 2 with Mxx Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
1523.6 k
.45x(400x300-5730)x25 + 0.95x5730.3x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(400x300-5730)x25 + 0.95x5730.3x460
OK Applied Moments (Mx1, Mx2) -104.6 kN.m, 85.6 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (3790 - 1524)/(3790 - 504) < 1 au = βa • K • h 0.058, 1.000, 300 Madd= N • au 1524 x 17.5 Mi=fn(Mx1, Mx2) -104.6 kN.m, 85.6 kN.m M2+Madd, M nom 131.3 kN.m, 22.9 kN.m M nom=fn(N, exx) 1523.6 kN, 15.0 mm Design Moment
3789.7 k OK 3661.1 k
X-X Moments 1.00 17.5 mm 26.7 kN.m 41.8 kN.m 26.7 kN.m 131.3 kN.m
Y-Y Moments Applied Moments (My1, My2) -79.2 kN.m, 51.6 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (3790 - 1524)/(3790 - 653) < 1 au = βa • K • h 0.051, 1.000, 300 Madd= N • au 1524 x 20.5 Mi=fn(My1, My2) -79.2 kN.m, 51.6 kN.m M nom=fn(M2+Madd) 110.4
1.00 20.5 mm 31.2 kN.m 31.7 kN.m 0.0 kN.m
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected], M nom=fn(N, eyy) Design Moment
: Job Ref : Sheet Ref / 79: D.O.C.K : OCT 2012 : F.O.O : K.M.M
1523.6, 20.0
31.2 kN.m 110.4 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(131.3² + 110.4² ) atn(110.4/ 131.3)
171.5 kN.m 40.1 deg
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M12)
0.616, 487 mm, 400 mm, 299.94 mm, 72146 mm², 178.0 m 1 x 32, 396.9, -0.113, -226, -153.4, -182.0 1 x 32, 221.8, 0.091, 182, 21.8, 146.7 1 x 20, 343.1, -0.050, -101, -99.6, -31.7 1 x 20, 284.8, 0.018, 35, -41.2, 11.1 1 x 20, 356.9, -0.066, -133, -113.4, -41.8 1 x 20, 313.0, -0.015, -31, -69.5, -9.6 1 x 32, 265.3, 0.040, 81, -21.8, 65.0 1 x 32, 90.2, 0.245, 437, 153.4, 351.5 1 x 20, 202.3, 0.114, 228, 41.2, 71.6 1 x 20, 144.0, 0.182, 364, 99.6, 114.4 1 x 20, 174.1, 0.147, 294, 69.5, 92.3 1 x 20, 130.2, 0.198, 396, 113.4, 124.5 72146 x 0.45 x 25 -182+147-32+11-42-10+65+351+72+114+9 +124+812-1523.6
Max Moment/Mu
811.6 x (487 / 2 - 178.0) 53.2 + (27.9+3.2+3.2+-0.5+4.7+0.7+-1.4 + (53.9+2.9+11.4+6.4+14.1) 171.5 / 179.7
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
86.1 mm, 180 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
72.5 mm, 240 m
OK
27.9 3.2 3.2 -0.5 4.7 0.7 -1.4 53.9 2.9 11.4 6.4 14.1 811.6
kN kN kN kN kN kN kN kN kN kN kN kN k
0.0
k OK 53.2 kN 179.7kN 0.95
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
NOMINAL LINKS BI-AXIAL , SLENDER, U NBRACED, COLUMN DESIGN Critical Case : 1 : Dead plus Live Part 2 of 2: with Myy Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
1523.6 k
.45x(400x300-5730)x25 + 0.95x5730.3x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(400x300-5730)x25 + 0.95x5730.3x460
OK Applied Moments (Mx1, Mx2) -104.6 kN.m, 85.6 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (3790 - 1524)/(3790 - 504) < 1 au = βa • K • h 0.058, 1.000, 300 Madd= N • au 1524 x 17.5 Mi=fn(Mx1, Mx2) -104.6 kN.m, 85.6 kN.m M2+Madd, M nom 131.3 kN.m, 0.0 kN.m M nom=fn(N, exx) 1523.6 kN, 15.0 mm Design Moment
3789.7 k OK 3661.1 k
X-X Moments 1.00 17.5 mm 26.7 kN.m 41.8 kN.m 26.7 kN.m 131.3 kN.m
Y-Y Moments Applied Moments (My1, My2) -79.2 kN.m, 51.6 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (3790 - 1524)/(3790 - 653) < 1
1.00
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected], au = βa • K • h Madd= N • au Mi=fn(My1, My2) M nom=fn(M2+Madd) M nom=fn(N, eyy) Design Moment
: Job Ref : Sheet Ref / 80: D.O.C.K : OCT 2012 : F.O.O : K.M.M
0.051, 1.000, 300 1524 x 20.5 -79.2 kN.m, 51.6 kN.m 110.4 1523.6, 20.0
20.5 mm 31.2 kN.m 31.7 kN.m 30.5 kN.m 31.2 kN.m 110.4 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(131.3² + 110.4² ) atn(110.4/ 131.3)
171.5 kN.m 40.1 deg
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp= 0
0.616, 487 mm, 400 mm, 299.94 mm, 72146 mm², 178.0 m 1 x 32, 396.9, -0.113, -226, -153.4, -182.0 1 x 32, 221.8, 0.091, 182, 21.8, 146.7 1 x 20, 343.1, -0.050, -101, -99.6, -31.7 1 x 20, 284.8, 0.018, 35, -41.2, 11.1 1 x 20, 356.9, -0.066, -133, -113.4, -41.8 1 x 20, 313.0, -0.015, -31, -69.5, -9.6 1 x 32, 265.3, 0.040, 81, -21.8, 65.0 1 x 32, 90.2, 0.245, 437, 153.4, 351.5 1 x 20, 202.3, 0.114, 228, 41.2, 71.6 1 x 20, 144.0, 0.182, 364, 99.6, 114.4 1 x 20, 174.1, 0.147, 294, 69.5, 92.3 1 x 20, 130.2, 0.198, 396, 113.4, 124.5 72146 x 0.45 x 25 -182+147-32+11-42-10+65+351+72+114+9+124+812-1523.6
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M12)
811.6 x (487 / 2 - 178.0) 53.2 + (27.9+3.2+3.2+-0.5+4.7+0.7+-1.4 + (53.9+2.9+11.4+6.4+14.1)
Max Moment/Mu
171.5 / 179.7
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
86.1 mm, 180 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
72.5 mm, 240 m
27.9 3.2 3.2 -0.5 4.7 0.7 -1.4 53.9 2.9 11.4 6.4 14.1 811.6 0.0
kN kN kN kN kN kN kN kN kN kN kN kN k k OK 53.2 kN
179.7kN
0.95
OK
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
Nominal links
COLUMN @ COLUMN TYPE C5 LEVEL 2
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 81: D.O.C.K : OCT 2012 : F.O.O : K.M.M
Basic Data Design to
BS 8110: 199
Grades Fy, Fyv, Fcu
460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 400 mm deep column βy : for 500 mm wide column Lc=5000
Top: Shallow, Bottom: Shallow Top: Shallow, Bottom: Deep Lox=5000-(600+600)/2 Loy=5000-(600+600)/2
1.50 1.30 4400 4400
LEX=6600.0 MM, LEX/H=16.5, EXX=20.0 MM LEY=5720.0 MM, LEY/B=11.4, EYY=20.0 MM BI-AXIAL , SLENDER, UNBRACED, COLUMN DESIGN Critical Case : 1 : Dead plus Live Part 1 of 2 with Mxx Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
1907.9 k
.45x(500x400-5730)x25 + 0.95x5730.3x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(500x400-5730)x25 + 0.95x5730.3x460
OK
4689.7 k OK 4471.1 k
X-X Moments
Applied Moments (Mx1, Mx2) -54.6 kN.m, 63.3 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (4690 - 1908)/(4690 - 1077) < 1 au = βa • K • h 0.136, 1.000, 400 Madd= N • au 1908 x 54.5 Mi=fn(Mx1, Mx2) -54.6 kN.m, 63.3 kN.m M2+Madd, M nom 167.2 kN.m, 38.2 kN.m M nom=fn(N, exx) 1907.9 kN, 20.0 mm Design Moment
1.00 54.5 mm 103.9 kN.m 25.3 kN.m 103.9 kN.m 167.2 kN.m
Y-Y Moments Applied Moments (My1, My2) 62.1 kN.m, 7.5 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (4690 - 1908)/(4690 - 1128) < 1 au = βa • K • h 0.065, 1.000, 400 Madd= N • au 1908 x 32.7 Mi=fn(My1, My2) 62.1 kN.m, 7.5 kN.m M nom=fn(M2+Madd) 124.5 M nom=fn(N, eyy) 1907.9, 20.0 Design Moment
1.00 32.7 mm 62.4 kN.m 40.3 kN.m 0.0 kN.m 62.4 kN.m 124.5 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(167.2² + 124.5² ) atn(124.5/ 167.2)
208.5 kN.m 36.7 deg
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu)
0.602, 619 mm, 500 mm, 372.96 mm, 115936 mm², 222.3 m 1 x 32, 529.9, -0.147, -295, -220.2, -236.9 1 x 32, 307.7, 0.061, 122, 2.0, 98.5 1 x 20, 460.7, -0.082, -165, -150.9, -51.7 1 x 20, 386.6, -0.013, -26, -76.8, -8.0 1 x 20, 460.8, -0.082, -165, -151.0, -51.8 1 x 20, 388.1, -0.014, -28, -78.3, -8.9 1 x 32, 311.8, 0.057, 115, -2.0, 92.4 1 x 32, 89.6, 0.266, 437, 220.2, 351.5 1 x 20, 232.9, 0.131, 263, 76.8, 82.6 1 x 20, 158.8, 0.201, 402, 150.9, 126.3 1 x 20, 231.4, 0.133, 266, 78.3, 83.5 1 x 20, 158.7, 0.201, 402, 151.0, 126.3 115936 x 0.45 x 25
52.2 0.2 7.8 0.6 7.8 0.7 -0.2 77.4 6.3 19.1 6.5 19.1 1304.3
kN kN kN kN kN kN kN kN kN kN kN kN k
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected], F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M12)
: Job Ref : Sheet Ref / 82: D.O.C.K : OCT 2012 : F.O.O : K.M.M
-237+99-52-8-52-9+92+351+83+126+83+12 +1304-1907.9
0.0
Max Moment/Mu
1304.3 x (619 / 2 - 222.3) 114.0 + (52.2+0.2+7.8+0.6+7.8+0.7+-0.2+77.4 + (6.3+19.1+6.5+19.1) 208.5 / 311.5
App. Shear Vx, v, v max M/N, 0.6h
0 kN, 0 N/mm², 4 N/mm² 87.6 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
65.3 mm, 300 m
OK
k OK 114.0 kN 311.5kN 0.66
X-X Shear Checks
Nominal links
Y-Y Shear Checks OK
NOMINAL LINKS BI-AXIAL , SLENDER, U NBRACED, COLUMN DESIGN Critical Case : 1 : Dead plus Live Part 2 of 2: with Myy Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
1907.9 k
.45x(500x400-5730)x25 + 0.95x5730.3x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(500x400-5730)x25 + 0.95x5730.3x460
OK
4689.7 k OK 4471.1 k
X-X Moments
Applied Moments (Mx1, Mx2) -54.6 kN.m, 63.3 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (4690 - 1908)/(4690 - 1077) < 1 au = βa • K • h 0.136, 1.000, 400 Madd= N • au 1908 x 54.5 Mi=fn(Mx1, Mx2) -54.6 kN.m, 63.3 kN.m M2+Madd, M nom 167.2 kN.m, 0.0 kN.m M nom=fn(N, exx) 1907.9 kN, 20.0 mm Design Moment
1.00 54.5 mm 103.9 kN.m 25.3 kN.m 103.9 kN.m 167.2 kN.m
Y-Y Moments Applied Moments (My1, My2) 62.1 kN.m, 7.5 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (4690 - 1908)/(4690 - 1128) < 1 au = βa • K • h 0.065, 1.000, 400 Madd= N • au 1908 x 32.7 Mi=fn(My1, My2) 62.1 kN.m, 7.5 kN.m M nom=fn(M2+Madd) 124.5 M nom=fn(N, eyy) 1907.9, 20.0 Design Moment
1.00 32.7 mm 62.4 kN.m 40.3 kN.m 38.2 kN.m 62.4 kN.m 124.5 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(167.2² + 124.5² ) atn(124.5/ 167.2)
208.5 kN.m 36.7 deg
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F)
0.602, 619 mm, 500 mm, 372.96 mm, 115936 mm², 222.3 m 1 x 32, 529.9, -0.147, -295, -220.2, -236.9 1 x 32, 307.7, 0.061, 122, 2.0, 98.5 1 x 20, 460.7, -0.082, -165, -150.9, -51.7 1 x 20, 386.6, -0.013, -26, -76.8, -8.0 1 x 20, 460.8, -0.082, -165, -151.0, -51.8 1 x 20, 388.1, -0.014, -28, -78.3, -8.9 1 x 32, 311.8, 0.057, 115, -2.0, 92.4 1 x 32, 89.6, 0.266, 437, 220.2, 351.5 1 x 20, 232.9, 0.131, 263, 76.8, 82.6 1 x 20, 158.8, 0.201, 402, 150.9, 126.3 1 x 20, 231.4, 0.133, 266, 78.3, 83.5 1 x 20, 158.7, 0.201, 402, 151.0, 126.3
52.2 0.2 7.8 0.6 7.8 0.7 -0.2 77.4 6.3 19.1 6.5 19.1
kN kN kN kN kN kN kN kN kN kN kN kN
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected], Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M12)
Job ref Sheet Made By Date Checked Approved
115936 x 0.45 x 25 -237+99-52-8-52-9+92+351+83+126+83+12 +1304-1907.9
Max Moment/Mu
1304.3 x (619 / 2 - 222.3) 114.0 + (52.2+0.2+7.8+0.6+7.8+0.7+-0.2+77.4 + (6.3+19.1+6.5+19.1) 208.5 / 311.5
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
87.6 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
65.3 mm, 300 m
OK
: Job Ref : Sheet Ref / 83: D.O.C.K : OCT 2012 : F.O.O : K.M.M
1304.3
k
0.0
k OK 114.0 kN 311.5kN 0.66
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
Nominal links
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 84: D.O.C.K : OCT 2012 : F.O.O : K.M.M
COLUMN @ COLUMN TYPE C5 LEVEL 1
Basic Data Design to
BS 8110: 199
Grades Fy, Fyv, Fcu
460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 400 mm deep column βy : for 500 mm wide column Lc=5000
Top: Shallow, Bottom: Shallow Top: Deep, Bottom: Shallow Lox=5000-(600+0)/2 Loy=5000-(600+0)/2
1.50 1.30 4700 4700
LEX=7050.0 MM, LEX/H=17.6, EXX=20.0 MM LEY=6110.0 MM, LEY/B=12.2, EYY=20.0 MM BI-AXIAL , SLENDER, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Part 1 of 2 with Mxx Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
2784.3 k
.45x(500x400-6987)x25 + 0.95x6986.9x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(500x400-6987)x25 + 0.95x6986.9x460
OK
5224.7 k OK 5007.5 k
X-X Moments
Applied Moments (Mx1, Mx2) -18.2 kN.m, 30.7 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (5225 - 2784)/(5225 - 1084) < 1 au = βa • K • h 0.155, 1.000, 400 Madd= N • au 2784 x 62.1 Mi=fn(Mx1, Mx2) -18.2 kN.m, 30.7 kN.m M2+Madd, M nom 203.7 kN.m, 55.7 kN.m M nom=fn(N, exx) 2784.3 kN, 20.0 mm Design Moment
1.00 62.1 mm 173.0 kN.m 12.3 kN.m 173.0 kN.m 203.7 kN.m
Y-Y Moments Applied Moments (My1, My2) 65.7 kN.m, -109.9 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (5225 - 2784)/(5225 - 1070) < 1 au = βa • K • h 0.075, 1.000, 400 Madd= N • au 2784 x 37.3 Mi=fn(My1, My2) 65.7 kN.m, -109.9 kN.m M nom=fn(M2+Madd) 213.8
1.00 37.3 mm 103.9 kN.m 44.0 kN.m 0.0 kN.m
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected], M nom=fn(N, eyy) Design Moment
: Job Ref : Sheet Ref / 85: D.O.C.K : OCT 2012 : F.O.O : K.M.M
2784.3, 20.0
103.9 kN.m 213.8 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(203.7² + 213.8² ) atn(213.8/ 203.7)
295.3 kN.m 46.4 deg
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Bar group13:M13 fn(bars,d,ε%,,la,F) Bar group14:M14 fn(bars,d,ε%,,la,F) Bar group15:M15 fn(bars,d,ε%,,la,F) Bar group16:M16 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M16)
0.685, 638 mm, 500 mm, 437.26 mm, 140201 mm², 252.4 m 1 x 32, 547.4, -0.088, -176, -228.5, -141.9 1 x 32, 278.1, 0.127, 255, 40.9, 204.9 1 x 20, 484.2, -0.038, -75, -165.3, -23.6 1 x 20, 416.9, 0.016, 33, -97.9, 10.2 1 x 20, 349.6, 0.070, 140, -30.6, 44.1 1 x 20, 504.9, -0.054, -108, -185.9, -34.0 1 x 20, 458.0, -0.017, -33, -139.0, -10.4 1 x 20, 411.1, 0.021, 42, -92.1, 13.2 1 x 32, 359.8, 0.062, 124, -40.9, 99.7 1 x 32, 90.5, 0.278, 437, 228.5, 351.5 1 x 20, 288.4, 0.119, 238, 30.6, 74.9 1 x 20, 221.0, 0.173, 346, 97.9, 108.8 1 x 20, 153.7, 0.227, 437, 165.3, 137.3 1 x 20, 226.8, 0.168, 337, 92.1, 105.8 1 x 20, 179.9, 0.206, 412, 139.0, 129.4 1 x 20, 133.0, 0.244, 437, 185.9, 137.3 140201 x 0.45 x 25 -142+205-24+10+44-34-10+13+100+351+7 +109+137+106+129+137+1577-2784.3
Max Moment/Mu
1577.3 x (638 / 2 - 252.4) 105.0 + (32.4+8.4+3.9+-1.0+-1.3+6.3+1.4 + (-1.2+-4.1+80.3+2.3+10.7+22.7+9.7 + (18.0+25.5) 295.3 / 319.0
App. Shear Vx, v, v max M/N, 0.6h
0 kN, 0 N/mm², 4 N/mm² 73.2 mm, 240 m
App. Shear Vy, v, v max M/N, 0.6b
0 kN, 0 N/mm², 4 N/mm² 76.8 mm, 300 m
OK
32.4 8.4 3.9 -1.0 -1.3 6.3 1.4 -1.2 -4.1 80.3 2.3 10.7 22.7 9.7 18.0 25.5 1577.3
kN kN kN kN kN kN kN kN kN kN kN kN kN kN kN kN k
0.1
k OK 105.0 kN
319.0kN 0.92
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
NOMINAL LINKS BI-AXIAL , SLENDER, U NBRACED, COLUMN DESIGN Critical Case : 1 : Dead plus Live Part 2 of 2: with Myy Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
2784.3 k
.45x(500x400-6987)x25 + 0.95x6986.9x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(500x400-6987)x25 + 0.95x6986.9x460
OK
5224.7 k OK 5007.5 k
X-X Moments
Applied Moments (Mx1, Mx2) -18.2 kN.m, 30.7 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (5225 - 2784)/(5225 - 1084) < 1 au = βa • K • h 0.155, 1.000, 400 Madd= N • au 2784 x 62.1 Mi=fn(Mx1, Mx2) -18.2 kN.m, 30.7 kN.m M2+Madd, M nom 203.7 kN.m, 0.0 kN.m M nom=fn(N, exx) 2784.3 kN, 20.0 mm Design Moment
1.00 62.1 mm 173.0 kN.m 12.3 kN.m 173.0 kN.m 203.7 kN.m
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 86: D.O.C.K : OCT 2012 : F.O.O : K.M.M
Y-Y Moments Applied Moments (My1, My2) 65.7 kN.m, -109.9 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (5225 - 2784)/(5225 - 1070) < 1 au = βa • K • h 0.075, 1.000, 400 Madd= N • au 2784 x 37.3 Mi=fn(My1, My2) 65.7 kN.m, -109.9 kN.m M nom=fn(M2+Madd) 213.8 M nom=fn(N, eyy) 2784.3, 20.0 Design Moment
1.00 37.3 mm 103.9 kN.m 44.0 kN.m 55.7 kN.m 103.9 kN.m 213.8 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(203.7² + 213.8² ) atn(213.8/ 203.7)
295.3 kN.m 46.4 deg
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Bar group13:M13 fn(bars,d,ε%,,la,F) Bar group14:M14 fn(bars,d,ε%,,la,F) Bar group15:M15 fn(bars,d,ε%,,la,F) Bar group16:M16 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M16)
0.685, 638 mm, 500 mm, 437.26 mm, 140201 mm², 252.4 m 1 x 32, 547.4, -0.088, -176, -228.5, -141.9 1 x 32, 278.1, 0.127, 255, 40.9, 204.9 1 x 20, 484.2, -0.038, -75, -165.3, -23.6 1 x 20, 416.9, 0.016, 33, -97.9, 10.2 1 x 20, 349.6, 0.070, 140, -30.6, 44.1 1 x 20, 504.9, -0.054, -108, -185.9, -34.0 1 x 20, 458.0, -0.017, -33, -139.0, -10.4 1 x 20, 411.1, 0.021, 42, -92.1, 13.2 1 x 32, 359.8, 0.062, 124, -40.9, 99.7 1 x 32, 90.5, 0.278, 437, 228.5, 351.5 1 x 20, 288.4, 0.119, 238, 30.6, 74.9 1 x 20, 221.0, 0.173, 346, 97.9, 108.8 1 x 20, 153.7, 0.227, 437, 165.3, 137.3 1 x 20, 226.8, 0.168, 337, 92.1, 105.8 1 x 20, 179.9, 0.206, 412, 139.0, 129.4 1 x 20, 133.0, 0.244, 437, 185.9, 137.3 140201 x 0.45 x 25 -142+205-24+10+44-34-10+13+100+351+7 +109+137+106+129+137+1577-2784.3
Max Moment/Mu
1577.3 x (638 / 2 - 252.4) 105.0 + (32.4+8.4+3.9+-1.0+-1.3+6.3+1.4 + (-1.2+-4.1+80.3+2.3+10.7+22.7+9.7 + (18.0+25.5) 295.3 / 319.0
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
73.2 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
76.8 mm, 300 m
OK
32.4 8.4 3.9 -1.0 -1.3 6.3 1.4 -1.2 -4.1 80.3 2.3 10.7 22.7 9.7 18.0 25.5 1577.3
kN kN kN kN kN kN kN kN kN kN kN kN kN kN kN kN k
0.1
k OK 105.0 kN
319.0kN 0.92
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
Nominal links
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 87: D.O.C.K : OCT 2012 : F.O.O : K.M.M
COLUMN @ TYPE C7 LEVEL 8
Basic Data Design to
BS 8110: 199
Grades Fy, Fyv, Fcu
460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 400 mm deep column βy : for 600 mm wide column Lc=3300
Top: Shallow, Bottom: Shallow Top: Shallow, Bottom: Shallow Lox=3300-(700+700)/2 Loy=3300-(600+600)/2
1.50 1.50 2600 2700
LEX=3900.0 MM, LEX/H=9.8, EXX=20.0 MM LEY=4050.0 MM, LEY/B=6.8, EYY=20.0 MM BI-AXIAL , SHORT, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Part 1 of 2 with Mxx Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
233.1 k
.45x(600x400-1357)x25 + 0.95x1357.2x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-1357)x25 + 0.95x1357.2x460
OK Applied Moments (Mx1, Mx2) M nom=fn(N, exx) Design Moment
-99.9 kN.m, 92.2 kN.m 233.1 kN, 20.0 mm
3277.8 k OK 3009.3 k
X-X Moments 4.7 kN.m 99.9 kN.m
Y-Y Moments Applied Moments (My1, My2) Design Moment
-1.3 kN.m, 0.0 kN.m 1.3 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(99.9² + 1.3² ) atn(1.3/ 99.9)
99.9 kN.m 0.7 deg
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 88: D.O.C.K : OCT 2012 : F.O.O : K.M.M
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M12)
0.219, 408 mm, 600 mm, 89.42 mm, 45948 mm², 42.2 m 1 x 12, 353.1, -1.032, -437, -149.2, -49.4 1 x 12, 346.7, -1.007, -437, -142.8, -49.4 1 x 12, 350.9, -1.024, -437, -147.1, -49.4 1 x 12, 348.8, -1.015, -437, -144.9, -49.4 1 x 12, 255.8, -0.651, -437, -51.9, -49.4 1 x 12, 158.4, -0.270, -437, 45.5, -49.4 1 x 12, 61.1, 0.111, 222, 142.8, 25.1 1 x 12, 54.7, 0.136, 272, 149.2, 30.7 1 x 12, 59.0, 0.119, 238, 144.9, 27.0 1 x 12, 56.8, 0.128, 255, 147.1, 28.9 1 x 12, 249.3, -0.626, -437, -45.5, -49.4 1 x 12, 152.0, -0.245, -437, 51.9, -49.4 45948 x 0.45 x 25 -49-49-49-49-49-49+25+31+27+29-49-4 +517-233.1
Max Moment/Mu
516.9 x (408 / 2 - 42.2) 83.6 + (7.4+7.1+7.3+7.2+2.6+-2.2+3.6+4.6 + (3.9+4.2+2.2+-2.6) 99.9 / 128.8
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
428.6 mm, 240 m
100 As/bd, vc, vc' As/Svreq, Sv, Links Asvreq, Asvpvd
0.65%, 0.57 N/mm², 0.57 N/mm² 0 mm, 125 mm, 4 no 8 mm legs 0 mm², 201 mm²
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
5.6 mm, 360 m
OK
7.4 7.1 7.3 7.2 2.6 -2.2 3.6 4.6 3.9 4.2 2.2 -2.6 516.9
kN kN kN kN kN kN kN kN kN kN kN kN k
0.0
k OK 83.6 kN 128.8kN 0.77
X-X Shear Checks OK
links reqd. Link check
Nominal OK Y-Y Shear Checks OK
NOMINAL LINKS BI-AXIAL , SHORT, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Part 2 of 2: with Myy Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
233.1 k
.45x(600x400-1357)x25 + 0.95x1357.2x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-1357)x25 + 0.95x1357.2x460
OK Applied Moments (Mx1, Mx2) Design Moment
3277.8 k OK 3009.3 k
X-X Moments
-99.9 kN.m, 92.2 kN.m 99.9 kN.m
Y-Y Moments Applied Moments (My1, My2) M nom=fn(N, eyy) Design Moment
-1.3 kN.m, 0.0 kN.m 233.1, 20.0
4.7 kN.m 4.7 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(99.9² + 4.7² ) atn(4.7/ 99.9)
100.0 kN.m 2.7 deg
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
Job ref Sheet Made By Date Checked Approved
: Job Ref : Sheet Ref / 89: D.O.C.K : OCT 2012 : F.O.O : K.M.M
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M12)
0.235, 428 mm, 600 mm, 100.67 mm, 46019 mm², 51.9 m 1 x 12, 371.1, -0.940, -437, -157.3, -49.4 1 x 12, 348.1, -0.860, -437, -134.4, -49.4 1 x 12, 363.4, -0.914, -437, -149.7, -49.4 1 x 12, 355.8, -0.887, -437, -142.0, -49.4 1 x 12, 273.8, -0.602, -437, -60.1, -49.4 1 x 12, 176.6, -0.264, -437, 37.1, -49.4 1 x 12, 79.4, 0.074, 148, 134.4, 16.7 1 x 12, 56.5, 0.154, 307, 157.3, 34.8 1 x 12, 71.7, 0.101, 201, 142.0, 22.7 1 x 12, 64.1, 0.127, 254, 149.7, 28.8 1 x 12, 250.9, -0.522, -437, -37.1, -49.4 1 x 12, 153.7, -0.184, -369, 60.1, -41.7 46019 x 0.45 x 25 -49-49-49-49-49-49+17+35+23+29-49-4 +518-233.1
Max Moment/Mu
517.7 x (428 / 2 - 51.9) 83.8 + (7.8+6.6+7.4+7.0+3.0+-1.8+2.2+5.5 + (3.2+4.3+1.8+-2.5) 100.0 / 128.4
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
428.6 mm, 240 m
100 As/bd, vc, vc' As/Svreq, Sv, Links Asvreq, Asvpvd
0.65%, 0.57 N/mm², 0.57 N/mm² 0 mm, 125 mm, 4 no 8 mm legs 0 mm², 201 mm²
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
20 mm, 360 m
OK
7.8 6.6 7.4 7.0 3.0 -1.8 2.2 5.5 3.2 4.3 1.8 -2.5 517.7
kN kN kN kN kN kN kN kN kN kN kN kN k
-0.1
k OK 83.8 kN
128.4kN 0.77
X-X Shear Checks OK
links reqd. Link check
Nominal OK Y-Y Shear Checks OK
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 90: D.O.C.K : OCT 2012 : F.O.O : K.M.M
COLUMN @ TYPE C7 LEVEL 7
Basic Data Design to
BS 8110: 199
Grades Fy, Fyv, Fcu
460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 400 mm deep column βy : for 600 mm wide column Lc=3300
Top: Shallow, Bottom: Shallow Top: Shallow, Bottom: Shallow Lox=3300-(700+700)/2 Loy=3300-(600+600)/2
1.50 1.50 2600 2700
LEX=3900.0 MM, LEX/H=9.8, EXX=20.0 MM LEY=4050.0 MM, LEY/B=6.8, EYY=20.0 MM U NI-AXIAL , SHORT, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
560.0 k
.45x(600x400-2061)x25 + 0.95x2060.9x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-2061)x25 + 0.95x2060.9x460
OK M nom Design Moment
3577.4 k OK 3309.7 k
X-X Moments
11.2 122.2 kN.m
Moment Capacity Mu X-X Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp= 0 Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M6) Max Moment/Mu
0.334, 400 mm, 600 mm, 133.44 mm, 72058 mm², 60.0 m 2 x 12, 58.0, 0.198, 396, 142.0, 89.5 2 x 16, 340.0, -0.542, -437, -140.0, -175.7 2 x 12, 342.0, -0.547, -437, -142.0, -98.8 2 x 16, 60.0, 0.193, 385, 140.0, 154.9 2 x 16, 245.3, -0.293, -437, -45.3, -175.7 2 x 16, 154.7, -0.056, -111, 45.3, -44.8 72058 x 0.45 x 25 90 -176 -99 + 155 -176 -45 + 811 -560 810.7 x (400 / 2 - 60.0) 113.5 + (12.7+24.6+14.0+21.7+8.0+-2.0) 122.2 / 192.4
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
218.2 mm, 240 m
OK
12.7 kN 24.6 kN 14.0 kN 21.7 kN 8.0 kN -2.0 kN 810.7 k 0.0 k 113.5 kN 192.4kN 0.63
X-X Shear Checks OK
Nominal links
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 91: D.O.C.K : OCT 2012 : F.O.O : K.M.M
COLUMN @ TYPE C7 LEVEL 6
Basic Data Design to
BS 8110: 199
Grades Fy, Fyv, Fcu
460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 400 mm deep column βy : for 600 mm wide column Lc=3300
Top: Shallow, Bottom: Shallow Top: Shallow, Bottom: Shallow Lox=3300-(700+700)/2 Loy=3300-(600+600)/2
1.50 1.50 2600 2700
LEX=3900.0 MM, LEX/H=9.8, EXX=20.0 MM LEY=4050.0 MM, LEY/B=6.8, EYY=20.0 MM U NI-AXIAL , SHORT, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
946.9 k
.45x(600x400-1357)x25 + 0.95x1357.2x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-1357)x25 + 0.95x1357.2x460
OK M nom Design Moment
3277.8 k OK 3009.3 k
X-X Moments
18.9 129.3 kN.m
Moment Capacity Mu X-X Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp= 0 Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M4) Max Moment/Mu
0.416, 400 mm, 600 mm, 166.40 mm, 89856 mm², 74.9 m 4 x 12, 58.0, 0.228, 437, 142.0, 197.7 4 x 12, 342.0, -0.369, -437, -142.0, -197.7 2 x 12, 245.3, -0.166, -332, -45.3, -75.1 2 x 12, 154.7, 0.025, 49, 45.3, 11.2 89856 x 0.45 x 25 198 - 198 - 75 + 11 + 1011 - 946.9 1010.9 x (400 / 2 - 74.9) 126.5 + (28.1+28.1+3.4+0.5) 129.3 / 186.5
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
136.6 mm, 240 m
OK
28.1 kN 28.1 kN 3.4 kN 0.5 kN 1010.9 k 0.0 k 126.5 kN 186.5kN 0.69
X-X Shear Checks OK
Nominal links
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 92: D.O.C.K : OCT 2012 : F.O.O : K.M.M
COLUMN @ TYPE C7 LEVEL 5
Basic Data Design to
BS 8110: 199
Grades Fy, Fyv, Fcu
460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 400 mm deep column βy : for 600 mm wide column Lc=3300
Top: Shallow, Bottom: Shallow Top: Shallow, Bottom: Shallow Lox=3300-(700+700)/2 Loy=3300-(600+600)/2
1.50 1.50 2600 2700
LEX=3900.0 MM, LEX/H=9.8, EXX=20.0 MM LEY=4050.0 MM, LEY/B=6.8, EYY=20.0 MM U NI-AXIAL , SHORT, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
1309.9 k
.45x(600x400-1357)x25 + 0.95x1357.2x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-1357)x25 + 0.95x1357.2x460
OK M nom Design Moment
3277.8 k OK 3009.3 k
X-X Moments
26.2 98.3 kN.m
Moment Capacity Mu X-X Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp= 0
0.531, 400 mm, 600 mm, 212.54 mm, 114773 mm², 95.6 m 4 x 12, 54.0, 0.261, 437, 146.0, 197.7 4 x 12, 346.0, -0.220, -437, -146.0, -197.7 2 x 12, 246.7, -0.056, -112, -46.7, -25.4 2 x 12, 153.3, 0.098, 195, 46.7, 44.1 114773 x 0.45 x 25 198 - 198 - 25 + 44 + 1291 - 1309.9
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M4) Max Moment/Mu
1291.2 x (400 / 2 - 95.6) 134.7 + (28.9+28.9+1.2+2.1) 98.3 / 195.7
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
75 mm, 240 m
OK
28.9 28.9 1.2 2.1 1291.2 0.0
kN kN kN kN k k OK 134.7 kN 195.7kN 0.50
X-X Shear Checks OK
Nominal links
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 93: D.O.C.K : OCT 2012 : F.O.O : K.M.M
COLUMN @ TYPE C7 LEVEL 4
Basic Data Design to
BS 8110: 199
Grades Fy, Fyv, Fcu
460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 400 mm deep column βy : for 600 mm wide column Lc=3300
Top: Shallow, Bottom: Shallow Top: Shallow, Bottom: Shallow Lox=3300-(700+700)/2 Loy=3300-(600+600)/2
1.50 1.50 2600 2700
LEX=3900.0 MM, LEX/H=9.8, EXX=20.0 MM LEY=4050.0 MM, LEY/B=6.8, EYY=20.0 MM U NI-AXIAL , SHORT, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Axial Capacity Applied Axial N Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
.45x(600x400-1357)x25 + 0.95x1357.2x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-1357)x25 + 0.95x1357.2x460
OK M nom Design Moment
1652.8 k 3277.8 k OK 3009.3 k
X-X Moments
33.1 93.4 kN.m
Moment Capacity Mu X-X Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp= 0 Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M4) Max Moment/Mu
0.623, 400 mm, 600 mm, 249.40 mm, 134674 mm², 112.2 m 4 x 12, 54.0, 0.274, 437, 146.0, 197.7 4 x 12, 346.0, -0.136, -271, -146.0, -122.7 2 x 12, 246.7, 0.004, 8, -46.7, 1.7 2 x 12, 153.3, 0.135, 270, 46.7, 61.0 134674 x 0.45 x 25 198 - 123 + 2 + 61 + 1515 - 1652.8 1515.1 x (400 / 2 - 112.2) 133.0 + (28.9+17.9+-0.1+2.8) 93.4 / 182.5
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
56.5 mm, 240 m
OK
28.9 kN 17.9 kN -0.1 kN 2.8 kN 1515.1 k 0.0 k 133.0 kN 182.5kN 0.51
X-X Shear Checks OK
Nominal links
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 94: D.O.C.K : OCT 2012 : F.O.O : K.M.M
COLUMN @ TYPE C7 LEVEL 3
Basic Data Design to
BS 8110: 199
Grades Fy, Fyv, Fcu
460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 400 mm deep column βy : for 600 mm wide column Lc=3500
Top: Shallow, Bottom: Deep Top: Shallow, Bottom: Shallow Lox=3500-(700+950)/2 Loy=3500-(600+950)/2
1.30 1.50 2675 2725
LEX=3477.5 MM, LEX/H=8.7, EXX=20.0 MM LEY=4087.5 MM, LEY/B=6.8, EYY=20.0 MM U NI-AXIAL , SHORT, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Axial Capacity Applied Axial N Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
1978.6 k .45x(600x400-1357)x25 + 0.95x1357.2x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-1357)x25 + 0.95x1357.2x460
OK M nom Design Moment
3277.8 k OK 3009.3 k
X-X Moments
39.6 90.9 kN.m
Moment Capacity Mu X-X Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp= 0 Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M4) Max Moment/Mu
0.719, 400 mm, 600 mm, 287.79 mm, 155408 mm², 129.5 m 4 x 12, 54.0, 0.284, 437, 146.0, 197.7 4 x 12, 346.0, -0.071, -142, -146.0, -64.0 2 x 12, 246.7, 0.050, 100, -46.7, 22.6 2 x 12, 153.3, 0.164, 327, 46.7, 74.0 155408 x 0.45 x 25 198 - 64 + 23 + 74 + 1748 - 1978.6 1748.3 x (400 / 2 - 129.5) 123.2 + (28.9+9.4+-1.1+3.5) 90.9 / 163.9
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
45.9 mm, 240 m
OK
28.9 kN 9.4 kN -1.1 kN 3.5 kN 1748.3 k 0.0 k 123.2 kN 163.9kN 0.55
X-X Shear Checks OK
Nominal links
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 95: D.O.C.K : OCT 2012 : F.O.O : K.M.M
COLUMN @ TYPE C7 LEVEL 2
Basic Data Design to Grades Fy, Fyv, Fcu
BS 8110: 199 460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 400 mm deep column βy : for 600 mm wide column Lc=5000
Top: Deep, Bottom: Shallow Top: Shallow, Bottom: Shallow Lox=5000-(950+700)/2 Loy=5000-(950+600)/2
1.30 1.50 4175 4225
LEX=5427.5 MM, LEX/H=13.6, EXX=20.0 MM LEY=6337.5 MM, LEY/B=10.6, EYY=20.0 MM UNI-AXIAL , SLENDER, U NBRACED, COLUMN DESIGN Critical Case : 1 : Dead plus Live Axial Capacity Applied Axial N Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
.45x(600x400-2865)x25 + 0.95x2865.1x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-2865)x25 + 0.95x2865.1x460
OK
2400.0 k 3919.8 k OK 3653.1 k
X-X Moments
Applied Moments(M1, M2) 62.0 kN.m, -90.9 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (3920 - 2400)/(3920 - 1308) < 1 au = βa • K • h 0.092, 1.000, 400 Madd= N • au 2400 x 36.8 Initial Moment Mi=fn(M1,M2) 62.0 kN.m, -90.9 kN.m M2+Madd, M nom 179.3, 48.0 Design Moment
1.00 36.8 mm 88.4 kN.m 36.4 kN.m 179.3 kN.m
Moment Capacity Mu X-X Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp= 0 Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M6) Max Moment/Mu
0.761, 400 mm, 600 mm, 304.23 mm, 164284 mm², 136.9 m 2 x 20, 58.0, 0.283, 437, 142.0, 274.6 2 x 16, 344.0, -0.046, -92, -144.0, -36.8 2 x 20, 342.0, -0.043, -87, -142.0, -54.6 2 x 16, 56.0, 0.286, 437, 144.0, 175.7 2 x 16, 244.0, 0.069, 139, -44.0, 55.7 2 x 16, 156.0, 0.171, 341, 44.0, 137.1 164284 x 0.45 x 25 275 -37 -55 +176 +56 +137 +1848 -2400 1848.2 x (400 / 2 - 136.9) 116.6 + (39.0+5.3+7.8+25.3+-2.5+6.0) 179.3 / 197.5
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
74.7 mm, 240 m
OK
39.0 kN 5.3 kN 7.8 kN 25.3 kN -2.5 kN 6.0 kN 1848.2 k 0.0 k 116.6 kN 197.5kN 0.90
X-X Shear Checks OK
Nominal links
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 96: D.O.C.K : OCT 2012 : F.O.O : K.M.M
COLUMN @ TYPE C7 LEVEL 1
Basic Data Design to Grades Fy, Fyv, Fcu
BS 8110: 199 460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 400 mm deep column βy : for 600 mm wide column Lc=5000
Top: Shallow, Bottom: Shallow Top: Shallow, Bottom: Shallow Lox=5000-(700+0)/2 Loy=5000-(600+0)/2
1.50 1.50 4650 4700
LEX=6975.0 MM, LEX/H=17.4, EXX=20.0 MM LEY=7050.0 MM, LEY/B=11.8, EYY=20.0 MM SLENDER, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live
U NI-AXIAL ,
Axial Capacity Applied Axial N Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
.45x(600x400-5105)x25 + 0.95x5105.1x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-5105)x25 + 0.95x5105.1x460
OK
2927.7 k 4873.5 k OK 4609.2 k
X-X Moments
Applied Moments(M1, M2) -34.3 kN.m, 58.6 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (4873 - 2928)/(4873 - 1308) < 1 au = βa • K • h 0.152, 1.000, 400 Madd= N • au 2928 x 60.8 Initial Moment Mi=fn(M1,M2) -34.3 kN.m, 58.6 kN.m M2+Madd, M nom 236.6, 58.6 Design Moment
1.00 60.8 mm 178.0 kN.m 23.4 kN.m 236.6 kN.m
Moment Capacity Mu X-X Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp= 0 Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M6) Max Moment/Mu
0.780, 400 mm, 600 mm, 311.97 mm, 168463 mm², 140.4 m 2 x 25, 60.5, 0.282, 437, 139.5, 429.0 3 x 20, 342.0, -0.034, -67, -142.0, -63.5 2 x 25, 339.5, -0.031, -62, -139.5, -60.6 3 x 20, 58.0, 0.285, 437, 142.0, 411.9 2 x 20, 242.3, 0.078, 156, -42.3, 98.2 2 x 20, 157.7, 0.173, 346, 42.3, 217.5 168463 x 0.45 x 25 429 -64 -61 +412 +98 +218 +1895 -2927.7 1895.2 x (400 / 2 - 140.4) 113.0 + (59.8+9.0+8.5+58.5+-4.2+9.2) 236.6 / 253.8
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
80.8 mm, 240 m
OK
59.8 kN 9.0 kN 8.5 kN 58.5 kN -4.2 kN 9.2 kN 1895.2 k 0.0 k 113.0 kN 253.8kN 0.93
X-X Shear Checks OK
Nominal links
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 97: D.O.C.K : OCT 2012 : F.O.O : K.M.M
COLUMN @ TYPE C8 LEVEL 8
Basic Data Design to Grades Fy, Fyv, Fcu
BS 8110: 199 460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 400 mm deep column βy : for 600 mm wide column Lc=3300
Top: Shallow, Bottom: Shallow Top: Shallow, Bottom: Shallow Lox=3300-(700+700)/2 Loy=3300-(600+600)/2
1.50 1.50 2600 2700
LEX=3900.0 MM, LEX/H=9.8, EXX=20.0 MM LEY=4050.0 MM, LEY/B=6.8, EYY=20.0 MM U NI-AXIAL , SHORT, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Axial Capacity Applied Axial N Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
.45x(600x400-1357)x25 + 0.95x1357.2x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-1357)x25 + 0.95x1357.2x460
OK M nom Design Moment
55.7 k 3277.8 k OK 3009.3 k
Y-Y Moments
1.1 150.4 kN.m
Moment Capacity Mu Y-Y Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp= 0
0.139, 600 mm, 400 mm, 83.65 mm, 30115 mm², 37.6 m 4 x 12, 54.0, 0.124, 248, 246.0, 112.2 4 x 12, 546.0, -1.934, -437, -246.0, -197.7 2 x 12, 380.0, -1.240, -437, -80.0, -98.8 2 x 12, 220.0, -0.570, -437, 80.0, -98.8 30115 x 0.45 x 25 112 - 198 - 99 - 99 + 339 - 55.7
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M4) Max Moment/Mu
338.8 x (600 / 2 - 37.6) 88.9 + (27.6+48.6+7.9+-7.9) 150.4 / 165.1
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
2700.2 mm, 360 m
100 As/bd, vc, vc' As/Svreq, Sv, Links Asvreq, Asvpvd OK
0.62%, 0.54 N/mm², 0.54 N/mm² 0 mm, 125 mm, 4 no 8 mm legs 0 mm², 201 mm²
OK
27.6 48.6 7.9 -7.9 338.8 0.0
kN kN kN kN k k OK 88.9 kN 165.1kN 0.91
Y-Y Shear Checks OK
links reqd. Link check 0.00
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 98: D.O.C.K : OCT 2012 : F.O.O : K.M.M
COLUMN @ TYPE C8 LEVEL 7
Basic Data Design to Grades Fy, Fyv, Fcu
BS 8110: 199 460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 400 mm deep column βy : for 600 mm wide column Lc=3300
Top: Shallow, Bottom: Shallow Top: Shallow, Bottom: Shallow Lox=3300-(700+700)/2 Loy=3300-(600+600)/2
1.50 1.50 2600 2700
LEX=3900.0 MM, LEX/H=9.8, EXX=20.0 MM LEY=4050.0 MM, LEY/B=6.8, EYY=20.0 MM U NI-AXIAL , SHORT, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Axial Capacity Applied Axial N Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
.45x(600x400-1357)x25 + 0.95x1357.2x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-1357)x25 + 0.95x1357.2x460
OK M nom Design Moment
131.2 k 3277.8 k OK 3009.3 k
Y-Y Moments
2.6 88.6 kN.m
Moment Capacity Mu Y-Y Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp= 0 Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M4) Max Moment/Mu
0.163, 600 mm, 400 mm, 98.08 mm, 35309 mm², 44.1 m 4 x 12, 58.0, 0.143, 286, 242.0, 129.4 4 x 12, 542.0, -1.584, -437, -242.0, -197.7 2 x 12, 378.7, -1.001, -437, -78.7, -98.8 2 x 12, 221.3, -0.440, -437, 78.7, -98.8 35309 x 0.45 x 25 129 - 198 - 99 - 99 + 397 - 131.2 397.2 x (600 / 2 - 44.1) 101.6 + (31.3+47.8+7.8+-7.8) 88.6 / 180.8
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
675.3 mm, 360 m
100 As/bd, vc, vc' As/Svreq, Sv, Links Asvreq, Asvpvd
0.63%, 0.54 N/mm², 0.54 N/mm² 0 mm, 125 mm, 4 no 12 mm legs 0 mm², 452 mm²
OK
31.3 kN 47.8 kN 7.8 kN -7.8 kN 397.2 k 0.0 k 101.6 kN 180.8kN 0.49
Y-Y Shear Checks OK
links reqd. Link check 0.00 OK
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 99: D.O.C.K : OCT 2012 : F.O.O : K.M.M
COLUMN @ TYPE C8 LEVEL 6
Basic Data Design to Grades Fy, Fyv, Fcu
BS 8110: 199 460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 400 mm deep column βy : for 600 mm wide column Lc=3300
Top: Shallow, Bottom: Shallow Top: Shallow, Bottom: Shallow Lox=3300-(700+700)/2 Loy=3300-(600+600)/2
1.50 1.50 2600 2700
LEX=3900.0 MM, LEX/H=9.8, EXX=20.0 MM LEY=4050.0 MM, LEY/B=6.8, EYY=20.0 MM U NI-AXIAL , SHORT, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Axial Capacity Applied Axial N Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
.45x(600x400-1357)x25 + 0.95x1357.2x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-1357)x25 + 0.95x1357.2x460
OK M nom Design Moment
259.3 k 3277.8 k OK 3009.3 k
Y-Y Moments
5.2 132.4 kN.m
Moment Capacity Mu Y-Y Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp= 0 Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M4) Max Moment/Mu
0.202, 600 mm, 400 mm, 120.95 mm, 43542 mm², 54.4 m 4 x 12, 58.0, 0.182, 364, 242.0, 164.8 4 x 12, 542.0, -1.218, -437, -242.0, -197.7 2 x 12, 378.7, -0.746, -437, -78.7, -98.8 2 x 12, 221.3, -0.290, -437, 78.7, -98.8 43542 x 0.45 x 25 165 - 198 - 99 - 99 + 490 - 259.3 489.8 x (600 / 2 - 54.4) 120.3 + (39.9+47.8+7.8+-7.8) 132.4 / 208.0
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
510.6 mm, 360 m
100 As/bd, vc, vc' As/Svreq, Sv, Links Asvreq, Asvpvd
0.63%, 0.54 N/mm², 0.54 N/mm² 0 mm, 125 mm, 4 no 12 mm legs 0 mm², 452 mm²
OK
39.9 kN 47.8 kN 7.8 kN -7.8 kN 489.8 k 0.0 k 120.3 kN 208.0kN 0.63
Y-Y Shear Checks OK
links reqd. Link check 0.00 OK
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 100: D.O.C.K : OCT 2012 : F.O.O : K.M.M
COLUMN @ TYPE C8 LEVEL 5
Basic Data Design to Grades Fy, Fyv, Fcu
BS 8110: 199 460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 400 mm deep column βy : for 600 mm wide column Lc=3300
Top: Shallow, Bottom: Shallow Top: Shallow, Bottom: Shallow Lox=3300-(700+700)/2 Loy=3300-(600+600)/2
1.50 1.50 2600 2700
LEX=3900.0 MM, LEX/H=9.8, EXX=20.0 MM LEY=4050.0 MM, LEY/B=6.8, EYY=20.0 MM BI-AXIAL , SHORT, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Part 1 of 2 with Mxx Nominal considered Axial Capacity Applied Axial N Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
.45x(600x400-1357)x25 + 0.95x1357.2x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-1357)x25 + 0.95x1357.2x460
OK Applied Moments (Mx1, Mx2) M nom=fn(N, exx) Design Moment
402.8 k 3277.8 k OK 3009.3 k
X-X Moments
1.5 kN.m, 0.0 kN.m 402.8 kN, 20.0 mm
8.1 kN.m 8.1 kN.m
Y-Y Moments Applied Moments (My1, My2) Design Moment
-136.4 kN.m, 126.6 kN.m 136.4 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(8.1² + 136.4² ) atn(136.4/ 8.1)
136.6 kN.m 86.6 deg
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F)
0.254, 623 mm, 600 mm, 157.87 mm, 52206 mm², 76.8 m 1 x 12, 565.5, -0.904, -437, -254.2, -49.4 1 x 12, 74.3, 0.185, 371, 237.0, 41.9 1 x 12, 401.7, -0.541, -437, -90.5, -49.4 1 x 12, 238.0, -0.178, -355, 73.2, -40.2 1 x 12, 559.7, -0.891, -437, -248.4, -49.4 1 x 12, 554.0, -0.878, -437, -242.7, -49.4 1 x 12, 548.2, -0.865, -437, -237.0, -49.4 1 x 12, 57.1, 0.223, 437, 254.2, 49.4 1 x 12, 384.5, -0.502, -437, -73.2, -49.4 1 x 12, 220.8, -0.140, -279, 90.5, -31.6 1 x 12, 68.6, 0.198, 396, 242.7, 44.8
12.6 9.9 4.5 -2.9 12.3 12.0 11.7 12.6 3.6 -2.9 10.9
kN kN kN kN kN kN kN kN kN kN kN
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 101: D.O.C.K : OCT 2012 : F.O.O : K.M.M
Bar group12:M12 fn(bars,d,ε%,,la,F) 1 x 12, 62.8, 0.211, 421, 248.4, 47.7 Concrete Fc=(Ac•.45•fcu) 52206 x 0.45 x 25 F Equlibrum (Ft) + FC - Fapp = 0 -49+42-49-40-49-49-49+49-49-32+45+4 +587-402.8 Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M12) Max Moment/Mu
587.3 x (623 / 2 - 76.8) 137.7 + (12.6+9.9+4.5+-2.9+12.3+12.0+11.7 + (12.6+3.6+-2.9+10.9+11.8) 136.6 / 233.8
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
20 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
338.6 mm, 360 m
OK
11.8 kN 587.3 k 0.0
k OK 137.7 kN 233.8kN 0.58
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
NOMINAL LINKS BI-AXIAL , SHORT, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Part 2 of 2: with Myy Nominal considered Axial Capacity Applied Axial N Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
.45x(600x400-1357)x25 + 0.95x1357.2x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-1357)x25 + 0.95x1357.2x460
OK Applied Moments (Mx1, Mx2) Design Moment
402.8 k 3277.8 k OK 3009.3 k
X-X Moments
1.5 kN.m, 0.0 kN.m 1.5 kN.m
Y-Y Moments Applied Moments (My1, My2) M nom=fn(N, eyy) Design Moment
-136.4 kN.m, 126.6 kN.m 402.8, 20.0
8.1 kN.m 136.4 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(1.5² + 136.4² ) atn(136.4/ 1.5)
136.4 kN.m 89.4 deg
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M12)
0.243, 604 mm, 600 mm, 146.58 mm, 51893 mm², 67.1 m 1 x 12, 549.8, -0.963, -437, -247.6, -49.4 1 x 12, 57.8, 0.212, 424, 244.4, 47.9 1 x 12, 385.8, -0.571, -437, -83.6, -49.4 1 x 12, 221.8, -0.180, -359, 80.4, -40.6 1 x 12, 548.7, -0.960, -437, -246.5, -49.4 1 x 12, 547.6, -0.958, -437, -245.5, -49.4 1 x 12, 546.6, -0.955, -437, -244.4, -49.4 1 x 12, 54.6, 0.220, 437, 247.6, 49.4 1 x 12, 382.6, -0.563, -437, -80.4, -49.4 1 x 12, 218.6, -0.172, -344, 83.6, -38.9 1 x 12, 56.7, 0.215, 429, 245.5, 48.5 1 x 12, 55.7, 0.217, 434, 246.5, 49.1 51893 x 0.45 x 25 -49+48-49-41-49-49-49+49-49-39+49+4 +584-402.8
583.8 x (604 / 2 - 67.1) 137.3 + (12.2+11.7+4.1+-3.3+12.2+12.1+12.1
12.2 11.7 4.1 -3.3 12.2 12.1 12.1 12.2 4.0 -3.3 11.9 12.1 583.8
kN kN kN kN kN kN kN kN kN kN kN kN k
0.0
k
OK 137.3 kN
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
Max Moment/Mu
Job ref Sheet Made By Date Checked Approved
+ (12.2+4.0+-3.3+11.9+12.1) 136.4 / 235.5
OK App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
3.7 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
338.6 mm, 360 m
: Job Ref : Sheet Ref / 102: D.O.C.K : OCT 2012 : F.O.O : K.M.M
235.5kN 0.57
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
Nominal links
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 103: D.O.C.K : OCT 2012 : F.O.O : K.M.M
COLUMN @ TYPE C8 LEVEL 4
Basic Data Design to
BS 8110: 199
Grades Fy, Fyv, Fcu
460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 400 mm deep column βy : for 600 mm wide column Lc=3300
Top: Shallow, Bottom: Shallow Top: Shallow, Bottom: Shallow Lox=3300-(700+700)/2 Loy=3300-(600+600)/2
1.50 1.50 2600 2700
LEX=3900.0 MM, LEX/H=9.8, EXX=20.0 MM LEY=4050.0 MM, LEY/B=6.8, EYY=20.0 MM BI-AXIAL , SHORT, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Part 1 of 2 with Mxx Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
531.3 k
.45x(600x400-1357)x25 + 0.95x1357.2x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-1357)x25 + 0.95x1357.2x460
OK Applied Moments (Mx1, Mx2) M nom=fn(N, exx) Design Moment
1.3 kN.m, 0.0 kN.m 531.3 kN, 20.0 mm
3277.8 k OK 3009.3 k
X-X Moments 10.6 kN.m 10.6 kN.m
Y-Y Moments Applied Moments (My1, My2) Design Moment
-125.9 kN.m, 114.0 kN.m 125.9 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(10.6² + 125.9² ) atn(125.9/ 10.6)
126.3 kN.m 85.2 deg
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 104: D.O.C.K : OCT 2012 : F.O.O : K.M.M
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M12)
0.294, 632 mm, 600 mm, 185.76 mm, 60358 mm², 91.7 m 1 x 12, 573.2, -0.730, -437, -257.4, -49.4 1 x 12, 82.9, 0.194, 388, 232.8, 43.8 1 x 12, 409.7, -0.422, -437, -94.0, -49.4 1 x 12, 246.3, -0.114, -228, 69.4, -25.8 1 x 12, 565.0, -0.715, -437, -249.2, -49.4 1 x 12, 556.8, -0.699, -437, -241.0, -49.4 1 x 12, 548.6, -0.684, -437, -232.8, -49.4 1 x 12, 58.4, 0.240, 437, 257.4, 49.4 1 x 12, 385.2, -0.376, -437, -69.4, -49.4 1 x 12, 221.8, -0.068, -136, 94.0, -15.3 1 x 12, 74.7, 0.209, 418, 241.0, 47.3 1 x 12, 66.5, 0.225, 437, 249.2, 49.4 60358 x 0.45 x 25 -49+44-49-26-49-49-49+49-49-15+47+4 +679-531.3
Max Moment/Mu
679.0 x (632 / 2 - 91.7) 152.1 + (12.7+10.2+4.6+-1.8+12.3+11.9+11.5 + (12.7+3.4+-1.4+11.4+12.3) 126.3 / 252.1
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
20 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
237 mm, 360 m
OK
12.7 10.2 4.6 -1.8 12.3 11.9 11.5 12.7 3.4 -1.4 11.4 12.3 679.0
kN kN kN kN kN kN kN kN kN kN kN kN k
0.0
k OK 152.1 kN 252.1kN 0.50
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
NOMINAL LINKS BI-AXIAL , SHORT, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Part 2 of 2: with Myy Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
531.3 k
.45x(600x400-1357)x25 + 0.95x1357.2x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-1357)x25 + 0.95x1357.2x460
OK Applied Moments (Mx1, Mx2) Design Moment
3277.8 k OK 3009.3 k
X-X Moments
1.3 kN.m, 0.0 kN.m 1.3 kN.m
Y-Y Moments Applied Moments (My1, My2) M nom=fn(N, eyy) Design Moment
-125.9 kN.m, 114.0 kN.m 531.3, 20.0
10.6 kN.m 125.9 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(1.3² + 125.9² ) atn(125.9/ 1.3)
125.9 kN.m 89.4 deg
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
Job ref Sheet Made By Date Checked Approved
: Job Ref : Sheet Ref / 105: D.O.C.K : OCT 2012 : F.O.O : K.M.M
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M12)
0.281, 604 mm, 600 mm, 169.52 mm, 60206 mm², 77.3 m 1 x 12, 549.5, -0.785, -437, -247.5, -49.4 1 x 12, 57.6, 0.231, 437, 244.5, 49.4 1 x 12, 385.6, -0.446, -437, -83.5, -49.4 1 x 12, 221.6, -0.107, -215, 80.5, -24.3 1 x 12, 548.5, -0.783, -437, -246.5, -49.4 1 x 12, 547.5, -0.780, -437, -245.5, -49.4 1 x 12, 546.5, -0.778, -437, -244.5, -49.4 1 x 12, 54.6, 0.237, 437, 247.5, 49.4 1 x 12, 382.5, -0.440, -437, -80.5, -49.4 1 x 12, 218.5, -0.101, -202, 83.5, -22.9 1 x 12, 56.6, 0.233, 437, 245.5, 49.4 1 x 12, 55.6, 0.235, 437, 246.5, 49.4 60206 x 0.45 x 25 -49+49-49-24-49-49-49+49-49-23+49+4 +677-531.3
Max Moment/Mu
677.3 x (604 / 2 - 77.3) 152.2 + (12.2+12.1+4.1+-2.0+12.2+12.1+12.1 + (12.2+4.0+-1.9+12.1+12.2) 125.9 / 253.7
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
2.4 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
237 mm, 360 m
OK
12.2 12.1 4.1 -2.0 12.2 12.1 12.1 12.2 4.0 -1.9 12.1 12.2 677.3
kN kN kN kN kN kN kN kN kN kN kN kN k
0.0
k OK 152.2 kN 253.7kN 0.49
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
Nominal links
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 106: D.O.C.K : OCT 2012 : F.O.O : K.M.M
COLUMN @ TYPE C8 LEVEL 3
Basic Data Design to Grades Fy, Fyv, Fcu
BS 8110: 199 460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 400 mm deep column βy : for 600 mm wide column Lc=3500
Top: Shallow, Bottom: Deep Top: Shallow, Bottom: Shallow Lox=3500-(700+950)/2 Loy=3500-(600+950)/2
1.30 1.50 2675 2725
LEX=3477.5 MM, LEX/H=8.7, EXX=20.0 MM LEY=4087.5 MM, LEY/B=6.8, EYY=20.0 MM U NI-AXIAL , SHORT, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Axial Capacity Applied Axial N Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
.45x(600x400-1357)x25 + 0.95x1357.2x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-1357)x25 + 0.95x1357.2x460
OK M nom Design Moment
644.1 k 3277.8 k OK 3009.3 k
Y-Y Moments
12.9 125.4 kN.m
Moment Capacity Mu Y-Y Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp= 0 Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M4) Max Moment/Mu App. Shear Vy, v, v max
0.316, 600 mm, 400 mm, 189.69 mm, 68288 mm², 85.4 m 4 x 12, 54.0, 0.250, 437, 246.0, 197.7 4 x 12, 546.0, -0.657, -437, -246.0, -197.7 2 x 12, 380.0, -0.351, -437, -80.0, -98.8 2 x 12, 220.0, -0.056, -112, 80.0, -25.3 68288 x 0.45 x 25 198 - 198 - 99 - 25 + 768 - 644.1 768.2 x (600 / 2 - 85.4) 164.9 + (48.6+48.6+7.9+-2.0) 125.4 / 268.0 0 kN, 0 N/mm², 4 N/mm²
48.6 kN 48.6 kN 7.9 kN -2.0 kN 768.2 k 0.0 k 164.9 kN 268.0kN 0.46
OK M/N, 0.6b
194.7 mm, 360 m Nominal links
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 107: D.O.C.K : OCT 2012 : F.O.O : K.M.M
COLUMN @ TYPE C8 LEVEL 2
Basic Data Design to Grades Fy, Fyv, Fcu
BS 8110: 199 460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 400 mm deep column βy : for 600 mm wide column Lc=5000
Top: Deep, Bottom: Shallow Top: Shallow, Bottom: Shallow Lox=5000-(950+700)/2 Loy=5000-(950+600)/2
1.30 1.50 4175 4225
LEX=5427.5 MM, LEX/H=13.6, EXX=20.0 MM LEY=6337.5 MM, LEY/B=10.6, EYY=20.0 MM BI-AXIAL , SLENDER, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Part 1 of 2 with Mxx Nominal considered Axial Capacity Applied Axial N Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
.45x(600x400-2413)x25 + 0.95x2412.7x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-2413)x25 + 0.95x2412.7x460
OK Applied Moments (Mx1, Mx2) 0.0 kN.m, 1.5 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (3727 - 779)/(3727 - 1316) < 1 au = βa • K • h 0.092, 1.000, 400 Madd= N • au 779 x 36.8 Mi=fn(Mx1, Mx2) 0.0 kN.m, 1.5 kN.m M2+Madd, M nom 30.2 kN.m, 15.6 kN.m M nom=fn(N, exx) 779.2 kN, 20.0 mm Design Moment
779.2 k 3727.2 k OK 3459.9 k
X-X Moments 1.00 36.8 mm 28.7 kN.m 0.9 kN.m 28.7 kN.m 30.2 kN.m
Y-Y Moments Applied Moments (My1, My2) -86.4 kN.m, 81.8 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (3727 - 779)/(3727 - 1393) < 1 au = βa • K • h 0.056, 1.000, 400 Madd= N • au 779 x 33.5 Mi=fn(My1, My2) -86.4 kN.m, 81.8 kN.m M nom=fn(M2+Madd) 112.5 M nom=fn(N, eyy) 779.2, 20.0 Design Moment
1.00 33.5 mm 26.1 kN.m 34.6 kN.m 0.0 kN.m 26.1 kN.m 112.5 kN.m
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 108: D.O.C.K : OCT 2012 : F.O.O : K.M.M
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(30.2² + 112.5² ) atn(112.5/ 30.2)
116.5 kN.m 75.0 deg
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) Equlibrum (Ft) + FC - Fapp= 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M12)
0.409, 683 mm, 600 mm, 279.18 mm, 82589 mm², 149.3 m 1 x 16, 614.6, -0.420, -437, -273.0, -87.9 1 x 16, 143.3, 0.170, 341, 198.3, 68.5 1 x 16, 457.5, -0.224, -437, -115.9, -87.9 1 x 16, 300.4, -0.027, -53, 41.2, -10.7 1 x 16, 589.7, -0.389, -437, -248.1, -87.9 1 x 16, 564.8, -0.358, -437, -223.2, -87.9 1 x 16, 539.9, -0.327, -437, -198.3, -87.9 1 x 16, 68.6, 0.264, 437, 273.0, 87.9 1 x 16, 382.8, -0.130, -260, -41.2, -52.2 1 x 16, 225.7, 0.067, 134, 115.9, 27.0 1 x 16, 118.4, 0.202, 403, 223.2, 81.1 1 x 16, 93.5, 0.233, 437, 248.1, 87.9 82589 x 0.45 x 25 -88+69-88-11-88-88-88+88-52+27+81+8 +929-779.2
Max Moment/Mu
929.1 x (683 / 2 - 149.3) 178.7 + (24.0+13.6+10.2+-0.4+21.8+19.6+17.4 + (24.0+2.2+3.1+18.1+21.8) 116.5 / 354.0
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
38.7 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
144.4 mm, 360 m
OK
24.0 13.6 10.2 -0.4 21.8 19.6 17.4 24.0 2.2 3.1 18.1 21.8 929.1
kN kN kN kN kN kN kN kN kN kN kN kN k
-0.1
k OK 178.7 kN 354.0kN 0.32
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
NOMINAL LINKS BI-AXIAL , SLENDER, U NBRACED, COLUMN DESIGN Critical Case : 1 : Dead plus Live Part 2 of 2: with Myy Nominal considered Axial Capacity Applied Axial N Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
.45x(600x400-2413)x25 + 0.95x2412.7x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-2413)x25 + 0.95x2412.7x460
OK Applied Moments (Mx1, Mx2) 0.0 kN.m, 1.5 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (3727 - 779)/(3727 - 1316) < 1 au = βa • K • h 0.092, 1.000, 400 Madd= N • au 779 x 36.8 Mi=fn(Mx1, Mx2) 0.0 kN.m, 1.5 kN.m M2+Madd, M nom 30.2 kN.m, 0.0 kN.m M nom=fn(N, exx) 779.2 kN, 20.0 mm Design Moment
779.2 k 3727.2 k OK 3459.9 k
X-X Moments 1.00 36.8 mm 28.7 kN.m 0.9 kN.m 28.7 kN.m 30.2 kN.m
Y-Y Moments Applied Moments (My1, My2) -86.4 kN.m, 81.8 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (3727 - 779)/(3727 - 1393) < 1 au = βa • K • h 0.056, 1.000, 400 Madd= N • au 779 x 33.5 Mi=fn(My1, My2) -86.4 kN.m, 81.8 kN.m M nom=fn(M2+Madd) 112.5
1.00 33.5 mm 26.1 kN.m 34.6 kN.m 15.6 kN.m
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected], M nom=fn(N, eyy) Design Moment
Job ref Sheet Made By Date Checked Approved
: Job Ref : Sheet Ref / 109: D.O.C.K : OCT 2012 : F.O.O : K.M.M
779.2, 20.0
26.1 kN.m 112.5 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(30.2² + 112.5² ) atn(112.5/ 30.2)
116.5 kN.m 75.0 deg
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M12)
0.409, 683 mm, 600 mm, 279.18 mm, 82589 mm², 149.3 m 1 x 16, 614.6, -0.420, -437, -273.0, -87.9 1 x 16, 143.3, 0.170, 341, 198.3, 68.5 1 x 16, 457.5, -0.224, -437, -115.9, -87.9 1 x 16, 300.4, -0.027, -53, 41.2, -10.7 1 x 16, 589.7, -0.389, -437, -248.1, -87.9 1 x 16, 564.8, -0.358, -437, -223.2, -87.9 1 x 16, 539.9, -0.327, -437, -198.3, -87.9 1 x 16, 68.6, 0.264, 437, 273.0, 87.9 1 x 16, 382.8, -0.130, -260, -41.2, -52.2 1 x 16, 225.7, 0.067, 134, 115.9, 27.0 1 x 16, 118.4, 0.202, 403, 223.2, 81.1 1 x 16, 93.5, 0.233, 437, 248.1, 87.9 82589 x 0.45 x 25 -88+69-88-11-88-88-88+88-52+27+81+8 +929-779.2
Max Moment/Mu
929.1 x (683 / 2 - 149.3) 178.7 + (24.0+13.6+10.2+-0.4+21.8+19.6+17.4 + (24.0+2.2+3.1+18.1+21.8) 116.5 / 354.0
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
38.7 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
144.4 mm, 360 m
OK
24.0 13.6 10.2 -0.4 21.8 19.6 17.4 24.0 2.2 3.1 18.1 21.8 929.1
kN kN kN kN kN kN kN kN kN kN kN kN k
-0.1
k OK 178.7 kN 354.0kN 0.32
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
Nominal links
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
: Job Ref : Sheet Ref / 110: D.O.C.K : OCT 2012 : F.O.O : K.M.M
COLUMN @ TYPE C8 LEVEL 1
Basic Data Design to
BS 8110: 199
Grades Fy, Fyv, Fcu
460 N/mm², 460 N/mm², 25 N/mm
Restraint Conditions and Effective Lengths βx : for 400 mm deep column βy : for 600 mm wide column Lc=5000
Top: Shallow, Bottom: Shallow Top: Shallow, Bottom: Shallow Lox=5000-(700+0)/2 Loy=5000-(600+0)/2
1.50 1.50 4650 4700
LEX=6975.0 MM, LEX/H=17.4, EXX=20.0 MM LEY=7050.0 MM, LEY/B=11.8, EYY=20.0 MM BI-AXIAL , SLENDER, UNBRACED, COLUMN D ESIGN Critical Case : 1 : Dead plus Live Part 1 of 2 with Mxx Nominal considered Axial Capacity Applied Axial N
Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
963.8 k
.45x(600x400-3770)x25 + 0.95x3769.9x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-3770)x25 + 0.95x3769.9x460
OK Applied Moments (Mx1, Mx2) 0.0 kN.m, 2.0 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (4305 - 964)/(4305 - 1321) < 1 au = βa • K • h 0.152, 1.000, 400 Madd= N • au 964 x 60.8 Mi=fn(Mx1, Mx2) 0.0 kN.m, 2.0 kN.m M2+Madd, M nom 60.6 kN.m, 19.3 kN.m M nom=fn(N, exx) 963.8 kN, 20.0 mm Design Moment
4305.0 k OK 4039.3 k
X-X Moments 1.00 60.8 mm 58.6 kN.m 1.2 kN.m 58.6 kN.m 60.6 kN.m
Y-Y Moments Applied Moments (My1, My2) -36.2 kN.m, 64.4 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (4305 - 964)/(4305 - 1367) < 1
1.00
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected], au = βa • K • h Madd= N • au Mi=fn(My1, My2) M nom=fn(M2+Madd) M nom=fn(N, eyy) Design Moment
: Job Ref : Sheet Ref / 111: D.O.C.K : OCT 2012 : F.O.O : K.M.M
0.069, 1.000, 400 964 x 41.4 -36.2 kN.m, 64.4 kN.m 104.3 963.8, 20.0
41.4 mm 39.9 kN.m 25.8 kN.m 0.0 kN.m 39.9 kN.m 104.3 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(60.6² + 104.3² ) atn(104.3/ 60.6)
120.6 kN.m 59.8 deg
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0
Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M12)
0.472, 720 mm, 600 mm, 339.70 mm, 94952 mm², 194.9 m 1 x 20, 640.5, -0.310, -437, -280.6, -137.3 1 x 20, 222.0, 0.121, 243, 137.9, 76.2 1 x 20, 501.0, -0.166, -332, -141.1, -104.4 1 x 20, 361.5, -0.022, -45, -1.6, -14.1 1 x 20, 592.9, -0.261, -437, -233.0, -137.3 1 x 20, 545.3, -0.212, -424, -185.5, -133.1 1 x 20, 497.8, -0.163, -326, -137.9, -102.3 1 x 20, 79.3, 0.268, 437, 280.6, 137.3 1 x 20, 358.3, -0.019, -38, 1.6, -12.0 1 x 20, 218.8, 0.125, 249, 141.1, 78.3 1 x 20, 174.4, 0.170, 341, 185.5, 107.0 1 x 20, 126.8, 0.219, 437, 233.0, 137.3 94952 x 0.45 x 25 -137+76-104-14-137-133-102+137-12+7 +107+137+1068-963.8
Max Moment/Mu
1068.2 x (720 / 2 - 194.9) 176.2 + (38.5+10.5+14.7+0.0+32.0+24.7+14.1 + (38.5+0.0+11.0+19.8+32.0) 120.6 / 412.2
App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
62.9 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
108.2 mm, 360 m
OK
38.5 10.5 14.7 0.0 32.0 24.7 14.1 38.5 0.0 11.0 19.8 32.0 1068.2
kN kN kN kN kN kN kN kN kN kN kN kN k
-0.1
k OK 176.2 kN 412.2kN 0.29
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
NOMINAL LINKS BI-AXIAL , SLENDER, U NBRACED, COLUMN DESIGN Critical Case : 1 : Dead plus Live Part 2 of 2: with Myy Nominal considered Axial Capacity Applied Axial N Nuz=.45•(B•H-acs)•fcu + .95•asc•fy
.45x(600x400-3770)x25 + 0.95x3769.9x460
Ncap=.9•.45•(B•H-acs)•fcu + .95•asc•fy.9x.45x(600x400-3770)x25 + 0.95x3769.9x460
OK Applied Moments (Mx1, Mx2) 0.0 kN.m, 2.0 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (4305 - 964)/(4305 - 1321) < 1 au = βa • K • h 0.152, 1.000, 400 Madd= N • au 964 x 60.8 Mi=fn(Mx1, Mx2) 0.0 kN.m, 2.0 kN.m M2+Madd, M nom 60.6 kN.m, 0.0 kN.m M nom=fn(N, exx) 963.8 kN, 20.0 mm Design Moment
963.8 k 4305.0 k OK 4039.3 k
X-X Moments 1.00 60.8 mm 58.6 kN.m 1.2 kN.m 58.6 kN.m 60.6 kN.m
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
Job ref Sheet Made By Date Checked Approved
: Job Ref : Sheet Ref / 112: D.O.C.K : OCT 2012 : F.O.O : K.M.M
Y-Y Moments Applied Moments (My1, My2) -36.2 kN.m, 64.4 kN.m K = Kmin > (Nuz - N)/(Nuz - Nbal) < 1 1.00 > (4305 - 964)/(4305 - 1367) < 1 au = βa • K • h 0.069, 1.000, 400 Madd= N • au 964 x 41.4 Mi=fn(My1, My2) -36.2 kN.m, 64.4 kN.m M nom=fn(M2+Madd) 104.3 M nom=fn(N, eyy) 963.8, 20.0 Design Moment
1.00 41.4 mm 39.9 kN.m 25.8 kN.m 19.3 kN.m 39.9 kN.m 104.3 kN.m
Resultant Design Moment M=sqr(Mx² + My²) θ = atn(My / Mx)
sqr(60.6² + 104.3² ) atn(104.3/ 60.6)
120.6 kN.m 59.8 deg
Moment Capacity Design Data X/h, h, b, X, Ac, Ybar Bar group1:M1 fn(bars,d,ε%,,la,F) Bar group2:M2 fn(bars,d,ε%,,la,F) Bar group3:M3 fn(bars,d,ε%,,la,F) Bar group4:M4 fn(bars,d,ε%,,la,F) Bar group5:M5 fn(bars,d,ε%,,la,F) Bar group6:M6 fn(bars,d,ε%,,la,F) Bar group7:M7 fn(bars,d,ε%,,la,F) Bar group8:M8 fn(bars,d,ε%,,la,F) Bar group9:M9 fn(bars,d,ε%,,la,F) Bar group10:M10 fn(bars,d,ε%,,la,F) Bar group11:M11 fn(bars,d,ε%,,la,F) Bar group12:M12 fn(bars,d,ε%,,la,F) Concrete Fc=(Ac•.45•fcu) F Equlibrum (Ft) + FC - Fapp = 0 Concrete Mc=Fc•(H/2-Ybar) Mu =Mc + (M1+...+M12) Max Moment/Mu
0.472, 720 mm, 600 mm, 339.70 mm, 94952 mm², 194.9 m 1 x 20, 640.5, -0.310, -437, -280.6, -137.3 1 x 20, 222.0, 0.121, 243, 137.9, 76.2 1 x 20, 501.0, -0.166, -332, -141.1, -104.4 1 x 20, 361.5, -0.022, -45, -1.6, -14.1 1 x 20, 592.9, -0.261, -437, -233.0, -137.3 1 x 20, 545.3, -0.212, -424, -185.5, -133.1 1 x 20, 497.8, -0.163, -326, -137.9, -102.3 1 x 20, 79.3, 0.268, 437, 280.6, 137.3 1 x 20, 358.3, -0.019, -38, 1.6, -12.0 1 x 20, 218.8, 0.125, 249, 141.1, 78.3 1 x 20, 174.4, 0.170, 341, 185.5, 107.0 1 x 20, 126.8, 0.219, 437, 233.0, 137.3 94952 x 0.45 x 25 -137+76-104-14-137-133-102+137-12+7 +107+137+1068-963.8 1068.2 x (720 / 2 - 194.9) 176.2 + (38.5+10.5+14.7+0.0+32.0+24.7+14.1 + (38.5+0.0+11.0+19.8+32.0) 120.6 / 412.2
OK App. Shear Vx, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6h
62.9 mm, 240 m
App. Shear Vy, v, v max
0 kN, 0 N/mm², 4 N/mm²
M/N, 0.6b
108.2 mm, 360 m
38.5 10.5 14.7 0.0 32.0 24.7 14.1 38.5 0.0 11.0 19.8 32.0 1068.2
kN kN kN kN kN kN kN kN kN kN kN kN k
-0.1 k 176.2 kN 412.2kN 0.29
X-X Shear Checks OK
Nominal links
Y-Y Shear Checks OK
Nominal links
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
Job ref Sheet Made By Date Checked Approved
: Job Ref : Sheet Ref / 113: D.O.C.K : OCT 2012 : F.O.O : K.M.M
PAD FOOTING DESIGN RESULTS BASE TYPE E GRID F/10 -------------------------------------------------------------------------------Columns/Loadings: Column Cmb N Mx My 1C3 1 -3191.9 -34.8 -99.2 G+Q *F 2 -3109.9 -32.3 -96.6 (G+Q)P11 *F 3 -3015.1 -32.7 -95.9 (G+Q)P12 *F 4 -2571.6 -22.5 -87.4 (G+Q)P21 *F 5 -2245.6 -38.6 -57.3 (G+Q)P22 *F 6 -3173.2 -33.4 -99.3 (G+Q)P31 *F 7 -3113.8 -34.3 -95.8 (G+Q)P32 *F 8 -2577.0 -22.9 -87.2 (G+Q)P41 *F 9 -2246.5 -38.6 -57.0 (G+Q)P42 *F 10 -3104.0 -31.9 -96.5 (G+Q)P51 *F 11 -3015.4 -32.6 -96.3 (G+Q)P52 *F 12 -2657.4 -10.4 -92.8 G+Q+Nx 13 -2688.1 -48.8 -72.8 G+Q-Nx 14 -2658.9 -32.0 -75.6 G+Q+Ny 15 -2686.6 -27.1 -89.9 G+Q-Ny Column: 1C1 bx = 400.0 mm by = 600.0 mm Effects: Critical Combination = 1 (G+Q *F) N = -3191.9 kN Mx = 34.8 kN.m My = 99.2 kN.m Footing Dimensions: Lx = 3000.0 mm Ly = 3000.0 mm h = 800.0 mm h-Tap = 0.0 mm Soil Stresses: S-max = 403.620 kN/m2 S-min = 344.086 kN/m2 Allowable Soil Stress will be amplified by the factor (x1.4) = 420.000 kN/m2 As-min (Both Dir's) = 1600.00 mm2/m X Dir: Footing Design: M = 339.2 kN.m/m K/K' = 0.15 < 1.0 As = 1600.00 mm2/m T20-175 Shear Check (At Column Face): (BS8110-Cl.3.4.5.2) v = 0.70 N/mm2 < v-max = 4.00 N/mm2 Shear Check (At 'd' from Column): (BS8110-Cl.3.4.5.2) v = 0.30 N/mm2 < vc = 0.39 N/mm2 Punching Check (At Column Face): (BS8110-Cl.3.7.6.4) Vt = 3275.0 kN V-eff = 3331.7 kN v = 2.25 N/mm2 < v-max = 4.00 N/mm2 Punching Check (At '1.5d'): (BS8110-Cl.3.7.6.4) Vt = 602.5 kN V-eff = 621.0 kN v = 0.08 N/mm2 < vc = 0.39 N/mm2 Y Dir: Footing Design: M = 286.4 kN.m/m K/K' = 0.14 < 1.0 As = 1600.00 mm2/m T20-175 Shear Check (At Column Face): (BS8110-Cl.3.4.5.2) v = 0.66 N/mm2 < v-max = 4.00 N/mm2 Shear Check (At 'd' from Column): (BS8110-Cl.3.4.5.2) v = 0.26 N/mm2 < vc = 0.40 N/mm2 Punching Check (At Column Face): (BS8110-Cl.3.7.6.4) Vt = 3275.0 kN V-eff = 3331.7 kN v = 2.25 N/mm2 < v-max = 4.00 N/mm2 Punching Check (At '1.5d'): (BS8110-Cl.3.7.6.4) Vt = 602.5 kN V-eff = 659.3 kN v = 0.08 N/mm2 < vc = 0.40 N/mm2
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
Job ref Sheet Made By Date Checked Approved
: Job Ref : Sheet Ref / 114: D.O.C.K : OCT 2012 : F.O.O : K.M.M
BASE TYPE F GRID G/10 -------------------------------------------------------------------------------Columns/Loadings: Column Cmb N Mx My 1C4 1 -4173.0 -0.9 -120.2 G+Q *F 2 -3270.5 15.3 -119.7 (G+Q)P11 *F 3 -3453.4 1.1 -126.6 (G+Q)P12 *F 4 -2923.8 -14.5 -83.8 (G+Q)P21 *F 5 -3590.4 6.4 -36.7 (G+Q)P22 *F 6 -3674.3 0.5 -120.9 (G+Q)P31 *F 7 -4021.7 1.1 -106.9 (G+Q)P32 *F 8 -3014.2 -15.5 -86.6 (G+Q)P41 *F 9 -3607.9 6.0 -42.0 (G+Q)P42 *F 10 -3269.0 15.9 -119.4 (G+Q)P51 *F 11 -3456.0 1.3 -126.5 (G+Q)P52 *F 12 -3454.2 24.3 -97.9 G+Q+Nx 13 -3479.2 -25.1 -98.4 G+Q-Nx 14 -3445.6 -3.8 -92.1 G+Q+Ny 15 -3487.8 3.1 -104.1 G+Q-Ny Column: 1C2 bx = 400.0 mm by = 600.0 mm Effects: Critical Combination = 1 (G+Q *F) N = -4173.0 kN Mx = 0.9 kN.m My = 120.2 kN.m Footing Dimensions: Lx = 3400.0 mm Ly = 3400.0 mm h = 900.0 mm h-Tap = 0.0 mm Soil Stresses: S-max = 413.416 kN/m2 S-min = 376.440 kN/m2 Allowable Soil Stress will be amplified by the factor (x1.4) = 420.000 kN/m2 As-min (Both Dir's) = 1800.00 mm2/m X Dir: Footing Design: M = 465.0 kN.m/m K/K' = 0.17 < 1.0 As = 1800.00 mm2/m T20-150 Shear Check (At Column Face): (BS8110-Cl.3.4.5.2) v = 0.73 N/mm2 < v-max = 4.00 N/mm2 Shear Check (At 'd' from Column): (BS8110-Cl.3.4.5.2) v = 0.32 N/mm2 < vc = 0.40 N/mm2 Punching Check (At Column Face): (BS8110-Cl.3.7.6.4) Vt = 4470.6 kN V-eff = 4532.4 kN v = 2.70 N/mm2 < v-max = 4.00 N/mm2 Punching Check (At '1.5d'): (BS8110-Cl.3.7.6.4) Vt = 967.4 kN V-eff = 967.8 kN v = 0.10 N/mm2 < vc = 0.40 N/mm2 Y Dir: Footing Design: M = 400.2 kN.m/m K/K' = 0.15 < 1.0 As = 1800.00 mm2/m T20-150 Shear Check (At Column Face): (BS8110-Cl.3.4.5.2) v = 0.70 N/mm2 < v-max = 4.00 N/mm2 Shear Check (At 'd' from Column): (BS8110-Cl.3.4.5.2) v = 0.28 N/mm2 < vc = 0.40 N/mm2 Punching Check (At Column Face): (BS8110-Cl.3.7.6.4) Vt = 4470.6 kN V-eff = 4532.4 kN v = 2.70 N/mm2 < v-max = 4.00 N/mm2 Punching Check (At '1.5d'): (BS8110-Cl.3.7.6.4) Vt = 967.4 kN V-eff = 1029.2 kN v = 0.10 N/mm2 < vc = 0.40 N/mm2
BASE TYPE G GRID H/10 -------------------------------------------------------------------------------Columns/Loadings: Column Cmb N Mx My 1C3 1 -2266.6 35.3 -97.3 G+Q *F 2 -1772.3 21.1 -95.9 (G+Q)P11 *F 3 -2124.0 33.1 -94.3 (G+Q)P12 *F
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected], 4 5 6 7 8 9 10 11 12 13 14 15
-2101.4 -1779.1 -2149.6 -2203.0 -2139.8 -1777.4 -1798.9 -2132.0 -1924.2 -1848.7 -1865.4 -1907.5
28.3 35.4 33.5 35.6 28.2 35.4 21.5 33.2 50.0 8.1 26.3 31.9
-61.7 -45.4 -94.6 -94.1 -63.3 -45.1 -96.2 -94.9 -72.8 -87.4 -75.6 -84.6
: Job Ref : Sheet Ref / 115: D.O.C.K : OCT 2012 : F.O.O : K.M.M
(G+Q)P21 (G+Q)P22 (G+Q)P31 (G+Q)P32 (G+Q)P41 (G+Q)P42 (G+Q)P51 (G+Q)P52 G+Q+Nx G+Q-Nx G+Q+Ny G+Q-Ny
*F *F *F *F *F *F *F *F
Column:
1C3 bx = 400.0 mm by = 600.0 mm Effects: Critical Combination = 1 (G+Q *F) N = -2266.6 kN Mx = 35.3 kN.m My = 97.3 kN.m Footing Dimensions: Lx = 2600.0 mm Ly = 2600.0 mm h = 700.0 mm h-Tap = 0.0 mm Soil Stresses: S-max = 409.527 kN/m2 S-min = 318.975 kN/m2 Allowable Soil Stress will be amplified by the factor (x1.4) = 420.000 kN/m2 As-min (Both Dir's) = 1400.00 mm2/m X Dir: Footing Design: M = 245.7 kN.m/m K/K' = 0.15 < 1.0 As = 1400.00 mm2/m T20-200 Shear Check (At Column Face): (BS8110-Cl.3.4.5.2) v = 0.69 N/mm2 < v-max = 4.00 N/mm2 Shear Check (At 'd' from Column): (BS8110-Cl.3.4.5.2) v = 0.28 N/mm2 < vc = 0.39 N/mm2 Punching Check (At Column Face): (BS8110-Cl.3.7.6.4) Vt = 2374.9 kN V-eff = 2437.8 kN v = 1.90 N/mm2 < v-max = 4.00 N/mm2 Punching Check (At '1.5d'): (BS8110-Cl.3.7.6.4) Vt = 332.8 kN V-eff = 353.8 kN v = 0.06 N/mm2 < vc = 0.39 N/mm2 Y Dir: Footing Design: M = 200.5 kN.m/m K/K' = 0.13 < 1.0 As = 1400.00 mm2/m T20-200 Shear Check (At Column Face): (BS8110-Cl.3.4.5.2) v = 0.65 N/mm2 < v-max = 4.00 N/mm2 Shear Check (At 'd' from Column): (BS8110-Cl.3.4.5.2) v = 0.24 N/mm2 < vc = 0.40 N/mm2 Punching Check (At Column Face): (BS8110-Cl.3.7.6.4) Vt = 2374.9 kN V-eff = 2437.8 kN v = 1.90 N/mm2 < v-max = 4.00 N/mm2 Punching Check (At '1.5d'): (BS8110-Cl.3.7.6.4) Vt = 332.8 kN V-eff = 395.7 kN v = 0.06 N/mm2 < vc = 0.40 N/mm2
BASE TYPE D GRID F/9 -------------------------------------------------------------------------------Columns/Loadings: Column Cmb N Mx My 1C2 1 -5097.5 -111.9 31.6 G+Q *F 2 -4122.6 -129.3 35.4 (G+Q)P11 *F 3 -3664.6 -122.2 63.5 (G+Q)P12 *F 4 -4475.5 -13.6 19.4 (G+Q)P21 *F 5 -3308.5 -121.3 -3.7 (G+Q)P22 *F 6 -5056.4 -105.2 32.1 (G+Q)P31 *F 7 -4131.4 -121.7 35.7 (G+Q)P32 *F 8 -4480.6 -17.5 19.4 (G+Q)P41 *F 9 -3346.3 -122.8 -2.4 (G+Q)P42 *F 10 -4115.8 -128.7 35.5 (G+Q)P51 *F 11 -3663.6 -122.1 62.4 (G+Q)P52 *F
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected], 12 13 14 15
-4187.3 -4232.3 -4213.7 -4205.8
-73.9 -104.7 -91.3 -87.3
Job ref Sheet Made By Date Checked Approved
15.2 40.2 36.2 19.2
: Job Ref : Sheet Ref / 116: D.O.C.K : OCT 2012 : F.O.O : K.M.M
G+Q+Nx G+Q-Nx G+Q+Ny G+Q-Ny
Column:
1C4 bx = 400.0 mm by = 600.0 mm Effects: Critical Combination = 1 (G+Q *F) N = -5097.5 kN Mx = 111.9 kN.m My = 31.6 kN.m Footing Dimensions: Lx = 3800.0 mm Ly = 3800.0 mm h = 1000.0 mm h-Tap = 0.0 mm Soil Stresses: S-max = 405.093 kN/m2 S-min = 373.711 kN/m2 Allowable Soil Stress will be amplified by the factor (x1.4) = 420.000 kN/m2 As-min (Both Dir's) = 2000.00 mm2/m X Dir: Footing Design: M = 580.1 kN.m/m K/K' = 0.16 < 1.0 As = 2000.00 mm2/m T20-150 Shear Check (At Column Face): (BS8110-Cl.3.4.5.2) v = 0.72 N/mm2 < v-max = 4.00 N/mm2 Shear Check (At 'd' from Column): (BS8110-Cl.3.4.5.2) v = 0.32 N/mm2 < vc = 0.38 N/mm2 Punching Check (At Column Face): (BS8110-Cl.3.7.6.4) Vt = 5529.5 kN V-eff = 5578.6 kN v = 2.97 N/mm2 < v-max = 4.00 N/mm2 Punching Check (At '1.5d'): (BS8110-Cl.3.7.6.4) Vt = 1334.7 kN V-eff = 1383.8 kN v = 0.11 N/mm2 < vc = 0.38 N/mm2 Y Dir: Footing Design: M = 517.3 kN.m/m K/K' = 0.15 < 1.0 As = 2000.00 mm2/m T20-150 Shear Check (At Column Face): (BS8110-Cl.3.4.5.2) v = 0.70 N/mm2 < v-max = 4.00 N/mm2 Shear Check (At 'd' from Column): (BS8110-Cl.3.4.5.2) v = 0.29 N/mm2 < vc = 0.38 N/mm2 Punching Check (At Column Face): (BS8110-Cl.3.7.6.4) Vt = 5529.5 kN V-eff = 5578.6 kN v = 2.97 N/mm2 < v-max = 4.00 N/mm2 Punching Check (At '1.5d'): (BS8110-Cl.3.7.6.4) Vt = 1334.7 kN V-eff = 1349.5 kN v = 0.11 N/mm2 < vc = 0.38 N/mm2
BASE TYPE D GRID F/8 -------------------------------------------------------------------------------Columns/Loadings: Column Cmb N Mx My 1C2 1 -5486.0 -175.9 -1.9 G+Q *F 2 -4269.7 -197.4 -3.4 (G+Q)P11 *F 3 -3916.9 -188.9 -32.9 (G+Q)P12 *F 4 -4710.7 -29.1 0.2 (G+Q)P21 *F 5 -3447.1 -186.4 24.8 (G+Q)P22 *F 6 -5437.2 -168.9 -2.0 (G+Q)P31 *F 7 -3929.4 -189.3 24.5 (G+Q)P32 *F 8 -4716.1 -33.4 0.4 (G+Q)P41 *F 9 -3905.3 -185.7 -5.4 (G+Q)P42 *F 10 -4263.5 -196.6 -3.3 (G+Q)P51 *F 11 -3943.2 -190.1 -29.8 (G+Q)P52 *F 12 -4494.6 -128.7 -13.8 G+Q+Nx 13 -4527.6 -151.8 10.6 G+Q-Nx 14 -4513.7 -141.7 6.8 G+Q+Ny 15 -4508.5 -138.8 -10.0 G+Q-Ny Column: 1C5 bx = 400.0 mm by = 600.0 mm Effects: Critical Combination = 1 (G+Q *F) N = -5486.0 kN Mx = 175.9 kN.m
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
Job ref Sheet Made By Date Checked Approved
: Job Ref : Sheet Ref / 117: D.O.C.K : OCT 2012 : F.O.O : K.M.M
My = 1.9 kN.m Footing Dimensions: Lx = 3900.0 mm Ly = 3900.0 mm h = 1000.0 mm h-Tap = 0.0 mm Soil Stresses: S-max = 415.061 kN/m2 S-min = 379.103 kN/m2 Allowable Soil Stress will be amplified by the factor (x1.4) = 420.000 kN/m2 As-min (Both Dir's) = 2000.00 mm2/m X Dir: Footing Design: M = 627.4 kN.m/m K/K' = 0.18 < 1.0 As = 2000.00 mm2/m T20-150 Shear Check (At Column Face): (BS8110-Cl.3.4.5.2) v = 0.76 N/mm2 < v-max = 4.00 N/mm2 Shear Check (At 'd' from Column): (BS8110-Cl.3.4.5.2) v = 0.35 N/mm2 < vc = 0.38 N/mm2 Punching Check (At Column Face): (BS8110-Cl.3.7.6.4) Vt = 5944.3 kN V-eff = 6021.4 kN v = 3.20 N/mm2 < v-max = 4.00 N/mm2 Punching Check (At '1.5d'): (BS8110-Cl.3.7.6.4) Vt = 1666.8 kN V-eff = 1743.9 kN v = 0.14 N/mm2 < vc = 0.38 N/mm2 Y Dir: Footing Design: M = 564.9 kN.m/m K/K' = 0.17 < 1.0 As = 2000.00 mm2/m T20-150 Shear Check (At Column Face): (BS8110-Cl.3.4.5.2) v = 0.74 N/mm2 < v-max = 4.00 N/mm2 Shear Check (At 'd' from Column): (BS8110-Cl.3.4.5.2) v = 0.32 N/mm2 < vc = 0.38 N/mm2 Punching Check (At Column Face): (BS8110-Cl.3.7.6.4) Vt = 5944.3 kN V-eff = 6021.4 kN v = 3.20 N/mm2 < v-max = 4.00 N/mm2 Punching Check (At '1.5d'): (BS8110-Cl.3.7.6.4) Vt = 1666.8 kN V-eff = 1667.7 kN v = 0.13 N/mm2 < vc = 0.38 N/mm2
BASE TYPE D GRID F/7 -------------------------------------------------------------------------------Columns/Loadings: Column Cmb N Mx My 1C2 1 -4841.8 -132.4 -26.7 G+Q *F 2 -3912.3 -147.7 -34.4 (G+Q)P11 *F 3 -3593.9 -140.3 21.9 (G+Q)P12 *F 4 -3986.4 -23.6 7.4 (G+Q)P21 *F 5 -3337.4 -141.2 -61.7 (G+Q)P22 *F 6 -4802.4 -127.1 -26.7 (G+Q)P31 *F 7 -3515.6 -143.3 -58.3 (G+Q)P32 *F 8 -3991.6 -26.8 7.4 (G+Q)P41 *F 9 -3443.0 -139.5 19.2 (G+Q)P42 *F 10 -3906.8 -147.3 -34.3 (G+Q)P51 *F 11 -3959.5 -141.2 -31.5 (G+Q)P52 *F 12 -3974.0 -97.9 -33.9 G+Q+Nx 13 -4010.9 -113.4 -10.1 G+Q-Nx 14 -3988.8 -106.5 -13.4 G+Q+Ny 15 -3996.1 -104.8 -30.6 G+Q-Ny Column: 1C6 bx = 400.0 mm by = 600.0 mm Effects: Critical Combination = 1 (G+Q *F) N = -4841.8 kN Mx = 132.4 kN.m My = 26.7 kN.m Footing Dimensions: Lx = 3700.0 mm Ly = 3700.0 mm h = 900.0 mm h-Tap = 0.0 mm Soil Stresses: S-max = 406.490 kN/m2 S-min = 368.817 kN/m2 Allowable Soil Stress will be amplified by the factor (x1.4) = 420.000 kN/m2
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
X Dir:
Y Dir:
Job ref Sheet Made By Date Checked Approved
: Job Ref : Sheet Ref / 118: D.O.C.K : OCT 2012 : F.O.O : K.M.M
As-min (Both Dir's) = 1800.00 mm2/m Footing Design: M = 547.0 kN.m/m K/K' = 0.19 < 1.0 As = 1800.00 mm2/m T20-150 Shear Check (At Column Face): (BS8110-Cl.3.4.5.2) v = 0.79 N/mm2 < v-max = 4.00 N/mm2 Shear Check (At 'd' from Column): (BS8110-Cl.3.4.5.2) v = 0.38 N/mm2 < vc = 0.40 N/mm2 Punching Check (At Column Face): (BS8110-Cl.3.7.6.4) Vt = 5213.9 kN V-eff = 5277.6 kN v = 3.14 N/mm2 < v-max = 4.00 N/mm2 Punching Check (At '1.5d'): (BS8110-Cl.3.7.6.4) Vt = 1775.3 kN V-eff = 1838.9 kN v = 0.18 N/mm2 < vc = 0.40 N/mm2 Footing Design: M = 487.2 kN.m/m K/K' = 0.18 < 1.0 As = 1800.00 mm2/m T20-150 Shear Check (At Column Face): (BS8110-Cl.3.4.5.2) v = 0.76 N/mm2 < v-max = 4.00 N/mm2 Shear Check (At 'd' from Column): (BS8110-Cl.3.4.5.2) v = 0.35 N/mm2 < vc = 0.40 N/mm2 Punching Check (At Column Face): (BS8110-Cl.3.7.6.4) Vt = 5213.9 kN V-eff = 5277.6 kN v = 3.14 N/mm2 < v-max = 4.00 N/mm2 Punching Check (At '1.5d'): (BS8110-Cl.3.7.6.4) Vt = 1775.3 kN V-eff = 1789.0 kN v = 0.18 N/mm2 < vc = 0.40 N/mm2
BASE TYPE C GRID G/9 -------------------------------------------------------------------------------Columns/Loadings: Column Cmb N Mx My 1C1 1 -5757.7 43.2 24.8 G+Q *F 2 -3864.4 82.9 34.7 (G+Q)P11 *F 3 -3718.3 47.0 86.6 (G+Q)P12 *F 4 -4038.1 -27.8 1.9 (G+Q)P21 *F 5 -3667.9 47.4 -28.6 (G+Q)P22 *F 6 -4389.9 39.7 31.9 (G+Q)P31 *F 7 -3921.5 45.9 26.5 (G+Q)P32 *F 8 -4582.8 -24.5 -1.2 (G+Q)P41 *F 9 -4075.6 47.9 -14.7 (G+Q)P42 *F 10 -3870.1 82.3 35.0 (G+Q)P51 *F 11 -3743.5 47.3 80.5 (G+Q)P52 *F 12 -4694.6 54.1 22.2 G+Q+Nx 13 -4724.7 14.8 21.8 G+Q-Nx 14 -4712.8 31.9 29.4 G+Q+Ny 15 -4706.5 37.0 14.6 G+Q-Ny Column: 1C9 bx = 400.0 mm by = 600.0 mm Effects: Critical Combination = 1 (G+Q *F) N = -5757.7 kN Mx = 43.2 kN.m My = 24.8 kN.m Footing Dimensions: Lx = 4000.0 mm Ly = 4000.0 mm h = 1000.0 mm h-Tap = 0.0 mm Soil Stresses: S-max = 402.640 kN/m2 S-min = 389.890 kN/m2 Allowable Soil Stress will be amplified by the factor (x1.4) = 420.000 kN/m2 As-min (Both Dir's) = 2000.00 mm2/m X Dir: Footing Design: M = 650.3 kN.m/m K/K' = 0.18 < 1.0 As = 2000.00 mm2/m T20-150 Shear Check (At Column Face): (BS8110-Cl.3.4.5.2) v = 0.76 N/mm2 < v-max = 4.00 N/mm2 Shear Check (At 'd' from Column): (BS8110-Cl.3.4.5.2) v = 0.36 N/mm2 < vc = 0.38 N/mm2
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
Y Dir:
Job ref Sheet Made By Date Checked Approved
: Job Ref : Sheet Ref / 119: D.O.C.K : OCT 2012 : F.O.O : K.M.M
Punching Check (At Column Face): (BS8110-Cl.3.7.6.4) Vt = 6245.1 kN V-eff = 6264.1 kN v = 3.33 N/mm2 < v-max = 4.00 N/mm2 Punching Check (At '1.5d'): (BS8110-Cl.3.7.6.4) Vt = 1976.4 kN V-eff = 1995.4 kN v = 0.16 N/mm2 < vc = 0.38 N/mm2 Footing Design: M = 580.9 kN.m/m K/K' = 0.17 < 1.0 As = 2000.00 mm2/m T20-150 Shear Check (At Column Face): (BS8110-Cl.3.4.5.2) v = 0.74 N/mm2 < v-max = 4.00 N/mm2 Shear Check (At 'd' from Column): (BS8110-Cl.3.4.5.2) v = 0.33 N/mm2 < vc = 0.38 N/mm2 Punching Check (At Column Face): (BS8110-Cl.3.7.6.4) Vt = 6245.1 kN V-eff = 6264.1 kN v = 3.33 N/mm2 < v-max = 4.00 N/mm2 Punching Check (At '1.5d'): (BS8110-Cl.3.7.6.4) Vt = 1976.4 kN V-eff = 1987.9 kN v = 0.16 N/mm2 < vc = 0.38 N/mm2
BASE TYPE C GRID G/8 -------------------------------------------------------------------------------Columns/Loadings: Column Cmb N Mx My 1C1 1 -6085.6 79.2 2.1 G+Q *F 2 -3923.5 123.2 -0.3 (G+Q)P11 *F 3 -3798.8 83.3 -59.9 (G+Q)P12 *F 4 -4294.2 -22.7 1.1 (G+Q)P21 *F 5 -3789.8 85.0 55.6 (G+Q)P22 *F 6 -4592.1 75.5 0.4 (G+Q)P31 *F 7 -3815.8 82.8 48.8 (G+Q)P32 *F 8 -4880.3 -17.9 1.6 (G+Q)P41 *F 9 -4000.1 84.3 -7.6 (G+Q)P42 *F 10 -3928.9 121.0 0.0 (G+Q)P51 *F 11 -4208.4 84.3 -43.9 (G+Q)P52 *F 12 -4948.9 77.7 1.8 G+Q+Nx 13 -4973.8 48.1 1.5 G+Q-Nx 14 -4963.4 61.0 8.9 G+Q+Ny 15 -4959.3 64.8 -5.6 G+Q-Ny Column: 1C10 bx = 400.0 mm by = 600.0 mm Effects: Critical Combination = 1 (G+Q *F) N = -6085.6 kN Mx = 79.2 kN.m My = 2.1 kN.m Footing Dimensions: Lx = 4100.0 mm Ly = 4100.0 mm h = 1100.0 mm h-Tap = 0.0 mm Soil Stresses: S-max = 407.920 kN/m2 S-min = 393.765 kN/m2 Allowable Soil Stress will be amplified by the factor (x1.4) = 420.000 kN/m2 As-min (Both Dir's) = 2200.00 mm2/m X Dir: Footing Design: M = 694.5 kN.m/m K/K' = 0.16 < 1.0 As = 2200.00 mm2/m T20-125 Shear Check (At Column Face): (BS8110-Cl.3.4.5.2) v = 0.72 N/mm2 < v-max = 4.00 N/mm2 Shear Check (At 'd' from Column): (BS8110-Cl.3.4.5.2) v = 0.31 N/mm2 < vc = 0.39 N/mm2 Punching Check (At Column Face): (BS8110-Cl.3.7.6.4) Vt = 6642.0 kN V-eff = 6673.9 kN v = 3.21 N/mm2 < v-max = 4.00 N/mm2 Punching Check (At '1.5d'): (BS8110-Cl.3.7.6.4) Vt = 1489.4 kN V-eff = 1521.3 kN v = 0.10 N/mm2 < vc = 0.39 N/mm2 Y Dir: Footing Design: M = 624.5 kN.m/m K/K' = 0.15 < 1.0
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
Job ref Sheet Made By Date Checked Approved
: Job Ref : Sheet Ref / 120: D.O.C.K : OCT 2012 : F.O.O : K.M.M
As = 2200.00 mm2/m T20-125 Shear Check (At Column Face): (BS8110-Cl.3.4.5.2) v = 0.69 N/mm2 < v-max = 4.00 N/mm2 Shear Check (At 'd' from Column): (BS8110-Cl.3.4.5.2) v = 0.29 N/mm2 < vc = 0.39 N/mm2 Punching Check (At Column Face): (BS8110-Cl.3.7.6.4) Vt = 6642.0 kN V-eff = 6673.9 kN v = 3.21 N/mm2 < v-max = 4.00 N/mm2 Punching Check (At '1.5d'): (BS8110-Cl.3.7.6.4) Vt = 1489.4 kN V-eff = 1490.3 kN v = 0.10 N/mm2 < vc = 0.39 N/mm2
BASE TYPE C GRID G/7 -------------------------------------------------------------------------------Columns/Loadings: Column Cmb N Mx My 1C1 1 -6465.5 59.4 -85.3 G+Q *F 2 -4542.7 93.0 -68.3 (G+Q)P11 *F 3 -4447.5 61.3 21.3 (G+Q)P12 *F 4 -4531.3 -17.0 -42.4 (G+Q)P21 *F 5 -4773.7 63.7 -144.6 (G+Q)P22 *F 6 -5339.2 56.7 -90.7 (G+Q)P31 *F 7 -4996.8 62.6 -141.0 (G+Q)P32 *F 8 -4990.4 -14.2 -39.6 (G+Q)P41 *F 9 -4438.3 62.0 15.4 (G+Q)P42 *F 10 -4547.4 92.2 -67.8 (G+Q)P51 *F 11 -4995.6 62.5 -90.9 (G+Q)P52 *F 12 -5278.9 57.2 -69.8 G+Q+Nx 13 -5309.9 37.4 -71.1 G+Q-Nx 14 -5286.7 46.1 -62.7 G+Q+Ny 15 -5302.1 48.4 -78.1 G+Q-Ny Column: 1C11 bx = 400.0 mm by = 600.0 mm Effects: Critical Combination = 1 (G+Q *F) N = -6465.5 kN Mx = 59.4 kN.m My = 85.3 kN.m Footing Dimensions: Lx = 4200.0 mm Ly = 4200.0 mm h = 1100.0 mm h-Tap = 0.0 mm Soil Stresses: S-max = 417.069 kN/m2 S-min = 393.643 kN/m2 Allowable Soil Stress will be amplified by the factor (x1.4) = 420.000 kN/m2 As-min (Both Dir's) = 2200.00 mm2/m X Dir: Footing Design: M = 750.2 kN.m/m K/K' = 0.17 < 1.0 As = 2200.00 mm2/m T20-125 Shear Check (At Column Face): (BS8110-Cl.3.4.5.2) v = 0.75 N/mm2 < v-max = 4.00 N/mm2 Shear Check (At 'd' from Column): (BS8110-Cl.3.4.5.2) v = 0.34 N/mm2 < vc = 0.39 N/mm2 Punching Check (At Column Face): (BS8110-Cl.3.7.6.4) Vt = 7053.2 kN V-eff = 7089.5 kN v = 3.41 N/mm2 < v-max = 4.00 N/mm2 Punching Check (At '1.5d'): (BS8110-Cl.3.7.6.4) Vt = 1842.6 kN V-eff = 1866.5 kN v = 0.12 N/mm2 < vc = 0.39 N/mm2 Y Dir: Footing Design: M = 672.5 kN.m/m K/K' = 0.16 < 1.0 As = 2200.00 mm2/m T20-125 Shear Check (At Column Face): (BS8110-Cl.3.4.5.2) v = 0.73 N/mm2 < v-max = 4.00 N/mm2 Shear Check (At 'd' from Column): (BS8110-Cl.3.4.5.2) v = 0.31 N/mm2 < vc = 0.39 N/mm2 Punching Check (At Column Face): (BS8110-Cl.3.7.6.4) Vt = 7053.2 kN V-eff = 7089.5 kN v = 3.41 N/mm2 < v-max = 4.00 N/mm2
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
Job ref Sheet Made By Date Checked Approved
: Job Ref : Sheet Ref / 121: D.O.C.K : OCT 2012 : F.O.O : K.M.M
Punching Check (At '1.5d'): (BS8110-Cl.3.7.6.4) Vt = 1842.6 kN V-eff = 1878.9 kN v = 0.12 N/mm2 < vc = 0.39 N/mm2
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
Job ref Sheet Made By Date Checked Approved
: Job Ref : Sheet Ref / 122: D.O.C.K : OCT 2012 : F.O.O : K.M.M
BASE TYPE F GRID H/9 -------------------------------------------------------------------------------Columns/Loadings: Column Cmb N Mx My 1C4 1 -3741.6 42.6 15.5 G+Q *F 2 -3299.1 -8.9 18.3 (G+Q)P11 *F 3 -2684.5 38.9 46.5 (G+Q)P12 *F 4 -3075.1 57.9 -3.5 (G+Q)P21 *F 5 -2585.5 39.0 -16.2 (G+Q)P22 *F 6 -3077.4 44.1 18.3 (G+Q)P31 *F 7 -3135.2 36.9 17.9 (G+Q)P32 *F 8 -3429.4 52.3 -4.4 (G+Q)P41 *F 9 -2638.1 40.9 -14.6 (G+Q)P42 *F 10 -3519.2 -8.5 17.3 (G+Q)P51 *F 11 -2695.2 39.1 45.3 (G+Q)P52 *F 12 -3127.0 50.6 21.7 G+Q+Nx 13 -3054.5 17.2 4.5 G+Q-Nx 14 -3084.8 31.7 18.5 G+Q+Ny 15 -3096.7 36.1 7.7 G+Q-Ny Column: 1C13 bx = 400.0 mm by = 600.0 mm Effects: Critical Combination = 1 (G+Q *F) N = -3741.6 kN Mx = 42.6 kN.m My = 15.5 kN.m Footing Dimensions: Lx = 3200.0 mm Ly = 3200.0 mm h = 800.0 mm h-Tap = 0.0 mm Soil Stresses: S-max = 407.549 kN/m2 S-min = 386.251 kN/m2 Allowable Soil Stress will be amplified by the factor (x1.4) = 420.000 kN/m2 As-min (Both Dir's) = 1600.00 mm2/m X Dir: Footing Design: M = 397.2 kN.m/m K/K' = 0.18 < 1.0 As = 1600.00 mm2/m T20-175 Shear Check (At Column Face): (BS8110-Cl.3.4.5.2) v = 0.76 N/mm2 < v-max = 4.00 N/mm2 Shear Check (At 'd' from Column): (BS8110-Cl.3.4.5.2) v = 0.35 N/mm2 < vc = 0.39 N/mm2 Punching Check (At Column Face): (BS8110-Cl.3.7.6.4) Vt = 3969.0 kN V-eff = 3991.7 kN v = 2.70 N/mm2 < v-max = 4.00 N/mm2 Punching Check (At '1.5d'): (BS8110-Cl.3.7.6.4) Vt = 1131.8 kN V-eff = 1154.5 kN v = 0.14 N/mm2 < vc = 0.39 N/mm2 Y Dir: Footing Design: M = 343.7 kN.m/m K/K' = 0.17 < 1.0 As = 1600.00 mm2/m T20-175 Shear Check (At Column Face): (BS8110-Cl.3.4.5.2) v = 0.73 N/mm2 < v-max = 4.00 N/mm2 Shear Check (At 'd' from Column): (BS8110-Cl.3.4.5.2) v = 0.32 N/mm2 < vc = 0.40 N/mm2 Punching Check (At Column Face): (BS8110-Cl.3.7.6.4) Vt = 3969.0 kN V-eff = 3991.7 kN v = 2.70 N/mm2 < v-max = 4.00 N/mm2 Punching Check (At '1.5d'): (BS8110-Cl.3.7.6.4) Vt = 1131.8 kN V-eff = 1140.7 kN v = 0.14 N/mm2 < vc = 0.40 N/mm2
BASE TYPE F GRID H/8 -------------------------------------------------------------------------------Columns/Loadings: Column Cmb N Mx My 1C4 1 -4253.7 39.0 -1.2 G+Q *F 2 -3572.8 -19.8 -0.2 (G+Q)P11 *F 3 -3211.4 32.9 -28.4 (G+Q)P12 *F
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected], 4 5 6 7 8 9 10 11 12 13 14 15
-3559.4 -2777.4 -3512.6 -3224.0 -3743.9 -3206.1 -4029.9 -3270.4 -3537.0 -3479.0 -3503.4 -3512.6
63.9 33.4 40.1 32.5 57.6 31.9 -19.0 35.2 43.7 18.5 29.5 32.7
Job ref Sheet Made By Date Checked Approved
-0.9 27.4 -1.2 26.1 -0.8 0.1 0.3 -28.0 7.4 -9.5 4.3 -6.4
: Job Ref : Sheet Ref / 123: D.O.C.K : OCT 2012 : F.O.O : K.M.M
(G+Q)P21 (G+Q)P22 (G+Q)P31 (G+Q)P32 (G+Q)P41 (G+Q)P42 (G+Q)P51 (G+Q)P52 G+Q+Nx G+Q-Nx G+Q+Ny G+Q-Ny
*F *F *F *F *F *F *F *F
Column:
1C14 bx = 400.0 mm by = 600.0 mm Effects: Critical Combination = 1 (G+Q *F) N = -4253.7 kN Mx = 39.0 kN.m My = 1.2 kN.m Footing Dimensions: Lx = 3400.0 mm Ly = 3400.0 mm h = 900.0 mm h-Tap = 0.0 mm Soil Stresses: S-max = 408.049 kN/m2 S-min = 395.761 kN/m2 Allowable Soil Stress will be amplified by the factor (x1.4) = 420.000 kN/m2 As-min (Both Dir's) = 1800.00 mm2/m X Dir: Footing Design: M = 457.1 kN.m/m K/K' = 0.16 < 1.0 As = 1800.00 mm2/m T20-150 Shear Check (At Column Face): (BS8110-Cl.3.4.5.2) v = 0.72 N/mm2 < v-max = 4.00 N/mm2 Shear Check (At 'd' from Column): (BS8110-Cl.3.4.5.2) v = 0.31 N/mm2 < vc = 0.40 N/mm2 Punching Check (At Column Face): (BS8110-Cl.3.7.6.4) Vt = 4549.6 kN V-eff = 4568.3 kN v = 2.72 N/mm2 < v-max = 4.00 N/mm2 Punching Check (At '1.5d'): (BS8110-Cl.3.7.6.4) Vt = 984.5 kN V-eff = 1003.3 kN v = 0.10 N/mm2 < vc = 0.40 N/mm2 Y Dir: Footing Design: M = 399.8 kN.m/m K/K' = 0.15 < 1.0 As = 1800.00 mm2/m T20-150 Shear Check (At Column Face): (BS8110-Cl.3.4.5.2) v = 0.69 N/mm2 < v-max = 4.00 N/mm2 Shear Check (At 'd' from Column): (BS8110-Cl.3.4.5.2) v = 0.28 N/mm2 < vc = 0.40 N/mm2 Punching Check (At Column Face): (BS8110-Cl.3.7.6.4) Vt = 4549.6 kN V-eff = 4568.3 kN v = 2.72 N/mm2 < v-max = 4.00 N/mm2 Punching Check (At '1.5d'): (BS8110-Cl.3.7.6.4) Vt = 984.5 kN V-eff = 985.1 kN v = 0.10 N/mm2 < vc = 0.40 N/mm2
BASE TYPE E GRID H/7 -------------------------------------------------------------------------------Columns/Loadings: Column Cmb N Mx My 1C3 1 -3523.6 37.2 8.8 G+Q *F 2 -2889.1 -8.7 29.1 (G+Q)P11 *F 3 -2717.4 30.9 34.3 (G+Q)P12 *F 4 -3031.2 52.7 -5.3 (G+Q)P21 *F 5 -2441.8 34.5 -22.2 (G+Q)P22 *F 6 -2927.8 38.5 6.3 (G+Q)P31 *F 7 -2607.8 34.6 -19.9 (G+Q)P32 *F 8 -3342.3 48.1 -4.7 (G+Q)P41 *F 9 -2583.6 31.2 31.5 (G+Q)P42 *F 10 -3098.4 -8.4 31.3 (G+Q)P51 *F 11 -3025.9 32.9 8.1 (G+Q)P52 *F
Job ref Sheet Made By Date Checked Approved
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected], 12 13 14 15
-2941.7 -2888.8 -2903.4 -2927.0
38.1 21.4 28.8 30.7
14.9 -1.3 12.5 1.1
: Job Ref : Sheet Ref / 124: D.O.C.K : OCT 2012 : F.O.O : K.M.M
G+Q+Nx G+Q-Nx G+Q+Ny G+Q-Ny
Column:
1C15 bx = 400.0 mm by = 600.0 mm Effects: Critical Combination = 1 (G+Q *F) N = -3523.6 kN Mx = 37.2 kN.m My = 8.8 kN.m Footing Dimensions: Lx = 3100.0 mm Ly = 3100.0 mm h = 800.0 mm h-Tap = 0.0 mm Soil Stresses: S-max = 407.415 kN/m2 S-min = 388.876 kN/m2 Allowable Soil Stress will be amplified by the factor (x1.4) = 420.000 kN/m2 As-min (Both Dir's) = 1600.00 mm2/m X Dir: Footing Design: M = 369.3 kN.m/m K/K' = 0.17 < 1.0 As = 1600.00 mm2/m T20-175 Shear Check (At Column Face): (BS8110-Cl.3.4.5.2) v = 0.73 N/mm2 < v-max = 4.00 N/mm2 Shear Check (At 'd' from Column): (BS8110-Cl.3.4.5.2) v = 0.33 N/mm2 < vc = 0.39 N/mm2 Punching Check (At Column Face): (BS8110-Cl.3.7.6.4) Vt = 3730.6 kN V-eff = 3750.4 kN v = 2.53 N/mm2 < v-max = 4.00 N/mm2 Punching Check (At '1.5d'): (BS8110-Cl.3.7.6.4) Vt = 884.5 kN V-eff = 904.3 kN v = 0.11 N/mm2 < vc = 0.39 N/mm2 Y Dir: Footing Design: M = 317.9 kN.m/m K/K' = 0.15 < 1.0 As = 1600.00 mm2/m T20-175 Shear Check (At Column Face): (BS8110-Cl.3.4.5.2) v = 0.70 N/mm2 < v-max = 4.00 N/mm2 Shear Check (At 'd' from Column): (BS8110-Cl.3.4.5.2) v = 0.29 N/mm2 < vc = 0.40 N/mm2 Punching Check (At Column Face): (BS8110-Cl.3.7.6.4) Vt = 3730.6 kN V-eff = 3750.4 kN v = 2.53 N/mm2 < v-max = 4.00 N/mm2 Punching Check (At '1.5d'): (BS8110-Cl.3.7.6.4) Vt = 884.5 kN V-eff = 889.6 kN v = 0.11 N/mm2 < vc = 0.40 N/mm2
BASE TYPE G GRID F5/9b -------------------------------------------------------------------------------Columns/Loadings: Column Cmb N Mx My 1C5 1 -2784.3 18.2 -65.7 G+Q *F 2 -2642.1 18.9 -63.8 (G+Q)P11 *F 3 -2403.6 19.1 -62.8 (G+Q)P12 *F 4 -1695.5 15.5 -35.2 (G+Q)P21 *F 5 -2025.5 13.8 -26.9 (G+Q)P22 *F 6 -2717.2 18.6 -65.6 (G+Q)P31 *F 7 -2733.3 18.2 -63.3 (G+Q)P32 *F 8 -1704.3 15.4 -35.5 (G+Q)P41 *F 9 -2035.5 13.7 -27.3 (G+Q)P42 *F 10 -2641.4 19.1 -63.8 (G+Q)P51 *F 11 -2401.8 19.1 -62.9 (G+Q)P52 *F 12 -2318.2 21.1 -55.1 G+Q+Nx 13 -2320.3 10.4 -53.2 G+Q-Nx 14 -2324.9 15.1 -52.3 G+Q+Ny 15 -2313.7 16.5 -56.0 G+Q-Ny Column: 1C19 bx = 300.0 mm by = 400.0 mm Effects: Critical Combination = 1 (G+Q *F) N = -2784.3 kN Mx = 18.2 kN.m
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
Job ref Sheet Made By Date Checked Approved
: Job Ref : Sheet Ref / 125: D.O.C.K : OCT 2012 : F.O.O : K.M.M
My = 65.7 kN.m Footing Dimensions: Lx = 2800.0 mm Ly = 2800.0 mm h = 700.0 mm h-Tap = 0.0 mm Soil Stresses: S-max = 407.303 kN/m2 S-min = 361.396 kN/m2 Allowable Soil Stress will be amplified by the factor (x1.4) = 420.000 kN/m2 As-min (Both Dir's) = 1400.00 mm2/m X Dir: Footing Design: M = 317.0 kN.m/m K/K' = 0.19 < 1.0 As = 1400.00 mm2/m T20-200 Shear Check (At Column Face): (BS8110-Cl.3.4.5.2) v = 0.78 N/mm2 < v-max = 4.00 N/mm2 Shear Check (At 'd' from Column): (BS8110-Cl.3.4.5.2) v = 0.38 N/mm2 < vc = 0.39 N/mm2 Punching Check (At Column Face): (BS8110-Cl.3.7.6.4) Vt = 2967.2 kN V-eff = 3011.6 kN v = 3.36 N/mm2 < v-max = 4.00 N/mm2 Punching Check (At '1.5d'): (BS8110-Cl.3.7.6.4) Vt = 1033.7 kN V-eff = 1045.5 kN v = 0.18 N/mm2 < vc = 0.39 N/mm2 Y Dir: Footing Design: M = 289.6 kN.m/m K/K' = 0.19 < 1.0 As = 1400.00 mm2/m T20-200 Shear Check (At Column Face): (BS8110-Cl.3.4.5.2) v = 0.78 N/mm2 < v-max = 4.00 N/mm2 Shear Check (At 'd' from Column): (BS8110-Cl.3.4.5.2) v = 0.37 N/mm2 < vc = 0.40 N/mm2 Punching Check (At Column Face): (BS8110-Cl.3.7.6.4) Vt = 2967.2 kN V-eff = 3011.6 kN v = 3.36 N/mm2 < v-max = 4.00 N/mm2 Punching Check (At '1.5d'): (BS8110-Cl.3.7.6.4) Vt = 1033.7 kN V-eff = 1078.2 kN v = 0.19 N/mm2 < vc = 0.40 N/mm2
BASE TYPE A GRID F/5-6 -------------------------------------------------------------------------------Columns/Loadings: Column Cmb N Mx My 1W1 1 -1496.8 -149.4 -0.2 G+Q *F 2 -1448.6 -145.4 -0.4 (G+Q)P11 *F 3 -1317.1 -124.7 -0.2 (G+Q)P12 *F 4 -1205.3 -68.9 0.1 (G+Q)P21 *F 5 -1038.4 -90.9 -0.4 (G+Q)P22 *F 6 -1412.8 -129.7 -0.2 (G+Q)P31 *F 7 -1286.6 -133.7 -0.3 (G+Q)P32 *F 8 -1304.6 -78.9 0.1 (G+Q)P41 *F 9 -1173.3 -104.5 -0.3 (G+Q)P42 *F 10 -1454.2 -143.2 -0.4 (G+Q)P51 *F 11 -1194.6 -107.7 -0.3 (G+Q)P52 *F 12 -1035.3 -85.9 -1.7 G+Q+Nx 13 -1466.3 -156.1 1.3 G+Q-Nx 14 -1600.2 -110.0 1.5 G+Q+Ny 15 -901.3 -131.9 -1.9 G+Q-Ny 1W5 1 -3890.3 -1256.9 -0.5 G+Q *F 2 -3597.7 -1140.6 -1.0 (G+Q)P11 *F 3 -3084.6 -1058.2 -0.6 (G+Q)P12 *F 4 -3189.7 -696.7 0.4 (G+Q)P21 *F 5 -2894.8 -756.4 -0.9 (G+Q)P22 *F 6 -3766.6 -1090.0 -0.5 (G+Q)P31 *F 7 -3326.3 -1196.4 -0.7 (G+Q)P32 *F 8 -3265.3 -797.7 0.3 (G+Q)P41 *F 9 -2866.3 -895.6 -0.8 (G+Q)P42 *F 10 -3580.2 -1064.8 -0.9 (G+Q)P51 *F 11 -3099.1 -898.6 -0.6 (G+Q)P52 *F 12 -3417.8 329.5 -4.4 G+Q+Nx
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
1W7
1W8
1W3
1C7
1C8
13 14 15 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 1 2 3 4
-3069.5 -2761.3 -3726.0 -3301.4 -3123.1 -2789.9 -2623.0 -2373.1 -3170.1 -2878.0 -2738.7 -2545.4 -3108.7 -2618.6 -2489.6 -3019.3 -2872.7 -2636.2 -2465.0 -2298.6 -1983.6 -2138.2 -1786.9 -2366.0 -2017.6 -2246.2 -1808.6 -2324.0 -1975.2 -2309.8 -1807.7 -2100.8 -2016.7 -1601.7 -1506.0 -1325.9 -1322.5 -1155.5 -1537.7 -1359.8 -1384.6 -1209.4 -1509.0 -1276.0 -1333.1 -1340.8 -1381.5 -1292.4 -963.8 -909.3 -786.5 -741.9 -714.1 -920.8 -855.7 -770.5 -724.5 -895.1 -770.7 -688.6 -918.1 -742.1 -864.6 -2604.1 -2594.4 -2599.5 -1840.5
-2387.6 -1204.1 -854.0 -259.7 -235.9 -69.3 -157.5 -334.3 -279.9 -217.0 -108.0 -156.8 -218.7 -224.7 -1082.4 666.9 710.5 -1126.0 -215.6 -152.9 -42.0 -153.0 -270.8 -248.6 -178.1 -92.4 -129.5 -124.7 -162.3 -764.6 420.3 727.1 -1071.4 -138.0 -116.7 -109.4 -75.8 -69.9 -116.6 -118.5 -87.3 -87.4 -111.1 -88.6 37.2 -261.0 -116.0 -107.7 -0.3 0.5 0.1 -0.5 0.5 -0.1 0.1 -0.6 0.3 0.5 0.3 3.7 -4.1 -0.3 -0.1 -82.1 -83.7 -82.0 -40.0
Job ref Sheet Made By Date Checked Approved
: Job Ref : Sheet Ref / 126: D.O.C.K : OCT 2012 : F.O.O : K.M.M
3.6 G+Q-Nx 3.2 G+Q+Ny -4.0 G+Q-Ny -1.0 G+Q *F -0.7 (G+Q)P11 -0.6 (G+Q)P12 -0.7 (G+Q)P21 -0.3 (G+Q)P22 -0.7 (G+Q)P31 -0.6 (G+Q)P32 -0.9 (G+Q)P41 -0.3 (G+Q)P42 -0.7 (G+Q)P51 -0.5 (G+Q)P52 1.1 G+Q+Nx -2.8 G+Q-Nx -0.8 G+Q+Ny -0.9 G+Q-Ny -1.0 G+Q *F -0.7 (G+Q)P11 -0.6 (G+Q)P12 -0.7 (G+Q)P21 -0.3 (G+Q)P22 -0.7 (G+Q)P31 -0.6 (G+Q)P32 -0.9 (G+Q)P41 -0.3 (G+Q)P42 -0.7 (G+Q)P51 -0.5 (G+Q)P52 1.1 G+Q+Nx -2.8 G+Q-Nx -0.8 G+Q+Ny -0.9 G+Q-Ny -0.2 G+Q *F -0.4 (G+Q)P11 -0.2 (G+Q)P12 0.1 (G+Q)P21 -0.4 (G+Q)P22 -0.2 (G+Q)P31 -0.3 (G+Q)P32 0.1 (G+Q)P41 -0.3 (G+Q)P42 -0.4 (G+Q)P51 -0.2 (G+Q)P52 -1.7 G+Q+Nx 1.3 G+Q-Nx 1.5 G+Q+Ny -1.9 G+Q-Ny 36.2 G+Q *F 32.6 (G+Q)P11 -6.7 (G+Q)P12 19.8 (G+Q)P21 46.6 (G+Q)P22 36.0 (G+Q)P31 33.1 (G+Q)P32 19.8 (G+Q)P41 -7.4 (G+Q)P42 32.7 (G+Q)P51 47.1 (G+Q)P52 17.1 G+Q+Nx 40.5 G+Q-Nx 36.9 G+Q+Ny 20.8 G+Q-Ny 42.0 G+Q *F 40.7 (G+Q)P11 44.7 (G+Q)P12 38.4 (G+Q)P21
*F *F *F *F *F *F *F *F *F *F
*F *F *F *F *F *F *F *F *F *F
*F *F *F *F *F *F *F *F *F *F
*F *F *F *F *F *F *F *F *F *F
*F *F *F
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
Job ref Sheet Made By Date Checked Approved
: Job Ref : Sheet Ref / 127: D.O.C.K : OCT 2012 : F.O.O : K.M.M
5 -2183.3 -82.5 17.7 (G+Q)P22 *F 6 -2595.6 -82.0 41.9 (G+Q)P31 *F 7 -2591.2 -82.1 41.3 (G+Q)P32 *F 8 -1848.8 -40.0 38.6 (G+Q)P41 *F 9 -2501.0 -82.0 44.3 (G+Q)P42 *F 10 -2592.6 -83.7 40.7 (G+Q)P51 *F 11 -2281.0 -82.4 18.2 (G+Q)P52 *F 12 -2150.5 -68.8 24.5 G+Q+Nx 13 -2213.3 -67.0 46.1 G+Q-Nx 14 -2209.7 -67.5 42.3 G+Q+Ny 15 -2154.1 -68.3 28.2 G+Q-Ny Columns: 1W9, 1W7, 1W8, 1W10, 1W11, 1C7, 1C8 bx = 6300.0 mm by = 8100.0 mm Effects: Critical Combination = 1 (G+Q *F) N = -16323.1 kN Mx = 3822.5 kN.m My = 15138.9 kN.m Footing Dimensions: Lx = 7500.0 mm Ly = 9700.0 mm h = 500.0 mm h-Tap = 0.0 mm Soil Stresses: S-max = 414.254 kN/m2 S-min = 72.750 kN/m2 Allowable Soil Stress will be amplified by the factor (x1.4) = 420.000 kN/m2 As-min (Both Dir's) = 1000.00 mm2/m X Dir: Footing Design: M = 74.2 kN.m/m K/K' = 0.10 < 1.0 As = 1000.00 mm2/m T20-250 Shear Check (At Column Face): (BS8110-Cl.3.4.5.2) v = 0.58 N/mm2 < v-max = 4.00 N/mm2 Shear Check (At 'd' from Column): (BS8110-Cl.3.4.5.2) v = 0.16 N/mm2 < vc = 0.42 N/mm2 Punching Check (At Column Face): (BS8110-Cl.3.7.6.4) Vt = 5288.9 kN V-eff = 8316.6 kN v = 0.66 N/mm2 < v-max = 4.00 N/mm2 Punching Check (At '1.5d'): (BS8110-Cl.3.7.6.4) Vt = 511.4 kN V-eff = 1120.0 kN v = 0.08 N/mm2 < vc = 0.42 N/mm2 Y Dir: Footing Design: M = 130.3 kN.m/m K/K' = 0.16 < 1.0 As = 1000.00 mm2/m T20-250 Shear Check (At Column Face): (BS8110-Cl.3.4.5.2) v = 0.74 N/mm2 < v-max = 4.00 N/mm2 Shear Check (At 'd' from Column): (BS8110-Cl.3.4.5.2) v = 0.32 N/mm2 < vc = 0.41 N/mm2 Punching Check (At Column Face): (BS8110-Cl.3.7.6.4) Vt = 5288.9 kN V-eff = 8316.6 kN v = 0.66 N/mm2 < v-max = 4.00 N/mm2 Punching Check (At '1.5d'): (BS8110-Cl.3.7.6.4) Vt = 511.4 kN V-eff = 3539.1 kN v = 0.24 N/mm2 < vc = 0.41 N/mm2
BASE TYPE B GRID G-H/5-6 -------------------------------------------------------------------------------Columns/Loadings: Column Cmb N Mx My 1W2 1 -2111.5 -882.1 0.5 G+Q *F 2 -1887.5 -839.9 1.0 (G+Q)P11 *F 3 -1850.6 -764.4 0.9 (G+Q)P12 *F 4 -1935.1 -407.5 -0.3 (G+Q)P21 *F 5 -1689.2 -498.1 0.5 (G+Q)P22 *F 6 -1940.5 -762.4 0.5 (G+Q)P31 *F 7 -1779.8 -800.8 0.7 (G+Q)P32 *F 8 -1978.0 -471.4 -0.2 (G+Q)P41 *F 9 -1793.8 -634.4 0.6 (G+Q)P42 *F 10 -2041.6 -814.6 1.1 (G+Q)P51 *F 11 -1795.5 -604.7 0.7 (G+Q)P52 *F 12 -1958.9 -405.3 2.9 G+Q+Nx
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
1W6
1W11
1W9
1W4
1W10
13 14 15 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 1 2 3 4
-1584.1 -2215.2 -1327.8 -3241.8 -2782.2 -2538.7 -2744.9 -2668.2 -2885.1 -2852.6 -2939.4 -2458.2 -2778.5 -2755.9 -2537.9 -2869.2 -2235.3 -3171.8 -1627.3 -1376.5 -1305.2 -1697.3 -1496.5 -1491.6 -1371.4 -1737.8 -1355.2 -1483.4 -1493.2 -1798.4 -946.5 -1339.5 -1405.4 -3161.1 -2801.9 -2630.8 -2532.8 -2417.1 -2829.4 -2761.8 -2697.7 -2467.5 -2847.2 -2590.3 -2294.3 -2970.9 -2686.8 -2578.3 -2437.4 -2127.0 -2003.8 -2153.4 -1992.3 -2199.5 -2104.0 -2257.9 -1946.2 -2204.4 -2078.7 -2082.9 -1994.5 -2049.1 -2028.3 -1165.2 -1028.7 -987.4 -1044.6
-1025.1 -706.1 -724.3 -1276.9 -1068.5 -1028.6 -695.6 -685.3 -1102.0 -1132.8 -786.7 -843.6 -1001.7 -847.1 160.1 -2231.8 -1149.5 -922.2 -190.1 -5.4 45.1 -210.2 -147.8 -99.6 -145.7 -288.4 15.3 100.4 -97.7 620.5 -928.1 508.9 -816.5 -268.8 -129.8 -43.2 -209.5 -275.0 -220.1 -240.2 -242.0 -98.7 -45.7 -200.8 -74.5 -357.3 546.6 -978.5 -880.0 -794.5 -742.7 -444.0 -493.6 -764.3 -800.4 -505.9 -616.6 -755.8 -600.5 -96.0 -1333.4 -755.2 -674.2 -2.0 29.8 32.9 -26.9
Job ref Sheet Made By Date Checked Approved
-2.1 3.1 -2.3 0.2 0.6 0.6 -0.4 0.2 0.2 0.4 -0.3 0.4 0.7 0.4 2.0 -1.8 2.6 -2.3 -1.0 -0.9 -0.9 -0.7 -0.7 -1.0 -1.0 -0.6 -0.8 -0.8 -0.7 1.4 -3.0 -0.9 -0.8 -1.0 -0.8 -0.8 -0.7 -0.6 -0.9 -1.0 -0.7 -0.7 -0.7 -0.6 1.4 -3.0 -0.8 -0.8 0.5 1.0 0.9 -0.2 0.4 0.5 0.7 -0.1 0.6 1.0 0.7 2.8 -2.0 3.1 -2.3 -0.6 -0.6 -0.5 -0.3
: Job Ref : Sheet Ref / 128: D.O.C.K : OCT 2012 : F.O.O : K.M.M
G+Q-Nx G+Q+Ny G+Q-Ny G+Q *F (G+Q)P11 (G+Q)P12 (G+Q)P21 (G+Q)P22 (G+Q)P31 (G+Q)P32 (G+Q)P41 (G+Q)P42 (G+Q)P51 (G+Q)P52 G+Q+Nx G+Q-Nx G+Q+Ny G+Q-Ny G+Q *F (G+Q)P11 (G+Q)P12 (G+Q)P21 (G+Q)P22 (G+Q)P31 (G+Q)P32 (G+Q)P41 (G+Q)P42 (G+Q)P51 (G+Q)P52 G+Q+Nx G+Q-Nx G+Q+Ny G+Q-Ny G+Q *F (G+Q)P11 (G+Q)P12 (G+Q)P21 (G+Q)P22 (G+Q)P31 (G+Q)P32 (G+Q)P41 (G+Q)P42 (G+Q)P51 (G+Q)P52 G+Q+Nx G+Q-Nx G+Q+Ny G+Q-Ny G+Q *F (G+Q)P11 (G+Q)P12 (G+Q)P21 (G+Q)P22 (G+Q)P31 (G+Q)P32 (G+Q)P41 (G+Q)P42 (G+Q)P51 (G+Q)P52 G+Q+Nx G+Q-Nx G+Q+Ny G+Q-Ny G+Q *F (G+Q)P11 (G+Q)P12 (G+Q)P21
*F *F *F *F *F *F *F *F *F *F
*F *F *F *F *F *F *F *F *F *F
*F *F *F *F *F *F *F *F *F *F
*F *F *F *F *F *F *F *F *F *F
*F *F *F
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
1C6
1C6
1C7
1C7
5 6 7 8 9 10 11 12 13 14 15 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 1 2 3 4 5 6 7 8 9 10 11
-941.3 -1060.1 -995.2 -1082.8 -957.2 -1087.4 -991.3 -1031.0 -920.7 -1091.8 -859.9 -831.7 -723.6 -665.4 -645.2 -645.8 -741.8 -738.6 -694.2 -625.7 -714.5 -683.7 -565.7 -816.4 -611.5 -770.5 -424.1 -354.1 -317.7 -418.3 -387.9 -375.9 -366.5 -444.5 -326.2 -361.7 -384.0 -417.0 -295.4 -254.2 -458.3 -2927.7 -2485.7 -2918.7 -2210.3 -2893.0 -2925.5 -2916.1 -2209.6 -2914.2 -2490.8 -2902.2 -2447.8 -2446.7 -2460.9 -2433.6 -783.7 -581.1 -733.1 -818.8 -775.6 -782.1 -713.8 -809.7 -783.0 -613.5 -772.6
-1.9 3.0 9.8 -28.3 19.4 40.5 13.9 125.7 -128.7 161.4 -164.4 -0.1 0.2 0.0 -0.5 0.3 0.0 -0.1 -0.6 0.1 0.3 0.2 4.6 -4.8 -0.5 0.2 -0.2 0.1 -0.1 -0.6 0.2 -0.1 -0.2 -0.7 0.0 0.2 0.1 4.4 -4.8 -0.6 0.1 34.3 47.4 34.7 4.9 34.6 34.6 34.7 4.9 34.7 47.2 34.5 27.2 29.7 28.7 28.1 25.0 7.3 25.4 30.3 25.9 25.2 25.4 30.2 25.5 7.2 25.7
Job ref Sheet Made By Date Checked Approved
-0.4 -0.6 -0.6 -0.3 -0.5 -0.5 -0.4 0.1 -1.0 -0.4 -0.5 145.2 120.3 48.2 102.6 146.5 142.0 144.4 104.8 48.7 120.6 141.2 118.2 117.2 124.2 111.1 1.7 3.7 2.8 -0.9 1.8 1.6 2.4 -0.6 2.2 3.9 2.4 12.2 -9.5 6.6 -3.9 -0.2 0.1 0.4 -0.3 -0.4 -0.2 -0.1 -0.3 0.0 0.2 0.0 0.0 -0.4 3.9 -4.3 -6.3 -0.2 -6.0 -7.9 -6.4 -6.2 -7.3 -8.2 -5.5 0.6 -5.6
: Job Ref : Sheet Ref / 129: D.O.C.K : OCT 2012 : F.O.O : K.M.M
(G+Q)P22 (G+Q)P31 (G+Q)P32 (G+Q)P41 (G+Q)P42 (G+Q)P51 (G+Q)P52 G+Q+Nx G+Q-Nx G+Q+Ny G+Q-Ny G+Q *F (G+Q)P11 (G+Q)P12 (G+Q)P21 (G+Q)P22 (G+Q)P31 (G+Q)P32 (G+Q)P41 (G+Q)P42 (G+Q)P51 (G+Q)P52 G+Q+Nx G+Q-Nx G+Q+Ny G+Q-Ny G+Q *F (G+Q)P11 (G+Q)P12 (G+Q)P21 (G+Q)P22 (G+Q)P31 (G+Q)P32 (G+Q)P41 (G+Q)P42 (G+Q)P51 (G+Q)P52 G+Q+Nx G+Q-Nx G+Q+Ny G+Q-Ny G+Q *F (G+Q)P11 (G+Q)P12 (G+Q)P21 (G+Q)P22 (G+Q)P31 (G+Q)P32 (G+Q)P41 (G+Q)P42 (G+Q)P51 (G+Q)P52 G+Q+Nx G+Q-Nx G+Q+Ny G+Q-Ny G+Q *F (G+Q)P11 (G+Q)P12 (G+Q)P21 (G+Q)P22 (G+Q)P31 (G+Q)P32 (G+Q)P41 (G+Q)P42 (G+Q)P51 (G+Q)P52
*F *F *F *F *F *F *F
*F *F *F *F *F *F *F *F *F *F
*F *F *F *F *F *F *F *F *F *F
*F *F *F *F *F *F *F *F *F *F
*F *F *F *F *F *F *F *F *F *F
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
Job ref Sheet Made By Date Checked Approved
: Job Ref : Sheet Ref / 130: D.O.C.K : OCT 2012 : F.O.O : K.M.M
12 -720.8 19.6 4.7 G+Q+Nx 13 -600.2 21.9 -15.2 G+Q-Nx 14 -739.1 20.9 0.8 G+Q+Ny 15 -581.9 20.6 -11.3 G+Q-Ny Columns: 1W3, 1W1, 1W2, 1W4, 1W5, 1W6, 1C12, 1C16, 1C18, 1C17 bx = 6400.0 mm by = 8100.0 mm Effects: Critical Combination = 1 (G+Q *F) N = -18711.5 kN Mx = 10921.8 kN.m My = 8340.7 kN.m Footing Dimensions: Lx = 8000.0 mm Ly = 10200.0 mm h = 600.0 mm h-Tap = 0.0 mm Soil Stresses: S-max = 410.337 kN/m2 S-min = 89.318 kN/m2 Allowable Soil Stress will be amplified by the factor (x1.4) = 420.000 kN/m2 As-min (Both Dir's) = 1200.00 mm2/m X Dir: Footing Design: M = 129.2 kN.m/m K/K' = 0.12 < 1.0 As = 1200.00 mm2/m T20-250 Shear Check (At Column Face): (BS8110-Cl.3.4.5.2) v = 0.62 N/mm2 < v-max = 4.00 N/mm2 Shear Check (At 'd' from Column): (BS8110-Cl.3.4.5.2) v = 0.21 N/mm2 < vc = 0.39 N/mm2 Punching Check (At Column Face): (BS8110-Cl.3.7.6.4) Vt = 7434.9 kN V-eff = 9120.3 kN v = 0.58 N/mm2 < v-max = 4.00 N/mm2 Punching Check (At '1.5d'): (BS8110-Cl.3.7.6.4) Vt = 959.3 kN V-eff = 2644.8 kN v = 0.14 N/mm2 < vc = 0.39 N/mm2 Y Dir: Footing Design: M = 223.9 kN.m/m K/K' = 0.19 < 1.0 As = 1200.00 mm2/m T20-250 Shear Check (At Column Face): (BS8110-Cl.3.4.5.2) v = 0.78 N/mm2 < v-max = 4.00 N/mm2 Shear Check (At 'd' from Column): (BS8110-Cl.3.4.5.2) v = 0.37 N/mm2 < vc = 0.39 N/mm2 Punching Check (At Column Face): (BS8110-Cl.3.7.6.4) Vt = 7434.9 kN V-eff = 9120.3 kN v = 0.58 N/mm2 < v-max = 4.00 N/mm2 Punching Check (At '1.5d'): (BS8110-Cl.3.7.6.4) Vt = 959.3 kN V-eff = 2523.2 kN v = 0.13 N/mm2 < vc = 0.39 N/mm2
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
Job ref Sheet Made By Date Checked Approved
: Job Ref : Sheet Ref / 131: D.O.C.K : OCT 2012 : F.O.O : K.M.M
STRUT AND TIE (MEMBER) Member 1 (N.10-N.11) @ Level 1 Classification and Properties (BS 5950: 2000) Section (3.56 kg/m) Class = Fn(D/t,py) Auto Design Load Cases
48.3x3.2 CHS 3.56 [Grade 43] 15.09, 275 1
(Axial: Non-Slender)
Plastic
113.7 58.696 kN 0.375
OK Table 24 a OK
(Axial: Non-Slender)
Plastic
104.87 66.56 kN 0.543
OK Table 24 a OK
(Axial: Non-Slender)
Plastic
100.13 71.183 kN 0.620
OK Table 24 a OK
(Axial: Non-Slender)
Plastic
97.88 73.461 kN 0.632
OK Table 24 a OK
(Axial: Non-Slender)
Plastic
115.14 64.241 kN
OK Table 24 a
Strut by One Row of Bolts or Equivalent Weld (Case 1) λ = Fn(Lx,Ly,rx,ry) Pc = Area.pc F (Strut)/Pc
1.819,1.819,1.6,1.6 4.53x129.57/10 = 21.992 / 58.696
STRUT AND TIE (MEMBER) Member 3 (N.11-N.12) @ Level 1 Classification and Properties (BS 5950: 2000) Section (3.56 kg/m) Class = Fn(D/t,py) Auto Design Load Cases
48.3x3.2 CHS 3.56 [Grade 43] 15.09, 275 1
Strut by One Row of Bolts or Equivalent Weld (Case 1) λ = Fn(Lx,Ly,rx,ry) Pc = Area.pc F (Strut)/Pc
1.678,1.678,1.6,1.6 4.53x146.93/10 = 36.147 / 66.56
STRUT AND TIE (MEMBER) Member 5 (N.12-N.13) @ Level 1 Classification and Properties (BS 5950: 2000) Section (3.56 kg/m) Class = Fn(D/t,py) Auto Design Load Cases
48.3x3.2 CHS 3.56 [Grade 43] 15.09, 275 1
Strut by One Row of Bolts or Equivalent Weld (Case 1) λ = Fn(Lx,Ly,rx,ry) Pc = Area.pc F (Strut)/Pc
1.602,1.602,1.6,1.6 4.53x157.14/10 = 44.142 / 71.183
STRUT AND TIE (MEMBER) Member 7 (N.13-N.14) @ Level 1 Classification and Properties (BS 5950: 2000) Section (3.56 kg/m) Class = Fn(D/t,py) Auto Design Load Cases
48.3x3.2 CHS 3.56 [Grade 43] 15.09, 275 1
Strut by One Row of Bolts or Equivalent Weld (Case 1) λ = Fn(Lx,Ly,rx,ry) Pc = Area.pc F (Strut)/Pc
1.566,1.566,1.6,1.6 4.53x162.17/10 = 46.435 / 73.461
STRUT AND TIE (MEMBER) Member 9 (N.1-N.2) @ Level 1 Classification and Properties (BS 5950: 2000) Section (3.97 kg/m) Class = Fn(D/t,py) Auto Design Load Cases
48.3x3.6 CHS 3.97 [Grade 43] 13.42, 275 1
Strut by One Row of Bolts or Equivalent Weld (Case 1) λ = Fn(Lx,Ly,rx,ry) Pc = Area.pc
1.819,1.819,1.58,1.58 5.06x126.96/10 =
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected], F (Strut)/Pc
Job ref Sheet Made By Date Checked Approved
: Job Ref : Sheet Ref / 132: D.O.C.K : OCT 2012 : F.O.O : K.M.M
62.227 / 64.241
0.969
OK
(Axial: Non-Slender)
Plastic
104.87 66.56 kN 0.570
OK Table 24 a OK
(Axial: Non-Slender)
Plastic
100.13 71.183 kN 0.296
OK Table 24 a OK
(Axial: Non-Slender)
Plastic
97.88 73.461 kN 0.152
OK Table 24 a OK
(Axial: Non-Slender)
Plastic
3.94 cm² 108.35 kN 0.181
OK
(Axial: Non-Slender)
Plastic
STRUT AND TIE (MEMBER) Member 11 (N.2-N.3) @ Level 1 Classification and Properties (BS 5950: 2000) Section (3.56 kg/m) Class = Fn(D/t,py) Auto Design Load Cases
48.3x3.2 CHS 3.56 [Grade 43] 15.09, 275 1
Strut by One Row of Bolts or Equivalent Weld (Case 1) λ = Fn(Lx,Ly,rx,ry) Pc = Area.pc F (Strut)/Pc
1.678,1.678,1.6,1.6 4.53x146.93/10 = 37.917 / 66.56
STRUT AND TIE (MEMBER) Member 13 (N.3-N.4) @ Level 1 Classification and Properties (BS 5950: 2000) Section (3.56 kg/m) Class = Fn(D/t,py) Auto Design Load Cases
48.3x3.2 CHS 3.56 [Grade 43] 15.09, 275 1
Strut by One Row of Bolts or Equivalent Weld (Case 1) λ = Fn(Lx,Ly,rx,ry) Pc = Area.pc F (Strut)/Pc
1.602,1.602,1.6,1.6 4.53x157.14/10 = 21.056 / 71.183
STRUT AND TIE (MEMBER) Member 15 (N.4-N.5) @ Level 1 Classification and Properties (BS 5950: 2000) Section (3.56 kg/m) Class = Fn(D/t,py) Auto Design Load Cases
48.3x3.2 CHS 3.56 [Grade 43] 15.09, 275 1
Strut by One Row of Bolts or Equivalent Weld (Case 1) λ = Fn(Lx,Ly,rx,ry) Pc = Area.pc F (Strut)/Pc
1.566,1.566,1.6,1.6 4.53x162.17/10 = 11.156 / 73.461
STRUT AND TIE (MEMBER) Member 17 (N.2-N.10) @ Level 1 Classification and Properties (BS 5950: 2000) Section (3.09 kg/m) Class = Fn(D/t,py) Auto Design Load Cases
42.4x3.2 CHS 3.09 [Grade 43] 13.25, 275 1
Axially Loaded Member in Tension : 3.4.3 (Case 1) Ae = Fn(Ag,A.net,py,Us) Tc = Ae.py F (Tie)/Tc
3.94,3.94,275,410 3.94x275/10 = 19.594 / 108.35
STRUT AND TIE (MEMBER) Member 19 (N.3-N.11) @ Level 1 Classification and Properties (BS 5950: 2000) Section (3.09 kg/m) Class = Fn(D/t,py) Auto Design Load Cases
42.4x3.2 CHS 3.09 [Grade 43] 13.25, 275 1
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
Job ref Sheet Made By Date Checked Approved
: Job Ref : Sheet Ref / 133: D.O.C.K : OCT 2012 : F.O.O : K.M.M
Axially Loaded Member in Tension : 3.4.3 (Case 1) Ae = Fn(Ag,A.net,py,Us) Tc = Ae.py F (Tie)/Tc
3.94,3.94,275,410 3.94x275/10 = 17.27 / 108.35
3.94 cm² 108.35 kN 0.159
OK
(Axial: Non-Slender)
Plastic
3.94 cm² 108.35 kN 0.110
OK
(Axial: Non-Slender)
Plastic
3.94 cm² 108.35 kN 0.041
OK
(Axial: Non-Slender)
Plastic
STRUT AND TIE (MEMBER) Member 21 (N.4-N.12) @ Level 1 Classification and Properties (BS 5950: 2000) Section (3.09 kg/m) Class = Fn(D/t,py) Auto Design Load Cases
42.4x3.2 CHS 3.09 [Grade 43] 13.25, 275 1
Axially Loaded Member in Tension : 3.4.3 (Case 1) Ae = Fn(Ag,A.net,py,Us) Tc = Ae.py F (Tie)/Tc
3.94,3.94,275,410 3.94x275/10 = 11.91 / 108.35
STRUT AND TIE (MEMBER) Member 23 (N.5-N.13) @ Level 1 Classification and Properties (BS 5950: 2000) Section (3.09 kg/m) Class = Fn(D/t,py) Auto Design Load Cases
42.4x3.2 CHS 3.09 [Grade 43] 13.25, 275 1
Axially Loaded Member in Tension : 3.4.3 (Case 1) Ae = Fn(Ag,A.net,py,Us) Tc = Ae.py F (Tie)/Tc
3.94,3.94,275,410 3.94x275/10 = 4.432 / 108.35
STRUT AND TIE (MEMBER) Member 25 (N.1-N.10) @ Level 1 Classification and Properties (BS 5950: 2000) Section (3.56 kg/m) Class = Fn(D/t,py) Auto Design Load Cases
48.3x3.2 CHS 3.56 [Grade 43] 15.09, 275 1
STRUT AND TIE (MEMBER) Member 27 (N.2-N.11) @ Level 1 Classification and Properties (BS 5950: 2000) Section (3.09 kg/m) Class = Fn(D/t,py) Auto Design Load Cases
42.4x3.2 CHS 3.09 [Grade 43] 13.25, 275 1
(Axial: Non-Slender)
Plastic
112.45 51.971 kN 0.488
OK Table 24 a OK
(Axial: Non-Slender)
Plastic
Strut by One Row of Bolts or Equivalent Weld (Case 1) λ = Fn(Lx,Ly,rx,ry) Pc = Area.pc F (Strut)/Pc
1.563,1.563,1.39,1.39 3.94x131.91/10 = 25.338 / 51.971
STRUT AND TIE (MEMBER) Member 29 (N.3-N.12) @ Level 1 Classification and Properties (BS 5950: 2000) Section (3.09 kg/m) Class = Fn(D/t,py) Auto Design Load Cases
42.4x3.2 CHS 3.09 [Grade 43] 13.25, 275 1
Kiri Consult Ltd Civil, Structural, Project Management, Surveying & Environmental Consultants Lenana Close, Off Lenana Road, Hurlingham NAIROBI Tel: 020-2714897 P.O Box: 4125-00506 Nbr. Fax: 020- 2714896 Email:
[email protected],
Job ref Sheet Made By Date Checked Approved
: Job Ref : Sheet Ref / 134: D.O.C.K : OCT 2012 : F.O.O : K.M.M
Strut by One Row of Bolts or Equivalent Weld (Case 1) λ = Fn(Lx,Ly,rx,ry) Pc = Area.pc F (Strut)/Pc
1.563,1.563,1.39,1.39 3.94x131.91/10 = 18.2 / 51.971
112.45 51.971 kN 0.350
OK Table 24 a OK
(Axial: Non-Slender)
Plastic
112.45 51.971 kN 0.214
OK Table 24 a OK
(Axial: Non-Slender)
Plastic
112.45 51.971 kN 0.147
OK Table 24 a OK
STRUT AND TIE (MEMBER) Member 31 (N.4-N.13) @ Level 1 Classification and Properties (BS 5950: 2000) Section (3.09 kg/m) Class = Fn(D/t,py) Auto Design Load Cases
42.4x3.2 CHS 3.09 [Grade 43] 13.25, 275 1
Strut by One Row of Bolts or Equivalent Weld (Case 1) λ = Fn(Lx,Ly,rx,ry) Pc = Area.pc F (Strut)/Pc
1.563,1.563,1.39,1.39 3.94x131.91/10 = 11.108 / 51.971
STRUT AND TIE (MEMBER) Member 33 (N.5-N.14) @ Level 1 Classification and Properties (BS 5950: 2000) Section (3.09 kg/m) Class = Fn(D/t,py) Auto Design Load Cases
42.4x3.2 CHS 3.09 [Grade 43] 13.25, 275 1
Strut by One Row of Bolts or Equivalent Weld (Case 1) λ = Fn(Lx,Ly,rx,ry) Pc = Area.pc F (Strut)/Pc
1.563,1.563,1.39,1.39 3.94x131.91/10 = 7.625 / 51.971