Grid-connected PV installation Best practice guidelines
AuSES PV Installation Best Practice Workshop
1
Why best practice? AS/NZS mandate minimum requirements Best practices go above and beyond and include non-technical aspects Improve the quality/reputation of the PV industry Some best practices may be included in new versions of AS/NZS
AuSES PV Installation Best Practice Workshop
2
Before installation Visit customer’s site before preparing quote, don’t use satellite imagery Watch out for shading
◦ Solar Pathfinder, SunEye, mobile phone apps, visual estimate
Plan cable routes, inverter location, panel layout ◦ Minimize effect of shading
AuSES PV Installation Best Practice Workshop
3
Before installation Watch out for meter box upgrades Give a firm quote, no hidden costs Give a timeline to installation and stick to it Assist with regulatory approvals
◦ Grid connection, planning, RECs
AuSES PV Installation Best Practice Workshop
4
Before installation
Give an accurate estimated energy yield (in writing) ◦ PVSyst ◦ RETScreen ◦ Manual calculations using BOM or NASA or the ASRDH
AuSES PV Installation Best Practice Workshop
5
Before installation
Inclination
Azimuth -90°
-60°
-30°
0°
30°
60°
90°
0°
90%
90%
90%
90%
90%
90%
90%
15°
88%
93%
96%
98%
96%
93%
88%
30°
83%
92%
98%
100%
98%
92%
83%
45°
77%
88%
95%
97%
95%
88%
77%
60°
69%
80%
87%
90%
87%
80%
69%
75°
60%
70%
77%
78%
77%
70%
60%
90°
51%
59%
63%
63%
63%
59%
51%
AuSES PV Installation Best Practice Workshop
6
Health and Safety
AuSES PV Installation Best Practice Workshop
7
Health and Safety
AuSES PV Installation Best Practice Workshop
8
PV modules
AuSES PV Installation Best Practice Workshop
9
PV modules
AuSES PV Installation Best Practice Workshop
10
PV modules
AuSES PV Installation Best Practice Workshop
11
PV modules
AuSES PV Installation Best Practice Workshop
12
A note on fuses Overcurrent protection may be required when multiple stings are connected in parallel AS/NZS 5033:2005 provides sizing requirements for overcurrent protection AS/NZS 5033:2005 does not provide mandatory trip times for protection
AuSES PV Installation Best Practice Workshop
13
A note on fuses
IEC 61730.2 tests modules to withstand 135% of the maximum series fuse rating for 2 hours
=> size overcurrent protection so that it does not trip under normal operation, but trips within 2 hours of an overcurrent situation. Look at fuse/MCB manufacturer’s datasheets. AuSES PV Installation Best Practice Workshop
14
A note on fuses
AuSES PV Installation Best Practice Workshop
15
Polarized DC circuit breakers Pay attention to the direction of current Generally speaking, the PV array goes in the terminals marked + and – Check wiring with manufacturer
AuSES PV Installation Best Practice Workshop
16
DC cabling
AuSES PV Installation Best Practice Workshop
17
DC cabling
AuSES PV Installation Best Practice Workshop
18
DC cabling
AuSES PV Installation Best Practice Workshop
19
DC cabling
AuSES PV Installation Best Practice Workshop
20
DC cabling
AuSES PV Installation Best Practice Workshop
21
Inverters - good
AuSES PV Installation Best Practice Workshop
22
Inverters - good
AuSES PV Installation Best Practice Workshop
23
Inverters - better
AuSES PV Installation Best Practice Workshop
24
Inverters - best
AuSES PV Installation Best Practice Workshop
25
Inverters - best
AuSES PV Installation Best Practice Workshop
26
Labelling and documentation
AuSES PV Installation Best Practice Workshop
27
Labelling and documentation
AuSES PV Installation Best Practice Workshop
28
Labelling and documentation
Documentation should be given to customer after installation is complete: ◦ Overall working of system ◦ Data sheets and handbooks (PV modules, inverters, mounting rails) ◦ List of equipment supplied, with serial numbers ◦ Wiring diagrams and string layout
AuSES PV Installation Best Practice Workshop
29
Labelling and documentation ◦ Commissioning sheet and installation checklist ◦ Expected annual yield ◦ Warranty certificates and manufacturer’s contact details ◦ Maintenance procedures, shutdown procedure, alarms installed and action required.