PMP Tutorial
Short Description
Download PMP Tutorial...
Description
PMP Tutorial This tutorial gives a very high level overview for the PMP certification exam. It does not cover sufficient information to clear the exam. You need to at least know the concepts mentioned in the tutorial to clear the exam. You may use it either as a starting point to get an initial overview, or you may use it as a last minute refresher to ensure you have covered everything. The tutorial is divided into the following topics PMP fundamentals - This chapter covers general information about project management that is not part of nine process areas. Integration - covers the knowledge area of Project Integration Management. Scope - covers the knowledge area of Project Scope Management. Time - covers the knowledge area of Project Time Management. Cost - covers the knowledge area of Project Cost Management. Risk - covers the knowledge area of Project Risk Management. Quality - covers the knowledge area of Project Quality Management. HR - covers the knowledge area of Project HR Management. Communications - covers the knowledge area of Project Communication Management. Procurement - covers the knowledge area of Project Procurement Management. Ethics - covers the PMP's code of ethics. The PMP exam format has the following distribution across the five process groups Project Initiation Project Planning Project Execution Project Project Monitoring Monitoring and and Control Control Project Closure Professio sional re responsibilit lity
11% 23% 27% 21% 9% 9%
Project Fundamentals Every facet of human life is a project. Every little step we take, from the moment we wake up up to the time we settle to sleep, is filled with mini projects. It's then not a stretch to assume that the way we handle actual projects (from work, school, etc.) is reflection of the way we handle the biggest project there is - our existence. That's why it's doubly important to come up with the perfect habit of proper planning and management of projects. This page covers general information about the discipline of project management. 1. 2. 3. 4.
A project project is a temporary temporary endeavor endeavor.. Projects Projects are unique unique and non-rep non-repetitiv etitive. e. Building Building a road is is an example example of a project. The process of building a road takes a finite amount of time, and produces a unique product. Operations on the other hand are repetitive. Delivering mail every day is an example of operation. The character characteristics istics associat associated ed with a project project are - unique unique purpose, purpose, tempor temporary ary in nature, nature, require require resources (often from various domains), should have a primary sponsor and/or customer, and involves uncertainty. Project Project management management is the the application application of of knowledge, knowledge, skills, skills, tools, tools, and technique techniques s to project project activities activities in order to meet project requirements A program program consists consists of a related related group group of projects. projects. Project Projects s are finite finite where as as programs programs are ongoing ongoing and and continuous. Programs may be repetitive and cyclic. In some cases Project Management is a subset of Program Management. The project manager may report to the program manager in such cases. A project may or may not be a part of a program, but a program will always have projects. A portfolio consists of multiple programs. As an example Building a house may be a project. Building a colony consisting of row of houses is a program. Building a set of colonies to develop a new city can be considered a portfolio.
5. 6.
A subproject is a subset of a project. Subprojects can be subcontracted. Technical or Functional Manager may be in charge of a subproject. Type of organization - This is an important concept to understand for the PMP exam. The type of organizations in decreasing order of Project Manager's authority are o Projectized o Strong Matrix o Weak Matrix o Functional Project Manager has maximum authority in a Projectized organization and least authority in a Functional organization. In Functional organizations staff is organized based upon their specialty, such as engineering or sales. In these organizations, functional managers are responsible for specialized departments like marketing. In Functional organization, the role of Project Manager is limited. In Projectized organization, PMs have more authority and independence. All the persons in the project team report to the Project Manager. Real situations are a mixture of functional and projectized organizations. These mixed situations are called matrix organizations. Strong matrix organizations have characteristics of projectized organizations. Weak matrix organizations have characteristics of functional organizations.
7. Leadership style varies from autocratic to democratic. Shared leadership involves team members taking
most of the decisions. It encourages team development. 8. Project Management consists of nine Knowledge Areas. These are o Project Integration Management o Project Scope Management o Project Cost Management o Project Time Management o Project Risk Management o Project Quality Management o Project HR Management o Project Communication Management o Project Procurement Management Each Knowledge area has further Processes. There are a total of 42 processes. Each process has inputs, outputs and "tools and techniques" (ITTO). The PMBOK primarily covers each of the processes and it's ITTO in detail. You need to understand the concepts related to each of the input, output and "tools and techniques". 9. Further the discipline of Project Management has five process groups. These are o Initiation o Planning o Execution o Control o Closure
Each process is part of one of these five project phases. It is important to know the process group for each of the 42 processes. 10. Project Sponsors are primarily involved in funding the project. Tasks performed by project sponsor include o Provides financial support o Accepts the project during scope verification o May provide key milestone and deliverables due dates o Does not sign the Project Charter. This is done by Senior Management. Tasks performed by the senior management include o o o o
Issues the project charter Helps organize the work into projects Helps identify risks Approves the final project plan
Stakeholders are all the individuals that are concerned with the project. Stakeholders have vested interest in the outcome of the project. They include project team members, customers, management, and other individuals who get impacted by the project. Stakeholders role includes o Distributed information during the project. o Notified of project plan changes o Are listed in the project team directory. o Become risk owners. 11. At the end of each project phase, reviews against a set of metrics are performed. If the project fails to meet these metrics, the project may not be allowed to continue. These phase end reviews are called Stage gates or Phase exits. 12. Project Life cycle: All projects have four parts in life cycle. These are 1. 2. 3. 4.
Starting the project Organizing and preparing Carrying out the project work Closing the project
2.
At the beginning of the project there is less cost and less demand for resources. Also there is a higher risk of failure at the beginning of the project. The risk reduces over the life of the project. The stakeholder influence is maximum at the beginning of the project and reduces over the life of the project. 3. Projects have multiple competing constraints. These are o o o o o o
Scope Quality Schedule Budget Resources Risk
Different stakeholders may give different priority to these constraints. As an example budget may be the most important constraint for the project sponsor. Scope may be imortant for a customer support engineer, and quality may be important for the testing team. A project team has to balance the demand of these constraints. 13. Progressive Elaboration means adding more details in an iterative fashion. Project Management Plan is
developed using progressive elaboration. 14. Project Management Office (PMO) is a group in an organization providing centralized project management services. The exact role of PMO may vary across organizations. PMO may provide services related to project management or may be directly responsible for project management. 15. Enterprise Environmental Factors refer to external factors in the company, that may influence the project. Enterprise Environmental Factors may include cultural factors, political climate, infrastructure and other external factors within the organization that may impact the project. Enterprise Environmental Factors are input to many planning processes.
Project Integration Management This chapter covers key concepts related to Project Integration Management. 1.
The knowledge area of Project Integration Management consists of the following seven processes Project Integration Processes Process
Project Phase
Key Deliverables
Develop Project Charter
Initiating
Project Charter
Develop Project Management Plan
Planning
Project Management Plan
Direct and Manage Project Execution Execution
Deliverables
Monitor and Control Project Work
Monitoring and Control Change Requests
Perform Integrated Change Control
Monitoring and Control Change Requests status updates
Close Project or Phase 2.
3.
Closure
Final product
A project charter o Formally authorizes the project. o Gives the objectives and business case o Identifies the Project Manager. o Generic enough not to change often. o Written by a Manager higher in authority than Project Manager. o Includes name, description, deliverables o A project does not start unless it has a Project charter. The Inputs, Tools and Techniques and Output of Develop Project Charter process are given below. Develop Project Charter process Inputs
Project Statement of work
Tools & Techniques
Expert judgment
Outputs
Project Charter
Business case Contract Enterprise environmental factors Organizational process assets 4. 5.
During project execution the project team focuses on completing the tasks assigned. The Senior Management protects the project from changes and loss of resources. The Project Manager integrates all the pieces into the project as a whole. The Inputs, Tools and Techniques, and Outputs of the Develop Project Management Plan process are given in the table below. Develop Project Management Plan process Inputs
Project charter
Tools & Techniques
Expert judgment
Outputs
Project Management Plan
Outputs from planning processes Enterprise environmental factors Organizational process assets 6.
At the end of each phase of a project, a lessons learned document must be prepared. The lessons learned document defines what was done right, wrong etc. It is required to be completed in order for the project to be completed. 7. Project Management Information System (PMIS) is a system that keeps track of status of all the project tasks. It is used to track the status of the project. The exam does not focus on any specific system (for example Microsoft Project ). 8. Project Management Plan is developed by Project Manager with inputs from the team, stakeholders and management. Project Management Plan development is iterative. A Project Management Plan is bought into, approved, realistic and formal. 9. A Project Management Plan includes o Project Charter o Budget o Schedule o Resources o Scope Statement o WBS o Responsibility charts/assignments o Management Plans 10. A Project Management Plan consolidates other management plans. These are: A. B. C. D. E. F. G. H. I. J.
Scope management plan Requirement management plan Schedule management plan Cost management plan Quality management plan Process improvement plan Human resource plan Communication management plan Risk management plan Procurement management plan
The Project Management Plan also includes project baselines. These are: K. Schedule baseline L. Cost performance baseline and M. Scope baseline 2. Project baseline refers to the original version of the project management plan. Once the project management plan is baselined, it may only be changed by raising a change request. 3. Progressive Elaboration involves the process of taking a project from concept to detailed design. 4. Kick-off meeting happens after the planning phase and before the project execution. It is typically used to communicate responsibilities of key stakeholders. 5. Direct and Manage Project Execution process includes performing the work defined in the PMP to achieve project goals. The Input, Tools and Techniques and Outputs of this process are given below. Direct and Manage Project Execution process Inputs
Tools & Techniques
Outputs
Project management plan
Expert judgment
Deliverables
Approved change requests
Project management information system
Work performance information
Enterprise Environmental factors
Change requests
Organizational process assets
Project management plan updates Project document updates
6.
Monitor and Control project work process includes tracking and reviewing the progress of the project. The Input, Tools and Techniques and Outputs of this process are given below. Monitor and Control project work process Inputs
Tools & Techniques
Project management plan
Expert judgment
Outputs
Change requests
Performance reports
Project management plan updates
Enterprise environmental factors
Project document updates
Organizational process assets 7.
The change requests that get generated are evaluated as part of the Perform Integrated Change Control process. The change requests on the project deliverables and project artifacts are managed in this process. The Input, Tools and Techniques and Outputs of this process are given below. Perform Integrated Change Control process Inputs
Tools & Techniques
Outputs
Project management plan
Expert judgment
Work performance information
Change control meetings Project management plan updates
Change requests
Change request status updates Project document updates
Enterprise environmental factors Organizational process assets 8. Change Control Board is formed to review change requests. It is used to approve or reject change
requests. After the project scope has been baselined, each requested change must go through a change control review process. 9. Project Manager needs to be proactive in looking for deviations from project plan and then take timely corrective action. After that the Project Manager needs to evaluate the effectiveness of corrective action, and measure performance of corrective action, and then determine the need for further corrective action. 10. When a change request is received, the following steps must be taken (in this order) -
2.
1. Evaluate (assess) the impact of change to the project 2. Create alternatives including cutting other tasks, crashing, fast-tracking etc. 3. Meet with management, sponsors etc. 4. Meet with the customer if necessary The Close Project or Phase is the process of formal completion of all project related activities. The Input, Tools and Techniques and Outputs of this process are given below. Close Project or Phase Inputs
Project management plan
Tools & Techniques
Expert judgment
Outputs
Final product, service or result transition
Accepted deliverables
Organizational process assets updates
Organizational process assets 3.
At the end of each phase of a project, a lessons learned document must be prepared. The lessons learned document defines what was done right, wrong etc. It is required to be completed in order for the project to be completed.
Project Scope Management This chapter covers key concepts related to Project Scope Management. 1.
The knowledge area of Project Scope Management consists of the following processes Scope Management Processes Process
Project Group
Key Deliverables
Collect Requirements planning
Requirements document
Define Scope
planning
project scope statement
Create WBS
planning
WBS, WBS dictionary
Verify Scope
Monitoring and Controlling Acceptance deliverables
Control Scope
Monitoring and Controlling Change Requests
2. The knowledge area of Scope Management includes the processes required to ensure that the project
includes all the work, and only all the work required to complete the project successfully. It is primarily concerned with controlling what is and what is not in the scope. 3. Project Portfolio Management is the process of project selection. It involves making a decision about which project an organization should execute. 4. There are two types of project selection methods. These are o Benefits Measurement o Constrained Optimization 5. Benefits Measurement project selection methods involve comparing the values of one project against another. There are the following type of Benefit Measurement project selection techniques o Murder Boards - This involves a committee asking tough questions from each project o Scoring Models - Different projects are given scores based on certain defined criteria. Project with higher score is selected. o Benefits Cost Ratio - This technique involves computing benefits to cost ratio (BCR) for a project. Project with higher BCR is selected. o Payback period - This technique involves considering how long it takes back to "pay back" the cost of the project. Inflation or interest earned in not considered in this technique. A project with lower pay back period is better. o Discounted Cash Flow - This technique takes into account the interest earned on the money. The Future Value (FV) of projects is compared. FV=PV(1+i)n PV is the present value of the project. A project with higher present value is better. o Internal Rate of Return (IRR) - A project that has higher IRR is better, as it is giving higher return on money. 6. Constrained Optimization Project selection methods are used for large projects. These are techniques based on mathematical models. The Constrained Optimization techniques are o Linear Programming o Non-Linear Programming o Integer Algorithm o Dynamic Programming o Multi-objective Programming 7. Expected monetary value of a project (or expected value) is equal to probability*impact . So if probability of a project's success is 20% and revenue earned if successful is $100000, then the net value of the project will be $20,000. A project with higher net value should be selected when performing project selection. 8. Management by Objective (MBO) is a management philosophy with three objectives o Establish unambiguous and realistic objectives o Periodically Evaluate if objectives are being met o Take corrective actions. MBO works only if management supports it.
9.
Collect Requirements process involves documenting stakeholders needs to meet project objectives. The Inputs, Tools and Techniques, and Outputs of Collect Requirements process are given below. Collect Requirements Process Inputs
Project charter
Tools & Techniques
Outputs
Interviews
Requirements documentation
Stakeholder register Focus groups
Requirements management plan
Facilitated workshops
Requirements traceability matrix
Group creativity techniques Questionaires and surveys Observations Prototypes Group decision-making techniques 10. The Define Scope process involves defining detailed description of the project and major deliverables. The Input, Tools and Techniques and Output of the Define Scope process are: Define Scope Process Inputs
Project charter
Tools & Techniques
Expert judgment
Outputs
Project scope statement
Requirements documentation Product analysis
Project document updates
Organizational process assets Alternative identification Facilitated workshops 11. Create WBS is the process of dividing the project deliverables into smaller components. The Inputs, Tools and Techniques and Outputs of Create WBS process are: Create WBS Process Inputs
Project Scope Statement
Tools & Techniques
Decomposition
Outputs
WBS
Requirements documentation
WBS dictionary
Organizational process assets
Scope baseline Project document updates
12. Work Breakdown Structure (WBS) is an important part of the exam. It is a graphical representation of the hierarchy of the project. The WBS template can be reused across projects. WBS forces the project team to think through all the levels of the project. If a task is not in the WBS, then it is not part of the project. 13. 8/80 rule for WBS - No task should be less than 8 hours or more than 80 hours. 14. WBS dictionary explains all the WBS components. Also WBS is input to most of the planning processes. Specifically WBS is input to the following processes o Cost Estimating o Cost Budgeting o Scope control o Activity Definition o Plan Purchases and Acquisitions 15. The Verify Scope is the process in which the project customer formally accepts the project deliverables. Scope Verification happens at the end of each phase. During the Verify Scope process customer gives feedback on work performed. While Verify Scope process focuses on customer acceptance, Perform Quality Control process focuses on correctness of work. 16. The table below gives inputs, Tools & Techniques, and Outputs of the Verify Scope process. Verify Scope Process Inputs
Project management plan
Tools & Techniques
Inspection
Outputs
Accepted Deliverables
Requirements documentation
Change requests
Requirements traceability matrix
Project document updates
Validated deliverables 17. Control Scope process involves monitoring the status of project and managing scope changes. The Inputs, Tools and Techniques and Outputs of Control Scope process are: Control Scope Process Inputs
Tools & Techniques
Outputs
Project management plan
Variance analysis
Work performance measurements
Requirements documentation
Change requests
Requirements traceability matrix
Project management plan updates
Organizational process assets
Organizational process assets updates
Work performance information
Project document updates
Project Time Management This chapter covers key concepts related to Project Time Management. 1.
The knowledge area of Project Time Management consists of the following processes Time Management Processes Process
2.
Project Phase
Key Deliverables
Define Activities
Planning
Activity List, Milestone list
Sequence Activities
Planning
Project Schedule network diagrams
Estimate Activity Resources Planning
Activity resource requirements, Resource breakdown structure
Estimate Activity Durations
Planning
Activity duration estimates
Develop Schedule
Planning
Project Schedule
Control Schedule
Monitoring and Controlling
Work Performance measurements, Change Requests
class="basic" The Define Activities process has the following Inputs, Tools and Techniques and Outputs Define Activities Process Inputs
Tools and Techniques
Scope baseline
Decomposition
Outputs
Activity list
Enterprise environmental factors Rolling wave planning
Activity attributes
Organizational process assets
Milestone list
Templates Expert judgment
3.
The Sequence Activities process has the following Inputs, Tools and Techniques and Outputs Sequence Activities Process Inputs
Tools and Techniques
Outputs
Project scope statement
Precedence diagram method (PDM) or AON
Project schedule network diagrams
Activity List
Applying leads and lags
Project document updates
Activity attributes
Schedule Network Templates
Milestone list
Dependency determination
Organizational process assets 4.
The Estimate Activity Resources process has the following Inputs, Tools and Techniques and Outputs Estimate Activity Resources Process Inputs
Tools and Techniques
Outputs
Activity List
Expert judgment
Activity resource requirements
Activity attributes
Alternative analysis
Resource breakdown structure
Resource calendars
Published estimating data
Project document updates
Enterprise environmental factors Bottom-up estimating Organizational process assets 5.
Project Management software
The Estimate Activity Durations process has the following Inputs, Tools and Techniques and Outputs Estimate Activity Durations Process Inputs
Tools and Techniques
Outputs
Activity list
Expert judgment
Activity duration estimates
Activity attributes
Analogous estimating
Project document updates
Activity resource requirements
Parametric estimating
Resource calendars
Three-point estimates
Project scope statement
Reserve analysis
Enterprise environmental factors Organizational process assets 6.
The Develop Schedule process has the following Inputs, Tools and Techniques, and OutputsDevelop Schedule Process Inputs
Tools and Techniques
Outputs
Organizational process assets
Schedule network analysis Project Schedule
Project scope statement
Critical path method
Schedule baseline
Activity List
Schedule Compression
Schedule data
Activity attributes
What-if scenario analysis
Project document updates
Project Schedule Network diagram Resource levelling Activity Resource requirements
Critical chain method
Resource Calendars
Scheduling tool
Activity duration estimates
Applying calendars
Project Management Plan Risk Register
Adjusting Leads and Lags
Enterprise environmental factors 7.
The Control Schedule process has the following Inputs, Tools and Techniques and Outputs Control Schedule Process Inputs
Tools and Techniques
Outputs
Project management plan
Performance reviews
Work performance measurements
Project schedule
Variance analysis
Organizational process assets updates
Work performance information Project management software Change requests Organizational process assets Resource leveling What-if scenario analysis
Project management plan updates Project document updates
Adjusting leads and lags Schedule compression Scheduling tool 8.
Bar charts (or Gantt charts) are used to display tasks and their dates in a graphical fashion. They are used to display information of the type task 1 is scheduled from date A to date B. Typically the date range is displayed in the X-axis and the tasks on the Y-axis. Bar charts do not show task dependencies. They are generally used to track progress and show to the team. 9. Milestone charts are similar to bar charts but display only major events. They display major milestones (for example bridge design completed). They are used to report status to Management. 10. Network diagrams are used to display activities and their dependencies. Network diagrams can be used to perform critical path analysis. Network diagrams can also be used to perform crashing and fast tracking of the project. There are two type of network diagrams o Activities on Node (or Precedence) o Activities on Arrow (or AOA) Precedence is most commonly used. AON and AOA cannot have loops or conditional relationships. 11. An activity in a network diagram is displayed as shown below. Activity name class="basic"Activity Number Estimate 12. As an example Documentation 2
5 days
13. In the above example Documentation is activity number 2 and is estimated to last 5 days. 14. Precedence (or Activity on Node) diagrams can be used to display four type of relationship between activities. These are
o o o o
Finish-To-Start Start-To-Start Start-To-Finish Finish-To-Finish
Finish-to-start relationship means the dependent activity cannot start until the first activity is finished. This is the most common way to represent relationships between activities. 15. Activity on Array (AOA) network diagrams have the following characteristics. o AOA only uses Finish-To-Start relationship between tasks. o PERT and CPM can only be used with AOA. o Dummy events are shown with dotted lines. They do not take any time. They show dependencies between tasks. 16. Longest path through the network diagram is called the critical path. The activities on the critical paths are called critical activities. 17. Lags are inserted waiting times in between tasks. For example Task B cannot start until three days after task A completes. 18. Slack or Float is the amount of time a task can be delayed without delaying the project. Tasks on the critical path have zero float. 19. Critical Path Method (CPM) has the following characteristics. o It uses one time estimate per activity o It can be drawn only using AOA diagrams o It can have dummy events 20. Program Evaluation and Review Technique (PERT) has the following characteristics. o It uses three estimates per activity - optimistic, pessimistic and most likely o It can be drawn only using AOA diagrams o It can have dummy events 21. PERT utilizes more information than CPM as it considers the "Pessimistic" and "Optimistic" values in addition to the "Most Likely" value in its calculations. The following are formulae used by PERT Mean = (P + 4M + O)/6 Standard Deviation = (P-O)/6 Variance = ((P-O)/6) 2 Here P is the pessimistic estimate, O is the optimistic estimate and M is the most likely estimate. 22. GERT is another type of network diagram. It can support looping. 23. If a project has more than one critical paths then the risk to the project increases. 24. Resource levelling refers to keeping the resources same across the duration of the project.
Project Cost Management This chapter covers key concepts related to Project Cost Management. 1.
The knowledge area of Project Cost Management consists of the following processes Project Cost Processes Process
Estimate Costs
Project Phase
Planning
Determine Budget Planning Control Costs 2. 3.
Key Deliverables
Activity Cost Estimates,Basis of estimates Cost performance baseline
Monitoring and Controlling Work performance measurements
Alternative identification process identifies other solutions to an identified problem. Value Analysis approach is used to find more affordable, less costly methods for accomplishing the same task. 4. The Estimate Costs process takes the following inputs o Scope baseline o Project schedule o Human resource plan o Risk register o Enterprise environmental factors o Organizational process assets 5. Depreciation is technique used to compute the estimated value of any object after few years. There are three type of depreciation techniques. These are o Straight line depreciation The same amount is deprecated (reduced) from the cost each year.
Double-declining balance - In the first year there is a higher deduction in the value - twice the amount of straight line. Each year after that the deduction is 40% less than the previous year. o Sum of year depreciation - Lets say the life of an object is five years. The total of one to five is fifteen. In first year we deduce 5/15 from the cost, in second year we deduce 4/15, and so on. Analogous Estimating is an estimating technique with the following characteristics o Estimates are based on past projects (historical information) o It is less accurate when compared to bottom-up estimation o It is a top-down approach o It takes less time when compared to bottom-up estimation o It is a form of an expert judgment
o
6.
7. In Parametric Modeling Estimation, you use a mathematical model to make an estimate. It is of two
types. o o
Regression Analysis is a mathematical model based upon historical information. Learning Curve model is based upon the principal that the cost per unit decreases as more work gets completed. 8. Bottom up estimation is same as WBS estimation. It involves estimating each work item and adding the estimates to get the total project estimate. 9. You can expect five to ten questions related to Earned Value Management. These are generally pretty simple once you have good understanding of the concepts, and remember the formulae. These formulae are explained below. 10. Planned Value (PV) refers to what the project should be worth at this point in the schedule. It is also referred as BCWS (Budgeted Cost of Work Scheduled). 11. Earned Value (EV) is the physical work completed to date and the authorized budget for that. It is also referred as BCWP (Budgeted Cost of Work Performed). 12. Actual Cost (AC) is the actual amount of money spent so far. It is also referred as ACWP (Actual Cost of Work Performed). 13. Estimate At Completion (EAC) refers to the estimated total cost of the project at completion. 14. CPI refers to Cost Performance Index. It is defined as CPI = EV/AC If CPI is less than 1, this means that the project is over budget. 15. BAC refers to Budget at Completion. It is related to EAC. EAC = BAC/CPI 16. ETC refers to Estimate to Completion. It is defined as ETC = EAC - AC 17. CV refers to Cost Variance. It is defined as CV = EV - AC 18. SV refers to Schedule Variance. It is defined as SV = EV - PV
Negative cost or schedule variance means that project is behind in cost or schedule. 19. SPI refers to Schedule Performance Index. It is defined as SPI = EV/PV 20. VAC refers to Variance At Completion. It is defined as VAC = BAC - EAC 21. The process of Cost budgeting defines time phased cost estimates for the project. For example, in the first month the project will require $10,000. Cost estimating involves defining cost estimates for tasks. Cost budgeting defines cost estimates across time. 22. The tools and techniques used for Estimate Costs are o Expert judgment o Analogous estimating o Parametric estimating o Bottom-up estimating o Three-point estimates o Reserve analysis o Cost of quality o Project Management estimating software o Vendor bid analysis 23. Cost baseline refers to what is expected to be spent on the project. It is usually an S-curve. That is the expenditure is less in the beginning, and the end. The expenditure is maximum during the middle of the project. 24. The after project costs are called life cycle costs.
Project Quality Management This chapter covers key concepts related to Project Quality Management. 1.
The knowledge area of Project Quality Management consists of the following processes Quality Management Processes Process
Plan Quality
Project Phase
Quality Management Plan, Quality Metrics
Planning
Perform Quality Assurance Execution Perform Quality Control
Key Deliverables
Change Requests
Monitoring and Controlling Quality control measurements
2. The process of Plan Quality includes defining quality requirements of the project and documenting how
the project will ensure compliance. The ITTO of Plan Quality process are given below. Plan Quality Process Inputs
Tools and Techniques
Outputs
Scope baseline
Cost-benefit analysis
Quality management plan
Stakeholder register
Cost of quality
Quality metrics
Cost performance baseline
Control charts
Quality checklists
Schedule baseline
Benchmarking
Process improvement plan
Risk register
Design of experiments
Project document updates
Enterprise environmental factors Stastical sampling Organizational process assets
Flowcharting Proprietary quality management methodology Additional quality planning tools
3.
Grade refers to category or rank given to entities having same functional use but different technical characteristics. As an example, for different grades of hotels, the customers expectations are different. Poor grade may be acceptable, but poor quality is not. 4. The aim of quality is to ensure "Conformance to requirements" and "fitness for use". 5. Quality Policy defines the company goals and how to adhere to them. This acts as an input to Quality Planning for a project. Quality Policy is part of Organizational Process assets. 6. Deming suggested a process of Plan-Do-Check-Act to improve quality. According to Deming, each process should go through these steps to improve the quality. 7. Kaizen Theory - Apply continuous small improvements to reduce costs and ensure consistency. 8. Marginal Analysis - You compare the cost of incremental improvements against the increase in revenue made from quality improvements. Optimal quality is reached when cost of improvements equals the costs to achieve quality. 9. The value of sigma of Normal Distribution are given below. These are important for the exam. Normal Distribution Sigma values Sigma
Percentage covered
One sigma
68.26%
Two sigma
95.46%
Three sigma 99.73% Six sigma
99.99%
10. Based on the above table, we can see that in six sigma one out of 10,000 items can have defects. In three sigma, twenty seven out of 10,000 items can have defects. 11. Giving extras i.e. doing more than the project scope is called gold-plating. PMI does not recommend gold-plating. 12. Quality must be planned in and not inspected in. Prevention is more important than inspection. 13. Quality Assurance is done during execution of the project. It includes o Process of evaluating overall performance on a regular basis o Re-evaluating quality standards o Quality audits - structured review of quality activities that identify lessons learned. These lessons learned are used for process improvement.
Perform Quality Assurance involves reviewing the quality requirements and auditing the results from quality control measurements. Perform Quality Assurance uses data created during Perform Quality Control.
ITTO of Perform Quality Assurance Inputs
Tools and Techniques
Outputs
Project management plan
Plan Quality and Perform Quality Control tools and techniques
Organizational process updates
Quality metrics
Quality audits
Change requests
Work performance information
Process analysis
Project management plan updates
Quality control measurements
Project document updates
14. Perform Quality Control focuses on correctness of work. It includes inspections. The inputs, tools and techniques and outputs (ITTO) used for Perform Quality Control process are ITTO of Perform Quality Control Inputs
Tools and Techniques
Outputs
Project management plan
Cause and effect diagram
Quality control measurements
Quality metrics
Control charts
Validated changes
Quality checklists
Flowcharting
Validated deliverables
Work performance measurements
Histogram
Organizational process assets updates
Approved change requests
Pareto chart
Change requests
Deliverables
Run chart
Project management plan updates
Organizational process assets
Scatter diagram
Project document updates
Statistical Sampling Inspection Approved change requests review 15. In Just-In-Time (JIT) Quality, the amount of inventory is zero. The inputs are made available, just when
they are required. This reduces the storage cost. 16. Rule of seven : In control charts, if there are seven points on one side of mean, then an assignable cause must be found. 17. The process of Analogous Estimation involves looking at the history of past projects, and use them to make estimates.
Project HR Management This chapter covers key concepts related to Project HR Management. 1.
The knowledge area of Project HR Management consists of the following processes HR Management Processes Process
Project Phase
Key Deliverables
Develop Human Resource Plan Planning
Human Resource Plan
Acquire Project Team
Execution
Project Staff assignments
Develop Project Team
Execution
Team performance assessments
Manage Project Team
Execution
Change requests
2.
Develop Human Resource Plan process involves identifying and documenting project roles and responsibilities. The table below gives the inputs, tools and techniques, and Outputs for the Develop Human Resource Plan process Develop Human Resource Plan Process Inputs
3.
Tools and Techniques
Outputs
Enterprise environmental factors
Organization charts and Human resource plan position descriptions
Organizational process assets
Organizational Theory
Activity resource requirements
Networking
Acquire project team process involves identifying and obtaining the team necessary to execute the project. The table below gives the inputs, tools and techniques, and Outputs for the Acquire project team process Acquire project team process Inputs
Tools and Techniques
Project management plan
Pre-assignment
Outputs
Project staff assignments
Enterprise environmental factors Negotiation
Resource calendars
Organizational process assets
Project management plan updates
Acquisition Virtual teams
4.
Develop project team process involves improving the competencies of the team members and improving teamwork between the team. The table below gives the inputs, tools and techniques, and Outputs for the Develop project team process Develop project team process Inputs
Project staff assignment
Tools and Techniques
Interpersonal skills
Project management plan Training Resource calendars
Outputs
Team performance assessments Enterprise environmental factors updates
Team-building activities Ground rules Co-location Recognition and rewards
5. Responsibility Assignment Matrix (RAM) defines who does what. The Staffing Management Plan
6.
7.
defines when will people get added and removed from the project. A Project Manager may yield authority over the project team in one of the following ways o Referent - project team knows the PM o Formal Power - Power due to Project Managers position o Technical Power - Project Manager has strong technical skills in the projects domain. o Coercive Power - The project team is afraid of the power the Project Manager holds. Conflicts in the team are caused due to the following reasons in decreasing order of occurrences. o Schedules o Project Priorities o Resources o Technical Opinions So the most common cause of conflicts in projects are issues related to schedules.
8.
Conflicts are best resolved by those in the team. 9. There are standard conflict resolution techniques available to resolve conflicts. These are (from best to worst) o Problem Solving or Confrontation (look at the facts, analyze them and find a solution). This is an example of win-win situation. o Compromising (Find the middle route). This is an example of loose-loose situation. o Withdrawal or Avoidance o Smoothing (Emphasize the agreements) o Forcing (Do it my way). This is an example of win-loose situation. 10. The process of problem solving has these steps o Define the cause of the problem o Analyze the problem o Identify solution o Implement a decision
o Review the decision, and confirm that the problem is solved. 11. Manage project team process is the process of tracking team member performance and managing issues within the team. The table below gives the inputs, tools and techniques, and Outputs for the Manage project team process Manage project team process Inputs
Tools and Techniques
Outputs
Project staff assignments
Observation and conversation Enterprise environmental factors updates
Project management plan
Project performance appraisals Organizational process assets updates
Team performance assets
Conflict management
Change requests
Performance reports
Issue log
Project management plan updates
Organizational process assets Interpersonal skills 12. War room is a technique for team building. As part of this the project team meets in one room. It helps to
create a project identity. 13. Halo Effect is the assumption that because the person is good at a technology, he will be good as a project manager. 14. There are many organizational theories. Some of the main ones are - Expectancy Theory, McGregory Theory, Herzberg Theory, Maslow's Hierarchy of needs. 15. Expectancy Theory - People accept to be rewarded for their efforts. This is a motivation factor. People put in more efforts because they accept to be rewarded for their efforts. 16. McGregory Theory of X and Y - There are two type of employees. Employees of type X need to be always watched. They cannot be trusted and need to be micro managed. Employees of type Y, on the other hand, are self-motivated. They can work independently. 17. Herzberg Theory - Hygiene factors (salary, cleanliness etc.) if not present can destroy motivation. However good hygiene alone does not improve motivation. What motivates people is the work itself. The motivation factors for employees include responsibility, self-actualization, growth, recognition etc. 18. Maslow's Hierarchy of needs - there are various levels of needs for an employee. When a lower level is met, employee attempts to reach the next higher level. The maximum satisfaction is achieved when the employee reaches the highest level of satisfaction - self-fulfillment. These level of needs from the highest to lowest are o Self-fulfillment o Esteem o Social o Safety o Physiology
Project Communication Management This chapter covers key concepts related to Project Communication Management. 1.
The knowledge area of Project Communication Management consists of the following processes class="basic"Communication Management Processes Process
Process Group
Identify Stakeholders
Initiating
Stakeholders register
Plan Communications
Planning
Communication Management Plan
Distribute Information
Executing
Organization process assets updates
Manage Stakeholders Expectations Executing Report Performance 2. 3. 4. 5.
Key Deliverables
Change requests
Monitoring and Controlling Performance Reports
Communication Management Plan defines how and when the various stakeholders receive information, and communicate with each other. Memos, emails are examples of non-formal communication. The total number of communication channels between n stakeholders is n(n-1)/2. So if there are ten stakeholders in a project, there are 45 channels of communication. The Identify Stakeholders process involves identifying all persons and organizations that may impact the outcome of project. Project stakeholders may include customers, project team, project sponsor and other persons involved in the project. During stakeholder analysis the power and interest of the stakeholders is plotted with Interest on X-axis and Power on Y-axis. The Inputs, Tools and Techniques, and Output of Identify Stakeholders process is given below. Identify Stakeholders
Inputs
Tools & Techniques
Outputs
Project Charter
Stakeholder analysis Stakeholder register
Procrement documents
Expert judgment
Stakeholder management strategy
Enterprise environmental factors Organizational process assets 6.
Plan Communications process involves determining what kind of information should be shared with which project stakeholder. This is documented in the Communication management plan. Also documented is how and when the communication needs to be shared with stakeholders. The Inputs, Tools and Techniques, and Output of Plan Communications process is given below. Plan Communications Process Inputs
Tools & Techniques
Outputs
Stakeholder register
Communication requirements analysis
Communications management plan
Stakeholder management strategy
Communication technology
Project document updates
Enterprise environmental factors Communication models Organizational process assets 7.
Communication methods
Throughout the project duration, information is shared with stakeholders as planned. This sharing of information is part of the Distribute Information process. The Inputs, Tools and Techniques, and Output of Distribute Information process is given below. Distribute Information Inputs
Tools & Techniques
Project management plan
Communication methods
Performance reports
Information distribution tools
Outputs
Organizational process assets updates
Organizational process assets 8.
As part of the Manage Stakeholder Expectations process, the project manager works with the stakeholders, understands and addresses their needs and expectations. The Inputs, Tools and Techniques, and Output of Manage Stakeholder Expectations process is given below. Manage Stakeholder Expectations Process Inputs
Stakeholder register
Tools & Techniques
Outputs
Communication methods Organizational process assets updates
Stakeholder management strategy Interpersonal skills
Change requests
Project management plan
Project management plan updates
Management skills
Issue log
Project document updates
Change log Organizational process assets 9.
The Report Performance process involves sharing the project status reports and measurements with appropriate stakeholders. Report Performance Process Inputs
Tools & Techniques
Outputs
Project Management Plan
Variance analysis
Performance reports
Work performance information
Forecasting methods
Organizational process assets updates
Work performance measurements Communication methods Change requests Budget forecasts
Reporting systems
Organizational process assets
Project Risk Management This chapter covers key concepts related to Project Risk Management. 1.
The knowledge area of Project Risk Management consists of the following processes -
Risk Management Processes Process
2. 3.
Project Phase
Key Deliverables
Plan Risk Management
Planning
Risk Management Plan
Identify Risks
Planning
Risk register
Perform Qualitative Risk Analysis
Planning
Risk register updates
Perform Quantitative Risk Analysis Planning
Risk register updates
Plan Risk Responses
Planning
Risk related contract decisions
Monitor and Control Risks
Monitoring and Controlling Risk register updates
A project risk is a potential source of deviation from the project plan. Project risks can have a negative or positive impact on the project. Project risks that are negative are called threats. Project risks that are positive are called opportunities. Responses to threat include -o Reducing the probability of risk o Developing contingency plans o Passively accepting consequences. o Transferring risk Insurance is an example of transferring risk.
4. 5.
Non-critical risks should be documented. They should be revisited and reviewed regularly. Risks are identified in all phases. 6. Work-around refers to how to handle risks that have occurred but are not part of risk response plan. This happens in risk monitoring and control phase. 7. Delphi technique is most commonly used to obtain expert opinions on technical issues. It can be used to get inputs on Scope, Estimates or Risks. Some characteristics of the Delphi technique are o The experts identities are anonymous. They are not in the same room. o The PM tries to build a consensus among the experts.
Project Procurement Management This chapter covers key concepts related to Project Procurement Management. 1.
Procurement Management involves getting work done by people outside the project team. Project Procurement Management includes administering contracts and change control process to manage contracts or purchase orders. The knowledge area of Project Procurement Management consists of the following processes Procurement Management Processes Process
Project Phase
Key Deliverables
Plan Procurements
Planning
Procurement Management Plan
Conduct Procurements
Execution
Selected Sellers, Procurement contract award
Administer Procurements Monitoring and Controlling Change requests Close Procurements 2.
Closure
Closed procurements
The Plan Procurement process involves build versus buy decisions. The Inputs, Tools and Techniques, and Outputs of Plan Procurement process are listed in the table below. Plan Procurement process Inputs
Tools and Techniques
Outputs
Scope baseline
Make-or-buy analysis
Procurement management plan
Requirements documentation
Expert judgment
Procurement statements of work
Teaming agreements
Contract types
Make-or-buy decisions
Risk register
Procurement documents
Risk-related contract decisions
Source selection criteria
Activity resource requirements
Change requests
Project schedule Activity cost estimates Cost performance baseline
Enterprise environmental factors Organizational process assets 3. 4.
A contract is a formal agreement. It is a legal document biding to both seller and buyer. Changes to contract must be in writing and formally controlled. Most Governments back all contracts by providing a court system. The process of Conduct Procurement involves receiving seller responses, selecting a seller, and awarding a contract. During this process bids or proposals from sellers are evaluated, and one or more seller is selected to execute the work. Conduct Procurement process Inputs
Tools and Techniques
Outputs
Project Management Plan
Bidder conferences
Selected sellers
Procurement documents
Proposal evaluation techniques Procurement contract award
Source Selection criteria
Independent estimates
Resource calendars
Qualified seller list
Expert judgment
Change requests
Seller proposals
Advertising
Project management plan updates
Project documents
Internet search
Project document updates
Make-or-buy decisions
Procurement negotiations
Teaming agreements Organizational process assets 5. Sole Source refers to a market condition in which only one qualified seller exists in the market. Single Source refers to a market condition in which the company prefers to contract with only one seller. Oligopoly refers to a market condition where very few sellers exist, and the action of one seller will have
6. 7.
impact on other seller prizes. Bidder conferences are meetings between buyer and sellers before the bid is submitted. The conference is used by buyers to provide consistent information to all sellers. The process of Administer Procurement involves managing procurement relationships and ensuring the seller performance meets the procurement requirements. Administer Procurement process Inputs
Tools and Techniques
Outputs
Procurement documents
Contract change control system
Procurement documentation
Project management plan
Procurement performance reviews Organizational assets updates
Contract
Inspection and audits
Change requests
Performance reports
Performance reporting
Project management plan updates
Approved change requests
Payment systems
Work performance information Claims administration Records management system 8. 9.
10. 11. 12.
Contract can be used as a risk management tool, as in transferring risk. Centralized Contracting refers to a separate contracting office that handles contracts for all projects. In De-centralized Contracting a contract administrator is assigned for each project. Force majeure is a powerful and unexpected event, such as hurricane or other disaster. Privity is contractual information between customer and vendor. The process of Close Procurement involves completing each procurement. The process involves verifying that all planned work as per the contract has been completed. Close Procurement process Inputs
Tools and Techniques
Project management plan
Procurement audits
Procurement documentation Negotiated settlements
Outputs
Closed procurements Organizational process updates
Records management system
Code of Professional Ethics This chapter covers PMI's code of Professional Conduct. The PMP code of Professional Conduct is defined at http://www.pmi.org/PDF/AP_PMICodeofEthics.pdf
1. Culture Shock refers to the initial disorientation that a person first experiences when visiting a country
other than his own. 2. Ethnocentrism is a typical belief that one's culture is superior to the foreigner's culture. 3. PMP's Code of Professional Conduct is a document provided by PMI. It is a guide to Project Managers on how to conduct as a professional. 4. PMP aspirants need to provide accurate and truthful information through out the application process. Any violations can lead to disciplinary action. 5. If a project team member or the project manager has a conflict of interest, then it must be brought into notice of all the stake-holders, to prevent any appearance of improperiety. As an example of this consider a case where a Project Manager is evaluating some vendors. Lets assume the Project Manager has friendship with one of the vendors. In such a situation, the Project Manager should let all the stakeholders know, and offer herself to be excluded out of the evaluation process. 6. The confidentiality of any intellectual property information that a PMP professional works with, must be maintained. 7. Any information that a PMP provides to general public must be accurate and truthful. 8. A PMP must not accept any form of inappropriate gifts. Similarly a PMP must not offer inappropriate compensation for personal gains.
View more...
Comments