PROJECT CHARTER GENERAL SUPPLIES E-COMMERCE WEBSITE
12/07/2015 General Supplies 41, SPRING HILL PKWY SE, SMYRNA, GA-30080
Project Charter Project Name
: General Supplies E-commerce Website
Focus Area online business
: Creation of E-commerce website for the successful operation of
Prepared By
Document Owners
Organizational Roles
Rob Wade
Business Analyst / Project Manager
Josephine
Architect
Prashaanth
Developer
Gayathri
QA Tester
Chuchu
Support Specialist
Project Charter Version Control
Version
Date
Author
Change Description
A
12/07/2015
Rob Wade
Primary Scope and Project Charter
Project Charter
Table of Contents
1. Project Charter Purpose 2. Project Executive Summary 3. Project Overview 4. Project Scope 4.1 Goal and Objectives 4.2 Statement of Work (SOW) 4.3 Project Deliverable 4.4 Project Estimated Costs & Duration 5. Project Conditions 5.1 Project Assumptions 5.2 Project Risks 5.3 Project Constraints 6. Project Structure Approach 7. Project Team Organization Plans 8. Approvals
Project Charter 1. Project Charter Purpose
The project team will determine and identify the required steps for developing an e-commerce website that covers the combination of business models. Our website will establish the process of buying the products of General Supplies company online. We will examines the business model and incorporate it onto the website. The project team will discover possible solutions for the new e-commerce business. The project team will become knowledgeable on how to develop an e-commerce website
2. Project Executive Summary •
•
•
•
•
•
•
•
Project Goal : Creation of new e-commerce website for General Supplies company that will be successful and generate revenues Objectives : To create and maintain a high revenue e-commerce website to capture the business potential of selling General Supplies products online Scope : Deliver a quality e-commerce website within the time, cost and project requirements set by the project team Assumptions : There are lot of e-commerce websites that have been successful in generating the revenues. The e-commerce business has also witnessed growth in the last 5 years Risks : Identify and research possible risks starting up new ecommerce website Costs : Deliver the website within the allotted money for the project. Costs would be considered for website specifications such as human resources, training and other expenses that might arise Timeline : Develop a reasonable timeline by researching other ecommerce websites and determine time taken to complete the entire project. Approach : Project Manager will conduct weekly project meeting The project manager will be responsible for delegating work and assign project duties. The project manager will communicate via email, phone and conference calls.
Project Charter •
Organization as follows
: Star Associates. The organizational structure of this project is
Rob Wade Josephine Prashaanth Gayathri ChuChu
: Business Analyst / Project Manager : Architect : Developer : QA Tester : Support Specialist
3.Project Overview
Our Project's mission is to develop a new and successful e-commerce website for General Supplies company. The site will feature the products of General Supplies company and will enable online purchase of selected products. We will examine the possible methods to develop the e-commerce website into premium premiu m online business for General Supplies company
4. Project Scope 4.1 Goals and Objectives Goals •
•
•
•
Enable General Supplies company to sell their products online. Gather requirements for the website
Develop website to increase the revenue through online sales Develop the website within allocated cost, time and resources
Objectives •
•
•
•
Create an e-commerce website selling their products online Research many e-commerce websites to develop ideas and actions point to incorporate onto the developing website The project team will research the best model and design for generating revenue through online sales Complete the website within $275,000.00 before 11/30/2016 with 5 resources
Project Charter 4.2 Departmental Statement of Work Statement of Work
Responsibility
Due Date
Business case
Business Analyst, Architect
01/14/16
Planning
Business Analyst
02/25/16
Design
Business Analyst, Architect
03/25/16
Build
Developer
05/26/16
Quality Assurance Testing
QA Tester
07/18/16
Implementation
Business Analyst, Architect
07/26/16
Project Website Soft Launch
Developer, Business Analyst
08/17/16
Hard Launch
Developer
08/18/16
Handover
Business Analyst, Architect
08/25/16
Online Support
Business Analyst, Support Specialist
10/14/16
4.3 Project Deliverables Milestones
Sign off Project Schedules and contracts
Sign off business case
Deliverables
Audit E-Commerce objectives Develop project schedule Budget, Risk and Change control planning Contracts and Cross functional requirement High level requirement Business Assessment Technical Specification
Project Charter Milestones
Deliverables
Sign off Planning
Requirement Gathering Content Outline Website Page layout
Sign off Design
Visual Element Design Create Prototype template Design Review
Sign off Development
CSS & HTML Coding Module Integration Content Population Unit Testing Security Implementation
Sign Off Testing
Site Testing Cross Device Testing Performance Testing User Experience Testing
Sign off Soft Launch
Configure production Server Verify Production Server Transfer files to Production Server Final UAT & copy proofing
Project Closure
Completion of Project
Project Estimated Cost and Duration Project Phases
Due Date
Business Case
01/14/16
• • •
Planning
02/25/16
• • •
Deliverables
Cost
High Level Requirement Business Case Assessment Technical Specification
$64,655.00
Requirement Gathering Content Outline Website Page Layout
$25,103.25
Project Charter
Project Phases
Due Date
Design
03/25/16
Deliverables
• • •
Build
06/25/16
• • • • •
Quality Assurance Testing
07/18/16
• • • •
Implementati on
07/26/16
• •
•
Project Website Soft Launch
08/17/16
$34,280.00
CSS & HTML Coding Module Integration Content Population Unit Testing Security Implementation
$41,700.00
Site Testing Cross Device Testing Performance Testing User Experience Testing
$32,584.00
Prepare Launch Schedule Register with search Engines Check DNS Entries
$12,360.00
•
Hard Launch
• •
Hard Launch
08/18/16
•
Handover
08/25/16
•
$800.00 $6,940.00
•
Complete Project Documentation Prepare User Manual Site training
•
Go Live Support 1
$19,640.00
•
10/14/16
Visual Element Design Create Prototype Template Design Review
Configure production Server $14,680.00 Verify Production Server Transfer files to Production Server Final UAT Final copy proofing
•
•
Online Support
Cost
Project Charter
5. Project Conditions 5.1 Project Assumptions •
•
•
Creation of E-commerce website for General Supplies company incorporates all the General Supplies products available in their retail store Develop alternate revenue generation for General Supplies company by selling their products online E-commerce business has has been successful and grown in the last last 5 years and alternate mode of selling develops General Supplies company business initiatives.
5.2 Project Risks Risk Areas
Likelihoo d /Impact
Risk Owner
Mitigation Plan
Scope Creep
High
Project Manager
Contact project sponsor to determine future project requirements; no more changes to current project.
Custom Coding Overruns
High
Project Manager
Strict guidelines around scope creep, updates on project documents.
5.3 Project Constraints •
•
Budget : The requirement to complete the project under the estimated cost of $275,000.00 Time : Client requires to launch the website before November 30,2016.
Project Charter 6. Project Structure Approach
Project Manager will conduct weekly project meeting. The project manager will be responsible for delegating work and assign project duties. The project manager will communicate via email, phone and conference calls.
7. Project Team Organization Plans
The constraints of the project are the cost and the time. Hence the team decided to include the associates from India , Prashaanth – Developer and Gayathri- QA tester and ChuChu from Philippines for Online Support Project Team Role
Project Team Members
Business Analyst
Rob Wade
Architect
Josephine
Developer
Prashaanth
QA Tester
Gayathri
Support Specialist
ChuChu
8. Approvals
Approved By
: ----------------------------------- ------(Project Sponsor : Mr. John Smith)