RENCANA ANGGARAN BIAYA (RAB) PEKERJAAN
: Rumah Type 45/70
LOKASI No I
Uraian Pekerjaan
Volume
: ……………………………………………………………… Harga Sat/Upah. Jumlah Sat. Indeks Rp. Rp.
PEKERJAAN PERSIAPAN 1 Pek. Pembersihan lokasi a. Pekerja b. Mandor
70
m2
10m2
org/hr
0.75
50,000.00
10m2
org/hr
0.025
80,000.00
37,500.00 2,000.00 39,500 x 70 /10
2 Pek. Direksi Keet
9
m2
120,000.00
1,080,000.00
3 Pek. Bouwplank
53
m1
a. Papan
10m2
m3
b. Kaso
10m2
m3
0.005
8,000,000.00
40,000.00
0.005
8,000,000.00
40,000.00
c. Paku
10m2
kg
0.1
12,000.00
1,200.00
d. Tukang
10m2
e. Pekerja
10m2
org/hr
0.8
80,000.00
64,000.00
org/hr
0.28
50,000.00
14,000.00
f. Mandor
10m2
org/hr
0.014
80,000.00
1,120.00 160320 x 53 /10
No I
Total Harga Rp.
Uraian Pekerjaan PEKERJAAN PERSIAPAN 1 Pek. Pembersihan lokasi
276,500.00
2 Pek. Direksi Keet
1,080,000.00
3 Pek. Bouwplank
849,696.00
Jumlah
dibulatkan
2,206,196.00 2,206,200.00
Jumlah Total Rp.
2,765,000.00 276,500.00
1,080,000.00
8,496,960.00 849,696.00
Nama : Anugrah Ramadhan SA Kelas : 3TB02 NPM : 21309399 RENCANA ANGGARAN BIAYA (RAB) PEKERJAAN
: Rumah Type 45/70
LOKASI No II
Uraian Pekerjaan
Volume
: ……………………………………………………………… Harga Sat/Upah. Sat. Indeks Rp.
PEKERJAAN BETON 1 Pek. Beton Sloof 15/20
1.59
m3
a. Semen
m3
6.72
57,000.00
b. Pasir
m3
0.54
200,000.00
c. Split
m3
0.82
200,000.00
d. Pekerja
org/hr
3
50,000.00
e. Tukang Batu
org/hr
1
80,000.00
f. Mandor
org/hr
0.1
80,000.00
2 Pek. Beton Kolom 15/15
1.0125
m3
a. Semen
m3
6.72
57,000.00
b. Pasir
m3
0.54
200,000.00
c. Split
m3
0.82
200,000.00
d. Pekerja
org/hr
3
50,000.00
e. Tukang Batu
org/hr
1
80,000.00
f. Mandor
org/hr
0.1
80,000.00
3 Pek. Beton Kolom 30/30
0.27
m3
a. Semen
m3
6.72
57,000.00
b. Pasir
m3
0.54
200,000.00
c. Split
m3
0.82
200,000.00
d. Pekerja
org/hr
3
50,000.00
e. Tukang Batu
org/hr
1
80,000.00
f. Mandor
org/hr
0.1
80,000.00
3 Pek. Beton Ring Balok 15/20
1.59
m3
a. Semen
m3
6.72
57,000.00
b. Pasir
m3
0.54
200,000.00
c. Split
m3
0.82
200,000.00
d. Pekerja
org/hr
3
50,000.00
e. Tukang Batu
org/hr
1
80,000.00
f. Mandor
org/hr
0.1
80,000.00
No II
Total Harga Rp.
Uraian Pekerjaan PEKERJAAN BETON 1 Pek. Beton Sloof 15/20
1,419,933.00
2 Pek. Beton Kolom 15/15
904,203.00
3 Pek. Beton Kolom 30/30
241,120.00
4 Pek. Beton Ring Balok 15/20
1,419,933.00
Jumlah dibulatkan
3,985,189.00 3,985,200.00
Jumlah
Jumlah Total
Rp.
Rp.
383,040.00 108,000.00 164,000.00 150,000.00 80,000.00 8,000.00 893,040 x 1.59
1,419,933.00
383,040.00 108,000.00 164,000.00 150,000.00 80,000.00 8,000.00 893,040 x 1.0125
904,203.00
383,040.00 108,000.00 164,000.00 150,000.00 80,000.00 8,000.00 893,040 x 0.27
241,120.00
383,040.00 108,000.00 164,000.00 150,000.00 80,000.00 8,000.00 893,040 x 1.59
1,419,933.00
RENCANA ANGGARAN BIAYA (RAB) PEKERJAAN
: Rumah Type 45/70
LOKASI No II
Uraian Pekerjaan
Volume
Sat.
53
m1
: ……………………………………………………………… Harga Sat/Upah. Jumlah Indeks Rp. Rp.
PEKERJAAN PONDASI 1 Pek. Galian Tanah a. Pekerja
org/hr
0.4
50,000.00
20,000.00
b. Mandor
org/hr
0.02
80,000.00
1,600.00 21,600 x 53
2 Pek. Pengurugan Tanah Kembali
3 Pek. Pasir Bawah Pondasi
53
m1
10.6
m3
1/4
1,144,800.00
286,200.00
a. Pekerja
org/hr
0.3
50,000.00
15,000.00
b. Mandor
org/hr
0.01
80,000.00
800.00 15,800 x 10.6
4 Material Pasir
10.6
m3
5 Pas. Batu Kali
23.32
m3
200,000.00
2,120,000.00
a. Batu Kali
m3
1,1
180,000.00
198,000.00
b. Pasir
m3
0.49
200,000.00
98,000.00
c. Semen
m3
4.04
57,000.00
230,280.00
d. Tukang Batu
org/hr
0.6
70,000.00
42,000.00
e. Pekerja
org/hr
1.5
50,000.00
75,000.00
f. Mandor
org/hr
0.02
80,000.00
1,600.00 644,880 x 23.32
No II
Total Harga Rp.
Uraian Pekerjaan PEKERJAAN PONDASI 1 Pek. Galian Tanah
1,144,800.00
2 Pek. Pengurugan Tanah Kembali
286,200.00
3 Pek. Pasir Bawah Pondasi
167,480.00
4 Material Pasir
2,120,000.00
5 Pas. Batu Kali
15,038,601.00
Jumlah dibulatkan
18,757,081.00 18,757,100.00
Jumlah Total Rp.
1,144,800.00
286,200.00
167,480.00
2,120,000.00
15,038,601.00