Product Costing - Cost Estimation in SAP
Short Description
Download Product Costing - Cost Estimation in SAP...
Description
Product Costing - Cost Estimation in SAP Cost Estimation •
The price of the finished goods (FG) and semi-finished goods (SFG) manufactured is determined through Standard Cost estimate.
•
Standard cost is estimated based on the cost of input materials, planned cost of activities and overheads.
•
It is the price at which the finished and semi-finished goods are valuated in finance.
•
The standard cost once estimated is valid for a specific period interval.
•
A standard cost estimate is created at the end of the period and is valid for the entire next period.
•
When the standard cost estimate for the respective material (FG & SFG) is released, the system updates the result of this estimate as standard price in ‘Accounting 1’ and ‘Costing 2’ view detail screen of the material master record.
•
This price is then valid for valuation of material in financial accounting till next cost estimate is run.
•
The materials are revaluated when the next standard cost estimate is released.
•
In this specific period interval, all the FG and SFG produced through production order or product cost collector are valued at the standard cost updated in the material master.
•
This is termed as ‘Cost of goods manufactured’ (COGM).
Following are the important tools used in cost estimate. •
Costing Variant
•
Cost Component Split
•
Costing Estimate with/without quantity structure
•
Costing Run/Price Update The above mentioned tools have been discussed in detail in this article to cover the concept behind the standard cost estimate in SAP.
Costing Variant
It is a key based on which standard cost is performed and valuated. Following are the control parameters in costing variant. (a) Costing Type : It updates price such as ‘Standard price’ or ‘Commercial price’ or ‘Tax valuation’ price depending upon the price update type. It contains the ‘calculation base ’ based on which prices are updated in material master for FG and SFG. For inventory valuation, calculation base will always be ‘COGM’. The COGM value will be determined through ‘Cost component split’. (b) Valuation Variant: It searches prices of input materials, activities and overhead ( overhead cost sheet ) during cost estimate. The strategy sequences for searching of the prices are specified for input materials, activities and overhead in the valuation variant. The strategy sequence prioritizes whether moving Avg. price, standard price or Info record price is to be picked up for input material, plan or actual price is to be picked for activities. It also specifies which costing sheet is to be used for overhead calculation (Material OH, Production OH). Strategy Sequence : Input Material Priority Strategy Sequence 1 2
Moving Average Price Last Price from Purchasing Info Record
Strategy Sequence : Activity Prices
Priority Strategy Sequence 1. Actual Price of Previous Period 2. Plan Price for the Period 3. Plan Price as Average of All Fiscal Year Periods (c) Date Control : It determines period for which cost estimate is applicable. (d) Quantity Structure control : It determines BOM and routing which is to be considered for costing. It considers only those BOM and Routing which have the status ‘Release for Costing’. Cost Component Split What elements of costs are to be considered in ‘Cost of goods manufactured (COGM)’ is specified in Cost component structure. Each cost component mentioned in Costing (A) are captured in controlling through cost elements which are grouped in Cost Component Structure (B) as COGM, COGS. In Costing Type of costing variant, COGM will be specified as the calculation base for standard cost. Therefore, the summation of COGM in Cost component structure will be carried to SFG’s and FG’s material master as standard cost.
Cost estimate with quantity structure - CK11N •
Cost estimate with quantity structure is a tool for estimating material costs.
•
It calculates standard cost of goods manufactured.
•
CK11N is the transaction code for cost estimate with quantity structure.
•
In cost estimate SFG or FG code, plant, costing variant, costing version, costing period interval, quantity structure date ( BOM and Routing), valuation date for input material in BOM and activities in routing needs to be specified.
•
All dates as mentioned are defaulted by the system through Date control in costing variant which can be overwritten manually.
•
In cost estimate, the system on the basis of costing variant and the finished good item code specified determines the quantity structure of the BOM and Routing.
•
It then valuates the input materials in the BOM and the production activities from the routing with prices according to the strategy sequence maintained in the Valuation Variant (see costing variant) for input material and activities.
•
It calculates the overhead as per Costing Sheet maintained in costing variant.
•
Cost estimate gives break up of the costing according to the cost component split defined for the cost estimate.
•
Cost estimate result needs to be saved before price update run or costing run.
•
The cost estimate with quantity structure accesses data in the Production Planning (PP), Materials Management (MM), and Controlling (CO) application of the SAP System.
Cost Estimates without Quantity Structure: KKPAN •
Costing without a quantity structure is a tool for planning costs and setting prices for materials without reference to quantity structure ( BOM and routing ) in Production Planning.
•
It is intended for materials with insufficient or no quantity structure data. It can also be used to enter data from non-SAP systems.
•
This is very useful while simulating costing based on Management requirement without creating quantity structure in the system.
•
A material cost estimate without a quantity structure enables to plan the costs for raw materials, internal activities, and external activities for a product in the form of a unit cost estimate.
•
Unit costing is a type of spreadsheet that, due to its integration, can use existing master data and prices in the system, such as activity prices from Cost Center Accounting.
•
Cost estimates without quantity structure can access data in various application components: • Materials Management (MM), such as material master records and services • Production Planning (PP), such as work centers and resources • Controlling (CO), such as cost centers and activity types
Costing Run / Price update: •
Once cost estimate is carried out, costing results needs to be transferred to material master for updating prices.
•
Depending on the purpose of costing (Inventory valuation for AS-2, simulation costing for the purpose for management decision etc), selected price controls( Standard Price, Tax Valuation Price, Commercial Price) specified in the costing type ( see costing variant ) in the material master can be updated.
•
When the cost estimate is ‘Marked’ Future standard price in the material master is updated.
•
After marking, the cost estimate is ‘Released’, the new released standard price becomes the ‘Current standard price’ and standard price previously updated in ‘Current standard price’ is updated in the ‘Previous standard price’.
•
The existing inventory gets revalued with the new current standard price and system passes following accounting entry for revaluation. FG/ SFG inventory A/c Dr / Cr Revaluation – Inventory Dr / Cr
SAP T Code To be used Create Cost Estimate with quantity structure
CK151N
Display Cost Estimate with quantity structure
CK13N
Comparison with itemization
CK33
Create Cost estimate without quantity structure
KKPAN
Change Cost estimate without quantity structure
KKPBN
Display Cost Estimate without quantity structure
KKPCN
Price Update
CK24
Create Costing Run
CKMATSEL
Edit Costing Run
CKMATCON
Accounting → Controlling → Product Cost Controlling → Material Costing → Cost Estimate with Quantity Structure → CK11N - Create
•
Accounting → Controlling → Product Cost Planning → Material Costing → Cost Estimate with Quantity Structure → CK13N – Display
•
Accounting → Controlling → Product Cost Controlling → Product Cost Planning → Material Costing → CK24 - Price Update → CK24 Price Update
•
• •
•
• • • • • • • • • •
You prepare the material cost estimate with quantity structure, on basis of data provided by Production Planning module. The cost estimate is a tool for planning non order-related costs and establishing prices for materials. It is used to calculate the cost of good manufactured and cost of good sold for each product unit You can see the results of the saved material cost estimate. From here, you can call the reports for analysis purposes. You want to display & analyse cost estimate that you have calculated & saved. You see the costing information, such as BOM, Routing, costing variances etc, and you can see the cost estimates in 3 view: (1) itemization, (2) cost component - primary split view, (3) cost component – process view. Once you have carried out a cost estimate for a material, you can transfer the costing results to the material master as prices. To set a new standard price in the material master, you must mark and release the standard cost estimate. Before you can mark and release a standard cost estimate, you must allow standard cost estimates to be marked and released in a company code. If you release a standard cost estimate for a material, the marked price is transferred into the material master record as the current standard price for the current period. This price is then active for external accounting. The materials with "S" price control are valuated with the new standard price. The current standard price becomes the previous standard price. Simultaneously periodic unit price is used in single-level and multilevel material price determination to valuate the materials for the closed period. Once you have released the cost estimate, you cannot create a new standard cost estimate in this period. Although you can delete a released cost estimate, the materials are still valuated with the released standard price. When a current standard cost estimate is deleted, the previous standard price no longer becomes the current standard price. To determine a new standard price, you have to carry out costing, marking and releasing afresh
Once you have carried out a cost estimate for a material, you can transfer the costing results to the material master as prices. To set a new standard price in the material master, you must mark and release the standard cost estimate. Before you can mark and release a standard cost estimate, you must allow Accounting → Controlling → Product standard cost estimates to be marked and released in a company code. Cost Controlling → Product Cost Planning → Material Costing → CK24 - If you release a standard cost estimate for a material, the marked price is transferred into the material master record as the current standard price for the current period. This price is then Price Update → CK24 - Price Update active for external accounting. The materials with "S" price control are valuated with the new standard price. The current standard price becomes the previous standard price. Simultaneously periodic unit price is used in single-level and multilevel material price determination to valuate the materials for the closed period. Once you have released the cost estimate, you cannot create a new standard cost estimate in this period. Although you can delete a released cost estimate, the materials are still valuated with the released standard price. When a current standard cost estimate is deleted, the previous standard price no longer becomes the current standard price. To determine a new standard price, you have to carry out costing, marking and releasing afresh. CK24 Release Price Update
The cost estimate has the status ‘VO: Marked without errors’. Only the results of cost estimates that have been marked without errors can be released.
CK40N Edit Costing Run
The costing run enables to cost, analyze, mark and release more than one product at the same time. Costing with quantity structure results in an explosion of the BOM and the derivation
of activity prices from the routings and work centers to create a cost estimate for each product. Marking the cost estimate results in the standard price becoming visible on the material master in the field Planned Price as the future standard price. Releasing the cost estimate can occur once the period roll-over has happened and the standard price becomes the current valuation price of the product. A financial document is created for the valuation difference of stock. Every goods issue in the new period will effectively be valued against the new standard price. Mass costing run for all products that are valuated at standard price. Requirements Bill of Materials (BOM’s) must be maintained. Activity prices must exist as planned prices on the cost centers linked to Work Centers. Routings and activity types must be maintained. Accounting →Controlling →Product Cost During Production order settlement, either Work In Process (if incomplete delivery) or Variance (if complete delivery) is posted. If Variance is posted, any WIP posted before will be reversed. Controlling →Cost Object Controlling →Product Cost by Order→Period-End You want to post WIP or Variance after WIP & Variance calculation Closing→Single Functions →Settlement→ CO88 - Collective Processing Accounting → Controlling → Product The costing run enables to cost, analyze, mark and release more than one product at Cost Controlling → Product Cost the same time. Planning → Material Costing → CK40N - Edit Costing Run Costing with quantity structure results in an explosion of the BOM and the derivation
of activity prices from the routings and work centers to create a cost estimate for each product. CK40N Edit Costing Run
Marking the cost estimate results in the standard price becoming visible on the material master in the field Planned Price as the future standard price. Releasing the cost estimate can occur once the period roll-over has happened and the standard price becomes the current valuation price of the product. A financial document is created for the valuation difference of stock. Every goods issue in the new period will effectively be valued against the new standard price. Bill of Materials (BOM’s) must be maintained. Activity prices must exist as planned prices on the cost centers linked to Work Centers. Routings and activity types must be maintained. Mass costing run for all products that are valuated at standard price.
Accounting → Controlling → Product Cost Controlling → Product Cost Planning → Environment → Costing Run → CK44 - Delete Costing Run
The administrative data for the costing run (name, description, selection and structure explosion) is deleted. The material cost estimates themselves are not deleted. You have to delete them in a second step (delete test data).
CKAPP01 Display materials to be costed
The report displays the following materials:
You have created costing run that you no longer wanted in the system. For example costing run with wrong dates or costing variant. When you create a new costing variant, you want to delete the first one with error.
•
Materials that can be costed (the No Costing indicator is not set in the costing view of the material master) • Materials for which no marked or released standard cost estimates exist in the system This report can be used to check if materials that do not have cost estimate (marked or released). Scenario Run this report to check if there are any semi-finished products ‘HALB’ or finished products to be costed in plant 1200.
CKAPP03 Display sales order to be costed
You can call up this report to obtain a quick overview of the sales order items to be costed. Flat product materials are costed on the sales order. The materials are costed and marked when the sales order is saved. It is possible that a sales order cost estimate, may be saved with error due to routings or BOM changes. In order to monitor these sales orders with incorrect cost estimates you need to run this report. The report lists down the sales order in the order of delivery date. The report has 2 columns Status SD and Costing status. In case of incorrect cost estimate the Status SD column will show COST and the costing status as blank. Run this report periodically or daily to find the sales order to be costed for configured material
You can delete costing results that are no longer required from the database when you specify certain criteria. This function is called reorganization You can delete cost estimates:• Future standard cost estimates Accounting → Controlling → Product • Current standard cost estimates Cost Controlling → Product Cost • Previous standard cost estimates Planning → Environment → Material • Cost estimates not in material master (cost estimates saved but not yet Costing → CKR1 - Delete Test Data marked or released) Wrong cost estimate, due to wrong price of raw materials or error in BOM & routing, can be deleted. Then new cost estimates can be calculated. Be careful not to delete ‘Current standard cost estimates’ if there is already transaction data for that month. CKR1 - Delete Test Data A cost estimate can only be deleted if it is not locked. CKR1 Reorganization of cost estimate
CO03 Display PP Production order Accounting → Controlling → Product Cost Controlling → Cost Object Controlling → Product Cost by Order → Order → PP Production Order → CO03 - Display
The PP Production order is the cost object for carrying production costs for manufacture of Finished product. All costs such as Material consumption, internal activities consumption is collected on the production order. The production order also provides the comparison of the planned cost, target cost and actual cost. . You need to see the actual costs collected on the Production order and also compare it with the planned cost.
CO88 Settlement prodn order collective During Production order settlement, either Work In Process (if incomplete delivery) or Variance (if complete delivery) is posted. If Variance is posted, any WIP posted before will be reversed. Accounting →Controlling →Product Cost Controlling →Cost Object Controlling You want to post WIP or Variance after WIP & Variance calculation. →Product Cost by Order→Period-End Closing→Single Functions Work In Process and Variance was calculated. →Settlement→CO88 - Collective Processing CO88 - Collective Processing. Accounting → Controlling → Product Cost Controlling → Product Cost Planning → Information System → Summarized Analysis → Analyze Costing Run → S_ALR_87099931 - Price vs Cost Estimate
•
•
In this transaction you can compare the selected cost estimates against a material master price that you select. You want to compare the cost estimate calculated in the particular costing run with the current standard price of materials.
During Product Cost Collectors settlement, either WIP (at target cost) or Variance (if or both) is posted. Through the production process, Product Cost Collectors are debited with actual costs. The actual costs posted to a product cost collector can be more or less than the value with which a product cost collector was credited when the goods receipt was posted. Accounting → Controlling → Product When you settle, this difference between the debit and credit of the product cost collector is transferred to Financial Accounting (FI). Settlement also feeds data from Cost Controlling → Cost Object Cost Object Controlling to other components. Controlling → Product Cost by The following can happen during the settlement process: Period → Period-End Closing → The order balance can be reduced to zero by transferring to Financial Accounting (FI) Single Functions: Product Cost the difference between the preliminary inventory valuation (goods receipt) and the Collector → Settlement → KK87 actual costs incurred. The price difference can also be transferred to Profit Center Individual Processing KK87 Settlement of Prod. Cost Coll – Individual
Accounting (EC-PCA). The total variance can be transferred to profitability segments in Profitability Analysis (CO-PA). This enables you to see an additional contribution margin in CO-PA. You can transfer the individual variance categories of the total variance to value fields in COPA in combination with certain cost elements or cost element groups You want to post WIP or Variance after WIP and Variance calculation. The WIP calculation function valuates the unfinished products (work in process). In the Product Cost by Period component, work in process is valuated at target costs. Accounting → Controlling → The operation quantities confirmed for the manufacturing orders or production versions Product Cost Controlling → Cost (only in repetitive manufacturing) that are not scrap are valuated at target cost in Object Controlling → Product Cost accordance with the valuation variant for work in process and scrap. by Period → Period-End Closing → You calculate work in process at target costs for the following objects: Single Functions: Product Cost • Product cost collectors Collector → Work in Process → • Production orders with quantity structure assigned to the product cost collectors Collective Processing → KKAO • Process orders assigned to the product cost collectors Calculate • As part of the period end processing Work In Process needs to be calculated for accurate period end closing. KKAO Calculate WIP for PCC Coll
Calculate WIP prodn order collective – KKAO Accounting → Controlling → Product Cost Controlling → Cost Object Controlling → Product Cost by Order → Period-End Closing → Single Functions → Work in Process → Collective Processing → KKAO Calculate
The system calculates Work In Process (WIP) to determine the costs incurred for materials that have not yet been delivered to stock. This calculates the value of the unfinished goods. In Product Cost by Order the work in process is calculated for the Manufacturing Order. The work in process for manufacturing orders is normally calculated at actual costs. Work in process at actual costs is calculated as the difference between the debits for material withdrawals, internal activity allocations, external activities, and overhead costs (that is, the Actual Costs assigned to the object) and the Actual Credits from goods receipts for delivery to stock. The work in process can be transferred to Financial Accounting and Profit Center WIP = amount if only partial Goods Receipts has been performed. WIP = 0 if only complete Goods Receipts has been performed. You want to calculated WIP either when Order is completed or at month end. WIP must be calculated when order is completed. In this case WIP =0. WIP must also be calculated at month end even though order is not completed. In this case WIP=amount.
The system calculates Work In Process (WIP) to determine the costs incurred for materials that have not yet been delivered to stock. This calculates the value of the unfinished goods. In Product Cost by Order the work in process is calculated for the Manufacturing Order. The work in process for manufacturing orders is normally calculated at actual Accounting → Controlling → Product costs. Work in process at actual costs is calculated as the difference between the debits for material withdrawals, internal activity allocations, external activities, and Cost Controlling → Cost Object overhead costs (that is, the Actual Costs assigned to the object) and the Actual Credits Controlling → Product Cost by from goods receipts for delivery to stock. Order → Period-End Closing → Single Functions → Work in Process The work in process can be transferred to Financial Accounting and Profit Center WIP = amount if only partial Goods Receipts has been performed. → Collective Processing → KKAQ WIP = 0 if only complete Goods Receipts has been performed. Display KKAQ Display WIP for CO Production Order Coll.
KKAS Calculate WIP for PCC – Individual Accounting → Controlling → Product Cost Controlling → Cost Object Controlling → Product Cost by Period → Period-End Closing → Single Functions: Product Cost Collector → Work in Process → Individual Processing → KKAS Calculate
The WIP calculation function valuates the unfinished products (work in process). In the Product Cost by Period component, work in process is valuated at target costs. The operation quantities confirmed for the manufacturing orders or production versions (only in repetitive manufacturing) that are not scrap are valuated at target cost in accordance with the valuation variant for work in process and scrap. You calculate work in process at target costs for the following objects: • Product cost collectors • Production orders with quantity structure assigned to the product cost collectors • Process orders assigned to the product cost collectors As part of the period end processing Work In Process needs to be calculated prior to variance calculation and settlement for accurate period end closing
Display WIP for Product Cost – Collective - KKAT Accounting → Controlling → Product Cost Controlling → Cost Object Controlling → Product Cost by Period → Period-End Closing → Single Functions: Product Cost Collector → Work in Process → Individual Processing → KKAT Display
• • •
The system calculates the work in process. The work in process is updated to the product cost collector or manufacturing order under results analysis cost elements. You want to display work in process that you calculated.
KKAX Calculate WIP IndividuallyKKAX Accounting → Controlling → Product Cost Controlling → Cost Object Controlling → Product Cost by Order → Period-End Closing → Single Functions → Work in Process → Individual Processing → KKAX Calculate
The WIP calculation process valuates the unfinished products (work in process). In the Product Cost by Order component, the work in process is valuated at actual costs. Work in process is the difference between the debit and credit of an order that has not been completely delivered. This method determines the work in process for each production order by calculating the difference between the actual costs incurred and the actual costs settled (that is, the difference between the debits for goods issues, internal activity allocations, external activities, and overhead on the one hand, and the credits for goods receipts on the other). Once the last part of the order lot has been delivered to stock, any remaining work in process must be canceled so that the order costs can properly be settled to stock. The status of the order determines whether WIP calculation creates or cancels the work in process. If the order has the status REL (released), the system can calculate work in process. Once the order receives the status DLV (Delivered) or TECO (Technically completed), the work in process calculated in a previous period is canceled.
Display WIP for Prod. Order – Individual - KKAY Accounting → Controlling → Product Cost Controlling → Cost Object Controlling → Product Cost by Order → Period-End Closing → Single Functions → Work in Process → Individual Processing → KKAY - Display
The system calculates Work In Process (WIP) to determine the costs incurred for materials that have not yet been delivered to stock. This calculates the value of the unfinished goods. In Product Cost by Order the work in process is calculated for the Manufacturing Order. The work in process for manufacturing orders is normally calculated at actual costs. Work in process at actual costs is calculated as the difference between the debits for material withdrawals, internal activity allocations, external activities, and overhead costs (that is, the Actual Costs assigned to the object) and the Actual Credits from goods receipts for delivery to stock. The work in process can be transferred to Financial Accounting and Profit Center WIP = amount if only partial Goods Receipts has been performed. WIP = 0 if only complete Goods Receipts has been performed.
Accounting → Controlling → Product Cost Controlling → Cost Object Controlling → Product Cost by Order → Information System → Tools → Data Collection → S_ALR_87013099 – For Product Drill down
To select data for a drill down report, you must first execute a data collection run. The selected dataset is saved. You access this saved dataset when you execute the report. You can execute the data collection for one plant or for all plants in a controlling area.
KKS1 Accounting → Controlling → Product Cost Controlling → Cost Object Controlling → Product Cost by Order → Period-End Closing → Single Functions → Variances →
You can also select the summarization time frame. The values in the summarization time frame are re-summarized and any old values are overwritten. Summarized values that are outside of the summarization time frame are retained. • This step should be done before you execute the product drill down report
Collective Processing The system compares the control costs with the target costs and assigns the variances to variance categories. The variances are assigned to variance categories in the following sequence: • Input price variance • Resource-usage variance • Input quantity variance • Remaining input variance • Mixed-price variance • Output price variance • Lot size variance • Remaining variance Variance = 0 if only partial Goods Receipts has been performed.
•
KKS2
•
Accounting → Controlling → Product Cost Controlling → Cost Object Controlling → Product Cost by Order → Period-End Closing -> Single Functions → Variances → KKS2 - Individual Processing
Variance calculation product cost collector – collective Processing • • •
•
KKS6
Same Narration
KO88
Individual Processing • •
During Production order settlement, either Work In Process (if incomplete delivery) or Variance (if complete delivery) is posted. If Variance is posted, any WIP posted before will be reversed. You want to post WIP or Variance after WIP & Variance calculation
Actual costs
KRMI Accounting → Controlling → Product Cost Controlling → Cost Object Controlling → Product Cost by Period → Information System → Reports for Product Cost by Period → Line Items → Product Cost Collectors → KRMI - Actual Costs
You use this transaction to calculate the variances for all product cost collectors in a plant. The system compares the control costs with the target costs and assigns the variances to variance categories. Target cost version 0 is used to explain the difference between the debit and credit of the product cost collector or manufacturing order. The target costs calculated on the basis of the current standard cost estimate are compared with the actual costs from which the work in process has been deducted. The difference is assigned to different variance categories depending on the cause. Only the variances calculated with target cost version 0 can be transferred to Profitability Analysis (CO-PA). With target cost version 1, production variances for the product cost collector are calculated using the target costs determined on the basis of the preliminary cost estimate for the product cost collector. If you are using a product cost collector, the target costs cannot be determined on the basis of the preliminary cost estimate for the manufacturing order. Target cost version 1 is used for informational purposes. It cannot be settled.
Variance calculation product cost collector – Individual Processing
Accounting → Controlling → Product Cost Controlling → Cost Object Controlling → Product Cost by Period → Single Functions: Product Cost Collector → Variances → KKS6 - Individual Processing
Accounting →Controlling →Product Cost Controlling → Cost Object Controlling → Product Cost by Order → Period-End Closing → Single Functions → Settlement → KO88 - Individual Processing
Individual Processing
Same Narration
KKS5 Accounting → Controlling → Product Cost Controlling → Cost Object Controlling → Product Cost by Period → Period-End Closing → Single Functions: Product Cost Collector → Variances → KKS5 - Collective Processing
Variance = amount if only complete Goods Receipts has been performed.
• • • •
This transaction gives you the actual line items on the Product Cost Collectors created for particular material and production version. In Product Cost Controlling costs are collected on Product Cost Collectors with order types: RM01 - PCC for Repetitive Manufacturing RM01 - PCC for Process Orders CP01 – CO Production Orders
S_ALR_87013046 Accounting → Product Cost Controlling → Product Cost Planning → Information System → Object Comparisons → For Material → S_ALR_87013046 - Material Cost Estimate vs. Preliminary Order Cost Estimate
Material Cost Estimate vs. Preliminary Order Cost Estimate. • • •
S_ALR_87013099 Accounting → Controlling → Product Cost Controlling → Cost Object Controlling → Product Cost by Period → Information System → Reports for Product Cost by Period → Object Comparisons → S_ALR_87013099 - Order vs. Order Plan/Actual Comparison
Order Plan/Actual Comparison • • • • •
• • • • • • •
This transaction gives you a list of the orders. You can also view the details for an order from the order list. In Product Cost Controlling costs are collected on Product Cost Collectors with order types: RM01 - PCC for Repetitive Manufacturing RM01 - PCC for Process orders CP03 - Planning CO Production Orders This transaction gives you a list of the orders. You can also view the details for an order from the order list.
Price versus Cost estimate
S_ALR_87099931 Accounting → Controlling → Product Cost Controlling → Product Cost Planning → Information System → Summarized Analysis → Analyze Costing Run → S_ALR_87099931 - Price vs Cost Estimate
This transaction allows you to compare the costs of to separate cost collectors. The reporting time frame can be cumulative or limited. Two orders are compared with each other on the basis of cost elements. Only the actual costs of two product cost collectors can be compared, because no planned costs are updated on product cost collectors. In Product Cost Controlling costs are collected on Product Cost Collectors with order types: RM01 - PCC for Repetitive Manufacturing RM01 - PCC for Process Orders CP01 – CO Production Order
LIST OF ORDERS - Order Selection.
S_ALR_87013127 Accounting → Controlling → Product Cost Controlling → Cost Object Controlling → Product Cost by Period → Information System → Object List → S_ALR_87013127 Order Selection
Report that compares a material cost estimate with the preliminary cost estimate for a manufacturing order. You can use this report to compare a material cost estimate with the planned costs of manufacturing orders for this material. You can use transaction KOC4 to find orders by material and plant. After execution you can even display plan comparison between two selected orders via Goto -> Detailed analysis.
• •
•
In this transaction you can compare the selected cost estimates against a material master price that you select. You want to compare the cost estimate calculated in the particular costing run with the current standard price of materials.