Substation Project Schedule of one substation and other switching station....
Description
Project Schedule for ID
Task Name
Total schedule Substation-1
1 2
Duration
Start
Finish
433 days
Sat 6/7/14
428 days
Sat 6/7/14
Sat 8/8/15
12 days
Sat 6/7/14
Wed 6/18/14 Wed 7/16/14
Topographical Survey and Report Preparation
4
Soil Investigation and Report Preparation
40 days
Sat 6/7/14
5
Drawing and Design Finalization
72 days
Thu 7/17/14
Fri 9/26/14
72 days
Thu 7/17/14
Fri 9/26/14
18 days
Thu 7/17/14
Sun 8/3/14
Civl Design
7
Substation General & Switchyard Layout
8
Cable Trench/Tray
9 days
Thu 7/17/14
Fri 7/25/14
9
Quarter Buildings
30 days
Fri 7/18/14
Sat 8/16/14 Sun 8/10/14
10
Boundary wall
10 days
Fri 8/1/14
11
Access Road/Switchyard Road
15 days
Fri 8/1/14
Fri 8/15/14
12
Control Building
30 days
Thu 8/14/14
Fri 9/12/14
13
Guard House
14 days
Sat 8/30/14
Fri 9/12/14
14
Supporting Structures
29 days
Thu 8/21/14
Thu 9/18/14
15 16
Switchyard Foundation Electrical Design
18 days
Tue 9/9/14
Fri 9/26/14
47 days
Mon 8/4/14
Fri 9/19/14
17
Substation Earthing
12 days
Mon 8/4/14
Fri 8/15/14
18
Substation Shielding
10 days
Wed 8/20/14
Fri 8/29/14
19
Illumination System Design
8 days
Fri 9/12/14
Fri 9/19/14
20
Outdoor Lighting
3 days
Fri 8/22/14
Sun 8/24/14
21 22 23 24
Cable Schedule Civil Works Quarter Building (Single Storied) Upto Plinth Level
25
Excavation of Foundation
26
Solling, PCC for footing
27
Reinforcement and form work for Mat and Column Concreting of Pad
28 29 30 31 32 33 34
Reinforcement and form work for Tie Beam-1 Concreting of Tie Beam -1 Reinforcement and Form work for Tie Beam -2 Concreting of Tie Beam-2 Above Plinth Level Reinforcement and Formwork of Columns
43 days
Mon 8/4/14
Mon 9/15/14
212 days
Sun 8/17/14
Mon 3/16/15
158 days
Sun 8/17/14
Wed 1/21/15
50 days
Sun 8/17/14
Sun 10/5/14
5 days
Sun 8/17/14
Thu 8/21/14
12 days
Fri 8/22/14
Tue 9/2/14
8 days
Wed 9/3/14
Wed 9/10/14
3 days
Thu 9/11/14
Sat 9/13/14
8 days
Sun 9/14/14
Sun 9/21/14
3 days
Mon 9/22/14
Wed 9/24/14
8 days
Thu 9/25/14
Thu 10/2/14
3 days
Fri 10/3/14
Sun 10/5/14
18 days
Mon 10/6/14
Thu 10/23/14
8 days
Mon 10/6/14
Mon 10/13/14
35
Concreting of Columns
5 days
Tue 10/14/14
Sat 10/18/14
36
Flooring of Control Building
5 days
Sun 10/19/14
Thu 10/23/14 Wed 11/12/14
37
13 days
Fri 10/31/14
38
Formwork of Slab
5 days
Fri 10/31/14
Tue 11/4/14
39
Reinforcement of Beam and Slab
6 days
Wed 11/5/14
Mon 11/10/14
40 41
Slab
Concreting of Slab Others
2 days
Tue 11/11/14
Wed 11/12/14
70 days
Thu 11/13/14
Wed 1/21/15
10 days
Thu 11/13/14
Sat 11/22/14
9 days
Sun 11/23/14
Mon 12/1/14
Fri 12/5/14
Thu 12/18/14 Sun 12/28/14
42
Brick Masonary Works
43
Illumination Work
44
Heating and Ventilation
14 days
45
Fire Fighting System
15 days
Sun 12/14/14
46
Plaster works
8 days
Mon 12/29/14
Mon 1/5/15
47
Air conditioning works
6 days
Sat 12/20/14
Thu 12/25/14
48
Door and Windows work
49
Painting and Glazing works
7 days
Wed 1/7/15
Tue 1/13/15
19 days
Sat 1/3/15
Wed 1/21/15
50
Water supply and sanitation
10 days
Mon 12/29/14
Wed 1/7/15
51
Quarter Building (Double Storied)
184 days
Sun 8/17/14
Mon 2/16/15
50 days
Sun 8/17/14
Sun 10/5/14
5 days
Sun 8/17/14
Thu 8/21/14
12 days
Fri 8/22/14
Tue 9/2/14
8 days
Wed 9/3/14
Wed 9/10/14
52
Upto Plinth Level
53
Excavation of Foundation
54
Solling, PCC for footing
55
Reinforcement and form work for Mat and Column Concreting of Pad
56 57 58 59 60 61 62
Reinforcement and form work for Tie Beam-1 Concreting of Tie Beam -1 Reinforcement and Form work for Tie Beam -2 Concreting of Tie Beam-2 Above Plinth Level Reinforcement and Formwork of Columns
3 days
Thu 9/11/14
Sat 9/13/14
8 days
Sun 9/14/14
Sun 9/21/14
3 days
Mon 9/22/14
Wed 9/24/14
8 days
Thu 9/25/14
Thu 10/2/14
3 days
Fri 10/3/14
Sun 10/5/14
18 days
Mon 10/6/14
Thu 10/23/14
8 days
Mon 10/6/14
Mon 10/13/14
63
Concreting of Columns
5 days
Tue 10/14/14
Sat 10/18/14
64
Flooring of Control Building
5 days
Sun 10/19/14
Thu 10/23/14 Wed 11/12/14
65
13 days
Fri 10/31/14
66
Formwork of Slab
5 days
Fri 10/31/14
Tue 11/4/14
67
Reinforcement of Beam and Slab
6 days
Wed 11/5/14
Mon 11/10/14 Wed 11/12/14
68 69 70 71 72
Slab1
Concreting of Slab Above Ground Floor Reinforcement and Formwork of Columns Concreting of Columns Slab2
2 days
Tue 11/11/14
13 days
Wed 11/19/14
Mon 12/1/14
8 days
Wed 11/19/14
Wed 11/26/14
5 days
Thu 11/27/14
Mon 12/1/14
13 days
Tue 12/2/14
Sun 12/14/14
73
Formwork of Slab
5 days
Tue 12/2/14
Sat 12/6/14
74
Reinforcement of Beam and Slab
6 days
Sun 12/7/14
Fri 12/12/14 Sun 12/14/14
75 76
Concreting of Slab Others
2 days
Sat 12/13/14
69 days
Wed 12/10/14
Mon 2/16/15
77
Brick Masonary Works
15 days
Wed 12/10/14
Thu 12/25/14
78
Illumination Work
13 days
Fri 12/26/14
Thu 1/8/15
Project: Date: Thu 3/20/14
Task
Split
2015 June July August September October November December January February March April May June July Au 6/1 6/8 6/15 6/22 6/29 7/6 7/13 7/20 7/27 8/3 8/10 8/17 8/24 8/31 9/7 9/14 9/21 9/28 10/5 0/1 0/1 0/2 11/2 11/9 1/1 1/2 1/3 12/7 2/1 2/2 2/2 1/4 1/11 1/18 1/25 2/1 2/8 2/15 2/22 3/1 3/8 3/15 3/22 3/29 4/5 4/12 4/19 4/26 5/3 5/10 5/17 5/24 5/31 6/7 6/14 6/21 6/28 7/5 7/12 7/19 7/26 8/2 8/9
Thu 8/13/15
3
6
Substation/Switching Station
2014
Progress
Milestone
Summary
Project Summary Page 1
External Tasks
External Milestone
Deadline
Project Schedule for LAOS Substation/Switching Station ID
Task Name
Duration
Start
Finish
79
Heating and Ventilation
18 days
Sat 12/20/14
80
Fire Fighting System
19 days
Mon 12/29/14
Sat 1/17/15
81
Plaster works
13 days
Tue 1/6/15
Sun 1/18/15
82
Air conditioning works
83
Door and Windows work
Wed 1/7/15
8 days
Fri 12/26/14
Fri 1/2/15
10 days
Wed 1/14/15
Fri 1/23/15 Mon 2/16/15
84
Painting and Glazing works
26 days
Thu 1/22/15
85
Water supply and sanitation
13 days
Thu 1/8/15
Tue 1/20/15
185 days
Sat 9/13/14
Mon 3/16/15
56 days
Sat 9/13/14
Fri 11/7/14
5 days
Sat 9/13/14
Wed 9/17/14
86 87 88
Control Building Upto Plinth Level Excavation of Foundation
89
Solling, PCC for footing
90
Reinforcement and form work for Mat and Column Concreting of Pad
91 92 93 94 95 96
Reinforcement and form work for Tie Beam-1 Concreting of Tie Beam -1 Reinforcement and Form work for Tie Beam -2 Concreting of Tie Beam-2 Above Plinth Level
18 days
Thu 9/18/14
Sun 10/5/14
8 days
Mon 10/6/14
Mon 10/13/14
3 days
Tue 10/14/14
Thu 10/16/14
8 days
Fri 10/17/14
Fri 10/24/14
3 days
Sat 10/25/14
Mon 10/27/14
8 days
Tue 10/28/14
Tue 11/4/14
3 days
Wed 11/5/14
Fri 11/7/14
20 days
Sat 11/8/14
Thu 11/27/14
97
Reinforcement and Formwork of Columns
8 days
Sat 11/8/14
Sat 11/15/14
98
Concreting of Columns
5 days
Sun 11/16/14
Thu 11/20/14
99 100
Flooring of Control Building Slab
7 days
Fri 11/21/14
Thu 11/27/14
22 days
Fri 11/28/14
Fri 12/19/14
101
Formwork of Slab
10 days
Fri 11/28/14
Sun 12/7/14
102
Reinforcement of Beam and Slab
10 days
Mon 12/8/14
Wed 12/17/14
103 104
Concreting of Slab Indoor Cable Trench
2 days
Thu 12/18/14
Fri 12/19/14
7 days
Wed 12/31/14
Tue 1/6/15
105
Reinforcement for Trench
3 days
Wed 12/31/14
Fri 1/2/15
106
Formwork for Trench
2 days
Sat 1/3/15
Sun 1/4/15
107 108
Concreting of Trench Others
2 days
Mon 1/5/15
Tue 1/6/15
76 days
Wed 12/31/14
Mon 3/16/15 Thu 1/15/15
109
Brick Masonary Works
14 days
Wed 12/31/14
110
Illumination Work
20 days
Fri 1/16/15
Wed 2/4/15
111
Heating and Ventilation
25 days
Mon 1/5/15
Thu 1/29/15
112
Fire Fighting System
22 days
Tue 1/6/15
Tue 1/27/15
113
Plaster works
15 days
Thu 2/5/15
Thu 2/19/15
114
Tile Works
30 days
Wed 12/31/14
Thu 1/29/15
115
Door and Windows work
15 days
Wed 1/14/15
Wed 1/28/15
116
False ceiling and Air conditioning works
20 days
Fri 2/20/15
Wed 3/11/15
117
Painting and Glazing works
25 days
Fri 2/20/15
Mon 3/16/15
118
Water supply and sanitation
15 days
Wed 2/25/15
Wed 3/11/15
118 days
Sat 9/13/14
Thu 1/8/15
23 days
Sat 9/13/14
Sun 10/5/14
119 120
Guard House Upto Plinth Level
121
Excavation of Foundation
2 days
Sat 9/13/14
Sun 9/14/14
122
Solling, PCC for footing
4 days
Mon 9/15/14
Thu 9/18/14
123
Reinforcement and form work for Mat and Column Concreting of Pad
5 days
Fri 9/19/14
Tue 9/23/14
124 125 126 127 128 129
2 days
Wed 9/24/14
Thu 9/25/14
Reinforcement and form work for Tie Beam-1 Concreting of Tie Beam -1
4 days
Fri 9/26/14
Mon 9/29/14
1 day
Tue 9/30/14
Tue 9/30/14
Reinforcement and Form work for Tie Beam -2 Concreting of Tie Beam-2
4 days
Wed 10/1/14
Sat 10/4/14
Above Plinth Level
1 day
Sun 10/5/14
Sun 10/5/14
18 days
Mon 10/6/14
Thu 10/23/14
Mon 10/6/14
Wed 10/8/14
130
Reinforcement and Formwork of Columns
3 days
131
Concreting of Columns
3 days
Thu 10/9/14
Sat 10/11/14
132
Flooring
2 days
Wed 10/22/14
Thu 10/23/14 Fri 11/14/14
133
10 days
Wed 11/5/14
134
Formwork of Slab
4 days
Wed 11/5/14
Sat 11/8/14
135
Reinforcement of Beam and Slab
5 days
Sun 11/9/14
Thu 11/13/14 Fri 11/14/14
136 137
Slab
Concreting of Slab Others
1 day
Fri 11/14/14
50 days
Thu 11/20/14
Thu 1/8/15
Thu 11/20/14
Mon 11/24/14
138
Brick Masonary Works
5 days
139
Illumination Work
3 days
Tue 11/25/14
Thu 11/27/14
140
Fire Fighting System
5 days
Sun 12/14/14
Thu 12/18/14
141
Heating and Ventilation
4 days
Thu 12/18/14
Sun 12/21/14
142
Plaster works
3 days
Fri 12/19/14
Sun 12/21/14
143
Tile Works
6 days
Mon 12/22/14
Sat 12/27/14
144
Door and Windows work
3 days
Tue 11/25/14
Thu 11/27/14
145
Air conditioning works
4 days
Fri 12/26/14
Mon 12/29/14
146
Painting and Glazing works
6 days
Tue 12/30/14
Sun 1/4/15
147
Water supply and sanitation
4 days
Mon 1/5/15
Thu 1/8/15
88 days
Sat 9/27/14
Tue 12/23/14 Wed 10/29/14
148 149
Switchyard Foundation Works
33 days
Sat 9/27/14
150
Line Bay Excavation
3 days
Sat 9/27/14
Mon 10/13/14
151
Soling PCC for the footing
4 days
Sun 9/28/14
Wed 10/15/14
152
Reinforcement work for mat
8 days
Mon 9/29/14
Sat 10/18/14
153
Concreting of pad
3 days
Thu 10/2/14
Tue 10/21/14
154
Reinforcement work for Column
8 days
Fri 10/3/14
Sat 10/25/14
155
Formwork for column
5 days
Mon 10/6/14
Sun 10/26/14
156
Fixing of anchor bolts
5 days
Wed 10/8/14
Tue 10/28/14
Project: Date: Thu 3/20/14
Task
Split
2014
2015 June July August September October November December January February March April May June July Au 6/1 6/8 6/15 6/22 6/29 7/6 7/13 7/20 7/27 8/3 8/10 8/17 8/24 8/31 9/7 9/14 9/21 9/28 10/5 0/1 0/1 0/2 11/2 11/9 1/1 1/2 1/3 12/7 2/1 2/2 2/2 1/4 1/11 1/18 1/25 2/1 2/8 2/15 2/22 3/1 3/8 3/15 3/22 3/29 4/5 4/12 4/19 4/26 5/3 5/10 5/17 5/24 5/31 6/7 6/14 6/21 6/28 7/5 7/12 7/19 7/26 8/2 8/9
Progress
Milestone
Summary
Project Summary Page 2
External Tasks
External Milestone
Deadline
Project Schedule for LAOS Substation/Switching Station ID
Task Name
Duration
157
Concreting of Column
158
Transformer Bay
Start
Finish
4 days
Fri 10/10/14
36 days
Thu 10/30/14
Wed 10/29/14 Thu 12/4/14
5 days
Thu 10/30/14
Mon 11/17/14 Mon 11/17/14
159
Excavation
160
Soling PCC for the footing
161
Reinforcement work for mat
162
Concreting of pad
163
Reinforcement work for Column
11 days
Fri 11/7/14
Tue 12/2/14
164
Formwork for column
8 days
Mon 11/10/14
Wed 12/3/14
165
Fixing of anchor bolts and Transformer Leaque Concreting of Column
7 days
Tue 11/11/14
Wed 12/3/14
166
6 days
Thu 11/13/14
Thu 12/4/14
167
Structures for overhead strung Busbars
19 days
Fri 12/5/14
Tue 12/23/14
4 days
Fri 10/31/14
11 days
Sat 11/1/14
Tue 11/25/14
4 days
Wed 11/5/14
Tue 11/25/14
168
Excavation
1 day
Fri 12/5/14
Fri 12/5/14
169
Soling PCC for the footing
2 days
Sat 12/6/14
Sun 12/7/14
170
Reinforcement work for mat
3 days
Mon 12/8/14
Wed 12/10/14
171
Concreting of pad
2 days
Thu 12/11/14
Fri 12/12/14
172
Reinforcement work for Column
3 days
Sat 12/13/14
Mon 12/15/14
173
Formwork for column
2 days
Tue 12/16/14
Wed 12/17/14
174
Fixing of anchor bolts
3 days
Thu 12/18/14
Sat 12/20/14
175
Concreting of Column
3 days
Sun 12/21/14
Tue 12/23/14
176
27 days
Sun 12/21/14
Fri 1/16/15
177
Excavation
3 days
Sun 12/21/14
Tue 12/23/14
178
Reinforcement work
5 days
Wed 12/24/14
Sun 12/28/14
179
Formwork
4 days
Mon 12/29/14
Thu 1/1/15
180
Concreting
2 days
Fri 1/2/15
Sat 1/3/15
181
Installation of Cable Tray
13 days
Sun 1/4/15
Fri 1/16/15
182 183
Cable Trench and Tray
Acess Road and Switchyard Road Earthing
15 days
Sat 1/17/15
Sat 1/31/15
19 days
Sat 9/27/14
Wed 10/15/14 Thu 10/2/14
184
Excavation if required
6 days
Sat 9/27/14
185
Chemical Treatment
2 days
Fri 10/3/14
Sat 10/4/14
186
Laying of Copper Strip
5 days
Sun 10/5/14
Thu 10/9/14
Installation of Copper Electrode
2 days
187
Fri 10/10/14
Sat 10/11/14
4 days
Sun 10/12/14
Wed 10/15/14
189
Backfilling/filling with red clay and Bentonite powder Steel Structural works
42 days
Thu 1/1/15
Wed 2/11/15
190
Erection of Equipment Supporting Structure
42 days
Thu 1/1/15
Wed 2/11/15
191
Erection of Gantries
17 days
Sun 1/18/15
Tue 2/3/15
61 days
Tue 1/20/15
Sat 3/21/15
188
192
Installation
193
Outdoor Equipment
60 days
Tue 1/20/15
Fri 3/20/15
194
Transformer
12 days
Tue 1/20/15
Sat 1/31/15
195
Circuit Breaker
196
Disconnecting Switches
7 days
Thu 2/12/15
Wed 2/18/15
12 days
Thu 2/19/15
197
Mon 3/2/15
Capacitor Voltage Transformer
6 days
Tue 3/3/15
Sun 3/8/15
198
Current Transformer
4 days
Mon 3/9/15
Thu 3/12/15
199
Surge Arrester
1 day
Fri 3/13/15
Fri 3/13/15
200
Stringing of Conductor for Bus-Bar
1 day
Sat 3/14/15
Sat 3/14/15
201
Stringing of Conductors between Gantries
1 day
Sun 3/15/15
Sun 3/15/15
202
1 day
Mon 3/16/15
Mon 3/16/15
203
Tapping and connection of individual equipment Stringing of Earth wire for Shielding Protection
2 days
Tue 3/17/15
Wed 3/18/15
204
Auxillary Transformer
2 days
Thu 3/19/15
Fri 3/20/15
4 days
Wed 3/18/15
Sat 3/21/15 Sat 4/25/15
205 210
Indoor Equipment
35 days
Sun 3/22/15
211
Control and LV Power Cables
20 days
Sun 3/22/15
Fri 4/10/15
212
XLPE MV Power Cables
15 days
Sat 4/11/15
Sat 4/25/15
92 days
Sun 4/26/15
Sun 7/26/15
15 days
Sun 4/26/15
Sun 5/10/15
213
Cable Laying
Wiring
214
Transformer
215
Tap changer Panel
5 days
Mon 5/11/15
Fri 5/15/15
216
Current Transformer
4 days
Sat 5/16/15
Tue 5/19/15
217
Capacitive Voltage Transformer
7 days
Wed 5/20/15
Tue 5/26/15
218
Disconnecting Swithches
12 days
Wed 5/27/15
Sun 6/7/15
219
AC/DC Distribution/Marshalling Boxes
10 days
Mon 6/8/15
Wed 6/17/15
220
Control and Relay Panels
18 days
Thu 6/18/15
Sun 7/5/15
221
22kV Switchgear
21 days
Mon 7/6/15
Sun 7/26/15
222
13 days
Mon 7/27/15
Sat 8/8/15
223
Testing and Commissioning Pretesting
4 days
Mon 7/27/15
Thu 7/30/15
224
Testing in presence of employer authorities
6 days
Fri 7/31/15
Wed 8/5/15
225
Commissioning
3 days
Thu 8/6/15
Sat 8/8/15
420 days
Fri 6/20/14
Thu 8/13/15
substation 2
226 227
Topographical Survey and Report Preparation
12 days
Fri 6/20/14
Tue 7/1/14
228
Soil Investigation and Report Preparation
40 days
Fri 6/20/14
Tue 7/29/14
229
Drawing and Design Finalization
230
Civl Design
97 days
Sun 7/27/14
Fri 10/31/14
97 days
Sun 7/27/14
Fri 10/31/14 Wed 7/30/14
231
Cable Trench/Tray
4 days
Sun 7/27/14
232
Supporting Structures
14 days
Sat 10/18/14
Fri 10/31/14
233
Switchyard Foundation
10 days
Sat 9/27/14
Mon 10/6/14 Sun 9/21/14
234
37 days
Sat 8/16/14
235
Substation Earthing
7 days
Sat 8/16/14
Fri 8/22/14
236
Substation Shielding
5 days
Sat 8/30/14
Wed 9/3/14
237
Illumination System Design
3 days
Fri 9/19/14
Sun 9/21/14
238
Outdoor Lighting
1 day
Mon 8/25/14
Mon 8/25/14
18 days
Mon 8/25/14
Thu 9/11/14
91 days
Tue 10/7/14
Mon 1/5/15
239 240
Electrical Design
Cable Schedule Civil Works
Project: Laos Project Schedule Date: Thu 3/20/14
Task
Split
2014
2015 June July August September October November December January February March April May June July Au 6/1 6/8 6/15 6/22 6/29 7/6 7/13 7/20 7/27 8/3 8/10 8/17 8/24 8/31 9/7 9/14 9/21 9/28 10/5 0/1 0/1 0/2 11/2 11/9 1/1 1/2 1/3 12/7 2/1 2/2 2/2 1/4 1/11 1/18 1/25 2/1 2/8 2/15 2/22 3/1 3/8 3/15 3/22 3/29 4/5 4/12 4/19 4/26 5/3 5/10 5/17 5/24 5/31 6/7 6/14 6/21 6/28 7/5 7/12 7/19 7/26 8/2 8/9
Progress
Milestone
Summary
Project Summary Page 3
External Tasks
External Milestone
Deadline
Project Schedule for LAOS Substation/Switching Station ID
Task Name
241
Duration Switchyard Foundation Works
242
Line Bay
Start
Finish
43 days
Tue 10/7/14
Tue 11/18/14
24 days
Tue 10/7/14
Thu 10/30/14 Tue 10/7/14
243
Excavation
1 day
Tue 10/7/14
244
Soling PCC for the footing
2 days
Wed 10/8/14
Thu 10/9/14
245
Reinforcement work for mat
5 days
Fri 10/10/14
Tue 10/14/14
246
Concreting of pad
2 days
Wed 10/15/14
Thu 10/16/14
247
Reinforcement work for Column
5 days
Fri 10/17/14
Tue 10/21/14
248
Formwork for column
4 days
Wed 10/22/14
Sat 10/25/14
249
Fixing of anchor bolts
3 days
Sun 10/26/14
Tue 10/28/14
250
Concreting of Column
251
Structures for Busbars
2 days
Wed 10/29/14
Thu 10/30/14
19 days
Fri 10/31/14
Tue 11/18/14
252
Excavation
1 day
Fri 10/31/14
Fri 10/31/14
253
Soling PCC for the footing
2 days
Sat 11/1/14
Sun 11/2/14
254
Reinforcement work for mat
3 days
Mon 11/3/14
Wed 11/5/14
255
Concreting of pad
2 days
Thu 11/6/14
Fri 11/7/14
256
Reinforcement work for Column
3 days
Sat 11/8/14
Mon 11/10/14
257
Formwork for column
2 days
Tue 11/11/14
Wed 11/12/14
258
Fixing of anchor bolts
3 days
Thu 11/13/14
Sat 11/15/14
259
Concreting of Column
3 days
Sun 11/16/14
Tue 11/18/14
260
16 days
Sun 12/21/14
Mon 1/5/15
261
Cable Trench and Tray Excavation
2 days
Sun 12/21/14
Mon 12/22/14
262
Reinforcement work
3 days
Tue 12/23/14
Thu 12/25/14
263
Formwork
3 days
Fri 12/26/14
Sun 12/28/14 Tue 12/30/14
264
Concreting
2 days
Mon 12/29/14
265
Installation of Cable Tray
6 days
Wed 12/31/14
Mon 1/5/15
8 days
Tue 10/28/14
Tue 11/4/14
2 days
Tue 10/28/14
Wed 10/29/14
1 day
Thu 10/30/14
Thu 10/30/14
2 days
Fri 10/31/14
Sat 11/1/14
1 day
Sun 11/2/14
Sun 11/2/14
266
Earthing
267
Excavation if required
268
Chemical Treatment
269
Laying of Copper Strip
270
Installation of Copper Electrode
271
Backfilling/filling with red clay and Bentonite powder Steel Structural works
2 days
Mon 11/3/14
Tue 11/4/14
272
25 days
Mon 1/5/15
Thu 1/29/15
273
Erection of Equipment Supporting Structure
25 days
Mon 1/5/15
Thu 1/29/15
274
Erection of Gantries
7 days
Mon 1/12/15
Sun 1/18/15
15 days
Fri 1/30/15
Fri 2/13/15
14 days
Fri 1/30/15
Thu 2/12/15
275 276
Installation Outdoor Equipment
277
Circuit Breaker
2 days
Fri 1/30/15
Sat 1/31/15
278
Disconnecting Switches
5 days
Sun 2/1/15
Thu 2/5/15
279
Capacitor Voltage Transformer
1 day
Fri 2/6/15
Fri 2/6/15
280
Current Transformer
1 day
Sat 2/7/15
Sat 2/7/15
281
Surge Arrester
1 day
Sun 2/8/15
Sun 2/8/15
282
Bus-Bar
1 day
Mon 2/9/15
Mon 2/9/15
283
Stringing of Conductors between Gantries
1 day
Tue 2/10/15
Tue 2/10/15
284
Tapping and connection of individual equipment Stringing of Earth wire for Shielding Protection
1 day
Wed 2/11/15
Wed 2/11/15
285 286
Indoor Equipment
1 day
Thu 2/12/15
Thu 2/12/15
1 day
Fri 2/13/15
Fri 2/13/15
287
Battery and Charger extension
1 day
Fri 2/13/15
Fri 2/13/15
288
Communication Panels
1 day
Fri 2/13/15
Fri 2/13/15
289 290 291 292
Control and Relay Panels Cable Laying Control and LV Power Cables Wiring
1 day
Fri 2/13/15
Fri 2/13/15
5 days
Sun 3/22/15
Thu 3/26/15
5 days
Sun 3/22/15
Thu 3/26/15
12 days
Fri 3/27/15
Tue 4/7/15
293
Current Transformer
1 day
Fri 3/27/15
Fri 3/27/15
294
Capacitive Voltage Transformer
1 day
Sat 3/28/15
Sat 3/28/15
295
Disconnecting Swithches
1 day
Sun 3/29/15
Sun 3/29/15
296
AC/DC Distribution/Marshalling Boxes
3 days
Mon 3/30/15
Wed 4/1/15
297
Control and Relay Panels
6 days
Thu 4/2/15
Tue 4/7/15
298
Testing and Commissioning
5 days
Sun 8/9/15
Thu 8/13/15
299
Pretesting
2 days
Sun 8/9/15
Mon 8/10/15
300
Testing in presence of employer authorities
2 days
Tue 8/11/15
Wed 8/12/15
301
Commissioning
1 day
Thu 8/13/15
Thu 8/13/15
Project: Date: Thu 3/20/14
Task
Split
2014
2015 June July August September October November December January February March April May June July Au 6/1 6/8 6/15 6/22 6/29 7/6 7/13 7/20 7/27 8/3 8/10 8/17 8/24 8/31 9/7 9/14 9/21 9/28 10/5 0/1 0/1 0/2 11/2 11/9 1/1 1/2 1/3 12/7 2/1 2/2 2/2 1/4 1/11 1/18 1/25 2/1 2/8 2/15 2/22 3/1 3/8 3/15 3/22 3/29 4/5 4/12 4/19 4/26 5/3 5/10 5/17 5/24 5/31 6/7 6/14 6/21 6/28 7/5 7/12 7/19 7/26 8/2 8/9