QCP-Piping Prefab Erection Rev.2
Short Description
QCP-Piping Prefab Erection Rev.2...
Description
JOB
UNIT
670700
000
SPC. 000-ZA-E-02631 Sh. 1 of 54
BUILDING NEW BOOSTER STATION BS-160 AT SOUTH EAST KUWAIT
Rev. 2
Document title: Quality Control Plan for Piping Prefabrication and Erection Subcontract No. Unit: P300009297 General Contract No. 37472
Doc. class.: A
KOC Doc. No. -----------------
KHARAFI NATIONAL
QUALITY CONTROL PLAN FOR PIPING PREFABRICATION AND ERECTION
2
Revised as indicated and Issued for Company Review and Approval
Farukh Butt
Fouad Khordahij
Mancini
29-03-10
1
Revised as indicated and Issued for Company Review and Approval
Farukh Butt
Fouad Khordahij
Mancini
06-02-10
0
Approved for Implementation (Ref. Letter 37472/KS/T/03639)
Farukh Butt
Fouad Khordahij
Mancini
02-11-09
C
Re-issued for Company Review and Approval (Ref. Letter 37472/KS/T/02898)
Farukh Butt
Fouad Khordahij
Mancini
13-09-09
B
Re-issued for Company Review and Approval (Ref. Letter 37472/KS/T/02239 and 02327)
Farukh Butt
Fouad Khordahij
Mancini
05-08-09
A
Issued for Company Review and Approval
Farukh Butt
Jean Yazji
Mancini
17-06-09
Prepared
Checked
Approved
Date
Rev.
Description
This document is the property of SAIPEM who will safeguard its rights according to the civil and penal provisions of the law.
335226530.doc
JOB
UNIT
670700
000
SPC. 000-ZA-E-02631 BUILDING NEW BOOSTER STATION BS-160 AT SOUTH EAST KUWAIT
Sh. 2 of 54
Document title: Quality Control Plan for Piping Prefabrication and Erection Subcontract No. Unit: P300009297 General Contract No. 37472
Rev. 2
Doc. class.: A
KOC Doc. No. -----------------
REVISION RECORD SHEET NOTES i)
Revisions after Rev. 1A, A & 0 are denoted by a vertical line in the left hand margin against the revised text, with the revision number displayed next to the revision line as shown on the left.
ii)
Revision nos. 1A, 2A, 3A etc. are issued for Contractor approval
iii)
Revision nos. A, B, C are issued for Company approval, and implementation after Company approval is Rev.0. Subsequent revisions are 1, 2, 3 etc.
2
No.
Date
1A
17 Mar. 2009
2A
Description of Revision
By
Rev.
App.
Issued for Contractor Review & Approval
Farukh Butt
Jean Yazji
Mancini
11 May. 2009
Reissued for Contractor Review & Approval
Farukh Butt
Jean Yazji
Mancini
A
17 June. 2009
Issued for Company Review & Approval
Farukh Butt
Jean Yazji
Mancini
B
05 Aug. 2009
Farukh Butt
Fouad Khordahij
Mancini
C
13 Aug.2009
Re-issued for Company Review & Approval (Ref. Letter 37472/KS/T/02239 and 02327 ) Re-issued for Company Review and Approval (Ref. Letter 37472/KS/T/02898)
Farukh Butt
Fouad Khordahij
Mancini
0
02 Nov.2009
Approved for Implementation (Ref. Letter 37472/KS/T/03639)
Farukh Butt
Fouad Khordahij
Mancini
1
06 Feb. 2010
Revised as indicated and Issued for Company Review and Approval
Farukh Butt
Fouad Khordahij
Mancini
2
29 Mar. 2010
Revised as indicated and Issued for Company Review and Approval
Farukh Butt
Fouad Khordahij
Mancini
This document is the property of SAIPEM who will safeguard its rights according to the civil and penal provisions of the law.
335226530.doc
JOB
UNIT
670700
000
SPC. 000-ZA-E-02631 BUILDING NEW BOOSTER STATION BS-160 AT SOUTH EAST KUWAIT
Sh. 3 of 54
Document title: Quality Control Plan for Piping Prefabrication and Erection Subcontract No. Unit: P300009297 General Contract No. 37472
Rev. 2
Doc. class.: A
KOC Doc. No. -----------------
CONTENTS
1.
2.
3.
4.
5.
GENERAL 1.1.
Scope and Objective
1.2.
Terms and definitions
QUALITY CONTROL PLANNING 2.1.
Information Related to this Document
2.2.
Issuing of QCP and ITPs
2.3.
Subcontractor responsibility
2.4.
Local Regulations
APPLICABLE DOCUMENTATION 3.1.
Specifications Codes and Standards
3.2.
Applicable Revision
3.3.
Construction Item definition
PIPING ERECTION 4.1.
General
4.2.
Materials Handling
4.3.
Materials Traceability
4.4.
Fit-Up of piping
4.5.
Threaded joints
4.6.
Flanged joints
4.7.
Pressure Testing
4.8.
Specific Requirements for Placing Underground RTR/Thermoplastic Material Piping in Trenches
ATTACHMENTS 5.1.
ITP LIST
5.2.
INSTALLATION FORMS LIST
5.3.
PRECOMMISSIONING FORMS LIST
This document is the property of SAIPEM who will safeguard its rights according to the civil and penal provisions of the law.
335226530.doc
JOB
UNIT
670700
000
SPC. 000-ZA-E-02631 BUILDING NEW BOOSTER STATION BS-160 AT SOUTH EAST KUWAIT
Sh. 4 of 54
Document title: Quality Control Plan for Piping Prefabrication and Erection Subcontract No. Unit: P300009297 General Contract No. 37472
Rev. 2
Doc. class.: A
KOC Doc. No. -----------------
1
GENERAL
2
Scope and Objective
3
This document provides guidance and minimum requirements of Subcontractor for inspecting, checking and testing piping prefabrication and erection during construction of “BUILDING NEW BOOSTER STATION BS-160 AT SOUTH EAST KUWAIT”.
4
This document is additional to QAS No. 000-ZA-E-09698 (Quality Assurance Requirements for Construction Subcontractor), QAS No. 000-ZA-E-09699 (Quality Control Requirements for Contractor), (internal documents of Contractor) and shall be read together other applicable contractual documentation.
5
Terms and definitions
6
The following terms and definitions are applicable to all Contractor specifications related to quality requirements for Subcontractors. Sub Contractor Kharafi National, including its Subcontractor to whom any part of the Works has been subcontracted by Contractor/Company. Contractor
Saipem appointed by Company to perform the Works.
Company
Kuwait Oil Company that receives the services related to the Works provided by Contractor and by its Subcontractor(s).
TPI
Third Party Inspection: Any organization, authority, person or persons, to which Subcontractor has subcontracted the execution of inspection and or laboratory testing, related activities.
Works
Means the permanent new, revamped and refurbished facilities constituting the Project, including all the construction services, materials and equipment to be provided by Contractor/Company to satisfy ITP obligations pursuant to the Contract undertaken with the Company.
QMS
Quality Management System: part of the organization’s management system that focuses on achievement of results, in relation to the quality objectives, to satisfy the needs, expectations and requirements of Contractor/Company and of any other interested parties, as appropriate.
QAS
Quality Assurance Specification: Contractor document specifying the minimum requirements related to Subcontractor’s QMS and QA/QC Manual specific for the Works.
QCP
Quality Control Specification: Subcontractor plan containing all quality control requirements. This Plan complements and compiles all applicable ITP(s).
ITP
Inspection and Test Plan: Subcontractor plan of inspection and tests required by engineering and vendors documents or elsewhere specified. ITP(s) shall provide references to applicable procedures, acceptance criteria, documentation, quality records and inspection attendance to be performed, in chronological order, from initial inspection, throughout final inspections and mechanical completion. ITP(s) and relevant forms shall be issued as QCP enclosures.
This document is the property of SAIPEM who will safeguard its rights according to the civil and penal provisions of the law.
335226530.doc
JOB
UNIT
670700
000
SPC. 000-ZA-E-02631 BUILDING NEW BOOSTER STATION BS-160 AT SOUTH EAST KUWAIT
Sh. 5 of 54
Document title: Quality Control Plan for Piping Prefabrication and Erection Subcontract No. Unit: P300009297 General Contract No. 37472
Rev. 2
Doc. class.: A
KOC Doc. No. -----------------
IN
Inspection Notification: Written notification to be issued by Subcontractor in order to allow all parties involved to perform their inspection and test witness as planned in the applicable ITP.
QA
Quality Assurance: Part of quality management focused on providing confidence that quality requirements will be fulfilled.
QC
Quality Control: Part of quality management focused on fulfilling quality requirements.
NCR
Non Conformity Report: Document recording a non-fulfilment of a requirement.
Non Conformity The non-fulfilment of specified requirements. Special Process A process, the results of which are highly dependent on the control of the process or the skill of the operator and in which the specified quality cannot be readily determined by inspection or test on the product. Calibration
Comparison of a measurement and test equipment with a reference standard or with another one provided with better tolerance in order to detect or to measure possible inaccuracies and to document or eliminate them.
7
Any other terms related to quality and not listed above shall conform to section 3 “Term and Definition” of ISO 9000:2000 “Quality Management System – Fundamentals and vocabulary”.
8
QUALITY CONTROL PLANNING
9
Information Related to this Document
10
This document includes the ITP(s) and forms, listed under paragraph 5.1 and 5.2, for performing inspection, tests to be carried out during site activities related to piping prefabrication and erection works.
11
The ITP’s are separated in two groups: 1. General ITP(s) include but are not limited to the following initial checks and
verification: This document is the property of SAIPEM who will safeguard its rights according to the civil and penal provisions of the law.
335226530.doc
JOB
UNIT
670700
000
SPC. 000-ZA-E-02631 BUILDING NEW BOOSTER STATION BS-160 AT SOUTH EAST KUWAIT
Sh. 6 of 54
Document title: Quality Control Plan for Piping Prefabrication and Erection Subcontract No. Unit: P300009297 General Contract No. 37472
Rev. 2
Doc. class.: A
KOC Doc. No. -----------------
- Documentation - Personnel and equipment - Material receiving - Ambient conditions - Etc. These ITPs and relevant inspection and testing activities are coded with series TB.000X.XX. 2. Specific ITP(s) include inspection and tests which are directly related to construction
items and or part of the Works that can be identified and tracked through engineering drawings. These ITPs and relevant inspection activities are coded with series TB.010X.XX.
This document is the property of SAIPEM who will safeguard its rights according to the civil and penal provisions of the law.
335226530.doc
JOB
UNIT
670700
000
SPC. 000-ZA-E-02631 BUILDING NEW BOOSTER STATION BS-160 AT SOUTH EAST KUWAIT
Sh. 7 of 54
Document title: Quality Control Plan for Piping Prefabrication and Erection Subcontract No. Unit: P300009297 General Contract No. 37472
Rev. 2
Doc. class.: A
KOC Doc. No. -----------------
12
Issuing of QCP and ITPs
13
Subcontractor has issue this document same as site QCP and ITP(s) using format template.
14
If additional QC Codes are required, the same shall be numbered adding an alphanumeric suffix to the preceding available QC Code. New QC Codes shall be approved by Contractor.
15
Subcontractor during the execution of the Works shall revise and update, as and when required, the QCP to incorporate any other pertinent requirements set forth in engineering specifications, standards, design codes, recommended practices, safety design, referred hereafter or included elsewhere in the contractual and vendor documents.
16
Prior to start construction work the QCP shall be submitted for review and approval.
17
Subcontractor responsibility
18
Subcontractor will prepare and update any other necessary QCP(s) and ITP(s), and quality procedures to include all inspections, examinations and tests required to verify the quality of the Works. The above documents shall be timely submitted to Contractor for review and approval in order to ensure their availability in approved status prior to starting of the piping prefabrication and erection work.
19
Subcontractor will perform and record all inspections, examinations and tests required as per contract and shall carry out all the works necessary for the preparation of inspections, examinations and tests, including adequate scaffolding for safely witnessing the inspection.
20
Subcontractor will provide, for the execution of testing, inspection and measurements all necessary equipment, tools and shall make available the applicable international Standards and Codes.
21
Subcontractor will issue inspections, examinations and tests reports immediately after the completion of each inspection activity. All reports shall be approved and signed off by Subcontractor authorized personal prior to submission to Contractor for review or approval, as appropriate.
22
Other Parties signature on inspection, examination and test reports does not release the Subcontractor from his responsibilities.
23
Local Regulations
24
Inspections and tests required by local regulations are out from the scope of this Plan. However, they shall be strictly adhered to and documented by Subcontractor. Copy of such records shall be submitted for review.
25
When local regulations are less stringent than the applicable design codes, the latter shall prevail.
This document is the property of SAIPEM who will safeguard its rights according to the civil and penal provisions of the law.
335226530.doc
JOB
UNIT
670700
000
SPC. 000-ZA-E-02631 BUILDING NEW BOOSTER STATION BS-160 AT SOUTH EAST KUWAIT
Sh. 8 of 54
Document title: Quality Control Plan for Piping Prefabrication and Erection Subcontract No. Unit: P300009297 General Contract No. 37472
26
APPLICABLE DOCUMENTATION
27
Specifications Codes and Standards
3.1.1
Project Specifications 015-LH-1001-EF1655
-
SPC-1655-PM-4200-01
-
SPC-1655-PM-4200-02 SPC-1655-WM-01 15-WH-1002
-
CRT-1655-KOC-P001
-
KOC-P-001
-
015-WH-1001 Quality
-
Rev. 2
Doc. class.: A
KOC Doc. No. -----------------
Addendum to Specification for piping material Classes KOC specification for pressure testing piping Systems KOC Spec for piping Fabrication and Erection KOC Spec for General Welding requirements Field Welding requirements: Welding Heat Treatment and NDT of Piping Painting and Coating of metal surface – new Construction Painting and Coating of metal surface – new Construction Welding Procedure Approval & Welding Requirement
3.1.2
3.1.3
Subcontractor’s Technical Work Instructions 000-AZ-E-02580
-
Piping Erection
000-AZ-E-02588
-
Positive Material Identification Procedure (Intrex)
000-AZ-E-02590
-
Alloy Verification Procedure (HEISCO)
000-AZ-E-02577
-
Fabrication, Installation and Testing of RTRP Piping
000-AZ-E-02543
-
Procedure for Pressure Test - Piping
000-AZ-E-02576
-
Piping Fabrication
000-AZ-E-02581
-
Fabrication and Installation of Galvanized Iron-Piping
Codes and Standards Refer to the codes and standards contained in the above specification
This document is the property of SAIPEM who will safeguard its rights according to the civil and penal provisions of the law.
335226530.doc
JOB
UNIT
670700
000
SPC. 000-ZA-E-02631 BUILDING NEW BOOSTER STATION BS-160 AT SOUTH EAST KUWAIT
Sh. 9 of 54
Document title: Quality Control Plan for Piping Prefabrication and Erection Subcontract No. Unit: P300009297 General Contract No. 37472
Rev. 2
Doc. class.: A
KOC Doc. No. -----------------
28
Applicable Revision
29
Unless otherwise specified in contract documents, the applicable revision or edition of applicable Specifications and Standards is the last valid at the time when contract or agreement are made to enter into effective date.
30
Construction Item definition
31
Prior to start construction works the “Main Item” shall be defined including sub-items. The “Main Item” is the principal object of inspections and tests required for construction works. The “Main Item” to be related to the ITP is the “isometric” or “lines” including piping components, saddles, reinforcing plates and supports.
32
PIPING ERECTION
33
General
34
The Subcontractor shall be responsible for the receiving, identification, storing, handling, traceability and installation of all permanent piping components including fittings and valves from time of receipt at the job shop/site until final acceptance of Works, Subcontractor shall be responsible to maintain the piping material in good condition.
35
Subcontractor Superintendent, through the Craft Supervisors, shall have responsibility for the actual performance of all work directly related to the storage, segregation of different type and grade of materials, handling, (this shall include any such work performed for Subcontractors by other parties).
36
Subcontractor Superintendent shall enforce housekeeping requirements in or around the erection areas.
37
Receiving and storing piping materials shall be carried out as the relevant project documentation and as per this section.
38
Subcontractor shall keep record for control & tracing of all pipes relevant also to P.O., packing list , heat number, certificates, inspection report .
This document is the property of SAIPEM who will safeguard its rights according to the civil and penal provisions of the law.
335226530.doc
JOB
UNIT
670700
000
SPC. 000-ZA-E-02631 BUILDING NEW BOOSTER STATION BS-160 AT SOUTH EAST KUWAIT
Sh. 10 of 54
Document title: Quality Control Plan for Piping Prefabrication and Erection Subcontract No. Unit: P300009297 General Contract No. 37472
Rev. 2
Doc. class.: A
KOC Doc. No. -----------------
39
Materials Handling
40
All material shall be handled with care during fabrication and installation to prevent damage. Lined and coated pipes and fittings shall be lifted with wide fabric or rubbercovered slings and padding shall be used to prevent damage to lining or coating.
41
The materials shall be handled at all times in a manner that prevents contamination, damage to the pipe-walls, bevelled ends, and to the coating (including internal coatings, if applied). Equipment & slings will be suitable for material handling, Slings shall be nylon or equivalent; steel cables shall not be used. Coated pipe shall not be rolled or dragged on the ground.
42
Internal of piping spools shall be visually inspected for cleanliness, and shall have foreign material removed from the inside, and shall have end protectors installed. After assembly and installation, the piping shall be cleaned inside to remove all loose materials.
43
Materials Traceability
44
Piping material traceability is a mandatory requirement applicable to all piping materials and components and is relevant to the identification, registration, marking of all plant lines and isometric piping materials. Standard traceability allows the identification of piping materials per: Piping component type (pipe, elbow, flange,etc.) Dimensions (size and thickness) Rating (# 150; # 300 etc.) Material standard and grade (ASTM-A-106 Gr.B; ASTM-A-105/N etc.). The identification of the material from receiving, storing and throughout all construction phases is managed by means of specific piping components coding assigned by engineering to each type of component as listed in the line specification.
45
Full Traceability will be maintained the Subcontractor and shall comply with the following requirement: Transferring the material heat number on pipe segments during cutting operations, prefabrication and erection maintaining the same on all piping components with the necessary traceability marking, colour coding; Indicating the material heat numbers and/ or traceability numbers on Traceable documents and on relevant prefabricated or erected pipe spools. Preparing the drawings with the identification and traceability summary table detailing for each isometric all pipe segments and components with the following minimum information: drawing number showing the position of the pipe segment or components and relevant traceability number, type, quality and size of the component/material, material heat number, manufacture name
This document is the property of SAIPEM who will safeguard its rights according to the civil and penal provisions of the law.
335226530.doc
JOB
UNIT
670700
000
SPC. 000-ZA-E-02631 BUILDING NEW BOOSTER STATION BS-160 AT SOUTH EAST KUWAIT
Sh. 11 of 54
Document title: Quality Control Plan for Piping Prefabrication and Erection Subcontract No. Unit: P300009297 General Contract No. 37472
Rev. 2
Doc. class.: A
KOC Doc. No. -----------------
46
All the above work process shall be detailed by Subcontractor in ITP own “Piping Fabrication and Erection Procedure” and “Positive Material Identification Procedure” to be issued to Contractor for approval prior to start the work.
47
Fit-Up of piping
48
Components to be welded shall be aligned, spaced and fitted up as required by the welding specification and piping construction tolerances.
49
For socket weld connections the pipe shall be cut and inspected to ensure that the cut end of the pipe is straight to enable the specified gap between the end of the pipe and socket.
50
Threaded joints
51
Prior to starting the work, the following preliminary positive verifications shall be carried out: availability of Subcontractor approved threaded Joints procedure; adequacy and approval of lubricant and sealant to be used; adequacy of pipe threading equipment and tools.
52
Subcontractor shall demonstrate to Contractor the suitability of equipment, tools and sealant for threaded joints by means of initial sample testing. Care shall be taken, not to damage the threads, during installation. The thread standard shall conform to the specified Standard. Minimum number of engaged pipe threads shall meet the requirements of the specified Standard. Unless otherwise specified the required number of exposed threads shall be from two to three.
53
For seal Welding of Threaded Joints the seal weld shall be a fillet weld going from the outer diameter of the female part, smoothly with slight concavity, to the male part covering all exposed threads without undercut, using an approved procedure. Seal welding of threaded joints is to be carried out when indicated on project documents. Seal weld will be as per ASME B31.3
54
Flanged joints
55
All type of flanged Joints shall be assembled in accordance with the applicable Piping Specification and Standard. As a minimum, bolts tightening of high pressure flanged joints rating 1500 lb and above, grinding of the inside surface of welded joints of orifice flanges and flanged connections on machinery shall be carried out under controlled condition.
56
Prior to start the work Subcontractor shall issue the installation procedure for flanged joints assembly to address as a minimum requirements and “Good Practices” for: - steel flanged bolt tightening methods; - RTR (Fibreglass) flanged tightening sequence and torque; - Gasket identification installation and verification. Flange shall not be joined without gasket, all stud & bolts shall be treated with graphitic oil before installation For underground RTR In case of specific contract requirements of SS strips the requirements will be applied.
This document is the property of SAIPEM who will safeguard its rights according to the civil and penal provisions of the law.
335226530.doc
JOB
UNIT
670700
000
SPC. 000-ZA-E-02631 BUILDING NEW BOOSTER STATION BS-160 AT SOUTH EAST KUWAIT
Sh. 12 of 54
Document title: Quality Control Plan for Piping Prefabrication and Erection Subcontract No. Unit: P300009297 General Contract No. 37472
Rev. 2
Doc. class.: A
KOC Doc. No. -----------------
57
Pressure Testing
58 59
Applicable ASME B31.3, B31.4 or B31.8 will be used. Subcontractor shall make hydrostatic test diagrams and test procedures available at site prior to conducting the test. The test diagrams and procedures shall include the limits of piping (including test manifold), equipment included in each test, test pressure, test temperature, fluid and flushing requirements.
60
Pressure testing of piping shall be carried out as per project piping specification and the hydro test procedure 000-AZ-E-02543 and in accordance with the applicable code. In addition, the following requirements shall apply.
61
The test fluid shall be injected at the lowest point in the system to minimize entrapped air. All vents shall be open during filling.
62
After the test pressure is reached and before commencement of inspection of the system, the isolation valve between the temporary test manifold/piping and the piping/equipment under pressure test shall be closed and the test pump disconnected. All systems (piping and equipment) while being hydrostatic tested shall be protected from being over pressured.
63
Subcontractor shall make hydrostatic test diagrams and test procedures available at site before testing, and be available at the job sites for pressure tests. In case of test for buried System a dedicated procedure will be issued
64
For Gravity atmospheric test Subcontractor shall make dedicated procedure to describe method and acceptance.
65
All the equipments & instrumentations that could be damage by the test will be removed and reinstalled after test.
66
Specific Requirements for Placing Underground RTR/Thermoplastic Material Piping in Trenches
67
Company specification KOC-MP-011-2 will be applied for all the installation, moreover same more requirements are expressed here below in case of conflict KOC specification will prevail.
68
Small and composite spools can be pre-joined prior to lowering in the trench where there is no risk of joint failure. Pipes shall be joined sufficiently after lowering operation so that no movement of the pipe will take place at location where joints are being cured. Any vibration or movement of uncured or partially cured joints shall be avoided to minimize the risk of joint failures.
69
Applicable methods for lowering pipe into the trench shall be in accordance with pipe Manufacturer recommendations and be performed in a way not to over-stress the piping. Suitable equipment and tools for raising and lowering the pipe into the ditch shall be used.
70
For trench depth in excess of 5 feet, it shall be the Subcontractor’s responsibility to submit specific laying conditions (trench depth, handling equipment, pipe diameter, etc.) to CONTRACTOR/COMPANY for approval.
71
Bedding and backfill shall be performed as per Manufacturer recommendation. Any conflicts between project specifications and Manufacturer recommendation shall be resolved in writing by the Subcontractor through the Contractor Site Representative.
This document is the property of SAIPEM who will safeguard its rights according to the civil and penal provisions of the law.
335226530.doc
JOB
UNIT
670700
000
SPC. 000-ZA-E-02631 BUILDING NEW BOOSTER STATION BS-160 AT SOUTH EAST KUWAIT
Sh. 13 of 54 Rev. 2
Document title: Quality Control Plan for Piping Prefabrication and Erection Subcontract No. Unit: P300009297 General Contract No. 37472
72
The above requirements are addition.
73
ATTACHMENTS
74
ITP LIST
75
General ITP
76
77
ITP TB-0001
Document Review
ITP TB-0002
Material Receiving
Doc. class.: A
KOC Doc. No. -----------------
Specific ITP ITP TB-0101
Steel Pressure Piping Prefabrication and Erection
ITP TB-0102
Fibreglass/Plastic Pressure Piping Erection
ITP TB-0106
Piping System Precommissioning
ITP TB-0107
Atmospheric Underground Piping
INSTALLATION FORMS LIST MDT.TB.CDQ.0101
Isometric Control Sheet
MDT.TB.CDQ.0103
Check of Installed Supports and Anchor
MDT.TB.CDQ.0104
Inspection Report of flange alignment, parallelism and bolts tightening
MDT.TB.CDQ.0105
Visual Check of Orifice Flanges Report
MDT.TB.CDQ.0106
Release for Backfilling (UG Pressure Piping)
MDT.TB.CDQ.0107
Pipe Threads Checking and Wrench Tightening
MDT.TB.CDQ.0108
Release for Pressure Test
This document is the property of SAIPEM who will safeguard its rights according to the civil and penal provisions of the law.
335226530.doc
JOB
UNIT
670700
000
SPC. 000-ZA-E-02631 BUILDING NEW BOOSTER STATION BS-160 AT SOUTH EAST KUWAIT
Sh. 14 of 54 Rev. 2
Document title: Quality Control Plan for Piping Prefabrication and Erection Subcontract No. Unit: P300009297 General Contract No. 37472
78
Doc. class.: A
KOC Doc. No. -----------------
MDT.TB.CDQ.0109
Pressure Test report
MDT.TB.CDQ.0110
RTR/Thermoplastic Joint Preparation and Assembly Report
MDT.TB.CDQ.0111
Checking of Heating Blanket Application and Curing Time
MDT.TB.CDQ.0112
Before Pressure Test- Internal Pipe Cleaning
MDT.TB.CDQ.0113
Release Report of Piping Prefabricated Spools
MDT.TB.CDQ.0117
Inspection Report of Laid
MDT.TB.CDQ.0118
Inspection Report of Pipes Watertight Test
MDT.TB.CDQ.0119
Finishing Inspection Report of Complete System Watertight Fulfilment
MDT.TB.CDQ.0120
Inspection Report for Trenches Excavation and Beddings
MDT.TB.CDQ.0121
Pre-Test Punch Listing Check List
MDT.TB.CDQ.0122
RTRP Daily Bonding Inspection Report
MDT.TB.CDQ.0123
Pipe Support Fabrication Inspection Report
MDT.TB.CDQ.0124
Final Inspection and Release Record for Pipe Support
Pipes
PRECOMMISSIONING FORMS LIST MDT.TB.CDQ.901
Pre-Commissioning Record Sheet Piping System Cleaning / Blowing / Flushing
MDT.TB.CDQ.902
Piping Items Check List - (Removal / Reinstatement)
MDT.TB.CDQ.903
Temporary Spades, Paddles & Blinds Check List – (Installation / Removal)
MDT.TB.CDQ.904
Instruments Check List - (Removal / Reinstatement)
MDT.TB.CDQ.905
System Drying and Inerting
This document is the property of SAIPEM who will safeguard its rights according to the civil and penal provisions of the law.
335226530.doc
JOB 670700
PROJECT LOCATION
QCP: 000-ZA-E-02631
SOUTH EAST KUWAIT PROJECT TITLE BUILDING NEW BOOSTER STATION BS-160 AT SOUTH EAST KUWAIT ITP No. TB-0001
DISCIPLINE
Title: DOCUMENT REVIEW QC CODE TB
TB
TB
0001
0001
0001
02
03
ITEMS
Check availability of CC approved procedure for piping internal cleaning
Reference Document
Acceptance Criteria
Quality Records/ Document
CC
Q C
SP
UPR,
Approved
000-AZ-E02543
P
R
Approved
000-AZ-E02580
P
Approved
000-AZ-E02580
Approved
CL
Notes
R
R/A
UPR- Up dated Procedure Register
R
R
R/A
P
R
R
R/A
000-AZ-E02588 000-AZ-E02590
P
R
R
R/A
Approved
000-AZ-E02577
P
W
W
W
Approved
000-AZ-E02543
P
R
R
R/A
000-AZ-E02543
Check availability of CC approved procedure for flange joint- gasket installation and flange bolt tightening
000-AZ-E02580,
Check availability of CC approved procedure for piping material traceability
000-AZ-E02580,
Involvement TP
C O
UPR
UPR
TB
0001
04
Review of approved procedure for positive material identification (PMI)
000-AZ-E02588 000-AZ-E02590, UPR
TB
TB
0001
0001
05
06
Rev. 2
Sh. 15 of 54
PIPING Description
01
UNIT 000
Check certificate of training from manufacturer for the pipe fiberglass jointing personnel.
000-AZ-E02577
Check availability of CC approved procedure for piping pressure testing: - Hydrostatic testing; - Pneumatic testing; - Leak testing; - Etc.
000-AZ-E02543
CC – Sub contractor QC – QC Sub contractor SP – Contractor Supervision
UPR
UPR
ORGANIZATION CODE CO –Contractor Commissioning TP – Laboratory / Third Party CL – Company
P – Perform/Submit S – Surveillance R – Review
INVOLVEMENT CODE W – Witness H – Hold Point R/A – Review/Approval
JOB 670700
PROJECT LOCATION
QCP: 000-ZA-E-02631
SOUTH EAST KUWAIT PROJECT TITLE BUILDING NEW BOOSTER STATION BS-160 AT SOUTH EAST KUWAIT ITP No. TB-0002
DISCIPLINE
Title: MATERIAL RECEIVING QC CODE TB
0002
Piping bulk material receiving at warehouse
Reference Document
Packing list 000-AZ-E-02013 000-AZ-E-02572
TB
TB
0002
0002
02
04
Rev. 2
Sh. 16 of 54
ITEMS
PIPING Description
01
UNIT 000
Warehoused material identification and traceability (Identification marks, Tags, colour coding etc.) -PMI (if required) (See Notes)
Acceptance Criteria
Mill Test Certificates, Purchase Order IFC Drawings
000-AZ-E-02013 000-AZ-E-02014
000-AZ-E-02572
000-AZ-E-02572
Quality Records/ Document OSD Report MAGA Print-out “RICEMATE” “STNNCNF” Warehouse Log book () Warehouse Material Maps PMI certification
Involvement CC
P
Q C
H
SP
W
TP
C O
CL
Notes
W
000-AZ-E-02013 - Material Management Storage and Preservation Procedure 000-AZ-E-02572- Handling, Unload and storage of Project materials
-PMI shall be carried out in accordance to Project/Contract specification. 000-AZ-E-02014 – PMI Procedure
P
H
S
S
P
W
S
S
Piping Materials protection and preservation 000-AZ-E-02013
CC – Sub contractor QC – QC Sub contractor SP – Contractor Supervision
000-AZ-E-02013
ORGANIZATION CODE CO –Contractor Commissioning TP – Laboratory / Third Party CL – Company
Warehouse Log book ()
P – Perform/Submit S – Surveillance R – Review
INVOLVEMENT CODE W – Witness H – Hold Point R/A – Review/Approval
JOB 670700
PROJECT LOCATION
QCP: 000-ZA-E-02631
SOUTH EAST KUWAIT PROJECT TITLE BUILDING NEW BOOSTER STATION BS-160 AT SOUTH EAST KUWAIT ITP No. TB-0101
QC CODE TB 0101
TB 0101
TB 0101
01a
01b
02
Sh. 17 of 54
DISCIPLINE
Title: STEEL PRESSURE PIPING PREFABRICATION AND ERECTION
(only for underground Piping) Check coordinates and elevation of trench excavation and bedding compaction. (See Notes) Piping Material Heat Number Traceability
Reference Document
ITEMS
Acceptance Criteria
Quality Records/ Document
Involvement Notes CC
Q C
SP
TP
CO
CL
R
Document review and material receiving applicable inspection shall be completed as per ITP No. TB-0001 and ITP No. TB-0002
S
Refer ITP No. CV-0201 in QCP No. 000-ZA-E02612.(QCP for General Civil Works)
AFC Drawings, Updated Drawing Register
AFC Drawings
MDT.TB.CDQ.0101
P
R
R
AFC Piping Drawings
AFC Piping Drawings
Piping arrangement DWGS
P
H
W
Latest Revision
Latest Revision
MDT.TB.CDQ.0120
Material Test Certificates
Weld Summary List
P
W
S
000-AZ-E-2576 000-AZ-E-2580 SPC-1655-PM4200-02
ISO-Weld Map
S
Material Test Certificates
CC – Sub contractor QC – QC Sub contractor SP – Contractor Supervision 335226530.doc
Rev. 2
PIPING
Description Pre-installation inspection: (See Notes) - Verification of isometric, piping arrangement dwg, components and spools - Preparation of isometric control sheets.
UNIT 000
ORGANIZATION CODE CO –Contractor Commissioning TP – Laboratory / Third Party CL – Company
P – Perform/Submit S – Surveillance R – Review
INVOLVEMENT CODE W – Witness H – Hold Point R/A – Review/Approval
JOB 670700
PROJECT LOCATION
QCP: 000-ZA-E-02631
SOUTH EAST KUWAIT PROJECT TITLE BUILDING NEW BOOSTER STATION BS-160 AT SOUTH EAST KUWAIT ITP No. TB-0101
QC CODE TB 0101
03
Sh. 18 of 54
DISCIPLINE
Title: STEEL PRESSURE PIPING PREFABRICATION AND ERECTION
Rev. 2
ITEMS
PIPING Reference Document
Acceptance Criteria
Description Inspection of orifice flanges : (See Notes) - Visual Inspection of Internal weld profile; - Dimensional checks; - Inspection of orifice flanges (orientation).
UNIT 000
AFC Drawings, 000-AZ-E-2576, SPC-1655-PM4200-02
AFC Drawings, SPC-1655-PM4200-02 Clause 4.5, 4.6
Quality Records/ Document
MDT.TB.CDQ.0105
Involvement Notes CC
Q C
SP
TP
CO
W
CL
P
H
H
W
Dimensional checks
P
H
W
S
Welding, NDE (PMI), PWHT (if required) (See Notes) Check of identification marking of spools
P
H
W
S
P
H
W
For inspection of flow orifice plate, refer to ITP No.SM-0101 in QCP No.000-ZA-E-02651 “Instrumentation and Automation system”
W
TB AFC Drawings,
2
TB 0101 04A
Release of Pipe Supports - Dimensional checks - Welding, NDE, PWHT (if required) (See Notes) CC – Sub contractor QC – QC Sub contractor SP – Contractor Supervision
335226530.doc
000-AZ-E-2576,
000-AZ-E-2576,
SPC-1655-PM4200-02
SPC-1655-PM4200-02
ORGANIZATION CODE CO –Contractor Commissioning TP – Laboratory / Third Party CL – Company
MDT.TB.CDQ.0123 MDT.TB.CDQ.0124
P – Perform/Submit S – Surveillance R – Review
P
R
S
INVOLVEMENT CODE W – Witness H – Hold Point R/A – Review/Approval
PMI if required shall be carried out as per ITP No. WL- 0101 in 000-ZA-E02623. All Welding and NDE
JOB 670700
PROJECT LOCATION
QCP: 000-ZA-E-02631
SOUTH EAST KUWAIT PROJECT TITLE BUILDING NEW BOOSTER STATION BS-160 AT SOUTH EAST KUWAIT ITP No. TB-0101
QC CODE TB 0101
TB 0101
TB 0101
TB 0101
TB 0101
05
06
07
08
09
Sh. 19 of 54
DISCIPLINE
Title: STEEL PRESSURE PIPING PREFABRICATION AND ERECTION
Pipe supports and pipe anchor: positions according to drawings
Final mechanical inspection of installed piping release for pressure testing: (See Notes) -Clearance of punch items preventing pressure test -Final inspection of piping joints: (See Pre-test internal cleaning and pipe circuit preparation
CC – Sub contractor QC – QC Sub contractor SP – Contractor Supervision
Rev. 2
ITEMS
PIPING Reference Document
Acceptance Criteria
Description Inspection of piping flanges alignment, parallelism (pipe to pipe, pipe to equipment and machinery) and bolts tightening For threaded joint check the minimum number of engaged pipe threads and maximum exposed pipe threads
UNIT 000
000-AZ-E-2580 SPC-1655-PM4200-02 000-AZ-E-2581 SPC-1655-PM4200-02
SPC-1655-PM4200-02 Clause 4.12, 4.20 SPC-1655-PM4200-02 Clause 4.15
AFC Drawing, 000-AZ-E-2580, SPC-1655-PM4200-02
AFC Drawing SPC-1655-PM4200-02 Clause 4.7
AFC Drawings, 000-AZ-E-2543 SPC-1655-PM4200-01 000-AZ-E-2543, SPC-1655-PM4200-01
Quality Records/ Document
MDT.TB.CDQ.0104
MDT.TB.CDQ.0107
Notes CC
Q C
SP
TP
CO
CL
P
H
W
S
P
W
S
S
P
H
W
MDT.TB.CDQ.0103
AFC Drawings, SPC-1655-PM4200-01 Clause 4.1
MDT.TB.CDQ.0108 , 108A, Welding Summary List (MDT.WL.CDQ.
SPC-1655-PM4200-01 Clause 4.1
MDT.TB.CDQ.0112
ORGANIZATION CODE CO –Contractor Commissioning TP – Laboratory / Third Party CL – Company
Involvement
W
P
H
H
H
P
W
S
S
P – Perform/Submit S – Surveillance R – Review
INVOLVEMENT CODE W – Witness H – Hold Point R/A – Review/Approval
Piping test-pack preparation (TP- Folder). For welding, PWHT and NDE works, refer to ITP NO. WL-0101 in QCP No.
JOB 670700
PROJECT LOCATION
QCP: 000-ZA-E-02631
SOUTH EAST KUWAIT PROJECT TITLE BUILDING NEW BOOSTER STATION BS-160 AT SOUTH EAST KUWAIT ITP No. TB-0101
QC CODE TB 0101
10
Sh. 20 of 54
DISCIPLINE
Title: STEEL PRESSURE PIPING PREFABRICATION AND ERECTION
UNIT 000
Rev. 2
ITEMS
PIPING Reference Document
Acceptance Criteria
Description
Quality Records/ Document
Involvement Notes CC
Q C
SP
P
H
H
TP
CO
CL
Piping pressure testing 000-AZ-E-2543 SPC-1655-PM4200-01
TB 0101
11
SPC-1655-PM4200-02 clause 4.2
MDT.TB.CDQ.0109
H
Piping Lay-up
(follow ITP TB-0106 Precommissioning activities)
N/A
N/A
NA
R
R
See Notes
TB010112(Underground Piping) See NotesAFC DrawingAFC DrawingMDT.TB.CDQ.0106PHHW Refer ITP No.CV-0201. in QCP n.000-ZA-E-02612 for general civil works.
CC – Sub contractor QC – QC Sub contractor SP – Contractor Supervision 335226530.doc
ORGANIZATION CODE CO –Contractor Commissioning TP – Laboratory / Third Party CL – Company
P – Perform/Submit S – Surveillance R – Review
INVOLVEMENT CODE W – Witness H – Hold Point R/A – Review/Approval
For painting, coating and insulation works refer to QCP - 000-ZA-E-02633 for Painting Work; - 000-ZA-E-02634 for Insulation Work; - 000-ZA-E-02635 for
JOB 670700
PROJECT LOCATION
QCP: 000-ZA-E-02631
SOUTH EAST KUWAIT PROJECT TITLE BUILDING NEW BOOSTER STATION BS-160 AT SOUTH EAST KUWAIT ITP No. TB-0102
TB
0102
PIPING Acceptance Criteria
Quality Records/ Document
CC
Q C
SP
Before commencement the Project works review and approval of following documents:
AFC Drawing
AFC Drawing
P
H
A
BPS
BPS
Bonding Procedure Specification (BPS),
-Bonding Procedure Specification See Notes
Bonder’s Qualification Certificate
Bonder’s Qualification Certificate
Bonder’s Qualification Certificate,
Description 01
ITEMS
Reference Document
QC CODE
-Bonder’s Qualification See Notes
Rev. 2
Sh. 21 of 54
DISCIPLINE
Title: FIBERGLASS/PLASTIC PRESSURE PIPING ERECTION
UNIT 000
ASME B 31.3
ASME B 31.3
Involvement TP
CO
CL W/A
Notes Refer 000-AZ-E-02577 (Procedure for Fabrication and Erection of RTRP piping) for 1. Bonding Procedure Specification (BPS),
Bonder’s Register
2. Bonder’s Qualification Certificate, 3. Bonder’s Register
TB
TB
0102
0102
01a
01b
Pre-installation inspection: See Notes - Verification of isometric, piping arrangement dwg, components and spools; - Preparation of isometric control sheets. (Underground Piping) Check coordinate and elevation of trench excavation and bedding compaction.
AFC Drawing, Updated Drawing Register
Latest AFC Drawing
MDT.TB.CDQ.0101
P
R
R
R
AFC Piping Drawings
AFC Piping Drawings
Piping arrangement DWGS
P
H
W
W
Latest Revision
Latest Revision
MDT.TB.CDQ.0120
See Notes
CC – Sub contractor QC – QC Sub contractor SP – Contractor Supervision
ORGANIZATION CODE CO –Contractor Commissioning TP – Laboratory / Third Party CL – Company
P – Perform/Submit S – Surveillance R – Review
INVOLVEMENT CODE W – Witness H – Hold Point R/A – Review/Approval
Document review and material receiving applicable inspection shall be completed as per ITP No. TB-0001 and ITP No. TB-0002
Refer ITP No. CV-0201 in QCP No. 000-ZA-E-02612. (QCP for General Civil Works)
JOB 670700
PROJECT LOCATION
QCP: 000-ZA-E-02631
SOUTH EAST KUWAIT PROJECT TITLE BUILDING NEW BOOSTER STATION BS-160 AT SOUTH EAST KUWAIT ITP No. TB-0102
QC CODE TB
TB
TB
TB
0102
0102
0102
0102
Description 02
03
04
05
Check joint and assembly preparation: a) Squareness of cut spigot end b) Insert depth c) Nose thk. d) Spigot diameter e) Adhesive application Check heating blanket application and curing time.
Final mechanical inspection of installed piping: See Notes - Pre-test punch listing - Release for pressure testing Pre-test internal cleaning and pipe circuit preparation
CC – Sub contractor QC – QC Sub contractor SP – Contractor Supervision
Rev. 2
Sh. 22 of 54
DISCIPLINE
Title: FIBERGLASS/PLASTIC PRESSURE PIPING ERECTION
UNIT 000
ITEMS
PIPING Reference Document
Acceptance Criteria
Quality Records/ Document
CC
Q C
SP
000-AZ-E-2577
000-AZ-E-2577
MDT.TB.CDQ.0110
P
W
S
S
KOC-MP-011-2
BPS
MDT.TB.CDQ.012 2
KOC-MP-011-2
000-AZ-E-2577
P
W
W
S
BPS
BPS
MDT.TB.CDQ.0111 MDT.TB.CDQ.0122
MDT.TB.CDQ.0108, MDT.TB.CDQ.0121
P
H
H
H
MDT.TB.CDQ.0112
P
W
S
S
BPS
Involvement TP
CO
CL
Notes
000-AZ-E-2577
AFC Drawing,
AFC Drawing,
000-AZ-E-2577
KOC-MP-011-2
KOC-MP-011-2
Clause 11
000-AZ-E-2577 KOC-MP-011-2
KOC-MP-011-2
ORGANIZATION CODE CO –Contractor Commissioning TP – Laboratory / Third Party CL – Company
P – Perform/Submit S – Surveillance R – Review
INVOLVEMENT CODE W – Witness H – Hold Point R/A – Review/Approval
Piping test-pack preparation (TP- Folder).
JOB 670700
PROJECT LOCATION
QCP: 000-ZA-E-02631
SOUTH EAST KUWAIT PROJECT TITLE BUILDING NEW BOOSTER STATION BS-160 AT SOUTH EAST KUWAIT ITP No. TB-0102
QC CODE TB
TB
0102
0102
Description 06
07
Piping pressure testing
(Underground Piping) Check of trenching and Release for backfilling See Notes
CC – Sub contractor QC – QC Sub contractor SP – Contractor Supervision
Rev. 2
Sh. 23 of 54
DISCIPLINE
Title: FIBERGLASS/PLASTIC PRESSURE PIPING ERECTION
UNIT 000
ITEMS
PIPING Reference Document
Acceptance Criteria
Quality Records/ Document
Involvement CC
Q C
SP
TP
CO
CL
Line list,
Line List
000-AZ-E-2577
MDT.TB.CDQ.0 109
P
H
H
W
KOC-MP-011-2
KOC-MP-011-2 Clause 14.0
AFC Drawing Latest Revision
AFC Drawing Latest Revision
MDT.TB.CDQ.0 106
P
H
H
H
ORGANIZATION CODE CO –Contractor Commissioning TP – Laboratory / Third Party CL – Company
P – Perform/Submit S – Surveillance R – Review
INVOLVEMENT CODE W – Witness H – Hold Point R/A – Review/Approval
Notes
Refer ITP No. CV-0201 in QCP No. 000-ZA-E02612.(QCP for General Civil Works)
JOB 670700
PROJECT LOCATION
QCP: 000-ZA-E-02631
SOUTH EAST KUWAIT PROJECT TITLE BUILDING NEW BOOSTER STATION BS-160 AT SOUTH EAST KUWAIT ITP No. TB-0106
DISCIPLINE
Title: PIPING SYSTEM PRECOMMISSIONING QC CODE TB
TB
TB
TB
TB
TB
0106
0106
0106
0106
0106
0106
01
02
03
04
05
06
Description Preparation of piping system Mechanical Completion
Pre-Commissioning Record Sheet Piping System Cleaning / Blowing / Flushing
Piping Items Check List - (Removal & Reinstatement)
Temporary Spades, Paddles & Blinds Check List - (Installation)- (Removal)
Instruments Check List - (Removal) (Reinstatement)
System Drying and Inerting
CC – Sub contractor QC – QC Sub contractor SP – Contractor Supervision
UNIT 000
Rev. 2
Sh. 24 of 54
ITEMS
PIPING Reference Document
Acceptance Criteria
Quality Records/ Document
000-AZ-E-02543,
SPC-1655-PM4200-01 clause 4.15, 4.16
SPC-1655-PM4200-01 000-AZ-E-02543, SPC-1655-PM4200-01
SPC-1655PM-4200-01 Clause 4.15
AFC Drawing, 000-AZ-E-02543 SPC-1655-PM4200-01
SPC-1655PM-4200-01
AFC Drawing, 000-AZ-E-02543 SPC-1655-PM4200-01
SPC-1655PM-4200-01
AFC Drawing, 000-AZ-E-02543 SPC-1655-PM4200-01
SPC-1655PM-4200-01
000-AZ-E-02543 SPC-1655-PM4200-01
SPC-1655PM-4200-01 Clause 4.15
Involvement CC
Q C
SP
TP
C O
TEST PACK Folder
P
R
R
R
MDT.TB.CDQ.901
P
H
H
W
MDT.TB.CDQ.902
P
H
H
W
MDT.TB.CDQ.903
P
H
H
W
MDT.TB.CDQ.904
P
H
H
W
MDT.TB.CDQ.905
P
H
H
H
Notes
CL
Clause 4.16
Clause 4.16 (If applicable)
Clause 4.16
ORGANIZATION CODE CO –Contractor Commissioning TP – Laboratory / Third Party CL – Company
P – Perform/Submit S – Surveillance R – Review
(If required by Project Specification)
INVOLVEMENT CODE W – Witness H – Hold Point R/A – Review/Approval
JOB 670700
PROJECT LOCATION
QCP: 000-ZA-E-02631
SOUTH EAST KUWAIT PROJECT TITLE BUILDING NEW BOOSTER STATION BS-160 AT SOUTH EAST KUWAIT
ITP No. TB-0107
QC CODE TB 0107
01
Sh. 25 of 54
DISCIPLINE
Title: ATMOSPHERIC UNDERGROUND PIPING Description Check atmospheric underground piping installation before backfilling
Rev. 2
ITEMS
PIPING Reference Document AFC Drawing 000-AZ-E-02543, SPC-1655-PM4200-01
TB 0107
02
Gravity testing of the pipe as required by the testing procedure Release for Backfilling
000-AZ-E-02543, SPC-1655-PM4200-01
TB 0107
03
Check the integrity of the complete system (pipes and PITP, manholes) watertight fulfilment.
000-AZ-E-02543, SPC-1655-PM4200-01
CC – Sub contractor QC – QC Sub contractor SP – Contractor Supervision
UNIT 000
Acceptance Criteria
Quality Records/ Document
CC
QC
SP
MDT.TB.CDQ.0117
P
H
W
W
No Leaks detected MDT.TB.CDQ.0118
P
H
W
W
No Leaks detected MDT.TB.CDQ.0119
P
H
H
W
AFC Drawing Latest revision
ORGANIZATION CODE CO –Contractor Commissioning TP – Laboratory / Third Party CL – Company
Involvement
P – Perform/Submit S – Surveillance R – Review
TP
CO
CL
INVOLVEMENT CODE W – Witness H – Hold Point R/A – Review/Approval
Notes
PLANT LOCATION
JOB
UNIT
670700
000
QC CODE
SOUTH EAST KUWAIT PROJECT TITLE BUILDING NEW BOOSTER STATION
BS 160 - AT SOUTH EAST KUWAIT
REPORT No DATE:
ISOMETRIC CONTROL SHEET PAGE
LINE NUMBER
ISO/SK No.
SPOOL No.
JOINT TYPE
MATERIAL TYPE AND GRADE
NOTES
OF
BUTT BRANCH JOINT WELD WELD No.
REINFO FILLED ORIFICE RCED WELD FLANGE PAD
INSPECTION NOTIFICATION REFERENCE
IN No. KHARAFI NATIONAL
SAIPEM
KOC
NAME DESIGNATION SIGNATURE Date
Form code: MDT.TB.CDQ.0101
335226530.doc
Page 26 of
54
PLANT LOCATION
SOUTH EAST KUWAIT PROJECT TITLE BUILDING NEW BOOSTER STATION
BS 160 - AT SOUTH EAST KUWAIT
JOB
UNIT
670700
000
QC CODE
REPORT No DATE:
CHECK OF INSTALLED SUPPORTS AND ANCHOR Test Pack No:
PAGE
LINE NUMBER
NOTES=
C= CONFORMING NC= NOT CONFORMING KHARAFI NATIONAL
CORRECT NUMBER AND POSITION OF SUPPORTS AND ANCHOR ACCORDING TO DRAWINGS
C
NC
C
NC
C
NC
C
NC
C
NC
C
NC
C
NC
C
NC
C
NC
C
NC
C
NC
C
NC
C
NC
C
NC
OF NOTES
INSPECTION NOTIFICATION REFERENCE (TO DRW, SPECIFICATION)
SAIPEM
IN No. KOC
NAME DESIGNATION SIGNATURE Date Form code: MDT.TB.CDQ.0103
335226530.doc
Page 27 of
54
PLANT LOCATION
JOB
UNIT
670700
000
QC CODE
SOUTH EAST KUWAIT PROJECT TITLE BUILDING NEW BOOSTER STATION
REPORT No
BS 160 - AT SOUTH EAST KUWAIT
DATE:
INSPECTION REPORT OF FLANGE ALIGNMENT, PARALLELISM AND BOLTS TIGHTENING JOINT REF.No. (see note 1)
Test Pack No:
PIPING ISOMETRIC REF.DWG.No. (see note 1)
Joint no. :
Line number:
ISO/DWG :
Joint no. :
Line number:
ISO/DWG :
Joint no. :
Line number:
ISO/DWG :
Joint no. :
Line number:
ISO/DWG :
CHECKS CHECKS OF CORRECT MATERIAL
C
NC
Flange
Check correct installation for : Size (inch), Type, Rating, Material
Gasket
Check correct installation for : Size (inch), Type, number for Ring Gasket) , Material (Outer Guide Ring - Inner Guide Ring -Ring Joint Basket – Others…..) C NC
Bolts & Nuts
C
Check correct installation for : Size (inch), Type, Material, Quantity
YES
Lubricant:
NC
NO
CHECKS BEFORE BOLTS TIGHTENING PARALLELISM CHECK ALIGNMENT CHECK
C
REMOVAL OF TEMPORARY GASKETS AND INST. OF PERMANENT FINAL GASKET
NC
C
NC
BOLTS TIGHTENING By Torque
:
Bolt tensioning method :
Torque value
Torque/Tensioning equipment No: RESULTS:
ACCEPTABLE
Calibration due :
NOT ACCEPTABLE
NOTES Notes: 1-Subcontractor shall identify on piping isometric dwgs. the joint reference number using an alfa
numeric code.
KHARAFI NATIONAL
:
INSPECTION NOTIFICATION REFERENCE
IN No.
SAIPEM
KOC
NAME DESIGNATION SIGNATURE Date Form code: MDT.TB.CDQ.0104
JOB
335226530.doc
UNIT
Page 28 of
54
670700 PLANT LOCATION
000
QC CODE
SOUTH EAST KUWAIT PROJECT TITLE BUILDING NEW BOOSTER STATION
BS 160 - AT SOUTH EAST KUWAIT
REPORT No DATE:
VISUAL CHECKS OF ORIFICE FLANGES Test Pack No:
PAGE
PIPING LINE NUMBER
NOTES:
ORIFICE FLANGE No.
C= CONFORMING NC= NOT CONFORMING KHARAFI NATIONAL
INTERNAL GRINDING OF WELD ROOT
ORIFICE FLANGE ORIENTATION PRESSURE HOLES
C NC
C NC
C NC
C NC
C NC
C NC
C NC
C NC
C NC
C NC
C NC
C NC
C NC
C NC
C NC
C NC
C NC
C NC
C NC
C NC
C NC
C NC
C NC
C NC
C NC
C NC
C NC
C NC
C NC
C NC
C NC
C NC
OF NOTE / REMARKS
INSPECTION NOTIFICATION REFERENCE (TO DRW, SPECIFICATION)
SAIPEM
IN No. KOC
NAME DESIGNATION SIGNATURE Date Form code: MDT.TB.CDQ.0105
335226530.doc
Page 29 of
54
PLANT LOCATION
SOUTH EAST KUWAIT PROJECT TITLE BUILDING NEW BOOSTER STATION
BS 160 - AT SOUTH EAST KUWAIT
335226530.doc
JOB
UNIT
670700
000
QC CODE
REPORT No DATE:
Page 30 of
54
KHARAFI NATIONAL NAME
SAIPEM
KOC
RELEASE FOR BACKFILLING (U/G PRESSURE PIPING)
DESIGNATION
Test Pack No:
PAGE
SIGNATURE Date
PIPING LINE NUMBER
DRAWING NUMBER
CHECK THE CORRECT INSTALLATION OF PIPING IN TRENCHES RELEASE FOR BACKFILLING
YES / NO
OF
REMARKS
YES
NO
YES
NO
YES
NO
YES
NO
YES
NO
YES
NO
YES
NO
YES
NO
YES
NO
YES
NO INSPECTION NOTIFICATION REFERENCE
NOTES
IN No.
Form code: MDT.TB.CDQ.0106
335226530.doc
Page 31 of
54
PLANT LOCATION
JOB
UNIT
670700
000
QC CODE
SOUTH EAST KUWAIT PROJECT TITLE BUILDING NEW BOOSTER STATION
BS 160 - AT SOUTH EAST KUWAIT
REPORT No DATE:
PIPE THREADS CHECKING AND WRENCH TIGHTENING Procedure :
Test Pack No:
PAGE
OF
VISUAL CHECK OF THE THREADS
PIPING LINE NUMBER
C NC
NOTES:
C= CONFORMING NC= NOT CONFORMING KHARAFI NATIONAL
NOTES
WRENCH TIGHTENING ENGAGED AND EXPOSED CHECK THREADS
C NC
C
NC
C
NC
C
NC
C
NC
C
NC
C
NC
C
NC
C
NC
C
NC
C
NC
C
NC
C
NC
C
NC
C
NC
C
NC
C
NC
C
NC
C
NC
C
NC
C
NC
C
NC
C
NC
C
NC
C
NC INSPECTION NOTIFICATION REFERENCE
(TO DRW, SPECIFICATION)
SAIPEM
IN No. KOC
NAME DESIGNATION SIGNATURE Date Form code: MDT.TB.CDQ.0107
335226530.doc
Page 32 of
54
PLANT LOCATION
JOB
UNIT
670700
000
QC CODE
SOUTH EAST KUWAIT PROJECT TITLE BUILDING NEW BOOSTER STATION
BS 160 - AT SOUTH EAST KUWAIT
REPORT No DATE:
RELEASE FOR PRESSURE TEST TEST PACK NUMBER:
PIPING LINE NUMBER
Clearance of Punch Items preventing pressure test (1)-(2)
Cleaning execution and line ready for pressure test (3)
Temporary installation (4)
Release for pressure Test
NOTES
NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES NO YES
Notes:
1) 2) 3) 4)
This Form shall be used in conjunction with the applicable Pre-Test Punch Listing Checklist. MDT.TB.CDQ.0121 Indicate on NOTE “No Punch items. “If there are no punch list to be recorded. For pre-test cleaning report see MDT.TB.CDQ.0112 For Temporary installation use MDT.TB.CDQ.0102 TEMPORARY SPADES, PADDLES & BLINDS – (INSTALLATION)
REMARKS
INSPECTION NOTIFICATION REFERENCE
IN No. KHARAFI NATIONAL
SAIPEM
KOC
NAME DESIGNATION SIGNATURE Date Form code: MDT.TB.CDQ.0108
335226530.doc
Page 33 of
54
PLANT LOCATION
SOUTH EAST KUWAIT PROJECT TITLE BUILDING NEW BOOSTER STATION
BS 160 - AT SOUTH EAST KUWAIT
335226530.doc
JOB
UNIT
670700
000
QC CODE
REPORT No DATE:
Page 34 of
54
KHARAFI NATIONAL
SAIPEM
NAME
KOC
PRESSURE TEST REPORT
TEST PACK NUMBER: DESIGNATION LINE NUMBER : SIGNATURE
LINE NUMBER :
LINE Date NUMBER :
LINE NUMBER :
LINE NUMBER :
LINE NUMBER :
LINE NUMBER :
LINE NUMBER :
LINE NUMBER :
LINE NUMBER : PAGE
OF
TEST PROCEDURE No.: Pressure Test Check List Y
N
N/A
Y
1- Discs and flappers removed from check valves
6- Temperature equilibrium established between test fluid and system
2- Vents and drains installed
7- Lab. analysis of water chemistry made
3- Bleed valve installed
8- Safety precautions enforced for air/gas tests
N
N/A
4- Press. Temp. Recorder installed 5- Flushing procedure reviewed and approved
Test Pressure_(BAR)
______________
Type of Test Fluid
______________
Duration of Test
Test Results -
______________
Acceptable
P.G-1 No:
Calib.Due:
P.G-2 No:
Calib.Due:
P.G-3 No:
Calib.Due:
PSV No:
Calib.Due:
Pressure/Temp.Recorder No:
Calib.Due:
Not Acceptable
NOTES
INSPECTION NOTIFICATION REFERENCE
IN No. Form code: MDT.TB.CDQ.0109
PLANT LOCATION
JOB
UNIT
670700
000
QC CODE
SOUTH EAST KUWAIT PROJECT TITLE BUILDING NEW BOOSTER STATION
BS 160 - AT SOUTH EAST KUWAIT
REPORT No DATE:
RTR/THERMOPLASTIC JOINT PREPARATION AND ASSEMBLY REPORT
Line No.
Joint No.
Size cm inch
Joint preparation
Pass
335226530.doc
Fail
Adhesive application
Pass
Fail
Release for Heating Blanket Curing Yes
Not
Page 35 of
54
NOTES
INSPECTION NOTIFICATION REFERENCE
IN No. KHARAFI NATIONAL
SAIPEM
KOC
NAME DESIGNATION SIGNATURE Date Form code: MDT.TB.CDQ.0110
335226530.doc
Page 36 of
54
PLANT LOCATION
JOB
UNIT
670700
000
QC CODE
SOUTH EAST KUWAIT PROJECT TITLE BUILDING NEW BOOSTER STATION
REPORT No
BS 160 - AT SOUTH EAST KUWAIT
DATE:
CHECKING OF HEATING BLANKET APPLICATION AND CURING TIME
Procedure:
Test Pack No:
JOINT NO.
LINE NUMBER
PAGE
- Check size - Check proper installation of heating blanket - Check pipe ends closure
Check voltage
Check adhesive bonding curing time
OF
Release for Pressure Test
C
NC
C
NC
C
NC
NOTES
Yes
Not
INSPECTION NOTIFICATION REFERENCE
IN No. KHARAFI NATIONAL
SAIPEM
KOC
NAME DESIGNATION SIGNATURE Date Form code: MDT.TB.CDQ.0111
335226530.doc
Page 37 of
54
PLANT LOCATION
SOUTH EAST KUWAIT PROJECT TITLE BUILDING NEW BOOSTER STATION
BS 160 - AT SOUTH EAST KUWAIT
JOB
UNIT
670700
000
QC CODE
REPORT No DATE:
BEFORE PRESSURE TEST - INTERNAL PIPE CLEANING TEST PACK. No:
PAGE
LINE No.
Cleaning execution for line ready for pressure test
C C C C C C C C C C C C C C C
C
OF
NOTES
NC NC NC NC NC NC NC NC NC NC NC NC NC NC NC
NC
NOTES
INSPECTION NOTIFICATION REFERENCE
IN No. KHARAFI NATIONAL
SAIPEM
KOC
NAME DESIGNATION SIGNATURE Date Form code : MDT.TB.CDQ.0112
335226530.doc
Page 38 of
54
PLANT LOCATION
JOB
UNIT
670700
000
QC CODE
SOUTH EAST KUWAIT PROJECT TITLE
BUILDING NEW BOOSTER STATION BS-160
REPORT No DATE:
RELEASE REPORT OF PIPING PREFABRICATED SPOOLS PAGE SL. No.
Isometric Drg. No.
335226530.doc
Line No
Rev
Spoo l
Piping Class
Matl. Check
Fit Up & Welding
PWHT + Hardness
NDT
Visual Check
OF
Dimens Welded ional Pipe Check Support
Paint Syste m
Page 39 of
54
Re ma rks
IN No. KHARAFI NATIONAL
SAIPEM
KOC
NAME SIGNATURE DESIGNATION DATE Form code: MDT.TB.CDQ.0113
335226530.doc
Page 40 of
54
PLANT LOCATION
JOB
UNIT
670700
000
QC CODE
SOUTH EAST KUWAIT PROJECT TITLE BUILDING NEW BOOSTER STATION
REPORT No
BS 160 - AT SOUTH EAST KUWAIT
DATE:
INSPECTION REPORT OF LAID PIPES Test Pack No:
PAGE REFERENCE DRAWING
Tag or line number
Number
OF
LAID PIPES
Rev.
-MATERIALS (DIAMETERS DIMENSIONS) -GRADIENTS -LEVELS -POSITIONS
RESULTS
FROM PIT/MANHOLE/ CATCH BASIN
TO PIT/MANHOLE/ CATCH BASIN
C NC C NC C NC C NC C NC C NC C NC C NC C NC C NC C NC
C NC C NC C NC C NC C NC C NC C NC C NC C NC C NC C NC NOTES:
C= CONFORMING NC= NOT CONFORMING
(TO DRW, SPECIFICATION)
CONFORMIN G/ NOT CONFORMIN G
INSPECTION NOTIFICATION REFERENCE
IN No. KHARAFI NATIONAL
SAIPEM
KOC
NAME DESIGNATION SIGNATURE DATE Form code: MDT.TB.CDQ.0117
335226530.doc
Page 41 of
54
PLANT LOCATION
JOB
UNIT
670700
000
QC CODE
SOUTH EAST KUWAIT PROJECT TITLE BUILDING NEW BOOSTER STATION
REPORT No
BS 160 - AT SOUTH EAST KUWAIT
DATE:
INSPECTION REPORT OF PIPES WATERTIGHT TEST Test Pack No:
PAGE
PIPE Drawing No / line number
FROM
TO
Internal PITP / PITP / DiameterØ MANHOLES MANHOLES
NOTES
RESULTS Duration Time (Minutes)
OF
RELEASE FOR BACKFILLING
PASS
FAIL
YES
NOT
N/A
INSPECTION NOTIFICATION REFERENCE
IN No. KHARAFI NATIONAL
SAIPEM
KOC
NAME DESIGNATION SIGNATURE Date Form code: MDT.TB.CDQ.0118
335226530.doc
Page 42 of
54
PLANT LOCATION
UNIT
670700
000
QC CODE
SOUTH EAST KUWAIT PROJECT TITLE BUILDING NEW BOOSTER STATION
BS 160 - AT SOUTH EAST KUWAIT
JOB
REPORT No DATE:
FINISHING INSPECTION REPORT OF COMPLETE SYSTEM WATERTIGHT FULFILMENT TEST PACK No:
PAGE
Line Number
NOTES:
C= CONFORMING NC= NOT CONFORMING
Drawing number
(TO DRW, SPECIFICATION)
PITP, MANHOLES INSTALLED STEPS, FRAMES, COVER SLAB, GRATING & ERMETIC COVER
OF
PITP, MANHOLES INTERNAL CLEANING
C NC
C NC
C NC
C NC
C NC
C NC
C NC
C NC
C NC
C NC
C NC
C NC
C NC
C NC
C NC
C NC
C NC
C NC
C NC
C NC
C NC
C NC
INSPECTION NOTIFICATION REFERENCE
IN No. KHARAFI NATIONAL
SAIPEM
KOC
NAME DESIGNATION SIGNATURE Date Form code: MDT.TB.CDQ.0119
JOB 335226530.doc
UNIT
Page 43 of
54
670700 PLANT LOCATION
SOUTH EAST KUWAIT PROJECT TITLE BUILDING NEW BOOSTER STATION
BS 160 - AT SOUTH EAST KUWAIT
335226530.doc
000
QC CODE
REPORT No DATE:
Page 44 of
54
KHARAFI NATIONAL
SAIPEM
KOC
INSPECTION REPORT FOR TRENCHES EXCAVATION AND BEDDING
NAME DESIGNATION
REFERENCE
SIGNATURE Date
PAGE
Line No.
Drawing No.
CONTROLS TRENCH BEDDING COORDINATES COMPACTION ELEVATIONS
C
NOTES: = CONFORMING SPECIFICATION)
OF
RESULTS PASS
FAIL
C NC
C NC NA
C NC
C NC NA
C NC
C NC NA
C NC
C NC NA
C NC
C NC NA
C NC
C NC NA
C NC
C NC NA
C NC
C NC NA
C NC
C NC NA
C NC
C NC NA
C NC
C NC NA
NC= NOT CONFORMING NA=NOT APPLICABLE (TO DRW/
INSPECTION NOTIFICATION REFERENCE
IN No.
Compaction test certificate No: Form code: MDT.TB.CDQ.0120
PLANT LOCATION
SOUTH EAST KUWAIT PROJECT TITLE BUILDING NEW BOOSTER STATION
BS 160 - AT SOUTH EAST KUWAIT
JOB
UNIT
670700
000
QC CODE
REPORT No DATE:
PRE-COMMISSIONING RECORD SHEET PIPING SYSTEM CLEANING /BLOWING /FLUSHING Area: System No.:
Location: Sub system No.:
Test Pack No:
Service: Cleaning Medium: 335226530.doc
Page 45 of
54
Pressure Max.: METHOD USED:
P&ID No.
Line No.
FROM
BLOWING / FLUSHING & CLEANING SATISFACTORY EXECUTED
TO
C / NC/ NA
DATE
C NC NA C NC NA C NC NA C NC NA C NC NA C NC NA C NC NA C NC NA C NC NA Comments: Blowing / Flushing / Cleaning has been satisfactorily performed in accordance with PROCEDURE: Cleaning Observations:
C
NC= NOT CONFORMING NA=NOT APPLICABLE (TO DRW/
NOTES= = CONFORMING SPECIFICATION)
KHARAFI NATIONAL
INSPECTION NOTIFICATION REFERENCE
IN No.
SAIPEM
KOC
NAME DESIGNATION SIGNATURE Date Form code: MDT.TB.CDQ.901
PLANT LOCATION
SOUTH EAST KUWAIT PROJECT TITLE BUILDING NEW BOOSTER STATION
BS 160 - AT SOUTH EAST KUWAIT
JOB
UNIT
670700
000
QC CODE
REPORT No DATE:
PIPING ITEMS CHECK LIST - (REMOVAL & REINSTATEMENT) Test Pack No: SYSTEM No. PIPING ITEM
335226530.doc
SUB SYSTEM No. LOCATION LINE / EQUIPMENT No.
P & ID No.
REMOVAL DATE
REINSTATEMENT DATE
Page 46 of
54
NOTES=
C= CONFORMING NC= NOT CONFORMING
INSPECTION NOTIFICATION REFERENCE (TO DRW, SPECIFICATION)
KHARAFI NATIONAL
IN No.
SAIPEM
KOC
NAME DESIGNATION SIGNATURE Date Form code : MDT.TB.CDQ.902
PLANT LOCATION
SOUTH EAST KUWAIT PROJECT TITLE BUILDING NEW BOOSTER STATION
BS 160 - AT SOUTH EAST KUWAIT
JOB
UNIT
670700
000
QC CODE
REPORT No DATE:
TEMPORARY SPADES, PADDLES & BLINDS CHECKLIST – (INSTALLATION & REMOVAL) Test Pack. No: SYSTEM No. BLIND No.
335226530.doc
SUB SYSTEM No. LOCATION LINE / EQUIPMENT No.
P & ID No.
INSTALLATION DATE
REMOVAL DATE
Page 47 of
54
NOTES=
C= CONFORMING NC= NOT CONFORMING
INSPECTION NOTIFICATION REFERENCE (TO DRW, SPECIFICATION)
KHARAFI NATIONAL
IN No.
SAIPEM
KOC
NAME DESIGNATION SIGNATURE Date Form code : MDT.TB.CDQ.903
PLANT LOCATION
SOUTH EAST KUWAIT PROJECT TITLE BUILDING NEW BOOSTER STATION
BS 160 - AT SOUTH EAST KUWAIT
JOB
UNIT
670700
000
QC CODE
REPORT No DATE:
INSTRUMENTS CHECK LIST - (REMOVAL & REINSTATEMENT) Test Pack. No: SYSTEM No. INSTRUMENT TAG No.
335226530.doc
SUB SYSTEM No. LOCATION LINE / EQUIPMENT No.
P & ID No.
REMOVAL DATE
REINSTATEMENT DATE
Page 48 of
54
NOTES
INSPECTION NOTIFICATION REFERENCE
IN No. KHARAFI NATIONAL
SAIPEM
KOC
NAME DESIGNATION SIGNATURE Date Form code : MDT.TB.CDQ.904
335226530.doc
Page 49 of
54
PLANT LOCATION
SOUTH EAST KUWAIT PROJECT TITLE BUILDING NEW BOOSTER STATION
BS 160 - AT SOUTH EAST KUWAIT
JOB
UNIT
670700
000
QC CODE
REPORT No DATE:
SYSTEM DRYING AND INERTING WE CERTIFY THAT SYSTEM No.: .......................................and SUBSYSTEM No.: ....................................... HAVE BEEN SAMPLED AND TESTED AS FOLLOWS: REQUIRED VALUE: ....................................... MEASURED VALUE: ....................................... DEW POINT: ______________________________________________________________________________ OXYGEN: _________________________________________________________________________________ SAMPLE POINTS
RESULT :
C
NC
Instrument Tag No. Calibration due date.
NOTES=
C= CONFORMING NC= NOT CONFORMING KHARAFI NATIONAL
INSPECTION NOTIFICATION REFERENCE (TO DRW / SPECIFICATION)
SAIPEM
IN No. KOC
NAME DESIGNATION SIGNATURE Date Form code : MDT.TB.CDQ.905
335226530.doc
Page 50 of
54
PLANT LOCATION
JOB
UNIT
670700
000
QC CODE
SOUTH EAST KUWAIT PROJECT TITLE BUILDING NEW BOOSTER STATION
REPORT No
BS 160 - AT SOUTH EAST KUWAIT
DATE:
FINAL INSPECTION AND RELEASE RECORD FOR PIPE SUPPORT DRAWING / DOCUMENT NUMBER: Sl.No
Item Number/ Sub assembly Number
REV.: Type of item
Qty
Matl. Check
Weld Visual
Final Dimen sion
Trail Assy.
SB & Painting
NDT
NOTES=
Galvan izing
Markin g& Taging
Rema rks
INSPECTION NOTIFICATION REFERENCE
IN No. SUB CONTRACTOR
KHARAFI NATIONAL
SAIPEM
KOC
NAME DESIGNATION SIGNATURE Date Form code: MDT.TB.CDQ.0124
335226530.doc
Page 51 of
54
PLANT LOCATION
JOB
UNIT
670700
000
QCP CODE
SOUTH EAST KUWAIT PROJECT TITLE BUILDING NEW BOOSTER STATION BS 160 - AT SOUTH EAST KUWAIT
REPORT NO
TEST PACK. No:
PRE-TEST PUNCH LISTING CHECKLIST SL.NO.
ITEM NO.
DESCRIPTION
Form code : MDT.TB.CDQ.0121
ACTION BY
NOTE: A - To be done prior to test C - During Pre-commissioning.
CATEGORY
COMPLETION DATE
Signature & Date
RESULT KN
S.p.A
KOC
B - To be done after test.
RTRP DAILY BONDING INSPECTION REPORT (Adhesive joints) Sl.No.
335226530.doc
ISO No.
Rev. No.
Piping Class
Joint no
Joint Type
Size (Inch)
Thicknes s (Sch/mm)
Bonder No
BPS No
Fit up Insp.
Curing
Final Insp.
Page 52 of 54
Adhesive Type used
Remarks
PLANT LOCATION
UNIT
670700
000
QCP CODE
SOUTH EAST KUWAIT PROJECT TITLE BUILDING NEW BOOSTER STATION BS 160 - AT SOUTH EAST KUWAIT
KHARAFI NATIONAL
JOB
REPORT NO
KOC
SAIPEM
NAME DESIGNATION SIGNATURE DATE Form Code: MDT.TB.CDQ.0122
PIPE SUPPORT FABRICATION INSPECTION REPORT Sl.No.
SUPPORT NO / DRAWING NO.
MARK / PART NO.
TYPE OF ITEM
MATERIAL
SUB CONTRACTOR
QTY
FIT UP ACCEPTANCE
DIM. AS PER DRG.
KHARAFI NATIONAL
DIM OBSERVED
WPS NO
DATE OF WELDING
WELDER NO
WELD VISUAL
KOC
SAIPEM
NAME DESIGNATION SIGNATURE 335226530.doc
NDT REPORT (IF APPLICABLE)
Page 53 of 54
REMARKS
PLANT LOCATION
SOUTH EAST KUWAIT PROJECT TITLE BUILDING NEW BOOSTER STATION BS 160 - AT SOUTH EAST KUWAIT
JOB
UNIT
670700
000
QCP CODE REPORT NO
DATE Form Code: MDT.TB.CDQ.0123 Refer ITP-RV-0101 in QCP 000-ZA-E-02635 for Lining and Coating Works.
Latest revision Latest revision - Check coating and holiday testing before back-filling -Check of trenching and Release for backfilling
335226530.doc
Page 54 of 54