pspr
Short Description
Download pspr...
Description
Power System Reliability – Concepts & Techniques
by
Dr Lalit Goel Professor of Power Engineering & Director of Admissions Nanyang Technological University, Singapore
IEEE PES Distinguished Lecturer Program India, Nov/Dec, 2011
Outline
Outline
1. Power System Reliability • Generating System (HLI) Reliability Assessment
• Composite System (HLII) Reliability Assessment • Distribution System Reliability Assessment • Cost-Benefit Considerations • Concluding Remarks
2
Outline 2. Generation System Reliability Assessment
• Generating Unit Modeling • Capacity Outage Probability Table • Evaluation of Risk of Capacity Shortfall • Comparison of Deterministic & Probabilistic Criteria • Incorporating Load Forecast Uncertainty • Concluding Remarks 3
1. Power System Reliability An electric power system serves the basic function of supplying customers, both large and small, with electrical energy as economically and as reliably as possible. The reliability associated with a power system is a measure of its ability to provide an adequate supply of electrical energy for the period of time intended under the operating conditions encountered. Modern society, because of its pattern of social and working habits, has come to expect the power supply to be continuously available on demand - this, however, is not physically possible in reality due to random system failures which are generally outside the control of power system engineers, operators and planners.
4
Power System Reliability The probability of customers being disconnected can be reduced by increased investment during either the planning phase, operating phase, or both. Over-investment can lead to excessive operating costs which must be reflected in the tariff structure. Consequently, the economic constraints can be violated even though the system may be highly reliable.
On the other hand, under-investment can lead to the opposite situation. It is evident therefore that the economic and reliability constraints can be quite competitive, and this can lead to extremely difficult managerial decisions at both the planning and operating phases.
5
Power System Reliability The criteria and techniques first used in practical applications were basically deterministic (rule-of-thumb) ones, for instance • Planning generating capacity - installed capacity equals the expected maximum demand plus a fixed percentage of the expected maximum demand;
• Operating capacity - spinning capacity equals the expected load demand plus a reserve equal to one or more largest units; • Planning network capacity - construct a minimum number of circuits to a load group, the minimum number being dependent on the maximum demand of the group.
6
Power System Reliability
Although the above-mentioned three and other criteria have been developed to account for randomly occurring failures, they are inherently deterministic. The essential weakness of these methods is that they do not account for the probabilistic/stochastic nature of system behavior, customer load demands and/or of component failures. Such aspects can be considered only through probabilistic criteria.
7
Power System Reliability Typical probabilistic aspects are as follows: • Forced outage rate of generating units is known to be a function of unit size and therefore a fixed percentage reserve cannot ensure a consistent risk; • Failure rates of overhead lines are functions of their lengths, design aspects, locations and environment, etc. - therefore a consistent risk of supply interruption cannot be ensured by constructing a minimum number of circuits;
• All planning and operating decisions are based on load forecasting techniques which cannot predict future loads precisely, i.e., uncertainties will always exist in the forecasts. This imposes statistical factors which should be assessed probabilistically. 8
Power System Reliability Adequacy and Security The concept of power system reliability, i.e., the overall ability of the system to satisfy the customer load requirements economically and reliably, is extremely broad. For the sake of simplicity, power system reliability can be divided into the two basic aspects of • system adequacy, and • system security. Adequacy relates to the existence of sufficient facilities within the system to satisfy customer load demands. These include the facilities to generate power, and the associated transmission and distribution facilities required to transport the generated energy to the load points. Adequacy, therefore, relates to static system conditions. 9
Power System Reliability
Security
pertains to the response of the system to the perturbations/disturbances it is subjected to. These may include conditions associated with local and widespread disturbances and loss of major generation/transmission.
Most of the techniques presently available are in the domain of adequacy assessment.
10
Power System Reliability Power system functional zones
Hierarchical levels
11
Power System Reliability
12
Power System Reliability
13
Power System Reliability
14
Power System Reliability
15
Generating System (HLI) Reliability Assessment Generating capacity reliability is defined in terms of the adequacy of the installed generating capacity to meet the system load demand. Outages of generating units and/or load in excess of the estimates could result in “loss of load”, i.e., the available capacity (installed capacity - capacity on outage) being inadequate to supply the load. In general, this condition requires emergency assistance from neighboring systems and emergency operating measures such as system voltage reduction and voluntary load curtailment. Depending on the shortage of the available capacity, load shedding may be initiated as the final measure after the emergency actions. The conventional definition of “loss of load” includes all events resulting in negative capacity margin or the available capacity being less than the load. 16
Generating System (HLI) Reliability Assessment
The basic methodology for evaluating generating system reliability is to develop probability models for capacity on outage and for load demand, and calculate the probability of loss of load by a convolution of the two models. This calculation can be repeated for all the periods (e.g., weeks) in a year considering the changes in the load demand, planned outages of units, and any unit additions or retirements, etc.
17
Generating System (HLI) Reliability Assessment Probabilistic Criteria and Indices An understanding of the probabilistic criteria and indices used in generating capacity reliability (HLI) studies is important. These include: 1. loss of load probability (LOLP) 2. loss of load expectation (LOLE) 3. loss of energy expectation (LOEE)/expected energy not supplied (EENS) 4. frequency & duration (F&D) indices 5. energy index of reliability (EIR) 6. energy index of unreliability (EIU), and 7. system minutes (SM). 18
Generating System (HLI) Reliability Assessment LOLP This is the oldest and the most basic probabilistic index. It is defined as the probability that the load will exceed the available generation. Its weakness is that it defines the likelihood of encountering trouble (loss of load) but not the severity; for the same value of LOLP, the degree of trouble may be less than 1 MW or greater than 1000 MW or more. Therefore it cannot recognize the degree of capacity or energy shortage. This index has been superseded by one of the following expected values in most planning applications because LOLP has less physical significance and is difficult to interpret. 19
Generating System (HLI) Reliability Assessment LOLE This is now the most widely used probabilistic index in deciding future generation capacity. It is generally defined as the average number of days (or hours) on which the daily peak load is expected to exceed the available capacity. It therefore indicates the expected number of days (or hours) for which a load loss or deficiency may occur. This concept implies a physical significance not forthcoming from the LOLP, although the two values are directly related. It has the same weaknesses that exist in the LOLP.
20
Generating System (HLI) Reliability Assessment LOEE This index is defined as the expected energy not supplied (EENS) due to those occasions when the load exceeds the available generation. It is presently less used than LOLE but is a more appealing index since it encompasses severity of the deficiencies as well as their likelihood. It therefore reflects risk more truly and is likely to gain popularity as power systems become more energy-limited due to reduced prime energy and increased environmental controls.
21
Generating System (HLI) Reliability Assessment EIR and EIU These are directly related to LOEE which is normalized by dividing by the total energy demanded. This basically ensures that large and small systems can be compared on an equal basis and chronological changes in a system can be tracked.
22
Generating System (HLI) Reliability Assessment Frequency & Duration (F&D) Indices The F&D criterion is an extension of LOLE and identifies expected frequencies of encountering deficiencies and their expected durations. It therefore contains additional physical characteristics but, although widely documented, is not used in practice. This is due mainly to the need for additional data and greatly increased complexity of the analysis without having any significant effect on the planning decisions.
23
Composite System (HLII) Reliability Assessment Objective • Composite generating and transmission system evaluation is concerned with the total problem of assessing the ability of the generation and transmission system to supply adequate and suitable electrical energy to the major system load points (Hierarchical level II - HL II) • The problem of calculating reliability indices is equivalent to assessing the expected value of a test function F(x), i.e., :
• All basic reliability indices can be represented by this expression, by using suitable definitions of the test function. 24
Composite System (HLII) Reliability Assessment Applications in power system planning • Expansion - selection of new generation, transmission, subtransmission configurations; • Operation - selection of operating scenarios; • Maintenance - scheduling of generation and transmission equipment
Basic models • G&T Equipment : Markovian or not; Two or multi-states.
Up
Down 25
Composite System (HLII) Reliability Assessment Basic models • Load : Chronological or not; Markovian or not; Correlated or not.
• System : AC or DC network representation.
26
Composite System (HLII) Reliability Assessment Reliability Measures (Conventional) System indices (sometimes appearing under different names) • LOLP = Loss of load probability • LOLE = Loss of load expectation (h/year) • EPNS = Expected power not supplied (MW) • EENS = Expected energy not supplied (MWh/year) • LOLF = Loss of load frequency (occ./year) • LOLD = Loss of load duration (h) • LOLC = Loss of load cost ($/year) Load point indices • LOLP, LOLE, etc. 27
Composite System (HLII) Reliability Assessment Reliability Measures (Well-Being) System indices • • • • • • • • •
Prob {H} = Probability of healthy state Prob {M} = Probability of marginal state Prob {R} = Probability of at risk state (LOLP) Freq {H} = Frequency of healthy state (occ./year) Freq {M} = Frequency of marginal state (occ./year) Freq {R} = Frequency of at risk state (LOLF) (occ./year) Dur {H} = Duration of healthy state (h) Dur {M} = Duration of marginal state (h) Dur {R} = Duration of at risk state (LOLD) (h)
Success Healthy Marginal
At Risk
Load point indices • Prob {H}, Freq {H}, etc. 28
Composite System (HLII) Reliability Assessment Assessment Tools State Selection • Enumeration
State Analysis (adequacy) • Power flow
• Monte Carlo simulation
o
Linear DC model
o Non-sequential
o
Non-linear AC model
o Sequential or chronological o Pseudo-chronological/sequential
• Optimal power flow o
Linear DC model
o
Non-linear AC model
29
Distribution System Reliability Assessment
Load Point Indices • failure rate,
• average outage time, r • average annual unavailability, U
= .r
• average load disconnected, L • expected energy not supplied, E =
U.L
30
Distribution System Reliability Assessment State Space (Markov) Model
State
Probability (P)
Visiting frequency (f)
Residence time (r)
0 1 2 3
P0 = A1.A2 P1 = U1.A2 P2 = A1.U2 P3 = U1.U2
f0 = P0/r0 f1 = P1/r1 f2 = P2/r2 f3 = P3/r3
r0 = 1/(1 + 2) r1 = 1/(1 + 2) r2 = 1/(2 + 1) r3 = 1/(1 + 2)
0
1
1
1
2
2
2
2
2
1
1
3
State space diagram for two-component, fourstate model
31
Distribution System Reliability Assessment Series Structure, n Components
32
Distribution System Reliability Assessment Parallel Structure, n (independent) Components n i ri n 1 Interruption frequency fs = 8760 [Interruptions/year] i=1 8760 i=1 ri
Interruption duration rs =
1 n
1 r i=1 i
Annual downtime Us = 8760
[hours/interruption]
n
i ri 8760 [hours/year] i=1
Us Unavailability qs = 8760 33
Distribution System Reliability Assessment System Oriented Reliability Indices, Number of Interruptions • Weighting by number of customers – System Average Interruption Frequency Index :
fi = number of interruptions at load point i Ni = number of customers connected to load point i n = number of load points interrupted ntot = total number of load points
34
Distribution System Reliability Assessment System Oriented Reliability Indices, Annual Interruption Time • Weighting by number of customers – System Average Interruption Duration Index :
Ui = firi = annual outage time for load point i ri = Average outage duration for load point i 35
Distribution System Reliability Assessment System Oriented Reliability Indices, Average Interruption Duration • Weighting by number of customers – Customer Average Interruption Duration Index :
n
SAIFI CAIDI = SAIDI
fi Ni
n
Ui Ni
i=1 n tot
i=1 n
i=1
i=1
Ni
tot
fi Ni
n
Ui Ni = i=1 n
tot
Ni i=1
n
fi ri Ni = i=1 n
tot
Ni i=1 36
Distribution System Reliability Assessment System Oriented Reliability Indices, Unavailability, Energy Not Supplied
• Average Service Unavailability Index
• Energy Not Supplied
• Average Energy Not Supplied
37
Cost-Benefit Considerations
• COST of providing quality and continuity of service < should be related to the >
• WORTH or BENEFIT of having that quality and continuity
38
Cost-Benefit Considerations
Due to the complex and integrated nature of a power system, failures in any part of the system can cause interruptions which range from inconveniencing a small number of local residents to a major and widespread catastrophic disruption of supply. The economic impact of these outages is not necessarily restricted to loss of revenue by the utility or loss of energy utilization by the customer but, in order to estimate the true costs, should also include indirect costs imposed on customers, society, and the environment due to the outage.
39
Cost-Benefit Considerations For instance, in the case of the 1977 New York blackout, 84% of the total costs of the blackout were attributed to indirect costs. In order to reduce the frequency and duration of these events, it is necessary to invest either in the design phase, the operating phase, or both. A whole series of questions come to mind: • • •
• •
is it worth spending any money? how much should be spent? should the reliability be increased, maintained at existing levels, or allowed to degrade? who should decide - the utility, a regulator, the customer? on what basis should the decision be made?
40
Cost-Benefit Considerations
The underlying trend in all these questions is the need to determine the worth of reliability in a power system, who should contribute to this worth, and who should decide the levels of reliability and investment required to achieve them. The basic questions that therefore need to be answered are “Is it worth it?” and “Where or on what should the next dollar be invested in the system to achieve the maximum reliability benefit?”.
41
Cost-Benefit Considerations The first step in answering the above questions is illustrated in the figure below, which shows how the reliability of a product/system is related to the investment cost, i.e., increased investment is required in order to improve reliability. This clearly shows the general trend that the incremental cost C to achieve a given increase in reliability R increases as the reliability level increases. Alternatively, a given increase in investment produces a decreasing increment in reliability as the reliability is increased. In either case, high reliability is expensive to achieve.
Incremental cost of reliability
42
Cost-Benefit Considerations The incremental cost of reliability, C/R, is one way of deciding whether an investment in the system is worth it. However, it does not adequately reflect the benefits seen by the utility, the customer, or society in general. The two aspects of reliability and economics can be appraised more consistently by comparing reliability cost (investment cost needed to achieve a certain level of reliability) with reliability worth (benefit derived by the customer and society).
43
Cost-Benefit Considerations The basic concept of reliability cost/reliability worth evaluation is relatively simple and can be presented by the curves of the figure shown below. These curves show that the investment cost generally increases with higher reliability. On the other hand, the customer costs associated with failures decrease as the reliability increases.
Utility and customer costs
44
Cost-Benefit Considerations
The total costs are the sum of these two individual costs. This total cost exhibits a minimum, and so an “optimum” or target level of reliability is achieved. Two difficulties usually arise in the total cost assessment. Firstly, the calculated indices are usually derived only from approximate models. Secondly, there are significant problems in assessing customer perceptions of system failure costs.
45
Cost-Benefit Considerations The disparity between the calculated indices and the monetary costs associated with supply interruptions is shown in the figure. The left hand side of the figure shows the calculated indices at the various hierarchical levels. The right hand side indicates the interruption cost data obtained by user studies.
It can be seen that the relative disparity between the calculated indices at the three hierarchical levels and the data available for worth assessment decreases as the consumer load points are approached.
46
Cost-Benefit Considerations
There have been many studies concerning interruption and outage costs. These studies show that, although trends are similar in virtually all cases, the costs vary over a wide range and depend on the country of origin and the type of customer. It is apparent therefore that considerable research still needs to be conducted on the subject of interruption costs.
47
Cost-Benefit Considerations
Broadly speaking, the cost of a power interruption from the customer's perspective is dependent both on the customer and interruption characteristics. Customer characteristics include type of customer, nature of his/her activities/demand requirements. Outage costs will therefore vary substantially between customers within a class, and between classes of customers. Interruption characteristics include the parameters of frequency, duration and magnitude of outage, time of occurrence, time of year, whether partial outage or complete, etc.
48
Cost-Benefit Considerations The most fundamental and methodological approach that has been used to assess direct, short-term customer outage costs is the customer survey method. This approach appears to find favors with electric utilities for estimating the outage costs to be used for planning purposes. It is based on the premise that the customer is in the best position to assess his/her monetary losses associated with power failures. The surveys ask the monetary losses that would be sustained by them under certain specified scenarios of interruptions, and also their willingness to pay in order to avoid having those interruptions. A very important consideration in determining the interruption cost through surveys is the choice of the valuation method. Three types of approaches have been undertaken in this regard.
49
Cost-Benefit Considerations 1. The first and the most obvious approach is a direct solicitation of the outage costs for given outage conditions. The approach provides reasonable and consistent results in situations where losses can be directly identified.
2. The second approach seeks the customers' opinions on what they would be willing to pay to avoid having the interruption(s), or conversely what amount they would be willing to accept for having to experience the outage (willingness-to-pay and willingness-toaccept theories). This is based on the theory that incremental willingness to pay (accept) gives the corresponding marginal increments (decrements) in service reliability.
50
Cost-Benefit Considerations
3. The third and final approach is that of indirect worth evaluation, where customers' responses to indirect questions are used to derive a monetary figure. This approach includes the respondents' selection of interruptible/curtailable options, their predictions of what preparatory actions they might take in the event of recurring interruptions, their ranking of a set of reliability/rate alternatives and selecting an option most suitable for their needs, etc. This approach has been used in major Canadian surveys, and has also been used by many utilities and governmental agencies to estimate the costs of interruptions.
51
Cost-Benefit Considerations Utilization of the gathered interruption cost estimates in a practical planning context could involve converting the gathered data into a functional representation or cost model. The traditional cost model is known as a composite customer damage function (CCDF), which defines the overall average costs of interruptions as a function of the interruption duration in a given service area that was used in the surveys. Since the customers are asked to provide their best estimates of monetary losses for selected outage scenarios, the interruption cost data collected using the survey method are duration specific. These data can be used to create customer damage functions (CDFs) for specific customer classes (sectors). The average sector costs associated with each studied interruption scenario are used to create sector customer damage functions (SCDFs) which are then (usually) weighted using their respective energy consumptions to create a CCDF for the entire studied area. 52
Cost-Benefit Considerations
53
Cost-Benefit Considerations
54
Cost-Benefit Considerations
55
Concluding Remarks • Probabilistic, as opposed to deterministic, indices are more popular in reliability evaluation of electric power systems.
• Fundamental reliability indices are those of probability, frequency and duration of failures, regardless of whether the system study is at HLI, HLII or HLIII system levels. • There should be some conformity between the reliability of various parts of the power system. It is pointless to reinforce quite arbitrarily a strong part of the system where weak areas still exist. Consequently, a balance is required between generation, transmission and distribution - this does not mean that the reliability of each should be equal. The reliability of different zones will, in general, be different since HLII failures can cause widespread outages whereas distribution failures are very localized. 56
Concluding Remarks • There should be some benefit gained by an improvement in reliability, i.e., the incremental or marginal investment cost should be related to the customer‟s incremental or marginal valuation of the improved reliability. Reliability cost Vs reliability worth (benefit) evaluation can enable utilities to make objective decisions about investments and maintenance for enhancing supply reliability. • Probabilistic methods are as important and critical today as they were a few decades ago, particularly in the light of increased pressure for economic justifications and the need to manage our assets effectively, efficiently and reliably.
57
2. Generation System Reliability Assessment The determination of the required amount of system generating capacity to ensure an adequate supply is an important aspect of power system planning and operation. The total problem can be divided into two conceptually different areas designated as static and operating capacity requirements. The static capacity area relates to the long-term evaluation of this overall system requirement. The operating capacity area relates to the short-term evaluation of the actual capacity required to meet a given load level.
58
Generation System Reliability Assessment The Static requirement can be considered as the installed capacity that must be planned and constructed in advance of the system requirements. The static reserve must be sufficient to provide for
the overhaul of generating equipment,
outages that are not planned or scheduled, and
load growth requirements in excess of the estimated values.
59
Generation System Reliability Assessment Generating capacity reliability is defined in terms of the adequacy of the installed generating capacity to meet the system load demand. Outages of generating units and/or load in excess of the estimates could result in “loss of load”, i.e., the available capacity (installed capacity capacity on outage) being inadequate to supply the load. In general, this condition requires emergency assistance from neighboring systems and emergency operating measures such as system voltage reduction and voluntary load curtailment. Depending on the shortage of the available capacity, load shedding may be initiated as the final measure after the emergency actions. The conventional definition of “loss of load” includes all events resulting in negative capacity margin or the available capacity being less than the load.
60
Generation System Reliability Assessment The basic methodology for evaluating generating system reliability is to develop probability models for capacity on outage and for load demand, and calculate the probability of loss of load by a convolution of the two models. This calculation can be repeated for all the periods (e.g., weeks) in a year considering the changes in the load demand, planned outages of units, and any unit additions or retirements, etc. The methods available to compute generating system reliability indices are described in this module.
61
Generation System Reliability Assessment Generating unit Modeling Generating unit parameters Generating unit means all equipment up to the high voltage terminals of the generator transformer and the station service transformers. Forced outage means the occurrence of a component failure or other condition which requires that the generating unit be removed from service immediately or up to and including the very next weekend. The basic generating unit parameter used in static capacity evaluation is the probability of finding the unit on forced outage at some distant time in the future. This probability is defined as the unit unavailability, and historically in power system applications is known as the unit forced outage rate (FOR). It is strictly speaking not a rate in modern reliability terms, since it is a ratio of two time values. 62
Generation System Reliability Assessment
Unit availability is defined as the probability of finding the unit in the operating (up) state at any future time.
expected failure rate (f/yr)
expected repair rate (rep/yr)
m
mean time to failure = MTTF = 1/
r
mean time to repair = MTTR = 1/
m+r
mean time between failures = MTBF = 1/f
f
cycle frequency = 1/T
T
cycle time = 1/f 63
Generation System Reliability Assessment The concepts of availability and unavailability as illustrated in the above equations are associated with the simple 2-state model shown in Figure 2.1. Down
Up
Figure 2.1 Two state model of unit
This model is directly applicable to a base load generating unit which is either operating or forced out of service. Scheduled outages must be considered separately.
64
Generation System Reliability Assessment In practice, however, generating units are complex pieces of machinery and in addition to complete failures experience partial failures where they continue to operate but at reduced capacity levels. A 3- or even multistate model is therefore required to more accurately represent the generating capacity model, as shown in Figure 2.2. 0
Full output
2
1
Partial output
Failed
Figure 2.2 State space diagram of component with partial output state 65
Capacity Outage Probability Table The purpose of the capacity model is to recognize the probabilistic nature of available generation capacity. The analytical generation model is generally in the form of discrete levels of capacity available (or unavailable) and their respective probabilities. This type of model is sufficient to calculate reliability indices in terms of probability, expected days (hours) of loss of load, and expected unserved (unsupplied) energy. There are many ways of creating and manipulating this capacity outage probability table (COPT), but the essential objectives and outcomes are the same. As the name suggests, the COPT is a simple array of capacity levels together with their probabilities. The basic assumptions for the capacity model are as follows:
66
Capacity Outage Probability Table 1. Each generating unit exists in one of two states, operating (up) or non-operating (down). Multi-state models can also be used to represent units having derated states. 2. The failure performance of a unit is independent of the operating level, the system load and the outage pattern of other units, etc. Generating capacity out of service due to forced outages is multinomially distributed with outage probabilities as parameters. The total number of available (or unavailable) capacity states in an N-unit system is 2N. For example, a 3-unit system (each unit can exist in 2 states) will have 23 = 8 states of available capacity (see Figure 2.3).
67
Capacity Outage Probability Table
A up, B up, C up
A up, B up, C down
A up, B down, C up
A down, B up, C up
A down, B down, C up
A down, B up, C down
A up, B down, C down
A down, B down, C down
68
Capacity Outage Probability Table 1
1U 2U 3U
2 1D 2U 3U
3
1U 2D 3U
4
1U 2U 3D
5 1D 2D 3U
6
1U 2D 3D
7
1D 2U 3D
8
1D 2D 3D
Figure 2.3 State space diagram for three component system
69
Capacity Outage Probability Table The basic statistic used in developing the capacity model is the probability of a generating unit being on forced outage, i.e. the forced outage rate. If all the units in the system are identical, the COPT can be easily obtained using the Binomial distribution.
Pr = nCrUrAn-r where A = unit availability U = unit unavailability n = number of identical units r = number of units in the failed state, and Pr = probability of r units in the down state. 70
Capacity Outage Probability Table Example 2.1: Let there be 4 identical generating units, 25 MW, 1% FOR each. Then
P0 = probability that zero units are in the failed state (i.e., all the 4 are up) = 4C0.(0.01)0.(0.99)4-0 = 0.994 = 0.960596. Similarly, the probability of exactly one unit being in the failed state P1 = 4C1.(0.01)1.(0.99)4-1 = 0.0388119 Thus, (A + U)4 = A4 + 4A3U + 6A2U2 + 4AU3 + U4 = P0 +P1 + P2 + P3 + P4 = 1.000000
71
Capacity Outage Probability Table STATE (i)
Capacity IN (MW)
Capacity OUT (MW)
State Probability (pi)
Cumulative Probability (Pi)
No. of UNITS DOWN
1
100
0
0.960596
1.000
NONE
2
75
25
0.0388119
0.0394038
1
3
50
50
0.000588
0.0005919
2
4
25
75
0.0000039
0.00000391
3
5
0
100
1x10-8
1x10-8
ALL
Ʃ = 1.000
The COPT can also be developed using cumulative probability, i.e., the probability of finding a quantity of capacity on outage equal to or greater than the indicated amount. e.g., cumulative probability of 0 MW capacity on outage is unity. The cumulative probability values decrease as the capacity on outage increases. Although this is not completely true for the individual COPT, the same general trend is followed. 72
Capacity Outage Probability Table Theoretically, the COPT incorporates all the system capacity. The table can, however, be truncated by omitting all capacity outages for which the cumulative probability is less than a specified value, e.g., 10-8. This also results in a considerable saving in computer time as the table is truncated progressively with each unit addition.
Alternatively, table rounding approach can be used by rounding the table to discrete levels after combining. The capacity rounding increment used depends upon the accuracy desired. The final rounded table contains capacity outage magnitudes that are multiples of the rounding increment. The number of capacity levels decreases as the rounding increment increases, with a corresponding decrease in accuracy.
73
Capacity Outage Probability Table Units are non-identical It is extremely unlikely, however, that all the units in a practical system will be identical, and therefore the Binomial distribution has limited application. The units can be combined, however, using basic probability concepts and this approach can be extended to a simple but powerful recursive technique in which the units are added sequentially to produce the final model. Example 2.2: Consider a 4-generating unit system with an installed capacity of 100 MW consisting of one 40 MW, 4% FOR unit and three 20 MW, 4% FOR units. Obtain the capacity model in the form of a COPT. Solution: First combine the three 20 MW units (identical) using binomial concepts (Table A). Then obtain the COPT for the 40 MW unit (Table B). 74
Capacity Outage Probability Table Table A i
Capacity IN (MW)
Capacity OUT (MW)
Probability (pi)
1
60
0
3C0 x 0.963 x 0.040 = 0.884736
2
40
20
3C1 x 0.962 x 0.041 = 0.110592
3
20
40
3C2 x 0.961 x 0.042 = 0.004608
4
0
60
3C3 x 0.960 x 0.043 = 0.000064 Ʃ = 1.000
Table B State
Capacity IN
Capacity OUT
Probability
1
40
0
0.96
2
0
40
0.04
75
Capacity Outage Probability Table Now we need to combine Tables A and B, i.e., each row of Table A must be combined with each row of Table B separately, and all identical states combined together. Rule used: If 2 events are independent, the probability of occurrence of one is not affected by the probability of occurrence of the other, i.e., P(A B) = P(A). P(B) e.g., combining state 1 of Table A with state 2 of Table B capacity in = 60 + 0 = 60 MW capacity out = 0 + 40 = 40 MW state probability = 0.884736 x 0.04 = 0.0353894 We thus get a total of 4 states (Table A) times 2 states (Table B) = 8 states, which can further be reduced by combining the ones with identical capacity available (or unavailable). 76
Capacity Outage Probability Table STATE
Table C
a b c d e f g h
STATE
Table D
(i) (ii) (iii) (iv) (v) (vi)
Capacity IN 100 60 80 40 60 20 40 0
Capacity OUT 0 40 20 60 40 80 60 100
Capacity Capacity IN OUT 100 80 60 40 20 0
0 20 40 60 80 100
How obtained? 1(A), 1(B) 1(A), 2(B) 2(A), 1(B) 2(A), 2(B) 3(A), 1(B) 3(A), 2(B) 4(A), 1(B) 4(A), 2(B)
Probability 0.8493465 0.0353894 0.1061683 0.0044236 0.0044236 0.0001843 0.0000614 0.0000025 Ʃ = 1.00
How obtained?
Probability (state)
Cumulative Prob.
a c b+e d+g f h
0.8493465 0.1061683 0.039813 0.004485 0.0001843 0.0000025
1.00 0.1506534 0.0444851 0.004672 0.0001868 0.0000025 77
Capacity Outage Probability Table Recursive Algorithm for COPT The capacity model can be created using a simple algorithm which can also be used to remove a unit from the model. This approach can also be used for a multi-state unit, i.e., a unit which can exist in one or more derated (partial output) states as well as in the fully up and fully down states. The algorithm is illustrated first using the 2-state units, and is then extended using the multi-state unit representations. Case 1: 2-State Unit Representation The cumulative probability of a particular capacity outage state of X MW, after a unit of capacity C MW and forced outage rate U is added, is given by P(X) = (1 - U).P‟(X) + (U).P‟(X - C) = (A).P‟(X) + (U).P‟(X - C) 78
Capacity Outage Probability Table where P‟(X) = cumulative probability of capacity outage state of X MW before a unit is added P(X) = cumulative probability of capacity outage state of X MW after a unit is added, and A and U are the availability and unavailability of the unit being added. The above expression is initialized by setting
P‟(X) = 1.0 for X 0, and P‟(X) = 0.0 otherwise.
79
Capacity Outage Probability Table Example 2.3: The algorithm is illustrated using the 100 MW system with the following data:
three 20 MW units, = 0.4 f/yr, = 9.6 rep/yr each, and one 40 MW unit with = 0.4 f/yr and = 9.6 rep/yr.
Consider also that the 20 MW units are loaded first followed by the 40 MW unit. Solution: Given = 0.4 failures/yr, and = 9.6 repairs/yr. Therefore
80
Capacity Outage Probability Table The system COPT is created sequentially as follows: Step 1: Add the first unit. Values of X are 0 and 20 MW. P(0) = (0.96).(1.0) + (0.04).(1.0) = 1.00 P(20) = (0.96).(0.0) + (0.04).(1.0) = 0.04 Step 2: Add the 2nd unit. Values of X: 0, 20 and 40 MW. P(0) = (0.96).(1.0) + (0.04).(1.0) = 1.00 P(20) = (0.96).(0.04) + (0.04).(1.0) = 0.0784 P(40) = (0.96).(0.0) + (0.04).(0.04) = 0.0016
81
Capacity Outage Probability Table Step 3: Add the 3rd unit. Values of X: 0, 20, 40 and 60 MW. P(0) = (0.96).(1.0) + (0.04).(1.0) = 1.00 P(20) = (0.96).(0.0784) + (0.04).(1.0) = 0.115264 P(40) = (0.96).(0.0016) + (0.04).(0.0784) = 0.004672 P(60) = (0.96).(0.0) + (0.04).(0.0016) = 0.000064
82
Capacity Outage Probability Table Step 4: Add the 4th unit. Values of X: 0, 20, 40, 60, 80 & 100 MW. P(0) = (0.96)(1.0) + (0.04)(1.0) = 1.00 P(20) = (0.96)(0.115264) + (0.04)(1.0) = 0.1506534 P(40) = (0.96)(0.004672) + (0.04)(1.0) = 0.00444851 P(60) = (0.96)(0.000064) + (0.04)(0.115264) = 0.0046718 P(80) = (0.96)(0.0) + (0.04)(0.004672) = 0.0001868 P(100) = (0.96)(0.0) + (0.04)(0.000064) = 0.0000025 It must be emphasized that for step number n, results from step (n-1) only are utilized (other than the initial conditions, if need be) - results prior to step (n-1) are of no consequence. 83
Capacity Outage Probability Table Exercise 2.1: A generating system consists of 3 generating units - two 3 MW, 2% FOR and one 5 MW, 2% FOR. Obtain the system COPT using the recursive algorithm.
84
Capacity Outage Probability Table Case 2: Multi-state unit representation The equation for 2-state representation can be modified to include multi-state unit representations. n P( X ) pi.P' ( X Ci ) i1
where: n is the no. of states of unit being added Ci is the capacity outage (MW) of state i for the unit being added, and pi is the probability of existence of the unit state i. Note that for n = 2, the above equation reduces to the form for 2-state representation. 85
Capacity Outage Probability Table Example 2.3 Revisited: Consider that in the system of Example 2.3, the 4th unit (40 MW) exists in 3 states as follows: state (i)
capacity out Ci (MW)
state probability (pi)
1 2 3
0 20 40
0.95 0.04 0.01
Solution: Since units 1, 2 and 3 (the 20 MW units) are still 2-state units, the capacity models for steps 1, 2 and 3 will remain the same as before. Step 4, however, will be different due to the unit 4 which is a multi-state unit. 86
Capacity Outage Probability Table Step 4: Add unit 4. X = 0, 20, 40, 60, 80, 100 MW. P(0) = (0.95)(1.0) + (0.04)(1.0) + (0.01)(1.0) = 1.0
P(20) = (0.95)(0.115264) + (0.04)(1.0) + (0.01)(1.0) = 0.1595008 P(40) = (0.95)(0.004672) + (0.04)(0.115264) + (0.01)(1.0) = 0.0190489
P(60) = (0.95)(0.000064) + (0.04)(0.004672) + (0.01)(0.115264) = 0.0014003 P(80) = (0.95)(0.0) + (0.04)(0.000064) + (0.01)(0.004672) = 0.0000492 P(100) = (0.95)(0.0) + (0.04)(0.0) + (0.01)(0.000064) = 0.0000006
87
Capacity Outage Probability Table Exercise 2.2: Obtain the COPT using the recursive algorithm for the following system: Unit A: 10 MW, 8% FOR, 2-state
Unit B: 20 MW, 8% FOR, 2-state Unit C: 30 MW, 8% FOR, 2-state Unit D: 40 MW, exists in 3 states, with full forced outage rate of 8%, and 50% derated capacity state has a probability of 0.06.
88
Evaluation of Risk of Capacity Shortfall The generation system model described in the previous chapter can be convolved with an appropriate load model to produce a system risk index. In order to convolve the capacity model with the load model, we need to identify the various kinds of load models that can be used. The simplest load model is where each day is represented by its daily peak load. The individual daily peak loads can be arranged in descending order to form a cumulative load model known as the daily peak load variation curve (DPLVC). The resultant model is known as the load duration curve (LDC) when the individual hourly load values are used, and in this case the area under the curve represents the energy required in the given period. This, however, is not the case with the DPLVC. Typical shapes of a LDC and DPLVC are shown in Figure 2.4 - both indicate the probability that a particular load level will be exceeded. 89
Evaluation of Risk of Capacity Shortfall
load level
DPLVC
LDC
0
0.2
0.4
0.6
0.8
1.0
time, p.u.
Figure 2.4
Typical shapes of a DPLVC and a LDC
90
Evaluation of Risk of Capacity Shortfall In the analytical approach, the applicable system COPT is combined with the system load characteristic to give an expected risk of loss of load. The units are in days if the DPLVC is used, and in hours if the LDC is used. Prior to combining the COPT it should be realized that there is a difference between the terms “capacity outage” and “loss of load”.
The term “capacity outage” indicates loss of generation which may or may not result in a loss of load. This condition depends upon the generating capacity reserve margin and the system load level. A “loss of load” will occur only when the capability of the generating capacity remaining in service is exceeded by the system load level.
91
Evaluation of Risk of Capacity Shortfall The loss of load expectation (LOLE) index, using the daily peak loads, is the expected number of days in the specified period in which the daily peak load will exceed the available capacity. LOLE =
days/period.........................................(2.1)
where: Ci
= available capacity on day i,
Li
= forecast peak load on day i, and
Pi(Ci-Li)
= probability of loss of load on day i.
(The last value is directly obtained from the cumulative COPT.) 92
Evaluation of Risk of Capacity Shortfall Example 2.4: Consider the generation system data and the 365-day load data shown below. Table 2.1: System data
Unit no.
capacity (MW)
failure rate (f/day)
repair rate (rep/day)
1
25
0.01
0.49
2
25
0.01
0.49
3
50
0.01
0.49
Table 2.2: Load data daily peak load (MW)
57
52
46
41
34
no. of occurrences
12
83
107
116
47
93
Evaluation of Risk of Capacity Shortfall The cumulative COPT for the system is shown below. Table 2.3 state (i)
capacity out (MW)
cumulative probability
1
0
1.00000
2
25
0.058808
3
50
0.020392
4
75
0.000792
5
100
0.000008
94
Evaluation of Risk of Capacity Shortfall Using Eqn 2.1, in conjunction with the COPT and load data, the LOLE is obtained as follows: LOLE = 12P(100-57) + 83P(100-52) + 107P(100-46) + 116P(100-41) +
47P(100-34) LOLE = 12(0.020392) + 83(0.020392) + 107(0.0007920) + 116(0.000792)
+ 47(0.000792) LOLE = 2.15108 days/year
95
Evaluation of Risk of Capacity Shortfall The same LOLE index can also be obtained using the DPLVC. Figure 2.5 below shows a typical system load-capacity relationship where the load model is shown as a continuous curve for a period of 365 days. It can be seen from Figure 2.5 that any capacity outage less than the reserve will not contribute to the system LOLE. Outages of capacity in excess of the reserve will result in varying numbers of time units during which loss of load would occur. Expressed mathematically, the contribution to the system LOLE made by capacity outage Ok is pktk time units, where pk is the individual probability of the capacity outage Ok. The total LOLE for the study interval is given by Eqn 2.2.
96
Evaluation of Risk of Capacity Shortfall Installed capacity (MW)
Daily peak load (MW)
Ok
0
Reserve
tk
Time load exceeds the indicated value
365
Figure 2.5 Relationship between load, capacity and reserve
97
Evaluation of Risk of Capacity Shortfall LOLE =
time units..........................................................(2.2)
Alternatively, the system LOLE can be obtained using the cumulative probability values from the COPT, as given by Eqn 2.3. LOLE =
time units................................................(2.3)
where Pk is the cumulative outage prob. for capacity state Ok. If the load characteristic in Figure 2.4 is the LDC, the value of LOLE will be in hours/period; for a DPLVC it will be in days/period. The period of study could be a week, a month or a year. The simplest application is the use of the curve on a yearly basis. If no generating unit maintenance were performed, the COPT would be valid for the entire period. 98
Evaluation of Risk of Capacity Shortfall Example 2.5: The application of Eqns 2.2 and 2.3 can be illustrated by a simple numerical example. Consider a system containing five 40 MW units each with a FOR of 1%. The COPT of this system is shown in Table 2.4. Capacity out of service (MW)
Individual probability
Cumulative probability
0
0.950991
1.000000
40
0.048029
0.049009
80
0.000971
0.000980
120
0.000009
0.000009
Table 2.4
1.000000
In the above COPT, binomial distribution concepts have been used and probability values below 10-6 have been neglected. 99
Evaluation of Risk of Capacity Shortfall
Daily peak load (%)
Let the system load model be represented by the annual DPLVC shown in Figure 2.6 - the curve is assumed to be linear for simplicity. In actual practice, however, the curve will be non-linear but the concept is still applicable. The 100% point on the abscissa corresponds to 365 days, while that on the ordinate corresponds to the system forecast peak (160 MW in this case). 100
40
0
Figure 2.6
Percentage of days the daily peak load exceeded the indicated value
DPLVC for the Example System
100 100
Evaluation of Risk of Capacity Shortfall The LOLE can be evaluated using Eqn 2.2 (individual probabilities) or Eqn 2.3 (cumulative probabilities) - both the methods are illustrated here. The time periods tk are calculated using the equation of the straight line DPLVC, and are shown in Figure 2.7. The LOLE calculations using Eqn 2.2 are shown in Table 2.5.
Daily peak load (MW)
Installed capacity = 200 MW O2 = 40MW
O3 = 80MW
O4 = 120MW
160 T4 = 41.7%
120 t3 = T3 = 41.7%
80 64
0
Figure 2.7
t4 = 83.4%
Time (%)
64
100
Time periods during which loss of load occurs 101
Evaluation of Risk of Capacity Shortfall Table 2.5 LOLE using individual probabilities
capacity out of service (MW)
capacity in service (MW)
individual probability (pk)
total time (tk) (%)
LOLE (pktk) (%)
0
200
0.950991
0
0
40
160
0.048029
0
0
80
120
0.000971
41.7
0.040491
120
80
0.000009
83.4
0.000751
1.00000
0.04124
The LOLE is 0.0412413% of the time base units, i.e., LOLE = 0.0412413(365/100) = 0.150410 days/yr If the cumulative probability values are used, the time quantities used are the interval or increases in curtailed time represented by Tk in Figure 2.7. The calculations are shown in Table 2.6. 102
Evaluation of Risk of Capacity Shortfall Table 2.6 LOLE using cumulative probabilities capacity out of service (MW)
capacity in service (MW)
cumulative prob. (Pk)
time LOLE (PkTk) interval Tk (%) (%)
0
200
1.000000
0
0
40
160
0.049009
0
0
80
120
0.000980
41.7
0.040866
120
80
0.000009
41.7
0.000375 0.04124
System LOLE = 0.0412414% (365/100) = 0.15041 d/yr
103
Evaluation of Risk of Capacity Shortfall If, however, it is assumed that instead of the load pattern being given by the DPLVC or the LDC, it is constant throughout the time period considered, then the system LOLE can be directly obtained as the cumulative probability of the first negative margin, i.e., of the first load loss state.
For instance, if the peak load in the example system described above is assumed to be constant at 160 MW for the year, then LOLE = Cum. Prob. of capacity out > 40 MW
= (0.000980) (time period) = (0.000980) (365) = 0.357755 days/yr
104
Evaluation of Risk of Capacity Shortfall Note that this value is significantly higher than the 0.15041 days/yr obtained using the DPLVC - hence it provides a pessimistic appraisal of the system performance. While the load in general is not expected to remain constant over a given time period, for planning purposes a single load level may be adequate in order to evaluate alternative capacity reinforcement/expansion proposals.
105
Evaluation of Risk of Capacity Shortfall Exercise 2.3 A generating system contains 120 MW capacity in six 20 MW units which are connected through step-up station transformers to a high voltage load bus, as shown in Figure 2.8. The generators have =3 failures/yr, and =97 repairs/yr each, whereas the transformers have =0.1 failures/yr and =19.9 repairs/yr each. For an annual forecast peak load of 95 MW, evaluate
the system LOLE at the load bus, given that the annual DPLVC is a straight line from the 100% to the 70% points.
[Ans.: 3.322 days/yr]
106
Evaluation of Risk of Capacity Shortfall 1
2
3
4
5
6
Generating bus
LOAD
Figure 2.8 Single line diagram of Exercise 2.3
107
Comparison of Deterministic & Probabilistic Criteria It was stated earlier that deterministic risk criteria such as “percentage reserve” and “loss of largest unit” do not define consistently the true risk in the system, whereas probabilistic criteria consider the actual influencing factors that govern system behaviour, unlike the deterministic ones. An example will help to illustrate this aspect.
Example 2.6: Consider the following four systems: system 1, twenty-four 10 MW, 1% FOR units system 2, twelve 20 MW, 1% FOR units system 3, twelve 20 MW, 3% FOR units system 4, twenty-two 10 MW, 1% FOR units 108
Comparison of Deterministic & Probabilistic Criteria All 4 systems are very similar but not identical. In each system, the units are identical and therefore the COPT can be constructed using the binomial distribution. The results are shown below in Tables 2.7 to 2.10 (arrays truncated to a cumulative probability of 10-6). Table 2.7 Capacity Outage Probability Table for System 1 System 1 Capacity (MW)
Probability
Out
In
Individual
Cumulative
0 10 20 30 40 50
240 230 220 210 200 190
0.785678 0.190467 0.022125 0.001639 0.000087 0.000004
1.000000 0.214322 0.023855 0.001730 0.000091 0.000004
109
Comparison of Deterministic & Probabilistic Criteria Table 2.8 Capacity Outage Probability Table for System 2 System 2 Out 0 20 40 60 80
Capacity (MW) In 240 220 200 180 160
Probability Individual Cumulative 0.886384 1.000000 0.107441 0.113616 0.005969 0.006175 0.000201 0.000206 0.000005 0.000005
Table 2.9 Capacity Outage Probability Table for System 3 System 3
Capacity (MW)
Probability
Out 0
In 240
Individual 0.693841
Cumulative 1.000000
20
220
0.257509
0.306159
40
200
0.043803
0.048650
60
180
0.004516
0.004847
80
160
0.000314
0.000331
100
140
0.000016
0.000017
120
120
0.000001
0.000001 110
Comparison of Deterministic & Probabilistic Criteria Table 2.10 Capacity Outage Probability Table for System 4 System 4 Out 0 10 20 30 40 50
Capacity (MW) In 220 210 200 190 180 170
Probability Individual Cumulative 0.801631 1.000000 0.178140 0.198369 0.018894 0.020229 0.001272 0.001335 0.000061 0.000063 0.000002 0.000002
The load level or demand on the system is assumed to be constant. If the risk in the system is defined as the probability of not meeting the load, then the true risk in the system is given by the value of cumulative probability corresponding to the outage state one level below that which satisfies the load on the system. 111
Comparison of Deterministic & Probabilistic Criteria The two deterministic criteria can now be compared with this probabilistic risk.
(a) Percentage Reserve Margin Assume that the expected load demands in systems 1, 2, 3 and 4 are 200, 200, 200 and 183 MW respectively. The installed capacity in each system is such that there is a 20% reserve margin, i.e., a constant for all 4 systems. The probabilistic (true) risks in the 4 systems are (from the above four tables): risk in system 1 = 0.000004 risk in system 2 = 0.000206 risk in system 3 = 0.004847 risk in system 4 = 0.000063 112
Comparison of Deterministic & Probabilistic Criteria It can be seen that the true risk in system 3 is 1000 times greater than that in system 1. A detailed analysis of the 4 systems will show that the variation in true risk depends on forced outage rates, number of units and load demand. The percentage reserve method cannot account for these factors and therefore, although using a “constant” risk criterion, does not provide consistent risk assessment of the system.
(b) Largest Unit Reserve Assume now that the expected load demands in systems 1, 2, 3 and 4 are 230, 220, 220 and 210 MW respectively. The installed capacity in all four cases is such that the reserve is equal to the largest unit which again is a constant for all four systems. In this case the true (probabilistic) risks in the systems are: 113
Comparison of Deterministic & Probabilistic Criteria risk in system 1 = 0.023855 risk in system 2 = 0.006175 risk in system 3 = 0.048650 risk in system 4 = 0.020229 The variation in risk is much smaller in this case, which gives some credence to the criterion. The risk merit order has changed from 3 -2 - 4 - 1 (percentage reserve criterion) to 3 - 1 - 4 - 2 (largest unit reserve criterion). It can clearly be concluded from the above comparisons that the use of deterministic or “rule-of-thumb” criteria can lead to very divergent probabilistic risks even for systems that are very similar. The deterministic criteria are therefore inconsistent, unreliable and subjective methods for reserve margin planning. 114
Incorporating Load Forecast Uncertainty In the previous sections of this chapter it has been assumed that the actual peak load will differ from the forecast value with zero probability. This is extremely unlikely in actual practice as the forecast is normally predicted on past experience. If it can be realized that some uncertainty can exist, it can be described by a probability distribution whose parameters (mean, standard deviation, etc.) can be determined from past experience, future load modeling and possible subjective evaluation. The uncertainty in load forecasting can be included in the risk computations by dividing the load forecast probability distribution into class intervals, the number of which depends upon the accuracy desired. The area of each class interval represents the probability that the load is the class interval mid-value. 115
Incorporating Load Forecast Uncertainty The LOLE is computed for each load represented by the class interval, and multiplied by the probability that that load exists. The sum of these products represents the LOLE for the forecast load. The calculated risk level increases as the forecast load uncertainty increases. It is extremely difficult to obtain sufficient historical data to determine the probability distribution describing the load forecast uncertainty (LFU). Published data, however, has suggested that the uncertainty can be reasonably described by a Gaussian (Normal) distribution.
The distribution mean is the forecast peak load. The distribution can be divided into a discrete number of class intervals. The load representing the class interval mid-point is assigned the designated probability for that class interval. This is shown in Figure 2.9, where the LFU distribution is divided into seven steps. 116
Incorporating Load Forecast Uncertainty The probability values of the seven load levels are presented in Table 2.11. It has been found that there is very little difference in the calculations between representing the distribution by 7 steps or 49 steps. The error is, however, dependent on the capacity levels for the system. A similar approach can be used to represent an unsymmetrical distribution, if required. Table 2.11 Probability values for seven-step LFU distribution no. of standard deviations associated probability from the mean 3
0.006
2
0.061
1
0.242
0
0.382 117
Incorporating Load Forecast Uncertainty Probability given by indicated area
0.061 0.006 -3
0.382 0.242
0.242
-2
No. of standard deviations from the mean
-1
0
+1
0.061 0.006
+2
+3
Mean = forecast load (MW)
Figure 2.9 Seven-step Gaussian distribution for LFU
118
Incorporating Load Forecast Uncertainty Example 2.7: Consider a generating system consisting of twelve 5 MW, 1% FOR units. The COPT is shown in Table 2.12 (probability values less than 10e-08 have been neglected). The forecast peak load is 50 MW, with uncertainty LFU assumed to be normally distributed using a seven-step approximation (Figure 2.9). The standard deviation (SD) is 2% of the forecast peak load. The monthly LDC is represented by a straight line at a load factor of 70% (minimum per unit load = two times per unit load factor minus one = 0.40). The LOLE calculations are shown in Table 2.13. Note that if there were no uncertainty in the forecast load, the system risk level would be 0.02523965 hrs/month. With LFU included, the new risk is 0.07839425 hrs/month. 119
Incorporating Load Forecast Uncertainty It can therefore be inferred that LFU is an extremely important parameter and in the light of the financial, societal and environmental uncertainties which electric power utilities face, it may be the single most important parameter in operating capacity reliability evaluation. Table 2.12 COPT for Example System capacity on outage cumulative probability (MW) 0 1.00000000 5 0.11361513 10 0.00617454 15 0.00020562 20 0.00000464 25 0.00000007
120
Incorporating Load Forecast Uncertainty Period = 1 month = 30 days = 720 hours Forecast load = mean = 50 MW Standard deviation (SD) = 2% = (50) (0.02) = 1 MW Table 2.13 LOLE results using LFU (1) (2) (3) (4) (5) no. of SD load probab. LOLE weighted from the (MW) of the for the load LOLE mean load in in col. (2) =(3) x (4) col. (2) (hrs/month) (hrs/month)
-3 -2 -1 0 +1 +2 +3
47 48 49 50 51 52 53
0.006 0.061 0.242 0.382 0.242 0.061 0.006
0.011101 0.016010 0.020719 0.025239 0.170028 0.309247 0.443213
0.000067 0.000977 0.005014 0.009667 0.041147 0.018864 0.002659 0.078394
121
Incorporating Load Forecast Uncertainty Exercise 2.4: Consider the four 25 MW, 1% FOR unit system with an annual constant forecast peak load of 80 MW as its DPLVC. The load forecast uncertainty (LFU) distribution is shown below in Figure 2.10. Determine the system LOLE. 12.257467 days/yr
0.75
p(x)
Answer:
0.10
0.15
X -10
X 0
X +10
x
Deviation from forecast (MW)
Figure 2.10
122
Incorporating Load Forecast Uncertainty Exercise 2.5: Consider that a generating system consists of five units as follows: Three 40 MW, 0.5% FOR units, one 50 MW, 2% FOR unit and one 60 MW, 2% FOR unit. The annual DPLVC is a straight line between the 100% and the 40% points. For a system forecast peak load of 200 MW, and using the LFU distribution shown below in Figure 2.11, determine the system risk (LOLE). Answer: 3.56591 days/yr
p(x)
0.6
Figure 2.11 0.2
0.2
X X X 0 +10 -10 Deviation from forecast (MW)
x 123
Concluding Remarks The applications of basic probability concepts to generating capacity reliability assessment and their use in generation planning for the long term have been illustrated. The LOLE technique is the most widely used probabilistic technique at the present time. This index, however, has received some criticism in the past on the grounds that it does not recognize the difference between a small capacity shortage and a large one, i.e., it is simply concerned with „loss of load‟. All shortages are therefore treated equally in the LOLE method. It is, however, possible to produce many additional indices such as the expected capacity shortage (if a shortage occurs), the expected number of days that specified shortages occur, etc. It is mainly a question of deciding what expectation indices are required, and then proceeding to calculate them. The derived values are expected values (long run average) and should not be expected to occur every year. 124
Concluding Remarks The indices should also not be considered as absolute measures of capacity adequacy, since they do not
describe the frequency and duration of inadequacies
include operating considerations such as spinning reserve requirements, dynamic and transient system disturbances, etc.
Indices such as LOLE and LOEE are simply indications of static capacity adequacy which respond to the basic elements that influence the performance of the given system. Inclusion of maintenance, load forecast uncertainty, etc. make the derived indices sensitive to these parameters and therefore a more overall appealing index, but still does not make the index an absolute measure of generating system reliability. 125
THANK YOU for your Time & Patience 126
View more...
Comments