Published on Planning Planet (http://www.planningplanet.com) Home > Rates, Norms & Durations
By PP Wiki Created 5 Feb 2009 - 05:54
Rates, Norms & Durations What is needed to come up with a production rate? A duration of time, the manhours involved, and an amount of work produced? This section is here to document this. What information do you have that you can share?
Automotive Automotive Production Rates & Build Times:
Bridges Bridges Production Rates & Buld Times:
Bridge Decking Traffic Decking Installation of temporary traffic decking, consisting of steel beam decking and concrete panels. • A typical rate of = 1.6 m2/hr.
Cable Stringing Covered Steel Footbridge Simple universal beam steel bridge in modular sections, welded on site. 16 truss sections each 15 m in length, supported on H-frame vertical columns / supports. • • • • • • •
Support Steelwork Fabrication (4 bays) = 25 days Support Steelwork Erection (4 bays) = 30 days Truss erections (4 bays) = 18 days Paintwork To Steel (16 bays) = 35 days Bridge Deck Concrete Works (16 bays) = 60 days (staggered) Bridge Lighting, Roof etc (16 bays) = 40 days Bridge Finishing, Handrails and Grano = 14 days
Structural Steelwork... Task / Description
Slow
Ave
Fast
Units
Simple Universal Beam Steel Bridge, erect support steel H frames
-
1.2
-
days/no
Simple Universal Beam Steel Bridge, erect 15m truss
-
3.3
-
m/day
Design Final Finishes
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 2 of 100
Formwork & Bases Paintwork Structural Steelwork Steel Frames Task / Description
Slow
Ave
Fast
3.4
-
4.6
Tons/day
Wall Frame, Bow String Truss and Frame
-
1.6
-
Tons/day
Roof Frame, Curved Truss and Frame
-
5.2
-
Tons/day
Wall Frame, Glazed Frame and Atrium
-
0.3
-
Tons/day
Steel Frame and Roof Members
Units
Building & Construction Building & Construction Production Rates & Build Times:
Blockwork Blockwork Task / Description
Slow
Ave
Fast
Units
Thermalite Blockwork, under 100mm thick
1.8
2.5
3.2
m2/hr
Thermalite Blockwork, under 100-150mm thick
1.4
1.9
2.5
m2/hr
Thermalite Blockwork, over 150mm thick
1.2
1.6
2.1
m2/hr
Lightweight Concrete Blockwork, under 100mm thick
1.5
2.2
2.9
m2/hr
Lightweight Concrete Blockwork, under 100-150mm thick
1.4
1.9
2.1
m2/hr
Lightweight Concrete Blockwork, over 150mm thick
1.2
1.6
2.0
m2/hr
Heavyweight Concrete Blockwork, under 100mm thick
1.4
2.1
2.9
m2/hr
Heavyweight Concrete Blockwork, under 100-150mm thick
1.2
1.6
2.1
m2/hr
Heavyweight Concrete Blockwork, over 150mm thick
1.1
1.4
1.8
m2/hr
Face Finish, Raked Out
-
71.4
-
m2/hr
Face Finish, Bag Rubbed
-
29.4
-
m2/hr
Face Finish, Flush Pointing
-
17.6
-
m2/hr
Building Frameworks Curtain Walling Curtain Walling rate Assume 30m2 per week for general curtain walling Slow
Ave
Fast
Vertical Glazed Lights, 6m x 2.5m
Task / Description
-
14.5
-
m2/day
Vertical Glazed Walls, large scale
-
70.0
-
m2/day
Clerestory Frame/Glazing, 3m x 4m
-
28.0
-
m2/day
Oriel Window Frame/Glazing, 4m x 2m
-
35.0
-
m2/day
Glazed Curtain Wall, First Fix
-
1.2
-
m2/hr
http://www.planningplanet.com/print/book/export/html/422384
Units
11/3/2014
Page 3 of 100
Glazed Curtain Wall, Second Fix
-
1.1
-
m2/hr
High Quality Glazed Curtain Walling
-
25.0
-
m2/day
Holding Down Bolts Stanchion Bases stanchion.
Bolt 4 No Numbers -->
6 No
8 No
Make Softwood Framework
0.50
0.70
0.93
Fix Bolts / Framework
1.32
1.54
1.73
Strike Framework
0.38
0.44
0.49
Item
Metal Frameworks Roof Structure Structural Steel Structures
For medium sized applications with a single crane and fixing gang.
A typical rate
3.4 - 4.6 tonnes/day.
Structural steel for glazed wall, made of 18 no "bow string" strusses 25 m tall, cross braced and wired together, consisting of 69 tonnes of steelwork. Erection in 6 weeks.
Erection Rate
1.65 tonnes/day
Strucural steelwork for curved building roof, 18 number curved complex trussess and cross pearlins etc. Consisting of 500 tonnes of steel. Initially programmed for 14 weeks site installation period.
All Rates in Weeks...
GA drawings
0- 6
Shop Drawings
4 - 13
Buildings Dept Approval
14 - 17
Shop Fabrication
18 - 30
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 4 of 100
Corrosion Protection
22 - 32
Site Pre-Assembly
32 - 34
Erection Time
35 - 38 (24 hr working)
Erection Rate
8.95 tonnes/day
Structural steelwork for glazed wall and atria over, 4 number bow string trussess in wall and in roof. Consisting of 7.5 tonnes of steelwork. Erection in 6.5 weeks.
Erection Rate
0.23 tones/day
Timber Frameworks Roof Structure Usually carried out with a minimum of a 2 man gang, sometimes with an additional labourer. For a typical semi-detached house structure or similar...
Roof Trusses 1.28 no/hr
Wall Plates
2.76 m/hr
Rafters
1.17 m/hr
Ceiling Joists 32.10 m/hr
Timber frame superstructure Timber framing rates for hospital of 3173m2 GIFA Assuming that the labour is a 4 man squad working an 8 hour day as this would be normal practice • Wall panels up to 3m in hieght including both external and internal panels ; 30 panels per day (average panel 3.5m long) • Wall panels over 3m in height including both internal and external panels ; 20 panels per day (average panel 2.5m long) • Loose floor joists position and fix 175m sq per day • Loose floor joists position, fix & position and fix floor decking 125m sq per day • Floor/roof cassette assumed simple 12 X 2.4m 300m sq per day • Floor/roof cassette complex shape 150 – 200 m sq per day • Trussed roof erect, brace,sark and felt 100m sq per day (up to 8m span measured at horizantial) • Trussed roof erect, brace,sark and felt 80m sq per day (up to 12m span measured at horizantial)
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 5 of 100
• Hip or valley up to 12m long 1 man a day • Medium dormer window (2.4m wide) 1 man a day I hope this helps , but please bare in mind that the more complex projects will take longer. Timber Frames... Task / Description
Slow
Ave
Fast
Units
Roof Trusses
-
1.3
-
no/hr
Wall Plates
-
2.7
-
m/hr
Roof Rafters
-
1.2
-
m/hr
Ceiling Joists
-
32.1
-
m/hr
Roof Carcass, Common Rafters, under 3m
18.2
20.0
21.7
no/hr
Roof Carcass, Common Rafters, 3-6mm
13.3
16.6
18.2
no/hr
Roof Carcass, Common Rafters, over 6m
14.1
15.6
16.1
no/hr
Roof Carcass, Jack Rafters, under 3m
18.8
20.1
21.7
no/hr
Roof Carcass, Jack Rafters, 3-6mm
10.4
16.1
16.6
no/hr
Roof Carcass, Purlins, under 3m
5.1
5.4
5.8
no/hr
Roof Carcass, Purlins, 3-6mm
4.3
4.8
5.1
no/hr
Roof Carcass, Purlins, over 6m
3.5
4.3
4.6
no/hr
Roof Carcass, Binders, under 3m
5.7
6.6
7.6
no/hr
Roof Carcass, Binders, 3-6mm
2.1
2.3
2.5
no/hr
Roof Carcass, Binders, over 6m
1.3
1.5
1.6
no/hr
Roof Carcass, Hangers, under 3m
8.2
9.0
9.6
no/hr
Roof Carcass, Collars under 3m
7.6
8.0
9.1
no/hr
Roof Carcass, Collars 3-m
6.5
7.4
8.3
no/hr
12.0
13.1
15.3
no/hr
142.0
166.0
175.0
no/hr
Roof Soffits, Softwood, nailed
-
9.2
-
m/hr
Roof Soffits, Softwood, screwed
-
3.9
-
m/hr
Roof Soffits Asbestos, under 300mm nailed
-
9.1
-
m/hr
Roof Soffits Asbestos, under 300mm screwed
-
3.8
-
m/hr
Roof Soffits, Asbestos, over 300mm nailed
-
3.5
-
m/hr
Roof Soffits, Asbestos, over 300mm screwed
-
1.3
-
m/hr
Roof Facia Panels, Softwood
5.1
7.2
9.3
m/hr
Roof Facia Panels, Asbestos
1.3
2.5
3.9
m/hr
Roof Facia Panel Studding, nailed
7.3
8.1
9.0
m/hr
Roof Facia Panel Studding, screwed
4.6
5.2
5.8
m/hr
Roof Facia Panel Studding, bolted to beams
5.4
5.9
6.6
m/hr
Roof Works, Fix Herringbone Strutting
-
5.1
-
m/hr
Roof Works, Fix Firing Strips
-
25.0
-
m/hr
Roof Works, Fix Drip/Tilt Filleting
-
20.5
-
m/hr
Roof Carcass, Ridge Boards under 3m Roof Carcass, Cut Rafter Feet to line
Chases Chases
Cutting Chases In Brickwork In Brickwork (m/hr)
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 6 of 100
By Hand
Chase depth -->
0-25mm
25-37mm
37-50mm
Ne 25 mm wide
4.17
2.78
2.08
25-50 mm wide
3.45
2.27
1.69
50-75 mm wide
2.86
1.92
1.45
75-100 mm wide
2.50
1.67
1.23
Ne 25 mm wide
11.1
5.56
4.17
25-50 mm wide
6.67
4.55
3.33
50-75 mm wide
6.67
4.55
3.33
75-100 mm wide
5.00
3.33
2.50
Machine
Cutting Chases In Concrete In Concrete (m/hr) By Hand
Chase depth -->
0-25mm
25-37mm
37-50mm
Ne 25 mm wide
3.03
2.04
1.54
25-50 mm wide
2.50
1.67
1.25
50-75 mm wide
2.13
1.41
1.05
75-100 mm wide
1.82
1.22
0.92
Chase depth -->
0-25mm
25-37mm
37-50mm
Ne 25 mm wide
5.88
4.00
3.03
25-50 mm wide
5.00
3.33
2.50
50-75 mm wide
4.17
2.86
2.13
75-100 mm wide
3.70
2.44
1.81
Machine
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 7 of 100
Cutting Chases In Heavyweight Blockwork In Heavyweight Blockwork (m/hr) By Hand
Chase depth -->
0-25mm
25-37mm
37-50mm
Ne 25 mm wide
3.85
2.63
1.96
25-50 mm wide
3.23
2.17
1.64
50-75 mm wide
2.70
1.82
1.36
75-100 mm wide
2.33
1.56
1.18
Machine
Ne 25 mm wide
7.69
5.00
3.85
25-50 mm wide
6.25
4.17
3.13
50-75 mm wide
5.26
3.57
2.70
75-100 mm wide
4.55
3.13
2.33
Cutting Chases In Lightweight Blockwork In Lightweight Blockwork (m/hr) By Hand
Chase depth -->
0-25mm
25-37mm
37-50mm
Ne 25 mm wide
7.69
5.00
3.85
25-50 mm wide
6.25
4.17
3.13
50-75 mm wide
5.26
3.45
2.63
75-100 mm wide
4.55
3.03
2.27
Chase depth -->
0-25mm
25-37mm
37-50mm
Ne 25 mm wide
14.2
10.0
7.69
25-50 mm wide
11.1
7.69
5.88
50-75 mm wide
10.0
7.14
5.26
Machine
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 8 of 100
75-100 mm wide
9.09
6.25
4.76
Cutting Switch Boxes Cutting Switch Boxes etc (No/hr)
Box Type -->
Small
Large
Hand
7.14
3.57
Machine
12.5
5.56
Hand
6.67
4.17
Machine
12.5
6.25
Lightweight Blockwork Hand
Hand Machine
20.0 25.0
10.0 14.3
Heavyweight Blockwork Hand
Hand Machine
7.69 12.5
3.85 5.88
Concrete
Brickwork
Computer Room / Raised Floors Typically installed by a 2 man gang Medium sized room incl cutting 2.67 m2/hr
Concrete Related Works Formwork Beam Falsework Formwork Rates include for making, fixing, cleaning and minor repair works etc, rates in m2/hr. Soffits - On runners and props, including erection of props etc.
Hight of Beam Soffit---> Width
0 - 3.5 m
Fix
3.5 - 5.0 m
Strike
Fix
Strike
100 0.70 200 mm
1.23
0.58
1.02
200 0.81 300 mm
1.39
0.68
1.15
300 0.93 500 mm
1.54
0.78
1.28
500 1.16 750 mm
1.85
0.96
1.54
1.23
2.17
1.03
1.82
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 9 of 100
exc 750 mm
Soffits - On runners and props, on previously erected props etc.
Hight of 0 - 3.5 m Beam Soffit--->
3.5 - 5.0 m
Width
Strike
Fix
Strike
100 0.96 200 mm
1.69
0.91
1.67
200 1.11 300 mm
1.92
1.05
1.82
300 1.27 500 mm
2.08
1.20
2.00
500 1.56 750 mm
2.50
1.49
2.44
exc 750 1.64 mm
2.86
1.39
2.70
Fix
Sides - Strutted from soffit bearers etc.
Hight of 0 - 3.5 m Beam Soffit--->
3.5 - 5.0 m
Depth
Strike
Fix
Strike
100 0.78 200 mm
1.23
0.74
1.18
200 0.93 300 mm
1.39
0.88
1.32
300 1.06 500 mm
1.54
1.02
1.47
500 1.47 750 mm
2.08
1.39
2.00
exc 750 1.54 mm
2.33
1.47
2.33
Fix
Sides - Using clamps and struts etc. Hight of 0 - 3.5 m Beam Soffit--->
3.5 - 5.0 m
Depth
Strike
Fix
Strike
100 0.91 200 mm
1.47
0.87
1.39
200 1.09 300 mm
1.64
1.04
1.56
300 1.27 500 mm
1.82
1.20
1.72
Fix
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 10 of 100
Columns Formwork Rates include for fixing, cleaning and minor repair works etc, rates in m2/hr unless otherwise stated.
Cross Sectional Area-->
Ne 0.2 m2
Exc 0.2 m2
Item
Fix
Strike
Fix
Strike
KickersDirect to slab (no/hr)
4.00
12.50
2.63
8.33
KickersSuspended (no/hr)
2.08
12.50
1.39
8.33
Square Sides-Timber Clamped and Propped Column Height--> Item Cross Section
2-3m
Fix
3-4m
Strike
Fix
Strike
0.00 1.35 0.05 m2
2.70
1.67
3.57
1.69 0.05 0.10 m2
3.45
1.82
3.85
0.10 1.82 0.20 m2
4.00
2.33
4.55
2.04 0.20 0.40 m2
4.55
2.44
5.00
exc 2.33 0.40 m2
5.26
2.50
5.88
Footing formwork Activity
Labor (L) Helper (Mandays)
Material (M)
Material (M)
Material (M)
Sqm
0.8 Mandays/10Sqm
1.5 Mandays/10Sqm
MS Wall Form Panel - 1250 x 500 : 16Nos/10Sqm
Props 2m to 3m Long : 2 Nos/Rm
Shuttering Oil : 4Ltr/10Sqm
Footing Deshuttering & Sqm insitu Stacking
0.48 Mandays/10Sqm
0.9 Mandays/10Sqm
TASKS
Footing Footing Shuttering & formwork Providing Support
Task Labor (L) Carpenter UOM (Mandays)
Formwork & Falsework - Ground Foundation Formwork FORMWORK & FALSEWORK Ground Foundation Formwork All formwork rates in m2/hr.
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 11 of 100
Item
Shutter size
Fix
Strike
1.64
3.85
1.82
4.55
1.50 - 2.25 m2 2.00
5.00
2.25 - 3.00 m2 2.22
5.56
exc 3.00 m2
2.50
7.14
1.72
4.55
0.75 - 1.50 m2 1.82
4.55
1.50 - 3.00 m2 2.50
6.25
3.00 - 5.00 m2 2.63
6.67
2
To Pilecaps 0.75 m
0.75 - 1.50 m
2
To 0.75 m2 Foundations
To Ground Beams
2
1.82
4.55
1.50 - 3.00 m2 2.63
6.67
3.00 - 5.00 m2 2.70
7.14
1.50 m
Formwork Formwork Task / Description
Slow
Ave
Fast
Units
Pilecaps, < 0.7m2
0.9
1.6
2.0
m2/hr
Pilecaps, 0.7-2.5m2
1.6
2.0
2.3
m2/hr
Pilecaps, 2.5-3.0m2
2.0
2.3
2.5
m2/hr
Pilecaps, > 3.0m2
2.3
2.5
3.1
m2/hr
Ground Beams, < 0.7m2
1.1
1.7
1.8
m2/hr
Ground Beams, 0.7-1.5m2
1.7
1.8
2.5
m2/hr
Ground Beams, 1.5-3.0m2
1.8
2.5
2.6
m2/hr
Ground Beams, 3.0-5.0m2
2.5
2.6
3.5
m2/hr
Elevated Plain Slab Soffit
0.6
0.8
1.2
m2/hr
Beams, on erected falsework, width 100-200mm
0.9
1.0
1.1
m2/hr
Beams, on erected falsework, width 200-300mm
1.0
1.1
1.3
m2/hr
Beams, on erected falsework, width 300-500mm
1.2
1.3
1.5
m2/hr
Beams, on erected falsework, width 500-750mm
1.5
1.6
1.8
m2/hr
Beams, on erected falsework, width over 750mm
1.4
1.5
1.7
m2/hr
Walls, Construct Kickers
5.3
7.1
10.0
m2/hr
Walls, Fully Framed Formwork/Struts, 1.0-2.0m2
0.9
1.8
1.9
m2/hr
Walls, Fully Framed Formwork/Struts, 2.0-5.0m2
1.0
2.2
2.5
m2/hr
Walls, Fully Framed Formwork/Struts, over 5.0m2
1.2
2.5
2.9
m2/hr
Walls, StoriForm Shutters, 1.0-3.0m2
1.0
1.4
2.0
m2/hr
Walls, StoriForm Shutters, 3.0-5.0m2
1.9
2.3
3.3
m2/hr
Walls, StoriForm Shutters, 5.0-10.0m2
2.3
2.8
3.5
m2/hr
Walls, StoriForm Shutters, 10.0-15.0m2
3.2
4.5
4.0
m2/hr
Walls, StoriForm Shutters, over 15.0m2
3.8
4.8
5.4
m2/hr
Ground Slabs
1.0
1.5
1.8
m2/hr
Columns, Construct Kickers, direct to slab
3.2
4.1
5.4
no/hr
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 12 of 100
Columns, Construct Kickers, suspended from soffit slab
1.2
2.8
3.2
no/hr
Columns, Square Sides, Timber Clamp/Prop, csa < 0.1m2
1.3
1.6
1.8
m2/hr
Columns, Square Sides, Timber Clamp/Prop, csa 0.1-0.4m2
1.8
2.1
2.4
m2/hr
Columns, Square Sides, Timber Clamp/Prop, csa over 0.4m2
2.0
2.3
2.5
m2/hr
Columns, Square Sides, Steel Forms, 1.5 x 1.5 x 9.0m high
7.9
9.5
10.3
m2/hr
Columns, Square Sides, Steel Forms, 2.0 x 2.0 x 9.0m high
6.9
7.5
8.3
m2/hr
Columns, Square Sides, Steel Forms, 2.0 x 4.0 x 9.0m high
8.5
10.2
12.0
m2/hr
Columns, Round Sides, Sacrificial Plastic Mould, 3.0-4.0m dia
3.5
4.5
6.0
m2/hr
Columns, Round Sides, Steel Mould, 3.0-4.0m dia
5.2
6.5
7.5
m2/hr
Columns, Sloping Column Heads, extra over rate
-
2.5
3.5
hrs/no
Staircases, Stair Soffit, Sloping
0.7
0.8
1.0
m2/hr
Staircases, Stair Soffit, Flat Landing
0.8
0.9
1.2
m2/hr
Staircases, Wall Strings
0.4
0.6
-
m2/hr
Staircases, Open Strings
0.7
0.8
-
m2/hr
Staircases, Riser Boards fixed to strings
-
2.5
2.8
m2/hr
Staircases, Risers fixed to Strings
-
2.3
2.6
m2/hr
1.1
1.4
1.8
m2/hr
-
300.0
500.0
mm/hr
Table Form, Aluminum System, 400m2 bays
2.1
3.2
3.8
m2/hr
Table Form, H-Frame Steel Falsework, 400m2 bays
1.9
3.0
3.5
m2/hr
Tunnel Forms, Wall and Slab poured as one
-
15.6
17.5
m2/hr
Hollorib Decking, lay deck
-
43.5
47.5
m2/hr
Hollorib Decking, shear connecting studs
-
29.3
31.2
m2/hr
Stop Ends, no perforations
2.8
3.5
4.2
m2/hr
Stop Ends, minor perforations
1.2
1.5
1.9
m2/hr
Stop Ends, dense perforations
0.9
1.1
1.4
m2/hr
Box Outs, 0.01-0.05m2
7.6
8.2
9.1
no/hr
Box Outs, over 0.05m2
3.1
3.9
4.5
no/hr
Dummy Frames, under 3.0m2
4.5
6.2
7.1
no/hr
Dummy Frames, over 3.0m2
3.1
3.7
4.5
no/hr
Waffle Flooring, 2.4m grid Shaft Slip Forming
Formwork Re-Use Typical rate for number of formwork uses before shutter remake. NOTE: This varies significantly depending on care taken with shutters and programme time available etc. • Walls = 20 uses • Slab Soffits = 10 - 15 uses • Beam & Column Boxes = 30 uses
Hollorib Decking Hollorib Decking Lay decking = 350 m2/day Shear Connecting Studs 235 m2 studded per day per gun (4,000 studs/week) Concrete topping = 4,000 m2/week or 2,000 m2/week incl power floating
Raft formwork
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 13 of 100
Activity
Task Labor (L) Carpenter UOM (Mandays)
Labor (L) Helper (Mandays)
Material (M)
Material (M)
Material (M)
Sqm
0.71 Mandays/10Sqm
1.41 Mandays/10Sqm
MS Wall Form Panel - 1250 x 500 : 16Nos/10Sqm
Props 2m to 3m Long : 2 Nos/Rm
Shuttering Oil : 4Ltr/10Sqm
Raft Deshuttering & Sqm insitu Stacking
0.42 Mandays/10Sqm
0.84 Mandays/10Sqm
TASKS
Raft Raft Shuttering & formwork Providing Support
Ramp formwork
Activity
Ramp formwork
TASKS
Task - UOM
Ramp Shuttering & Sqm Providing Support
Ramp Deshuttering & Stacking Sqm Appropriately at Same Location
Labor (L) Carpenter (Mandays)
Labor (L) Helper (Mandays)
Material (M)
Material (M)
Material (M)
Adjustable Props 2.02m to MS Floor Form MS Floor 3.75 m : 0.22 0.44 Panel - 750 x Form Panel 2Nos/Sqm Mandays/Sqm Mandays/Sqm 600 1250 x 500 : and 13.3Nos/10Sqm 6.4Nos/10Sqm Shuttering Oil : 5Ltr/10Sqm
0.13 0.26 Mandays/Sqm Mandays/Sqm
Shades Formwork
Activity
TASKS
Shades Formwork
Weather Shade, Chajjas, Corbels Shuttering (Including Propping)
Task - UOM
Labor (L) Carpenter (Mandays)
Labor (L) Helper (Mandays)
Sqm
Adjustable MS Floor Props 0.12 0.14 Form Panel 2.02m to Mandays/Sqm Mandays/Sqm 750 x 600 3.75 m : 2.2Nos/Sqm 2Nos/Sqm
http://www.planningplanet.com/print/book/export/html/422384
Material (M)
Material (M)
Material (M)
Shuttering Oil : 0.3Ltr/Sqm
11/3/2014
Page 14 of 100
Weather Sqm Shade, Chajjas, Corbels Deshuttering & Stacking Appropriately at Same Location
0.07 0.08 Mandays/Sqm Mandays/Sqm
Staircase formwork Task Labor (L) Carpenter UOM (Mandays)
Activity
TASKS
Staircase formwork
Staircase (Excluding Spiral Staircase) Shuttering & Providing Support
Sqm
Staircase (Excluding Spiral Staircase) Deshuttering & Stacking Appropriately at Same Location
Sqm
Labor (L) Helper (Mandays)
Material (M)
0.23 Mandays/Sqm
0.46 Mandays/Sqm
Adjustable MS Floor Form Props Panel - 750 x 2.02m to 600 3.75 m : 2.2Nos/Sqm 2Nos/Sqm
0.14 Mandays/Sqm
0.28 Mandays/Sqm
Material (M)
Material (M)
Shuttering Oil : 5Ltr/10Sqm
Tunnel Forms Concrete - Tunnel Forms A system of forms which enables walls and slabs to be cast in the same pour. suited to buildings with large number of identically sized rooms, such as hotels or flats. Used in conjunction with high speed concrete pumps, pre-formed reinforced cages. Rates Setup
14 days
Slab & Walls 125 m2/day (equals 3.5 rooms) Dismantle
7 days
Waffle Flooring Rate includes for erection of decking and infill beams, cut position & nail plywood ribs, transport position and fix 800 mm x 800 mm waffle forms, clean and oil plywood and adjust to levels (m2/hr). Conservative Erection Rate... • 2.4 m grid, ne 3.5 m high soffit = 1.42 m2/hr • 3.5 - 5.5 m high soffit = 1.13 m2.hr Typical composite rate of 18.5 m2/day per 4 man gang. Rate includes decking, waffles and reinforcement fixing.
Walls formwork
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 15 of 100
Activity
TASKS
Task Labor (L) Carpenter UOM (Mandays)
Walls (Any Thickness), Including Walls Buttresses formwork Shuttering & Providing Support - Up to 3.5m Height
Walls Deshuttering & insitu Stacking
Labor (L) Helper (Mandays)
Sqm
2.22 Mandays/10Sqm (Including Both Sides)
2.64 Mandays/10Sqm (Including Both Sides)
Sqm
1.32 Mandays/10Sqm (Including Both Sides)
1.76 Mandays/10Sqm (Including Both Sides)
Material (M)
Material (M)
MS Wall Form Panel - 1250 x 500 - 32 Nos/10Sqm (Including Both Sides)
Props - 2m to 3m Long : 4Nos/Rm (Including Both Sides)
Material (M)
Shuttering Oil : 5Ltr/10Sqm (On One Side)
Making Good Concrete Rates including blowing out, preparations, clean and shutter joints and making a fair faced finish. By Hand
With Mechanical Sander
Walls
5.56 m2/hr
8.62 m2/hr
Columns
2.80 m2/hr
6.99 m2/hr
Sides and Soffits of Beams
2.80 m2/hr
6.99 m2/hr
Soffits of Slabs
4.21 m2/hr
7.58 m2/hr
Vertical Bolt Holes
16.67 no/hr
Horizontal Bolt Holes
14.49 no/hr
Vertical 28.57 Shutter Joints m/hr Horizontal 25.00 Shutter Joints m/hr Rub Down Precast Concrete
16.95 m2/hr
Scabble Single head brush hammer
0 - 4 mm 30.74 hrs/m2
Three head brush hammer
0 - 4 mm 37.14 hrs/m2
0 - 8 mm 59.14 hrs/m2
0 - 8 mm
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 16 of 100
71.12 hrs/m2
Mixing Concrete Mixing By Hand A typical rate of 0.32 m3/hr of concrete. Compulsory Paddle Mixer Generally with one or two 3.5m3 drums, giving a cycle time of 60 to 80 seconds (m3/Hr). Mix Time -->
60 secs
80 secs
Single drum plant
210
158
Double drum 420 plant
315
Task / Description
Slow
Ave
Fast
Units
Concrete Weight, 1m3
-
2.4
-
Tonnes
Readymix Lorry, Length
-
8.3
-
m
Readymix Lorry, Width
-
2.5
-
m
Readymix Lorry, Height
-
3.7
-
m
Readymix Lorry, Length
-
24.4
-
Tonnes
Readymix Lorry, Turning Circle
-
16.4
-
m
Readymix Lorry, Allowable Access Ramp Gradient
-
17.0
20.0
Mixing Concrete, By Hand
-
0.3
-
m3/hr
Mixing Concrete, Single Drum Paddle Mixer
158.0
180.0
210.0
m3/hr
Mixing Concrete, Double Drum Paddle Mixer
315.0
370.0
420.0
m3/hr
Mixing Concrete, Single Drum Plant Pan Mixer
-
120.0
-
m3/hr
Mixing Concrete, Dry Mix Plant
-
90.0
-
m3/hr
degrees
CONCRETING Properties 1 m3 of concrete weights 2.4 tonnes Skip Capacities Dual Flow Skips Skip Size
Qty Per Lift
Laiden Weight
0.50 m3
0.44 m3
1,261 kg
0.75 m3
0.68 m3
1,850 kg
3
3
2,585 kg
1.00 m
0.94 m
Rollover Skips, Front discharge Skip Size
Qty Per Lift
Laiden Weight
0.50 m3
0.44 m3
1,361 kg
0.75 m3
0.68 m3
2,057 kg
Readymix Lorries - Length
8.23 m
- Width
2.43 m
- Height
3.66 m
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 17 of 100
- Weight
24.38 tonnes
- Turning Circle
16.36 m
Dry Lean Concrete From readymix truck and spade finish (m3/hr). Roads and Runway Areas
1.39
Paths
0.57
Drains, tipped direct
0.85
Drains, thrown in
0.68
Placement & Finishing Concrete Cycle Times Blinding Concrete Placing blinding direct from ready mix truck, rate of 4-5 m2/hr or 0.2-0.3 m3/hr. Base / Floor Slabs Concourse slab concrete pour, 36 m x 18 m, concrete volume of 1,500 m3 and 290 tonnes of reinforcement. Blind 1 day, formwork 2 days, reinforcement 5 days and concrete on day 8. Adit base slabs, concrete volume of 140 m3. Steelfixing for 4 days and concrete on the 5th day. Tunnel Sections Simple cooling watermain tunnels, a typical cycle time of 5 days per 8 m sections, or a rate of 0.16 m/hr. Track Slab Track slab concrete pour, 36 m x 28 m, concrete volume of 1,050 m3 and 360 tonnes of reinforcement. Excavate 6 m from one edge 7 days, strut 9 days, final excavation 3 days, pile chipping 5 days, blind 4 days, reinforcement 5 days and concrete on day 32. On simple pours, with little formwork, 24 m x 28 m, concrete volume of 1,200 m3 and 220 tonnes of reinforcement. Blind 3 days, reinforcement 3 days and concrete on day 8. Wall Slabs Adit wall construction, concrete volume of 80 m3. Steelfixing for 3 days and concrete on 4th day. Roof Slabs Adit roof slab construction, concrete volume of 80 m3. Steelfixing for 4 - 5 days and concrete on the 6th day. Staircases Standard staircase, concrete volume of 60 - 80 m3. Steelfixing for 4 days, formwork for 3 days and concrete on the 7 th day. Simple staircase from track slab up to platform edge, a rise of 1.2 m, a typical cycle time of 3 days per flight.
Slip Forming Concrete - Slip Forming A typical period of 10 - 14 days is required to setup the shutter on the ground and cast the platform. Rate of climb of formwork = 200 - 300 mm/hr.
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 18 of 100
Table Forms Concrete - Table Forms Fast method of forming walls/slabs with movable shutter. This rate is inclusive of walls and columns etc. Rate of 100 - 150 m2/day
Concrete Finishing Concrete Finishing Task / Description
Slow
Ave
Fast
Units
Surface Finishing, Steel Float By Hand
9.2
13.9
25.0
m2/hr
Surface Finishing, Wood Float By Hand
11.7
17.2
29.4
m2/hr
Surface Finishing, Power Float
13.9
20.8
37.0
m2/hr
Surface Finishing, Light Brush on Trowel
55.8
90.1
170.0
m2/hr
Surface Finishing, Brush on Trowel Margin
28.8
48.5
85.0
m2/hr
Surface Finishing, Sprayed By Pump, expose aggregate
65.0
95.0
145.0
m2/hr
Surface Finishing, Wire Brush, expose aggregate
15.0
25.0
30.0
m2/hr
Making Good Walls, prepare, shutter, pour
-
5.5
8.6
m2/hr
Making Good Columns, prepare, shutter, pour
-
2.8
6.9
m2/hr
Making Good Sides of Beams, prepare, shutter, pour
-
2.8
7.0
m2/hr
Making Good Slab Soffits, prepare, shutter, pour
-
4.2
5.5
m2/hr
14.8
16.8
25.8
no/hr
-
18.0
-
m2/hr
30.7
59.5
73.8
Making Good Bolt Holes, prepare, shutter, pour Making Good Rubdown Precast Concrete, prepare, shutter, pour Making Good Scabble 3 head brush hammer, prepare, shutter, pour
hrs/m2
Concrete Finishes (m2/hr). Area Finished -->
0-40 m2
40-200 m2
exc 200 m2
Steel Float by Hand
9.26
13.89
25.00
Wood Float 11.76 by Hand
17.24
29.41
Power Float
13.89
20.83
37.04
Light Brush 55.56 on Trowel
90.91
166.67
Brush on Trowel Margin
27.78
45.45
83.33
Sprayed 55.56 using hand pump
90.91
142.86
Wire 6.99 Brush, expose agg
11.76
20.83
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 19 of 100
Concrete Pumping Large Concrete Pours, lorry pump. Simple Rule Of Thumb, concretors 0.5 - 1.0 hrs/m3 of concrete, depending on access, pour size and concrete availability. Base Slabs etc, 1,200m3 equalling 25 - 35m3/hr per pump, with 3 No pumps and 12 men for 2 shifts of 12 hrs.
OFC Laying OFC Laying By Using Concrete/Road Cutter Equipment Resources • • • • •
Survey Team of 4 (1 Suveyor , 3 Assistants) Equipment with Operator and Helper Cutting Line Marking team ( 2-3 Persons) OFC cable laying team ( 4 Persons) Splicing team (2 technicians )
Productivity if everything is planned properly with adequate overlap of 3-4 days. 400-500m/day can be achieved. By using trenching machine • • • •
Equipment with Operator and helper Mini Dozer with operator OFC Laying laying team (6-8 persons) Rest resources as per above
Productivity If everything has planned properly with adequate overlap of 2-3 days. 250-300m/day can be achieved.
Place Concrete Barrowing Concrete (m3/hr). Receive concrete from mixer/lorry direct to barrow, wheel to placing position, tip and return. Distance
0 - 10 m
2.32
10 - 20 m
1.81
20 - 50 m
1.08
As above but including load concrete from deck/tray. Distance
0 - 10 m
0.99
10 - 20 m
0.87
20 - 50 m
0.66
Extra over to place direct, for dump and shovel in from side, a typical rate of 0.26 hrs/m3.Direct From Ready Mix Lorry (m3/hr). Type
Ready Mix
Via Dumper
Via Dumper
Tip Direct
Tip Direct
Thrown In
Mass Fill
3.12
2.56
1.49
50mm Blinding
1.27
1.06
0.82
Ground Beams ne 0.1 m2 SA
1.52
1.30
1.00
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 20 of 100
Ground Beams ex 0.1 m2 SA
1.69
1.49
1.16
Pile Caps ne 0.1 m2 SA
1.16
1.06
0.79
Pile Caps ex 0.1 m2 SA
2.56
2.13
7.69
Duct Walls
0.78
0.71
0.52
Stub Columns
0.43
0.39
0.29
Ground Slab ne 155 mm
2.13
1.82
1.22
Ground Slab 150300 mm
2.33
1.96
1.27
Ground Slab 300500 mm
2.56
2.13
1.35
Drains, Bed 0.91 & Cover
0.85
0.73
By Lorry Mounted Concrete Pump (m3/hr). Thickness 13.5 m3/hr -->
18 m3/hr
ne 100 mm
2.17
2.63
100 - 150 2.44 mm
2.94
150 - 200 2.63 mm
3.23
200 - 300 2.86 mm
3.45
300 - 500 3.23 mm
3.85
1.64
1.82
0.5 - 0.10 1.59 m2
1.59
exc 0.10 m2
1.82
1.82
ne 150 mm
1.61
1.89
150 - 225 1.89 mm
2.33
exc 225 mm
2.56
3.23
Independent Beams
1.54
1.54
Stairs and Landings
1.27
1.89
Solid Slabs
Coffered Slabs Columns
Wall
By Dumper, From Ready Mix Lorry To Position (m3/hr). Dumper 0.6 m3 Capacity -->
0.8 m3
1.2 m3
1.5 m3
2.3 m3
0 - 20 m
14.08
18.82
25.00
33.33
10.41
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 21 of 100
20 - 50 m
9.09
12.36
16.39
22.22
29.41
50 - 100 m
7.29
10.41
13.88
18.86
25.00
100 250 m
5.78
7.87
10.00
13.51
18.18
250 500 m
3.65
4.95
8.33
8.95
12.35
500 750 m
2.16
2.92
4.27
5.43
7.87
750 1,000 m
-
-
-
3.97
5.78
By Tower/Mobile Crane (m3/hr). 0.4 m 0.6 Skip m Skip
0.8 m Skip
Pile Caps
SA ne 2 1.19 m2
1.39
1.61
Mass Fill Pours
SA 2-5 m3
1.75
2.04
2.33
ne 10 m3
3.70
4.17
4.76
10-25 m3
4.00
4.55
0.84
exc 25 m3
4.35
5.00
5.86
ne 100 mm
0.90
1.09
1.21
100-150 1.09 mm
1.31
1.47
150-200 1.26 mm
1.53
1.69
200-300 1.26 mm
1.53
1.69
Exc 300 1.38 mm
1.66
1.85
Trough & Coffered Slabs
0.95
1.09
1.21
Structural Topping ne 100 mm
0.90
1.09
1.25
Stairs & Landings
0.64
0.64
0.64
Slabs
Blinding
ne 150 mm
0.88
1.00
1.10
Beams
SA 0-0.05 m
0.52
0.58
0.69
SA 0.58 0.05-0.1 m
0.65
0.78
SA ex 0.1 m
0.76
0.85
1.02
ne 100 mm
0.64
0.76
0.88
Walls
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 22 of 100
Columns
100-150 0.76 mm
0.92
1.05
150-300 0.95 mm
1.11
1.28
exc 300 mm
1.10
1.28
1.47
SA ne 0.05 m2
0.43
0.45
0.48
0.48 SA 0.05-0.1 m2
0.50
0.54
SA ex 0.1 m2
0.53
0.57
0.51
Concrete Placement Task / Description
Slow
Ave
Fast
Units
Placing concrete, lorry based pump
30.0
40.0
50.0
m3/hr
Hollorib Decking, concrete topping
85.0
100.0
120.0
m2/hr
Hollorib Decking, concrete topping, incl PowerFloat
40.0
50.0
70.0
m2/hr
Placing Concrete, By Wheelbarrow over 1-10m
2.1
2.3
2.5
m3/hr
Placing Concrete, By Wheelbarrow over 10-20m
1.5
1.8
2.1
m3/hr
Placing Concrete, By Wheelbarrow over 20-50m
0.8
1.1
1.5
m3/hr
Placing Direct From Readymix Lorry, Mass Fill
2.8
3.1
3.3
m3/hr
Placing Direct From Readymix Lorry, 50mm Blinding
-
1.3
1.6
m3/hr
Placing Direct From Readymix Lorry, Ground Beams
1.5
-
1.7
m3/hr
Placing Direct From Readymix Lorry, Pile Caps
1.0
1.5
2.3
m3/hr
Placing Direct From Readymix Lorry, Duct Walls
-
0.8
1.1
m3/hr
Placing Direct From Readymix Lorry, Stub Columns
-
0.4
0.6
m3/hr
2.1
2.3
2.6
m3/hr
-
0.9
1.0
m3/hr
Placing From Tower Crane, Pile Caps
1.2
1.4
1.6
m3/hr
Placing From Tower Crane, Mass Fill
4.0
4.5
5.5
m3/hr
Placing From Tower Crane, Slabs under 150mm thick
0.9
1.3
1.7
m3/hr
Placing From Tower Crane, Slabs over 150mm thick
1.2
1.5
1.8
m3/hr
Placing From Tower Crane, Trough/Coffered Slabs
0.9
1.1
1.2
m3/hr
Placing From Tower Crane, Stairs and Landings
0.6
0.7
0.9
m3/hr
Placing Direct From Readymix Lorry, Ground Slab Placing Direct From Readymix Lorry,Drains Bed and Cover
Placing From Tower Crane, Blinding
0.8
1.0
1.1
m3/hr
Placing From Tower Crane, Beams under 150mm thick
0.5
0.6
0.8
m3/hr
Placing From Tower Crane, Beams over 150mm thick
0.6
0.8
1.0
m3/hr
Placing From Tower Crane, Walls
0.6
1.1
1.5
m3/hr
Placing From Tower Crane, Columns
0.4
0.5
0.6
m3/hr
Post Tensioning Works Post Tensioning Concrete - Post Tensioning Sequence: • Concrete poured 1st Bay. • After 48 hrs concrete is stressed to initial strength (15 kN takes 1 day). • 5 days after initial stressing, concrete is stressed to final strength (30 kN takes 1 day).
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 23 of 100
• Formwork may now be struck and adjacent bay poured. Post Tensioning Task / Description
Slow
Ave
Fast
Units
Lag for Initial Stress Tensioning after 1st bay cast
-
48.0
-
hrs
Lag for Final Stress Tensioning after Initial Stress
-
120.0
-
hrs
Pre-Cast Works PRECAST CONCRETE FLOOR SYSTEMS Plank Elements (crane handled) Rates given in hours/plank.
Plank ne 3m Lengths
3-6m
ex 6m
Unload/stack at ground level
0.016
0.019
0.022
Unload/stack upper levels
0.021
0.024
0.028
Sling from ground to levels
0.019
0.021
0.025
Place in position from stack
0.120
0.150
0.180
Activity
Block Elements Rates given in hours/thousand blocks.
Block 75125ex Thickness 125mm 200mm 200mm Activity Unload By pallets/stack forklift on ground By Crane
0.90
1.02
1.20
1.20
1.26
1.38
Unload By pallets/stack forklift at upper By levels Crane
1.50
1.62
1.80
2.34
2.40
2.70
Sling from ground to levels
By forklift
1.44
1.56
1.74
By Crane
1.56
1.62
1.80
12.00
13.80
15.00
Place in position from stacks
Reinforcement Footing Reinforcement
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 24 of 100
Activity
Task L Barbender/Fitter UOM (Mandays)
TASKS
Foot Rein - Placing in Position & Footing Binding - Using Mt Reinforcement TMT Bars, Mild Steel, Tor Steel
L - Helper (Mandays)
M
0.28 Mandays/0.1Mt
Bars 0.38 Include Mandays/0.1Mt 5% Wastage
Bars 0.28 Include Mandays/0.1Mt 5% Wastage
Bars 0.32 Include Mandays/0.1Mt 5% Wastage
Foot Rein Straightening, Cutting (With Machine Cutting), bending - Using TMT Bars, Mild Steel, Tor Steel
Mt
0.2 Mandays/0.1Mt
Foot Rein Straightening, Cutting (With Manual Cutting), bending - Using TMT Bars, Mild Steel, Tor Steel
Mt
0.29 Mandays/0.1Mt
M
M
Binding Wire : 5 kg/0.1Mt
Cover Blocks 10No/0.1Mt
Reinforcement Mesh reinforcement - to slabs = 10.5 m2/hr Mesh reinformcement - to beams/columns = 2.5 m2/hr Reinforcement Task / Description
Slow
Ave
Fast
Units
Slabs/Foundations, steelfixing, 6mm
40.3
38.4
36.5
hrs/tonne
Slabs/Foundations, steelfixing, 8mm
28.2
26.9
25.8
hrs/tonne
Slabs/Foundations, steelfixing, 10mm
22.5
20.6
20.1
hrs/tonne
Slabs/Foundations, steelfixing, 12mm
16.9
16.3
15.4
hrs/tonne
Slabs/Foundations, steelfixing, 16mm
12.0
11.5
10.9
hrs/tonne
Slabs/Foundations, steelfixing, 20mm
9.2
8.6
8.2
hrs/tonne
Slabs/Foundations, steelfixing, 25mm
6.9
6.7
6.5
hrs/tonne
Slabs/Foundations, steelfixing, 32mm
5.7
5.5
5.2
hrs/tonne
Slabs/Foundations, steelfixing, 40mm
5.3
5.1
4.9
hrs/tonne
Slabs/Foundations, steelfixing, 50mm
5.2
4.9
4.6
hrs/tonne
Beams/Columns, steelfixing, 6mm
55.4
52.8
50.6
hrs/tonne
Beams/Columns, steelfixing, 8mm
38.8
37.0
35.1
hrs/tonne
Beams/Columns, steelfixing, 10mm
29.5
28.4
26.9
hrs/tonne
Beams/Columns, steelfixing, 12mm
23.4
22.4
21.9
hrs/tonne
Beams/Columns, steelfixing, 16mm
16.6
15.8
15.1
hrs/tonne
Beams/Columns, steelfixing, 20mm
12.4
11.9
11.3
hrs/tonne
Beams/Columns, steelfixing, 25mm
9.9
9.2
8.7
hrs/tonne
Beams/Columns, steelfixing, 32mm
6.8
6.6
6.2
hrs/tonne
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 25 of 100
Beams/Columns, steelfixing, 40mm
6.1
5.9
5.6
hrs/tonne
Beams/Columns, steelfixing, 50mm
6.1
5.9
5.6
hrs/tonne
Walls, steelfixing, 6mm
41.2
40.8
39.1
hrs/tonne
Walls, steelfixing, 8mm
29.2
28.6
27.4
hrs/tonne
Walls, steelfixing, 10mm
22.7
22.0
21.2
hrs/tonne
Walls, steelfixing, 12mm
17.6
17.3
16.9
hrs/tonne
Walls, steelfixing, 16mm
12.4
12.2
11.8
hrs/tonne
Walls, steelfixing, 20mm
9.4
9.2
8.7
hrs/tonne
Walls, steelfixing, 25mm
7.4
7.2
7.0
hrs/tonne
Walls, steelfixing, 32mm
7.0
6.8
6.4
hrs/tonne
Walls, steelfixing, 40mm
6.4
6.1
5.9
hrs/tonne
Walls, steelfixing, 50mm
5.3
5.1
4.8
hrs/tonne
Staircases, steelfixing, 6mm
48.9
48.0
45.5
hrs/tonne
Staircases, steelfixing, 8mm
34.4
33.6
31.9
hrs/tonne
Staircases, steelfixing, 10mm
26.6
25.8
24.3
hrs/tonne
Staircases, steelfixing, 12mm
20.9
20.4
19.5
hrs/tonne
Staircases, steelfixing, 16mm
14.6
14.4
13.8
hrs/tonne
Staircases, steelfixing, 20mm
11.3
10.8
10.5
hrs/tonne
Staircases, steelfixing, 25mm
8.6
8.4
8.2
hrs/tonne
Reinforcement Ratios Reinforcement Ratios Task / Description
Slow
Ave
Fast
Units
Pile Cap, Concrete m3 x Ratio = Rebar Tonnes
-
14.8
-
% ratio
Base Slab, Concrete m3 x Ratio = Rebar Tonnes
-
13.2
14.1
% ratio
Suspended Slab, Concrete m3 x Ratio = Rebar Tonnes
-
20.6
25.6
% ratio
Platform Slab, Concrete m3 x Ratio = Rebar Tonnes
-
15.6
-
% ratio
Columns, Concrete m3 x Ratio = Rebar Tonnes
15.8
18.7
28.7
% ratio
Walls, Concrete m3 x Ratio = Rebar Tonnes
14.7
15.0
-
% ratio
M
M
M
Binding Wire : 5 kg/0.1Mt
Cover Blocks 10No/0.1Mt
Staircase Reinforcement
Activity
TASKS
Staircase Rein Placing in Position Staircase & Binding - Using Reinforcement TMT Bars, Mild Steel, Tor Steel
Task L Barbender/Fitter UOM (Mandays)
Mt
0.32 Mandays/0.1Mt
L - Helper (Mandays)
Bars 0.34 Include Mandays/0.1Mt 5% Wastage
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 26 of 100
Staircase Rein Straightening, Cutting (With Machine Cutting), bending - Using TMT Bars, Mild Steel, Tor Steel.
Staircase ReinStraightening, Cutting (With Manual Cutting), bending - Using TMT Bars, Mild Steel, Tor Steel.
Mt
Mt
0.2 Mandays/0.1Mt
0.29 Mandays/0.1Mt
0.28 Bars Mandays/0.1Mt Include 5% Wastage
Bars 0.32 Include Mandays/0.1Mt 5% Wastage
Walls Reinforcement
Activity
TASKS
Walls Rein Placing in Position Walls & Binding - Using Reinforcement TMT Bars, Mild Steel, Tor Steel
Task L Barbender/Fitter UOM (Mandays)
L - Helper (Mandays)
M
Mt
0.41 Mandays/0.1Mt
Bars 0.45 Include Mandays/0.1Mt 5% Wastage
Walls Rein Straightening, Cutting (With Machine Cutting), bending - Using TMT Bars, Mild Steel, Tor Steel.
Mt
0.2 Mandays/0.1Mt
Bars 0.28 Include Mandays/0.1Mt 5% Wastage
Walls Rein Straightening, Cutting (With Manual Cutting), bending - Using TMT Bars, Mild Steel, Tor Steel.
Mt
0.39 Mandays/0.1Mt
Bars 0.43 Include Mandays/0.1Mt 5% Wastage
Mt
0.47 Mandays/0.1Mt
Bars 0.5 Include Mandays/0.1Mt 5% Wastage
Mt
0.55 Mandays/0.1Mt
Bars 0.57 Include Mandays/0.1Mt 5% Wastage
Walls Rein Stirrups Cutting and Bending
Walls Rein Stirrups Teing
M
M
Binding Wire : 5 kg/0.1Mt
Cover Blocks 10No/0.1Mt
Decking
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 27 of 100
Decking Task / Description
Slow
Ave
Fast
-
7.1
-
Simple Universal Beam Steel Bridge, concrete bridge deck, grano cover
Units
m/day
Demolition & Break Out Breaking Out & Openings Breaking Out Concrete And Remove (hrs/m3)
Slabs - unreinforced
Slabs - reinforced
Walls - unreinforced
Depth
Hand Machine
Ne 50 mm
2.35
1.96
50 - 100 mm
3.15
2.46
100 - 200 mm 3.75
3.94
200 - 300 mm 4.12
5.55
Ne 50 mm
4.71
3.92
50 - 100 mm
5.52
4.32
100 - 200 mm 5.88
4.71
200 - 300 mm 6.12
9.09
all walls
3.04
4.71
Walls - reinforced
all walls
5.52
3.92
Beams - reinforced
all sizes
7.50
5.89
Columns - reinforced
all sizes
9.20
7.30
Foundations - unreinforced all sizes
3.60
3.00
Foundations - reinforced
5.40
4.80
all sizes
Breaking Out Tarmac Rates include for breaking out and removal of rubble (hrs/m3).
Pavings
Depth
Hand Machine
Ne 50 mm
1.96
1.56
50-100 mm
2.08
1.64
100-150 mm 2.17
1.75
Roadways upto 150 mm
3.57
Breaking Out Brickwork Rates include for breaking out and removal of rubble (hrs/m3). Depth
Hand Machine
Walls/columns Ne 100 mm 2.40
1.38
exc 100 mm 2.75
1.57
all sizes
1.57
Foundation
2.75
Breaking Diaphragm Wall
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 28 of 100
Breaking Openings using coring machine 0.2m3/hour Breaking out to expose couplers using hand held braker 1.75m2/day ot 2.5m run/day (0.7m slab)
Task / Description
Slow
Ave
Fast
Units
Concrete Slabs, unreinforced 50-150mm
3.2
-
1.9
hrs/m3
Concrete Slabs, unreinforced 150-300mm
5.5
4.1
3.7
hrs/m3
Concrete Slabs, reinforced 50-150mm
5.2
-
3.9
hrs/m3
Concrete Slabs, reinforced 150-300mm
9.1
6.2
4.7
hrs/m3
Concrete Walls, unreinforced
4.7
3.9
3.1
hrs/m3
Concrete Walls, reinforced
5.6
4.7
3.9
hrs/m3
Concrete Foundations, unreinforced
3.6
3.3
3.0
hrs/m3
Concrete Foundations, reinforced
5.4
5.1
4.8
hrs/m3
Concrete Beams
7.5
6.5
5.6
hrs/m3
Concrete Columns
9.2
8.2
7.3
hrs/m3
Tarmac paving 20-50mm thick
1.9
1.7
1.5
hrs/m3
Tarmac paving 50-100mm thick
2.1
-
1.6
hrs/m3
Tarmac paving 100-150mm thick
2.1
-
1.7
hrs/m3
Tarmac roadway 150mm thick
-
3.6
-
hrs/m3
Brickwork, walls and columns
2.4
1.8
1.3
hrs/m3
Brickwork, foundations
2.7
2.1
1.5
hrs/m3
Cutting Holes Cutting Holes in concrete by Hand (no/hr
Hole depth (mm) --> 0-75 75-125 125-250 250-375 375-500
Ne 50 cm2
2.94 1.85
1.75
-
-
50-100 cm2
2.22 1.39
1.32
-
-
100-150 cm2
1.67 1.11
1.05
-
-
250-500 cm2
1.28 0.88
0.83
-
-
Cutting Holes in concrete by Machine (no/hr)
Hole depth (mm) --> 0-75 75-125 125-250 250-375 375-500
Ne 50 cm2
-
-
5.88
5.00
4.55
50-100 cm2
-
-
4.00
3.45
3.03
100-150 cm2
-
-
2.50
2.17
1.92
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 29 of 100
150-250 cm2
-
-
1.67
1.45
1.28
250-500 cm2
Common Brickwork Common Brickwork, by Machine (no/hr) Hole depth (mm) --> 0-75 75-125 125-250 250-375 375-500 Ne 100 cm2
-
16.6
7.69
5.26
4.00
100-250 cm2
-
12.5
5.88
4.00
2.94
250-500 cm2
-
10.0
5.00
3.33
2.50
500-100 cm2
-
8.33
4.17
2.78
2.08
Common Brickwork, by Hand (no/hr) Hole depth (mm) --> 0-75 75-125 125-250 250-375 375-500 Ne 100 cm2
11.1 8.33
5.56
3.85
-
100-250 cm2
9.09 7.14
4.55
3.23
-
250-500 cm2
7.69 5.88
3.85
2.70
-
500-100 cm2
6.67 4.76
3.23
2.27
-
Cutting Back Cutting Back Concrete Cutting Piles For Pile Caps, Using Breaker & Air Tools Providing A Rough Finish (hrs/pile)
Pile Diameter-->
0.35m 0.5m 0.6m 0.79m 0.94m 1.1m 2.2m
0 - 100mm high
0.32
0.44 0.63 0.93
1.38
1.74
8.10
100-200mm high
0.39
0.56 0.81 1.22
1.83
2.16
8.58
200-300mm high
0.44
0.64 0.94 1.45
1.92
2.34
9.00
300-500mm high
0.49
0.72 1.07 1.65
2.10
2.50
9.50
500-750mm high
0.68
1.02 1.54 2.16
2.55
2.55 10.01
750-1000mm high 0.83
1.32 1.78 2.36
3.37
4.20 10.52
Providing A Neat Finish (hrs/pile)
Pile Diameter-->
0.35m 0.5m 0.6m 0.79m 0.94m 1.1m 2.2m
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 30 of 100
0 - 100 mm high
-
0.63 0.90 1.32
1.93
2.25
9.72
100-200 mm high
-
0.76 1.11 1.65
2.39
2.81 10.29
200-300 mm high
-
0.85 1.25 1.93
2.49
3.04 10.85
300-500 mm high
-
1.05 1.59 2.38
2.73
3.25 11.40
500-750 mm high
-
1.41 2.13 2.97
3.45
4.30 12.01
750-1000mm high -
2.07 2.79 3.72
4.38
5.43 12.62
Cut Concrete Slabs Using Trolley Type Clipper Saw (m/hr)
Ne 25 mm deep 15.2
25-50 mm deep 11.5
50-75 mm deep 6.67
Cutting Back Task / Description
Slow
Ave
Fast
Units
Concrete Pile Caps, 50-300mm deep and 0.6m dia
0.6
-
0.3
hrs/no
Concrete Pile Caps, 300-750mm deep and 0.6m dia
1.5
-
0.4
hrs/no
Concrete Pile Caps, > 750mm deep and 0.6m dia
1.8
-
0.8
hrs/no
Concrete Pile Caps, 50-300mm deep and 1.1m dia
1.9
-
0.8
hrs/no
Concrete Pile Caps, 300-750mm deep and 1.1m dia
2.5
-
1.1
hrs/no
Concrete Pile Caps, > 750mm deep and 1.1m dia
4.2
-
2.3
hrs/no
Concrete Pile Caps, 50-300mm deep and 2.5m dia
9.2
-
8.2
hrs/no
Concrete Pile Caps, 300-750mm deep and 2.5m dia
10.1
-
9.5
hrs/no
Concrete Pile Caps, > 750mm deep and 2.5m dia
11.5
-
10.2
hrs/no
Concrete, Cutting Slabs, 5-25m deep
-
15.2
-
m/hr
Concrete, Cutting Slabs, 25-50m deep
-
11.5
-
m/hr
Concrete, Cutting Slabs, 50-75m deep
-
6.7
-
m/hr
Concrete, Cutting Holes, coring machine
-
0.2
-
m3/hr
Concrete, Cutting Back to expose couplers 0.7m slab
-
2.5
-
m/day
Slow
Ave
Fast
Units
Concrete, cutting by hand, < 25mm wide
1.5
2.1
3.1
m/hr
Concrete, cutting by hand, 25-50mm wide
1.2
1.6
2.5
m/hr
Cutting Chases Cutting Chases Task / Description
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 31 of 100
Concrete, cutting by hand, 50-75mm wide
1.0
1.4
2.1
m/hr
Concrete, cutting by hand, 75-100mm wide
0.9
1.2
1.8
m/hr
Concrete, cutting by machine, < 25mm wide
3.1
4.0
5.8
m/hr
Concrete, cutting by machine, 25-50mm wide
2.5
3.3
5.0
m/hr
Concrete, cutting by machine, 50-75mm wide
2.1
2.9
4.2
m/hr
Concrete, cutting by machine, 75-100mm wide
1.8
2.4
3.7
m/hr
Brickwork, cutting by hand, < 25mm wide
2.1
2.7
4.1
m/hr
Brickwork, cutting by hand, 25-50mm wide
1.6
2.3
3.5
m/hr
Brickwork, cutting by hand, 50-75mm wide
1.4
1.9
2.8
m/hr
Brickwork, cutting by hand, 75-100mm wide
1.2
1.6
2.5
m/hr
Brickwork, cutting by machine, < 25mm wide
4.2
5.5
11.1
m/hr
Brickwork, cutting by machine, 25-50mm wide
3.3
4.5
6.7
m/hr
Brickwork, cutting by machine, 50-75mm wide
3.3
4.5
6.7
m/hr
Brickwork, cutting by machine, 75-100mm wide
2.5
3.3
5.0
m/hr
Light Blockwork, cutting by hand, < 25mm wide
3.8
5.0
7.7
m/hr
Light Blockwork, cutting by hand, 25-50mm wide
3.2
4.2
6.3
m/hr
Light Blockwork, cutting by hand, 50-75mm wide
2.6
3.4
5.3
m/hr
Light Blockwork, cutting by hand, 75-100mm wide
2.3
3.1
4.5
m/hr
Light Blockwork, cutting by machine, < 25mm wide
7.7
10.0
14.2
m/hr
Light Blockwork, cutting by machine, 25-50mm wide
5.9
7.7
11.1
m/hr
Light Blockwork, cutting by machine, 50-75mm wide
5.2
7.2
10.0
m/hr
Light Blockwork, cutting by machine, 75-100mm wide
4.7
6.3
9.1
m/hr
Heavy Blockwork, cutting by hand, < 25mm wide
1.9
2.6
3.8
m/hr
Heavy Blockwork, cutting by hand, 25-50mm wide
1.6
2.1
3.2
m/hr
Heavy Blockwork, cutting by hand, 50-75mm wide
1.3
1.8
2.7
m/hr
Heavy Blockwork, cutting by hand, 75-100mm wide
1.2
1.5
2.3
m/hr
Heavy Blockwork, cutting by machine, < 25mm wide
3.8
5.0
7.7
m/hr
Heavy Blockwork, cutting by machine, 25-50mm wide
3.2
4.2
6.2
m/hr
Heavy Blockwork, cutting by machine, 50-75mm wide
2.7
3.6
5.2
m/hr
Heavy Blockwork, cutting by machine, 75-100mm wide
2.3
3.1
4.5
m/hr
Slow
Ave
Fast
Units
Cutting in Concrete, small box
7.1
9.5
12.5
no/hr
Cutting in Concrete, large box
3.6
4.5
5.6
no/hr
Cutting in Brickwork, small box
6.6
9.5
12.5
no/hr
Cutting in Brickwork, large box
4.2
5.3
6.3
no/hr
Cutting in Lightweight Blockwork, small box
20.0
23.0
25.0
no/hr
Cutting in Lightweight Blockwork, large box
10.0
12.5
14.3
no/hr
Cutting in Heavyweight Blockwork, small box
7.7
10.0
12.5
no/hr
Cutting in Heavyweight Blockwork, large box
3.8
4.8
5.9
no/hr
Cutting Switchboxes Cutting Switchboxes Task / Description
Housing Demolitions Demolition
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 32 of 100
Task / Description
Slow
Ave
Fast
-
2.5
-
Remove & Cart away, Ceramic Wall Tiles
2.0
2.5
3.4
m2/hr
Remove & Cart away, Wallpaper, 1 layer
-
8.7
-
m2/hr
Remove & Cart away, Wallpaper, 2 layers
-
7.1
-
m2/hr
Remove & Cart away, Wallpaper, 3 layers
-
5.7
-
m2/hr
Remove & Cart away, Lathe and Plaster Ceilings
3.2
4.6
5.0
m2/hr
Remove & Cart away, Plaster to Walls
2.1
3.1
5.9
m2/hr
Weight, Structural Steel
Units Tonnes/m3
Remove & Cart away, External Render
-
3.9
-
m2/hr
Remove & Cart away, Floor Screed
-
3.2
-
m2/hr
Remove & Cart away, Concrete Paving
-
4.0
-
m2/hr
Remove & Cart away, Brickwork Walls, 1.0 brick thick
-
1.3
-
m2/hr
Remove & Cart away, Brickwork Walls, 0.5 brick thick
-
2.6
-
m2/hr
Remove & Cart away, Brickwork Walls, Sand/Lime Mortar
-
1.8
-
hrs/100
Remove & Cart away, Fireplace and Hearth
-
1.9
-
hrs/no
Remove & Cart away, Floor Boards
-
6.2
-
m2/hr
Remove & Cart away, Skirting, Architrave, Dado rail etc
-
16.5
-
m/hr
Remove & Cart away, Staircase
-
7.3
-
hrs/no
Remove & Cart away, Windows, 0-1m2
-
0.6
-
hrs/no
Remove & Cart away, Windows 1-2m2
-
0.8
-
hrs/no
Remove & Cart away, Windows 2-3m2
-
0.9
-
hrs/no
Remove & Cart away, Doors
-
0.3
-
hrs/on
Remove & Cart away, Door Frame
-
0.1
-
hrs/no
Remove & Cart away, Floor and Ceiling Joists
-
1.1
-
hrs/m
Remove & Cart away, Wall Plates
-
3.9
-
hrs/m
Remove & Cart away, Iron Bath
-
1.4
-
/hrs/no
Remove & Cart away, Wash Basin/Sink
-
0.8
-
/hrs/no
Remove & Cart away, Pipework including brackets etc
-
6.1
-
m/hr
Removal of Housing Finishes HACKING OFF/ REMOVE MATERIALS Removal of Housing Finishes
Ceramic wall tiles Wallpaper
.
All rates in m2/hr, unless otherwise indicated. Remove and cart away.
2.50 -1 layer
8.70
-2 layers
7.05
-3 layers
5.75
Lathe & Plaster ceilings
4.55
Plaster to walls
3.05
External render
3.90
Floor screed
3.05
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 33 of 100
Concrete paving Brickwalls London Stocks
4.00 x 1 brick
1.35
- Londond Stocks x 0.5 bricks
2.65
Sand/Lime mortar
1.80 hrs/100
Fireplace and metal hearth
1.90 hrs/no
Floor Boards
6.20
Architrave, dado, skirting etc
16.50 m/hr
Staircase Windows
7.35 hrs/no 2
0.65 hrs/no
1 - 2 m2
0.80 hrs/no
2 - 3 m2
0.91 hrs/no
0-1m
Doors
0.25 hrs/no
Door frame
0.10 hrs/no
Floor & Ceiling Joists
1.09 hrs/m
Wall plate
3.90 hrs/m
Bath
1.45 hrs/no
Basin
0.85 hrs/no
Pipework, incl brackets etc
6.15 m/hr
Drainage, Manholes and Gulleys Manholes and Gulleys Slow
Ave
Fast
Concrete Pre-Cast Manhole Units, 610 x 455 x 51 mm
Task / Description
-
1.2
-
hrs/no
Concrete Pre-Cast Manhole Units, 990 x 610 x 64 mm
-
1.6
-
hrs/no
Brickwork Manhole, 1.0 brick engineering
-
0.3
-
m2/hr
Brickwork Manhole, 1.5 brick engineering
-
0.2
-
m2/hr
Brickwork Manhole, 2.0 brick engineering
-
0.2
-
m2/hr
Benching to Manhole, under 0.5m2
-
0.9
-
hrs/no
Benching to Manhole, 0.5-0.75m2
-
1.2
-
hrs/no
Benching to Manhole, 0.75-1.0m2
-
1.8
-
hrs/no
Brickwork Manhole, build in pipes, under 150mm dia
-
0.1
-
hrs/no
Brickwork Manhole, build in pipes, 150-225mm dia
-
0.2
-
hrs/no
Brickwork Manhole, build in pipes, over 225mm dia
-
0.3
-
hrs/no
0.3
0.6
1.2
hrs/no
Yard Gulleys, 75-150mm dia pipes, bed and level
-
2.2
-
no/hr
Yard Gulleys, 150-225mm dia pipes, bed and level
-
1.8
-
no/hr
Yard Gulleys, 225-300mm dia pipes, bed and level
-
1.5
-
no/hr
Brickwork Manhole, build in cast iron covers
http://www.planningplanet.com/print/book/export/html/422384
Units
11/3/2014
Page 34 of 100
Road Gulleys, 600mm deep, bed and level
-
1.2
-
no/hr
Road Gulleys, 750mm deep, bed and level
-
0.8
-
no/hr
Road Gulleys, 900mm deep, bed and level
-
0.4
-
no/hr
Road Gulleys, 1,200mm deep, bed and level
-
0.3
-
no/hr
Road Gulleys, install gratings
-
5.0
-
no/hr
PVC Manhole
-
15.0
-
mins/no
Land Drains Task / Description
Slow
Ave
Fast
Units
Land Drains, Concrete, butt jointed, under 150mm dia, 0-5m run
-
11.6
-
m/hr
Land Drains, Concrete, butt jointed, under 150mm dia, 5-30m run
-
14.1
-
m/hr
Land Drains, Concrete, butt jointed, under 150mm dia, over 30m run
-
18.8
-
m/hr
Land Drains, Concrete, butt jointed, 150-225mm dia, 0-5m run
-
8.4
-
m/hr
Land Drains, Concrete, butt jointed, 150-225mm dia, 5-30m run
-
10.2
-
m/hr
Land Drains, Concrete, butt jointed, 150-225mm dia, over 30m run
-
11.9
-
m/hr
Land Drains, Concrete, butt jointed, 225-300mm dia, 0-5m run
-
5.4
-
m/hr
Land Drains, Concrete, butt jointed, 225-300mm dia, 5-30m run
-
6.5
-
m/hr
Land Drains, Concrete, butt jointed, 225-300mm dia, over 30m run
-
7.9
-
m/hr
Drainage Task / Description
Slow
Ave
Fast
Units
PVC Drainage, 1m pipes, 100-150mm dia, 0-5m run
-
5.7
-
m/hr
PVC Drainage, 1m pipes, 100-150mm dia, 5-30m run
-
8.1
-
m/hr
PVC Drainage, 1m pipes, 100-150mm dia, over 30m run
-
9.5
-
m/hr
PVC Drainage, 3m pipes, 100-150mm dia, 0-5m run
-
12.2
-
m/hr
PVC Drainage, 3m pipes, 100-150mm dia, 5-30m run
-
15.2
-
m/hr
PVC Drainage, 3m pipes, 100-150mm dia, over 30m run
-
18.2
-
m/hr
PVC Drainage, 6m pipes, 100-150mm dia, 0-5m run
-
22.2
-
m/hr
PVC Drainage, 6m pipes, 100-150mm dia, 5-30m run
-
27.7
-
m/hr
PVC Drainage, 6m pipes, 100-150mm dia, over 30m run
-
33.3
-
m/hr
PVC Drainage, 3m pipes, 150-200mm dia, 5-30m run
-
10.6
-
m/hr
PVC Drainage, 3m pipes, 150-200mm dia, over 30m run
-
12.8
-
m/hr
PVC Drainage, 6m pipes, 150-200mm dia, 5-30m run
-
21.2
-
m/hr
PVC Drainage, 6m pipes, 150-200mm dia, over 30m run
-
25.6
-
m/hr
Stoneware Drainage, Cement/Sand Joints, 75mm dia, 0-5m run
-
4.7
-
m/hr
Stoneware Drainage, Cement/Sand Joints, 75mm dia, 5-30m run
-
5.5
-
m/hr
Stoneware Drainage, Cement/Sand Joints, 75mm dia, over 30m run
-
6.6
-
m/hr
Stoneware Drainage, Cement/Sand Joints, 100mm dia, 0-5m run
-
4.4
-
m/hr
Stoneware Drainage, Cement/Sand Joints, 100mm dia, 5-30m run
-
5.0
-
m/hr
Stoneware Drainage, Cement/Sand Joints, 100mm dia, over 30m run
-
6.2
-
m/hr
Stoneware Drainage, Cement/Sand Joints, 150mm dia, 0-5m run
-
3.2
-
m/hr
Stoneware Drainage, Cement/Sand Joints, 150mm dia, 5-30m run
-
3.8
-
m/hr
Stoneware Drainage, Cement/Sand Joints, 150mm dia, over 30m run
-
4.5
-
m/hr
Stoneware Drainage, Cement/Sand Joints, 225mm dia, 0-5m run
-
2.1
-
m/hr
Stoneware Drainage, Cement/Sand Joints, 225mm dia, 5-30m run
-
2.6
-
m/hr
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 35 of 100
Stoneware Drainage, Cement/Sand Joints, 225mm dia, over 30m run
-
3.1
-
m/hr
Stoneware Drainage, Cement/Sand Joints, 300mm dia, 0-5m run
-
1.4
-
m/hr
Stoneware Drainage, Cement/Sand Joints, 300mm dia, 5-30m run
-
1.7
-
m/hr
Stoneware Drainage, Cement/Sand Joints, 300mm dia, over 30m run
-
2.4
-
m/hr
Stoneware Drainage, Cement/Sand Joints, over 375mm dia, 0-5m run
-
1.1
-
m/hr
Stoneware Drainage, Cement/Sand Joints, over 375mm dia, 5-30m run
-
1.3
-
m/hr
Stoneware Drainage, Cement/Sand Joints, over 375mm dia, over 30m run
-
1.6
-
m/hr
Stoneware Drainage, Flexible Joints, 75mm dia, 0-5m run
-
8.3
-
m/hr
Stoneware Drainage, Flexible Joints, 75mm dia, 5-30m run
-
10.0
-
m/hr
Stoneware Drainage, Flexible Joints, 75mm dia, over 30m run
-
12.5
-
m/hr
Stoneware Drainage, Flexible Joints, 100mm dia, 0-5m run
-
7.7
-
m/hr
Stoneware Drainage, Flexible Joints, 100mm dia, 5-30m run
-
9.1
-
m/hr
Stoneware Drainage, Flexible Joints, 100mm dia, over 30m run
-
10.0
-
m/hr
Stoneware Drainage, Flexible Joints, 150mm dia, 0-5m run
-
5.2
-
m/hr
Stoneware Drainage, Flexible Joints, 150mm dia, 5-30m run
-
6.2
-
m/hr
Stoneware Drainage, Flexible Joints, 150mm dia, over 30m run
-
7.7
-
m/hr
Stoneware Drainage, Flexible Joints, 225mm dia, 0-5m run
-
2.7
-
m/hr
Stoneware Drainage, Flexible Joints, 225mm dia, 5-30m run
-
3.3
-
m/hr
Stoneware Drainage, Flexible Joints, 225mm dia, over 30m run
-
4.0
-
m/hr
Stoneware Drainage, Flexible Joints, 300mm dia, 0-5m run
-
1.7
-
m/hr
Stoneware Drainage, Flexible Joints, 300mm dia, 5-30m run
-
2.1
-
m/hr
Stoneware Drainage, Flexible Joints, 300mm dia, over 30m run
-
2.5
-
m/hr
Stoneware Drainage, Flexible Joints, over 375mm dia, 0-5m run
-
1.4
-
m/hr
Stoneware Drainage, Flexible Joints, over 375mm dia, 5-30m run
-
1.6
-
m/hr
Stoneware Drainage, Flexible Joints, over 375mm dia, over 30m run
-
2.1
-
m/hr
PVC, Stoneware, Pitch Fibre & Concrete Joints
-
2.4
-
mins/no
Pitch Fibre Pipes, 75mm dia, 0-5m run
-
9.1
-
m/hr
Pitch Fibre Pipes, 75mm dia, 5-30m run
-
16.6
-
m/hr
Pitch Fibre Pipes, 75mm dia, over 30m run
-
20.0
-
m/hr
Pitch Fibre Pipes, 100mm dia, 0-5m run
-
9.1
-
m/hr
Pitch Fibre Pipes, 100mm dia, 5-30m run
-
16.6
-
m/hr
Pitch Fibre Pipes, 100mm dia, over 30m run
-
20.0
-
m/hr
Pitch Fibre Pipes, 150mm dia, 0-5m run
-
6.6
-
m/hr
Pitch Fibre Pipes, 150mm dia, 5-30m run
-
12.5
-
m/hr
Pitch Fibre Pipes, 150mm dia, over 30m run
-
14.3
-
m/hr
Pitch Fibre Pipes, 200mm dia, 0-5m run
-
6.2
-
m/hr
Pitch Fibre Pipes, 200mm dia, 5-30m run
-
11.1
-
m/hr
Pitch Fibre Pipes, 200mm dia, over 30m run
-
12.5
-
m/hr
Pitch Fibre Pipes, 225mm dia, 0-5m run
-
5.8
-
m/hr
Pitch Fibre Pipes, 225mm dia, 5-30m run
-
10.0
-
m/hr
Pitch Fibre Pipes, 225mm dia, over 30m run
-
12.1
-
m/hr
Hepsleve Rubber Joint System, 75mm dia, 0-5m run
-
12.5
-
m/hr
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 36 of 100
Hepsleve Rubber Joint System, 75mm dia, 5-30m run
-
14.3
-
m/hr
11.2
16.6
30.1
m/hr
Hepsleve Rubber Joint System, 100mm dia, 0-5m run
-
10.0
-
m/hr
Hepsleve Rubber Joint System, 100mm dia, 5-30m run
-
12.5
-
m/hr
Hepsleve Rubber Joint System, 100mm dia, over 30m run
-
14.3
-
m/hr
Hepsleve Rubber Joint System, 150mm dia, 0-5m run
-
7.1
-
m/hr
Hepsleve Rubber Joint System, 150mm dia, 5-30m run
-
9.1
-
m/hr
8.3
10.0
13.8
m/hr
Hepsleve Rubber Joint System, 225mm dia, 0-5m run
-
6.8
-
m/hr
Hepsleve Rubber Joint System, 225mm dia, 5-30m run
-
4.5
-
m/hr
Hepsleve Rubber Joint System, 225mm dia, over 30m run
-
5.5
-
m/hr
Hepsleve Rubber Joint System, 300mm dia, 0-5m run
-
2.5
-
m/hr
Hepsleve Rubber Joint System, 300mm dia, 5-30m run
-
2.9
-
m/hr
Hepsleve Rubber Joint System, 300mm dia, over 30m run
-
3.7
-
m/hr
Hepsleve Rubber Joint System, over 375mm dia, 0-5m run
-
1.9
-
m/hr
Hepsleve Rubber Joint System, over 375mm dia, 5-30m run
-
2.3
-
m/hr
Hepsleve Rubber Joint System, over 375mm dia, over 30m run
-
2.7
-
m/hr
Concrete Pipes, 1.5m pipes, 375mm dia, 0-5m run
-
2.8
-
m/hr
Concrete Pipes, 1.5m pipes, 375mm dia, 5-30m run
-
3.4
-
m/hr
Concrete Pipes, 1.5m pipes, 375mm dia, over 30m run
-
3.8
-
m/hr
Concrete Pipes, 1.5m pipes, 450mm dia, 0-5m run
-
2.7
-
m/hr
Concrete Pipes, 1.5m pipes, 450mm dia, 5-30m run
-
3.2
-
m/hr
Concrete Pipes, 1.5m pipes, 450mm dia, over 30m run
-
3.6
-
m/hr
Concrete Pipes, 1.5m pipes, 525mm dia, 0-5m run
-
2.5
-
m/hr
Concrete Pipes, 1.5m pipes, 525mm dia, 5-30m run
-
2.9
-
m/hr
Concrete Pipes, 1.5m pipes, 525mm dia, over 30m run
-
3.4
-
m/hr
Concrete Pipes, 1.5m pipes, 600mm dia, 0-5m run
-
2.4
-
m/hr
Concrete Pipes, 1.5m pipes, 600mm dia, 5-30m run
-
2.7
-
m/hr
Concrete Pipes, 1.5m pipes, 600mm dia, over 30m run
-
3.3
-
m/hr
Concrete Pipes, 1.5m pipes, 675mm dia, 0-5m run
-
2.2
-
m/hr
Concrete Pipes, 1.5m pipes, 675mm dia, 5-30m run
-
2.6
-
m/hr
Concrete Pipes, 1.5m pipes, 675mm dia, over 30m run
-
2.9
-
m/hr
Concrete Pipes, 1.5m pipes, 750mm dia, 0-5m run
-
1.1
-
m/hr
Concrete Pipes, 1.5m pipes, 750mm dia, 5-30m run
-
2.4
-
m/hr
Concrete Pipes, 1.5m pipes, 750mm dia, over 30m run
-
2.5
-
m/hr
Concrete Pipes, 1.5m pipes, 1,050mm dia
-
2.9
4.2
m/day
Concrete Pipes, 1.5m pipes, 1,500mm dia
-
2.5
3.8
m/day
Concrete Pipes, 1.5m pipes, 1,800mm dia
-
2.1
2.6
m/day
Concrete Pipes, 2.5m pipes, 375mm dia, 0-5m run
-
3.6
-
m/hr
Concrete Pipes, 2.5m pipes, 375mm dia, 5-30m run
-
4.3
-
m/hr
Concrete Pipes, 2.5m pipes, 375mm dia, over 30m run
-
5.0
8.0
m/hr
Concrete Pipes, 2.5m pipes, 450mm dia, 0-5m run
-
3.4
-
m/hr
Concrete Pipes, 2.5m pipes, 450mm dia, 5-30m run
-
4.1
-
m/hr
Concrete Pipes, 2.5m pipes, 450mm dia, over 30m run
-
4.5
9.0
m/hr
Concrete Pipes, 2.5m pipes, 525mm dia, 0-5m run
-
3.3
-
m/hr
Concrete Pipes, 2.5m pipes, 525mm dia, 5-30m run
-
3.8
-
m/hr
Hepsleve Rubber Joint System, 75mm dia, over 30m run
Hepsleve Rubber Joint System, 150mm dia, over 30m run
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 37 of 100
Concrete Pipes, 2.5m pipes, 525mm dia, over 30m run
-
4.1
-
m/hr
Concrete Pipes, 2.5m pipes, 600mm dia, 0-5m run
-
3.0
-
m/hr
Concrete Pipes, 2.5m pipes, 600mm dia, 5-30m run
-
3.5
-
m/hr
Concrete Pipes, 2.5m pipes, 600mm dia, over 30m run
-
4.0
-
m/hr
Concrete Pipes, 2.5m pipes, 675mm dia, 0-5m run
-
2.8
-
m/hr
Concrete Pipes, 2.5m pipes, 675mm dia, 5-30m run
-
3.3
-
m/hr
Concrete Pipes, 2.5m pipes, 675mm dia, over 30m run
-
3.7
-
m/hr
Concrete Pipes, 2.5m pipes, 750mm dia, 0-5m run
-
2.6
-
m/hr
Concrete Pipes, 2.5m pipes, 750mm dia, 5-30m run
-
3.1
-
m/hr
Concrete Pipes, 2.5m pipes, 750mm dia, over 30m run
-
3.6
-
m/hr
Lay Shingle Around Pipework, under 150mm dia
-
7.0
-
m/hr
Lay Shingle Around Pipework, over 150mm dia
4.0
5.5
9.0
m/hr
Slow
Ave
Fast
Units
Hydraulic Excavator, 0.3m3 bucket, Sand/Soil - Basement Works
6.4
8.0
9.4
m3/hr
Hydraulic Excavator, 0.3m3 bucket, Gravel Beds - Basement Works
5.5
6.9
8.1
m3/hr
Hydraulic Excavator, 0.3m3 bucket, Clay/Chalk - Basement Works
5.2
6.5
7.9
m3/hr
Hydraulic Excavator, 0.3m3 bucket, Hard Ground - Basement Works
4.7
5.9
8.2
m3/hr
Hydraulic Excavator, 0.4m3 bucket, Sand/Soil - Basement Works
12.6
15.4
18.9
m3/hr
Hydraulic Excavator, 0.4m3 bucket, Gravel Beds - Basement Works
11.7
14.3
16.7
m3/hr
Hydraulic Excavator, 0.4m3 bucket, Clay/Chalk - Basement Works
10.9
13.3
15.6
m3/hr
9.7
11.8
14.0
m3/hr
Hydraulic Excavator, 0.5m3 bucket, Sand/Soil - Basement Works
18.2
20.0
23.0
m3/hr
Hydraulic Excavator, 0.5m3 bucket, Gravel Beds - Basement Works
16.5
18.1
20.0
m3/hr
Hydraulic Excavator, 0.5m3 bucket, Clay/Chalk - Basement Works
15.4
16.7
19.3
m3/hr
Hydraulic Excavator, 0.5m3 bucket, Hard Ground - Basement Works
13.3
15.4
17.7
m3/hr
Slow
Ave
Fast
Units
Excavate Spoil Heaps to Transport, 0.6m3 bucket, Sand/Soil
14.5
20.0
25.6
m3/hr
Excavate Spoil Heaps to Transport, 0.6m3 bucket, Gravel Beds
15.2
20.4
25.6
m3/hr
Excavate Spoil Heaps to Transport, 0.6m3 bucket, Clay/Chalk
12.3
18.5
23.2
m3/hr
Excavate Spoil Heaps to Transport, 0.6m3 bucket, Boulder Clay
11.2
16.9
21.3
m3/hr
Excavate Spoil Heaps to Transport, 1.1m3 bucket, Sand/Soil
25.4
30.3
35.7
m3/hr
Excavate Spoil Heaps to Transport, 1.1m3 bucket, Gravel Beds
25.6
31.3
37.0
m3/hr
Excavate Spoil Heaps to Transport, 1.1m3 bucket, Clay/Chalk
22.5
27.8
33.3
m3/hr
Earthworks & Excavation Basement Excavations Basement Excavation Basement Excavation Task / Description
Hydraulic Excavator, 0.4m3 bucket, Hard Ground - Basement Works
Excavate and Remove Excavate and Remove Task / Description
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 38 of 100
Excavate Spoil Heaps to Transport, 1.1m3 bucket, Boulder Clay
18.9
24.4
30.3
m3/hr
Load Spoil to Barge, capacity 2,000m3
-
8.0
-
hrs
Load Spoil to Barge, capacity 1,500m3
-
6.5
-
hrs
Load Spoil to Barge, capacity 1,000m3
-
5.5
-
hrs
Spoil conveyor, 600mm belt, 150m/min
-
260.0
-
m3/hr
Bell Ground Anchors Bell Ground Anchors Task / Description
Slow
Ave
Fast
Units
Uncased Anchors, 10m long
-
2.0
-
no/day
Top Cased Anchors, 15m long
-
1.0
-
no/day
Anchors stressing
-
2.2
-
no/day
Bored Piling Bored Piling Task / Description
Slow
Ave
Fast
Cycle Time, 5-20m deep
8.0
4.0
4.0
days/no
Cycle Time, 20-40m deep
10.0
8.0
-
days/no
Cycle Time, 40-70m deep
25.0
10.0
-
days/no
Cycle Time, 70-90m deep
45.0
25.0
-
days/no
Cycle Time, 90-135m deep
60.0
45.0
-
days/no
Move piling setup to next location
-
2.0
-
hrs
Excave shaft by grab, general fill/uppr levels
-
3.5
-
m/hr
Excave shaft by grab, sand/minor rubble
-
2.1
-
m/hr
Excave shaft by grab, marinve/aluvium
-
2.5
-
m/hr
Excave shaft by grab/RCD, CDT
-
0.5
-
m/hr
Excave shaft by grab/RCD, CDG 200/gravel
-
0.5
-
m/hr
Excave shaft by RCD/Chisel, corestones
-
0.5
-
m/hr
Excave Rock Socket by RCD, grade IV/V rock
-
0.2
0.3
m/hr
Excave Rock Socket by RCD, grade II/III rock
-
0.1
0.2
m/hr
Excave Rock Socket by RCD, tendering rate
-
0.1
-
m/hr
Add/remove RCD plant
-
2.0
-
hrs
Add/remove RCD drill string/drill bit
-
5.0
-
hrs
Remove Obstruction, above water hand hammers
-
0.8
-
m/hr
Remove Obstruction, below water heavy chisel
-
0.5
-
m/hr
60.0
53.0
50.0
hrs
Install air lift tremmie tube
-
5.0
-
hrs
Fabricate reinforcement cages
-
2.5
-
hs/cage
Install reinforcement cages
-
2.0
-
hrs/no
Shaft cleaning, air lifting after excavation
-
8.0
-
hrs
Shaft cleaning, air lifting after cage installed
-
2.0
-
hrs
Concrete Plug, RCD off/tremmie/concrete/cure/RCD on
http://www.planningplanet.com/print/book/export/html/422384
Units
11/3/2014
Page 39 of 100
Shaft concreting/extract casing 5-70m deep
-
12.0
-
hrs
Shaft concreting/extract casing 70-95m deep
-
14.0
-
hrs
Shaft concreting/extract casing 95-135m deep
-
48.0
-
hrs
Concrete curing prior to remove telescopic casing
-
72.0
-
hrs
Concrete Testing, Coring Test
-
3.2
2.2
Concrete Testing, Sonic Logging Test
-
2.5
-
hrs/no
Concrete Testing, Vibration Test
-
6.5
-
hrs/no
m/hr
Bulk Excavation Bulk Excavation Task / Description
Slow
Ave
Fast
Units
Excavation Bulking Factor, Sand/Soil
-
15.0
20.0
%
Excavation Bulking Factor, Gravel
-
33.0
-
%
Excavation Bulking Factor, Clay/Chalk
-
40.0
-
%
Excavation Bulking Factor, Boulder Clay
-
45.0
-
%
Excavation Bulking Factor, Rock
-
60.0
-
%
Spoil Weight, Rock
-
2.5
-
Tonnes/m3
Spoil Weight, Concrete
-
2.4
-
Tonnes/m3
Spoil Weight, Landfill/CDG
-
1.9
-
Tonnes/m3
Spoil Weight, Sand
-
1.8
-
Tonnes/m3
Rail Mounted Grab, 2.0m3 bucket 2.4min lift cycle
30.0
48.0
59.0
m3/hr
Crane Mounted Clamshell Grab, 2.0m3 bucket 2.9min lift cycle
25.0
33.0
41.0
m3/hr
Crane Mounted Clamshell Grab, 2.5m3 bucket 2.9min lift cycle
34.0
42.0
52.0
m3/hr
Hydraulic Excavator, 0.3m3 bucket, Sand/Soil
6.9
8.7
10.2
m3/hr
Hydraulic Excavator, 0.4m3 bucket, Sand/Soil
23.4
28.6
33.4
m3/hr
Hydraulic Excavator, 0.5m3 bucket, Sand/Soil
45.5
50.0
58.0
m3/hr
Hydraulic Excavator, 0.3m3 bucket, Gravel Beds
5.6
7.1
8.2
m3/hr
Hydraulic Excavator, 0.4m3 bucket, Gravel Beds
20.5
25.0
29.0
m3/hr
Hydraulic Excavator, 0.5m3 bucket, Gravel Beds
36.8
40.0
46.0
m3/hr
Hydraulic Excavator, 0.3m3 bucket, Clay/Chalk
5.6
7.1
8.3
m3/hr
Hydraulic Excavator, 0.4m3 bucket, Clay/Chalk
20.5
25.0
28.7
m3/hr
Hydraulic Excavator, 0.5m3 bucket, Clay/Chalk
37.0
40.0
46.0
m3/hr
Hydraulic Excavator, 0.3m3 bucket, Hard Ground
4.5
6.1
7.2
m3/hr
Hydraulic Excavator, 0.4m3 bucket, Hard Ground
17.9
22.2
25.0
m3/hr
Hydraulic Excavator, 0.5m3 bucket, Hard Ground
25.7
28.6
32.9
m3/hr
Dewatering Cofferdam Works Soil Mix Wall Three auger machine drilling and mixing cement into three cores. H-piles dropped into two, then machine moves along by two holes. • An average output was 4 - 5 m/day.
Dewatering
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 40 of 100
To setup a cofferdam dewatering system, including boring, pump installation and outflow pipework and drainage tanks etc, typical rates are... • Small 2 hole system, for an overrun tunnel, with a single drilling rig takes about 7 - 10 days to get up and running. • A larger system, with 10 - 15 holes, for a station type cofferdam will take in the region of 3 weeks with 2 rigs. This can be speeded up with the use of more rigs to reduce the well boring times. A typical rate of 2.5 days per pump installation can be used to calculate detailed pumping arrangements. The water level can be dropped in a "closed cofferdam" within a 6 to 8 hour period for a 25,000 m2 cofferdam with a 2 m water level reduction. For smaller closed areas it will take only a few hours at most to reduce the water level by 2.5 - 3 metres. Recharge System - Average well depth of say 55 m deep, not into rock, 9 wells in 10 days or 1.11 days/no with an additional 4 - 5 days to connect pipework and recharge backup tanks etc. Dewatering Task / Description
Slow
Ave
Fast
Units
10.0
8.0
6.0
days
Setup large 15 hole system
-
21.0
-
days
Calculate system times per pump
-
2.5
-
days/pump
Setup Recharge System
-
3.5
-
days/pump
Setup small 2 hole system
Excavate & Reduce Levels Excavate By Hand Trenches (m3/hr)
Depth in Metres->
Ne 1.5
1.5-3.0
3.0-4.5
Sand/Soil lose
0.66
0.45
0.33
Sand/Soil firm 0.57
0.38
0.28
Gravel
0.45
0.31
0.23
Clay/Heavy Soil
0.46
0.31
0.24
Boulder Clay
0.38
0.26
0.19
2
3
Pits or Bases Ne 2 m (m /hr) Depth in Metres->
Ne 1.5
1.5-3.0
3.0-4.5
Sand/Soil lose
0.5
0.33
-
Sand/Soil firm 0.43
0.29
-
Gravel
0.34
0.23
-
Clay/Heavy Soil
0.35
0.24
-
Boulder Clay
0.28
0.19
-
Hand Transportation of Spoil (m3/hr) Wheel 0 - 10 m
6.25
10 - 20 m
3.23
20 - 50 m
2.13
Trim Excavation (m3/hr) Ave Thickness
Sand
Gravel
Clay
Boulders
0 - 25 mm
20.00
16.67
20.00
14.29
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 41 of 100
25 - 50 mm
11.11
8.33
9.09
7.69
50 - 75 mm
7.69
5.88
6.25
5.00
75 - 125 mm
5.56
4.35
4.55
3.70
Excavate & Spread and Level Small Scale Spread and Level By Hand Including load and wheel an average of 20 m from tipped heap (m3/hr) Layers ->
n.e.25mm 2575mm
75.200mm Exc.200mm
n.e. 200 m2
1.03
1.03
1.12
1.23
exc. 200 m2
1.37
1.37
1.49
1.64
n.e. 200 m2
-
0.86
0.93
1.03
exc. 200 m2
-
1.14
1.23
1.37
n.e. 200 m2
-
0.85
1.02
1.27
exc. 200 m2
-
1.02
1.27
1.69
Sand/Soil
Gravel/Shingle
Hardcore
Spread and Level By Crawler Shovel Rates in (m3/hr) 0.6m3
0.8m3
1.0m3
1.2m3
n.e. 200 m2
18.67
38.46
43.48
52.63
exc. 200 m2
24.39
50.00
55.56
66.67
n.e. 200 m2
18.87
38.46
43.48
52.63
exc. 200 m2
24.39
50.00
55.56
66.67
n.e. 200 m2
15.87
31.25
37.04
43.48
2
19.23
40.00
47.62
55.56
n.e. 200 m2
17.24
35.71
43.48
47.62
exc. 200 m2
22.22
45.45
55.56
62.50
Machine Bucket-> Sand/Soil
Gravel/Shingle
Hardcore
exc. 200 m Clay
Note: • n.e means "not exceeding"
Excavation Works Excavate & Load Excavate Spoil Heaps and Load to Transport (m3/hr):
Material
0.6 m3
0.8 m3
1.0 m3
1.2 m3
Sand/Soil
20.0
25.6
30.3
35.7
Gravel
20.4
25.6
31.3
37.0
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 42 of 100
Clay/Chalk
18.5
23.2
27.8
33.3
Boulder Clay 16.9
21.3
24.4
30.3
Note: • 0.6m3, 0.8m3, 1.0m3 and 1.2m3 are excavator bucket capacity. • 20.0, 25.6, 30.3 and 35.7 etc are excavation rates in m3 / hr
Excavate By Crawler Shovel. Including excavate and bank/stock pile (m3/hr) Sand/Soil
Machine Bucket -> 0.6m3
0.8m3
1.0m3
1.2m3
Pushed n.e.20 m
20.00
25.00
30.30
35.71
Pushed 20 50 m
13.89
20.41
23.81
27.78
Pushed 50 125 m
7.63
12.66
16.67
20.41
20.40
25.64
31.25
37.04
Pushed 20 - 14.29 50 m
20.83
25.00
28.57
Pushed 50 100 m
12.82
17.24
21.28
18.52
23.26
27.78
33.33
Pushed 20 - 12.66 50 m
18.52
21.74
25.64
Pushed 50 100 m
11.63
15.15
18.87
16.95
21.28
24.39
30.30
Pushed 20 - 11.63 50 m
16.95
19.61
23.26
Pushed 50 100 m
10.42
13.70
17.54
Gravel
Pushed n.e. 20 m
7.69
Clay/Chalk/Heavy Soil Pushed n.e. 20 m
6.99
Boulder Clay Pushed n.e. 20 m
6.33
Including excavate and load to transport (m3/hr) Machine Bucket ->
0.6m3
0.8m3
1.0m3
1.2m3
Sand/Soil
17.86
23.26
27.03
30.30
Gravel
16.67
23.26
27.78
31.25
Chalk/Heavy Soil
14.71
21.74
25.00
29.41
Boulder Clay
13.70
19.61
22.22
27.03
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 43 of 100
Ground Excavation Ground Excavation Rates (m3/hr): Ground Type
Bucket
Bulk Works
Basements
Trenches
Small & Deep
Sand/Soil
0.3m3
8.7
8.0
7.1
8.4>
0.4m3
28.5
15.4
25.0
10.0
0.5m3
50.0
20.0
28.6
13.3
0.3m3
7.1
6.9
6.1
4.5
0.4m3
25.9
14.3
22.2
8.7
0.5m3
40.0
18.1
28.6
11.1
0.3m3
7.1
6.5
6.1
4.1
Gravel
Clay/Chalk
V.Difficult
0.4m3
25.0
13.3
22.2
8.3
0.5m3
40.0
16.7
28.6
10.5
0.3m3
6.1
5.9
5.4
4.1
0.4m3
22.2
11.8
20.0
7.7
0.5m3
28.6
11.8
20.0
6.7
Small or Deep Excavations Task / Description
Slow
Ave
Fast
Units
Hydraulic Excavator, 0.3m3 bucket, Sand/Soil
6.7
8.4
9.9
m3/hr
Hydraulic Excavator, 0.3m3 bucket, Gravel Beds
3.2
4.5
5.0
m3/hr
Hydraulic Excavator, 0.3m3 bucket, Clay/Chalk
3.3
4.1
5.2
m3/hr
Hydraulic Excavator, 0.3m3 bucket, Hard Ground
3.3
4.1
5.2
m3/hr
Hydraulic Excavator, 0.4m3 bucket, Sand/Soil
8.2
10.0
11.7
m3/hr
Hydraulic Excavator, 0.4m3 bucket, Gravel Beds
7.1
8.7
10.2
m3/hr
Hydraulic Excavator, 0.4m3 bucket, Clay/Chalk
6.5
8.3
9.4
m3/hr
Hydraulic Excavator, 0.4m3 bucket, Hard Ground
6.3
7.7
9.1
m3/hr
Hydraulic Excavator, 0.5m3 bucket, Sand/Soil
12.2
13.3
15.4
m3/hr
Hydraulic Excavator, 0.5m3 bucket, Gravel Beds
10.2
11.1
12.9
m3/hr
Hydraulic Excavator, 0.5m3 bucket, Clay/Chalk
9.7
10.5
12.1
m3/hr
Hydraulic Excavator, 0.5m3 bucket, Hard Ground
6.1
6.7
7.7
m3/hr
Material Weights Wagon sizes and tonnage capacities vary and should be taken into consideration. • • • •
Rock = 2.5 T/m3 Concrete = 2.4 T/m3 Landfill / CDG = 1.9 T/m3 Sand = 1.8 T/m3
Spoil By Barge Removal / Transportation Of Spoil By Barge: The size, getting material to the facility, location and movement restrictions of the barge loading facilities are critical to production. A 2,000 m3 flat bottom barge, could easily be loaded 1.5 times per day, with a planned allowance of 2 no movements per day for example... • 1,000 m3 barge, filled in 9.5 hrs = 2 movements/day • 1,500 m3 barge, filled in 6.5 hrs = 3.5 movements/day
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 44 of 100
Spoil By Conveyor Removal / Transportation Of Spoil By Conveyor: The size and location of the conveyor are critical to production and should be sized according to the most critical peaks in excavation. • There are the following parameters to select... Max excavation per hour
185 m3/hr
Assume belt size
600 mm
Assume conveyor trough angle 20 degrees • From the above you read off specific parameters from the suppliers table... Recommended belt speed
150 m/min
Angle of repose for dry sand 35 degrees Angle of surcharge
20 degrees
• You must then read off, from the manufacturers tables the conveyor capacity... Cross-sectional area of load
0.02979 m2
At a speed of 150 m/min gives 268 m3/hr • Assume a bulking factor for excavated sane = 15%, and assume 50 minutes work per hour to allow for blockages and maintenance etc... • 268 x 85% x 50/60 = 190 so therefore capacity of conveyor = 190 m3 per hour = OK. Hong Kong Airport Express Station conveyor was capable of 11,500 m3/week.
Ground Compaction Compact & Consolidate Compact & Consolidate using Vibratory Roller or compactor. • • • • •
Sand 31.25 m2/hr Soil 58.82 m2/hr Clay 55.56 m2/hr Hardcore 38.46 m2/hr Ash 57.85 m2/hr
Deep Compaction Essentially required in order to reduce expected ground settlement and to protect underground utilities / structures etc. • Deep compaction by 350 mm dia Vibroflot, 3 m centres in sand. • Working on 12 hour basis, a vibroflot will achieve an output of 3-4,000 m3/shift (5,000 m3/day has been achieved in an extended shift). Ground Compaction Task / Description
Slow
Ave
Fast
Units
330.0
380.0
465.0
m3/hr
28.5
31.2
45.2
m2/hr
Vibro-Roller, Soil
-
58.8
-
m2/hr
Vibro-Roller, Clay
-
55.6
-
m2/hr
Vibro-Roller, Hardcore
-
38.4
-
m2/hr
Vibro-Roller, Ash
-
57.8
-
m2/hr
Deep Vibroflot, 3m centres Vibro-Roller, Sand
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 45 of 100
Hand Fill & Compact Loose from side of excavation, including compaction (m3/hr)... Material
Ne 100m
100-200mm
200-300mm
exc 300m
Loose Sand/Soil
0.85
1.02
1.28
1.69
Clay/Heavy Chalk 0.77
0.92
1.16
1.56
Hoging
0.81
0.97
1.20
1.61
Hardcode
0.71
0.84
1.06
1.41
Ground Monitoring Reclamation & Filling Spread & Leveling Spread and Level Task / Description
Slow
Ave
Fast
Units
13.9
20.4
25.0
m3/hr
7.6
9.5
12.6
m3/hr
14.2
20.4
25.6
m3/hr
7.6
10.2
12.8
m3/hr
12.7
18.4
23.2
m3/hr
Crawler Shovel, 0.8m3 bucket, Clay/Chalk, pushed 50-120m to stockpile
6.9
8.9
11.6
m3/hr
Crawler Shovel, 0.8m3 bucket, Boulder Clay, pushed 5-50m to stockpile
11.6
16.9
21.3
m3/hr
6.3
8.2
10.4
m3/hr
Crawler Shovel, 1.2m3 bucket, Sand/Soil, pushed 5-50m to stockpile
23.8
28.5
35.7
m3/hr
Crawler Shovel, 1.2m3 bucket, Sand/Soil, pushed 50-120m to stockpile
16.7
18.5
20.4
m3/hr
Crawler Shovel, 1.2m3 bucket, Gravel, pushed 5-50m to stockpile
25.0
32.0
37.0
m3/hr
Crawler Shovel, 1.2m3 bucket, Gravel, pushed 50-120m to stockpile
17.2
19.3
21.2
m3/hr
Crawler Shovel, 1.2m3 bucket, Clay/Chalk, pushed 5-50m to stockpile
21.7
27.5
33.3
m3/hr
Crawler Shovel, 1.2m3 bucket, Clay/Chalk, pushed 50-120m to stockpile
15.1
16.9
18.8
m3/hr
Crawler Shovel, 1.2m3 bucket, Boulder Clay, pushed 5-50m to stockpile
19.6
24.5
30.3
m3/hr
Crawler Shovel, 1.2m3 bucket, Boulder Clay, pushed 50-120m to stockpile
13.7
15.9
17.5
m3/hr
Crawler Shovel, 0.6m3 bucket, 50-200m2, Sand/Soil
18.6
28.5
38.5
m3/hr
Crawler Shovel, 0.6m3 bucket, over 200m2, Sand/Soil
24.4
37.2
50.0
m3/hr
Crawler Shovel, 0.6m3 bucket, 50-200m2, Gravel
18.9
28.6
38.4
m3/hr
Crawler Shovel, 0.6m3 bucket, over 200m2, Gravel
24.2
37.2
50.0
m3/hr
Crawler Shovel, 0.6m3 bucket, 50-200m2, Hardcore
15.8
23.5
31.2
m3/hr
Crawler Shovel, 0.6m3 bucket, over 200m2, Hardcore
19.2
29.6
40.0
m3/hr
Crawler Shovel, 0.8m3 bucket, Sand/Soil, pushed 5-50m to stockpile Crawler Shovel, 0.8m3 bucket, Sand/Soil, pushed 50-120m to stockpile Crawler Shovel, 0.8m3 bucket, Gravel, pushed 5-50m to stockpile Crawler Shovel, 0.8m3 bucket, Gravel, pushed 50-120m to stockpile Crawler Shovel, 0.8m3 bucket, Clay/Chalk, pushed 5-50m to stockpile
Crawler Shovel, 0.8m3 bucket, Boulder Clay, pushed 50-120m to stockpile
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 46 of 100
Crawler Shovel, 0.6m3 bucket, 50-200m2, Boulder Clay
17.2
26.4
35.7
m3/hr
Crawler Shovel, 0.6m3 bucket, over 200m2, Boulder Clay
22.2
33.8
45.4
m3/hr
Crawler Shovel, 1.2m3 bucket, 50-200m2, Sand/Soil
43.5
48.0
52.6
m3/hr
Crawler Shovel, 1.2m3 bucket, over 200m2, Sand/Soil
55.5
61.1
66.7
m3/hr
Crawler Shovel, 1.2m3 bucket, 50-200m2, Gravel
43.8
48.3
52.9
m3/hr
Crawler Shovel, 1.2m3 bucket, over 200m2, Gravel
55.5
61.1
66.7
m3/hr
Crawler Shovel, 1.2m3 bucket, 50-200m2, Hardcore
37.1
40.3
43.5
m3/hr
Crawler Shovel, 1.2m3 bucket, over 200m2, Hardcore
47.6
51.6
55.6
m3/hr
Crawler Shovel, 1.2m3 bucket, 50-200m2, Boulder Clay
43.8
45.7
47.6
m3/hr
Crawler Shovel, 1.2m3 bucket, over 200m2, Boulder Clay
55.6
59.1
62.5
m3/hr
Steel Strutting Steel Strutting... Task / Description
Slow
Ave
Fast
Units
Horizontal heavy duty strutting
-
2.0
-
days/no
Diagonal heavy duty strutting
-
6.0
-
days/no
Trench Excavations Trench Excavation... Slow
Ave
Fast
Units
Hydraulic Excavator, 0.3m3 bucket, Sand/Soil
Task / Description
5.6
7.1
8.2
m3/hr
Hydraulic Excavator, 0.3m3 bucket, Gravel Beds
4.8
6.1
7.3
m3/hr
Hydraulic Excavator, 0.3m3 bucket, Clay/Chalk
4.8
6.1
7.1
m3/hr
Hydraulic Excavator, 0.3m3 bucket, Hard Ground
9.7
5.4
6.4
m3/hr
Hydraulic Excavator, 0.4m3 bucket, Sand/Soil
20.5
25.0
29.2
m3/hr
Hydraulic Excavator, 0.4m3 bucket, Gravel Beds
18.2
22.2
26.0
m3/hr
Hydraulic Excavator, 0.4m3 bucket, Clay/Chalk
18.2
22.2
26.0
m3/hr
Hydraulic Excavator, 0.4m3 bucket, Hard Ground
17.0
20.0
23.4
m3/hr
Hydraulic Excavator, 0.5m3 bucket, Sand/Soil
26.0
28.6
33.1
m3/hr
Hydraulic Excavator, 0.5m3 bucket, Gravel Beds
26.3
28.6
33.2
m3/hr
Hydraulic Excavator, 0.5m3 bucket, Clay/Chalk
26.3
28.6
33.2
m3/hr
Hydraulic Excavator, 0.5m3 bucket, Hard Ground
22.7
25.0
28.8
m3/hr
Excavate and Board Trench, 0.5-1.5m deep, < 2.0m wide
3.3
4.5
6.8
m2/hr
Excavate and Board Trench, 1.5-3.0m deep, < 2.0m wide
3.0
4.2
6.5
m2/hr
Excavate and Board Trench, 3.0-4.5m deep, < 2.0m wide
2.7
4.0
6.0
m2/hr
Excavate and Board Trench, 0.5-1.5m deep, > 2.0m wide
6.6
7.1
8.8
m2/hr
Excavate and Board Trench, 1.5-3.0m deep, > 2.0m wide
6.2
6.7
9.2
m2/hr
Excavate and Board Trench, 3.0-4.5m deep, > 2.0m wide
5.8
6.2
10.5
m2/hr
Ground Trench Excavation Strut Rates Ground Trench Excavation / Strut Rates (m2/hr) Trench width not exceeding 2.0 m wide
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 47 of 100
Trench Depth -->
Ne1.5m
1.5-3m
3-4.5m
Single horiz boards
Fix Strike
16.7 33.3
--
--
Double horiz boards
Fix Strike
7.7 16.7
7.7 14.3
--
Single strut vert boards
Fix Strike
14.3 33.3
--
--
Close Boards,with whaling
Fix Strike
4.5 9.1
4.2 8.3
4.0 8.0
Trench width exceeding 2.0m wide
Trench Depth
Ne1.5m
1.5-3m
3-4.5m
Single horiz boards
Fix Strike
5.6 11.1
5.3 10.0
--
Double horiz boards
Fix Strike
7.1 14.3
7.1 14.3
--
Single strut Fix Strike vert boards
5.9 112.5
5.6 11.1
5.3 10.0
Close Boards, with whaling
7.1 14.3
6.7 1.3
6.7 12.5
Fix Strike
Traditional mass fill foundations Includes excavation and concrete pour. Assumes 450mm wide, average of 1.5m deep, No earthwork support, reinforcement or claymaster. 35 linear metres per day per gang.
Fencing Works Fencing Works Task / Description
Slow
Ave
Fast
Units
Site Hoarding, timber posts, plywood nailed to horizontal rails
1.0
1.2
-
m/hr
Post Erection, Timber / Metal, dig, erect, fix
3.3
4.5
-
no/hr
Post Erection, Concrete, dig, erect, fix
3.2
4.0
-
no/hr
Fence Erection, Chainlink, posts at 1.5m
-
4.2
-
m/hr
Fence Erection, Chainlink, posts at 2.0m
-
4.4
-
m/hr
Fence Erection, Chainlink, posts at 3.0m
-
5.5
-
m/hr
Fence Erection, Chestnut Pailings, posts at 1.5m
-
23.8
-
m/hr
Fence Erection, Chestnut Pailings, posts at 2.0m
-
33.3
-
m/hr
Fence Erection, Chestnut Pailings, posts at 3.0m
-
41.6
-
m/hr
Fence Erection, Barbed Wire, posts at 1.5m
-
71.4
-
m/hr
Fence Erection, Barbed Wire, posts at 2.0m
-
100.0
-
m/hr
Fence Erection, Barbed Wire, posts at 3.0m
-
125.0
-
m/hr
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 48 of 100
Gate Erection, Chainlink on frame
-
4.1
-
no/hr
Foundation Works Elements relating to substructures / foundations...
Barrette Piles Barrette Piles Task / Description
Slow
Ave
Fast
0.5
1.1
1.2
-
4.0
-
40.0
50.0
55.0
Trimming top of barrette panels
-
2.4
-
days/no
Concrete Testing, Coring Test
4.0
3.5
2.0
days/no
-
0.7
-
days/no
Rule of Thumb, overall rate by Mill Fabricate reinforcement cages Concreting barrette panels
Concrete Testing, Sonic Logging Test
Units hrs/no hrs/cage m3/hr
Bored Piling Pre-Drilling - Site Investigation • Pre-boring will be carried out at each location to ascertain the target founding level. • Rotary rig drilling operations incorporate the use of a steel core that is used when a core sample is required. Another type of boreing is called “Wash Bore” or “Percussive Bore” which simply means that a bore is flushed out and is used when no soil sample is required. Typical rates are... Type of Strata
Plant Used
Rate (m/hr)
Top soft deposits of site fill Percussive / Rotary
10.00
Grade V/IV rock deposits
3.15
Wash Boring
Triple Tube Sampling 0.75 Grade III/II rock deposits
Rotary
0.50
Triple Tube Sampling 0.50
With a standard rig, working a 12 hour shift, a typical output rate of 66 hrs/hole/rig is possible. • As-Built Information. On Central Reclamation, Contract UA11/91, borehole drilling completed with the following results... 1. 2. 3. 4.
Average depth of 61.15 m, total depth of 428 m Average rock socket depth of 4.65 m The durations ranged from 4 to 8 days Average of 5.85 days, total duration of 41 days.
The Target Founding level • This is defined as the required socket into the bedrock, which is defined as moderately decomposed rock grade III or better with a core recovery greater than 85% (allowable bearing capacity of 5 mPa). The continuity of the founding rock is demonstrated by continuing the pre-bored hole a maximum of 5 metres or 3 times the pile diameter, whichever is the greater. • The cores are logged, stored and photographed and submitted together with proposed founding levels for approval. Setting Out
Before starting excavation at the pile position the following steps are taken:
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 49 of 100
• Survey and record the existing ground level at the pile position • Setout the pile location from the reference points and in order to monitor the position of the steel casing, control pins are usually established at two orthogonal positions, offset from the centre of the pile. Pile Tolerances • In the case of out of position casings, adjustment can be made to keep the vertical alignment and plan position within the limits of no more than 75 mm off-centre on plan position and not deviating by more than 1:75 from the vertical axis. Pile Excavation / Casings • The shaft of the pile is excavated within a temporary steel casing with an outside diameter of say approximately 200 - 300 mm greater than the pile diameter. The casing is used mainly in areas of unstable ground and are driven using hydraulic casing oscillator attached to a crawler crane or a casing vibrator. • Shaft excavation is carried out using a single or double hammer grab supported by crawler crane. The steel casing toe is kept in front of the excavation level until it is 0.5 metres above the pile cut-of level. The pile shaft is often flooded with bentonite or water and excavation proceeds to the top of the CDG. • Excavation then proceeds by reverse circulation drilling (RCD) using large diameter drilling heads with special rock cutters and flushing by air lift. Bentonite or water levels are always maintained above the ground water level to ensure stability of the shaft. Calculation Of Bored Pile Construction / Excavation Time • Piling times can be reduced by the use of service cranes for reinforcement and concreting activities. • An additional extended shift would often be required for certain piles, as would RCD down-time. • Forecast construction times can be derived by using output rates (hours per item)...
Operation
Element
Details
Hours
Add or Remove
Reverse Circluation Drill Plant (RCD)
incl drill bit
2 hrs
Add or Remove
RCD drill bit
(incl assembly of drill string) 5 hrs
RCD bell-out bit
(incl drill string & stabilisers) 5 hrs
Installation
Cleaning Time
Concreting
Airlift tremmie tube
5 hrs
Reinforcement cages
(time for joining each cage) 2 hrs
Initial airlift cleaning
(after finishing excavation)
8 hrs
Final airlift cleaning
(after fixing steel cage)
2 hrs
Incl extract casing
( < 70 m deep)
12 hrs
( > 70 and < 95 m deep)
14 hrs
( > 95 and < 135 m deep)
48 hrs
Curing Time
Only required prior to removal of telescopic casings
72 hrs
Cycle Time
Move piling setup to next location
2 hrs
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 50 of 100
Shaft Excavation Strata
Plant Used
Rate (m/hr)
General Fill (upper ground levels)
Grab
3.50 m/hr
Sand, Minor Rubble
Grab
2.10 m/hr
Marine / Alluvium Deposits
Grab
2.50 m/hr
CDG < 150
RCD/Grab
1.50 m/hr
CDG > 150 < 200
RCD
1.00 m/hr
CDG > 200, Compacted Gravel
RCD
0.50 m/hr
CDT
RCD / Grab
0.50 m/hr
Corestones
RCD / Chisel
0.50 m/hr
Rock Socket - Grade IV/V
RCD
0.25 m/hr
Rock Socket - Grade II/III
RCD
0.125 m/hr
Rock Socket - (Tendering Rate)
RCD
0.10 m/hr
• Forecast excavation or cycle times can then be derived by analysing ground conditions. Site investigation will provide the depths / types of strata which can then be matched to production output rates (see above). • Note - A pile’s diameter has negligible effect on production time and as such is ignored. Example - For a pile founding on rock at 60 m deep... (a) Calculate Allowance For Plant Time / Other Elements (hrs)....
Element
Hours
Set up RCD
5.0
Excavate Time
See Below
Remove RCD (including drill bit, string and stabilisers) 5.0
Setup / Remove Airlift Tremmie Tube
5.0
Initial Post-Excavation Airlifting
5.0
Place reinforcement (5 No cages @ 12m = 5 x 2 hrs)
10.0
http://www.planningplanet.com/print/book/export/html/422384
11/3/2014
Page 51 of 100
Setup / Remove Airlift Tremmie Tube
5.0
Final Post-Reinforcement Airlifting
2.0
Concrete and remove casing
12.0
Move to next location
2.0
Calculate Total Construction / Plant Time
52.0 hrs
(b) Calculate Allowance For Excavation Time (hrs)...
Depth of Strata (m) Type of Rock
Production Rate (m/hr) Plant Used Time (Hrs)
0 - 20
Sand/minor rubble
2.00
Grab
10.0
20 - 35
CDG less than 150
1.50
RCD/Grab
10.0
35 - 47
CDG more than 150
1.00
RCD
12.0
47 - 57
CDG > 200/corestones
0.50
RCD
20.0
57 - 60
Rock socket
0.20
RCD
15.0
(c) Calculate Total Pile Excavation Time = 67.0 hrs (d) Overall Pile Time
Construction / Plant Time (“b” above) 52.0 hrs
Excavation Time
(“d” above) 67.0 hrs
OVERALL CYCLE TIME (“b” + “d”) 119 hrs
(With 12 hr shifts)
(“b” + “d”)
9.9 days
Bored Pile Construction As-Builts • General Rule of Thumb Pile Times (days)...