1

INGENIEROS CIVILES MEXICANOS S.A. DE C.V.

PRESUPUESTO DE CONSTRUCCIÓN OBRA N° 23042007 DE LA CALLE REVOLUCION DE OCTUBRE EN LA COLONIA INSURGENTES NUMERO 124 DE LA CIUDAD DE POZA RICA DE HIDALGO, VERACRUZ C.P. 93280 QUE CONSTARA DE 1 PLANTA, PROPIEDAD DE Laura Enriqueta _Antonio Santiago R.F.C. ANAC2304071HPEA8 FECHA: 1 DE NOVIEMBRE DEL 2012. NOMBRE DEL CONSTRUCTOR: Carlos Armando Nuñez Franco N° REGISTRO 010792 PERITO O D.R.O. OBRAS PUBLICAS N° DE REGISTRO 23/04/2007

No°

CONCEPTO

IMPORTE

%

1

PRELIMINARES

$21,048.15

3.59

2

CIMENTACION

$56,186.43

9.59

3

ALBAÑILERIA

$374,823.82

64.00

4

ACABADO EN MUROS

$14,376.26

2.45

5

HERRERIA

$25,072.00

4.28

6

BLANQUEADO Y PINTURA

$11,501.44

1.96

7

MANO DE OBRA

$82,675.00

14.12

IMPORTE TOTAL

$585,683.09

IVA

$93,709.29

COSTO TOTAL DE LA OBRA A CONTRATAR

$679,392.38

(CANTIDAD CON LETRA): (SEIS CIENTOS SETENTA Y NUEVE MIL TRESCIENTOS NOVENTA Y DOS PESOS 38/100 M.N.)

AV. EJERCITO MEXICANO N° 100, COLONIA ARGENTINA TEL. 7821216211 CORREO: [email protected] POZA RICA DE HIDALGO, VER.

1

2

INGENIEROS CIVILES MEXICANOS S.A. DE C.V.

PRESUPUESTO DEL MATERIAL PARA LA CONSTRUCCIÓN DE UNA CANCHA DE FUTBOL RAPIDO

CLAVE 1

DESCRIPCIÓN O CONCEPTO DE OBRA

UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE

PRELIMINARES 1.1 1.2 1.3

1.4

Limpieza del área de trabajo 1800 m2 Trazo y nivelación del terreno Excavación a mano en terreno tipo "A", profundidad de 0.00 a 0.50 m. Incluye afine de taludes y fondo, equipo, herramienta y  todo lo necesario para su correcta ejecución. Relleno compactado con pisón de mano, en 1 capa de 15 cm, utilizando material producto de la excavación, sin control de laboratorio, incluye: acarreos, volteo del material, adicionamiento de agua, mano de obra, herramienta y todo lo necesario para su correcta ejecución.

jor m2

2 293

$450.00 $4.11

$900.00 $1,204.23

m3

146.5

$104.92

$15,370.78

m3

43.95

$81.30

$3,573.14

Total de PRELIMINARES

$21,048.15

CIMENTACIÓN

2

Plantilla de consolidación para desplante de la obra d e 10 cm de espesor, con concreto hecho en obra de F´c= 100 kg/cm2 2.1.1 Cemento 2.1.2 Grava 2.1.3 Arena 2.1.4 Agua

2.1

Contratrabe o Zapata de cimentación corrida de acuerdo al   proyecto, de 0.25 m por 0.25 m de sección, armada con 4 varillas 2.2 de 3/8, y estribos de alambrón de 1/4 @ 20 cm. Concreto de F´c= 150 kg/cm2. 2.2.1 Cemento 2.2.2 Grava 2.2.3 Arena 2.2.4 Agua 2.2.5 Varilla 3/8 2.2.6 Alambrón 1/4

m2

293

ton m3 m3 lts

4.395 12.525 10.855 4175.25

ml

293

ton m3 m3 lts ton ton

5.493 13.569 11.481 4175.136 0.718 0.338

$2,250.00 $350.00 $400.00 $0.07

$9,888.75 $4,383.75 $4,342.00 $292.27

$2,250.00 $350.00 $400.00 $0.07 $14,700.00 $14,000.00

$12,359.25 $4,749.15 $4,592.40 $292.26 $10,554.60 $4,732.00

TOTAL CIMENTACIÓN

AV. EJERCITO MEXICANO N° 100, COLONIA ARGENTINA TEL. 7821216211 CORREO: [email protected] POZA RICA DE HIDALGO, VER.

$56,186.43

2

3

3

INGENIEROS CIVILES MEXICANOS S.A. DE C.V.

ALBAÑILERIA Barda del área de juego y bancas (medidas de acuerdo al   plano), elaborada con Block de la región de 12x20x40 cm, colocada con mortero convencional. 3.1.1 Cemento 3.1.2 Arena 3.1.3 Agua 3.1.4 Block

3.1

3.2 3.2.1 3.2.2 3.2.3 3.2.4 3.2.5 3.2.6

3.3 3.3.1 3.3.2 3.3.3 3.3.4 3.3.5 3.3.6

3.4 3.4.1 3.4.2 3.4.3 3.4.4 3.4.5

3.5

Castillos de 0.15x 0.15 m, alturas de a cuerdo al plano , elaborados con 4 varillas de 3/8 y estribos @ 20 cm, de alambrón de 1/4; concreto de F´c= 150 kg/cm2. Cemento Grava Arena Agua Varilla de 3/8 Alambrón de 1/4 Cadena d e Cerramiento o Trabe d e 0.20x0.20 m, elaborada con 4 varillas de 3/8 y estribos @ 20 cm de alambrón de 1/4, concreto de F´c= 150 kg/cm2. Cemento Grava Arena Agua Varilla de 3/8 Alambrón de 1/4 Losa de las po rterías de 0.20 m de espesor, elaboradas con malla electro soldada para losa y concreto de F´c= 150 kg/cm2 Cemento Grava Arena Agua Malla Ele ctro soldada Piso del área de juego y bancas, elaborado con un concreto de F´c= 150 kg/cm2 y reforzado con Malla Electro soldada para piso. Bloques de 2x2m, 0.10 m de espesor. Cemento Grava Arena Agua Malla Ele ctro soldada

3.5.1 3.5.2 3.5.3 3.5.4 3.5.5 TOTAL ALBAÑILERIA

m2

306.5

ton m3 lts pza.

2.15 5.62 1334.78 4017

ml

70

ton m3 m3 lts ton ton

0.472 1.167 0.987 359.1 0.171 0.042

ml

227

ton m3 m3 lts ton ton

2.724 6.728 5.693 2070.24 0.556 0.262

m3

3.2

ton m3 m3 lts m2

0.48 1.185 1 364.8 10

m2

1221

ton m3 m3 lts m2

73.26 180.95 153.11 55677.6 1221

AV. EJERCITO MEXICANO N° 100, COLONIA ARGENTINA TEL. 7821216211 CORREO: [email protected] POZA RICA DE HIDALGO, VER.

$2,250.00 $400.00 $0.07 $4.38

$4,837.50 $2,248.00 $93.43 $17,594.46

$2,250.00 $350.00 $400.00 $0.07 $14,700.00 $14,000.00

$1,062.00 $408.45 $394.80 $25.14 $2,513.70 $588.00

$2,250.00 $350.00 $400.00 $0.07 $14,700.00 $14,000.00

$6,129.00 $2,354.80 $2,277.20 $144.92 $8,173.20 $3,668.00

$2,250.00 $350.00 $400.00 $0.07 22

$1,080.00 $414.75 $400.00 $25.54 $220.00

$2,250.00 $350.00 $400.00 $0.07 22

$164,835.00 $63,332.50 $61,244.00 $3,897.43 $26,862.00 $374,823.82

3

4

4

INGENIEROS CIVILES MEXICANOS S.A. DE C.V.

ACABADOS EN MUROS 4.1

Revoque de muros por ambos lados de 2 cm de grosor, mortero convencional.

3.5.1 Cemento 3.5.2 Arena 3.5.3 Agua TOTAL DE ACABADOS EN MUROS 5

m2

648.8

ton m3 lts

4.31 11.23 2667.98

ml

150

pza. pza. pza.

7.5 12 50

m3

0.843

saco lts

23 98.68

m2

648.8

bote lts

4 7.6

$2,250.00 $400.00 $0.07

$9,697.50 $4,492.00 $186.76 $14,376.26

$1,244.00 $166.00 $275.00

$9,330.00 $1,992.00 $13,750.00 $25,072.00

$230.00 $0.07

$5,290.00 $6.91

HERRERIA 5.1

Cercado del perímetro del área de juego, con malla ciclónica  forrada color verde, de 2 metros de altura

5.1.1 Malla Ciclónica forrada 5.1.2 Tubo Galvanizado de 3" 5.1.3 Placa o solera de 1" TOTAL DE HERRERIA 6

BLANQUEADO Y PINTURA 6.1

Blanqueado con Cemento Blanco

6.1.1 Cemento blanco 6.1.2 Agua 6.2

Pintura vinílica

6.2.1 Cubeta de 19 lts de Pintura blanca 6.2.2 Agua TOTAL BLANQUEADO Y PINTURA

$1,551.00 $0.07

$6,204.00 $0.53 $11,501.44

$503,008.09 $80,481.29 $583,489.38

TOTAL DE LOS MATERIALES PARA LA CONSTRUCCION DE LA CANCHA DE FUTBOL RAPIDO IMPUESTO TOTAL

AV. EJERCITO MEXICANO N° 100, COLONIA ARGENTINA TEL. 7821216211 CORREO: [email protected] POZA RICA DE HIDALGO, VER.

4

INGENIEROS CIVILES MEXICANOS S.A. DE C.V.

5

Concepto de

Cantida

Obra

d

Trazo y nivelación

293

Excavación

146.5

Rendimiento por

Cantidad de

 jornada m2, m3, ml

personal

2

Relleno Compactado

43.95

Plantilla de Consolidación

293

Contratrabe de cimentación

293

Barda perimetral de Block

306.5

Castillos

70

Cadena de Cerramiento o Trabe

227

Losa de las porterías

3.2

Piso del área de Juego y bancas

1221

Revoque en muros por ambos lados erca o e área de juego con malla

Unidad

648.8

150

Blanqueado de la barda

648.8

Pintado de la barda

648.8

m2

m3

m3

m2

m

m2

m

m

m3

m2

m2

m

m2

m2

ipo de personal Jornadas

Of. Albañil

21

Importe

$

250.00

$ 1,750.00

$

150.00

$ 1,050.00

$

250.00

$ 2,250.00

$

150.00

$ 4,050.00

$

250.00

$ 1,000.00

$

150.00

$ 1,200.00

$

250.00

$ 3,000.00

$

150.00

$ 4,500.00

$

300.00

$ 3,600.00

$

150.00

$ 1,800.00

$

300.00

$ 8,400.00

$

150.00

$ 4,200.00

$

300.00

$

750.00

$

150.00

$

750.00

$

300.00

$ 2,700.00

$

150.00

$ 1,350.00

$

250.00

$

250.00

$

150.00

$

150.00

$

250.00

$ 5,000.00

$

150.00

$ 15,000.00

$

250.00

$ 4,750.00

$

150.00

$ 7,125.00

$

300.00

$

600.00

$

200.00

$

800.00

$

250.00

$ 1,750.00

$

150.00

$ 2,100.00

$

250.00

$ 1,750.00

$

150.00

$ 1,050.00

3.5 2

Peón

2

Of. Albañil

4

4.5 6

Peón

2

Of. Albañil

3.5

2 4

Peón

2

Of. Albañil

7

6 5

Peón

2

Of. Especialista

12.5

6 2

Peón

2

Of. Especialista

5.5

14 2

Peón

1

Of. Especialista

9.5

2.5 2

peón

2

Of. Especialista

12.5

4.5 2

peón

1

Of. Albañil

1.5

1 1

Peón

2

Of. Albañil

10

10 10

Peón

2

Of. Albañil

10

9.5 5

Peón

1

Herrero

25

30

Salario

2 2

yudante Herrer

1

Of. Albañil

2

peón

1

Of. Albañil

30

7

7 1

Peón JORNADAS

AV. EJERCITO MEXICANO N° 100, COLONIA ARGENTINA TEL. 7821216211 CORREO: [email protected] POZA RICA DE HIDALGO, VER.

79.5

IMPORTE

$ 82,675.00

IVA

$ 13,228.00

TOTAL

$ 95,903.00

5

6

INGENIEROS CIVILES MEXICANOS S.A. DE C.V.

Costo de La maquinaria a utilizar, en este caso, solo se necesitara una revolvedora de trompo. Revoveldora de trompo MAXI-10 1 saco (320 lt) de gasolina 8 HP. Costo de la maquinaria (Cm) Valor de las llantas (Pn) Valor de las piezas especiales (Pa) Valor de la maquina (Vm) Horas efectivas al año (Hea) Vida Economica (V) Tasa de Seguro (s) % de Mantenimiento (Ko) % de Rescate (r) Tasa de Intereses (i) Vr = Vm * r Ve = V * Hea CONSUMOS Descripción Diesel Aceite lubricante

Unidad l l

OPERACIÓN Descripcion Operador de Equipo Mayor

= = = = = = = = = = = =

26,566.34

26,566.34 650 3 0.03 1 15 0.16 3,984.95 1,950.00

Cantidad 0.8 0.012

CARGOS FIJOS a) Depreciación: b) Inversión: c) Seguros: d) Mantenimiento: TOTAL DE CARGOS FIJOS:

Costo $6.71 $48.43

Importe $5.37 $0.58

TOTAL DE CONSUMO:

$5.95

Unidad jor

Cantidad 0.15625

Costo $381.12

TOTAL DE OPERACIÓN: TOTAL DE COSTO HORARIO: Costo por dia:

D= (Vm-Vr)/Ve Im= (Vm+Vr)*i/2*Hea Sm= (Vm+Vr)*s/2*Hea Mn=Ko*D $27.63

Importe $59.55 $59.55 $93.13

$745.04

AV. EJERCITO MEXICANO N° 100, COLONIA ARGENTINA TEL. 7821216211 CORREO: [email protected] POZA RICA DE HIDALGO, VER.

6

11.58 3.76 0.71 11.58

View more...