Engosoft

PMP Presentation

Saad Merie, PMP Planning Engineer

PMP Preparation Course – Engosoft – Saad Merie

Introduction

The Exam PMBOK Why I need PMP

PMP Preparation Course – Engosoft – Saad Merie

Introduction Why I need PMP PMP Holder

Non-PMP Holder

Globally Accredited More Salary (10-15% more)

More Job Ofers

Nothing of that

+71400 0

PMP Preparation Course – Engosoft – Saad Merie

Introduction The Exam: Duration

200 Questio n

4 Hours

72 Sec Per Questio n

PMP Preparation Course – Engosoft – Saad Merie

Introduction The Exam: Requirements Trainin g 35 PDUs

Fees

555$

Experience 4500 h (bachelor 4 years)

7500 h (High School)

PMP Preparation Course – Engosoft – Saad Merie

Introduction The Exam: Fees

150$ Register in PMI

405$ Exam Fees

275$ ReExam Fees

PMP Preparation Course – Engosoft – Saad Merie

Introduction The Exam: Passing Score

Proficient

Moderately Proficient

61

Below Proficient

PMP Preparation Course – Engosoft – Saad Merie

Introduction PMBOK Organizations & Framework General

Framework

Organization s

Knowledge Areas Integration

Scope

Time

Cost

Quality

Human Resources

Communication

Risk

Procurement

Stakeholder

PMP Preparation Course – Engosoft – Saad Merie

1. Introduction: General

1.2

temporary endeavor undertaken to create

Project?

a unique product, service, or result. Considered Finished in three cases:

• Complete all objectives (from Owner Side). • Terminated when Can't Complete its objectives. • Terminated when there is no need for it anymore.

PMP Preparation Course – Engosoft – Saad Merie

1. Introduction: General Project

Operation

1.2



Temporary: Has Start and End Dates



Creates a unique product



Progressively Elaborated



Over the Product Life Cycle



Enhancements with production



Enhancements may be small projects

PMP Preparation Course – Engosoft – Saad Merie

1. Introduction: General

1.2

Project Running assembly Building Watering Organizing an an Extension Plants a large Twice on line aa Baking a wedding cake Shelving books at the library in conference a toy factory house week

Operation

PMP Preparation Course – Engosoft – Saad Merie 1.2. 1

1. Introduction: General

Portfolio Subportfoli o

Programs

Projects

Program Subprogram

Projects

Project Phase 1

Phase 2

PMP Preparation Course – Engosoft – Saad Merie

1. Introduction: General

1.4

Project

Progra m

Portfoli o

Result of Company’s Strategic Consideration s

Coordination between projects to obtain benefits not available by managing projects individually

Manage Programs and Projects together to achieve Company’s Strategic Objectives

PMP Preparation Course – Engosoft – Saad Merie 1.4. 3

1. Introduction: General Why we make a Project?

Market Demand

Social Needs

Business Need

Customer request

Environment Environment al Needs Needs al

Legal Legal Requirement Requirement

Technological Technological advance advance

PMP Preparation Course – Engosoft – Saad Merie

1. Introduction: General

1.4. 3

Project Management Office PMO

Supportiv e

Controllin g

Act like Consultant

Force Projects to follow PMO rules

Templates, best practices, Training Projects May not follow PMO instructions

Directive Act like project manager

Rules may be management framework and methodologies High Control

Low Control

Moderate Control

PMP Preparation Course – Engosoft – Saad Merie

1. Introduction: General Project Management Office PMO

Supportiv e

When a project gets started, AProvides centralized group of When you sit down to do your this group makes sure that the process risk your project, the planning team hasfor followed allare of project managers who documents and templates you go to them to find a and good theassigned initiating processes to manage for your project. example of a risk plan that’s have theprojects. right approvals to been useful start on other projects. working.

Controllin g

1.4. 3

Directive

PMP Preparation Course – Engosoft – Saad Merie 1.3

1. Introduction: General What is Project management?

5 Process Groups Planning

47 Processes

Closin g

Initiatin g Monitorin g and Controllin g

Executing

PMP Preparation Course – Engosoft – Saad Merie 2.1

2.1 Organizational Influences Organizations are systematic Organization ?

arrangements of entities (persons and/or departments) aimed at accomplishing a purpose, which may involve undertaking

Structure Functional

projects. Culture and

Style Values

Matrix

Reward System

Projectized

Policies

Communication s Distance Efect Technology Usage

PMP Preparation Course – Engosoft – Saad Merie

2.1 Organizational Influences Organizations Structure Types

Each Employee has one boss (The Functional Manager) Employees are stafed by department (Production, Marketing, Finance ..) Each Department do its part in the project interdependent from other departments Coordination on Functional Managers Level

Functional Organization

2.1.3

PMP Preparation Course – Engosoft – Saad Merie

2.1 Organizational Influences Organizations Structure Types

Project Manager is assigned as coordinator Project Manager has some Authorities Each Department do its part in the project in Coordination with Other Departments Coordination on Lowest Level

Weak Matrix Organization

2.1.3

PMP Preparation Course – Engosoft – Saad Merie

2.1 Organizational Influences Organizations Structure Types

Project Manager work full time Project Manager has more Authorities Project Manager is under Functional Manager Department

Balanced Matrix Organization

2.1.3

PMP Preparation Course – Engosoft – Saad Merie

2.1 Organizational Influences Organizations Structure Types

Project Manager work full time Project Manager has wide but not full Authorities Project Manager is under Projects Management Department

Strong Matrix Organization

2.1.3

PMP Preparation Course – Engosoft – Saad Merie

2.1 Organizational Influences Organizations Structure Types

Project Team work in same place Project Manager has full Authorities All Company’s Resources located in the projects

2.1.3

Projectized Organization

PMP Preparation Course – Engosoft – Saad Merie

2.1 Organizational Influences Organizational Structure Efect

2.1.3

PMP Preparation Course – Engosoft – Saad Merie

2.1 Organizational Influences

2.1.4

Organizational Process Assets (OPA)

The plans, processes, policies, procedures, OPA

and Knowledge bases specific to and used by the performing organization. The Project Team can follow OPA when needed.

PMP Preparation Course – Engosoft – Saad Merie

2.1 Organizational Influences Organizational Process Assets (OPA)

• Internal Guidelines and Policies OPA

• Internal Forms and Templates • Change Procedures • Financial controls procedures • Risk control procedures • Historical information and lessons learned

2.1.4

PMP Preparation Course – Engosoft – Saad Merie

2.1 Organizational Influences

2.1.5

Enterprise Environmental Factors (EEF)

Refer to conditions, not under the control EEF

of the project team, that influence, constrain, or direct the project.

PMP Preparation Course – Engosoft – Saad Merie

2.1 Organizational Influences

2.1.5

Enterprise Environmental Factors (EEF)

• Organizational culture and structure EEF

• Government or industry standards • Existing human resources • Personnel administration • Marketplace conditions • Political climate • Project management information system

PMP Preparation Course – Engosoft – Saad Merie

2.2 Project Stakeholders

2.2.1

All interested entities that may afect on Stakeholders ?

the project in Positive or Negative way. • Project Team • Project Manager • The Owner • The Consultant • Competitor

PMP Preparation Course – Engosoft – Saad Merie 2.2.3

2.2.3 Project Success Will be measured in terms of completing the project within the constraints of:

Quality Cost

Time Scope

As Approved

Resource s and Risk

PMP Preparation Course – Engosoft – Saad Merie 2.4

2.4 Project Life Cycle Project Life Cycle

Design Phase

A project life cycle is the series of phases that a project passes through from its initiation to its closure.

Construction Phase

Maintenance Phase

PMP Preparation Course – Engosoft – Saad Merie 2.4

2.4 Project Life Cycle Construction Phase

Design Phase • • • • •

Initiating Planning Executing Controlling Closing

• • • • •

Initiating Planning Executing Controlling Closing

Maintenance Phase • • • • •

Initiating Planning Executing Controlling Closing

THE PROJECT

PMP Preparation Course – Engosoft – Saad Merie

2.4 Project Life Cycle

2.4

Types

Predictiv e

Iterative

Adaptive

Plan Driven / Waterfall

Repetitive iterations or phases to develop the product

Change Driven / Agile

Scope, Time and Cost Determined early and everything is planned

Each iteration include activities from process groups

Product Concept Submitted in short period and enhance with next submission

Construction Projects

Design Projects

Software Projects

PMP Preparation Course – Engosoft – Saad Merie

2.4 Project Life Cycle

2.4

PMP Preparation Course – Engosoft – Saad Merie

3. Project Management Processes What is Project management?

3.1

PMP Preparation Course – Engosoft – Saad Merie Project Management Process Groups Knowledge Areas

4. Project

Initiating Process Group 4.1 Develop

Integration

Project

Management

Charter

Planning Process Group

Executin g Process Group 4.3 Direct and

4.2 Develop Project Management Plan

Manage Project Work

Monitoring and Controlling Process Group 4.4 Monitor and Control

4.6 Close Project Work 4.5 Perform Integrated Change Control

5.1 Plan Scope Management 5. Project Scope

5.2 Collect Requirements

5.5 Validate Scope

Management

5.3 Define Scope

5.6 Control Scope

5.4 Create WBS 6.1 Plan Schedule Management 6.2 Define Activities 6. Project Time

6.3 Sequence Activities

Management

6.4 Estimate Activity Resources 6.5 Estimate Activity Durations 6.6 Develop Schedule

T 31Closing Process Group

6.7 Control Schedule

Project or Phase

PMP Preparation Course – Engosoft – Saad Merie Project Management Process Groups Knowledge Areas

7. Project Cost Management

8. Project Quality Management

9. Project HR Management 10. Project Communication Management

Initiatin g Process Group

Planning Process Group

Executing Process Group

Monitoring and Controlling Process Group

7.1 Plan Cost Management 7.2 Estimate Costs

7.4 Control Costs

7.3 Determine Budget 8.1 Plan Quality Management

9.1 Plan Human Resource Management

10.1 Plan Communications Management

8.2 Perform Quality Assurance

8.3 Control Quality

9.2 Acquire Project Team 9.3 Develop Project Team 9.4 Manage Project Team 10.2 Manage Communications

10.3 Control Communications

T 31 Closing Process Group

PMP Preparation Course – Engosoft – Saad Merie Project Management Process Groups Knowledge Areas

Initiating Process Group

Planning Process Group

Executing Process Group

Monitoring and Controlling Process Group

T 31Closing Process Group

11.1 Plan Risk Management 11.2 Identify Risks 11. Project Risk

11.3 Perform Qualitative

Management

11.6 Control Risks

Risk Analysis 11.4 Perform Quantitative Risk Analysis 11.5 Plan Risk Responses

12. Project Procurement Management 13. Project Stakeholder Management

13.1 Identify Stakeholders

12.1 Plan Procurement

12.2 Conduct

12.3 Control

12.4 Close

Management

Procurements

Procurements

Procurements

13.3 Manage

13.4 Control

Stakeholder

Stakeholder

Engagement

Engagement

13.2 Plan Stakeholder Management

PMP Preparation Course – Engosoft – Saad Merie

3. Project Management Processes

3.1

Project Information Work Performance Data

Work Performance Information

Raw Data Activity Progress Quality Measures Start and End Dates • Number of Defects

• Analyzing raw data • Deliverables Status • Change Requests Status • Estimated Finish

• • • •

Work Performance Reports • Reports about Data • Dashboards • KPI • Graphs • Suggestions

PMP Preparation Course – Engosoft – Saad Merie 554

Common Terms in PMBOK

Process

Deliverabl e

WBS

Series of activates to get an output(s)

Any Unique and Verifiable result required to be produced to complete the project

Work Breakdown Structure

PMP Preparation Course – Engosoft – Saad Merie 554

Common Terms in PMBOK

Baseline Approved Version of a work product that can be changed only through formal Change Request

Change Request

EEF

A formal proposal to modify any document, deliverable, or baseline.

Conditions, not under the immediate control of the team, that influence, constrain, or direct the project

PMP Preparation Course – Engosoft – Saad Merie

Common Terms in PMBOK

Expert Judgment Judgment provided based upon expertise in an application area

554

Milestone

Product

A significant point or event in a project

An artifact that is produced, is quantifiable, and can be either an end item in itself or a component item

PMP Preparation Course – Engosoft – Saad Merie

Common Terms in PMBOK

554

PMIS

Requireme nt

Resource

Project Management Information System

A condition or capability that is required to be present in a product, to satisfy the contract

Manpower Equipment And Materials

PMP Preparation Course – Engosoft – Saad Merie

Common Terms in PMBOK

Work Authorization System Formal Document define who is authorized to do what, and which are the procedures for the work to be done

554

PMP Preparation Course – Engosoft – Saad Merie

Exam Questions

Q

A project is handled by departments of an organization and expedited by a project coordinator. Which of the following statements is most likely to be true?

a) The performing organization is a weak matrix b) The performing organization is doing "management by projects" c) The performing organization is a strong matrix d) The performing organization is Projectized.

PMP Preparation Course – Engosoft – Saad Merie

Exam Questions

Q

Which of the following is NOT a type of project management office? A. Directive B. Value-driven C. Supportive D. Controlling

PMP Preparation Course – Engosoft – Saad Merie

Exam Questions Which of the following is NOT a characteristic of a project? A. Temporary B. Strategic C. Specific result D. Progressively elaborated

Q

PMP Preparation Course – Engosoft – Saad Merie

Exam Questions Which of the following is NOT true about portfolio management? A. The portfolio manager judges the success of the portfolio by combining data from all of its programs and projects. B. A portfolio can contain projects and programs. C. A portfolio is organized around a business goal. D. A portfolio is always a group of programs.

Q

PMP Preparation Course – Engosoft – Saad Merie

Exam Questions

Q

A project coordinator is having trouble securing programmers for her project. Every time she asks her boss to give a resource to the project he says that they are too busy to help out with her project. Which type of organization is she working in? A. Functional B. Weak Matrix C. Strong Matrix D. Projectized

PMP Preparation Course – Engosoft – Saad Merie

Exam Questions

Q

You’re a project manager working on a software engineering project. The programmers have started building the software, and the testers have started to create the test environment. Which process group includes these activities? A. Initiating B. Planning C. Executing D. Closing

PMP Preparation Course – Engosoft – Saad Merie

Exam Questions

Q

Which of the following is NOT true about overlapping phases?

A. Each phase is typically done by a separate team. B. There’s an increased risk of delays when a later phase can’t start until an earlier one ends. C. There’s an increased risk to the project due to potential for rework. D. Every phase must go through all five process groups.

PMP Preparation Course – Engosoft – Saad Merie 4

4. Project Integration Management Integration ?

includes the processes and activities to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management Process Groups Project Management Process Groups

Knowledg e Areas

4. Project Integration

Initiatin g Planning Process Process Group Group 4.1 Develop project

4.2 Develop Project Management Plan

Executing Process Group

4.3 Direct and Manage Project

Monitoring and Controlling Process Group 4.4 Monitor and Control Project Work 4.5 Perform

Closing Process Group

4.6 Close Project

PMP Preparation Course – Engosoft – Saad Merie

4. Project Integration Management 4.1 Project Charter

4.1

document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.

PMP Preparation Course – Engosoft – Saad Merie

4. Project Integration • Formally Authorize the project Management 4.1 Project Charter

4.1



Define Start and End



Create official record for the project



Guarantee that the project align with company’s strategic goals



It is not a contract



Approved and Changed by the sponsor



should be general so we don’t change it



Scope Changes subject to what is written in Charter



Without Charter, Project Cannot begin

PMP Preparation Course – Engosoft – Saad Merie

4. Project Integration 4.1 Develop Project Charter Management Inputs

Tools & Techniques

4.1

Outputs

.1 Project statement of work .2 Business case

.1 Expert judgment

.3 Agreements .4 Enterprise environmental factors .5 Organizational process assets

.1 Project charter

.2 Facilitation techniques

PMP Preparation Course – Engosoft – Saad Merie

4. Project Integration 4.1 Develop Project Charter Management

4.1

4.1.1 Develop Project Charter: Inputs 4.1.1.1 Project Statement of work

• Description of the product that the project create • Part of the Tender or the Contract • Refer to: • Business need (same as following business case) • Company’s Strategic Plan and where the project fit in it.

PMP Preparation Course – Engosoft – Saad Merie

4. Project Integration 4.1 Develop Project Charter Management

4.1

4.1.1 Develop Project Charter: Inputs 4.1.1.2 Business Case

• Describe from business point of view if the project worth investment. • Determine Project Boarder • Business Case define why we created the project (same reasons mentioned before here)

PMP Preparation Course – Engosoft – Saad Merie

4. Project Integration 4.1 Develop Project Charter Management

4.1

4.1.1 Develop Project Charter: Inputs 4.1.1.3 Agreements

• Can be Contract, Letter of Agreement, Letter of Intent, Email, or any other formal document

PMP Preparation Course – Engosoft – Saad Merie

4. Project Integration 4.1 Develop Project Charter Management

4.1.2 Develop Project Charter: Tools and Techniques 4.1.2.1 Expert Judgment

• Consultants • Stakeholders • Technical Advisors • Industry Experts • Subject Matter Experts (SME) • Project Management Office (PMO)

4.1

PMP Preparation Course – Engosoft – Saad Merie

4. Project Integration 4.1 Develop Project Charter Management

4.1.2 Develop Project Charter: Tools and Techniques 4.1.2.2 Facilitation Techniques

• Brainstorming • Conflict Resolution • Problem Solving • Meeting Management

4.1

PMP Preparation Course – Engosoft – Saad Merie 4.1

4. Project Integration 4.1 Develop Project Charter Management 4.1.3 Develop Project Charter: Outputs 4.1.3.1 Project Charter

Project Manager Authority

Project Purpose

Project Objectives

Assumptions and Constraints

Customer Needs

High Level Requirement s

High Level Risks

Summary Milestone Schedule

Summary Budget

Stakeholder List

Project Success Criteria

Who Approve the Charter

PMP Preparation Course – Engosoft – Saad Merie

4. Project Integration Management

4.2

the process of defining, preparing, and

4.2 Project Management Plan

coordinating all subsidiary plans and integrating them into a comprehensive project management plan. The key benefit of this process is a central document that defines the basis of all project work

PMP Preparation Course – Engosoft – Saad Merie 4.2

4. Project Integration Management • Define how to Execute, Monitor and Close 4.2 Project Management Plan

Project. • It is Progressively Elaborated and prepared over the project life cycle until project close. • It is controlled and approved through Perform Integrated Change Control Process. • When it is baselined, it can be changed Only with Change Request.

PMP Preparation Course – Engosoft – Saad Merie

4. Project Integration 4.2 Develop Project Management Plan Management Inputs

Tools & Techniques

4.2

Outputs

.1 Project charter .1 Expert judgment .2 Outputs from other processes .3 Enterprise environmental factors .4 Organizational process assets

.1 Project management plan .2 Facilitation techniques

PMP Preparation Course – Engosoft – Saad Merie

4. Project Integration 4.2 Develop Project Management Plan Management 4.2.3 Develop Project Management: Outputs 4.2.3.1 Project Management Plan



All other management plans



Scope Baseline, Schedule Baseline, Cost baseline



Selected Project life cycle



Selected processes for this project



Description of the Tools and Techniques for those processes



Description how we maintain the integrity of the baselines



Open Issues and cases

4.2

PMP Preparation Course – Engosoft – Saad Merie

4. Project Integration Management

4.2

PMP Preparation Course – Engosoft – Saad Merie

4. Project Integration Management

4.3

the process of leading and performing the

4.3 Direct and Manage Project Work

work defined in the project management plan and implementing approved changes to achieve the project’s objectives. The key benefit of this process is that it provides overall management of the project work.

PMP Preparation Course – Engosoft – Saad Merie

4. Project Integration 4.3 Direct and Manage Project Work Management Inputs .1 Project management plan .2 Approved change requests .3 Enterprise environmental factors .4 Organizational process assets

Tools & Techniques .1 Expert judgment

4.3

Outputs .1 Deliverables .2 Work performance data

.2 Project management information system

.3 Change requests .4 Project management plan updates

.3 Meetings

.5 Project documents updates

PMP Preparation Course – Engosoft – Saad Merie

4. Project Integration 4.3 Direct and Manage Project Work Management •

Perform Project Activities



Create Deliverables



Acquire, Train and manage project team



Get and manage resources



Apply method of Statements



Create and manage communication tunnels



Issue Change Requests



Manage Risks, Procurement and stakeholders



Collect and manage lessons learned



Apply process enhancements

4.3

PMP Preparation Course – Engosoft – Saad Merie 4.3

4. Project Integration 4.3 Direct and Manage Project Work Management

4.3.1 Direct and Manage Project Work: Inputs 4.3.1.2 Approved Change Requests



Outcome from 4.5 Perform Integrated Change Control



CRs which approved by CCB (Change Control Board)

• Approve • 4.5 Perform Integrated Change Control

CR

• Implement • 4.3 Direct and Approved CR Manage Project Work

• Follow up • 4.4 Monitor and Validated CR Control Project Work

PMP Preparation Course – Engosoft – Saad Merie

4. Project Integration 4.3 Direct and Manage Project Work Management

4.3.2 Direct and Manage Project Work: Tools and Techniques 4.3.2.2 Project Management Information System (PMIS)

Part of EEF that Contain: •

Scheduling Tool



Work Authorization System



Configuration Management System



Information Collection and Distribution System



Interface to Online Automated System



Automated Gathering and Reporting on KPIs

4.3

PMP Preparation Course – Engosoft – Saad Merie

4. Project Integration 4.3 Direct and Manage Project Work Management

4.3.2 Direct and Manage Project Work: Tools and Techniques 4.3.2.3 Meetings



Three Types: 1. Information Exchange. 2. Brainstorming and Options Evaluation. 3. Decision Making.



The Best Practice is to make each type in separate meeting.



Each meeting should have specific Agenda, Purpose and Time.



Should Documented through MOM and Action Items.



MOM to be saved in PMIS as planned.



Preferably FACE to FACE meeting.

4.3

PMP Preparation Course – Engosoft – Saad Merie

4. Project Integration 4.3 Direct and Manage Project Work Management

4.3

4.3.3 Direct and Manage Project Work: Outputs 4.3.3.1 Deliverables

Any Unique and Verifiable result required to be produced to complete the project.

PMP Preparation Course – Engosoft – Saad Merie 4.3

4. Project Integration 4.3 Direct and Manage Project Work Management

4.3.3 Direct and Manage Project Work: Outputs 4.3.3.2 Work Performance Data

Work Performance Data

Work Performance Information

Raw Data Activity Progress Quality Measures Start and End Dates • Number of Defects

• Analyzing raw data • Deliverables Status • Change Requests Status • Estimated Finish

• • • •

Work Performance Reports • Reports about Data • Dashboards • KPI • Graphs • Suggestions

PMP Preparation Course – Engosoft – Saad Merie 4.3

4. Project Integration 4.3 Direct and Manage Project Work Management

4.3.3 Direct and Manage Project Work: Outputs 4.3.3.3 Change Requests



CR: A formal proposal to modify any document, Deliverable, or baseline.



CRs are implemented in this process only. Corrective Action

Preventive Action

Defect Repair

Updates

Realign Project Performance with Project Management Plan

Insure that future performance is aligned with Project Management Plan

Modify the product or part of it as per requirements and standards

Update plans and documents to match new idea or content

PMP Preparation Course – Engosoft – Saad Merie 4.3

4. Project Integration 4.3 Direct and Manage Project Work Management

4.3.3 Direct and Manage Project Work: Outputs 4.3.3.3 Change Requests

Corrective Action

Preventiv e Action

Defect Repair

Final Project Cost Change Honeycomb at Costs areWall over may exceed Colors Columns budget Budget

Updates

PMP Preparation Course – Engosoft – Saad Merie

4. Project Integration Management the process of tracking, reviewing, and 4.4 Monitor and Control Project Work

4.4

reporting the progress to meet the performance objectives defined in the project management plan. The key benefit of this process is that it allows stakeholders to understand the current state of the project, the steps taken, and budget, Schedule, and scope forecasts.

PMP Preparation Course – Engosoft – Saad Merie 4.4

4. Project Integration Management • Compare Actual vs Planned Performance 4.4 Monitor and Control Project Work

• Determine if Change Request is needed • Identify new Risks and follow up current ones • Monitor Product Status • Analyze project information • Prepare Cost and Schedule Estimates • Follow up Implemented Change Requests

PMP Preparation Course – Engosoft – Saad Merie

4. Project Integration 4.4 Monitor and Control Project Work Management Inputs .1 Project management plan

4.4

Tools & Techniques

Outputs

..1 Expert judgment

.1 Change requests

.2 Analytical techniques

.2 Work performance reports

.3 Project management information system

.3 Project management plan updates

.4 Meetings

.4 Project documents updates

.2 Schedule forecasts .3 Cost forecasts .4 Validated changes .5 Work performance information .6 Enterprise environmental factors .7 Organizational process assets

PMP Preparation Course – Engosoft – Saad Merie

4. Project Integration 4.4 Monitor and Control Project Work Management

4.4.1 Monitor and Control Project Work: Inputs 4.4.1.2 Schedule Forecasts

Comes from Control Schedule Process 4.4.1.3 Cost Forecasts

Comes from Control Costs Process

4.4

PMP Preparation Course – Engosoft – Saad Merie

4. Project Integration 4.4 Monitor and Control Project Work Management

4.4

4.4.1 Monitor and Control Project Work: Inputs 4.4.1.4 Validated Changes

• Approve • 4.5 Perform Integrated Change Control

CR

• Implement • 4.3 Direct and Approved CR Manage Project Work

• Follow up • 4.4 Monitor and Validated CR Control Project Work

PMP Preparation Course – Engosoft – Saad Merie 4.4

4. Project Integration 4.4 Monitor and Control Project Work Management

4.4.1 Monitor and Control Project Work: Inputs 4.4.1.5 Work Performance Information

Performance Data From 4.3

Performance Information

Performance Reports

PMP Preparation Course – Engosoft – Saad Merie 4.4

4. Project Integration 4.4 Monitor and Control Project Work Management

4.4.2 Monitor and Control Project Work: tools and Techniques 4.4.2.2 Analytical Techniques

Regression Analysis

Grouping Methods

Casual Analysis

Root Cause Analysis

Failure Mode and Efect Analysis FMEA

Fault Tree Analysis FTA

Reserve Analysis

Trend Analysis

Earned Value Management

Variance Analysis

PMP Preparation Course – Engosoft – Saad Merie

4. Project Integration 4.4 Monitor and Control Project Work Management

4.4

4.4.3 Monitor and Control Project Work: Outputs 4.4.3.1 Change Requests

Comparing Performance Results with Plan may require CR 4.4.3.2 Work Performance Reports

• Reports is the way to show information in useful interface to make it easy for decision makers, or to highlight problems. • It is part of Project Documents • Contain: Project Status, Memos, Reasons of Delay, Notes, Recommendations, Updates.

PMP Preparation Course – Engosoft – Saad Merie

4. Project Integration the process of reviewing all change requests; Management 4.5 Perform Integrated Change Control

4.5

approving changes and managing changes to deliverables, organizational process assets, project documents, and the project management plan; and communicating their disposition.

The key benefit of this process is that it allows for documented changes within the project to be considered in an integrated fashion while reducing project risk, which often arises from changes made without consideration to the overall project objectives or plans.

PMP Preparation Course – Engosoft – Saad Merie

4. Project Integration • It is Project Manager Responsibility Entirely Management 4.5 Perform Integrated Change Control

4.5

• It started from first inspection in the project till close • CRs may be requested by a stakeholder • All CRs should be documented officially • Estimate the impact of CR on time and cost • Approval through Change Control Board (CCB) • CCB can be one person and can include the sponsor • Approved and Rejected CRs to be distributed • Approved CRs will be implemented through 4.3

PMP Preparation Course – Engosoft – Saad Merie

4. Project Integration Configuration Management Control Keep: Management 4.5 Perform Integrated Change Control

4.5

1. Deliverables Specs 2. Processes Specs

Change Management Control: 1. Manage Changes on Deliverables 2. Manage Changes on Documents 3. Manage Changes on Baselines and Plans

PMP Preparation Course – Engosoft – Saad Merie

4. Project Integration 4.5 Perform Integrated Change Control Management Inputs .1 Project management plan

Tools & Techniques .1 Expert judgment

.2 Work performance reports .3 Change requests

Outputs .1 Approved change requests .2 Change log

.2 Meetings .3 Project management plan updates

.4 Enterprise environmental factors .5 Organizational process assets

4.5

.3 Change control tools

.4 Project documents updates

PMP Preparation Course – Engosoft – Saad Merie

4. Project Integration 4.5 Perform Integrated Change Control Management

4.5

4.5.1 Perform Integrated Change Control: Inputs 4.5.1.3 Change Requests

• Approve • 4.5 Perform Integrated Change Control

CR

• Implement • 4.3 Direct and Approved CR Manage Project Work

• Follow up • 4.4 Monitor and Validated CR Control Project Work

Project Manager Main Priority is to resist unnecessary changes

PMP Preparation Course – Engosoft – Saad Merie

4. Project Integration 4.5 Perform Integrated Change Control Management

4.5

4.5.3 Perform Integrated Change Control: Outputs 4.5.3.2 Change Log

• Approved and Rejected CRs to be documented in Change Log • to be updated and distributed Regularly to entities and stakeholders • Change Log is part of Project Documents

PMP Preparation Course – Engosoft – Saad Merie 4.6

4. Project Integration Management the process of finalizing all activities across all 4.6 Close Project or Phase

of the Project Management Process Groups to formally complete the project or phase. The key benefit of this process is that it provides lessons learned, the formal ending of project work, and the release of organization resources to pursue new endeavors.

PMP Preparation Course – Engosoft – Saad Merie

4. Project Integration 4.6 Close Project or Phase Management Inputs

Tools & Techniques

.1 Project management plan

.1 Expert judgment

.2 Accepted deliverables

.2 Analytical techniques

.3 Organizational process assets

.3 Meetings

4.6

Outputs .1 Final product, service, or result transition

.2 Organizational process assets updates

PMP Preparation Course – Engosoft – Saad Merie 4.6

4. Project Integration 4.6 Close Project or Phase Management 4.6.1 Close Project or Phase: Inputs 4.6.1.2 Accepted Deliverables

Deliverabl e

Control Quality

Verified Deliverable

Validate Scope

Close

Accepted DeliverableProject

Phase

/

PMP Preparation Course – Engosoft – Saad Merie

4. Project Integration 4.6 Close Project or Phase Management 4.6.3 Close Project or Phase: Outputs

4.6.3.2 Organizational Process Assets Updates

OPA to be update: • Project file in Company’s Archive • Lessons learned If the owner has no more money to pay for the project Then We have to close it

4.6

PMP Preparation Course – Engosoft – Saad Merie

Exam Questions

Q

A team member approaches you with a change that could cut your schedule down by a month. What is the first thing you should do? A. Write up a change request and see if you can get it approved. B. Make the change; it’s going to save time and nobody will want the project to take longer than it should. C. Figure out the impact on the scope of the work and the cost before you write up the change request. D. Tell the team member that you’ve already communicated the deadline for the project, so you can’t make any changes now.

PMP Preparation Course – Engosoft – Saad Merie

Exam Questions

Q

Brandi is a project manager on a software project. About halfway through development, her team found that they had not estimated enough time for some of the technical work they needed to do. She requested that the new work be added to the scope statement and that the time to do the work be added to the schedule. The change control board approved her change. What’s her next step? A. Update the scope and schedule baselines to reflect the approved change. B. Start doing the work. C. Gather performance metrics on the team’s work so far. D. Perform Quality Assurance.

PMP Preparation Course – Engosoft – Saad Merie

Exam Questions

Q

You have just delivered a product to your client for acceptance when you get a call that some features they were expecting are missing. What’s the first thing you should do? A. Get your team together and reprimand them for building a product that doesn’t meet user expectations. B. Tell the client that the product passed all of your internal quality inspections and scope verification processes, so it must be fine. C. Tell the team to start building the missing features into the product right away. D. Call a meeting with the client to understand exactly what is unacceptable in the product and try to figure out what went wrong along the way.

PMP Preparation Course – Engosoft – Saad Merie

Exam Questions

Q

Which of the following BEST describes the main purpose of the project charter? A. It authorizes the project manager to work on the project. B. It identifies the sponsor and describes his or her role on the project. C. It contains a list of all activities to be performed. D. It describes the initial scope of the work.

PMP Preparation Course – Engosoft – Saad Merie

Exam Questions

Q

Which of the following is NOT a characteristic of the Project Management plan? A. Collection of subsidiary plans B. Formal, written communication C. A bar chart that shows the order of tasks and their resource assignments D. Must be approved by project sponsor

PMP Preparation Course – Engosoft – Saad Merie

Exam Questions

Q

You are a project manager for a software project. Your team buys a component for a web page, but they run into defects when they use it. Those defects slow your progress down considerably. Fixing the bugs in the component will double your development schedule, and building your own component will take even longer. You work with your team to evaluate the cost and impact of all of your options and recommend hiring developers at the company that built the component to help you address problems in it. That will cost more, but it will reduce your delay by a month. What is your next step? A. Fix the component. B. Write up the change request and take it to the change control board. C. Start Plan Procurements so you can get the contract ready for the vendor. D. Change the scope baseline to include your recommendation.

PMP Preparation Course – Engosoft – Saad Merie

Exam Questions

Q

The terms of union contracts are considered ______________ in your project plan. A. Assumptions B. Constraints C. Requirements D. Collective bargaining agreements

PMP Preparation Course – Engosoft – Saad Merie

5. Project Scope Management Scope Management

5

includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully. Project Management Process Groups

Knowledg e Areas

5. Project Scope

Initiatin g Planning Process Process Group Group 5.1 Plan Scope Management 5.2 Collect Requirements

Executing Process Group

Monitoring and Controlling Process Group 5.5 Validate Scope

Closing Process Group

PMP Preparation Course – Engosoft – Saad Merie

5. Project Scope Management

5

Product Scope

Project Scope

Specs and Properties of the required Product

It is the work required to get the product

Final Product Should be Compared with Product Requirements (5.2)

Final Result should be compared with Project Management Plan

PMP Preparation Course – Engosoft – Saad Merie

5. Project Scope Management

5

Controlled Scope Change

(Gold Plating) Uncontrolled (Scope Creep)

PMP Preparation Course – Engosoft – Saad Merie

5. Project Scope Management

5

5.1 Plan Scope Management

Inputs .1 Project management plan

Tools & Techniques

Outputs

.1 Expert judgment

.1 Scope management plan

.2 Meetings

.2 Requirements management plan

.2 Project charter .3 Enterprise environmental factors .4 Organizational process assets

PMP Preparation Course – Engosoft – Saad Merie

5. Project Scope Management

5

5.1 Plan Scope Management 5.1.3 Plan Scope Management: Outputs 5.1.3.1 Scope Management Plan

A plan to define how the Scope will be defined, Managed, Controlled and Checked. 5.1.3.2 Requirements Management Plan

A plan to define how the requirements will be analyzed, documented and managed.

PMP Preparation Course – Engosoft – Saad Merie

5. Project Scope Management The Process of collect, document and 5.2 Collect Requirement s

manage stakeholders requirements to achieve project objectives. Project Success Depend on how much stakeholder involve in collect and document requirements process

5

PMP Preparation Course – Engosoft – Saad Merie

5. Project Scope Management

5

5.2 Collect Requirements

Inputs .1 Scope management plan

Tools & Techniques .1 Interviews .2 Focus groups .3 Facilitated workshops

.2 Requirements management plan

Outputs .1 Requirements documentation

.4 Group creativity techniques .5 Group decision-making techniques

.3 Stakeholder management plan

.6 Questionnaires and surveys .7 Observations

.4 Project charter

.8 Prototypes .9 Benchmarking

.5 Stakeholder register

.10 Context diagrams .11 Document analysis

.2 Requirements traceability matrix

PMP Preparation Course – Engosoft – Saad Merie

5. Project Scope Management

5

5.2 Collect Requirements

Business Requirement s

Stakeholder Requirement s

Solution Requirement s

Transition Requirement s (Training)

Project Requirement s

Quality Requirement s

PMP Preparation Course – Engosoft – Saad Merie

5. Project Scope Management

5

5.2 Collect Requirements 5.2.2 Collect Requirements: Tools and Techniques 5.2.2.2 Focus Groups

Arranged meetings between the prequalified stakeholders and subject matter experts to get their ideas about the required product.

PMP Preparation Course – Engosoft – Saad Merie

5. Project Scope Management

5

5.2 Collect Requirements 5.2.2 Collect Requirements: Tools and Techniques 5.2.2.3 Facilitated Workshops



Workshop between The Key Stakeholders



It increases trust between Stakeholders



One example is Joint Application Design (JAD) in software field



Other example is Quality Function Development QFD in industries



QFD Start with collecting customer need which known as Voice of Customer VOC.



The requirements get arranged and prioritized.

PMP Preparation Course – Engosoft – Saad Merie

5. Project Scope Management

5

5.2 Collect Requirements 5.2.2 Collect Requirements: Tools and Techniques 5.2.2.4 Group Creativity Techniques



Brainstorming



Nominal Group Technique: same as brainstorming but with vote



Idea/Mind Mapping: put all the ideas in one map



Affinity Diagram: put similar ideas in groups



Multi criteria Decision Analysis: add several criteria to ideas

PMP Preparation Course – Engosoft – Saad Merie

5. Project Scope Management 5.2 Collect Requirements 5.2.2 Collect Requirements: Tools and Techniques 5.2.2.5 Group Decision Making Techniques

• Unanimity (All) • Majority (More than 50%) • Plurality (Most of, Less than 50%) • Dictatorship 5.2.2.6 Questionnaires and Surveys

When trying to get requirements from wild audience, or several places.

5

PMP Preparation Course – Engosoft – Saad Merie

5. Project Scope Management

5

5.2 Collect Requirements 5.2.2 Collect Requirements: Tools and Techniques 5.2.2.7 Observations

• Known as Job Shadowing • Check how experts do the work • Used when it is hard to get the requirements 5.2.2.8 Prototypes

• To get early feedback on requirements and Model of the product. • Type of Risk Avoidance

PMP Preparation Course – Engosoft – Saad Merie

5. Project Scope Management 5.2 Collect Requirements 5.2.2 Collect Requirements: Tools and Techniques 5.2.2.9 Benchmarking

• Compare current practice with Best Practice 5.2.2.10 Context Diagrams

• Chart that show the whole process 5.2.2.11 Document Analysis

• We can get requirements by analyzing some documents like business plans, market conditions, agreements, request for

5

PMP Preparation Course – Engosoft – Saad Merie

5. Project Scope Management 5.2 Collect Requirements 5.2.3 Collect Requirements: Outputs 5.2.3.1 Requirements Documentation

Requirements Have to be: 1. Unambiguous (measurable and testable) 2. Traceable 3. Complete 4. Consistent 5. Acceptable to key stakeholders

5

PMP Preparation Course – Engosoft – Saad Merie

5. Project Scope Management

5

5.2 Collect Requirements 5.2.3 Collect Requirements: Outputs 5.2.3.2 Requirements Traceability Matrix

• It link Requirements with Deliverables, and Reduce Gold plating • The benefit of it is to insure that each requirement add business value • It is the basis of Requirement Management

PMP Preparation Course – Engosoft – Saad Merie

5. Project Scope Management

5

the process of developing a detailed 5.3 Define Scope

description of the project and product. Not all requirements will be in the scope of works, here we define which requirements should be included.

PMP Preparation Course – Engosoft – Saad Merie

5. Project Scope Management

5

5.3 Define Scope

Inputs

Tools & Techniques

.1 Scope management plan

.1 Expert judgment

.2 Project charter

.2 Product analysis

.3 Requirements documentation

.3 Alternatives generation

.4 Organizational process assets

.4 Facilitated workshops

Outputs .1 Project scope statement

.2 Project documents updates

PMP Preparation Course – Engosoft – Saad Merie

5. Project Scope Management

5

5.3 Define Scope 5.3.2 Define Scope: Tools and Techniques 5.3.2.2 Product Analysis

• It is used when the project is created to make a product only • To get the product, there are several ways, analyzing the product help to define them 5.3.2.3 Alternatives Generation

• Analyze all possible methods to accomplish the project

PMP Preparation Course – Engosoft – Saad Merie

5. Project Scope Management

5

5.3 Define Scope 5.3.3 Define Scope: Outputs 5.3.3.1 Project Scope Statement

It is progressively elaborated, and contains: • Product Scope Description • Acceptance Criteria • Deliverables list • Project Exclusion (what is excluded) • Constraints • Assumptions (Assumed in Charter, Detailed in Define Scope)

PMP Preparation Course – Engosoft – Saad Merie

5. Project Scope Management

5

the process of subdividing project 5.4 Create WBS

deliverables and project work into smaller, more manageable components.

The project decomposed into work packages, each one represent the lowest level that work can be managed, estimate, and controlled.

PMP Preparation Course – Engosoft – Saad Merie

5. Project Scope Management

5

5.4 Create WBS

Inputs

Tools & Techniques

Outputs

.1 Decomposition

.1 Scope baseline

.2 Expert judgment

.2 Project documents updates

.1 Scope management plan .2 Project scope statement .3 Requirements documentation .4 Enterprise environmental factors .5 Organizational process assets

PMP Preparation Course – Engosoft – Saad Merie

5. Project Scope Management

5

5.4 Create WBS 5.4.2 Create WBS: Tools and Techniques 5.4.2.1 Decomposition

• Subdividing Scope intro smaller components • It is progressively elaborated, and this known as Rolling Wave Planning • Level of decomposition depend on the project complexity • Decomposition can be by Stage or Deliverable • Extra Decomposition make work hard to follow up

PMP Preparation Course – Engosoft – Saad Merie

5. Project Scope Management

5

5.4 Create WBS 5.4.3 Create WBS: Outputs 5.4.3.1 Scope Baseline

WBS Dictionary

WBS

Scope Statemen t

Scope

Baseline

PMP Preparation Course – Engosoft – Saad Merie

5. Project Scope Management 5.4 Create WBS 5.4.3 Create WBS: Outputs 5.4.3.1 Scope Baseline

WBS Dictionary includes details about each WBS like: • WBS Accounts Code • Work Description • Constraints and Assumptions • Entity in charge • Internal Activities • Cost, time, resources estimates

5

PMP Preparation Course – Engosoft – Saad Merie

5. Project Scope Management 5.5 Validate Scope

5

the process of formalizing acceptance of the completed project deliverables.

PMP Preparation Course – Engosoft – Saad Merie

5. Project Scope Management

5

5.5 Validate Scope

Inputs

Tools & Techniques

.1 Project management plan .2 Requirements documentation

.1 Accepted deliverables .1 Inspection .2 Change requests

.3 Requirements traceability matrix .4 Verified deliverables .5 Work performance data

Outputs

.2 Group decision-making techniques

.3 Work performance information .4 Project documents updates

PMP Preparation Course – Engosoft – Saad Merie 5

5. Project Scope Management 5.5 Validate Scope 5.5.3 Validate Scope: Outputs 5.5.3.1 Accepted Deliverables

Deliverabl e

Control Quality

Verified Deliverable

Validate Scope

Close

Accepted DeliverableProject

Phase

/

PMP Preparation Course – Engosoft – Saad Merie

5. Project Scope Management

5

the process of monitoring the status of 5.6 Control Scope

the project and product scope and managing changes to the scope baseline.

Scope Creep: the additional work added to scope without consideration for time or cost or resources.

PMP Preparation Course – Engosoft – Saad Merie

5. Project Scope Management

5

5.6 Control Scope

Inputs

Tools & Techniques

Outputs

.1 Project management plan

.1 Work performance information

.2 Requirements documentation

.2 Change requests

.3 Requirements traceability matrix

.1 Variance analysis

.3 Project management plan updates

.4 Work performance data

.4 Project documents updates

.5 Organizational process assets

.5 Organizational process assets updates

PMP Preparation Course – Engosoft – Saad Merie

Exam Questions

Q

Which of the following best describes decomposition?

A. Waiting for a task to expire so that it can break down into smaller tasks B. Taking a deliverable and breaking it down into the smaller work Packages so that it can be organized and planned C. Categorizing work packages D. Dividing work packages into deliverables that can be planned for

PMP Preparation Course – Engosoft – Saad Merie

Exam Questions

Q

Tom is the project manager of an accounting project. He has just finished defining the scope for the project and is creating the WBS. He goes to his organizational process asset library and finds a WBS from a past project to use as a jumping-off point. Which of the following describes the asset that Tom is using? A. Decomposition B. Delphi technique C. Brainstorming D. Templates

PMP Preparation Course – Engosoft – Saad Merie

Exam Questions

Q

Which of the following is the correct order of the Monitoring and Controlling processes for Scope Management? A. First Validate Scope, then Control Scope. B. First Control Scope, then Validate Scope. C. Both happen simultaneously. D. There is not enough information to decide.

PMP Preparation Course – Engosoft – Saad Merie

Exam Questions

Q

You are managing a software project. During a walkthrough of newly implemented functionality, your team shows you a new feature that they have added to help make the workflow in the product easier for your client. The client didn’t ask for the feature, but it does look like it will make the product easier to use. The team developed it on their own time because they wanted to make the client happy. You know this change would never have made it through change control. What is this an example of? A. Gold plating B. Scope creep C. Alternatives analysis D. Schedule variance

PMP Preparation Course – Engosoft – Saad Merie

Exam Questions You are developing the project scope statement for a new project. Which of the following is NOT part of creating a project scope statement?

A. Validate Scope B. Using the project charter C. Alternatives identification D. Obtaining plan approval

Q

PMP Preparation Course – Engosoft – Saad Merie

Exam Questions

Q

The scope baseline consists of: A. The Scope Management plan, the project scope statement, and the WBS B. The Scope Management plan, requirements documents, and the WBS C. The Scope Management plan, the WBS, and the WBS dictionary D. The project scope statement, the WBS, and the WBS dictionary

PMP Preparation Course – Engosoft – Saad Merie

Exam Questions

Q

You are the project manager on a construction project. As you’re planning out the work your team will do, you divide up all of the work into work packages and create a WBS that shows how they fit into categories. For each one of the work packages, you write down details such as initial estimates and information about what account it should be billed against. Where do you store all of that information? A. Scope Management plan B. WBS C. WBS dictionary D. Project scope statement

PMP Preparation Course – Engosoft – Saad Merie 6

6. Project Time Management Time Management

includes the processes required to manage the timely completion of the project. Project Management Process Groups

Knowledg e Areas

6. Project Time Management

Initiati ng Process Group

Planning Process Group 6.1 6.2 6.3 6.4 6.5 6.6

Plan Schedule Management Define Activities Sequence Activities Estimate Activity Resources Estimate Activity Durations Develop Schedule

Executin g Process Group

Monitoring and Controlling Process Group 6.7 Control Schedule

Closing Process Group

PMP Preparation Course – Engosoft – Saad Merie

6. Project Time Management

6

6.1 Plan Schedule Management

Inputs

Tools & Techniques

.1 Project management plan

.1 Expert judgment

.2 Project charter .3 Enterprise environmental factors .4 Organizational process assets

.2 Analytical techniques

.3 Meetings

Outputs

.1 Schedule management plan

PMP Preparation Course – Engosoft – Saad Merie

6. Project Time Management 6.1 Plan Schedule Management 6.1.3 Plan Schedule Management: Outputs 6.1.3.1 Schedule Management Plan

• Methodology and tool of developing project schedule • Accuracy level of estimating • Units (days, months?) and Calendars • Updating Schedule procedures • Control Thresholds • Performance measurement rules (like EVM) • Reports samples

6

PMP Preparation Course – Engosoft – Saad Merie

6. Project Time Management

6

6.2 Define Activities

Inputs

Tools & Techniques

Outputs

.1 Schedule management plan

.1 Decomposition

.1 Activity list

.2 Rolling wave planning

.2 Activity attributes

.3 Expert judgment

.3 Milestone list

.2 Scope baseline .3 Enterprise environmental factors .4 Organizational process assets

PMP Preparation Course – Engosoft – Saad Merie

6. Project Time Management

6

6.2 Define Activities 6.2.2 Define Activities: Tools and Techniques 6.2.2.2 Rolling Wave Planning

Iterative planning technique in which the work to be accomplished in the near term is planned in detail, while the work in the future is planned at a higher level. It is a form of progressive elaboration.

PMP Preparation Course – Engosoft – Saad Merie

6. Project Time Management 6.2 Define Activities 6.2.3 Define Activities: Outputs 6.2.3.2 Activity Attributes

Other attributes to be added to activity list like: •

Activity ID



WBS ID



Activity Start and End Dates



Successor and Predecessor



Resources requirements

6

PMP Preparation Course – Engosoft – Saad Merie

6. Project Time Management

6

6.3 Sequence Activities

Inputs .1 Schedule management plan .2 Activity list

Tools & Techniques .1 Precedence diagramming method (PDM)

Outputs .1 Project schedule network diagrams

.3 Activity attributes .4 Milestone list

.2 Dependency determination

.5 Project scope statement .6 Enterprise environmental factors .7 Organizational process assets

.2 Project documents updates .3 Leads and lags

PMP Preparation Course – Engosoft – Saad Merie

6. Project Time Management 6.3 Sequence Activities 6.3.2 Sequence Activities: Tools and Techniques 6.3.2.1 Precedence Diagramming Method (PDM)

One way to show it is AON (Activity on Node) The Activity on node, and the relationship on Arrow It has 4 types of relationships: FS,FF,SS,SF A

B

6

PMP Preparation Course – Engosoft – Saad Merie

6. Project Time Management

6

6.3 Sequence Activities 6.3.2 Sequence Activities: Tools and Techniques 6.3.2.2 Dependency Determination

Mandatory Dependencies Hard Logic

Discretionary Dependencies

External Dependencies

Internal Dependencies

Out of Project team control

Under project team control

Soft Logic

Contractually or legally required Inherent in the nature of work

Best Practice

Has Physical limits It is not Constraints

Documented

PMP Preparation Course – Engosoft – Saad Merie

6. Project Time Management 6.3 Sequence Activities 6.3.2 Sequence Activities: Tools and Techniques 6.3.2.3 Leads and Lags

6

PMP Preparation Course – Engosoft – Saad Merie

6. Project Time Management

6

6.3 Sequence Activities 6.3.3 Sequence Activities: Outputs 6.3.3.1 Project Schedule Network Diagrams

Workflow shows logical relationships between activities, and explanation for strange ones.

PMP Preparation Course – Engosoft – Saad Merie

6. Project Time Management

6

6.4 Estimate Activity Resources

Inputs .1 Schedule management plan

Tools & Techniques .1 Expert judgment

.1 Activity resource requirements

.2 Activity list .3 Activity attributes

Outputs

.2 Alternative analysis

.4 Resource calendars .3 Published estimating data

.2 Resource breakdown structure

.5 Risk register .6 Activity cost estimates

.4 Bottom-up estimating

.7 Enterprise environmental factors .8 Organizational process assets

.3 Project documents updates .5 Project management software

PMP Preparation Course – Engosoft – Saad Merie

6. Project Time Management 6.4 Estimate Activity Resources 6.4.2 Estimate Activity Resources: Tools and Techniques 6.4.2.2 Alternative Analysis

• Manual vs Automatic • Buy vs Build vs Rent

6

PMP Preparation Course – Engosoft – Saad Merie

6. Project Time Management 6.4 Estimate Activity Resources 6.4.3 Estimate Activity Resources: Outputs 6.4.3.1 Activity Resource Requirements

• Quantity and Type • Assumptions and Basis of Estimate • Availability

6

PMP Preparation Course – Engosoft – Saad Merie

6. Project Time Management

6

6.5 Estimate Activity Durations

Inputs .1 Schedule management plan

Tools & Techniques

Outputs

.1 Expert judgment

.2 Activity list .3 Activity attributes

.2 Analogous estimating

.1 Activity duration estimates

.4 Activity resource requirements .5 Resource calendars .6 Project scope statement

.3 Parametric estimating .4 Three-point estimating

.7 Risk register .8 Resource breakdown structure .9 Enterprise environmental factors .10 Organizational process assets

.5 Group decision-making techniques .6 Reserve analysis

.2 Project documents updates

PMP Preparation Course – Engosoft – Saad Merie

6. Project Time Management 6.5 Estimate Activity Durations 6.5.2 Estimate Activity Duration: Tools and Techniques 6.5.2.2 Analogous Estimating

• Use date from old project for same activity • Activity should be same quantity • Used when we don’t have a lot of information • Pros: Low cost and Time • Cons: Lack of Accuracy

6

PMP Preparation Course – Engosoft – Saad Merie

6. Project Time Management 6.5 Estimate Activity Durations 6.5.2 Estimate Activity Duration: Tools and Techniques 6.5.2.3 Parametric Estimating

• Depends on unit estimate • Like square meter cost in construction • More Accuracy

6

PMP Preparation Course – Engosoft – Saad Merie

6. Project Time Management

6

6.5 Estimate Activity Durations 6.5.2 Estimate Activity Duration: Tools and Techniques 6.5.2.4 Three-Point Estimating  

Depend on Pert Technique: tO: Optimistic Likely

tP: Pessimistic

tM: Most

PMP Preparation Course – Engosoft – Saad Merie

6. Project Time Management

6

6.5 Estimate Activity Durations 6.5.2 Estimate Activity Duration: Tools and Techniques 6.5.2.5 Group Decision-Making Techniques

• Brainstorming , Delphi Technique , Nominal group • Used to enhance estimates • People who participate in estimates tend to keep their words.

PMP Preparation Course – Engosoft – Saad Merie

6. Project Time Management

6

6.5 Estimate Activity Durations 6.5.2 Estimate Activity Duration: Tools and Techniques 6.5.2.6 Reserve Analysis

Contingency Reserves Known-unknowns

Management Reserves Unknown-Unknowns

Accepted Identified Risks which have response Strategies Can be % or fixed number Calculated by Monte-Carlo Simulation

Unseen work inside scope

Not part of Schedule Baseline

Visited while executing Documented

Part of Overall Project Duration Requirements

PMP Preparation Course – Engosoft – Saad Merie

6. Project Time Management 6.6 Develop Schedule

6

The process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model.

PMP Preparation Course – Engosoft – Saad Merie 6

6. Project Time Management 6.6 Develop Schedule

Inputs

Tools & Techniques

Outputs

.1 Schedule management plan

.1 Schedule network analysis

.1 Schedule baseline

.2 Activity list .3 Activity attributes .4 Project schedule network diagrams .5 Activity resource requirements .6 Resource calendars

.2 Critical path method .2 Project schedule .3 Critical chain method .4 Resource optimization techniques

.3 Schedule data

.5 Modeling techniques

.4 Project calendars

.7 Activity duration estimates .8 Project scope statement .9 Risk register .10 Project staf assignments .11 Resource breakdown structure

.6 Leads and lags .5 Project management plan updates .7 Schedule compression

.12 Enterprise environmental factors .13 Organizational process assets

.8 Scheduling tool

.6 Project documents updates

PMP Preparation Course – Engosoft – Saad Merie

6. Project Time Management

6

6.6 Develop Schedule 6.6.2 Develop Schedule: Tools and Techniques 6.6.2.2 Critical Path Method (CPM)

Float

A B

C D E Time

PMP Preparation Course – Engosoft – Saad Merie

6. Project Time Management

6

6.6 Develop Schedule 6.6.2 Develop Schedule: Tools and Techniques 6.6.2.2 Critical Path Method (CPM)

A

Free Float

Total Float

B

C

D Time

PMP Preparation Course – Engosoft – Saad Merie

6. Project Time Management

6

6.6 Develop Schedule 6.6.2 Develop Schedule: Tools and Techniques 6.6.2.2 Critical Path Method (CPM)



Critical path is the longest path represent minimum project duration



Calculate ES,LS,EF,LF for all activities using forward pass and backward pass



It doesn’t consider Resources Limitation



It is used to Calculate float for each path in the Scheduling model



Total float: amount of time the activity can be late without making project late



Free float: amount of time the activity can be late without making next ES late

PMP Preparation Course – Engosoft – Saad Merie

6. Project Time Management 6.6 Develop Schedule 6.6.2 Develop Schedule: Tools and Techniques 6.6.2.3 Critical Chain Method

Bufer Path 1

CP

Path 2

Bufer

6

PMP Preparation Course – Engosoft – Saad Merie

6. Project Time Management 6.6 Develop Schedule 6.6.2 Develop Schedule: Tools and Techniques 6.6.2.3 Critical Chain Method



We add Bufer for each path to consider Resources Limitation and Uncertainty



It developed from CPM



It consider resource levelling and optimization



Critical Chain is Critical Path constrained by resources



Instead of Float Management, we have Bufer Management



We add Feeding Bufer on non-critical paths

6

PMP Preparation Course – Engosoft – Saad Merie

6. Project Time Management

6

6.6 Develop Schedule 6.6.2 Develop Schedule: Tools and Techniques 6.6.2.4 Resource Optimization Techniques

Resource Levelling

Resource Smoothing

Adjust Actives Start and Finish to get balanced resource requirements

Adjust Activities Start and Finish in Free / Total Float

Used when we have same Resources for same period

Put fixed limit for resources

Done on Critical Path

Not on Critical path

It may extend the project

No project extension

PMP Preparation Course – Engosoft – Saad Merie

6. Project Time Management

6

6.6 Develop Schedule 6.6.2 Develop Schedule: Tools and Techniques 6.6.2.5 Modelling Techniques

What-if Scenario Analysis •

Study each scenario and its impact on the project



What would happen in Scenario X?



It help with contingency plans

Simulation •

Check project duration with diferent estimates (like three point estimates)



Most famous one is Monte Carlo Simulation



We choose several input values randomly and check possible project duration

PMP Preparation Course – Engosoft – Saad Merie

6. Project Time Management 6.6 Develop Schedule 6.6.2 Develop Schedule: Tools and Techniques 6.6.2.5 Modelling Techniques

6

PMP Preparation Course – Engosoft – Saad Merie

6. Project Time Management

6

6.6 Develop Schedule 6.6.2 Develop Schedule: Tools and Techniques 6.6.2.7 Schedule Compression

Crashing

Fast Tracking

Add Resources

Make Activities Overlapping

Add Overtime

Modify Leads and Lags

Applied on Critical Path

May cause re-work

May increase Risk and Cost

May increase Risk

PMP Preparation Course – Engosoft – Saad Merie

6. Project Time Management

6

6.6 Develop Schedule 6.6.3 Develop Schedule: Outputs 6.6.3.1 Schedule Baseline

It is the Approved version of Schedule Model, and used as basis of comparison 6.6.3.2 Project Schedule

In the beginning of project it is same as schedule baseline, then it get updates •

Bar Chart or Gantt Chart



Milestone Chart



AON

PMP Preparation Course – Engosoft – Saad Merie

6. Project Time Management 6.6 Develop Schedule 6.6.3 Develop Schedule: Outputs 6.6.3.3 Schedule Data



Resources Histogram



Alternative Schedules in Best case or Worst Case



Contingency Reserves



Cash-Flow (later)



Procurement Schedule



Submittals Schedule



Assumptions and Constraints



Attributes

6

PMP Preparation Course – Engosoft – Saad Merie

6. Project Time Management

6

6.7 Control Schedule

Inputs

Tools & Techniques

Outputs

.1 Project management plan

.1 Performance reviews

.1 Work performance information

.2 Project schedule

.2 Project management software

.2 Schedule forecasts

.3 Resource optimization techniques .3 Work performance data

.3 Change requests .4 Modeling techniques

.4 Project calendars

.4 Project management plan updates .5 Leads and lags

.5 Schedule data .6 Organizational process assets

.6 Schedule compression .7 Scheduling tool

.5 Project documents updates .6 Organizational process assets updates

PMP Preparation Course – Engosoft – Saad Merie

6. Project Time Management 6.7 Control Schedule 6.7.2 Control Schedule: Tools and Techniques 6.7.2.1 Performance Reviews

To compare and measure time performance like: •

Trend Analysis



Critical Path Method – Float Management



Critical Chain Method – Bufer Management



Earned Value Management

6

PMP Preparation Course – Engosoft – Saad Merie 7

7. Project Cost Management the process that establishes the policies, Cost Management

procedures, and documentation for planning, managing, expending, and controlling project costs. Project Management Process Groups

Knowledg e Areas

Initiati ng Process Group

Planning Process Group

Executing Process Group

Monitoring and Controlling Process Group

7.1 Plan Cost Management 7. Project Cost Management

7.2 Estimate Costs 7.3 Determine Budget

7.4 Control Costs

Closing Process Group

PMP Preparation Course – Engosoft – Saad Merie

7. Project Cost Management

7

7.1 Plan Cost Management

Inputs

Tools & Techniques

.1 Project management plan

.1 Expert judgment

.2 Project charter .3 Enterprise environmental factors .4 Organizational process assets

.2 Analytical techniques

.3 Meetings

Outputs

.1 Cost management plan

PMP Preparation Course – Engosoft – Saad Merie

7. Project Cost Management 7.1 Plan Cost Management 7.1.2 Plan Cost Management: Tools and Techniques 7.1.2.2 Analytical Techniques

Used to calculate funding and revenue for the project • payback period • return on investment • internal rate of return • discounted cash flow • net present value

7

PMP Preparation Course – Engosoft – Saad Merie

7. Project Cost Management 7.1 Plan Cost Management 7.1.3 Plan Cost Management: Outputs 7.1.3.1 Cost Management Plan

• Units and currency • Level of Precision (0.00) • Level of Accuracy (±10%) • Organizational procedures links • Control Thresholds • Performance measurements rules (like EVM)

7

PMP Preparation Course – Engosoft – Saad Merie 7

7. Project Cost Management 7.2 Estimate Costs

• Rough Order of Magnitude ROM -25% to +75% • Definitive Estimate: -5% to +10%

Can Cut Costs

Fixed • Mobilization • Set-up Costs

Variable • Material Costs

Direct • Salaries • Materials

Indirect • Taxes • Zakat

PMP Preparation Course – Engosoft – Saad Merie

7. Project Cost Management

7

7.2 Estimate Costs

Inputs

Tools & Techniques

.1 Cost management plan

.1 Expert judgment .2 Analogous estimating

.2 Human resource management plan

.3 Parametric estimating

.3 Scope baseline

.4 Bottom-up estimating

.4 Project schedule .5 Risk register .6 Enterprise environmental factors

.5 Three-point estimating .6 Reserve analysis

.1 Activity cost estimates

.2 Basis of estimates

.7 Cost of quality .8 Project management software .9 Vendor bid analysis

.7 Organizational process assets

Outputs

.10 Group decision-making techniques

.3 Project documents updates

PMP Preparation Course – Engosoft – Saad Merie

7. Project Cost Management 7.2 Estimate Costs 7.2.2 Estimate Costs: Tools and Techniques 7.2.2.2 Analogous Estimating

• Use date from old project for same activity • Activity should be same quantity • Used when we don’t have a lot of information • Pros: Low cost and Time • Cons: Lack of Accuracy

7

PMP Preparation Course – Engosoft – Saad Merie

7. Project Cost Management 7.2 Estimate Costs 7.2.2 Estimate Costs: Tools and Techniques 7.2.2.3 Parametric Estimating

• Depends on unit estimate • Like square meter cost in construction • More Accuracy

7

PMP Preparation Course – Engosoft – Saad Merie

7. Project Cost Management

7

7.2 Estimate Costs 7.2.2 Estimate Costs: Tools and Techniques 7.2.2.5 Three-Point Estimating  

Depend on Pert Technique: cO: Optimistic Likely

cP: Pessimistic

cM: Most

PMP Preparation Course – Engosoft – Saad Merie

7. Project Cost Management

7

7.2 Estimate Costs 7.2.2 Estimate Costs: Tools and Techniques 7.2.2.6 Reserve Analysis

Contingency Reserves

Management Reserves

Known-unknowns

Unknown-Unknowns

Accepted Identified Risks which have response Strategies

Unseen work inside scope

Can be % or fixed number Not part of Cost Baseline Included in Cost Baseline Visited while executing Documented

Part of Overall Project Cost Requirements When used it moves to Cost baseline through CR

PMP Preparation Course – Engosoft – Saad Merie

7. Project Cost Management 7.2 Estimate Costs 7.2.2 Estimate Costs: Tools and Techniques 7.2.2.7 Cost of Quality (COQ)

Cutting of this costs may increase Risks

7

PMP Preparation Course – Engosoft – Saad Merie

7. Project Cost Management 7.2 Estimate Costs 7.2.2 Estimate Costs: Tools and Techniques 7.2.2.9 Vendor Bid Analysis

By ofer the job or part of it to vendors

7.2.2.10 Group Decision-Making Techniques



Brainstorming



Nominal Group Techniques



Delphi Technique

7

PMP Preparation Course – Engosoft – Saad Merie

7. Project Cost Management 7.2 Estimate Costs 7.2.3 Estimate Costs: Outputs 7.2.3.1 Activity Cost Estimates



Direct and Indirect Costs



Inflation influence



Contingency Reserves 7.2.3.2 Basis of Estimates



How estimate done



Assumptions and Constraints



Level of Accuracy

7

PMP Preparation Course – Engosoft – Saad Merie 7

7. Project Cost Management 7.3 Determine Budget

Inputs .1 Cost management plan

Tools & Techniques .1 Cost aggregation

.2 Scope baseline .3 Activity cost estimates

Outputs .1 Cost baseline

.2 Reserve analysis

.4 Basis of estimates .5 Project schedule

.3 Expert judgment

.2 Project funding requirements

.6 Resource calendars .7 Risk register

.4 Historical relationships

.8 Agreements .9 Organizational process assets

.5 Funding limit reconciliation

.3 Project documents updates

PMP Preparation Course – Engosoft – Saad Merie

7. Project Cost Management 7.3 Determine Budget 7.3.2 Determine Budget: Tools and Techniques 7.3.2.4 Historical Relationships



Parametric Estimates



Analogous Estimates

7.3.2.5 Funding Limit Reconciliation



Reconcile Funding limits



Funding may efect budget on time



Funding may require re-scheduling

7

PMP Preparation Course – Engosoft – Saad Merie

7. Project Cost Management 7.3 Determine Budget 7.3.3 Determine budget: Outputs 7.3.3.1 Cost Baseline



It is the Approved version of (Time Phased Project Budget)



Used as basis of comparison

Project Budget Cost Baseline Management Reserves

Contingency Reserves

Work Package Cost Estimate Activity Contingency Reserves

Activity Cost Estimate

7

PMP Preparation Course – Engosoft – Saad Merie

7. Project Cost Management 7.3 Determine Budget 7.3.3 Determine budget: Outputs 7.3.3.2 Project Funding Requirements

7

PMP Preparation Course – Engosoft – Saad Merie

7. Project Cost Management 7.4 Control Costs

• Check influences on Cost Baseline • Manage Changes when happened • Monitor expenses and compare it to funds • Control cost performance and variance

7

PMP Preparation Course – Engosoft – Saad Merie 7

7. Project Cost Management 7.4 Control Costs

Inputs .1 Project management plan

.2 Project funding requirements

.3 Work performance data

.4 Organizational process assets

Tools & Techniques

Outputs

.1 Earned value management

.1 Work performance information

.2 Forecasting

.2 Cost forecasts

.3 To-complete performance index (TCPI)

.3 Change requests

.4 Performance reviews

.4 Project management plan updates

.5 Project management software

.5 Project documents updates

.6 Reserve analysis

.6 Organizational process assets updates

PMP Preparation Course – Engosoft – Saad Merie

7. Project Cost Management

7

7.4 Control Costs 7.4.2 Control Costs: Tools and Techniques 7.4.2.1 Earned Value Management Term

Definition

Term

Definition

EV

Earned Value

SV

Schedule Variance

AC

Actual Cost

CV

Cost Variance

PV

Planned Value

SPI

BAC = Budget

Budget At Completion

Schedule Performance Index

EAC

Estimate At Completion

CPI

Cost Performance Index BAC – EV BAC - AC

ETC

Estimate to Complete

Budget of Remaining Work

VAC

Variance at completion

Remaining Funds

PMP Preparation Course – Engosoft – Saad Merie

7. Project Cost Management

7

7.4 Control Costs 7.4.2 Control Costs: Tools and Techniques 7.4.2.1 Earned Value Management

SPI = CPI =

EV PV EV AC

SV = EV

PV

CV = EV

AC

PMP Preparation Course – Engosoft – Saad Merie

7. Project Cost Management

7

7.4 Control Costs 7.4.2 Control Costs: Tools and Techniques 7.4.2.1 Earned Value Management Over Budget

SPI

Ahead of Schedule

0

Under Budget Ahead of Schedule

1 CPI Over Budget

Under Budget

Behind Schedule

Behind Schedule 0

PMP Preparation Course – Engosoft – Saad Merie

7. Project Cost Management

7

7.4 Control Costs 7.4.2 Control Costs: Tools and Techniques 7.4.2.1 Earned Value Management Over Budget

SV

Ahead of Schedule

-

+ Under Budget Ahead of Schedule

+ CV

0 Over Budget

Under Budget

Behind Schedule

Behind Schedule -

PMP Preparation Course – Engosoft – Saad Merie

7. Project Cost Management 7.4 Control Costs 7.4.2 Control Costs: Tools and Techniques 7.4.2.1 Earned Value Management

Activity: Cutting the Grass Budget Cost: 1000 SAR Duration: 10 Days After 5 Days: •

We spent 600 SAR



We Finished 40% of the Field

What is SPI,CPI,CV,SV for this activity?

40 %

7

PMP Preparation Course – Engosoft – Saad Merie

7. Project Cost Management 7.4 Control Costs 7.4.2 Control Costs: Tools and Techniques 7.4.2.1 Earned Value Management

Actual Cost = 600 SAR Planned Value= 5 Days x 100 SAR= 500 SAR Earned Value= 40% x 1000 SAR= 400 SAR SPI = EV / PV = 400 / 500 = 0.8 CPI = EV / AC = 400 / 600 = 0.67 SV = EV – PV = 400 – 500 = -100 CV = EV – AC = 400 – 600 = -200

Cost= 600

40 % Value= 400

7

PMP Preparation Course – Engosoft – Saad Merie

7. Project Cost Management 7.4 Control Costs 7.4.2 Control Costs: Tools and Techniques 7.4.2.1 Earned Value Management

Over Budget Behind Schedule

7

PMP Preparation Course – Engosoft – Saad Merie

7. Project Cost Management 7.4 Control Costs 7.4.2 Control Costs: Tools and Techniques 7.4.2.1 Earned Value Management

7

PMP Preparation Course – Engosoft – Saad Merie 7

7. Project Cost Management 7.4 Control Costs 7.4.2 Control Costs: Tools and Techniques 7.4.2.2 Forecasting

1st Scenario: Continue as Planned

Budget of Remaining Works = BAC - EV

EAC

ETC = (BAC – EV) (/CPI=1) EAC = ETC + AC

=1 I P C =1

,

SPI

.67 0 = CPI

VAC = BAC - EAC

BAC

PMP Preparation Course – Engosoft – Saad Merie

7. Project Cost Management

7

7.4 Control Costs 7.4.2 Control Costs: Tools and Techniques 7.4.2.2 Forecasting

2nd Scenario: Consider Prev. CPI

Budget of Remaining Works = BAC - EV

EAC

ETC = (BAC – EV) / CPI EAC = ETC + AC

.67 0 = CPI 1

PI = S ,

BAC

.67 0 = CPI

VAC = BAC - EAC

PMP Preparation Course – Engosoft – Saad Merie 7

7. Project Cost Management 7.4 Control Costs 7.4.2 Control Costs: Tools and Techniques 7.4.2.2 Forecasting

3rd Scenario: Consider Prev. CPI and SPI

Budget of Remaining Works = BAC - EV

EAC

ETC = (BAC – EV) / CPI x SPI EAC = ETC + AC

I= P S , .67 0 =

CPI 0.8

67 . 0 = CPI

VAC = BAC - EAC

BAC

PMP Preparation Course – Engosoft – Saad Merie

7. Project Cost Management

7

7.4 Control Costs 7.4.2 Control Costs: Tools and Techniques 7.4.2.2 Forecasting

CPI = 1

)

CPI = Current

CPI and SPI = Current

PMP Preparation Course – Engosoft – Saad Merie

7. Project Cost Management

7

7.4 Control Costs 7.4.2 Control Costs: Tools and Techniques 7.4.2.2 Forecasting

ETC = BAC – EV = 600 EAC = ETC + AC = 1200 VAC = BAC – EAC = -200 ETC = (BAC – EV) / 0.67 = 900 EAC = ETC + AC = 1500 VAC = BAC – EAC = -500 ETC = (BAC – EV) / 0.67*0.8 = 1125 EAC = ETC + AC = 1725 VAC = BAC – EAC = -725

1

AC = 600

2

BAC = 1000

3

EV = 400

40 %

SPI = 0.8 CPI = 0.67

PMP Preparation Course – Engosoft – Saad Merie

7. Project Cost Management

7

7.4 Control Costs 7.4.2 Control Costs: Tools and Techniques 7.4.2.3 To-Complete Performance Index (TCPI) EAC = BAC EAC BAC

ETC = BAC – AC CPI

CPI T =

.67 0 = CPI

VAC = 0

PMP Preparation Course – Engosoft – Saad Merie

7. Project Cost Management 7.4 Control Costs 7.4.2 Control Costs: Tools and Techniques 7.4.2.3 To-Complete Performance Index (TCPI)  

TCPI: The required CPI to finish the project on the original budget It is the most index to tell us what is the performance of the project

7

PMP Preparation Course – Engosoft – Saad Merie

7. Project Cost Management

7

7.4 Control Costs 7.4.2 Control Costs: Tools and Techniques 7.4.2.3 To-Complete Performance Index (TCPI)  EAC = BAC = 1000

ETC = EAC - AC = 400 VAC = BAC – EAC = 0

TCPI

AC = 600 EV = 400

40 %

BAC = 1000 SPI = 0.8 CPI = 0.67

PMP Preparation Course – Engosoft – Saad Merie

7. Project Cost Management 7.4 Control Costs 7.4.2 Control Costs: Tools and Techniques 7.4.2.4 Performance Reviews



Variance Analysis •

SV



CV



VAC



The Accepted Variance get decrease with project progress



Trend Analysis



Earned Value Management

7

PMP Preparation Course – Engosoft – Saad Merie

Exam Questions

Q

You are the project manager for a railroad construction project. Your sponsor has asked you for a forecast for the cost of project completion. The project has a total budget of $80,000 and CPI of .95. The project has spent $25,000 of its budget so far. How much more money do you plan to spend on the project? A. $59,210 B. $80,000 C. $84,210 D. $109,210

PMP Preparation Course – Engosoft – Saad Merie

Exam Questions

Q

You are managing a project with a total budget of $450,000. According to the schedule, your team should have completed 45% of the work by now. But at the latest status meeting, the team reported that only 40% of the work has actually been completed. The team has spent $165,000 so far on the project. How would you BEST describe this project? A. The project is ahead of schedule and within its budget. B. The project is behind schedule and within its budget. C. The project is ahead of schedule and over its budget. D. The project is behind schedule and over its budget.

PMP Preparation Course – Engosoft – Saad Merie

Exam Questions

Q

You are managing a construction project that is currently being initiated. You met with the sponsors, and have started to work on identifying stakeholders. You’ve documented several key stakeholders and identified their needs. Before you can finish initiating the project, your company guidelines require that you make a rough order of magnitude estimate of both time and cost, so that the sponsor can allocate the final budget. What’s the range of a rough order of magnitude (ROM) estimate? A. –10% to +10% B. –25% to +75% C. –50% to +100% D. –100% to +200%

PMP Preparation Course – Engosoft – Saad Merie

Exam Questions

Q

You are managing a construction project to install new door frames in an office building. You planned on spending $12,500 on the project, but your costs are higher than expected, and now you’re afraid that your project is spending too much money. What number tells you the difference between the amount of money you planned on spending and what you’ve actually spent so far on the project? A. AC B. SV C. CV

PMP Preparation Course – Engosoft – Saad Merie

Exam Questions

Q

You’re managing a construction project to install several hundred air conditioner panels in a new office building. You have completed 350 panels out of a total of 900 planned panels, but according to your schedule you should have completed 400 of them. Your company’s contract states that you’ll be paid a fixed price of $75 per panel. You’ve spent $45,000 so far on the project. Which of the following BEST describes your situation? A. The CPI is .813, which means your project is currently over your budget. B. The CV is –$4,350, which means your project is currently over your budget. C. The TCPI is 1.833, which is the minumum CPI you need to stay within budget.