Project System

Table of contents 1. Organizational Units & Project Cycle 2. Project Structures 3 Planning and Budgeting 4. Materials and Services 5. Scheduling 6. Execution 7. Period End Closing 8. Information System

Organizational Units & Project Cycle

SAP Modular Structure: Overview FINANCE

9

LOGISTICS

SD

HUMAN RESOURCES

PS

Project System

CO

MM

PP

Materials Mgmt.

Product Planning

QM

Quality Mgmt.

FI

Financial Accounting

Sales & Distribution

R3

Controlling

AM

Fixed Asset Mgmt.

Client/Server ABAP/4 IM PM HR

Project System

Investment Mgt.

Plant Maint.

Human Resources

PS

IS Industry Solutions

9

9

Project Execution Procedure Execution Execution

Development Development Phase 1

Phase 2

Phase 3

Phase 4

Phase 5

Phase 6

Idea Generation To Concept Approval & Basic design

Detailed Engineering

Procurement

Construction

Commissioning & Start-up

Close out

Idea Idea initiation. initiation. Idea Idea screening. screening. Concept Concept design design Concept Concept approval. approval.

IMA11 Create AR IMA11 Plan AR Costs IMA11 Status Chg IMA11 Create Proj Def

Fund Fund approval approval

Detailed Detailed Design. Design. Engineering Engineering Pkg. Pkg. Procurement Procurement Pkg. Pkg. Construction Construction Pkg. Pkg.

Procurement. Procurement. Materials. Materials. Services. Services.

CN25 Enter Confirmation

CJ20N Create Proj Structure CJ20N Plan Ph 1-6 WBS IM52 Distribute Full Budget

ME21N Create PO’s CN25 Enter Time Confs ML81 Service Entry

Installation. Installation. Pre-commissioning. Pre-commissioning. Turn-over Turn-over to to owner. owner.

Commissing Commissing && Startup Startup plan. plan. Training. Training. Pre-startup Pre-startup

Project Project close close out out ..

CJ88 Final Settlement CJ20N Close Project CJ20N Plan Resources CJ20N Schedule Network CN25 Enter Time Conf’s CN25 Enter Time Conf’s ML81 Service Entry ML81 Service Entry CJ20N TECO WBS’s

Sequence of Events in Projects II M M

Inv. Prog

“Investment Positions”

Idea

Business Planning

Appropriation Request

Planning Master Data “Pre-Investment”

Investment Measure

Approval Budgeting

PS PS

Fiscal Year Change Detailed Engineering Settlement & Capitalisation Procurement Construction

IM / PS Overview Animation Investment Program Budget Distributed Plan

110 110 130

II M M

Investment Position

Investment Position

Investment Position

Budget Distributed Plan

Budget Distributed Plan

Budget Distributed Plan

80 80 100

20 20

Budget Approval

Appropriation Request

Plan

Project Required

Plan Ver 0

FI FI

MM MM

PM PM

100

ACTUAL VALUES

AUC

10 10

Cost Center Plan Actual

PS PS

Investment Measure “Project” Budget 80 100

CO CO

FI-AA FI-AA

Depreciation Simulation “Asset Class” Asset 1

Settlement Settlement Asset 2

PS Integration Points Animation Investment Position Budget 100 Distributed 100 Plan 100 PS PS

Investment Measure / Appropriation Request WBS 1.1

Budget Plan 100

II M M

CO CO

Comm Act Assign 20 40 65 20 45 60 Cost Center

Settlement

System Processing status

Actual / Plan

CRTD BUDG AVAC REL

FI-AA FI-AA

1100

1400

1500

1000

1700 Settlement

1200

1300

1600

Invoice

Material PR/PO

MM MM

Asset 1

AUC 40%

PM PM FI FI

60%

Service PR/PO

5Hrs. Conf

HR HR

Asset 2

Project Structure

Project Approach ‹

‹

‹

Projects are planned and implemented using a phase approach. These are further summarized as Development and Execution. Cost planning, budgeting, approval, resource planning are some of the activities that are done for each phase separately. Main project is represented under the execution phase where the planning, budgeting, scheduling is carried out.

Master Data in Project Systems ‹

Data that is stored in the database for long periods of time is referred to as master data

‹

Accurate master data reduces: ; Creation time for controlling documents ; Amount of errors in the controlling process

Master Data in Project Systems WBS elements

Network / Activities

Responsibility- oriented

Process- oriented

Assignments WBS elements and activities

13-1

Note: ALL CCA MASTER DATA IS MAINTAINED CENTRALLY

Master Data created in Project Systems Work Breakdown Structure Individual structural element in a work breakdown structure (WBS) representing the hierarchical organization of an R/3 project. Describes either a discrete task or a partial one that can be further subdivided. WBS Elements

Master Data created in Project System Networks A network represents the flow of a project or of a task within a project. Network / Activities

During the life of a project, networks are used as a basis for planning, analyzing, controlling and monitoring schedules, dates and resources (such as people, machines, materials, documents and drawings). You can assign networks to a project. A network is a special type of work order that has the same structure as production orders, maintenance orders, and inspection orders in the R/3 System.

Master Data used in Project Systems

Cost Center

Profit Center

Cost Center The cost center master record represents the main organizational unit in Controlling. Each department units will have their own Cost center number. Each department will plan and monitor their yearly budget / expenditure on their respective cost centers. Profit Center Is an organizational unit in Accounting that reflects a management-oriented structure of the organization for the purpose of internal control. Profit Center groups are collections of Profit centers with similar characteristics.

Activity Types Activity types define the type of activity that can be provided by a cost center (work activity, machine hours, and so on). Activity Types

Overview of Objects in PS

‹Investment

Programs

Investment Program

II M M

; Capital ; Expense ‹Appropriation II M M

“Investment Positions” Appropriation Requests

“Investment Measures” PS PS WBS Elements

Investment Projects WBS Elements

Requests ‹Work

Breakdown

Structures WBS Elements

‹Maintenance

Orders PS PS

PM PM “Activities”

‹Networks

M/Ord

M/Ord

Project Characteristics Hierarchy of Parts

Accounting

Purchasing

Controlling

Cross Departmental

Complexity & Uniqueness

Resources

Costs & Revenues

Dates

Budgeting

Planning & Controlling

Contents ‹

Master Data in Project Systems: ; Work Breakdown Structures ; Networks and Activities

‹

Status Control

‹

Tools ; Table controls

‹

Project Versions

What are Work Breakdown Structures used for? Planning: Dates: Š Planned Costs

Š Basic Dates Š Scheduled Dates Š Actual Dates

Periodic Processing: Š Overheads Š Settlement Š Earned Value Analysis

Budget: “WBS Structure”

Š Original Budget Š Budget Updates Š Release Budgets Š Availability Control

Execution: Š Actual Costs

Commitments: Š Purchase Requisition Š Purchase Order

Project Definition and Work Breakdown Structure

Project Definitions Project Definitions

Work Breakdown Structures

WBS Elements

Project Definition

Numbering Project Numbering & Coding Masks

Project Definition

Settings Field Requirements Project Profile

Responsibilities Dates

Organisational Data

Project Numbering ‹

System Business Number Logic ; You can tell a lot about a project by its number!

Approval Year 2006

Project Running Number WBS-Structure

V-0691001.00.00.00.00 Capital projects

Company Code 9100 A Ltd 9200 A1 Ltd

Project Coding Mask

PrjID V

Coding mask

Description

Lck

LkS

- 0000000.00.00.00.00 A Grp. Operative Project

I Coding mask Key

0 = number

Lock for operative WBS

Lock for standard WBS

Project Profile Control Field Key Simulation Status Profile

Organization

Controlling

Controlling Area

Planner Profile

Company Code

Budget Profile

Business Area

Settlemement Profile …

Project Profile

Planning Board / Dates WBS Scheduling Planning Board Profile Hierarchy Graphic …

Project Field requirements – Project Definition ‹

Project Definition ; Project Definition Description ; Person Responsible ; Applicant number ; Plant ; Finish Dates

Project Definition and Work Breakdown Structure Organisation & Responsibilities

Work Breakdown Structures Operative Indicators

Structure Objects

Documentation

WBS Organization and Responsibilities Animation

WBS 1 Project Definition

WBS 1.1

WBS 1.1.1

WBS 1.2

WBS 1.2.1

WBS 1.1.2

Key Profit Center

Responsible Cost Center

Person Responsible

Company Code

WBS 1.2.2

Operative Indicators and Attributes ; ;

WBS 1

WBS 1.2

WBS 1.3

Partially Rel

WBS 1.2.1

Released

Partially Rel

WBS 1.4.1

WBS 1.2.2

Released

WBS 1.4

Released

WBS 1.4.2

Released

Key ‹

Planning Element ; For planning costs ; Plan/actual cost comparison

‹

Account assignment element ; For posting actual costs ; Network / Maintenance Order assignments

Released

WBS Structure Objects WBS 1 Partially Rel

WBS 1.2

WBS 1.4

Partially Rel

WBS 1.2.1 Released

‹

Project Milestone

‹

PS Text Documents

Partially Rel

WBS 1.4.1

WBS 1.2.2 Released

Key

WBS 1.4.2

Released

‹

Investment Program item

‹

Project Organization

Released

Milestones in WBS WBS 1

approval

WBS 1.2

WBS 1.2.1

WBS 1.4

WBS 1.4.1

WBS 1.2.2

WBS 1.4.2

Key ‹

Milestone Trend Analysis

‹

For Informational / Reporting Purposes

Project Documentation WBS 1

WBS 1.2

WBS 1.2.1

W

W

WBS 1.2.2

Key ‹

PS Text E.g.. Word Documents

W

WBS 1.4

WBS 1.4.1



‹



WBS 1.4.2

Long Texts

Derivation of the WBS hierarchy Automatic derivation 1 V-0691001 2

Entries

2

V-0691001.01

3

V-0691001.01.01

3

V-0691001.01.02 V-0691001.02

Goal

1 V-0691001 1 V-0691001.01 1 V-0691001.02 1 V-0691001.01.01 1 V-0691001.01.02

V-0691001

V-0691001.01

Hierarchy Key level

V-0691001.01.01

V-0691001.01.02

V-0691001.02

Project Levels ‹

Project Levels: ; Each project must have a single Level 1 WBS ; Allows for ease of reporting at a project level ; Structure below Level 1 is determined by phase and other reporting requirements

This is an example of a typical project structure

Project Creation and Maintenance methods

‹

INDIRECT ; Transfer from Appropriation Requests ; Transfer Simulation

‹

PROCEDURE ; Copy a template ; Include (used most commonly)

Templates and Work Breakdown Structures

Template

V-1111111

V-1111111.02

V-1111111.03

Operative

V-0691001

V-0691001.02

V-0691001.03

Include Template Start

Include Template

Finish

Project Builder

Selected Project Project Definition & Structure

Worklist & Templates

Contents ‹

Master Data in Project Systems: ; Work Breakdown Structures ; Networks and Activities

‹

Status Control

‹

Tools ; Table controls

‹

Project Versions

Networks ‹

A key step in project planning is determining the sequence in which the activities will be performed.

‹

This involves determining which activities are dependent on each other and which activities require additional work or must be broken down even further.

‹

In Project Systems, this planning of processes and sequencing of activities is done using networks.

‹

A network consists of a network header and a series of activities either with relationships and, optionally milestones

Activities and Networks - Functions Internal Activity: Š Internal Work Š Dates, Capacities Š Costs Milestones: Š Milestone Trend Analysis

April 7

External Activity / Service: Š Dates Š Costs Š Commitments

Material: Costs Activity:

“Network”

Š Dates Š Costs Š Commitments

Š Dates Š Costs Periodic Processing: Š Overheads Š Settlement

Mar April

Network Header and Activities

Network Header Network Header

Network

Network Activities

Project Field requirements – Network Header ‹

Network Header ; Description ; MRP Controller

Activities and Activity Elements ‹

Four Types of Activities ; Internal Processing

Internal

External

; External Processing ; Costs, services ; General Cost Activities ‹

Reference Dates from Activity ; Start or Finish

‹

Activity Elements ; Work ; External ; Costs ; Service

General Costs

Service

Relationships Logical Sequence

Time Sequence FS Relationship

SS Relationship

FF Relationship

SF Relationship

Network Graphic Details Control key

Activity Activity number Days

Specification 16.02.2000 34 04.04.2000 0

Duration

Days

FS

Mechanical Layout

18.02.2000

21.02.2000

06.04.2000

07.04.2000

34 0

Days

FS

Procurement

17.05.2000 07.07.2000

FS

Description

18.05.2000 10.07.2000

34 34

08.06.2000 28.07.2000

Earliest finish

FS

Relationship

Days

Electronic Layout 21.02.2000 24.05.2000

64 30

31.03.2000 07.07.2000

Floats

Latest finish

Work Breakdown Structures & Networks compared WBS 1

‹

WBS

WBS 1.3

WBS 1.4

WBS 1.5

; Cost Control and Reporting ; Reflects Ownership

WBS 1.3.1

WBS 1.3.2

WBS 1.5.1

WBS 1.5.2

Versus ‹

NETWORK ; Work Control 1100

; Reflects Execution 1000

5000 1200

Network

Activity Assignment to WBS WBS 1 ‹

Date Planning

‹

Cost Planning

‹

Generating Settlement rules

WBS 1.3

WBS 1.3.1

WBS 1.4

WBS 1.3.2

WBS 1.5

WBS 1.5.1

WBS 1.5.2

1100 1000

5000 1200

Network

Different ways of creating Networks ‹

DIRECT METHODS ; “Create” network directly ; Create via Project Builder

‹

INDIRECT ; Project Planning Board and Simulation ; “Create WBS with Activities”.

‹

PROCEDURE ; Create manually or copy a template

Creating a Network Header Animation

Drop here Click here

Result

Creating Activities

Result Drop here Click here

Contents ‹

Master Data in Project Systems: ; Work Breakdown Structures ; Networks and Activities

‹

Status Control

‹

Tools ; Table controls

‹

Project Versions

System Status and User Status control

CRTD

PREL

CRTD

CRTD

‹

CRTD

CRTD

CRTD

PREL

CRTD

What is Status control used for?

CRTD

‹

; To allow or forbid certain business transactions. ‹

How? ; Status are activated manually or automatically by the system.

REL

REL

REL

REL

Which elements? ; Project definition and WBS elements are affected.

‹

Why system and user status? ; User status adds detail to the system Status.

System Status’s SYSTEM STATUS The following status are set by the system/user as the project goes through Its different stages: ‹

CRTD Created (Automatic)

‹

REL Released (Manual)

‹

LKD Locked (Manual)

‹

UNLK Unlock (Manual)

‹

BUDG Project Budgeted (Automatic)

‹

AVAC Availability Control Activated (Automatic)

‹



User Status is Optional (based on Client reqt.) USER STATUS The following status are set by the user as the project goes through its different stages: ‹

10 Initial ; The appropriation request has this status when it is created (Automatic). ‹ 20 A Grp Approval (Automatic on approval)

Note : User status configuration and usage is totally based on client requirement and is optional

System Status (1) Created (CRTD) CREATED

; Use 9

Initial system status for new WBS elements

9

Allows project structuring, date and cost planning.

9

Allows Budgeting

; Prerequisites 9

The superior WBS element MUST have status Created

Released (REL) ; Use

RELEASED

9

Allows costs and revenues to be posted to the project

9

Passed onto lower level WBS elements

; Prerequisites 9

….. Cont

Created must have been set

System Status (2) Technically Complete (TECO) ; Use

TECHNICALLY COMPLETE

9

For projects completed from a technical point of view.

9

Allows costs and revenues to be posted to the project.

; Prerequisites 9

Created or Released must have been set.

Closed (CLSD) ; Use

CLOSED

9

Prevents actual postings.

9

Prevents network creation.

; Prerequisites 9

Released or Technically complete must have been set.

Deletion Flag (DLFL) ; Use

FLAGGED FOR DELETION

9

Objects are deleted logically, but not physically.

; Prerequisites 9

Allowed if all costs have been settled completely.

9

Allowed if there are no reservations or commitments.

Contents ‹

Master Data in Project Systems: ; Work Breakdown Structures ; Networks and Activities

‹

Status Control

‹

Tools ; Table controls

‹

Project Versions

User Specific Table Control Settings

1

2 3

Click Here

1

Column Width

2

Move around

3

User Settings

Contents ‹

Master Data in Project Systems: ; Work Breakdown Structures ; Networks and Activities

‹

Status Control

‹

Tools ; Table controls

‹

Project Versions

Versions in Project Systems Project Version

Versions



“Project Snapshot” Can’t be changed!!! CO Plan Version

Simulation Version

Can be changed!!!

Simulation January

February

March

ve i t ra e Op

Project V-0691001 Version 001

Project V-0691001 Version 002

April

What are simulation versions used for?

Update Operative Project

Comparisons

SIM 001

Create

SIM 002

SIM 003

Planning & Budgeting

Business Scenario ‹

Cost planning is carried out during the planning phases and is reviewed through reports during subsequent review.

Planning versus Budgeting Planning

Budgeting

‹ Cost-oriented (cost elements, plan versions, period values) ,

‹ Funds-oriented (original, supplements, returns, annual values)

‹ Easily changed; line items created if desired

‹ Binding values; line items for each change

‹ No availability check

‹ Availability check: Warning at 95% Error message at 105%

Î"FUNDS REQUESTED"

Î"APPROVED FUNDS"

Aspects of Planning Project Structures:

Costs:

Dates:

Resources:

Contents ‹

WBS Cost Element Planning.

‹

Planned Costs in Networks.

‹

Budgeting.

‹

Commitment Management & Availability Control.

Cost Planning in Projects

WBS 1

WBS 1.1

WBS 1.2

WBS 1.3

Cost Element Planning Activity Activity // Network Network Costing Costing

WBS Cost Element Planning

Contents ‹

WBS Cost Element Planning.

‹

Planned Costs in Networks.

‹

Budgeting.

‹

Commitment Management & Availability Control.

Network Activities Internal Processing: Š Work / Services performed inhouse

External Processing: Š Purchasing of work / services

Costs Activity:

Services:

Š Planning of additional primary costs

Š Purchasing of services with service specifications

Internal Processing Work: 500hrs

Output provided to complete activities

1200

Work Center

Organizational unit Where an activity is carried out or work output is provided.

Scheduling Data

Responsible Persons

Cost Center

Cost Center Data

External Processing Work Performed by a third party (Vendor) 1300

PR Commitments Description Material Group Purchasing Group

Invoice Verfication

Purchase Requisition Bid Invitation

Actual Costs Good Receipt / Service Receipt

Quotation Entry

Quantity & Unit Price per Unit

Vendor Purchase Order

1000

Entry of Services performed PO Processing

Vendor Selection

PO Committments

Contents ‹

WBS Cost Element Planning.

‹

Planned Costs in Networks.

‹

Budgeting.

‹

Commitment Management & Availability Control.

Cost Planning and Budgeting

Budget applied for

Approved budget 2001 2000

Cost Planning Annual plan value

Bottom-up extrapolation

Cost Budgeting

Total 1 EE-1399 2 EE-13991399-1 3 EE-13991399-1-1 3 EE-13991399-1-2 2 EE-13991399-2 . . .

O R I G I N A L

P L N D T O T A L

D I S T R B T

... ... ... ...

Budget

Top-down distribution

Budgeting Overview

‹

Budget Values

Availability Control:

Budget Updates

; Against Current

Budget ; Against Budget Releases

Budget Carryforward

2001

2002

Release Budget

Budget Values Years 2002 2001 Overall

Structure

1 Concept 2 Feasability 3 Plan 4 Design . . . . .

Updates O R I G B U D G E T

R E T U R N S

S U P P L E M E N T S

T R A N S F E R S

NOTE: Current Budget = OB + Suppl – Ret +/- Transfers

Budget Updates Budget return

Budget supplement To project

In

From project

ct e oj r p

In

ct e oj r p

Budget transfer From project +- 100

-100 -100

+100 ct e j o r In p

Budget Management WBS: V-06910001 Original Budget

Current Budget

Overall

5,000

7,000

2002 2003

2,000 3,000

3,000 4,000

Budget Line Items Order

400010 Trade Fair

Document Year

Activity

Amount

030000001 2002

Original

2,000

030000200 2002

Supplement

3,000

030000306 2002

Return

(2,000)

Total

2002

3,000

NOTE: CB = OB + Suppl – Ret +/- Transfers

Budget Update Simulation Investment Program II M M

O.B C.B

Investment Position 1 O.B 100

O.B C.B

50

WBS 1.2 O.B 120 C.B 170

80

WBS 1.1.2 O.B

30

WBS 1.2.1 O.B C.B

ORIGINAL BUDGET ; Set IM Original Budget ; Distribute Original Budget ; Allocate Original Budget BUDGET SUPPLEMENT ; Supplement IM EUR 50 ; Distribute Supplement to PS ; Allocate Budget Supplement BUDGET TRANSFER ; Transfer EUR 30 from WBS 1.2.2 to WBS 1.2.1

200 250

WBS 1.1

O.B

Assignment

WBS 1

PS PS

WBS 1.1.1

Auto Link level 1 Capital Project to lowest IM position

Investment Position 2 O.B 200 C.B 250

Project Definition

O.B

‹

300 350

20 20 50

WBS 1.2.2 O.B 100 150 C.B 150 120

Budget Updates Report C.B O.B Supp Trn Ret 250 WBS 1 200 170 WBS 1.2 120 50 WBS 1.2.1 20 120 WBS 1.2.2 150 100

200 120 20 100

50 50 50

30 -30

Releasing the Budget Budget 10m

Budget 10m

EUR

EUR

EUR

Add 1 m

Add 5 m

EUR EUR

EUR EUR

EUR

Release EUR 2 m

Release EUR 3 m

Release EUR 8.0 m

Contents ‹

WBS Cost Element Planning.

‹

Planned Costs in Networks.

‹

Budgeting.

‹

Commitment Management & Availability Control.

Commitment Management (1) PS PS

2000

PS PS

3000

2000

1000

6000 4000

3000

1000

6000

5000

4000

5000

Materials Materials Materials

Services Materials Materials

Materials

Services Purchase Req

Purchase Order

MM MM

WBS WBS Element Element V-0691001.01 V-0691001.01 C/Elem 4000000

Committed 6000

Actual 5000

Assigned 11000

Commitment Management (2) MM MM

CO CO

Purchase Requisition

WBS WBS Element Element V-0691001.01 V-0691001.01 C/Elem Purchase Order

Committed

4000000

6000

Actual 5000

Assigned 11000

WBS WBS Element Element V-0691001.01 V-0691001.01 C/Elem Goods Receipt

4000000

Committed 0

Actual 11000

Assigned 11000

Availability Control No more Funds available!!

WBS 1.1.1

Business Events

Budget Comm Actual Total 2002 2003

50 30 20

10 5 5

40 25 15

Invoice

Availability check

Purchase order Purchase Requisition

Availability Control Simulation Budget

200 000

Budget 120 000 Actual

Budget

80 000

80 000

Assigned 100 75 000 Assigned

Commitments

Activities

25 000

75 000

At 105% budget completion, A warning message is Posted by the system and mail Sent to the responsible person.

At 95% budget completion, A warning message is Posted by the system.

Actual costs 80,000

Commitments (purchase order, purchase requisition, funds reservation)

Networks / Orders

Items within budget are Successfully posted.

75,000

25,000

CO CO

MM MM

PS PS

PM PM

Materials & Services

Business Scenario ‹

During Project Execution, both materials and services are procured. Materials are managed in plant stock.

‹

Project managers are interested in: ; Stock used on your project. (Stock controlling)

Integration with MM Definition 2000

3000

Material required for performing an activity or for manufacturing

1000

6000 4000

a product.

5000 Item Category

“Plant Stock”

Materials Materials Materials

“Non Stock”

Stock Item “L”

Non-Stock Item “N”

Reservation

Purchase Req.

MM MM

Procurement of Stock Items 2000

3000

1000

Definition 6000

Material components procured to stock. Reservations are

4000

5000

generated for stock items.

Material Reservation

Materials Item Materials Materials Category “L”

Material Withdrawal

GR Processing

MRP Run

Item Category “L”

PO Processing

Convert Planned PR

Planned PR

Procurement of Non Stock Items 2000

3000 Definition

1000

6000

Material procured directly by means of an activity

4000

5000 Actual Costs

Materials Item Materials Materials Category “N”

PR Commitments Invoice Verification

Goods receipt

Purchase Requisition Request for quotation

Item Category “N”

PO Monitoring PO Processing

Quotation Entry

Vendor Selection

PO Committments

Account Assignment Category

Account Assignment Category “L” Non Stock

Project Structure Work Breakdown Structure

WBS 1.1

WBS 1.1.1

WBS 1.1.1

WBS Elements

Network

Network Activity Materials

Assigning material components to activities initiates external procurement.

Material Component

Procurement Steps WBS 1.1

WBS 1.1.1

WBS 1.1.1 10

Goods issue T-20600

to Network Activity (Consumption) Goods receipt For Purchase order

Vendor

Purchase Components

Procurement Steps – Purchase Order WBS 1.1

WBS 1.1.1

WBS 1.1.1 10

Goods issue to Network

T-20600

Activity (Consumption) Goods receipt For Purchase order

Vendor

Purchase EUR

Components

Purchasing Components

Purchase order commitments

Procurement Steps – Goods Receipt WBS 1.1

WBS 1.1.1

WBS 1.1.1 10

Goods issue to Network

T-20600

Activity (Consumption) Goods receipt EUR

For Purchase order

Vendor

Purchase Components

Purchasing Components

The goods receipt reduces the commitment and posts it to actual

Procurement Steps – Goods Issue WBS 1.1

WBS 1.1.1

WBS 1.1.1 10

Goods issue T-20600

EUR

to Network Activity (Consumption) Goods receipt For Purchase order

Vendor

Purchase Components

Scheduling

Business Scenario ‹

You have created a project structure, you are now required to see if your project can be completed on time. Schedule your project to find the answer.

Dates Check Dates ‹

Inherit

Sets of Dates WBS

; Basic Dates.

8

; Forecast Dates

WBS / Networks

; Actual Dates

8

Extrapolate

Planning form

+

Ÿ

Scheduling

 

Scheduled Start to Finish

Planning different calendars

Shift

+

Project Dates ‹

Project Definition ; BASIC DATES

‹

Project Definitions

WBS Elements ; BASIC DATES ; FORECAST DATES ; Scheduled Dates ; Actual Dates

‹

Network Header ; BASIC DATES ; Scheduled Dates ; Actual Dates

‹

Network Header

Network Activity ; CONSTRAINTS ; Earliest scheduled dates ; Latest scheduled dates ; Actual Dates

‹

Activity Element ; Earliest scheduled dates ; Latest scheduled dates ; Actual Dates

BOLD – Manual Planning Dates

Italics – Automatic Dates

WBS / Overall Network Scheduling

Network scheduling

Scheduling of the overall network

WBS scheduling

Bottom-Up planning Project planning board WBS

P

P P1

P2

20 10 30

Network 1

P1

80

50

P2

10

60 40

Extrapolate Dates Automatically

70

Network 2

20 30 40 50 60 70 80 Basic dates in project definition

Example of scheduling 6D 8 8

20 3 3 10 1 1

2D 2 2

2D 4 5

30 3 4

40 5 6

50 9 9

3D 7 8

10 20 30 40 50 1

2

3

4

5

6

7

8

9

10 11 12 13

Days

3D 11 11

Time Constraints

1

Start

2

Start

Before

Before

After

After

For activities, time constraints set 1. An exact start / finish 2. The earliest value limit 3. The latest value limit

(

= must)

(

= not before)

(

= not after)

Finish

Actual Dates

Actual WBS Dates Work Breakdown Structure

Apr 7

Activity Confirmation Network, Network Activity

Apr 7

Actual Dates of Activities

30

30 40

10

Time

AS = Actual start PF = Provisional finish

20

Partial confirmation 20 (shift order)

Final confirmation 10

10

20

40

10

20

Scheduled dates

10

40

10

20

30

10

20

Time

20

AS

Time

PF

Execution

Contents ‹

CN25 Confirmations

Network Confirmation (CN25) -1

Network Confirmation (CN25)-2

Period End Closing

Period End Closing ‹

Month End Processing.

‹

Year End Processing.

Settlement Debit and Credit MM MM

; Material Withdrawal ; Goods Receipt

FI FI

CO CO ; Activity allocation

; Financial Journal Adjustments

; Transfers

; Recurring entries

Settlement Rules: ; Receivers ; Distribution Rules ; Settlement

FI FI

AM AM

CO CO

PS PS

Deriving Settlement Rules Settlement Strategies

2 Manually for Assets and Cost Centers

1

Proposed by default rule To assigned WBS

Periodic Settlement Processing 1 Periodic Settlement to AUC

2

Final Settlement to Fixed Assets

Final Asset Asset Under Construction

Period End Closing ‹

Month End Processing.

‹

Year End Processing.

Project Closing Case Flow Diagram Final Settlement from AUC to Assets

Reduce released budget

Return Original Budget To level 1 WBS

Return Budget To IM

Delete unused WBS Elements

Close project definition

Clear Project Stock

Update all WBS Elements to TECO

Perform Budget Return check

Information System

Report: Budget / Actual / Variance

Report: Budget / Actual / Commitment

Report: Actual / Commitment / Plan