Project Definition 1.1 (Kelompok 1 - PE C)
March 31, 2018 | Author: Rizki Firmansyah | Category: N/A
Short Description
Descripción: asdfghjk...
Description
PT PLN (Persero) ……………………..
Pembangunan PLTU Nagan Raya Unit III & IV Kapasitas 2x200 MW
= PROJECT DEFINITION =
Author
: Nuur’azizah Rosdiani Prian Muthaqin Robby Alfadhila Septian Ferdiansyah Shabrina Nadhila Yovi Rahman
PMO-PMM TI PLN
Creation Date
: 7 Januari 2017
Last Updated
: 9 Januari 2017
Document Ref
:
Version
: 1.1
01 PMM - INI
PT PLN (Persero) ……………………..
= TABLE OF CONTENT =
= TABLE OF CONTENT =
2
= DOCUMENT CONTROL =
3
= GENERAL INFO = A. Business Problem and Business Challenges B. Product or Services Description C. Strategic and Background D. Critical Success Factor E. Expected Benefit and Key Performance Indicator F. Area Impacted G. Technology H. Project Description I. General Subsequent Planning Activities J. Risk K. Constraints L. Assumptions M. Other Related Information
PMO-PMM TI PLN
4 5 5 5 7 7 8 9 9 14 14 14 14 15
01 PMM - INI
PT. PLN (Persero) ……………………..
= DOCUMENT CONTROL =
Revision History Date
Author
09-01-17
Version 1.1
Kelompok 1
Reference Project Definition 1.0
Reviewers Name Yovi Rahman, S.T.
Title
Signature
GM
Distribution No Copy
Name
Location
Note To Holders: If you receive an electronic copy of this document and print it out, please write your name on the equivalent of the cover page, for document control purposes. If you receive a hard copy of this document, please write your name on the front cover, for document control purposes.
PMO-PMM TI PLN
3 dari 15
01 PMM - INI
PT. PLN (Persero) ……………………..
= GENERAL INFO =
Project ID
:
08 / PLTU / UIP I / REGSUM / 2017
Project Name
:
Pembangunan PLTU Nagan Raya #3,4 Kapasitas 2x200 MW
Project Owner
:
Yovi Rahman, S.T.
Project Manager
:
Septian Ferdiansyah T., S.T.
Project Dependency
:
Main
:
Pembangunan Proyek Pembangkit 35000 MW
Sub
:
Proyek Pembangkitan Sumatera
Predecessor
:
Proyek PLTU Nagan Raya Unit 1 & 2 Kapasitas 2x100 MW
Successor
:
Sistem Pembangkitan Sumatera Bagian Utara
Brief Description on Dependency
:
Sistem PLTU Nagan Raya 3 dan 4 memastikan ketersediaan tenaga listrik untuk wilayah Aceh dan sekitarnya
Dependency Map
:
PMO-PMM TI PLN
4 dari 15
01 PMM - INI
PT. PLN (Persero) ……………………..
A. Business Problem and Business Challenges Provide a brief concise description of the business problem and business challenges. Beban puncak listrik di Aceh yaitu sebesar 325 MW, maka seharusnya ketersediaan listrik di Aceh mencapai sekitar 500 MW. Namun, saat ini hanya tersedia 340 MW yang berasal dari beberapa pembangkit di wilayah Aceh dan sebagian dari wilaya Sumatera Utara. Salah satu pembangkit yang menjadi sumber tenaga listrik di Aceh yaitu PLTU Nagan Raya Unit 1 & 2 Kapasitas 2x100 MW. Pembangunan PLTU Nagan Raya Unit 1 & 2 Kapasitas 2x100 MW hanya beroperasi 50%. Hal tersebut terjadi karena keterbatasan material batu bara yang digunakan untuk menghidupkan dua unit pembangkit tersebut. Kadar kalori batu bara yang diperoleh dari hasil tambang di wilayah Aceh Barat saat ini sangat rendah dan tidak sesuai dengan spesifikasi yang telah ditentukan, sehingga untuk memenuhi kebutuhan bahan bakar tersebut batu bara harus dicampur dengan batu bara khusus yang didatangkan dari luar Aceh. Selain itu, energi listrik yang dihasilkan oleh PLTU Nagan Raya 1 & 2 masih disuplai ke Sumatera Utara. Ini disebabkan interkoneksi yang belum tersambung antara PLTU Nagan Raya 1 & 2 ke PLTD Seuneubok, Aceh Barat, yang dapat mengalirkan arus listrik ke tiga kabupaten di kawasan pantai barat Aceh itu (Aceh Jaya, Aceh Barat dan Nagan Raya). Akibatnya, pasokan listrik bagi masyarakat Aceh sampai saat ini masih terbatas sehingga kerap menyebabkan terjadinya pemadaman listrik dan ikut mengganggu perekonomian masyarakat, termasuk investor yang telah menanamkan modalnya di Aceh. Business challenges : 1. Regulasi tentang pengadaan tanah / lahan Perlu adanya penyelarasan dan akselerasi dari pemerintah pusat mengenai perizinan. Karena selama ini banyak proyek mangkrak akibat dari lamanya proses pembebasan lahan dan perizinan. 2. Permodalan yang kuat Perlu adanya penjaminan yang kuat dari pemerintah untuk pendanaan terutama untuk proyek yang berskala besar untuk menjaga rasio keuangan.
B. Product or Services Description A.
B.
Tahap Persiapan 1.
Dokumen Studi Kelayakan, merupakan hasil studi kelayakan proyek PLTU Nagan Raya #3,4
2.
Dokumen Perizinan, merupakan dokumen yang menunjukkan proyek PLTU Nagan Raya #3,4 telah diizinkan untuk dibangun dari aspek penggunaan lahan, pembangunan dan sebagainya.
3.
Hasil Tes Tanah, untuk mengetahui karakteristik dan jenis tanah pada lahan proyek.
Tahap Execution
PMO-PMM TI PLN
5 dari 15
01 PMM - INI
PT. PLN (Persero) …………………….. Pekerjaan Sipil 1.
Pondasi, yaitu komponen bangunan struktur bawah yang menopang bangunan fungsional struktur atas.
2.
Bangunan PLTU
3.
Jetty, untuk menerima pasokan batu bara dari pulau lain dengan menggunakan kapal
Pekerjaan Mechanical dan Electrical 1.
2.
Coal Fuel System Coal Consumptions, untuk mengestimasi konsumsi batu bara pada powerplant baru. Demolition Coal, terdiri dari development of jetty, conveyor systems dan area coal yard berfungsi untuk mendistribusikan dan mengolah batu bara dari batu bara mentah yang baru tiba di jetty dengan kapal tongkang hingga tertampung pada area coal yard. Operational Generating System Boiler, sebagai tempat mengubah air dari fase cair ke fase uap dengan cara memanfaatkan panas. Turbine, untuk mengubah energi uap yang dihasilkan boiler menjadi energi gerak Generator, berfungsi mengubah energi mekanik/gerak dalam bentuk putaran poros menjadi energi listrik,yang akan membangkitkan tengangan bolak-balik menurut prinsip dasar.
3.
4. 5.
Generating Water Systems, untuk mengolah air yang berasal dari laut menjadi air yang siap digunakan sebagai sistem pendingin, generation system, air terdemineralisasi, fly ash and bottom ash removal, makeup system, unit dan housing, serta bolier blowdown cooling. Boiler Water Processing System Ashes and Dust Processing System Bottom Ash Handling System, mentransfer abu dari bagian bawah alat penampung debu ke tempat pembuangan dengan menggunakan truk atau conveyor
6.
Fly Ash Handling System, untuk mentransfer fly ash dari hopper ke silo dengan menggunakan pneumatic handling system. Ash Disposal Area, sebagai area pembuangan abu yang sudah tidak digunakan. Liquid Waste Processing System, untuk mengolah limbah cair di pembangkit sesuai standar yang
7.
Emergency Response, untuk mendeteksi, mencegah, melindungi dan menanggulangi bahaya kebakaran
8.
Sistem K3, untuk menjamin keselamatan dan keamanan SDM di pembangkit tersebut.
9.
Emergency Disaster Response System, untuk merencanakan dan menghasilkan prosedur keamanan
berlaku agar tidak mencemari lingkungan sekitar. yang mungkin terjadi di area sekitar pembangkit.
ketika keadaan emergensi terjadi, termasuk melakukan sosialisasi dan training/simulasi bencana.
Commissioning 1.
C.
Sertifikat Layik Operasi (SLO), yaitu sertifikat yang menunjukkan bahwa PLTU Nagan Raya #3,4 telah layak untuk digunakan sesuai dengan standar operasi dan keamanan yang berlaku.
Tahap Closing 1.
Dokumen Serah Terima Proyek, sebagai tanda bahwa proyek telah diselesaikan dan diserahkan kepada
owner.
C. Strategic and Background Please answer the following questions by marking “Yes” or “No.”
Yes
Is the project consistent with the state organization Business Plan.? If not, why not?
Yes
Is the project identified in the state organization strategic plan? If not, why not?
Yes
PMO-PMM TI PLN
6 dari 15
No
01 PMM - INI
PT. PLN (Persero) ……………………..
D. Critical Success Factor
Critical Success Factor proyek ini adalah:
Komitmen dan dukungan dari Direksi
Komitmen dan dukungan dari Project Owner
Komitmen dan dukungan dari Project Manager
Komitmen dan dukungan dari Tim Proyek
Komitmen dan dukungan dari User
Pengetahuan mengenai PLTU yang memadai dari setiap anggota tim
Ketersediaan sumber daya manusia yang memadai
Training yang memadai untuk semua anggota tim
Disiplin pelaksanaan sesuai dengan rencana kerja proyek / Project Management Plan
Dokumentasi proyek yang baik dan lengkap
Kesiapan alat berat, material, dan logistic yang mendukung kelancaran proyek
Kepemimpinan dan manajemen yang baik
Jasa Profesional service yang akan diberikan: PUSENLIS PUSENLIS bertugas sebagai engineering supervision serta melakukan design review.
Jasa Sertifikasi (JASER) Jasa Sertifikasi (JASER) bertugas untuk memastikan pembangkit yang telah dibangun telah laik operasi.
Jasa Manajemen Konstruksi (JMK) Jasa Manajemen Konstruksi (JMK) bertugas untuk mengawasi keberjalanan konstruksi proyek agar sesuai dengan standar dan spesifikasi teknis yang telah direncanakan.
E. Expected Benefit and Key Performance Indicator Short Term (6-12 bulan setelah proyek selesai) 1. Meningkatkan rasio elektrifikasi 2. Meningkatkan ketersediaan dan kehandalan tenaga listrik di wilayah Sumatera Bagian Utara Long Term (2-5 tahun setelah proyek selesai) 1. Meningkatkan tingkat perekonomian dan kesejahteraan masyarakat Sumatera bagian Utara 2. Meningkatkan revenue perusahaan 3. Meningkatkan citra PLN di mata masyarakat
PMO-PMM TI PLN
7 dari 15
01 PMM - INI
PT. PLN (Persero) …………………….. CATEGORY
SAVINGS PLAN ONE TIME
RECURRING
A. EMPLOYEE RELATED SAVINGS 1
Labor Cost Reduction / Avoidance
2
Reduces Turnover Subtotal B. EQUIPMENT RELATED SAVINGS 1 Elimination of Obsolete Equipment 2
Elimination of Maintenance Cost for Obsolete Equipment (including labor and parts) 3 Reduced Cost for Existing Equipment Based on Higher Utilization Subtotal C. SPACE RELATED SAVINGS 1 New Space Construction Avoidance Subtotal D. INVENTORY RELATED SAVINGS 1 Reduced Inventory Carrying Cost 2 Reduced Loss / Shrinkage Subtotal E. INFORMATION RELATED SAVINGS 1 Reduced IT Administration Support for Legacy Application 2 Resale of Existing Computer 3 Resale of Existing Computer Subtotal F. CUSTOMER SERVICES RELATED 1 Increase Sales 2 Improve Customer Satisfaction 3 Reduced Penalties Subtotal TOTAL SAVINGS
F. Area Impacted Check all appropriate functions: -
-
Business Operation Holding Distribution Business Process Material Management
Controlling and Assurance
Performance and Process Management Partner Management Energy Fulfillment Management
PMO-PMM TI PLN
Generation MSO
Finance & Accounting Management Human Resources Management
Risk Management
Scheduling Management Energy Operation, Administration and Automation
8 dari 15
Transmission
Regulatory Accounting
Asset, Facilities, Equipment Maintenance Marketing
01 PMM - INI
PT. PLN (Persero) ……………………..
Billing and Collection
Location Management – AM/FM/GIS Sales
Engineering, Procurement and Construction Customer Management
Other Business Functions:
G. Technology
Identify technology areas that might apply to this project. Check all appropriate categories: Application Architecture Category Corporate Mgt Automation Engineering, Design & Customer Service Construction
-
Operations Trading
Other Technology Areas:
H. Project Description
Provide high-level project description such as goal, objectives, deliverables & milestones, estimate schedule, cost, resources requirement.
Project Goal and Objective a. Goal Terselesaikannya pembangunan PLTU Nagan Raya Unit 3 & 4 Kapasitas 2x200 MW untuk memenuhi kebutuhan listrik di daerah Sumatera Bagian Utara. b. Objectives
Meningkatkan produktivitas listrik untuk mendukung program 35000 MW
Meningkatkan rasio elektrifikasi Indonesia menjadi 97% pada tahun 2019
Menjamin kehandalah sistem kelistrikan di wilayah Aceh Barat
Mendukung PLTU Nagan Raya Unit I & II dalam memenuhi kebutuhan tenaga listrik di wilayah Aceh Barat secara maksimal
Meningkatkan tingkat perekonomian masyarakat Aceh Barat dengan terpenuhinya kebutuhan listrik
Memanfaatkan SDA dan SDM dari lokasi sekitar proyek
PMO-PMM TI PLN
9 dari 15
01 PMM - INI
PT. PLN (Persero) ……………………..
Deliverables PROJECT PHASES
DELIVERABLES
SUBMISSION SCHEDULE
SIGNED – OFF REQUIRED Y
Project Initiation
Project Definition
Project Planning
Project Management Plan
Y
Kick Off Meeting
N
Feasibility Study
Y
Permission Documents
Y
Soil Investigation Result
Y
Foundation Document & Result
Y
Structure Plan & Result
Y
Guide Book / User Manual
N
Installed System
N
Trained User
N
Guide Book / User Manual
N
Installed System
N
Trained User
N
Modul Test Script
N
Modul Test Plan & Result
N
Integration Test Script
N
Integration Test Plan & Result
N
Preproduction System
N
Laporan Progress Pekerjaan
Y
Daily and Weekly Meeting Result
Y
Quality Control Document
Y
Quantity Surveyor Result
Y
Detail Design & Procurement of Additional Land
Civil Works
Mechanical Works
Electrical Works
Test / Commissioning
Project Controling & Monitoring
Tracking & Monitoring Performance Report Project Closing
Post Implementation Review Document Maintenance Document
PMO-PMM TI PLN
10 dari 15
Y N Y
01 PMM - INI
PT. PLN (Persero) ……………………..
Schedule and Milestones
Jadwal Project Implementasi
900 d
12-Jun-17
12-Jun-19
I. Tahap PREPARATION A. Feasibility Study B. Perizinan Proyek C. Soil Investigation dan Persiapan Lahan Proyek
245 d 150 d 150 d 45 d 180 d
12-Jun-17 12-Jun-17 12-Jun-17 12-Sep-17
27-Mar-18 12 -Sep-17 12-Sep-17 27-Okt-17
27-Sep-17 27-Sep-17
27-Mar-18 27-Mar-18
27-Sep-17
11-Okt-17
27-Sep-17
18-Okt-17
d
24-Jun-02
2-Oct-02
d
28-Okt-17 28-Okt-17 28-Jan-18 01-Des-17
01-Jun-18 28-Jan-18 28-Apr-18 01-Jun-18
D. Proses Pengadaan Material Konstruksi E. Proses Pengadaan Mesin Pembangkit
180 d 14 d
F. Proses Pengadaan Pengawas Proyek 21 d G. Penyusunan EGD II. Tahap EXECUTION
A. Civil Work 1. Pilling 2. Jetty 3. Foundation and Building PLTU B. Mechanical Works 1. Installation of main and auxiliary boiler 2. Installation of steam turbines and support 3. Compressed air system 4. Condenser cooling system 5. Coal and limestone handling system 6. Means ash handling 7. Fuel oil tanks 8. Water supply systems and raw materials 9. Air pollution control system 10. Wastewater treatments plants 11. Other work (soil, drainage, site road,etc) D. Electrical Work 1. Installation of the generator 2. Installation of transformer 3. Serandang Switch 4. Process control systems generating units, lighting units, communications, and alarms E. Test/ Pre-Commissioning 1. Electrical 2. Mechanical III. Tahap CLOSING A. Kumpulkan dan Review Data Proyek B. Serah Terima Proyek
PMO-PMM TI PLN
11 dari 15
d 120 d 90 d
01-Jun-18
90 d 90 d 90 d 90 d 90 d 90 d 90 d 30 d 60 d d 180 d 180 d 180 d
180 d 21 d
69.5 d 46 d 1d
12-Aug-02 12-Aug-02 11-Nov-02
12-Nov-02 14-Oct-02 11-Nov-02
01 PMM - INI
PT. PLN (Persero) ……………………..
Cost Estimate Rp 3.000.000.000.000,- (Tiga triliun rupiah)
Resources Requirement Estimate Kebutuhan Sumber Daya Manusia ROLE JUMLAH
KETERANGAN
Supervisor Civil Engineering
10
Penuh Waktu
Mechanichal Engineering
10
Penuh Waktu
Electrical Engineering
10
Penuh Waktu
Part of Steam Boiler
10
Penuh Waktu
Part of Turbine
10
Penuh Waktu
Commisioning
5
Penuh Waktu
Civil Engineer
100
Penuh waktu
Mechanical Technician
100
Penuh waktu
Electrical Engineer
100
Penuh waktu
Boiler Construction
50
Penuh waktu
Instrumentation
20
Penuh waktu
Insulator Engineering
50
Penuh waktu
Logging Worker
10
Penuh waktu
Material Control
10
Penuh waktu
Pipe Installer
30
Paruh waktu
Worker
PMO-PMM TI PLN
12 dari 15
01 PMM - INI
PT. PLN (Persero) …………………….. Equipment
50
Penuh waktu
Lifting Equipment Operator
10
Penuh waktu
Welding
40
Penuh waktu
Public Work
200
Penuh waktu
Total Kebutuhan SDM
825
Kebutuhan Material MATERIAL Natural Material Pasir Urug Tanah Urug Sirtu Concrete Sand Crushed Stone River Stone Brick Industrial Material Multiplex 12 mm Steel Bar Pile d 500 mm Pile d 600 mm Pile Structure Cement PC Kebutuhan Alat Berat ALAT BERAT Bulldozer Backhoe Motor Grader Dump Truck Hydrolic Submersible Pump
UNIT
VOLUME
m3 m3 m3 m3 m3 m3 Pc
150000 50000 30500 50000 70000 11500 3300000
Sheet ton m3 m3 ton Zak
25000 14500 60000 50000 3500 155000
UNIT 5 5 3 40 2
Kebutuhan Prasarana Lainnya a. Ruang Kerja b. Ruang Meeting c. Ruang Training d. Mushola e. Toilet f. Barak Pekerja g. Kantin Pekerja h. Area Penyimpanan Material i. Ruang Medis dan K3
PMO-PMM TI PLN
13 dari 15
01 PMM - INI
PT. PLN (Persero) ……………………..
I. General Subsequent Planning Activities Activity No.
1 2 3 4 5
Activity Description
Gap Analysis Review with Project Team Review Project Management Plan Approve Project Management Plan Kick-Off
No. of Days
10 2 3 1 1
Estimated Cost
Milestone
n.a n.a n.a n.a n.a
TOTAL
J. Risk
a. Ketidaksiapan Sumber Daya Manusia (kualitas dan kuantitas) b. kegagalan sentralisasi c. Data yang tidak akurat d. Resistansi terhadap perubahan (resistance to change) e. Keterlambatan pengadaan peralatan dan alat. f. Keterlambatan perizinan lahan proyek g. Permasalahan Force Mazor h. Ketidak profesionalan pihak ketiga. i. Dana investasi yang korporat K. Constraints
Kompetensi dan jumlah SDM PLN sebagai tim proyek
Dana investasi PLN yang terbatas
Ketergantungan dalam hal teknis seperti kondisi lapangan, ketersediaan material, dan produktivitas alat berat dan pekerja.
Ketergantungan dalam hal non-teknis seperti komunikasi dengan stakeholder terkait baik internal maupun eksternal.
Dapat terjadinya perubahan struktur organisasi dalam jangka waktu kontrak.
L. Assumptions Jumlah SDM terpenuhi sesuai dengan kebutuhan. Kompetensi dan kemampuan SDM sesuai dengan kualifikasi dan dapat menyelesaikan pekerjaan dengan baik. Anggaran yang dikeluarkan sesuai dengan rancangan anggaran yang telah ditetapkan. Tidak ada perubahan kebijakan pemerintas selama pelaksanaan proyek.
PMO-PMM TI PLN
14 dari 15
01 PMM - INI
PT. PLN (Persero) ……………………..
M. Other Related Information Lihat lampiran dan dokumen-dokumen berikut sebagai referensi dari proyek ini:
Kontrak
TOR
PMO-PMM TI PLN
15 dari 15
01 PMM - INI
View more...