PRINCE2_LESSON_14.pdf

Share Embed Donate


Short Description

Download PRINCE2_LESSON_14.pdf...

Description

PRINCE2® Foundation Lesson 14—Initiating a Project Process

Based on AXELOS PRINCE2® material. Material is reproduced under licence from AXELOS Limited. All rights reserved. PRINCE2® is a [registered] trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. AXELOS® is a [registered] trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved.

1

The Swirl logo™ is a trade mark of AXELOS Limited, used under the permission of AXELOS Limited. All rights reserved.

Copyright 2014, Simplilearn, All rights reserved. Copyright 2014, Simplilearn, All rights reserved.

Objective After completing this lesson, you will be able to:

2



State the purpose and objective of the Initiating a Project process



Identify the activities in the Initiating a Project process



Identify the strategies defined in the Initiating a Project process

Copyright 2014, Simplilearn, All rights reserved.

Purpose of Initiating a Project The purpose of the Initiating a Project process is to establish solid foundations for the project, enabling the

organization to understand the work that needs to be done to deliver the project’s products before committing to a significant spend.[1]

3

Copyright 2014, Simplilearn, All rights reserved.

Objective of Initiating a Project The objective is to ensure that there is a common understanding of :

4



the reasons for undertaking project.



the scope of project work.



cost and timescales.



expected benefits.



risks, issues and their management.



quality expectations and management.



decision making authorities.



information distribution.



monitoring and controlling of the project’s progress. Copyright 2014, Simplilearn, All rights reserved.

Initiating a Project—Overview This image gives an overview of Initiating a Project process.

Figure 14.1. Overview of Initiating a Project. Copyright © AXELOS Limited 2013. Material is reproduced under licence from AXELOS. All rights reserved.

5

Copyright 2014, Simplilearn, All rights reserved.

Initiating a Project—Activities Initiating a Project activities are Project Manager oriented. The process comprises the following activities:

6



Prepare the Risk Management Strategy



Prepare the Configuration Management Strategy



Prepare the Quality Management Strategy



Prepare the Communication Management Strategy



Set up the project controls



Create the Project Plan



Refine the Business Case



Assemble the Project Initiation Documentation Copyright 2014, Simplilearn, All rights reserved.

Risk Management Strategy The Risk Management Strategy describes the goals of applying risk management. It defines the following: ●

Risk management procedure



Roles and responsibilities



Risk tolerances



Timing of risk management activities



Tools and techniques



Reporting requirements

! 7

For composition of Risk Management Strategy please refer PRINCE2® Manual Appendix A. Copyright 2014, Simplilearn, All rights reserved.

Configuration Management Strategy Configuration Management Strategy defines the following: ●

Configuration Management procedure, E.g. planning, identification, control, status accounting,

verification and audit ●

Issue and change control procedure, E.g. capturing, examining, proposing, deciding and implementing



Timing of configuration management activities and issue and change control activities



Roles and responsibilities for the procedures (consider if a Change Authority and/or change budget

should be established and the scales for priority and severity of issues)

! 8

For composition of Configuration Management Strategy please refer PRINCE2® Manual Appendix A. Copyright 2014, Simplilearn, All rights reserved.

Quality Management Strategy The Quality Management Strategy describes the expectations and standards to be followed during project and the means of assessing the products of the project. The Quality Management Strategy

includes the following:

9



Quality management procedure (e.g. quality planning, quality control, quality assurance)



Roles and responsibilities for quality management activities



Timing of quality management activities



Tools and techniques

Copyright 2014, Simplilearn, All rights reserved.

Communication Management Strategy The Communication Management Strategy includes the following:

10



Communication management procedure



Timing of communication activities



Roles and responsibilities for communication activities



Stakeholder analysis

Copyright 2014, Simplilearn, All rights reserved.

Initiating a Project—Strategies The organisations have a mission to achieve and so the business strategies are developed by the corporate/programme management. ●

The strategies are derived from corporate/programme management strategies, standards and practices.



The strategies are defined by the Project Manager.



Project Assurance reviews the strategies.



The Project Board approves the strategies.



Project Support creates Quality Register, Configuration Item Records and the Project Manager approves these documents.

11

Copyright 2014, Simplilearn, All rights reserved.

Initiating a Project—Assemble the PID The image shows the process of assembling the PID.

Figure 14.9. Assemble the Project Initiation Documentation: activity summary. Copyright © AXELOS Limited 2013. Material is reproduced under licence from AXELOS. All rights reserved.

12

Copyright 2014, Simplilearn, All rights reserved.

Initiating a Project Process—Exercise The following questions are designed to test your comprehension of this process. Please solve them as a group activity.

Q

Q Q 13

Which role is responsible for each of the activities of the Initiating a Project process? Write activities and roles responsible.

How are the seven themes applied within the Initiating a Project process?

Which management products are created, developed, used and reviewed in Initiating a Project process? Copyright 2014, Simplilearn, All rights reserved.

Quiz

14

Copyright 2014, Simplilearn, All rights reserved.

While preparing the Configuration Management Strategy, the Project Manager recommended that the selected external supplier as Change Authority be authorised to approve and implement all changes. Is it a correct application of PRINCE2®?

QUIZ

1

a.

True

b. False

15

Copyright 2014, Simplilearn, All rights reserved.

While preparing the Configuration Management Strategy, the Project Manager recommended that the selected external supplier as Change Authority be authorised to approve and implement all changes. Is it a correct application of PRINCE2®?

QUIZ

1

a.

True

b. False

Answer: b. Explanation: Change Authority should be capable of representing the business, user and supplier stakeholder interests. The external supplier only represents the supplier interest. 16

Copyright 2014, Simplilearn, All rights reserved.

QUIZ

What process enables an organisation to understand the work that needs to be done to

2

deliver a project's products before it is approved?

a.

Directing a Project

b. Initiating a Project

17

c.

Starting up a Project

d.

Controlling a Stage

Copyright 2014, Simplilearn, All rights reserved.

QUIZ

What process enables an organisation to understand the work that needs to be done to

2

deliver a project's products before it is approved?

a.

Directing a Project

b. Initiating a Project c.

Starting up a Project

d.

Controlling a Stage

Answer: b. Explanation: The Initiating a Project process establishes solid foundations for the project.

18

Copyright 2014, Simplilearn, All rights reserved.

QUIZ

Which of the following is established within the Initiating a Project process?

3

a.

The various ways in which the project can be delivered

b. Those who require project information have been identified

19

c.

All the information required to develop the Project Brief is available

d.

Any constraints which could affect the project have been removed

Copyright 2014, Simplilearn, All rights reserved.

QUIZ

Which of the following is established within the Initiating a Project process?

3

a.

The various ways in which the project can be delivered

b. Those who require project information have been identified c.

All the information required to develop the Project Brief is available

d.

Any constraints which could affect the project have been removed

Answer: b. Explanation: An objective of the Initiating a Project process is to ensure that those who require project information have been identified. This is established within the Initiating a Project process. 20

Copyright 2014, Simplilearn, All rights reserved.

Summary Here is a quick recap of what we have learnt in this lesson:



The purpose of the Initiating a Project process is to enable the organisation to understand the work that needs to be done before committing to spending on it



Initiating a Project activities are Project Manager oriented



Strategies for risk management, configuration management, quality management and communication management are defined in the Initiating a Project process

21

Copyright 2014, Simplilearn, All rights reserved.

Thank You

Based on AXELOS PRINCE2® material. Material is reproduced under licence from AXELOS Limited. All rights reserved. PRINCE2® is a [registered] trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. AXELOS® is a [registered] trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved. The Swirl logo™ is a trade mark of AXELOS Limited, used under the permission of AXELOS Limited. All rights reserved.

22

Copyright2014, 2014, Simplilearn, All rights reserved. Copyright Simplilearn, All rights reserved.

Reference [1] Based on Managing Successful Projects with PRINCE2®, by AXELOS. Initiating a Project, Purpose.

23

Copyright 2014, Simplilearn, All rights reserved.

View more...

Comments

Copyright ©2017 KUPDF Inc.
SUPPORT KUPDF