user’s manual of Construction (part three)
General Support Volume-1 Measurement Book (Procedures & Guidelines)
Construction Management Power Grid Corporation of India Limited (A Government of India Enterprise) DOCUMENT CODE NO. : MR / CM / MB / 03-01
Nov. 1997
CONTENTS SECTION – ONE PROCEDURES FOR RECORDING PAGE 1.1
INTRODUCTION
1.2
MEASUREMENT BOOK
1.3
ABSTRACT BOOK
1.4
FORMAT OF MB/AB
1.4.1
SL. NO. OF MB/AB
1.4.2
SIZE OF MB/AB
1.5
RUNNING ACCOUNT BILL (RA BILL)
1.6
JOINT MEASUREMENT CERTIFICATE (JMC)
1.7
MATERIAL RECONCILIATION STATEMENT (MRS)
1.7.1
OWNER SUPPLIED MATERIALS.
1.7.2
CONTRACTOR SUPPLIED MATERIALS.
1.7.3
CEMENT & STEEL
1.8
CUSTODY OF MB/AB
1.8.1
ISSUE OF MB/AB
1.8.2
STOCK OF MB/AB
1.8.3
LOSS OF AB/MB
1.8.4
HANDING/TAKING OVER OF MB/AB
1.9
RECORDING OF MEASUREMENTS:
1.9.1
RECORDING IN MB
1.9.2
RECORDING IN AB
1.9.3
RELEASE OF PAYMENT
1.10
RECORDING AND TEST CHECKING
1.10.1
RESPONSIBILITIES FOR RECORDING & CHECKING MEASUREMENTS
1.10.2
TEST CHECKS
1.10.3
IMPORTANT ITEMS FOR MEASUREMENT (A)
HIDDEN & CONCEALED ITEMS
(B)
COSTLY/SPECIAL ITEMS
(C)
RECORDING OF MEASUREMENTS IN RESPECT OF LENGTH OF PILE: BORED CAST-IN-SITU PILES: DRIVEN CAST - IN - SITU PILES: DRIVEN PRE-CAST
(D)
MEASUREMENT OF STEEL BARS:
(E)
MEASUREMENTS OF EARTH MAT & FIRE FIGHTING PIPES
(F)
ANTIWEED TREATMENT IN SUBSTATION
SECTION -TWO GUIDELINES 2.1
GUIDELINES FOR MAINTENANCE OF MB/AB
2.2.
GUIDELINES FOR FILLING UP OF MATERIAL RECONCILIATION STATEMENT (MRS)
SECTION – THREE FORMATS & PROFORMAS ANNEXURE – I
FORMAT OF MEASUREMENT BOOK
ANNEXURE – II
FORMAT OF ABSTRACT BOOK
ANNEXURE – III
FORMAT OF RUNNING/FINAL ACCOUNT BILL
ANNEXURE- IV
FORMAT OF JOINT MEASUREMENT CERTIFICATE
ANNEXURE – VA
PROFORMA OF MATERIAL RECONC. STATEMENT (RECT.)
ANNEXURE – VB
PROFORMA OF MATERIAL RECONC. STATEMENT (CONSUMPTION)
ANNEXURE –VI
FORMAT OF STOCK REGISTER FOR MEASUREMENT/ABSTRACT BOOKS
ANNEXURE –VII
FORMAT OF CERTIFICATE FOR FINAL BILLS
ANNEXURE – VIII
FORMAT OF BILL MOVEMENT SHEET
ANNEXURE – IX
LOCATION CODES
ANNEXURE – X
FORMAT OF INDEX FOR TEST CHECKING
ANNEXURE – XI
FORMAT OF LEVEL BOOK
SECTION-FOUR CHECKLISTS & FLOW DIAGRAM ANNEXURE – XII
FORMAT OF CHECK LIST FOR RUNNING ACCOUNT BILLS
ANNEXURE – XIIIA
FORMAT OF CHECK LIST OF FINAL BILL FOR EARTH WORK
ANNEXURE – XIIIB
FORMAT OF CHECK LIST OF FINAL BILL (GENERAL)
ANNEXURE-XIV
FLOW DIAGRAM OF PAYMENT PROCEDURES
ANNEXURE – XV
CALCULATION OF EARTH VOLUME FROM SPOT LEVELS
ACRONYMS USED AB
Abstract Book
CC
Corporate Centre
CFM
Chief Finance Manager
CI Pipes CHP
Cast Iron Pipes Consumer Hold Point
C&M
Contracts & Materials
CPM
Chief Personnel Manager
CS Deptt.
Contract Services Department
DGM
Deputy General Manager
DHQ
Divisional Head Quarter
DOP E-I-C
Delegation of Powers Engineer-In-Charge
Engg.
Engineering
F&A
Finance & Accounts
FR GHQ
Fissured Rock Group Head Quarter
GR
Goods Receipt
HOD
Head of Department
HO/TO HQ
Handing Over/Taking Over Head Quarter
HR
Hard Rock
JMC
Joint Measurement Certificate
LOA LR
Letter of Award Lorry Receipt
MAB
Master Abstract Book
MB MICC
Measurement Book Material Inspection Clearance Certificate
MM
Materials Management
MRHOV
Material Receipt & Handing Over Voucher
MRN
Material Return Note
MRS
Material Reconciliation Statement
MTN
Material Transfer Note
MTV
Material Transfer Note
NIT No.
Notice Inviting Tender Number
NOC
No Objection Certificate
O&M
Operation & Maintenance
OS
Operation Services
P&C
Planning & Co-ordination
PV
Price Variation
Section-One Procedures for Recording
-----------------------------------------------------------------------------SECTION
ONE ------------------------------------------------------------------------------
PROCEDURES FOR RECORDING Back to contents page
1.1
Introduction Back to contents page Measurement methods need to be evolved, so that a uniform and standard procedures for recording various measurements and maintaining Measurement Books is followed throughout the Corporation in respect of erection contracts, supplycum-erection contracts, civil contracts, maintenance contracts & horticulture contracts. In line with the above, procedures and guidelines for Measurement Books alongwith appropriate formats have been prepared.
1.2
Measurement Book Back to contents page Various works at the construction sites being executed as works contract i.e. construction of Transmission Lines, Sub-Stations erection works, Civil Construction works, all maintenance works and other miscellaneous works shall be duly recorded in a book known as Measurement Book (MB). Measurements for the works actually executed shall be recorded in the MBs in a systematic & chronological orderlike security contracts etc. which are recurring in nature shall also be recorded.
1.3
Abstract Book Back to contents page An abstract of Measured quantities and payments shall be entered in another Book known as Abstract Book (AB). The payment shall be released on the basis of abstract recorded in AB supported with respective measurements recorded in MB. The following payments pertaining to each contract shall be entered in the Abstract Books for verification and releasing the payments for erection/construction/mtc. works to the concerned agency:a)
Mobilisation/materials/machinery advance.
b)
RA Bills and final bills.
c)
Any other advances.
d)
Reimbursement of Insurance premiums.
e)
PV Bills
f)
Approved extra items/substituted items/claims.
g)
Release of S.D. and other retention amounts etc.
MBs/ABs are considered to be the most important documents. MBs/ABs shall be standard in design and printing throughout the Corporation. As per the approved design & Size, printing of the MBs/ABs shall be carried out by each RHQ. At Corporate Centre printing work shall be taken up by Corporate Material Deptt. 1.4
Format of MB/AB Back to contents page
1.4.1
Sl. No. of MB/AB Back to contents page Each of the MB/AB shall be machine numbered serially. MB/AB shall have eight digit numbers as X/YY/MB/ZZZ AB 1 23 45 678 Ist digit 'X' in the code specifies the Corporate Centre, National Load Despatch and Region etc. Remaining two digits 'YY' denote location code viz. GHQ/Transmission Line office/Sub-station/Site offices. For Corporate Centre 2nd and 3rd digits shall be the abbreviated name of the deptt. as shown in the Annexure-IX. This shall be followed by word MB/AB as the case be (4th and 5th digit). Again it shall be followed by three digit Sl. No. (at 6th, 7th and 8th digit) of MB/AB as shown in illustration in AnnexureIX, being the Sl. No. of MB/AB. Above codification has been done in line with codification done for Uniform Material Codification System as circulated by Corporate Material Deptt. to keep uniformity. Any addition/deletion in the above codification shall only be done by the Corporate Centre.
1.4.2
Size of MB/AB Back to contents page The size of the Measurement Book shall be of standard A-4 size. Each Measurement Book shall contain 50 pages in
triplicate as per the standard format enclosed at AnnexureI. The first page shall be of white colour with perforations, the second page shall be of yellow colour with perforations and the third page shall be of light green colour without perforations. Similarly, ABSTRACT BOOKS are to be printed separately. Abstract Book shall also be of standard A-4 size. A standard format for Abstract Book is enclosed at Annexure-II. The abstract Book shall contain 100 pages. On the cover of the books, the following shall be printed: MEASUREMENT BOOKS (MB)/ ABSTRACT BOOKS (AB) i) ii) iii) iv) v) vi) 1.5
MB/AB No. on top right corner. Name of Region ..................... Name of Divn. ..................... Name of Group ..................... LOA No. & Date ..................... Name of work .....................
Running Account Bill (RA Bill) Back to contents page Abstract of the measured quantities and payments as prepared and entered in Abstract Book (vide 1.3 of Page 1) shall also be prepared on loose sheets known as Running Account Bill. Besides abstract of measured quantities and payments, RA Bill forms shall also contain the Certificates to be given by Engineer, acceptance of the payment by the contractor and approval by the competent authority. RA Bill form shall also contain the details of Pass Order of Accounts Deptt. i.e. payments, adjustments, deductions and recoveries, net payment made etc. in the bill. RA bill shall be prepared in 3 copies. Two copies shall be forwarded to concerned Finance Deptt. and third copy shall be retained as office copy by the official recording the Measurement. Along with these two copies of RA bill, two copies of Measurement Book and Abstract Book shall be forwarded for releasing the payment. After release of the payment Finance Deptt. shall send back the following documents to Group Head. i)
Abstract book with pass order.
ii)
2nd Copy of the RA bill alongwith pass order. This copy shall be kept by the recording official in the safe custody and filed in chronological order.
iii) 2nd copy of MB. The corrections, if any made by Finance Deptt. should be incorporated in copy of MB retained with the official recording the MB. The standard bill form for RA/Final Bill is enclosed at Annexure-III. 1.6
Joint Measurement Certificate (JMC) Back to contents page Joint Measurement is a record of measurements taken jointly by the representatives of Power Grid and of the executing agency. Joint Measurement certificate shall be of A4 size and shall be prepared in duplicate. Original copy of the JMC shall be white in colour and shall be perforated. Second copy of the JMC, without perforation shall be light green in colour and shall be prepared for the hidden/concealed items and shall be prepared immediately on starting/completion of an activity. A format of the JMC is enclosed as Annexure-IV.
1.7
Material Reconciliation Statement (MRS) Back to contents page
1.7.1
Owner Supplied Materials (OSM) Back to contents page In order to ensure timely & proper reconciliation of Owner Supplied Materials on construction sites of T/L, S/S and Civil works(including steel & cement), a material reconciliation statement (MRS) shall be submitted alongwith every third RA/Final bill. This material reconciliation statement both for receipt and consumption of Owner Supplied Materials is to be enclosed with every IIIrd RA/final bill and same shall be recorded in corresponding Measurement Books. Proformas of Material Reconciliation Statement both for materials received and consumed during the period are enclosed as Annexure-Va and Vb. Guidelines for filling up these proformas are also being enclosed.
1.7.2
Contractor Supplied Materials. Back to contents page For reconciliation of Contractor Supplied Materials at construction sites of T/L, S/S and Civil works, a material reconciliation statement (MRS) shall be submitted alongwith every third RA/Final bill.
The above MRS Proformas (both for OSM and Contractor supplied material) shall be submitted by erection contractor and duly signed by concerned site Engineer. 1.7.3.1
Cement & Steel Back to contents page
In case of consumption of steel/cement both for Owner's Supplied as well as Contractor's Supplied a statement shall be given in each of the RA Bills, shown hereunder +-----------------------------------------------------+ ¦ Theoretical Actual ¦ ¦ Consumption Consumption ¦ +-----------------------------------------------------¦ ¦ Cement ¦ ¦ ¦ ¦ Steel ¦ +-----------------------------------------------------+ 1.8
Custody of MB/AB Back to contents page
1.8.1
Issue of MB/AB Back to contents page Each group shall get the MB's issued from RHQ and the stock of blank Measurement Books shall be maintained by P & C deptt. of respective deptt./ Groups. The measurement books shall be issued to the concerned officials on specific indents. Each MB/AB, in addition to the standard format shall also contain pages in the beginning as per proforma enclosed at Section-Two indicating guide lines for recording measurements and an index. The issuing authority shall record on the inside cover of MB i) ii) iii) iv) v) vi)
MB No. Name of the work ..................... LOA No. & Date ..................... Issued To ..................... Date of Issue ..................... Certificate that the book has been examined by me and contains......pages duly numbered.
Issuing official Signature ................. Name ................. Designation ................. Date ................. 1.8.2
Receiving Official Signature Name………………… Designation…………. Date……………………………
Stock of MB/AB Back to contents page
The stock of blank measurement books in the custody of P&C deptt. at Regional/Divisional/group offices shall be verified atleast once a year by the respective Head/Incharge or his authorised representative not below the rank of E-4 and a certificate in token of verification shall be recorded in the stock register of MB/AB. The standard format for 'Stock Register for Measurement/ Abstract Books' is enclosed herewith at Annexure-VI. The executive receiving the measurement books shall count the pages of the MB at the time of receipt and record a certificate indicating the number of pages contained in the MB/AB. On closing of the contract entries shall be made in MB issuing register maintained in P&C deptt. Thereafter these shall be returned to F&A deptt. and these are to be preserved for a period of 10 years after closing of contract. In case of arbitration and court cases pertaining to certain contracts, the concerned MBs/ABs should be retained till such time the arbitration/court cases are finalised even though the 10 years period had exceeded. 1.8.3
Loss of AB/MB Back to contents page When an MB/AB is lost by an official, a report indicating the circumstances under which it was lost should immediately be reported to the Incharge of the work with a copy to F&A deptt. at regional/divisional/group offices for taking further action as considered necessary. Divisional/Regional head should constitute an enquiry committee for ascertaining the circumstances and facts under which MB/AB was lost. Penal action shall be taken as per findings of Enquiry Committee against defaulting/erring officials. Also the Site Engineer/Group Head shall ensure that the MB/AB lost be made up with the corrected second copy of measurement Book/RA bill.
1.8.4
Handing/Taking over of MB/AB Back to contents page MB/AB shall be properly handedover/taken over on transfer/long leave of the official to whom it is issued. Proper HO/TO certificate shall be furnished on the inside cover of the MB/AB in continuation to earlier issue certificate. The certificate shall be properly countersigned by the Group Head/HOD issuing authority with entry in MB/AB stock register.
1.9
Recording of measurements: Back to contents page The measurements shall be recorded neatly, clearly and accurately in the MB. Ballpen/Inkpen should be used for
making entries in the MB/AB. Overwriting and erasing shall not be done. In case, wrong measurements were recorded inadvertently, these shall be scored out under the full signatures of the person recording the measurements and fresh entries shall be made. Entries shall be made continuously and no blank page shall be left. Any blank pages left inadvertently shall be cancelled by diagonal lines in red under dated signatures. No page should be torn out under any circumstances. 1.9.1
Recording in MB Back to contents page While recording detailed measurement in instructions shall be carefully observed:-
MB,
following
Measurements shall be recorded in Measurement Books. Measurements can be recorded in any number of MB's depending upon classification of various works under one package, location of the works, site conditions etc. However, only one Abstract Book shall be issued and made against one contract. All advances, payments & adjustments pertaining to one contract shall be entered in the A.B. However, for transmission lines works where works under the same contract are divided amongst two or more officials who are stationed distant apart, Individual AB shall be maintained by the concerned officials. Officials stationed near to the GHQ or as decided by the Competent Authority shall be issued AB known as Master Abstract Book (MAB). Other officials shall be issued AB as follower Abstract Book & AB. In follower AB abstract of the since previous quantities & payments shall only be entered & shall be transferred in Master AB with suitable cross entries and complete details of up to date quantities & payments. Thus, bill for the purpose of release of payments with the upto date quantities and payments (inclusive those for sections covered by FAB) shall be prepared and entered in MAB. All advances, payments, release of security deposits etc. shall be entered in MAB for the purpose of release of payments by A/C Deptt. The entries at the time of first measurement for each of the works in MB shall be as under. a)
RA Bill No. ..................dtd. ..........
b)
Name of the work
:
c)
Location of the work
:
d)
Agency by which executed
: Contractor/departmental
e)
LOA No. and date
:
f)
Name of the contractor
:
g)
Date of commencement of work :
h)
Schedule / anticipated date of completion
:
i)
Period of Measurement
:
j)
Date of Recording of Measurement in MB.
From.........To.......
At the time of making subsequent measurements of such works, measurements of subsequent RA Bill may be recorded by commencing with the following entries:a)
RA Bill No………………………….dt.
b)
Period of Measurement :
c)
Date of Recording of Measurement in MB
d)
Schedule/anticipated case of final bill, should be recorded)
e)
No. & date of previous RA Bill.
From..........To
date of the actual
completion. (In date of completion
At the end of measurements, the Jr. Engineer/official recording measurements shall put his/her signatures in full with name and designation. Measurements shall be recorded in the MB on monthly/fortnightly basis. In case of concealed/hidden items measurements shall be recorded immediately on starting/completion of the activity. In case the recording of measurements directly in MB immediately on completion of the activity is not possible the measurements can be recorded in the JMC before reproducing the same in the MB. However for T/L concealed/hidden works, measurements shall be recorded on the basis of JMC only. On completion of the measurements, the Executive/Jr. Engineer recording the measurements shall give a certificate as "Measurements taken by me". The Signatures of the contractor/or his authorised agent shall also be obtained on the measurement Books in token of the proof that the measurement recorded in the measurement Book have been accepted. The contractor/or his authorised agent shall be asked to record a certificate "Measurement recorded at
Page No... to.. are accepted". In cases, where contractor or his authorised representative does not agree to sign the measurements or refuses to accept the measurements as recorded in the MB, Engineer-in-Charge or the person deputed by him for the purpose shall give a reasonable notice to the Contractor. If the Contractor fails to attend or send an authorised representative for measurement after such a notice or fails to countersign or to record his objection within a week from the date of measurement, then in any such event measurements taken by the Engineer-inCharge or by the person deputed by him shall be taken to be correct measurements of the work. If the Contractor objects to any of the measurements recorded on behalf of the Corporation a note to that effect shall be made in the Measurement Book against the item objected to and such note shall be signed and dated by both parties engaged in taking the measurement. The decision of the Accepting Authority on any such dispute or difference or interpretation shall be final and binding on both the parties and shall be beyond the scope of the settlement of disputes by Arbitration in respect of all contract items, substituted items, extra items and deviations. The Contractor shall, without extra charge, provide necessary assistance, labour and other things necessary for measurements. 1.9.2
Recording in AB Back to contents page After recording measurements and obtaining signature of the contractor or his authorised agent, an abstract of the work measured, shall be prepared in the Abstract Book. At the time of entering the abstract of first R.A. Bill the following entries are to be made:1)
RA Bill No.......... Date.........
2)
Name of work
:
3)
Name of the contractor
:
4)
LOA No. and date
:
5)
Date of commencement of work
:
6)
Sch. date/Ant. date of completion
:
7)
Period of measurements
:
From…………To…………….
For subsequent R.A Bills of same work the following entries are to be made:-
1)
RA Bill No.......... Dtd..........
2)
Period of measurements
: From…………To……………
3)
Reference to previous RA Bill Indicating page nos.
:
Sch./Ant. date of completion
:
4)
The abstract shall also indicate the payments if any made upto previous bill so as to arrive at the upto date payment proposed under the current bill. 1.9.3
Release of payment Back to contents page At the end of each Bill in the Abstract Book, the contractor shall give a certificate that the payments recommended for in the respective bills are accepted. Thereafter E-I-C shall forward the following documents to the concerned finance department for release of the payment: 1) Bill movement sheet as per Annexure-VIII. 2)
Two copies (Original & Duplicate) of the Measurement Book.
3)
Abstract Book
4)
Running Account bill in duplicate.
5)
Material Reconciliation Consumption)
6)
Certificate & Check Lists as per Annexures-A bill movement sheet for MB/AB shall be maintained by E-I-C and also by the F&A deptt. as per the format enclosed at Annexure-VIII. The accounts deptt. shall ensure that the running bills are passed within 5 days of receipt of the bill in F&A deptt. Where the running bill cannot be passed within receipt of 5 days, the accounts deptt. shall advice the bill preparing authority with remarks. Payments where Foreign Currency is involved the relevant documents shall be forwarded by the respective group/division office through Regional Finance to Corporate Centre. All the corrections in the MBs/ABs and bill forms including the pass order shall be done only in red ink by F&A Deptt. Where the work is not measurable such as patch work etc. a certificate shall be given in the Abstract by the in-charge to the effect that the work is not susceptible to measurements.
Statement
(Both
Receipt
&
A Flow Diagram regarding enclosed as Annexure-XIV.
release
of
payments
is
1.10
Recording and Test Checking Back to contents page
1.10.1
Responsibilities for recording & checking measurements Back to contents page
a)
Detailed measurements should be recorded by Executive or Senior Executive only. Junior Engineers(storekeepers in stores) may, in cases where the Engineer-in-charge considers that the exigencies of the service require it, record the measurements in measurement book subject to 100% verification by E1/E2/E3 for hidden/underground works & 40% for other works.
b) TRANSMISSION LINES ----------------------------------------------------------------------------------------------Approved by S. Items To be recorded by Test Checked by No. Field Work Engr. Inch. ----------------------------------------------------------------------------------------------01. Survey & SoilJr. Engr. E1/E2/E3 E4/E5 Divisional Head* Investigation 100% 100% 40% E6 20% E1/E2/E3 E4/E5 E6 --- do --100% 40% 20% 02.
Foundation work (classification & concreting etc.)
Jr. Engr. E1/E2/E3 E4/E5 Group Head** 100% 100% 40% Test Check-10% E1/E2/E3 E4/E5 --- do --100% 40% -----------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------S. Items To be recorded by Test Checked by Approved by
No.
Field Work Engr. Inch. ----------------------------------------------------------------------------------------------03.
04.
Pile,well,Spl. foundations and other works like benching/revetment etc.
Jr. Engr. 100%
E1/E2/E3 100%
E4/E5 40%
DGM
E1/E2/E3 100%
E4/E5 40%
E6 20%
--- do ---
Tower Erection
Jr. Engr. 100%
E1/E2/E3 40%
E4/E5 20%
Group Head Test Check-10%
E1/E2/E3 100%
E4/E5 40%
--- do ---
05.
Stringing
Jr. Engr. 100% E1/E2/E3 100%
E1/E2/E3 40% E4/E5 40%
E4/E5 20%
Group Head Test Check-10% --- do ---
06.
Other misc. works of line and O& M of line
Jr. Engr. 100%
E1/E2/E3 40%
E4/E5 20%
Group Head Test Check-10%
E1/E2/E3 E4/E5 --- do --100% 40% ----------------------------------------------------------------------------------------------*
-
Note
The Divisional Head shall accord the principle approval for the item and the approved note shall be enclosed with the bill. The bill shall be passed as per DOP - Bill shall be approved by the respective approving authority as per the DOP only. However, in the due course of works the test checks may be carried out by the various higher authorities as given in the above chart and this shall be recorded in prescribed formates in measurement book.
-
Divisional head should visit the site frequently. Test check of the important activities shall be carried out by the divisional head whenever he visits the site and the same shall be recorded in JMC/MB. ----------------------------------------------------------------------------------------------S. Items To be recorded by Test Checked by Approved by No. Field Work Engr. Inch. ----------------------------------------------------------------------------------------------01. Under Ground/ Jr. Engr. E1/E2/E3 E4/E5 Group Head Hidden/Costly 100% 100% 40% Test Check-10% Works E1/E2/E3 E4/E5 --- do --100% 40% 02.
Site Levelling
Jr. Engr. 100% E1/E2/E3 100%
E1/E2/E3 100% E4/E5 40%
E4/E5 40% E6 20%
Divisional Head* Test Check-10% --- do ---
03.
Boundaery wall (Super Str.)
Jr. Engr. 100% E1/E2/E3 100%
E1/E2/E3 40% E4/E5 40%
E4/E5 20%
Group Head Test Check-10% --- do ---
04.
Road Works
Jr. Engr. E1/E2/E3 E4/E5 Group Head 100% 40% 20% Test Check-10% E1/E2/E3 E4/E5 ----do---100% 40% -----------------------------------------------------------------------------------------------
----------------------------------------------------------------------------------------------Approved by S. Items To be recorded by Test Checked by No. Field Work Engr. Inch. -----------------------------------------------------------------------------------------------
05.
S/S. Civil/ Bldg. Constn./
06.
07.
Jr. Engr. 100%
E1/E2/E3 40%
E1/E2/E3 100%
E4/E5 40%
S/Yard Erection/Fire Fighting/A/C. TF/SR erection Etc.
Jr. Engr. 100%
E1/E2/E3 40%
E1/E2/E3 100%
E4/E5 40%
S/stn. O&M works
Jr. Engr. 100%
E1/E2/E3 40%
E4/E5 20%
Group Head Test Check-10% --- do ---
E4/E5 20%
Group Head Test Check-10% --- do ---
E4/E5 20%
Group Head Test Check-10%
E1/E2/E3 E4/E5 --- do --100% 40% ----------------------------------------------------------------------------------------------*
- The Divisional Head shall accord the principle approval for the item and the approved note shall be enclosed with the bill. The bill shall be passed as per DOP
Note-
Bill shall be approved by the respective approving authority as per the DOP only. However, in the due course of works the test checks may be carried out by the various higher authorities as given in the above chart and this shall be recorded in prescribed formates in measurement book.
-
Divisional head should visit the site frequently. Test check of the important activities shall be carried out by the divisional head whenever he visits the site and the same shall be recorded in JMC/MB.
1.10.2
Test Checks Back to contents page i)
Test checking is to be carried out by the authorities as stipulated in the para 1.10.1. Authority carrying out check test should record the same in the Measurement Book as per index for test checking (Annexure-X). Nevertheless authorities carrying out check test should ensure that item being test checked by him was not already test checked by the authority below him.
ii)
The percentage of the test check shown in para 1.10 is both for payment & possibly the number of items. Test check should be carried out atleast every alternate bill for the works at HQ of the authority and atleast every third bill for the work out of HQ of the authority. However, total test check carried out by an authority should satisfy the percentage mention as per para 1.10. Test check of the authority shall also include atleast 10% of test checks of the measurements of RCC item so as to ensure structural safety of the building/ structure. A remark to the effect that an item has been test checked shall be recorded against the items checked in the MB indicating the date of test check and initials of the test checking official. When measurements are taken by two persons jointly, both of them shall sign on the MB. For T/L foundation, test check shall be recorded in JMC.
iii) Divisional head should visit the site frequently. Test check of the important activities shall be carried out by the divisional head whenever he visits the site and the same shall be recorded in JMC/MB. v)
The official carrying out test check of the measurements, recorded by their subordinate official, is normally expected to carry out an effective check of costly, hidden & special items.
vi)
In case of levelling operations and earth work, measurements are required to be recorded in level books in addition to Measurement Books. The level books should be numbered, accounted for and handled like Measurement Books. Before starting the earth work (S/S levels), original ground level should be recorded in the level book in the presence of contractor or his authorised representative and should be signed by him
and the Departmental Officer who records the levels. All the local mounds and depressions should be indicated clearly in the drawing and field level book and should be checked by site Engineer before levelling is started. Measurements of the levelling work shall be recorded by an official not less than E1. Levels may also be taken by a Jr. Engineer but these shall be verified/checked by an officer not less then E1 in presence of the contractor. Contour map shall be prepared before commencement of the work & after completion of the job. Also "L"section & cross section as per the spot levels shall be prepared & duly signed by the rep. of Powergrid & contractor. The"L" section,contour plan & the level book shall be sent to DHQ & Approval of Divisional Head shall be obtained. After approval,the contour plan"L"section & spot levels field book shall be kept in the safe custody of E-I-C of the work. Format of Level Book is given in Annexure-XI. In case of large scale levelling works involving both cutting and filling, an accurate site plan should be prepared before the work is commenced. The portions requiring cutting and filling shall then be divided into squares and corresponding squares into filling, which are complementary to the squares in cutting given the same number. A table may be written upon the plan showing leads involved between the various complementary squares. This would form a lead chart for the work to be done. Before the work of levelling is commenced, the lead chart shall be checked by a responsible officials of the department not below the rank of an E4/E5 in presence of the contractor or his authorised representative and his signatures shall be obtained on the same. This should form an integral part of the contract and should be duly signed by both the parties before commencement of the work. The quantity payable for earthwork shall be lower of the two quantities derived from cutting or filling. The payment for lead shall be based on lead chart prepared in the aforesaid manner. The detailed calculation procedure has been explained as per Annexure-XV.
Every fourth running bill & the paid on the basis of levels. can, however, be made on the measurements. The EIC should quantities thus assessed are not the actual work done.
final bill should be Intermediate payments basis of borrow pit take care that the in any case more than
vi)
1.10.3
For gravel work, a detailed record of material brought by the contractor shall be maintained by the Site Engineer. Gravelling work shall be measured both ways i.e. stack measurement shall be taken before spreading the gravel and it shall be counter checked by measuring after the same has been spread and compacted. Both the modes of measurements shall be recorded in the MB.
Important Items for Measurement Back to contents page Important works within meaning of above, includes items which owing to the situation cannot be subsequently checked or which have very high unit rates. For guidance, these items are classified generally as follows: The list is only indicative and any such or similar items shall fall under this category. (A)
Hidden & Concealed Items Back to contents page
Items of work which owing subsequently be checked.
to
their
situation
cannot
i)
All work below ground level such as : (a) Concrete, Masonary, Steel work etc. in foundations
ii)
Fabricated steel work in columns, beams etc. which are encased either in masonary or concrete.
iii) Wood work, iron work etc. hidden by ceilings, wall panelling or floor boardings. iv)
Bitumen painting of roofs under mud phuska and tiles paving or under terrace concrete.
v)
Water proofing compounds used in grouting cement.
vi)
Lines of pipes buried in floor or masonary in internal sanitary, water supply or drainage installations.
vii) Any other above. (B)
hidden
or
concealed
work
not
mentioned
Costly/Special Items Back to contents page
-
Civil Works Items of works which are considered to have very high unit rates.
i)
RCC work.
ii)
Items in sunk ashlar stone or marble work, plain sunk or moulded in walls, columns, arches or domes. Any other stone superior to marble.
iii) Stone or marble in wall lining. iv)
v)
vi)
a)
All wood work in Chowkhats, trusses whether in country, Burmah teakwood.
frames Indian
or or
b)
All joinery work in shutters trellis works, miscellaneous wood work etc. whether in country, Indian or Burmah teakwood.
c)
All brass, oxidised brass or other similar costly fit-tings of doors, windows etc. where payable separately. Items of aluminium door/windows/glazing work.
a)
Steel work cut, hoisted and fixed or steel work fabricated, hoisted and fixed.
b)
Steel doors, windows, shutters, grills etc.
Flooring, skirting and dado work in situ-mosaic, terrazo tiles, Shahbad stone slabs, Agra stone slabs, or marble slabs.
vii) Ceiling with A.C. sheets, hard board insulation board or wooden planks. Items of false ceiling and its support system. viii)All sanitary fittings such as wash basins, sinks, urinals,stall urinals, bath tubs and water closets. ix)
x)
a)
Storage tank items in water supply.
b)
Sluice valves, fire hydrants etc. in water supply.
c)
C.I. or Hume pipes and specials and their lead caulked joints in water supply.
a)
Manholes, ventshafts, road gully chambers, adams syphons, manhole covers and frames.
b)
C.I. Inspection bends and chambers in C.I. Pipes drainage.
-
Electrical Items i)
Welding of aluminium pipes used for bus.
ii)
Welding of substation
ground
mat
used
for
earthing
of
iii) Welding of fire fighting pipes. iv)
Cables burried in ground.
v)
Earthing of substation and equipments.
vi)
Thermal ducts.
insulation
used
for
air
conditioning
vii) Laying & dressing of power & control cables. viii)Tightening of nut clamps/connectors.
(C)
bolts
for
ix)
Electrical fixtures and MCB's
x)
Electrical wires and its conduits.
Recording Pile:
of
Measurements
in
Respect
structures
of
Length
and
of
Back to contents page The method of measurement for different types of piles is given in IS:1200 part (XXIII) latest edition. However, the following method should be adopted in the case of bored cast in situ, driven cast in situ and driven pre- cast piles. Bored Cast-in-situ piles: The steel cage to be lowered in the pile bore hole shall be measured accurately by a steel tape on the ground. After the cage is lowered and rested in the hole, the length of the cage above the cut-off level shall be measured separately with the help of levels. The difference between the total length of the steel cage and the latter length shall be the length of the pile below cut-off level and shall be (x-Y) units (Fig.-I, Sketch-I). Driven Cast - in - situ piles: The height of the shoe shall be measured in advance of its placement in position. The length of the casing pipe to be driven for a particular pile shall be measured with the help of steel tape accurately on the
ground. If more than a single piece of casing pipe is required to be driven into the hole, the same shall also be measured. After the casing has been driven to refusal as per specification, the length of the casing above the cut-off level shall be measured with the help of levels. The length of the pile below cut off level shall be calculated by deducting the later length from the total length of the casing pipe(s) plus the shoe height (Fig.-I, Sketch-II) and shall be (x+z-y) units. However in case the reinforcement cage is made by joining two or more no. of cages then the overlapping distances at the joints should not be considered. Driven pre-cast The length of the pre-cast pile shall be measured upto toe with the help of steel tape accurately on the ground. The length above cut off level shall be measured with the help of levels. The length of the pile below cut off level/shall be (x-y) units(Fig.-I, Sketch-III). (D)
Measurement of Steel Bars: Back to contents page Bar or any other type of reinforcement used, like hard drawn steel wire fabric etc. for reinforced concrete shall be measured by weight in Tonnes. The weight shall be arrived at by multiplying the actual or theoretical length measured along standard hooks, cranks, bends, authorised laps etc. whichever is less, by the sectional weights. Claims for payment for this item shall be submitted with supporting document giving the schedule of Bars with sketches. The sectional weight to be adopted shall be IS Sectional weight. Standard hooks, cranks, bends, authorised laps etc. shall be measured. Separator pieces between two or more layers of steel shall not be measured. No payment shall be made for lap welding or butt welding if permitted, supports, chairs, hangers, etc. of height 300 mm and less, required for keeping the steel in position unless otherwise specified in the contract. For supporting horizontal reinforcement at heights larger than 300 mm, support drawings shall be prepared by the Contractor and payment shall be made for the supports as approved by the Engineer-inCharge, or as actually placed, whichever is less, at the same rate as for reinforcement.
No extra payment shall be paid for modification of already embedded reinforcement, if required due to faulty fabrication or placement. Dowels neither shown in the drawings nor instructed by the Engineer-inCharge, but required for construction facilities and/or sequences, shall not be measured.
(E)
Measurements of Earth Mat & Fire Fighting Pipes Back to contents page Earth Mat & hidden items these items hidden items
(F)
Fire Fighting Pipes shall be treated as and the measurements & the test check of shall be carried out as applicable to of Civil construction works.
Antiweed Treatment in Substation Back to contents page Anti-weed treatment shall be treated as hidden items and the measurements & the test check of these items shall be carried out as applicable to hidden items of Civil construction works.
Section-Two Guidelines
----------------------------------------------------------------SECTION
TWO ----------------------------------------------------------------GUIDELINES Back to contents page
2.1
Guidelines for maintenance of MB/AB Back to contents page
2.1.1
The Measurement Book/Abstract Book must be looked upon as the most important record since it is the basis of all accounts of quantities, work done by daily labour, by the piece worker or contractor or of materials received, which have to be counted or measured. The description of the works must be such as to admit the easy identification and check. Before the book is brought into use, the pages should be examined and any serious defects such as tearing off or the substitution of pages brought to notice at once.
2.1.2
All entries in Measurement Book/Abstract Book should be made in ink/dot pen.
2.1.3
As all payments of works or supplies must be based on the quantities recorded in the Measurement Book, it is incumbent upon the person taking the measurement to record the quantities clearly and accurately. If the measurements are taken in connection with a running contract on which work has been previously measured. He is further responsible (1) that a reference to the last set of measurement is recorded (2) that if entries for job or contract have been completed the fact is recorded prominently just above his initials.
2.1.4
Entries should be recorded continuously in the Measurement Books/Abstract Book. No blank page may be left and no page torn out. Any page left blank inadvertently must be canceled by diagonal lines, the cancellation being attested. No, entry should be crossed, or effected so as to be legible. If a mistake is made, it should be corrected by crossing out the incorrect words or figures and rewriting in the words or figures and the correction thus made should be initialed and dated by the officer making it. When any measurements are cancelled, the cancellation must be supported by the dated initials of the officer ordering the cancellation or by a reference to his orders by the officer who made the measurements. In either case, the reason for cancellation should be recorded. A reliable record is the object to be aimed at as it may have to be produced as an evidence in court of law.
2.1.5
No lines may be left blank. The lines not required should be carefully crossed out in ink in order to prevent additional entries being made afterwards. The total carried forward from the previous page of a measurement book should be entered above the top line, similarly the total at the foot of each page should be entered below the bottom line.
2.1.6
Each Measurement Book should be provided with an index which should be posted upto date as measurements are recorded in the book.
2.1.7
The signature of the contractor or his agent should be obtained in measurement book after such set of measurements with the addition, I accept all measurements. In the case of illiterate men their thumb impression may be taken.
2.1.8
Construction Engineers are responsible for the correctness of the entries in Measurement Book.
2.1.9
Check-measurements should be noted in Measurement Books, the items actually check measured being distinguished by the initials of checking officer.
2.2.
Guidelines for filling up of Statement (MRS, Annex.-Va & Vb)
Material
Reconciliation
Back to contents page 2.2.1
Itemwise proforma at Annexure-Va for receipt of various materials is to be submitted alongwith every IIIrd RA bill as well as the final bill by the erection contractor or his authorised representative and POWERGRID official recording the bill.
2.2.2
Items received datewise in various consignments in the period since the last MRS should be indicated in columns no. 1 to 14.
2.2.3
For supplies from the manufacturers, name of manufacturer should be filled up in column no.3. However, for supplies diverted from other regions, name of region should also be entered in this column. Possibly the make/manufacturer's name should also be mentioned.
2.2.4
MRHOV/TOC No. should be indicated for materials from suppliers in column no.8. MTV should also be filled up in this column if the supplies are diverted from other regions /other packages at the same site.
2.2.5
Itemwise opening balance from the last such Reconciliation statement for good/complete and damage/incomplete material should be entered in column No. 5&6. These entries have to be taken from Column (9&10) of Annexure-Vb submitted with the last MRS.
2.2.6
For material transferred out to other sites/regions, entries should be filled up in column no. 15 & 16. (Name of the site/region should also be filled up in Column No.3 along with all details of MTV No., make & date etc.)
2.2.7
Net receipt entries of Column No. 17 & 18 in Annexure-Va should be reproduced in column no. 2 & 3 of Annexure-Vb.
2.2.8
Material reconciliation statement for consumption (at Annexure-Vb) should be filled while preparing every IIIrd RA as well as the final bill by the erection contractor or his authorised representative and POWERGRID official recording the bill.
2.2.9
For control purpose RAB No. statement No. should be the same.
2.2.10
Material consumed since last reconciliation should be entered in Column No. 4 of Consumption Statement (Annex.Vb).
2.2.11
All the columns in the Annexure are self explanatory and should be filled up accordingly.
and
receipt/consumption
Section-Three Formats & Proforma
----------------------------------------------------------------------------------SECTION
THREE -----------------------------------------------------------------------------------
FORMAT OF MEASUREMENT BOOK
ANNEXURE-I Back to contents page POWER GRID CORPORATION OF INDIA LIMITED
GROUP.................... M.B.NO..........
RA BILL NO.............PAGE NO......
+-------------------------------------------------------------------+ ¦Sl.¦Item ¦DESCRIPTION ¦Carried Over¦ Details of ¦Content¦ ¦No.¦No. of¦ ¦to page No. ¦ actual ¦-------¦ ¦ ¦BOQ ¦ ¦of Abstract ¦ measurements ¦Area ¦ +---¦------¦------------¦------------¦----------------------¦-------¦ ¦ ¦ ¦ ¦ ¦ No ¦ L ¦ B ¦ D ¦ ¦ +---¦------¦------------¦------------¦----¦-----¦-----¦-----¦-------¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ +-------------------------------------------------------------------+ Dtd. sign. of the officer preparing the bill Dtd. Sign of contractor
Engineer/Sr. Engineer
Dtd. sign. of the officer authorising payment Dy. Mgr./Mgr./Chief Mgr.
Annexure-II Back to contents page FORMAT OF ABSTRACT BOOK
POWER GRID CORPORATION OF INDIA LIMITED
Period of Measurement
From………………..to………………………
Date of Recording of Measurement Schedule date of completion as per Bar Chart Actual Date of Completion (in case of final Bill) Reference to previous RA Bill RUNNING/FINAL BILL No............
Book No. .......... Page No. .......... +--------------------------------------------------------------------+ ¦Item No¦Descrip-¦Ref. ¦Quantity Executed ¦ ¦ ¦ AMOUNT ¦ ¦of BOQ ¦tion of ¦page no+------------------¦ ¦ ¦--------------¦ ¦ ¦work ¦of MB ¦Upto date¦Since ¦ ¦ ¦Upto ¦Since ¦ ¦ ¦ ¦ ¦ ¦Previous¦Unit¦Rate¦Date ¦Previous¦ +-------¦--------¦-------¦---------¦--------+----¦----¦-----¦--------¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ +--------------------------------------------------------------------+ Dtd. sign. of the Officer preparing the bill
Dtd. sign. of contractor
Engineer/Sr. Engineer
Dtd. sign. of the officer authorising payment Dy.Mngr./Mngr./Chief Mngr.
Annexure-III Back to contents page FORMAT OF RUNNING/FINAL ACCOUNT BILL
POWER GRID CORPORATION OF INDIA LIMITED Name of the work
:
Name of the Contractor
:
LOA No.
:
Period of Measurement
From…………….to…………………
:
Date of Recording of Measurement
:
Scheduled date of completion as per Bar Chart
:
Actual Date of Completion (in case of final Bill) : Reference to previous RA Bill
:
RUNNING/FINAL BILL No............ +--------------------------------------------------------------------+ ¦Item No¦Descrip-¦Ref. ¦Quantity Executed ¦ ¦ ¦ AMOUNT ¦ ¦of BOQ ¦tion of ¦page no+------------------¦ ¦ ¦--------------¦ ¦ ¦work ¦of MB ¦Upto date¦Since ¦ ¦ ¦Upto ¦Since ¦ ¦ ¦ ¦ ¦ ¦Previous¦Unit¦Rate¦Date ¦Previous¦ +-------¦--------¦-------¦---------¦--------+----¦----¦-----¦--------¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦TOTAL¦ ¦ ¦ ¦ ¦ ¦Add/deduct tender percentage if any ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ Total value of work upto date ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ Deduct upto date value of work ¦ ¦ ¦ ¦ ¦ ¦ shown in previous bill ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ Value of work since prev. bill ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ +--------------------------------------------------------------------+ CERTIFICATE & SIGNATURES 1.
The
measurement
recorded
above
are
based
on
the
entires
at
pages....to....of Measurement by...........on.............
Book
No....which
were recorded
2.
Certified that not less than the quantity of work shown above has actually been executed by the contractor.
3.
Certified that no other materials Plant/Machinery as shown in the schedules attached have been issued to the contractor.
4.
Certified that work has been completed as per specifications and methods of measurment are correct.
5.
There are no claims against the contractor.
Certificate No.4&5 are to be issued for final bills only
Dtd. sign. of the officer preparing bill
Dtd. sign. of the officer authorising payment
Dtd. sign. of contractor
Engr./Sr. Engr.
Dy. Mngr./Mngr./ Chief Mngr.
Running/Final Bill No........ Dated............... MEMORANDUM OF PAYMENT (FOR USE IN ACCOUNTS OFFICE) -----------------------------------------------------------------Value of Works since previous ¦ Bill payment now to be made as detailed ¦ below by recovery of amount creditable to ¦ ¦ i) Income tax ¦ ii) Security Deposit ¦ iii) Mobilisation advance ¦ iv) Interest ¦ v) Secured Advance ¦ vi) Retention Money ¦ vii) Cost of Material ¦ a) Cement ¦ b) Steel Mild ¦ c) Steel Tor ¦ d) Others ¦ viii)Rebate ¦ ix) Other Recoveries ¦ Total of Recoveries¦ ------------------------------------------------------------------
Pay....................Rs.................. Acctt/Sr.Acctt.
Acctt. Officer
Sr. Acct Officer
Manager(F)
Received Rs....................................... (Rs..............................................) +--------+ ¦ Stamp ¦ ¦ ¦ ¦ ¦ ¦ ¦ +--------+ (Full Signature of the Contractor) Paid by me vide cheque No.............of .............. ---------------------------------------------------------------Remarks
Annexure -IV Back to contents page FORMAT OF JOINT MEASUREMENT CERTIFICATE
POWER GRID CORPORATION OF INDIA LTD. JOINT MEASUREMENT CERTIFICATE(T/L. FOUNDATION) Name of Group Name of Line LOA No. & Date Executing Agency
: : : :
JMC No. .................. Loc No. .................. Drawing No. .................. (1) (a)
Date: ..................... Type of tower ............. Fndn. classification....... Depth of water table ......
Excavation Details Type of soil +------------------------------------------+ ¦ DESIGNATION¦ TYPE OF SOIL & DEPTH ¦ ¦ OF PIT +-----------------------------¦ ¦ ¦ DRY ¦ WET ¦ HARD ¦ FR ¦ HR ¦ +------------+-----¦-----¦-------¦----¦----¦ ¦ PIT A ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ PIT B ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ PIT C ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ PIT D ¦ ¦ ¦ ¦ ¦ ¦ +------------------------------------------+
b) c)
AREA OF PIT : L= .... mt. B= ..... mt. AREA = ..... sq. m. Vol. of Excavation = .......cu. m.
2) a)
Checking of casting Alignment of loc. & template b) Diagonal c) Level d) Quality of i) Metal ii) Sand iii) Cement iv) Reinforcement v) Water 3)
Concreting Details
= ..... = ..... = ..... = = = = =
.... .... .... .... ....
a) b) c) d)
Volume of concrete (1:2:4) Volume of concrete (1:3:6) Quant. of cement bags Quant. of Reinforcement (Dia. wise)
4)
Test cube prepared
= = = =
.......cu. m. .......cu. m. .......Bags .......MT
= ....
CERTIFICATE: WORK IS EXECUTED AS PER SPECIFICATION.
FOR CONTRACTOR
FOR POWERGRID
Signature ......
Signature ......
Name: .........
Name ...........
Design. ........
Design.(Jr.Engr./E1/E2/E3)
Date
Date ...........
........
Name of Contractor:Statement No.:Package Name/LOA:-
ANNEXIURE-VA
Back to contents page PROFORMA OF MATERIAL RECONCILIATION STATEMENT (RECEIPTS) Item Name Sl. No.
Name of Manuf./ Site or Region
Unit
Opening Balance
Good/ Comp. 1
2
i)
E/W
3
4
5
Date
MRHOV/ MRC/ MTV No.
Damage/ Incomp. 6
7
8
Received from Supplier
TRANSFER/ IN
TOTAL RECEIPT
TRANSFER OUT
NET RECEIPT =(OP.BAL+TOT. RECT.)-TR.OUT
GOOD/ COMP.
DAMAGE/ INCOMP.
GOOD/ COMP.
DAMAGE/ INCOMP.
GOOD/ COMP.
DAMAGE/ INCOMP.
GOOD/ COMP.
DAMAGE/ INCOMP.
GOOD/ COMP.
DAMAGE/ INCOMP.
9
10
11
12
13=9+11
14=10+12
15
16
17=5+13-15
18=6+14-16
----TOTAL ii)
ACSR -----TOTAL
iii)
M.S. Jt. For ACSR TOTAL
CONTRACTOR Signature ......... Name ............ Desgn. ............ Date .............
Name of Contractor:-
POWERGRID Signature ......... Name ............. Desgn. (Supr./E1/E2/E3) Date .............
Statement No.:Package Name/LOA:-
Annexure-VB Back to contents page
PROFORMA OF MATERIAL RECONCILIATION STATEMENT (CONSUMPTION) _________________________________________________________ FOR FINAL BILL _____________________________________________________ Sl. No.
Item Receipt
Good/ comp. 1
2
Qty. consumed since prev.
Allowable wastage
Damage/ Incomp. 3
Actual wastage by contractor
Total consumption= consumed+ (allow.\ actual wastage)
Qty. 4
5
6
7
8=4+(6or7)*
Material lying with the contractor
Balance Mat. to be Returned to POWERGRID
GOOD/ COMP.
DAMAGE/ INCOMP.
GOOD/ COMP.
DAMAGE/ INCOMP.
9=2-8
10=3
11=9+(7-6)#
12=10
MATERIAL RETURNED
GOOD/ COMP.
DAMAGE/ INCOMP.
13
14
MATERIAL NOT RETURNED/TO BE RECOVERED
GOOD/ COMP.
DAMAGE/ INCOMP.
15=11-13
16=12+14
CONTRACTOR
POWERGRID
POWERGRID
Signature .........
Signature .........
Signature .........
Name
Name
Name
............
.............
.............
Desgn. ............
Desgn. (Jr. Engr./E1/E2/E3)
Group Head …………………….
Date
Date
Date ……………………………….
.............
1. * Whichever is high 2. # If (7-6) > 0 otherwise 11=9
.............
Annexure-VI FORMAT OF STOCK REGISTER FOR MEASUREMENT/ABSTRACT BOOKS
Back to contents page POWERGRID CORPORATION OF INDIA LIMITED (A Govt. of India Enterprise) +--------------------------------------------------------------------------------------------------+ ¦ ¦ ¦ Receipt ¦Cumula-¦ Issued ¦Balance ¦ Verif- ¦ ¦Sl.¦Open.+---------------------------¦tive +----------------------------------¦Stock ¦ ied by ¦ ¦No.¦Bal. ¦Date¦No. ¦Sl. No.¦ Recd. ¦Receipt¦Date¦No.¦Sl. No. ¦Issued ¦Issued ¦ ¦ ¦ ¦ ¦ ¦ ¦of ¦ ¦ by ¦ ¦ ¦of ¦of books¦ by ¦ to ¦ ¦ ¦ ¦ ¦ ¦ ¦Books¦From-To¦(Sign.& ¦ ¦ ¦bo-¦ ¦(Sign.&¦(Sign.&)¦ ¦ (Sign.&¦ ¦ ¦ ¦ ¦ ¦ ¦Design.)¦ ¦ ¦oks¦ ¦Design)¦Design.)¦ ¦ Design)¦ ¦ 1 ¦ 2 ¦ 3 ¦ 4 ¦ 5 ¦ 6 ¦7=(2+4)¦ 8 ¦ 9 ¦ 10 ¦ 11 ¦ 12 ¦13=(7-9)¦ 14 ¦ +---+-----+----+-----+-------+--------+-------+----+---+--------+-------+--------+--------+--------¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ +--------------------------------------------------------------------------------------------------+
Annexure-VII Back to contents page FORMAT OF CERTIFICATE FOR FINAL BILLS
POWER GRID CORPORATION OF INDIA LIMITED
NAME OF WORK
................
LOA NO. & DATE: ............ NAME OF CONTRACTOR
......................
1)
Measurements recorded at Page No. ……………………… to ………………………. Of MB No. …………………… are accepted.
2)
Certified that the quantities under BOQ item No. ………………… was not required in the work and hence has not been executed.
2)
Final measurement and payment accepted in full and final settlement of the contract and there are no dues against this contract.
3)
There are no claims against this contract. SD/- & date CONTRACTOR
1)
Certified that the work on …………………………………………..
2)
Certified that site has been cleared by the contractor.
3)
Certified that the quantities of BOQ No......... was not required in this work and the same has not been executed through any other agency during the currency of the contract.
SD/- & Date E1/E2/E3
is
SD/- & Date E4/E5
hereby
taken
over
by
SD/- & Date Group Head
POWERGRID
Annexure - VIII Back to contents page FORMAT OF BILL MOVEMENT SHEET
POWER GRID CORPORATION OF INDIA LIMITED BILLS MOVEMENT SHEET (BY GHQ)
1)
Contract No. & date
:
_________________________
2)
Name of the Contractor
:
_________________________
3)
Name of work
:
_________________________
4)
Bill No and date
:
_________________________
5)
Date of receipt of the Bill by E-I-C
:
_________________________
Date of forwarding of Bill to Finance by Group Head and Despatch No.and MB/AB nos.
:
_________________________
Gross value of the R/A Bill
:
_________________________
6)
7)
Sign. of E4/E5
Sign. of Grp. Head (BY FINANCE DEPTT.)
1)
Contract No. & date
:
_________________________
2)
Name of the Contractor
:
_________________________
3)
Name of work
:
_________________________
4)
Bill No. and date
:
_________________________
5)
Date of receipt of the Bill
:
_________________________
6)
Date of passing the bill
:
_________________________
7)
Date of returning the bill to E-I-C and despatch no.
:
_________________________
Sign. of AO/Sr. AO/DM F&A
Sign. of Head/HOD
Annexure - IX Back to contents page LOCATION CODES
POWER GRID CORPORATION OF INDIA LIMITED LOCATION CODE : (1st DIGIT) 1.0
2.0
LOCATION
CODE
CORPORATE CENTRE (CC)
1
NATIONAL LOAD DESPATCH CENTRES (NLDCC)
2
NORTHERN REGION (NR-I)
3
NORTHERN REGION (NR-II)
4
EASTERN REGION (ER)
5
NORTH EASTERN REGION (NER)
6
WESTERN REGION (WR)
7
SOUTHERN (SR)
8
--
9
LOCATION CODE (II & III DIGIT) POWERGRID'S Groups/Sub Stn./Site Offices (01 to 40) NR-I BASSI (JAIPUR)
01
BALLABGARH
02
MANDOLA
03
AGRA
04
MURADNAGAR
05
BAREILLY
06
DADRI
07
RIHAND
08
VIDHYACHAL
09
KANPUR
10
ALLAHABAD
11
SHAKTINAGAR
12
NR - II WAGOORA
01
KISHENPUR
02
SALAL
03
SARNA
04
NURPUR
05
MOGA
06
MALERKOTLA
07
HISSAR
08
JAMMU
09
JALANDHAR
10
ABDULLAPUR
11
NALAGARH
12
ER FARAKKA
01
KAHALGAON
02
DURGAPUR
03
MAITHON
04
JAMSHEDPUR
05
ROURKELA
06
RENGALI
07
INDRAVATI
08
JEYPORE
09
MALDA
10
SILIGURI
11
BIRPARA
12
POOORNEA
13
DALKHOLA
14
NER MISA
01
BALIPARA
02
SALAKATI
03
IMPHAL
04
DIMAPUR
05
JIRIBAM
06
AIZWAL
07
HAFLONG
08
KUMARGHAT
09
NIRJULI
10
WR ITARSI
01
JABALPUR
02
BHADRAWATI
03
DEHGAM
04
SR GUNTUR
01
GHATKESAR MANDAL
02
CUDDAPAH
03
SALEM
04
BANGALORE
05
GOOTY
06
RAICHUR
07
KHAMMAM
08
VIJAYWADA
09
VISAKHAPATNAM
10
TRICHY
11
UDUMALPET
12
MADURAI
13
TRICHUR
14
CHENGULPET
15
JEYPORE
16
KORAPUT
17
3.0
STORES AT SEB'S SUB-STATION HAVING POWERGRID BAYS - CODE 41 TO 70
4.0
OFFICES AT SLDC (SUB-LOAD DESPATCH CENTRE) - CODE 71 TO 99 Illustration For Numbering MB/AB
(i)
Code for Constrn. Mgt.in Corp. Centre for MB No.125 is 1/CM/MB/125
(ii)
Code for Shaktinagar office in NR-I for MB No.112 is 3/12/MB/112
(iii)
Code for Abdullapur office in NR-II for AB No. 156 is 4/11/AB/156
Annexure-X Back to contents page FORMAT OF INDEX FOR TEST CHECKING
BOOK NO. ............. POWERGRID CORPORATION OF INDIA LIMITED MEASUREMENT BOOK I N D E X --------------------------------------------------------------------------------------------Sl. Page Name of Name of RA Bill Work order Details of test check Remarks No. Fromcontra- work No. & No./AgreeTo ctor Executed date ment No. & -----------------------date Page Design. of test No.& checking Date official ---------------------------------------------------------------------------------------------
___________________________________________________________________________________________________
Annexure-XI Back to contents page FORMAT OF LEVEL BOOK
POWER GRID CORPORATION OF INDIA LIMITED +-------------------------------------------------------+ ¦STATION¦ R E A D I N G S ¦R.L OF PLANE¦REDUCED¦REMARKS¦ ¦ +-----------------¦ OF ¦LEVEL ¦ ¦ ¦ ¦ BACK¦INTER¦FORE ¦COLLIMATION ¦ ¦ ¦ ¦ ¦SIGHT¦SIGHT¦SIGHT¦ ¦ ¦ ¦ +------- ¦-----¦-----¦-----¦------------¦-------¦-------¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ ¦ +-------------------------------------------------------+ Sign. ............ Name ............ Desig.(Jr.Engr./E1/E2/E3) Date ......
Section-Four Checklist & Flow Diagram
Annexure- XII Back to contents page
FORMAT OF CHECK LIST FOR RUNNING ACCOUNT BILLS
POWER GRID CORPORATION OF INDIA LIMITED
NAME OF WORK
.............
LOA NO. ........
NAME OF CONTRACTOR
.............
DATE ...........
RUNNING BILL NO.
.............
1)
2)
3)
4)
5)
6)
7)
8)
9)
10)
11)
Has the bill been prepared in the specified form and in ink/types.
:
YES/NO
Has the Contractor/Attorney signed the bill and accepted the measurements.
:
YES/NO
Have the measurement been test checked as per procedure.
:
YES/NO
Have all the items billed been covered by the sanctioned rates.
:
YES/NO
Has the work measured been executed within the period of completion as per the LOA/extension of time granted.
:
YES/NO
Does the quantities billed fall within the quanttities provided in the agreement.
:
YES/NO
Have the entries for the realisation of cost of materials issued/services rendered been made.
:
YES/NO
:
YES/NO
Has the statement submitted regarding Theoretical/ Actual consumption of cement/ steel.
:
YES/NO
All cuttings & overwriting have been checked & signed by E-I-C
:
YES/NO
Have the Material Reconciliation Statements both for Receipt & Consumption enclosed (with every 3rd RA bill)
Any other specific point (if any)
.............................................. .............................................. .............................................. .............................................. .............................................. .............................................. .............................................. .............................................. .............................................. ..............................................
Field Engineer
Work Incharge
Name
Name
...........
...........
Design. ...........
Design. ...........
Date
Date
...........
...........
Annexure- XIIIA Back to contents page
FORMAT OF CHECK LIST OF FINAL BILL FOR EARTH WORK
POWERGRID CORPORATION OF INDIA LIMITED (TO BE SUBMITTED WITH FINAL BILL)
Name of contractor ............................. LOA No. and date ................................... Special Checks to be exercised in case of final bill : 1.
Whether L section and cross section levels at the specified intervals (whether so required) have been recorded prior to commencement of the work and on completion of the work.
2.
Whether the level books have been kept in the safe custody of Incharge of the work.
3.
Whether initial ground levels have been recorded in the level book and got duly signed from the contractor or his authorized representative/agent and POWERGRID prior to the commencement of the work?
4.
5.
6.
Whether blocks levels recorded have been countersigned by the Incharge of the work? Whether record of levels with grid plan (which forms the basis for future measurements) have been made and original deposited with Engineer Incharge with one copy to Finance and accounts Departments, one copy to contractor and one copy to Jr. Engineer/ Engineer measuring the work?
Whether the compaction test results to the required percentage
YES/NO
YES/NO
YES/NO
YES/NO
YES/NO
have been achieved for each layer? If so mention the number of tests on specified surface area of each layer recorded? 7.
Whether location mentioned in the MB tally with those in the level book? (Uniformity in location mentioned in various documents should be maintained to ensure proper checks)
8.
Whether the calculations of quantities have been checked properly?
9.
Whether any extra earth is brought from outside the specified area for levelling and if so whether their location has been approved by Engineer I/C and quantum indicated separately?
10.
Whether the measurement have been taken as per the methods of measurements specified in special conditions/ specifications applicable to the contract?
11.
Whether all the excavated materials like singles, boulders, stones, ballast etc. which are not utilised in the levelling work and are required to be stacked as per direction of the E-I-C have been stacked properly (Counter check over the quantity with reference to the stacked materials with due allowance for voids/ shrinkage should be exercised).
12.
13.
14.
Whether the classification of soil other than 'ordinary soil' has been checked at each stage of recording measurements and approved by the E-I-C of the works: Whether all payments made for lead and lift have been measured as per pre-determined scheme of Lead and Lift for each area as approved by E-I-C of works? (The official recording the measurements of lead in MB shall record a certificate in the MB to the effect that the lead has been approved by the E-I-C) Where the excavation is in partial cutting and partial filling, the
YES/NO
YES/NO
YES/NO
YES/NO
YES/NO
YES/NO
YES/NO
YES/NO
YES/NO
disposal of earth which is cut should be indicated to ensure that payment for filling is not made for more than the necessary quantity. This shall have to be indicated on a plan grid with specified area indicating = ± filling/cutting.
Field Engr.
Work Inch.
Sig.
......
Sig.
......
Name
......
Name
......
Design. .....
Design. ....
Date
Date
Note:-
.....
....
The L-Section and cross-section to be prepared as per the direction of the E-I-C depending on the volume of work.
Annexure- XIIIB Back to contents page FORMAT OF CHECK LIST OF FINAL BILL (GENERAL)
POWERGRID CORPORATION OF INDIA LIMITED (TO BE SUBMITTED WITH FINAL BILL BY E-I-C)
Name of contractor ............................. Name of Works
.............................
LOA No. and date
.............................
1)
All the points (1 to 10) in checklist for RA Bill(Annex.- XII) have been taken care .
Yes/NO/NA
2)
Whether copies of LOA/ agreement available with all concerned.
Yes/NO/NA
3)
Final time extension approved by competent Authority(C/A).
Yes/NO/NA
4)
Final deviation statement approved by C/A.
Yes/NO/NA
5)
Final escalation bill has been submitted to Finance Department.
Yes/NO/NA
6)
Extra item/deduction item/substituted items have been got approved by C/A (to mention approval ref. no. and date)
Yes/NO/NA
7)
Any amendment issued by contracts Deptt. and if so, the reference of the same (Amendment No. and date)
Yes/NO/NA
8)
NOC issued by site.
Yes/NO/NA
9)
All certificates regarding final bill have been entered in MB as per Annexure-VII
Yes/NO/NA
10)
All retentions made upto pre final bill have been reviewed by E-I-C.
11)
All advances (mob., equip., matls. etc.) have been fully adjusted. Approval of C/A for Time Extension has been obtained with/ w.o. levy of LD. (ref. no. and date) and deduction of LD levied if any
12)
Yes/NO/NA
Yes/NO/NA
13)
has been affected in RA Bill No. ..... /Final Bill in full.
Yes/NO/NA
All relevant certificates required for closing of the contract have been received and enclosed.
Yes/NO/NA
14)
Corrections made in the MB of previous RA Bills taken care of in preparing abstract in the final bill.
Yes/NO/NA
15)
Recovery on account of material supplied outside the scope of LOA is made.
Yes/NO/NA
16)
"NO DEMAND CERTIFICATE" by the contractor enclosed.
Yes/NO/NA
17)
Any other specific points, (if any) ................................... ................................... ................................... ................................... ................................... ................................... ...................................
Field Engineer
Work Incharge
Sign.
...........
Sign.
...........
Name
...........
Name
...........
Design. ...........
Design. ...........
Date
Date
...........
...........
ANNEXURE-XIV FLOW DIAGRAM OF PAYMENT PROCEDURE EXECUTION OF WORKS AT SITE
For T/L Works
IF WORK UNDER THE SAME CONTRACT IS DIVIDED IN 2 OR MORE SECTIONS
ABSTRACT OF QTY’S & PAYMENT TO BE RECORDED IN FOLLOWER AB (FAB) BY INDIVIDUAL SECTION INCHARGE
ABSTRACT OF QTY’S & PAYMENT TO BE TRANSFERRED TO MAB WITH CROSS REFERENCE
For S/S works
PREPARATION OF JMC FOR FOUNDATION WORKS
PREPARATION OF JMC FOR HIDDEN ITEMS IF NOT RECORDED IN MB IMMEDIATELY
RECORDING OF MEASUREMENTS IN MB
RECORDING OF MEASUREMENTS IN MEASUREMENT BOOK (MB)
PREPARATION OF ABSTRACT OF QTY’S & PAYMENTS (BOTH PREVIOUS & UPTO DATE) IN ABSTRACT BOOK (AB)
RECORDING OF MEASUREMENTS IN ABSTRACT BOOK (AB)
PREPARATION OF RUNNING BILL (RAB) IN TRIPLICATE ON THE BASIS OF ABSTRACT
PREPARATION OF RUNNING BILL (RAB) IN TRIPLICATE ON THE BASIS OF ABSTRACT
PREPARATION OF MATERIAL RECONCILIATION STATEMENT (MRS) BOTH FOR RECEIPT & CONSUMPTION WITH EVERY IIIRD RAB
FORWARDING OF COMPLETE BILL TO FINANCE
1. RAB IN DUPLICATE 2. AB 3. MB SHEETS IN 2 COPIES 4. CERTIFICATE & CHECKLIST 5. MRS WITH EVERY IIIRD RAB 6. BILL MOVEMENT SHEET
CHECKING OF BILL BY FIN. DEPTT. MAKING ALL RECOVERIES, ADJUSTMENTS, TAXES & PLACING THE PASS ORDER
RELEASE OF PAYMENT
RETURN OF DOCUMENTS TO FIELD OFFICIALS
1. AB WITH PASS ORDER 2. IIND COPY OF RAB ALONG WITH PASS ORDER 3. IIND COPY OF MB DULY CORRECTED, IF ANY 4. BILL MOVEMENT SHEET
Annexure- XV Back to contents page CALCULATION OF EARTH VOLUME FROM SPOT LEVELS
In this method, the field work consists in dividing the area into a number of squares, rectangles or triangles and measuring the levels of their corners before and after the construction. Thus, the depth of excavation or height of filling at every corner is known. Let us assume that the four corners of any one square of rectangle are at different elevations but lie in the same inclined plane. Assume that it is desired to grade down to a level surface a certain distance below the lowest corner. The earth to be moved shall be a right truncated prism, with vertical edges at a, b, c and d [Fig. a]. If ha, hb, hc and hd represent the depth of excavation of the four corners, the volume of the right truncated prism shall be given by V = {(ha +hb +hc +hd)/4} X A = average height x horizontal area of the rectangle. Similarly, let us consider 'the triangle abc of Fig. (b). If ha, hb and hc, are the depths of excavation of the three corners, the volume of the truncated triangular prism is given by
1
2
a
b
d
c
2
4
2
4
3
e
f
4
Fig.(a)
3
1
2
2
4
1
1
1
Fig. (b)
V={(ha+hb+hc)/3} X A =(average depth) x horizontal area of the triangle. Volume of a group of rectangles or squares having the same area.[Fig. (a)]
Let us now consider a group of rectangles 'of the same area arranged as shown in [Fig.(b)]. It shall be seen by inspection that some of
the heights are used once only, some heights are common to two rectangles (such as at b), some heights are common to three rectangles (such as at e), and some heights are common to four rectangles (such as at f). Thus, in Fig. each corner height shall be used as many times as there are rectangles joining at the corner (indicated on the figure by numbers) Let ?h1= the sum of the heights used once. ?h2 = the sum of the heights used twice. ?h3 = the sum of the heights used thrice. ?h4 = the sum of the heights used four times. A = horizontal area of the cross-section of one prism. Then, the total volume is given by V = A(1Sh1+2Sh2+3Sh3+4Sh4)/4 Volume of a group of triangles having equal area [Fig. (b)] If the ground is very much undulating, the area may be divided into a number of triangles having equal area. In this case, some corner heights shall be used once such as point 'a' of Fig.(b) , some twice (such as at d), six times (such as at f) , and seven times (such as at j). The maximum number of times a corner height can be used is eight. Thus, in Fig. (b), each corner height shall be used as many times as there are triangles joining at the corner (indicated in the figure by numbers) . Let ?h1 =the sum of the heights used once. ?h2 =the sum of the heights used twice. ?h3 =the sum of the heights used thrice. ......................................... ......................................... ?h8 = the sum of height used eight times. A = area of each triangle. The total volume of the group is given by V=A/3(l?h1+2?h2+3?h3+4?h4+5?h5+6?h6+7?h7+8?h8)