Productivity Rates No. of working days : 6 days/ week (Saturday to Thursday, Friday is day off) Working shifts : one shift / day Working hours : 8 hours / day Over time and Fridays shall be used if necessary to keep on schedule or to compensate for any unexpected events.

No

Division

Productivity Rate per day

Item Describtion

Crew (Manpower/Equipment)

1

Div 02

Excavation Works

350 m³

1nos Loader  

2

Div 02

Shoring

50 m²

4 shoring labours

3

Div 02

Backfilling

80 m³

2 Roller + 2 compactor + 4 labors

4

Div 02

Preparation of blinding

200 m²

3 Labours + 1 Compactor  

5

Div 02

Anti Termite Control

600 m²

1 labour  

6

Div 02

Kerbstones

75m

3 Masons

7

Div 02

Inerlock Tiles

30m²

4 Masons

8

Div 02

Asphalt

9

Div 03

Concrete Slab

30m²

1 Asphalt paver + Roller + Pnuematic wheel + compacter & compressor  4 carpenters + 2 labour + 4 Steel Fixers

10

Div 03

Concrete Columns

5 nos

2 carpenters + 2 steel Fixers + 2 Labours

11

Div 03

Precast Concrete Cladding

60m²

6 mason + 1 crane

12

Div 03

Concrete Topping / Screed

40m³

5 concreter + 1 finisher  

13

Div 03

Leight weight concrete

60m³

6 concreter + 1 finisher  

14

Div 04

Block Works

15m²

1 Block work mason + 1 Labour  

15

Div 04

Glass Block Works

5m²

1 Mason + 1 Helper  

16

Div 05

Handrails

10m

1 Handrail mason + 1 helper  

17

Div 07

Waterproofing membrane

60m²

1 WP mason

18

Div 07

Protection Board

60m²

1 WP mason

19

Div 07

Building Insulation

100m²

1 Mason + 1 Helper  

20

Div 07

Concrete Pavers for Roof

30m²

1 Tile Layer + 1 Helper  

21

Div 07

Metal panels cladding

30m²

1 Cladding Mason + 1 Helper  

22

Div 07

Aluminium Flashing

60m²

1 Mason + 1 Helper  

23

Div 07

Fire Stop

40mr

1 Mason + 1 Helper  

24 25

Div 08 Div 08

Door Frames Door Leaves

5 Nos 5 Nos

1 Doors carpenters + 1 helper   1 Doors carpenters + 1 helper  

26

Div 08

Door Hardware

5 Nos

1 Doors carpenters + 1 helper  

27

Div 08

Frameless Glass panels

30m²

2 Metal Masons + 1 helper  

28

Div 09

Cement plaster 1st stage

60m²

1 Plaster mason + 1 Helper  

29

Div 09

Cement plaster 2nd stage

30m²

1 Plaster mason + 1 Helper  

30

Div 09

Ceramic walls for wet areas

12m²

1 ceramic mason + 1 helper  

31

Div 09

Ceramic Skirting

30mr

1 ceramic mason + 1 helper  

32

Div 09

G.B partition Studs+1st Layer +Insulation

20m²

2 mason + 1 Helper  

33

Div 09

G.B parititions Closing

50m²

2 mason + 1 Helper  

34

Div 09

Gypsum false ceiling

20m²

1 Mason + 1 Helper  

35

Div 09

Metal false ceiling

30m²

1 Mason + 1 Helper  

36

Div 09

Paint preparation

40m²

1 Painter  

37

Div 09

Painting Coats

40m²

1 Painter  

38

Div 09

Vinyl Tiles

25m²

1 Tile Layer + 1 Helper  

2000m²

111

 

Productivity Rate per day

Item Describtion

Crew (Manpower/Equipment)

No

Division

39

Div 09

Rubber Tiles

25m²

1 Tile Layer + 1 Helper  

40

Div 09

Marble Tiles

12m²

1 Tile Layer + 1 Helper  

41

Div 09

Marble Skirting

30mr

1 Tile Layer + 1 Helper  

42

Div 09

Marble Threshold

20mr

1 Tile Layer + 1 Helper  

43

Div 09

Marble Counter

15mr

1 Tile Layer + 1 Helper  

44

Div 09

Granite Flooring

12m²

1 Tile Layer + 1 Helper  

45

Div 09

Terrazzo Tiles

15m²

1 Tile Layer + 1 Helper  

46

Div 09

Insitu Terrazo tiles

5m²

1 Tile Layer + 1 Helper  

47

Div 09

Carpet Tiles

40m²

1 Tile Layer + 1 Helper  

48

Div 09

Wood Flooring

10m²

1 Mason + 1 Helper  

49

Div 10

Wall & Corner guards

7 nos

1 Mason + 1 Helper  

50

Div 10

Toilet Accessories

5 nos

1 Mason + 1 Helper  

51

Div 10

Access Flooring

20m²

1 Mason + 1 Helper  

52

Div 10

Internal Signage

12 Nos

1 Signage Mason

53

Div 12

Lab Furnitures

10 seats

1 Finishing Carp. + 1 helper  

54

Div 13

Shelter Doors

1 nos

3 Mason + 1 Helper  

55

Div 15

Laying Water supply pipes

30m

1 plumber + 1 helper  

56

Div 15

Laying Drainage pipes

24m

1 plumber + 1 helper  

57 58

Div 15 Div 15

Laying Fire Fighting Pipes Laying HVAC Ducts

24m 70 kg

1 FF Pipe Fitter + helper   1 Duct Fitter + 1 helper  

59

Div 15

Duct Insulation

20 m

1 Duct Fitter + 1 helper  

60

Div 15

HVAC Piping

20m

1 Pipe Fitter + 1 helper  

61

Div 16

Installing Cable Trays

15m

1 Electrician + Helper  

62

Div 16

Electrian Conduiting

24m

1 Electrician + Helper  

63

Div 16

Wiring Works

400m

3 Electricians + 3 helpers

64

Div 16

Laying Cables

20m

3 Electricians + 3 helpers

112