Productivity Rates

April 27, 2017 | Author: zawadimran | Category: N/A
Share Embed Donate


Short Description

j...

Description

Productivity rates of common items of work Productivity rates of some important items of work are presented here to have an over view of construction trends in the industry. The capacity of doing work by an artisan & skilled labour in the form of quantity of work per day (working 8 hours ) is given below: Sr.#

Particulars of item

1.

Earth work in excavation in ordinary soil including disposal upto (30 m) & lift (1.5 m) Earth filling under floors including compaction in 6” layers Disposal of surplus earth within a lead of 30 m Excavation in rock

2. 3. 4. 5. 6. 7. 8.

Quantity of work per day 3 cubic meter

Kind of labour required per day Mazdoor 1 Mason 1/22

6 cubic meter

Mazdoor 1 Bhishti 1/34 Mazdoor 1

3 cubic meter 5 cubic meter

Earth work over roofing including ramming Cement concrete 1:4:8, 1:5:10, 1:6:12 & 1:6:18 in foundation with brick ballast or stone ballast Plain cement concrete 1:2:4

3 cubic meter

R.C.C 1:2:4 in slabs, lintels & column etc. including bending, binding, centering &shuttering

4 cubic meter

8 cubic meter 6 cubic meter

Mazdoor 1 Mason 1/22 Mazdoor 1 Mason 1/22 Mazdoor 12 Mason 1 Bhishti 1 ¾ Mazdoor 9 Mason 1 Bhishti 1 ½ Mazdoor 16 Mason 1 Black smith 1 ½ Carpenter 1 ½

9.

Damp proof course 4 cm thick 1:2:4 concrete with two coats of hot bitumen laid hot

10 sq. meter

10.

Lime concrete in foundation

8 cubic meter

11.

Damp proof course 2.5 cm thick, 1:2:4 concrete with two coats of bitumen laid hot

12 sq. meter

12.

Reinforced brick work laid in cement mortar 1:2 or 1:3 in slabs & lintels

1 cubic meter

13.

1ts class brick work in cement mortar in foundation & plinth

1.5 cubic meter

14.

1st class brick work in cement mortar in super structure

1.3 cubic meter

15.

Plastering with any mortar ½”thick

13 sq. meter

16.

Cement pointing or lime pointing

10 sq. meter

17.

Cement pointing flush variety

20 sq. meter

18.

60 sq. meter

21.

White washing or colour washing (3 coats) White washing or colour washing (2 coats) White washing or colour washing (1 coat) Distempering (1 coat)

22.

Distempering (2 coats)

20 sq. meter

19. 20.

80 sq. meter 140 sq. meter 35 sq. meter

Bhishti 2 Mazdoor 2 ½ Mason 1 ½ Bhishti ½ Mazdoor 12 Mason 1 Bhishti 1 ¾ Mazdoor 2 Mason 1 ½ Bhishti ½ Mazdoor 3 Mason 1 Carpenter 1/10 Black smith 1/10 Bhishti 1/5 Mazdoor 2 Mason 1 Bhishti ¼ Mazdoor 2 Mason 1 Bhishti ¼ Mazdoor 1 Mason 1 Bhishti 3/5 Mazdoor 1 Mason 1 Bhishti 1/10 Mason 1 Mazdoor 1 White washer 1 Mazdoor 1 White washer 1 Mazdoor 1 White washer 1 Mazdoor 1 Painter 1 Mazdoor ½ Painter 1 Mazdoor 1

23. 24. 25. 26.

27.

28. 29.

Painting on new wood work with 3 coats of approved paint Painting 2 coats excluding priming coat on n wood work Painting old wood work one coat only Varnishing 2 coats on new wood work

15 sq. meter 20 sq. meter 50 sq. meter 16 sq. meter

Cement concrete flooring 4 cm 8 sq. meter thick concrete 1:2:4 Over 10 cm thick cement concrete 1:6:18 over 10 cm thick sand filling Brick flooring 10 cm concrete 12 sq. meter 1:6:18 over 10cm sand filling & cement pointed flush Making frames of doors & 18 cubic windows (chowkats) meter * Data from “Civil Estimating & Costing” by S.P.Mahajan

Painter 1 Mazdoor ½ Painter 1 Mazdoor ½ Painter 1 Mazdoor ½ Painter 1 Mazdoor ½

Mazdoor 2 Mason 1 ½ Bhishti 4/5 Brick layer 1 ½ Mazdoor 2 Bhishti ½ Carpenter 2 Mazdoor 1

Another set of information on productivity rates obtained from another source is presented as follows: Sr.# 1.

Quantity per day 45 cft per mason

2.

Particulars of items Brick work in lime or cement in foundation & plinth --do—in super structure

3.

Brick work in mud mortar in foundation & plinth

55 cft per mason

4.

-- do—in super structure

45 cft per mason

5.

Brick work in cement or lime mortar in arches

20 cft per mason

6.

--do—in jack arches

20 cft per mason

7.

Half brick wall in partition

50 sft per mason

35 cft per mason

8.

30 cft per mason

10.

Coursed rubble stone masonry in lime or cement mortar including dressing Random rubble stone masonry in lime or cement mortar Ashlar masonry in lime or cement mortar

11.

Stone arch work

15 cft per mason

12.

Lime concrete in foundation or floor

300 cft per mason

13.

Lime concrete in roofing

200 cft per mason

14.

Cement concrete 1:2:4

175 cft per mason

15.

R.B work

35 cft per mason

16.

R.C.C WORK

125 cft per mason

17.

½” Plastering with cement or lime mortar

80 sft per mason

18.

Pointing with cement or lime mortar

100 sft per mason

19.

White washing or colour washing (3 coats)

700 sft per white washer

20.

White washing or colour washing (1 coat)

2000 sft per white washer

21.

Painting or varnishing doors or windows (1 coat)

250 sft per painter

22.

Coal taring or solignum painting one coat

350 sft per painter

23.

Painting large surface 1 coat

350 sft per painter

24.

Distempering one coat

350 sft per painter

25.

1” c.c floor

75 sft per painter

26.

Flag-stone floor laying with lime or cement excluding L.C. Terrazzo floor 6mm thick mosaic work over 2cm thick cement concrete (1:2:4)

100 sft per mason

9.

27.

35 cft per mason 15 cft per mason

50 sft per mason

28.

70 sft per mason

29.

Brick on edge in floor with lime or cement mortar excluding L.C. Brick flat floor as in above

30.

Timber framing sal or teak wood

2.5 cft per carpenter

31.

--do--country wood

5 cft per carpenter

32.

Door & window shutters paneled or glazed

1.5 sft per carpenter

33.

--do-- battened

8 sft per carpenter

34.

Sawing hard wood

40 sft per pair of sawyers

35.

Sawing soft wood

60 sft per pair of sawyers

36.

Earthwork in excavation in ordinary soil

100 cft per beldar mazdoor

37.

Earthwork in excavation in hard soil

75 cft per beldar mazdoor

38.

Excavation in rock

35 cft per beldar mazdoor

39.

Sand filling in plinth

140 cft per beldar mazdoor

40.

Number of bricks laid by mason in brickwork upto a height of 10’

600 bricks per mason

41.

Amount of work-done by a mazdoor (helper) per day: • Mix • Deliver brick • Deliver mortar

1) 100 cft mortar per mazdoor 2) 4000 no. to a distance of 50’ per mazdoor 3) 200 cft per mazdoor

80 sft per mason

Labour (mazdoor) required for different works a) Earthwork per 1000 cft: Excavation in foundations, trenches etc. in ordinary soil including disposal up to 100’ & lift of 5’:

5 beldars & 4 mazdoors can do 1000 cft per day Refilling excavated earth in foundations, plinth etc. including compaction in 6” layers: 3 beldars, 2 mazdoors & ½ Bhishti can do 1000 cft per day Disposal of surplus earth within a lead of 100: 1 mazdoor can do 100 cft per day b) Cement concrete work per 100 cft: Laying cement concrete: 2 beldars, 3 mazdoors, ¾ Bhishti & ¼ mason can do 100 cft per day c) R.C.C work: Laying reinforced concrete: 3 beldars, 3 mazdoors, 1 1/3 bhishti & ½ mason can do 100 cft per day Centering & shuttering for flat surfaces: 4 beldars & 4 carpenters can do 90 sft per day Reinforcement work for R.C.C: 1 blacksmith or fixer & 1 beldar can bend & place in position 1 quintal of steel per day d) Stone work per 100 cft: Random rubble masonry with blue stone in foundations: 3 masons, 3 beldars, 2 mazdoors & ¼ bhishti can do 100 cft per day e) Brickwork per 100 cft: First class brick work in 1:4 cement mortar in super structure, partition walls, junctions of roof, Parapet walls & string course: 2 ¼ masons,4 ½ mazdoors & ½ bhishti can do 100 cft per day

f) Wood work: For the frames of doors & windows: 2 carpenters & 1 beldar can work (6.40 cft) of wood equivalent to 4 door frames (3”x4” of 3’11”x 7’) size per day For paneled, glazed shutters: 15 carpenters & 4 beldars can make & fix 4 shutters (40mm) thick of size (6’9”x3’9”) per day. Quantity of wood per shutter (2.66 cft) g) Iron work: Fixing (1 ½”x1/6”x15”) flat iron hold-fasts: 1 blacksmith, 1 mason & 1 beldar can fix 36 holdfasts per day Fixing 5/8” dia M.S rods: 1 blacksmith, 2 carpenters & 3 beldars can fix (54 ft) per day h) Flooring: 1 ½” thick cement concrete flooring of 400 sft require: 5 masons, 4 beldars, 3 mazdoors & 1 bhishti per day for mixing, laying & finishing. i) Finishing: Plastering with any mortar ½” thick: 3 masons, 3 mazdoors & 1 bhishti can plaster 400 sft per day. White washing or colour washing (3 coats): 1 white washer & 1 mazdoor can do 600 sft per day Painting 2 coats such as chocolate, red, grey etc. on wood or steel: 3 painters & 2 mazdoors can paint 100 sft per day.

* Data from “estimating & costing in civil engineering” by N.L. DUTTA (25th ed.) Productivity rates of some important items of work as obtained from internet are tabulated below: Excavation Work Task / Description

Slow

Ave

Fast Units

Excavate Spoil Heaps to Transport, 0.6m3 bucket, Sand/Soil

14.5

20.0

25.6 m3/hr

Excavate Spoil Heaps to Transport, 0.6m3 bucket, Gravel Beds

15.2

20.4

25.6 m3/hr

Excavate Spoil Heaps to Transport, 0.6m3 bucket, Clay/Chalk

12.3

18.5

23.2 m3/hr

Excavate Spoil Heaps to Transport, 0.6m3 bucket, Boulder Clay

11.2

16.9

21.3 m3/hr

Excavate Spoil Heaps to Transport, 1.1m3 bucket, Sand/Soil

25.4

30.3

35.7 m3/hr

Excavate Spoil Heaps to Transport, 1.1m3 bucket, Gravel Beds

25.6

31.3

37.0 m3/hr

Excavate Spoil Heaps to Transport, 1.1m3 bucket, Clay/Chalk

22.5

27.8

33.3 m3/hr

Excavate Spoil Heaps to Transport, 1.1m3 bucket, Boulder Clay

18.9

24.4

30.3 m3/hr

Load Spoil to Barge, capacity 2,000m3

-

8.0

- hrs

Load Spoil to Barge, capacity 1,500m3

-

6.5

- hrs

Load Spoil to Barge, capacity 1,000m3

-

5.5

- hrs

Spoil conveyor, 600mm belt, 150m/min

- 260.0

- m3/hr

Concrete Road surfacing Task / Description Concrete Road surfacing, Kerbs or Side Haunches

Slow

Ave

Fast Units

-

0.4

- m3/hr

Concrete Road surfacing, 150mm thick

-

12.5

- m2/hr

Concrete Road surfacing, 200mm thick

-

7.7

- m2/hr

Concrete Road surfacing, 300mm thick

-

6.7

- m2/hr

Basecourse Production Rates: We have found these production rates a good rule of thumb for the construction of Basecourse Urban environment: Spread & Compact Production = 30m3/hr Trimming Production = 250m2/hr Rural environment: Spread & Compact Production = 50m3/hr Trimming Production = 350m2/hr Waterproofing Task / Description

Slow

Ave

Fast Units

Asphalt coatings, horizontal surfaces

3.5

4.2

5.8 m2/hr

Asphalt coatings, vertical surfaces

1.2

1.7

2.2 m2/hr

Bituminous Brushed application, 2 coats

4.8

5.0

6.3 m2/hr

Bituminous Brushed application, 3 coats

3.3

3.5

4.4 m2/hr

Bituminous Sheets, horizontal surfaces

3.8

4.0

4.8 m2/hr

Bituminous Sheets, vertical surfaces

3.3

3.5

4.2 m2/hr

Polythene Sheets, horizontal surfaces

-

20.0

- m2/hr

Bentonite Sheets, horizontal surfaces

18.7

25.0

31.3 m2/hr

Bentonite Sheets, vertical surfaces

11.2

15.0

17.3 m2/hr

-

75.0

- m2/hr

Epoxy Based application, 1 coat

Epoxy Based application, 2 coat

-

38.0

- m2/hr

Wallpapering Task / Description

Slow

Ave

Fast Units

Strip Existing Wallpaper (3 layers) & Prepare Walls

-

5.0

- m2/hr

Fix Wallpaper and lining paper

-

5.0

- m2/hr

Fix Vinyl and Washable paper

-

4.2

- m2/hr

Fix Ceiling Lining Paper

-

4.0

- m2/hr

Slow

Ave

Fast Units

Mosaic Tiling, 0.045x0.045m

-

1.1

1.5 no/hr

Clay, quarry Tiles, Window Cills, setout and level

-

55.5

- m/hr

Clay, quarry Tiles, Window Cills, fix, grout and clean

-

1.5

- m2/hr

20.4

27.1

32.0 no/hr

Ceramic Tiles 150x150mm, Areas under 1.5m2 per room

0.9

1.0

1.2 m2/hr

Ceramic Tiles 150x150mm, Areas of 1.5-2.5m2 per room

1.4

1.6

1.9 m2/hr

Ceramic Tiles 150x150mm, Areas over 2.5m2 per room

1.5

1.7

2.1 m2/hr

Ceramic Tiles 150x150mm, Extra Over for Cutting

-

41.6

- no/hr

Ceramic Tiles 108x108mm, Ledges/Upstands

-

62.5

- no/hr

Ceramic Tiles 108x108mm, Areas under 1.5m2 per room

1.0

1.3

1.5 m2/hr

Ceramic Tiles 108x108mm, Areas of 1.5-2.5m2 per room

1.6

1.8

2.1 m2/hr

Ceramic Tiles 108x108mm, Areas over 2.5m2 per room

1.7

1.9

2.2 m2/hr

- 125.0

- no/hr

Wall Finishes Task / Description

Ceramic Tiles 150x150mm, Ledges/Upstands

Ceramic Tiles 108x108mm, Extra Over for Cutting

Ceramic Tiles, Grouting Works

2.2

2.5

2.6 m2/hr

Slow

Ave

Fast Units

Hydraulic Excavator, 0.3m3 bucket, Sand/Soil

5.6

7.1

8.2 m3/hr

Hydraulic Excavator, 0.3m3 bucket, Gravel Beds

4.8

6.1

7.3 m3/hr

Hydraulic Excavator, 0.3m3 bucket, Clay/Chalk

4.8

6.1

7.1 m3/hr

Hydraulic Excavator, 0.3m3 bucket, Hard Ground

9.7

5.4

6.4 m3/hr

Hydraulic Excavator, 0.4m3 bucket, Sand/Soil

20.5

25.0

29.2 m3/hr

Hydraulic Excavator, 0.4m3 bucket, Gravel Beds

18.2

22.2

26.0 m3/hr

Hydraulic Excavator, 0.4m3 bucket, Clay/Chalk

18.2

22.2

26.0 m3/hr

Hydraulic Excavator, 0.4m3 bucket, Hard Ground

17.0

20.0

23.4 m3/hr

Hydraulic Excavator, 0.5m3 bucket, Sand/Soil

26.0

28.6

33.1 m3/hr

Hydraulic Excavator, 0.5m3 bucket, Gravel Beds

26.3

28.6

33.2 m3/hr

Hydraulic Excavator, 0.5m3 bucket, Clay/Chalk

26.3

28.6

33.2 m3/hr

Hydraulic Excavator, 0.5m3 bucket, Hard Ground

22.7

25.0

28.8 m3/hr

Excavate and Board Trench, 0.5-1.5m deep, < 2.0m wide

3.3

4.5

6.8 m2/hr

Excavate and Board Trench, 1.5-3.0m deep, < 2.0m wide

3.0

4.2

6.5 m2/hr

Excavate and Board Trench, 3.0-4.5m deep, < 2.0m wide

2.7

4.0

6.0 m2/hr

Excavate and Board Trench, 0.5-1.5m deep, > 2.0m wide

6.6

7.1

8.8 m2/hr

Slow

Ave

Fast Units

-

1.3

- no/hr

Trench Excavation Task / Description

Timber Frames Task / Description Roof Trusses

Wall Plates

-

2.7

- m/hr

Roof Rafters

-

1.2

- m/hr

Ceiling Joists

-

32.1

- m/hr

Roof Soffits, Softwood, nailed

-

9.2

- m/hr

Roof Soffits, Softwood, screwed

-

3.9

- m/hr

Roof Soffits Asbestos, under 300mm nailed

-

9.1

- m/hr

Roof Soffits Asbestos, under 300mm screwed

-

3.8

- m/hr

Roof Soffits, Asbestos, over 300mm nailed

-

3.5

- m/hr

Roof Soffits, Asbestos, over 300mm screwed

-

1.3

- m/hr

Roof Facia Panels, Softwood

5.1

7.2

9.3 m/hr

Roof Facia Panels, Asbestos

1.3

2.5

3.9 m/hr

Roof Facia Panel Studding, nailed

7.3

8.1

9.0 m/hr

Roof Facia Panel Studding, screwed

4.6

5.2

5.8 m/hr

Roof Facia Panel Studding, bolted to beams

5.4

5.9

6.6 m/hr

Roof Works, Fix Herringbone Strutting

-

5.1

- m/hr

Roof Works, Fix Firing Strips

-

25.0

- m/hr

Roof Works, Fix Drip/Tilt Filleting

-

20.5

- m/hr

Slow

Ave

3.4

-

Steel Frames Task / Description Steel Frame and Roof Members

Fast Units 4.6

Tons/da y

Wall Frame, Bow String Truss and Frame

-

1.6

-

Tons/da y

Roof Frame, Curved Truss and Frame

-

5.2

-

Tons/da y

Wall Frame, Glazed Frame and Atrium

-

0.3

-

Tons/da y

Slow

Ave

Slate Roofs, Welsh Slate 3-5mm

-

18.0

- m2/day

Slate Roofs, Cumbrian Slate 8-11mm

-

8.5

- m2/day

Slate Roofs, Asbestos Slates

-

36.0

- m2/day

Tiled Roofs, Concrete Tiles

-

52.0

- m2/day

Tiled Roofs, Clay Pan Tiles

-

26.0

- m2/day

Slow

Ave

PVC Sheeted Roofs, large areas

-

50.0

- m2/day

PVC Sheeted Roofs, small areas

-

40.0

- m2/day

Plastic Profiled Sheet Systems

-

54.0

- m2/day

Slow

Ave

Fast Units

-

3.3

- m/hr

Slates and Tiling Task / Description

Fast Units

Sheeted Roofs Task / Description

Fast Units

Rainwater Works Task / Description UPVC Downpipes, 75mm

UPVC Guttering, 75mm

-

3.1

- m/hr

UPVC RWP Fittings, 75mm

-

3.1

- no/hr

Cast Iron Downpipes, 75mm

-

2.1

- m/hr

Cast Iron Guttering, 75mm

-

2.5

- m/hr

Cast Iron RWP Fittings, 75mm

-

2.2

- no/hr

Aluminium Downpipes, 72mm

-

2.5

- m/hr

Aluminium Guttering, 72mm

-

2.9

- m/hr

Aluminium RWP Fittings, 72mm

-

1.9

- no/hr

Curtain Walling Task / Description

Slow Ave

Fast Units

Vertical Glazed Lights, 6m x 2.5m

- 14.5

- m2/day

Vertical Glazed Walls, large scale

- 70.0

- m2/day

Clerestory Frame/Glazing, 3m x 4m

- 28.0

- m2/day

Oriel Window Frame/Glazing, 4m x 2m

- 35.0

- m2/day

Glazed Curtain Wall, First Fix

-

1.2

- m2/hr

Glazed Curtain Wall, Second Fix

-

1.1

- m2/hr

High Quality Glazed Curtain Walling

- 25.0

- m2/day

Metal Decking Task / Description Metal Decking, large areas

Slow

Ave

-

70.0

Fast Units - m2/da

y Metal Decking, small or complicated

-

28.0

-

m2/da y

Titanium Sheeted Roofs

-

9.5

-

m2/da y

Copper Roofs, flat work

-

3.0

-

m2/da y

Copper Roofs, sloping work

-

2.7

- m2/dy

Zinc Roofs, flat work

-

2.4

-

m2/da y

Zinc Roofs, sloping work

-

2.1

-

m2/da y

Aluminium Roofs, flat work

-

2.8

-

m2/da y

Aluminium Roofs, sloping work

-

1.9

-

m2/da y

Lead Roofs, flat work

-

2.5

-

m2/da y

Lead Roofs, sloping work

-

2.1

-

m2/da y

Lead Roofs, dormer cheeks

-

1.3

-

m2/da y

Lead Roofs, flat gutters

-

88.0

- m/day

Lead Roofs, flat copings

-

76.0

- m/day

Lead Roofs, stepped gutters

-

3.5

- m/day

Lead Roofs, shaped copings

-

3.3

- m/day

Lead Roofs, cover step flashings

-

3.2

- m/day

Lead Roofs, rooflight flashings

-

0.8

- no/day

Lead Roofs, domed roof coverings

-

m2/da y

-

0.7

Slow

Ave

Asphalt Roof in layers

-

45.0

-

Asbestos Sheets in layers

-

39.0

- m2/dy

Flat and Layered Roofs Task / Description

Fast Units m2/da y

View more...