Primavera Project Management 6 Workshop

Project Planning and Management

2

Develop the schedule and apply the resources and cost for the Plant Erection project by creating the Organisation Breakdown Structure and Enterprise Project Structure for the XYZ Company. The Organisation Breakdown Structure is as Shown below. President Prince

Vice President – Special Projects Zakir

Director – Plant Works Aslam

Vice President – Major Projects Siddiqqui

Director – Civil Works Mohammed

Program Manager – Internal Roshan

Director – Piping Works Siddharth

Program Manager – Bridges Raja

Director – Exploration Talaue

Program Manager CCP Felix

Program Manager – Oil Exploration Ahmed

Project Manager – Plant 1 Dilna

Project Manager – Bridge 1 Muthu

Project Manager – North Regin

Project Manager – Central Azhar

Project Manager – Plant 2 Francis

Project Manager – Bridge 2 Joe

Project Manager – South Ramu

Project Manager – East & West Reji

Project Planning and Management

3

The Project Structure is as shown below. XYZ

Special Projects

Plant Works

Major Projects

Civil Works

Piping Works

Bridges

Internal Works

Exploration

Cross Country Pipeline

Oil Exploration

Plant 1 Project

Bridge 1 Project

North side Projects

Plant 2 Project

Bridge 2 Project

South Side Projects

Gas Exploration

Assign the OBS to the EPS elements and projects. For this Plant erection project create a six day work week calendar with 9:00 AM to 6:00 PM and assign it as project calendar. Also create a five day work week calendar with timing as 10:00 AM to 6:00 PM and assign this calendar for two tasks. The start date of the project is May 2, 2009. The activities are shown with WBS for two levels and the resources are given below. Analyse the resources by using profile and table. The table given below shows the list of activities.

Project Planning and Management

4

ID

Name

SS

Project

1

Start of project

101

Tendering

2

Duration Predecessors

0

-

Preparation of Tender

20

1

3

Evaluation of Technical Bid

15

2

4

Evaluation of Commercial Bid

7

3

5

Award of Contract

7

4

102

Procurement

6

Ordering of Equipment

4

5

7

Site Handing Over

7

5

8

Delivery of Equipment

60

6

103

Erection Works

9

Erection of Civil Structures

20

7,8

10

Erection of Mechanical Equipment

35

7,8

11

Erection of Electrical Equipment

25

7,8

104

Testing & Closing

12

Testing of Plant

7

9,10,11

13

On load Testing

7

12

14

Commissioning

1

13

15

Finish of project

0

14

Project Planning and Management

5

Resource Definition The table given below shows the list of resources that are available for the whole project.

Name

Max. Avail.

Price/ Unit

Materials Manager

1

550/day

Engineer

3

500/day

Quality Controller

2

550/day

Supervisor

4

400/day

Office Assistant

1

200/day

Electrician

1

250/day

Labour

20

100/day

Crane

1

450/day

Excavator

1

400/day

Assigning Resources The table given below shows the list of resources that are needed for each and every activity. Analyse the resources by using resource profile.

Name

Resource Names

No. of units

Preparation of Tender

Engineer

1

Office Assistant

1

Evaluation of Tech. Bid

Engineer

1

Evaluation of Comm. Bid

Engineer

1

Award of Contract

Engineer

1

Office Assistant

1

Project Planning and Management

6

Name

Resource Names

No. of units

Ordering of Equipment

Materials Manager

1

Office Assistant

1

Engineer

1

Office Assistant

1

Materials Manager

1

Engineer

1

Labour

10

Engineer

1

Supervisor

2

Labour

15

Excavator

1

Materials Manager

1

Engineer

1

Supervisor

2

Labour

15

Crane

1

Engineer

1

Supervisor

2

Electrician

1

Labour

10

Crane

1

Quality Controller

2

Supervisor

1

Labour

5

Quality Controller

1

Supervisor

1

Labour

5

Site Handing Over

Delivery of Equipment

Erection of Civil Structures

Erection of Mechanical Equipment

Erection of Electrical Equipment

Testing of Plant

On load Testing

Project Planning and Management

7

Name

Resource Names

No. of units

Commissioning

Engineer

1

Office Assistant

5

Labour

5

Report 1) 2) 3) 4)

Prepare the schedule and find the critical path and finish date of the project. Assign the resources and find the total cost of the project. Track the project after 15 days with some delay in the activities. Prepare the following report a. Resource Control – Detail by Activity b. Monthly Project Cask Flow c. Resource Units Loading – Daily organised by WBS

Project Planning and Management

8

Step-by-Step Procedure Practice 1 – Defining Structure and Calendars To define Organizational Breakdown Structure 1) Select ENTERPRISE  OBS

2) Select the level below which you want to add the level and select ADD.

Project Planning and Management

9

3) If the newly created level wants to be inside the selected level, use SHIFT RIGHT.

To define Enterprise Project Structure 1) Select ENTERPRISE Enterprise Project Structure

2)

Select the level below which you want to add the level and select ADD.

3)

If the newly created level wants to be inside the selected level, use the SHIFT RIGHT.

To create new project 1) Select ENTERPRISE  Projects

Project Planning and Management

10

2) Select the EPS node in which project has to be created. Then ADD. 3) Enter the details about the project in activity details. View  Show on Bottom Project Details.

Project Planning and Management

11

To create new calendar. 1) Select ENTERPRISE  Calendars

2) Select Project and ADD.

Project Planning and Management

12

3) Select the calendar which you want to copy. Click

Project Planning and Management

.

13

4) Select

5) To define each days working time, click

Project Planning and Management

14

To assign a calendar as Project Calendar 1) Select ENTERPRISE  Projects 2) View  Show on Bottom  Project Details 3) Select Defaults

Project Planning and Management

15

4) Select calendar and click

To assign a calendar as Task Calendar 1) Open the project. File Open 2) View  Show on Bottom Activity Details 3) Select General

Project Planning and Management

16

Adding Activities 1) Open project

Project Planning and Management

17

2) Click

to add activities.

Activity Sequencing 1) Open the project 2) View Show on Bottom  Activity Details 3) Select Relationships

Project Planning and Management

18

Use either Predecessor or Successor to link the activities and give relationship type and lag.

WBS To define the WBS for the project 1) Project  WBS

2) Click . 3) To add one level below the selected level.

Project Planning and Management

19

To assign WBS level for the project 4) Use Activity Details  General

5) Click

6) Select WBS level and click

.

Project Planning and Management

20

Resources To define the resources 1) Enterprise  Resources

1) Click General to give resource ID, name etc. 2) Click Details to mention whether it is labour, non labour or material. Currency and overtime factor can also be mention here. 3) In the Units & Prices we can give the availability of resources and the price.

Project Planning and Management

21

To assign resources 1) Project Activities 2) View  Show on bottom  Activity Details 3) Select Resources

4) Click

to assign resource directly.

Project Planning and Management

22

5) Select the resource and click

Resource Analysis 

View  Show on bottom  Resource Usage Profile

Project Planning and Management

23

Red colour indicates the over allocation of resources.

Project Planning and Management

24

Update Progress 1) Save the baseline. Project  Maintain Baselines

Click

to create new baseline.

To assign the baseline Project Assign Baselines

Project Planning and Management

25

1) Select each and every activity and for each activity, you need to specify the Actual Start, Actual Finish and the percent complete and the remaining duration for the activities in status tab

2) Then, you need to schedule the project by specifying the data date that is the status date what you are going to set.

Project Planning and Management

26

3) For comparing the actual progress and the baseline schedule go to View  Bars and display the baseline bar.

Earned Value Analysis For doing the earned value analysis, follow all the steps mentioned in the previous topic. Go to Activity details  Expenses. Give the extra amount which you spend in the Actual cost and find the EVA. To get the EVA, Planned Value, Earned Value and Actual Cost, go to Tools Reports  Earned Value.

Report Generation For taking tabular reports, Tools Reports Reports

Project Planning and Management

27

Top Down Estimation The Top Down Estimation feature allows us to calculate the resource units of labour, non labour and material using estimated weight in a top down manner by applying weights to WBS elements and activities. The top down estimation approach can be followed in certain cases where the project’s total estimated units of the resource are known and with the help of that the individual resource units can be calculated. Certain conditions where the project manager/ resource manager knows the total resource units of the project based on his previous experience in the similar type of project. The top down estimation feature can be used for labour and non labour resource at once, but for material resource it has to be calculated individually only, since the unit of measure is different for each resource. Also this feature cannot be applied for Microsoft office Project managed projects. Any changes that we get through this Top Down Estimation cannot be made Undo. The Top Down Estimation feature works based on the weights that we give to WBS elements and Activities. The following procedure has to be followed in using the Top Down Estimation:  Give weights to the WBS elements for the set of activities under which the resource units need to be calculated  Give weights to the activities for which resource units need to be calculated  Apply Top Down Estimation by selecting the appropriate WBS for which the resource units need to be calculated.  Calculate resource units for labour, non labour and separately for material resources as it cannot be done at once as we do for labour and non labour.  Save the calculation for future comparison and use. Note: If labour units and non labour units follow different level of resource distribution in the WBS element then apply that separately as we do for material resource.

Assigning Estimation Weights to WBS Elements

Project Planning and Management

28

We can assign estimation weights to work breakdown structure (WBS) elements and activities to perform Top-down estimation. We can assign estimation weights directly in the Project Management module or import them from the Methodology Management module using Project Architect. The Project Management module uses the estimation weights to calculate the number of units that each WBS element receives in relation to its lower-level elements in the WBS hierarchy. For giving the Estimated Weights to the WBS elements select Display Columns Size or View Columns Size from that you can see the column Est Weight as shown in the figure below.

In the example above, WBS level 1 shows Pump Station and in the second level of WBS Pump Station 1 and Pump Station 2 are available. The activities under the WBS can be listed by selecting the Activities view. For the WBS elements and the activities Est. Weights can be given as required on how the resource units need to be calculated and distributed to the resources in the activities. For giving Est. Weight to the activities insert the column Est. Weight from the General category of the column.

Define some resource Labour, Non Labour and Material Resources and apply to the activities for calculating the units of resources for each activities.

Project Planning and Management

29

The resource definition sample is as shown below:

Now assign the resource to the activities. A sample assignment for an activity is as shown below:

Project Planning and Management

30

Now we give the est. weight for the WBS 1 – Pump Station 1 as 5 and WBS 2 – Pump Station 2 as 2. With this estimated weight now we can calculate the units of resources for the activities using Top Down Estimation. Note: In this situation we are not applying est. weights to the activities. Select Tools Top Down Estimation. The dialog box will appear as shown below:

Now we are going to calculate the estimated units for the Labour units. Select Estimated Labour and then select the WBS under which the units need to be calculated and give the Estimated Units for example as 500 using prior experience. The dialog box will appear as shown below with the estimated units and adjustment units calculated. Note: For calculating units for individual labour then in the resources, select resource.

Project Planning and Management

31

You can apply adjustment factor as required in positive or negative and as per that the adjustment units will be calculated. After applying adjustment factor: Now select Save As, so that in future it can be used to apply based on the applied units, which can be seen in the History. Now select Apply and you will be able to see the changes in the resource assignment for the activities. You can insert columns Budgeted Labour units and Budgeted Non Labour Units in the activity table and for material units it can be seen in the resource assignment information. The formula used in calculation is Estimated Units for WBS 1.1 = (Est. Weight of WBS 1.1 / Total Est. Weight of all WBS) * Estimated Units

Project Planning and Management

32

In the same way the resource units can be calculated for Non Labour Resource and Material Resource. For material resource we need to select the material resource in the option Resource. Now it can be seen that the units are assigned equally to the activities under the single WBS, but in real practice the activities will be having different assignment units. Now apply the weights to the activities using the Est. Weight column and follow the same procedure for calculating the units using Top Down Estimation. Est. Weights to activities assigned:

After doing the Top Down Estimation:

Project Planning and Management

33

Project Planning and Management

View more...