Project Timetable Feasib

October 27, 2017 | Author: William Andrew Gutiera Bulaqueña | Category: Feasibility Study, Scheduling (Production Processes), Technology, Economies, Business
Share Embed Donate


Short Description

Timetable sample of Feasib...

Description

Activities/Tasks

A. Feasibility Study

Predeces sor Activity None

Start Date

Finish Date

Duration

November 30 2015 December 31 2015 January 15 2016 March 31 2016 April 30 2016

91 Days

B. Pulling up of Equity C. Registration

A

D. Renovation

B

E. Equipment & Supplies F. Orders and Receipts of Console Gaming Equipment G. Installation of Gaming Equipment and Other Supplies H. Hiring and Training of Personnel I. Start of Operations

D

September 1 2015 December 1 2015 January 1 2016 January 1 2016 April 1 2016

D

April 1 2016

April 30 2016

30 Days

D

April 1 2016

April 30 2016

30 Days

G

May 1 2016

May 31 2016

31 Days

H

June 1 2016

B

31 Days 15 Days 91 Days 30 Days

Project Schedule Business purpose or objectives are set to be accomplished. Realization of these objectives can be obtained through proper planning and scheduling of specific business activities to be undertaker. The proportion of a project schedule is very important. And to concretize the various process/sequences, the proponents involved are a GANTT chart that will control and monitor the process. Areas of consideration: Feasibility Study Duration: From September 1 2015 to November 30 2015 The feasibility study will be completed within this period to which the researchers conducted a comprehensive study like interviews and surveys. The also involves an analysis of market, technical and financial feasibility of the business. Areas of consideration: Putting up of equity

Duration: From December 1 2015 to December 31 2015 Collection of cash contribution from the proponents for the capitalization of the business will take place within this period. Capitalization ranges from P500,000 to P700,000, thus requiring more time to put up the required capitalization.

Areas of consideration: Registration Duration: From January 1 - 15 2016 Areas of consideration: Renovation Duration: From January 1 2016 to March 31 2016 Aldecoa Drive, Brgy. Daro, Dumaguete City is the best location for our business because university and other schools are near the place and it is very accessible to the public. Furthermore, the place is surrounded by a number a boarding houses for students. The building, intended as its business locale is family owned. Areas of consideration: Equipment and Supplies Duration: From April 1-30 2016 The owner will have to canvas the console gaming equipment, furniture and other supplies for the Gaming Cafe which aims to get the lowest price but with high quality. The one who will give the better offer is the first priority. Areas of consideration: Orders and receipts of computer equipment and other supplies Duration: From April 1-30 2016 Orders of gaming equipments and other supplies should be listed for the purpose of monitoring. Receipts should be issued to determine the mode of payment. Areas of consideration: Installation of computer equipment and other supplies Duration: From April 1-30 2016 Delivery and installation of the console gaming equipments and other supplies/equipments to be used by the business for giving a quality service should be done during this period.

Areas of consideration: Hiring and training of personnel Duration: From May 1 – 31 2016 During this period, the partners will train its employees/workers for the different jobs assigned. Areas of consideration: Start of the Operation Duration: June 2016 The business will start during this period. Its goal is to give quality service at the most affordable price possible.