Rapid Package
March 10, 2017 | Author: Feruzatan | Category: N/A
Short Description
List of Contractors who won the Malaysia RAPID Package...
Description
RAPID PACKAGE SUMMARY
Five of the contracts are for engineering, procurement, construction, and commissioning (EPCC) for RAPID’s refinery and steam cracker component, Petronas said.
The Package 1 to Package 5 EPCC contracts were awarded to as listed
Package 1 o A consortium of CTCI Corp., Chiyoda Corp., Synerlitz (Malaysia) Sdn. Bhd., and MIE Industrial Sdn. Bhd. for the residue fluid catalytic cracking units (RFCC), LPG treating unit (LTU), propylene recovery unit (PRU), and caustic neutralization units.
Package 2 o Sinopec Engineering (Group) Co. Ltd. and Sinopec Engineering Group (Malaysia) Sdn. Bhd. for the crude distillation unit (CDU), atmospheric residue desulfurization units (ARDS), and hydrogen collection and distribution units (HCDU)
Package 3 o Tecnicas Reunidas SA and Tecnicas Reunidas Malaysia Sdn. Bhd. for the kerosene hydrotreating unit (KHT), diesel hydrotreating unit (DHT), naphtha hydrotreating unit (NHT), cracked-naphtha hydrotreating unit (CNHT), and continuous catalytic reformer units (CCR).
Package 4 o Petrofac International (UAE) LLC and Petrofac E&C Sdn. Bhd. for the amine recovery units (ARU), sulfur recovery units (SRU), sour water stripping units (SWS), liquid sulfur storage unit (LSSU), and sulfur solidification units (SSU)
Package 5 o Toyo Engineering Corp. and Toyo Engineering & Construction Sdn. Bhd. for the steam cracker complex consists of SCU, PGH, BDU, BZU, IBU (MTBE).
Package 22 o Tank farm awarded to Punj Lloyd with USD581M
The remaining six contracts, which involve construction of the project’s related infrastructure, were awarded as listed: • A consortium of UEM Builders Bhd. and Projek Penyelenggaraan Lebuhraya Bhd. for EPCC of temporary common-camp installations and infrastructure. • Zelan Construction Sdn. Bhd. for the basic design and EPCC of the material offloading facilities jetty at Tanjung Setapa. • WCT Bhd. for common construction access and permanent roads within the project site. • Syarikat Ismail Ibrahim Sdn. Bhd. for the temporary access road within the project site. • Bumi Dagang Sdn. Bhd. for construction of the main haulage road as well as an access road outside the project site. • Gadang Engineering (M) Sdn. Bhd. and Menta Construction Sdn. Bhd. for the Phase 2 site preparation works.
The company previously let a program management consultancy (PMC) contract, which includes overall project and site management, to a Technip SA-led joint venture with Fluor Corp. for specific EPCC packages within RAPID. Additionally, Petronas let an EPCC contract and long-term service agreement in June to a consortium of Siemens AG, Siemens Malaysia Sdn. Bhd., and MMC Engineering Services Sdn. Bhd. for the Pengerang cogeneration plant, one of RAPID’s associated installations, the company said. Petronas also let two procurement, construction, and commissioning (PCC) contracts in April for other RAPID-related associated installations. The first PCC contract was awarded to a consortium of Asia Baru Construction Sdn. Bhd. and Putra Perdana Construction Sdn. Bhd. for the Raw Water Supply Project, which will support RAPID’s raw water needs, while a second PCC contract went to a consortium of PBJV Group Sdn. Bhd. and CPM Construction Sdn. Bhd. for the Pengerang Gas Pipeline Project (PGPP), Petronas said. PGPP is part of the expansion of Malaysia’s Peninsular Gas Utilization pipeline network to the RAPID complex, subsidiary Petronas Gas Bhd.
Other associated installations to be included in RAPID will be Regasification Terminal 2 (RGT2), an air-separation unit, as well as crude and product tanks, the company said.
Package 6A: EPCC of LLDPE Unit Licensor: INEOS Tender No.: RAPID/CTC/28-2014-P6A Date of ITB Issue: 17/11/2014 Package 6B: EPCC of LDPE Unit Licensor: Exxonmobil Tender No.: RAPID/CTC/29-2014-P6B Date of ITB Issue: 17/11/2014 Package 7:
EPCC of Polypropylene Unit Licensor: Lyondell Bassell Tender No.: RAPID/CTC/XX-20XX-P7 Date of ITB Issue: 23/2/2015
Package 8:
EPCC of CPU, PPU, BPA and Phenolic Tank Farm Units Licensor: UOP, Lummus, Badger Tender No.: RAPID/CTC/15-2013-P8 Date of ITB Issue: 29/10/2014
Package 9:
EPCC of Elastomer/Rubber Licensor: Versalis Tender No.: RAPID/CTC/XX-2014-P9 Date of ITB Issue: 25/3/2015
Package 11: EPCC of EO/EG and EO/EG Tank Farms Unit Licensor: Shell Tender No.: RAPID/CTC/16-2013-P11 Date of ITB Issue: 7/1/2015 Package 12A:
EPCC of Solid Handling Facilities (Warehouse)
Package 26: EPCC OF Polycarbonate and Polycarbonate Tank farm Units Licensor: Asahi Kasei Tender No.: RAPID/CTC/XX-2014-P26 Date of ITB Issue: 25/11/2014