PMP REviwe.pdf
Short Description
Download PMP REviwe.pdf...
Description
What are the five (5) project management groups
Closing Processes
Controlling Processes
Executing Processes
Planning Processes
Initiating Processes
Name the six (6) processes within Project Procurement Management
Name the three (3) processes with Project Human Resource Management
Name the six (6) processes within Project Risk Management
Name the three (3) processes with Project Quality Management
Formalizing acceptance of the project or phase and bringing it to an orderly end.
Initiating processes, Planning processes, Executing processes, Controlling processes, Closing processes
Coordinating people and other resources to carry out the plan.
Ensuring that project objectives are met by monitoring and measuring progress regularly to identify variances from plan so that corrective action can be taken when necessary.
Authorizing the project or phase.
Defining and refining objectives and selecting the best of the alternative courses of action to attain the objectives that the project was undertaken to address.
Organizational Planning, Staff Acquisition, Team Development
Procurement Planning, Solicitation Planning, Solicitation, Source Selection, Contract Administration, Contract Closeout
Quality Planning, Quality Assurance, Quality Control
Risk Management Planning, Risk Identification, Qualitative Risk Analysis, Quantitative Risk Analysis, Risk Response Planning, Risk Monitoring and Control
Name the four (4) processes within Project Communications Management
Name the four (4) processes within Project Cost Management
Name the five (5) processes with Project Time Management
Name the five (5) processes with Project Scope Management
Name the three (3) processes within Project Integration Management
Work Package
Work Breakdown Structure, (WBS)
Workaround
Value Engineering, (VE)
Triggers
Resource Planning, Cost Estimating, Cost Budgeting, Cost Control
Communications Planning, Information Distribution, Performance Reporting, Administrative Closure
Initiation, Scope Planning, Scope Definition, Scope Verification, Scope Change Control
Activity Definition, Activity Sequencing, Activity Duration Estimating, Schedule Development, Schedule Control
A deliverable at the lowest level of the work breakdown structure, when that deliverable may be assigned to another project manager to plan and execute. This may be accomplished through the use of a subproject where the work package may be further decomposed into activities.
Project Plan Development, Project Plan Execution, Integrated Change Control
A response to a negative risk event. Distinguished from contingency plan in that a workaround is not planned in advance of the occurrence of the risk event.
A deliverable-oriented grouping of project elements that organizes and defines the total work scope of the project. Each descending level represents an increasingly detailed definition of the project work.
Triggers, sometimes called risk symptoms or warning signs, are indications that a risk has occurred or is about to occur. Triggers may be discovered in the risk identification process and watched in the risk monitoring and control process.
Value engineering is a creative approach used to optimize life-cycle costs, save time, increase profits, improve quality, expand market share, solve problems, and/or use resources more effectively.
Total Quality Management, (TQM)
Time-Scaled Network Diagram
Technical Performance Measurement
Team Development
Task
Target Start Date, (TS)
Target Finish Date, (TF)
Target Completion Date, (TC)
Successor Activity
Subproject
Any project network diagram drawn in such a way that the positioning and length of the activity represent its duration. Essentially, it is a bar chart that includes network logic.
A common approach to implementing a quality improvement program within an organization.
Developing individual and group competencies to enhance project performance.
Technical performance measurement compares technical accomplishments during project execution to the project plan’s schedule of technical achievement.
The date that work is planned (targeted) to start on an activity.
A generic term for work that is not included in the work breakdown structure, but potentially could be a further decomposition of work by the individuals responsible for that work. Also, lowest level of effort on a project.
An imposed date that constrains or otherwise modifies the network analysis.
The date that work is planned (targeted) to finish on an activity.
A smaller portion of the overall project.
1) In the arrow diagramming method, the activity that departs a node. 2) In the precedence diagramming method, the “to” activity.
Subnet
Statement of Work, (SOW)
Start Date
Stakeholder
Staff Acquisition
Source Selection
Solicitation Planning
Solicitation
Slack
Simulation
A narrative description of products or services to be supplied under contract.
A subdivision of a project network diagram, usually representing some form of subproject.
Individuals and organizations that are actively involved in the project, or whose interests may be positively or negatively affected as a result of project execution or project completion. They may also exert influence over the project and its results.
A point in time associated with an activity’s start, usually qualified by one of the following: actual, planned, estimated, scheduled, early, late, target, baseline, or current.
Choosing from among potential sellers.
Getting needed human resources assigned to and working on the project.
Obtaining quotations, bids, offers, or proposals as appropriate.
Documenting product requirements and identifying potential sources.
A simulation uses a project model that translates the uncertainties specified at a detailed level into their potential impact on objectives that are expressed at the level of the total project. Project simulations use computer models and estimates of risk at a detailed level, and are typically performed using the Monte Carlo technique.
Term used in arrow diagramming method for float.
Seller
Secondary Risk
Scope Verification
Scope Statement
Scope Planning
Scope Definition
Scope Change Control
Scope Change
Scope
Scheduled Start Date, (SS)
A risk that arises as a direct result of implementing a risk response.
The provider of goods or services to an organization.
The scope statement provides a documented basis for making future project decisions and for confirming or developing common understanding of project scope among the stakeholders. As the project progresses, the scope statement may need to be revised or refined to reflect approved changes to the scope of the project.
Formalizing acceptance of the project scope.
Subdividing the major deliverables into smaller, more manageable components to provide better control.
The process of progressively elaborating the work of the project, which includes developing a written scope statement that includes the project justification, the major deliverables, and the project objectives.
Any change to the project scope. A scope change almost always requires an adjustment to the project cost or schedule.
Controlling changes to project scope.
The point in time that work was scheduled to start on an activity. The scheduled start date is normally within the range of dates delimited by the early start date and the late start date. It may reflect leveling of scarce resources.
The sum of the products and services to be provided as a project.
Scheduled Finish Date, (SF)
Schedule Variance, (SV)
Schedule Performance Index, (SPI)
Schedule Development
Schedule Control
S-Curve
Risk Response Planning
Risk Response Plan
Risk Monitoring and Control
Risk Mitigation
1) Any difference between the scheduled completion of an activity and the actual completion of that activity. 2) In earned value, EV less BCWS = SV.
The point in time that work was scheduled to finish on an activity. The scheduled finish date is normally within the range of dates delimited by the early finish date and the late finish date. It may reflect leveling or scarce resources.
Analyzing activity sequences, activity durations, and resource requirements to create the project schedule.
The schedule efficiency ratio of earned value accomplished against the planned value. The SPI describes what portion of the planned schedule was actually accomplished. The SPI = EV divided by PV.
Graphic display of cumulative costs, labor hours, percentage of work, or other quantities, plotted against time. The name derives from the S-like shape of the curve (flatter at the beginning and end, steeper in the middle) produced on a project that starts slowly, accelerates, and then tails off. Also a term for the cumulative likelihood distribution that is a result of a simulation, a tool of quantitative risk analysis.
Controlling changes to the project schedule.
A document detailing all identified risks, including description, cause, probability of occurring, impact(s) on objectives, proposed responses, owners, and current status. Also known as risk register.
Developing procedures and techniques to enhance opportunities and reduce threats to the project’s objectives. The tools include avoidance, mitigation, transference, and acceptance.
Risk mitigation seeks to reduce the probability and/or impact of a risk to below an acceptable threshold.
Monitoring residual risks, identifying new risks, executing risk reduction plans, and evaluating their effectiveness throughout the project life cycle.
Risk Management Planning
Risk Management Plan
Risk Identification
Risk Event
Risk Database
Risk Category
Risk Avoidance
Risk Acceptance
Risk
Rework
Documents how the risk processes will be carried out during the project. This is the output of risk management planning.
Deciding how to approach and plan risk management activities for a project.
A discrete occurrence that may affect the project for better or worse.
Determining which risks might affect the project and documenting their characteristics. Tools used include brainstorming and checklists.
A source of potential risk reflecting technical, project management, organizational, or external sources.
A repository that provides for collection, maintenance, and analysis of data gathered and used in the risk management processes. A lessons-learned program uses a risk database. This is an output of the risk monitoring and control process.
This technique of the risk response planning process indicates that the project team has decided not to change the project plan to deal with a risk, or is unable to identify any other suitable response strategy.
Risk avoidance is changing the project plan to eliminate the risk or to protect the project objectives from its impact. It is a tool of the risk response planning process.
Action taken to bring a defective or nonconforming item into compliance with requirements or specifications.
An uncertain event or condition that, if it occurs, has a positive or negative effect on a project’s objectives.
Retainage
Responsibility Assignment Matrix, (RAM)
Resource Planning
Resource-Limited Schedule
Resource Leveling
Residual Risk
Reserve
Request for Quotation, (RFQ)
Request for Proposal, (RFP)
Remaining Duration, (RDU)
A structure that relates the project organization structure to the work breakdown structure to help ensure that each element of the project’s scope of work is assigned to a responsible individual.
A portion of a contract payment that is held until contract completion to ensure full performance of the contract terms.
A project schedule whose start and finish dates reflect expected resource availability. The final project schedule should always be resource limited.
Determining what resources (people, equipment, materials) are needed in what quantities to perform project activities.
A risk that remains after risk responses have been implemented.
Any form of network analysis in which scheduling decisions (start and finish dates) are driven by resource management concerns (e.g., limited resource availability or difficult-to-manage changes in resource levels).
Generally, this term is equivalent to request for proposal.
A provision in the project plan to mitigate cost and/or schedule risk. Often used with a modifier (e.g., management reserve, contingency reserve) to provide further detail on what types of risk are meant to be mitigated. The specific meaning of the modified term varies by application area.
The time needed to complete an activity.
A type of bid document used to solicit proposals from prospective sellers of products or services.
Quality Planning
Quality Control, (QC)
Quality Assurance, (QA)
Quantitative Risk Analysis
Qualitative Risk Analysis
Projectized Organization
Project Time Management includes what processes?
Project Time Management
Project Team Members
Project Scope Management includes what processes?
The process of monitoring specific project results to determine if they comply with relevant quality standards and identifying ways to eliminate causes of unsatisfactory performance.
Identifying which quality standards are relevant to the project, and determining how to satisfy them.
Measuring the probability and consequences of risks and estimating their implications for project objectives. Risks are characterized by probability distributions of possible outcomes. This process uses quantitative techniques such as simulation and decision tree analysis.
The process of evaluating overall project performance on a regular basis to provide confidence that the project will satisfy the relevant quality standards.
Any organizational structure in which the project manager has full authority to assign priorities and to direct the work of individuals assigned to the project.
Performing a qualitative analysis of risks and conditions to prioritize their effects on project objectives. It involves assessing the probability and impact of project risk(s) and using methods such as the probability and impact matrix to classify risks into categories of high, moderate, and low for prioritized risk response planning.
A subset of project management that includes the processes required to ensure timely completion of the project.
t consists of activity definition, activity sequencing, activity duration estimating, schedule development, and schedule control.
It consists of initiation, scope planning, scope definition, scope verification, and scope change control.
The people who report either directly or indirectly to the project manager.
Project Scope Management
Project Scope
Project Schedule
Project Risk Management includes what processes?
Project Risk Management
Project Quality Management
Project Procurement Management
Project Planning
Project Plan Execution
Project Plan Development
The work that must be done to deliver a product with the specified features and functions.
A subset of project management that includes the processes required to ensure that the project includes all of the work required, and only the work required, to complete the project successfully.
It includes the processes of risk management planning, risk identification, qualitative risk analysis, quantitative risk analysis, risk response planning, and risk monitoring and control.
The planned dates for performing activities and the planned dates for meeting milestones.
A subset of project management that includes the processes required to ensure that the project will satisfy the needs for which it was undertaken. It consists of quality planning, quality assurance, and quality control.
Risk management is the systematic process of identifying, analyzing, and responding to project risk. It includes maximizing the probability and consequences of positive events and minimizing the probability and consequences of events adverse to project objectives.
The development and maintenance of the project plan.
A subset of project management that includes the processes required to acquire goods and services to attain project scope from outside the performing organization. It consists of procurement planning, solicitation planning, solicitation, source selection, contract administration, and contract closeout.
Integrating and coordinating all project plans to create a consistent, coherent document.
Carrying out the project plan by performing the activities included therein.
Project Plan
Project Phase
Project Network Diagram
Project Manager (PM)
Project Management Team
Project Management Software
Project Management Professional, (PMP®)
Project Management Body of Knowledge, (PMBOK®)
Project Management, (PM)
Project Life Cycle
A collection of logically related project activities, usually culminating in the completion of a major deliverable.
A formal, approved document used to guide both project execution and project control. The primary uses of the project plan are to document planning assumptions and decisions, facilitate communication among stakeholders, and document approved scope, cost, and schedule baselines. A project plan may be summary or detailed.
The individual responsible for managing a project.
Any schematic display of the logical relationships of project activities. Always drawn from left to right to reflect project chronology. Often referred to as a PERT chart.
A class of computer applications specifically designed to aid with planning and controlling project costs and schedules.
The members of the project team who are directly involved in project management activities. On some smaller projects, the project management team may include virtually all of the project team members.
An inclusive term that describes the sum of knowledge within the profession of project management. As with other professions—such as law, medicine, and accounting—the body of knowledge rests with the practitioners and academics that apply and advance it. The PMBOK® includes proven, traditional practices that are widely applied, as well as innovative and advanced ones that have seen more limited use.
An individual certified as such by the Project Management Institute (PMI®).
A collection of generally sequential project phases whose name and number are determined by the control needs of the organization or organizations involved in the project.
The application of knowledge, skills, tools, and techniques to project activities to meet the project requirements.
Project Integration Management
Project Human Resource Management
Project Cost Management
Project Communications Management
Project Charter
Project
Program Evaluation and Review Technique, (PERT)
Program
Product Scope
Procurement Planning
A subset of project management that includes the processes required to make the most effective use of the people involved with the project. It consists of organizational planning, staff acquisition, and team development.
A subset of project management that includes the processes required to ensure that the various elements of the project are properly coordinated. It consists of project plan development, project plan execution, and integrated change control.
A subset of project management that includes the processes required to ensure timely and appropriate generation, collection and dissemination, storage and ultimate disposition of project information. It consists of communications planning, information distribution, performance reporting, and administrative closure.
A subset of project management that includes the processes required to ensure that the project is completed within the approved budget. It consists of resource planning, cost estimating, cost budgeting, and cost control.
A temporary endeavor undertaken to create a unique product, service, or result.
A document issued by senior management that formally authorizes the existence of a project. And it provides the project manager with the authority to apply organizational resources to project activities.
A group of related projects managed in a coordinated way. Programs usually include an element of ongoing work.
An event-oriented network analysis technique used to estimate program duration when there is uncertainty in the individual activity duration estimates. PERT applies the critical path method using durations that are computed by a weighted average of optimistic, pessimistic, and most likely duration estimates. PERT computes the standard deviation of the completion date from those of the path’s activity durations.
Determining what to procure and when.
The features and functions that characterize a product or service.
Probability and Impact Matrix
Predecessor Activity
Precedence Relationship
Precedence Diagramming Method, (PDM)
Planned Value, (PV)
PERT Chart
Performing Organization
Performance Reporting
Performance Measurement Baseline
Percent Complete, (PC)
1) In the arrow determine diagramming method, the activity that enters a node. 2) In the precedence diagramming method, the “from” activity.
whether a risk is considered low, moderate, or high by combining the two dimensions of a risk, its probability of occurrence, and its impact on objectives if it occurs.
A network diagramming technique in which activities are represented by boxes (or nodes). Activities are linked by precedence relationships to show the sequence in which the activities are to be performed.
The term used in the precedence diagramming method for a logical relationship. In current usage, however, precedence relationship, logical relationship, and dependency are widely used interchangeably, regardless of the diagramming method in use.
The term is commonly used to refer to a project network diagram.
The physical work scheduled, plus the authorized budget to accomplish the scheduled work.
Collecting and disseminating performance information. This includes status reporting, progress measurement, and forecasting.
The enterprise whose employees are most directly involved in doing the work of the project.
An estimate, expressed as a percent, of the amount of work that has been completed on an activity or a group of activities.
An approved plan against which deviations are compared for management control.
Path Convergence
Path
Pareto Diagram
Parametric Estimating
Organizational Planning
Organizational Breakdown Structure, (OBS)
Node
Network Path
Network Logic
Network Analysis
A set of sequentially connected activities in a project network diagram.
The node in the schedule where parallel paths merge or join. At that node, delays or elongation or any converging path can delay the project. In quantitative risk analysis of a schedule, significant risk may occur at this point.
An estimating technique that uses a statistical relationship between historical data and other variables (e.g., square footage in construction, lines of code in software development) to calculate an estimate.
A histogram, ordered by frequency of occurrence, that shows how many results were generated by each identified cause.
A depiction of the project organization arranged so as to relate work packages to organizational units.
Identifying, documenting, and assigning project roles, responsibilities, and reporting relationships.
Any continuous series of connected activities in a project network diagram.
One of the defining points of a network; a junction point joined to some or all of the other dependency lines.
The process of identifying early and late start and finish dates for the uncompleted portions of project activities.
The collection of activity dependencies that makes up a project network diagram.
Near-Critical Activity
Monte Carlo Analysis
Monitoring
Milestone Schedule
Milestone
Matrix Organization
Master Schedule
Loop
Start-to-finish relationship
Start-to-start relationship
A technique that performs a project simulation many times to calculate a distribution of likely results.
An activity that has low total float.
A summary-level schedule that identifies the major milestones.
The capture, analysis, and reporting of project performance, usually as compared to plan.
Any organizational structure in which the project manager shares responsibility with the functional managers for assigning priorities and for directing the work of individuals assigned to the project.
A significant event in the project. A completion of a major deliverable.
A network path that passes the same node twice. Loops cannot be analyzed using traditional network analysis techniques such as critical path method and program evaluation and review technique.
A summary-level schedule that identifies the major activities and key milestones.
The initiation of work of the successor depends upon the initiation of the work of the predecessor.
The completion of the successor is dependent upon the initiation of the predecessor.
Finish-to-finish relationship
Finish-to-start relationship
Name the four types of logical relationships
Logical Relationship
Line Manager
Life-Cycle Costing
Level of Effort, (LOE)
Lessons Learned
Lead
Late Start Date, (LS)
The initiation of work of the successor depends upon the completion of work of the predecessor.
The completion of the work of the successor cannot finish until the completion of work of the predecessor.
A dependency between two project activities, or between a project activity and a milestone.
Finish-to-start, Finish-to-finish, Start-to-start, Start-to-finish
The concept of including acquisition, operating, and disposal costs when evaluating various alternatives.
1) The manager of any group that actually makes a product or performs a service. 2) A functional manager.
The learning gained from the process of performing the project. Lessons learned may be identified at any point. Also considered a project record.
Support-type activity (e.g., vendor or customer liaison) that does not readily lend itself to measurement of discrete accomplishment. It is generally characterized by a uniform rate of activity over a period of time determined by the activities it supports.
In the critical path method, the latest possible point in time that an activity may begin without delaying a specified milestone (usually the project finish date).
A modification of a logical relationship that allows an acceleration of the successor task. For example, in a finish-to-start dependency with a ten-day lead, the successor activity can start ten days before the predecessor has finished.
Late Finish Date, (LF)
Lag
Invitation for Bid, (IFB)
Integrated Change Control
Initiation
Information Distribution
Hanger
Hammock
Graphical Evaluation and Review Technique, (GERT)
Grade
A modification of a logical relationship that directs a delay in the successor task. For example, in a finish-to-start dependency with a ten-day lag, the successor activity cannot start until ten days after the predecessor has finished.
In the critical path method, the latest possible point in time that an activity may be completed without delaying a specified milestone (usually the project finish date).
Coordinating changes across the entire project.
This term is equivalent to request for proposal. However, in some application areas, it may have a narrower or more specific meaning.
Making needed information available to project stakeholders in a timely manner.
Authorizing the project or phase.
An aggregate or summary activity (a group of related activities is shown as one and reported at a summary level). A hammock may or may not have an internal sequence.
An unintended break in a network path. Hangers are usually caused by missing activities or missing logical relationships.
A category or rank used to distinguish items that have the same functional use (e.g., “hammer”), but do not share the same requirements for quality (e.g., different hammers may need to withstand different amounts of force).
A network analysis technique that allows for conditional and probabilistic treatment of logical relationships (i.e., some activities may not be performed).
Functional Organization
Functional Manager
Free Float, (FF)
Forward Pass
Float
Firm Fixed-Price Contract, (FFP)
Finish Date
Fast Tracking
Exception Report
Event-on-Node
A manager responsible for activities in a specialized department or function (e.g., engineering, manufacturing, marketing).
An organization structure in which staff are grouped hierarchically by specialty (e.g., production, marketing, engineering, and accounting at the top level; with engineering, further divided into mechanical, electrical, and others).
he calculation of the early start and early finish dates for the uncompleted portions of all network activities.
The amount of time that an activity can be delayed without delaying the early start of any immediately following activities.
A type of contract where the buyer pays the seller a set amount (as defined by the contract), regardless of the seller’s costs.
The amount of time that an activity may be delayed from its early start without delaying the project finish date. Float is a mathematical calculation, and can change as the project progresses and changes are made to the project plan.
Compressing the project schedule by overlapping activities that would normally be done in sequence, such as design and construction.
A point in time associated with an activity’s completion. Usually qualified by one of the following: actual, planned, estimated, scheduled, early, late, baseline, target, or current.
A network diagramming technique in which events are represented by boxes (or nodes) connected by arrows to show the sequence in which the events are to occur. Used in the original program evaluation and review technique.
Document that includes only major variations from plan.
Estimate at Completion, (EAC)
Estimate
Element
Effort
Earned Value Management, (EVM)
Earned Value, (EV)
Early Start Date, (ES)
Early Finish Date, (EF)
Duration Compression
Duration, (DU)
An assessment of the likely quantitative result. Usually applied to project costs and durations and should always include some indication of accuracy (e.g., ±x percent). Usually used with a modifier (e.g., preliminary, conceptual, feasibility).
The expected total cost of an activity, a group of activities, or the project when the defined scope of work has been completed. Most techniques for forecasting EAC include some adjustment of the original cost estimate, based on actual project performance to date.
The number of labor units required to complete an activity or other project element. Usually expressed as staff hours, staff days, or staff weeks. Should not be confused with duration.
One of the parts, substances, or principles that make up a compound or complex whole.
The physical work accomplished plus the authorized budget for this work. The sum of the approved cost estimates (may include overhead allocation) foractivities (or portions of activities) completed during a given period (usually projectto-date).
A method for integrating scope, schedule, and resources, and for measuring project performance. It compares the amount of work that was planned with what was actually earned with what was actually spent to determine if cost and schedule performance are as planned.
In the critical path method, the earliest possible point in time on which the uncompleted portions of an activity can finish, based on the network logic and any schedule constraints. Early finish dates can change as the project progresses and changes are made to the project plan.
In the critical path method, the earliest possible point in time on which the uncompleted portions of an activity can start, based on the network logic and any schedule constraints. Early start dates can change as the project progresses and changes are made to the project plan.
The number of work periods (not including holidays or other nonworking periods) required to complete an activity or other project element. Usually expressed as workdays or workweeks. Sometimes incorrectly equated with elapsed time.
Shortening the project schedule without reducing the project scope. Duration compression is not always possible and often requires an increase in project cost.
Dummy Activity
Deliverable
Decision Tree Analysis
Data Date, (DD)
Current Start Date
Current Finish Date
Critical Path Method, (CPM)
Critical Path
Critical Activity
Crashing
Any measurable, tangible, verifiable outcome, result, or item that must be produced to complete a project or part of a project. Often used more narrowly in reference to an external deliverable, which is a deliverable that is subject to approval by the project sponsor or customer.
An activity of zero duration used to show a logical relationship in the arrow diagramming method. Dummy activities are used when logical relationships cannot be completely or correctly described with regular activity arrows. Dummies are shown graphically as a dashed line headed by an arrow.
The date at which, or up to which, the project’s reporting system has provided actual status and accomplishments. Also called as-of date.
The decision tree is a diagram that describes a decision under consideration and the implications of choosing one or another of the available alternatives. It incorporates probabilities or risks and the costs or rewards of each logical path of events and future decisions.
The current estimate of the point in time when an activity will be completed.
The current estimate of the point in time when an activity will begin.
The series of activities that determines the duration of the project. In a deterministic model, the critical path is usually defined as those activities with float less than or equal to a specified value, often zero. It is the longest path through the project.
A network analysis technique used to predict project duration by analyzing which sequence of activities (which path) has the least amount of scheduling flexibility (the least amount of float). Early dates are calculated by means of a forward pass, using a specified start date. Late dates are calculated by means of a backward pass, starting from a specified completion date (usually the forward pass’ calculated project early finish date).
Taking action to decrease the total project duration after analyzing a number of alternatives to determine how to get the maximum duration compression for the least cost.
Any activity on a critical path. Most commonly determined by using the critical path method. Although some activities are “critical,” in the dictionary sense, without being on the critical path, this meaning is seldom used in the project context.
Cost Variance, (CV)
Cost-Plus-Incentive-Fee Contract, (CPIF)
Cost-Plus-Fixed-Fee Contract, (CPFF)
What is the forumla for figuring the Cost Performance Index (CPI)?
Cost Performance Index, (CPI)
Cost of Quality
Cost Estimating
Cost Control
Cost Budgeting
Corrective Action
A type of contract where the buyer reimburses the seller for the seller’s allowable costs (allowable costs are defined by the contract), and the seller earns its profit if it meets defined performance criteria.
1) Any difference between the budgeted cost of an activity and the actual cost of that activity. 2) In earned value, EV less ACWP = CV.
CPI = EV divided by AC
A type of contract where the buyer reimburses the seller for the seller’s allowable costs (allowable costs are defined by the contract) plus a fixed amount of profit (fee).
The costs incurred to ensure quality. The cost of quality includes quality planning, quality control, quality assurance, and rework.
The cost efficiency ratio of earned value to actual costs.
Controlling changes to the project budget.
Developing an approximation (estimate) of the cost of the resources needed to complete project activities.
Changes made to bring expected future performance of the project in line with the plan.
Allocating the cost estimates to individual work activities.
Control Charts
Control Account Plan, (CAP)
Control
Contract Closeout
Contract Administration
Time and material contracts
Do cost-reimbursable contracts use incentives?
Cost-reimbursable contracts
Do fixed-price contracts use incentives?
Fixed-price / Lump-sum contracts
The CAP is a management control point where the integration of scope and budget and schedule takes place, and where the measurement of performance will happen. CAPs are placed at selected management points of the work breakdown structure.
Control charts are a graphic display of the results, over time and against established control limits, of a process. They are used to determine if the process is “in control” or in need of adjustment.
Completion and settlement of the contract, including resolution of any open items.
The process of comparing actual performance with planned performance, analyzing variances, evaluating possible alternatives, and taking appropriate corrective action as needed.
These contracts are a hybrid type of contractual arrangement that contain aspects of both cost-reimbursable and fixedprice arrangements. Time and material contracts resemble cost-type arrangements in that they are open ended, because the full value of the arrangement is not defined at the time of the award. Thus, time and material contracts can grow in contract value as if they were cost-reimbursable-type arrangements. Conversely, time and material arrangements can also resemble fixed-unit arrangements when, for example, the unit rates are preset by the buyer and seller, as when both parties agree on the rates for the category of “senior engineers.”
Managing the relationship with the seller.
Tthis category of contract involves payment to the contractor for its actual costs. Costs are classified as direct costs and indirect costs. Indirect costs are usually calculated as a percentage of direct costs.
Cost-reimbursable contracts include incentives for meeting or exceeding selected project objectives, such as schedule targets or total cost.
This category of contract involves a fixed total price for a well-defined product. Fixed-price contracts may also include incentives for meeting or exceeding selected project objectives, such as schedule targets.
Yes, fixed-price contracts may include incentives for meeting or exceeding selected project objectives, such as schedule targets.
Name 3 types of contracts.
Contract
Contingency Reserve
Constraint
Component
Communications Planning
Code of Accounts
Checklist
Chart of Accounts
Change Control Board, (CCB)
A contract is a mutually binding agreement that obligates the seller to provide the specified product and obligates the buyer to pay for it.
1. Fixed-price or lump-sum contracts, 2. Cost-reimbursable contracts, 3. Time and material contracts
Applicable restriction that will affect the performance of the project. Any factor that affects when an activity can be scheduled.
Contingency Planning. The development of a management plan that identifies alternative strategies to be used to ensure project success if specified risk events occur.
Determining the information and communications needs of the project stakeholders: who needs what information, when they will need it, and how it will be given to them.
A constituent part, an element.
A listing of many possible risks that might occur on a project. It is used as a tool in the risk identification process. Checklists are comprehensive, listing several types of risk that have been encountered on prior projects.
Any numbering system used to uniquely identify each element of the work breakdown structure.
A formally constituted group of stakeholders responsible for approving or rejecting changes to the project baselines.
Any numbering system used to monitor project costs by category. The project chart of accounts is usually based upon the corporate chart of accounts of the primary performing organization.
Calendar Unit
Budget at Completion, (BAC)
Brainstorming
Baseline
Describe a the make-up of a bar chart.
Bar Chart
Backward Pass
Assumptions analysis
Assumptions
Arrow Diagramming Method, (ADM)
The sum of the total budgets for a project.
The smallest unit of time used in scheduling the project. Calendar units are generally in hours, days, or weeks, but can also be in shifts or even in minutes. Used primarily in relation to project management software.
The original approved plan (for a project, a work package, or an activity), plus or minus approved scope changes.
A general creativity technique that can be used to identify risks using a group of team members or subject-matter experts. Typically, a brainstorming session is structured so that each participant’s ideas are recorded for later analysis. A tool of the risk identification process.
A graphic display of schedule-related information.
In the typical bar chart, activities or other project elements are listed down the left side of the chart, dates are shown across the top, and activity durations are shown as date-placed horizontal.
A technique that explores the assumptions’ accuracy and identifies risks to the project from inaccuracy, inconsistency, or incompleteness of assumptions.
The calculation of late finish dates and late start dates for the uncompleted portions of all network activities. Determined by working backwards through the network logic from the project’s end date. The end date may be calculated in a forward pass or set by the customer or sponsor.
A network diagramming technique in which activities are represented by arrows. The tail of. Activities are connected at points called nodes (usually drawn as small circles) to illustrate the sequence in which the activities are expected to be performed.
Assumptions are factors that, for planning purposes, are considered to be true, real, or certain. Assumptions affect all aspects of project planning, and are part of the progressive elaboration of the project. Project teams frequently identify, document, and validate assumptions as part of their planning process. Assumptions generally involve a degree of risk.
Arrow
Application Area
Administrative Closure
Actual Start Date, (AS)
Actual Finish Date, (AF)
Actual Cost, (AC)
Activity Sequencing
Activity Description
Activity Definition
Activity
A category of projects that have common elements not present in all projects. Application areas are usually defined in terms of either the product of the project. Application areas often overlap.
The graphic presentation of an activity.
The point in time that work actually started on an activity.
Generating, gathering, and disseminating information to formalize phase or project completion.
Total costs incurred that must relate to whatever cost was budgeted within the planned value and earned value (which can sometimes be direct labor hours alone, direct costs alone, or all costs including indirect costs) in accomplishing work during a given time period.
The point in time that work actually ended on an activity.
A short phrase or label used in a project network diagram. The activity description normally describes the scope of work of the activity.
Identifying and documenting interactivity logical relationships.
An element of work performed during the course of a project. An activity normally has an expected duration, an expected cost, and expected resource requirements. Activities can be subdivided into tasks.
Identifying the specific activities that must be performed to produce the various project deliverables.
The project charter is created during which life cycle phase?
Sigma level: +- 1 sigma, +- 2 sigma. +- 3 sigma, +- 6 sigma
Estimate types:1. Order of Magnitude, 2. Budget, 3. Definitive
Communication Paths, (formula)
Communication Paths
PERT, (formula)
PERT Probability Analysis
Interest
Standard Deviation, (formula)
Present Value, (formula)
Correctness: 68.26%, 95.46%, 99.73%, 99.99%
Initiation
N * (N-1) / 2
Accuracy: 1. -25% to +75%, 2. -10% to +25%, 3. -5% to +10%
P + 4M + O / 6
Number of communication paths, (N = number of people on project)
I = P * R * T, Interest = Principal * Rate * Time
Average of Pessimistic, Optimistic and 4 times the Most likely estimates
FV / (1+r)n, FV = future value; r = interest rate; n = number of time periods
P- O / 6
Schedule Performance Index
Schedule Performance Index, (formula)
Cost Performance Index, (formula)
Cost Performance Index, (formula)
Schedule Variance
Schedule Variance, (formula)
Cost Variance
Cost Variance, (formula)
Variance At Completion
Variance At Completion, (formula)
EV / PB or, BCWP / BCWS
I'm progressing at ___% of the rate originally planned.
EV / AC or BCWP / ACWP
I'm getting ___ cents out of every dollar.
EV-PV or, BCWP-BCWS
Negative: Behind schedule (bad)… Positive: Ahead of schedule (good)
EC-AC or BCWP-ACWP
Negative: Over budget (bad)… Positive: Under budget (good)
BAC-EAC
How much over/under budget do we expect to be?
Estimate To Complete
Estimate To Complete, (formula)
Estimate At Completion
Estimate At Completion,(formula)
Budget At Completion
Actual Cost or Actual Cost of Work Performed
Earned Value, or Budgeted Cost of Work Performed
Planned Value or Budgeted Cost of Work Scheduled
General Management Skills include:
Risk Response Control involve:
EAC-ACWP or BAC-BCWP / CPI
From this point on, how much MORE will it cost to finish?
BAC / CPI
As of now, we EXPECT the total project to cost $___.
What is the ACTUAL cost INCURRED? What have we spent to date?
How much did you BUDGET for the total job? TOTAL BUDGET
How much work SHOULD be done? (Estimated value of PLANNED work)
How much work is ACTUALLY done, per the budget?
Involves executing the risk management plan in order to respond to risk events over the course of the project.
Leading, Negotiating, Negotiating
Contingency planning involves:
Risk response to threats fall into the following categories:
Simulation uses a representation or model of a system to:
Decision Trees are:
Risk quantification involves:
Risk systems are:
Risk Identification consists of:
Some of the processes of Project Risk management:
Some of the inputs to administrative closure include:
Administrative closure consists:
Avoidance, mitigation, acceptance
Defining action steps to be taken if an identified risk event should occur.
Are diagrams that depict key interactions among decisions and associated chance events as they are understood by the decision maker.
Analyze the behavior or performance of a system
Also called triggers, are indirect manifestations of actual risk events.
Involves evaluating risks and risk interactions to assess the range of project outcomes.
Risk identification, risk quantification, risk response control
Determining which risks are likely to affect the project and documenting the characteristics of each.
Of verifying and documenting project results to formalize acceptance of the product of the project by the sponsor, client, or customer.
Performance measurement documentation, Documentation of the product of the project, Other project records
Earned value analysis is:
Trend analysis involves:
Variance analysis involves:
Performance review meetings are:
Forecasting involves:
Progress reporting describes:
Status reporting describes:
Performance reporting involves:
Information distribution:
Assumptions are:
Involves examining project results over time to determine if performance is improving or deteriorating.
The most commonly used method of performance measurement.
Held to assess project status or progress.
Involves comparing actual results to planned or expected results.
What the project team has accomplished.
Predicting future project status and progress.
Collecting and disseminating performance information in order to provide stakeholders with information about how resources are being used to achieve project objectives.
Where the project now stands.
Factors that, for planning purposes, will be considered to be true, real or certain.
Involves making needed information available to project stakeholders in a timely manner.
Information typically required to determine project communications requirements includes:
Communications planning involves:
Some of the processes in project communications management include:
Some of the tools and techniques for team development include:
Team development on a project is:
A Responsibility Assignment Matrix:
Staffing requirements:
Are Human resource administrative activities part of the responsibility of the project management team?
Project Human Resource Management consists of the following processes?
Trend Analysis involves?
Determining the information and communications needs of the stakeholders: who needs what information, when they will need it, and how will it be given to them.
Project organization and stakeholder responsibility relationships, external information needs.
Team-building activities, Reward and recognition systems, and Training
Information distribution, Performance reporting, Administrative closure
Is used to link project roles/responsibilities to project scope definition.
Often complicated when individual team members are accountable to both a functional manager and to the project manager.
No, seldom are the direct responsibility of the project management team.
Define what kinds of skills are required from what kinds of individuals or groups and in what time frames.
Using mathematical techniques to forecast future outcomes based on historical results?
Organizational planning, Staff acquisition, Team development
Flowcharting is used in quality control to?
Statistical sampling:
A Pareto diagram is:
Control charts are:
To help evaluate quality control outputs:
Quality assurance:
The inputs to Quality Planning include:
Some of the tools and techniques for quality planning include:
The major processes in project integration management are:
Integrated Change Control changes control requires?
Involves choosing part of a population of interest for inspection.
Help analyze how problems occur.
A graphical display of the results over time of a process.
A histogram, ordered by frequency of occurrence, that shows how many results were generated by type or category of identified cause.
Includes taking action to increase the effectiveness and efficiency of the project to provide added benefits to the project stakeholders.
The project management team should have a working knowledge of statistical quality control, especially probability.
Benefits/cost analysis, Benchmarking, Design of experiments
Quality policy, Scope statement, Product description
Maintaining the integrity of the performance measurement baselines - all approved changes should be reflected in the project plan, but only project scope changes will affect the performance measurement baselines. Ensuring that changes to the product scope are reflected in the definition of the project scope. Coordinating changes across knowledge areas.
Project plan development, Project plan execution, Integrated change control
Integrated Change Control is concerned with?
Project Plan Execution
Project Plan Development
Project Integration Management
5 Phases of Project Management
Initiation Phase Activities
Planning Phase Core Processes
Planning Phase Facilitating Processes
Activity
Activity aspects
Carrying out the project plan by performing the activities included therein. The vast majority of the project's budget will be expended in performing this process.
1) Influencing the factors which creates changes to ensure that changes are beneficial. 2) Determining that that a change has occurred. 3) Managing the actual changes when and as they occur.
Processes required to ensure that the various elements of the project are properly coordinated.
Taking the results of other planning processes and putting them into a consistent, coherent document that can be used to guide both project execution and project control.
Initiation
Initiation - Planning Execution - Control Closure
Quality Planning Communicaiton Planning - Risk ID - Risk Quantification - Risk Response Devlp Organizational Planning - Staff Acquisition - Procurement Planning - Solicitation Planning
Scope Planning - Scope Definition - Activity Definition Activity Sequencing - Activity Duration Estimating - Resource Planning - Cost Estimating Schedule Development - Cost Budgeting - Project Plan Development
Duration - Expected cost - Expected resources required
Element of work on a project
Activity definition
Activity description
Activity Duration Estimating
Activity-On-Arrow
Activity-On-Node
Actual Cost of Work Performed
Actual Finish Date
Actual Start Date
Administrative Closure
Application Area
The scope of work of the activity. - Used in project diagrams.
Identifying specific activities that must be performed in order to produce a project's deliverables.
Part of the Arrow Diagramming Method
Estimating the number of work periods that will be needed to complete individual activities.
Total costs incurred (direct and indirect) for a project.
Part of the Precedence Diagramming Method
When work starts.
When work ends.
Type of: product, project or customer. There is often overlap
Formalized project end.
Arrow
Arrow Diagramming Method
As-Of Date
Backward Pass
Bar Chart
Baseline
Baseline Finish Date
Baseline Start Date
Budget at Completion
Budget Estimate
Graphical representation of a project where activities are represented by arrows.
Graphic presentation of an activity.
Calculating a project length based on end-date
Same as Data Date
The original plan
Left side = Project elements Bottom = Date range (Also called = GANTT Chart)
Scheduled Start Date
Scheduled Finish Date
Estimate
The estimated total cost of the project when done.
Budget Cost of Work Performed
Budgeted Cost of Work Scheduled
Calendar Unit
Change Control Board
Change in Scope
Chart of Accounts
Charter
Code of Accounts
Communications Planning
Concurrent Engineering
Sum of approved cost estimates not yet completed. Part of Earned Value
Sum of approved cost estimates completed. Part of Earned Value
Group of stakeholders responsible for approving or rejecting changes in the project baseline.
Smaller unit (Hours Days - Weeks - Shifts Minutes)
Numbering system used to monitor project costs by category.
Scope Change
Numbering system used to identify each element of the work breakdown structure.
Same as project charter
Not Fast Tracking Calls for project implementations to be involved in the Design Phase.
Determining the communication needs and procedures for each stakeholder.
Contingency Planning
Contingency Reserve
Contract - 3 Categories
Contract Definition
Contract - 2 Parts
Contract - Fixed price/Lump Sum
Contract - Cost reimbursable
Contract - Unit Price
Contract Administration
Contract Close-out
Known Unknowns. They are buffers (cost, schedules, resources) built into the project baseline.
Risk mitigation plan
Mutually binding agreement.
1 - Fixed price or lump sum. 2 - Cost reimbursable. 3 - Unit price
Fixed price for a well-defined product or service.
Seller - delivers product or service. Buyer - obliged to pay for product or service.
Seller is paid a pre-set price for unit of product or service (i.e. $70 per hour)
Time and materials.
Completion of the contract.
Managing the relationship with the seller.
Control
Control Chart
Corrective Action
Cost Budgeting
Cost control.
Cost Estimating
Cost of Quality
Cost Performance Index = Formula
Cost Performance Index
Project Cost at Compellation
Graphical display of results.
Comparing planned vs. actual performance.
Allocating cost estimates to the actual project.
Used to get a project back on track.
Estimating project costs
Controlling changes in the project budget.
CPI = BCWP / ACWP
Cost incurred to ensure quality.
PCC = Original Cost Est. / CPI
Used to predict the magnitude of a project cost overrun.
Cost Plus Fixed Fee Contract
Cost Plus Inventive Fee Contract
Cost Variance
Crashing
Critical Activity
Critical Path Method
Current Finish Date
Current Start Date
Data Date
Deliverable
Time and Materials + fixed profit level if all goals are met.
Time and Materials + a fixed profit level.
Taking action to decrease a project timeline.
BCWP < ACWP Difference between estimated and actual cost.
The path with the least amount of flexibility.
Critical Path Method
Current estimate of project initiation.
Current estimate of project completion
Tangible and verifiable outcome.
As-Of-Date. Point of time that is between historical and future date.
Dependency
Dummy Activity
Duration
Duration Compressing
Early Finish Date
Early Start Date
Earned Value
Effort
Estimate
Estimate at Completion
Zero length. Place holder activities in a project schedule.
Requires another step to be accomplished.
Shorten duration without decreasing project scope.
Length of time to complete an activity.
Used in the Critical Path Method. Earliest date the project can be started by.
Used in the Critical Path Method. Earliest date the project can be completed by.
Not Duration. Resource units needed to complete an activity.
1 - Method for measuring project performance. 2 Budgeted cost. 3 Compares work planned vs. actually performed.
EAC = Actuals-to-date + ETC
Prediction of costs, resources needed and duration.
Estimate to Complete
Event-on-Node
Exception Report
Expected Monetary Value
Fast Tracking
Finish Date
Firm Fixed Price Contract
Fixed Price Incentive Fee Contract
Float
Forecast Final Cost
Project diagramming method that uses connected boxes.
Expected additional cost needed to complete an activity.
Monetary gain or lose due to an event.
Document which show only major variations to the project plan.
Project activities completed date.
Compressing a project schedule by overlapping activities. Not = Concurrent Engineering
Fixed price with a bonus for performance.
Fixed price, regardless of changes in Time and Material costs.
EST
Amount of time an activity can be delayed without affecting the project schedule.
Forward Pass
Fragnet
Free Float
Functional Manager
Functional Organization
Gantt Chart
Grade
Graphical Evaluation and Review Technique
Hammock
Hanger
Subnet
Calculating a project time-line based on a start-date.
Specialized department manager (i.e. Marketing Mgr.)
Amount of time an activity can be delayed without affecting an early start of a project.
Bar chart
Department (i.e. Marketing Dept) grouped staff.
Cartoon representation of a Conditional evaluation of a problem.
Items in the same category but require different quality controls.
Break in the project path - missed activities in the plan.
Summary/roll-up activity
Information Distribution
Initiation
Integrated Cost/Schedule Reporting
Invitation for Bid
Key Event Schedule
Lag
Late Finish Date
Late Start Date
Lead
Level of Effort
Committing the organization to begin a project phase.
Distributing necessary information to project stakeholders
Request for Proposal
Earned Value
A step in the project path must wait X days after its predecessor is completed.
Master Schedule
Latest possible date a task can begin without delaying the schedule.
Latest possible date a task can be completed without delaying the schedule.
Estimate of resources needed to complete the task.
A step in the project path which can start X days before its predecessor is completed.
Life-Cycle Costing
Line Manager
Link
Logic Diagram
Logical Relationships (4 Types)
Finish-to-Start Activity
Finish-to-Finish Activity
Finish-to-Start Activity
Finish-to-Start Activity
Loop
A manager who is also working directly on the project.
Acquisition Operating - Disposal costs. Considered when evaluating alternatives.
Project Network Diagram
Connection of steps
The FROM activity must FINISH before the TO activity can START.
Finish-to-start / Finish-to-finish / Start-to-start / Start-to-finish
The FROM activity must START before the TO activity can FINISH.
The FROM activity must FINISH before the TO activity can FINISH.
Cannot be in CPM or PERT. Can be in GERT
The FROM activity must START before the TO activity can FINSH.
Management Reserve
Master Schedule
Matrix Organization
Milestone
Mitigation
Modern Project Management
Monitoring
Monte Carlo Analysis
Near-Critical Activity
Network Analysis
Summary-level schedule that identifies key milestones.
Cost and schedule buffers planned by management for unseen events that would impact the project.
Significant event.
Project and Functional managers share responsibilities.
Broad / Not focused on cost and time / Focused on: scope, cost, time quality, risk, etc.
Steps to lessen risk by lowering probability.
Simulation of Risk that occurs throughout the project.
Tracking and reporting project performance and status.
The process of identifying early and late finish dates for the uncompleted portions of project activities.
An activity that has low total float.
Network Logic
Network Path
Node
Organizational Breakdown Structure
Organizational Planning
Integrated Change Control
Parametric Estimating
Pareto Diagram
Path
Path Convergence
Connected activities in the project network diagram.
A collection of dependencies that make up the project network diagram.
A depiction of the project into work breakdown "packages".
A junction point in a project network diagram.
Coordinating changes across the entire project.
Identifying, documenting and assigning project roles, responsibilities and reporting relationships.
Histogram ordered by frequency of occurrence that shows multiple results relating to one cause.
Estimates based on statistics and history.
Parallel paths that lead to one milestone, but may singularly delay a project.
Sequential activities.
Percent Complete
Performance Reporting
Performing Organization
Precedence Diagramming Method
Precedence Relationship
Predecessor Activity
Procurement Planning
Program
Program Evaluation and Review Technique
Project
Collecting and disseminating information about project performance to help ensure project progress.
Percent of work already performed.
Activities are represented by boxes and linked sequentially. A diagramming method.
The enterprise whose employees are most directly involved in doing the work of the project.
1 - Arrow Diagramming Method - Activity which enters a NODE. / 2 - Precedence Diagramming Method Activity which goes "away from" the NODE.
Refers to the diagramming methods.
A group of related projects. Usually on-going.
Determining what to procure and when.
A temporary endeavor undertaken to create a unique product or service.
Event-oriented. Used to estimate project duration. Used for projects with uncertainly in duration.
Project Charter
Project Communications Management
Project Cost Management
Project Human Resource Management
Project Integration Management
Project Life Cycle
Project Management
Project Management Body of Knowledge
Project Management Software
Project Management Professional
Subset project for collecting and dispersing project info.
Sr. Management's written authority given to the PM for organization resources.
Subset project for effectively using personnel in the project.
Subset project for ensuring a project is completed within budget.
A collection of sequential project phases.
Subset project for integrating subset projects into the whole.
Book of proven project management practices.
The knowledge, skills, tools and techniques to meet and exceed a stakeholders expectations with a project.
Certified PM from PMI
Computer application designed to plan and control a project.
Project Management Team
Project Manager
Project Network Diagram
Project Phase
Project Plan
Project Plan - Elements
Is a Project Plan Summary or Detailed?
Project Plan Development
Project Plan Execution
Project Planning
Individual responsible for managing the project.
Members of the project team.
A subset collection of project activities.
PERT or GANTT Schematic display of project activities.
Plan / Cost Assumptions / Schedule / Decisions / Scope
Formal document used to guide the project.
Taking the results of other planning processes and putting them into a new document.
Can be both
Development and maintenance of the project plan.
Carrying out the project plan details.
Project Procurement Management
Project Quality Management
Project Risk Management
Project Schedule
Project Scope Management
Project Team Members
Project Time Management
Projectized Organization
Quality Assurance
Quality Control
Subset of the project used to ensure the project is up to requirements at delivery.
Acquiring goods and services outside of the project team for use in the project.
Outlines dates for each activity in sequential order.
Subset of the project for identifying and mitigating risks.
They work for the Project Manager
Subset of the project used to ensure only the pre-defined work required is done and no more.
Where PM has 100% over project team. No shared authority.
Subset of the project that monitors and ensures a team meeting all milestone dates.
Process of evaluating specific project steps to verify they meet with the project quality standards.
Evaluating process to ensure the project will satisfy its quality standards.
Quality Planning
Remaining Duration
Request for Proposal
Request for Quotation
Reserve
Resource Leveling
Resource-Limited Schedule
Resource Planning
Responsibility Assignment Matrix
Retainage
Time needed to complete an activity.
Identifying which quality standards are relevant to the project.
Bid document from a company to a vendor for pricing information.
Bid document from company to vendor.
Where scheduling concerns are addressed by resource management concerns.
Provision in the project plan to mitigate cost and/or schedule risks.
Resource identification process.
Project where start and end date are based on resource availability.
Down payment on a contracted product or service.
Relates project organization structure to work breakdown structure.
Risk Event
Risk Identification
Risk Quantification
Risk Response Control
Risk Response Development
S-Curve
Schedule Control
Schedule Development
Schedule Performance Index
Schedule Variance
Identifying which risks will affect the project.
An occurrence that affects the projects outcome.
Responding to changes in risk over the course of the project.
Identifying probability of the risk.
Graph showing cumulative cost and labor over time.
Risk mitigation plan
Analyzing activity sequences, durations and resource requirements to create a project schedule.
Controlling changes to the project schedule
Difference between scheduled and actual timeframes.
Work performed / Work Schedule (BCWP / BCWS)
Scheduled Finished Date
Scheduled Start Date
Scope
Scope Change
Scope Change Control
Scope Definition
Scope Planning
Scope Verification
Should-Cost Estimate
Slack
Planned activity start date
Planned activity end date
Any change to the scope.
The sum of the products and services to be provided as a project.
Decomposing the major deliverables into small parts.
Controlling changes in the scope.
Auditing each scope element at the end of a project for completion.
Written scope statements.
Used in PERT for FLOAT
Used to judge the reasonableness of a vendors quote.
Solicitation
Solicitation Planning
Source Selection
Staff Acquisition
Stakeholder
Start Date
Statement of Work
Subnet
Successor Activity
Target Completion Date
Document stating requirements and potential sources to meet those requirements.
Obtaining quotes, bids and offers.
Getting human resources to work on the project.
Choosing a vendor or product.
Qualified starting date
People directly or indirectly involved in the project.
Subproject
A narrative description of products or services to be supplied under contract.
A constraining date in the project diagram.
Activity while "leaves" the node.
Team Development
Time-Scaled Network Diagram
Target Finish Date
Target Start Date
Total Float
Total Quality Management
Workaround
Work Breakdown Structure
Work Item
Work Breakdown Structure
Diagram where the physical shape of each activity object is proportional to the duration of that activity.
Developing team members to enhance the project.
The date the work for the activity is planned to be started by.
The date the work for the activity is planned to be completed by.
Quality improvement program.
Float
Deliverable oriented approach. / Project elements are rolled up into larger project deliverables.
An alternative risk mitigation plan. Leaves Risk in place.
Lowest level deliverable. / May be divided into activities.
Activity
Project Plan Execution - Inputs
Project Plan Development - Tools
Project Plan Execution - Tools
Integrated Change Control - Inputs
Integrated Change Control - Tools
Initiation - Inputs
Initiation - Tools
Scope Planning - Tools
Scope Planning Inputs
Scope Definition Tools
Project planning methodology, stakeholder skills & knowledge, project management information system (PMIS), earned value management (EVM)
Project plan, supporting details, organizational policies, preventive action, corrective action
Project plan, performance reports, change requests
General management skills, product skills & knowledge, work authorization system, project management information system (PMIS), and organization procedures
Product description, strategic plan, project selection criteria, and historical information
Change control system, configuration management, performance measurements, additional planning, and project management information system (PMIS)
Product analysis, benefit/cost analysis. alternative identification and expert judgement
Project selection methods, expert judgement
WBS templates and decomposition
Product description, project charter, constraints, and assumptions
Scope Definition Inputs
Scope Verification Tools
Scope Verification Input
Scope Change Control - Tools
Scope Change Control - Inputs
Activity Definition Tools
Activity Definition Inputs
Activity Sequencing Inputs
Activity Sequencing Tools
Project Plan Development - Input
Inspection
Scope statement, constraints, assumptions, other planning outputs, and historical information
Scope change control system, performance measurement, and additional planning
Work results, product documentation, WBS, scope statement and project plan
Decomposition and templates
WBS, performance reports, change requests, and scope management plan
Activity list, product description, mandatory dependencies, discretionary dependencies, external dependencies and milestones
WBS, scope statement, historical information, constraints, assumptions, and expert judgement
Other planning outputs, historical information, organizational policies, constraints, assumptions
Precedence Diagram Method (PDM), Arrow Diagram Method (ADM), conditional diagram techniques and network templates
Schedule Development - Inputs
Cost Control - Input
Activity Duration Estimating - Inputs
Schedule Development - Tools
Schedule Control Tools
Schedule Control Inputs
Resource Planning Tools
Resource Planning Inputs
Cost Estimating Tools
Cost Estimating Inputs
Cost baseline, performance reports, change requests, and cost management plan
Project network diagrams, activity duration estimates, resource requirements, resource pool descriptions, calendars, constraints, assumptions, leads and lags, risk management plan, and activity attributes
Mathematical analysis, duration compression, simulation, resource leveling heuristics, project management software, and coding structure
Activity list, constraints, assumptions, resource requirements, resource capabilities, historical information and identified risks
Project schedule, performance reports, change requests, and schedule management plan
Schedule change control software, performance measurements, additional planning, project management software, and variance analysis
WBS, historical information, scope statement, resource pool description, organizational policies, and activity duration estimates
Expert judgment, alternatives identification, and project management software
WBS, resource requirements, resource rates, activity duration estimates, estimating publications, historical information, chart of accounts, and risks
Analogous estimating, parametric modeling, bottom-up estimating, computerized tools, and other cost estimating methods
Cost Budgeting - Tools
Cost Budgeting - Tools
Cost Control - Tools
Activity Duration Estimating - Inputs
Quality Planning Tools
Quality Assurance Tools
Quality Assurance Inputs
Quality Control - Tools
Quality Control Inputs
Quality Planning Input
Cost estimating tools & techniques
Cost estimates, WBS, project schedule, and risk management plan
Expert judgment, analogous estimating, quantitative based durations, and reserve time (contingency)
Cost change control system, performance measurements, earned value management, additional planning, and computerized tools
Quality planning tools and techniques, and quality audits
Benefit/cost analysis, benchmarking, flow charting, design of experiments, cost of quality
Inspection, control charts, Pareto diagrams, statistical sampling, flow charting, and trend analysis
Quality management plan, quality control measurements, and operational definitions
Quality policy, scope statement, product description, standards and regulations, and other process inputs
Work results, quality management plan, operational definitions, and checklists
Organization Planning - Inputs
Staff Acquisition Tools
Staff Acquisition Inputs
Team Development Tools
Team Development Inputs
Communication Planning - Tools
Communications Planning - Inputs
Information Distribution - Tools
Information Distribution - Inputs
Performance Reporting - Tools
Negotiations, pre-assignment, and procurement
Project interfaces, staffing requirements, and constraints
Team building activities, general management skills, reward and recognition systems, collocation, and training
Staffing management plan, staffing pool descriptions, and recruitment practices
Stakeholder analysis
Project staff, project plan, staffing management plan, performance reports, and external feedback
Communication skills, information retrieval systems, and information distribution systems
Communications requirements, communications technology, constraints, and assumptions
Performance reviews, variance analysis, trend analysis, earned value analysis, and information distribution tools
Work results, communications management plan, and project plan
Administrative Closure - Inputs
Administrative Closure - Tools
Performance Reporting - Inputs
Risk Management Planning - Inputs
Risk Management Planning - Tools
Risk Identification Tools
Risk Identification Inputs
Qualitative Risk Analysis - Tools
Qualitative Risk Analysis - Input
Organizational Planning - Tools
Performance reporting tools, project reports, and project presentations
Performance measurement documents, product documentation, and other project records
Project charter, organizational risk management policies, defined roles and responsibilities, stakeholder risk tolerance, organization's risk management templates, and the WBS
Project plan, work results, and other project records
Documentation review, information gathering techniques, checklists, assumptions analysis, and diagramming techniques
Planning Meetings
Risk probability and impact, probability/impact risk rating matrix, project assumptions testing, and data precision ranking
Risk management plan, project planning outputs, risk categories, and historical information
Templates, human resource practices, organizational theory, and stakeholder analysis
Risk management plan, identified risks, project status, project type, data precision, scales of probability and impact, and assumptions
Risk Monitoring & Control Tools
Quantitative Risk Analysis - Inputs
Procurement Planning - Tools
Risk Monitoring and Control - Inputs
Solicitation - Tools
Solicitation Planning Inputs
Solicitation Planning Tools
Procurement Planning - Inputs
Solicitation - Inputs
Source Selection Inputs
Risk management plan, identified risks, list of prioritized risks, list of risks for additional analysis, historical information, expert judgment, and other planning outputs
Project risk response audits, periodic project risk reviews, earned value analysis, technical performance measurements, and additional risk response planning
Risk management plan, risk response plan, project communication, additional risk identification and analysis, and scope changes
Make of buy analysis, expert judgment, and contract type selection
Procurement management plan, statement of work, and other planning outputs
Bidders conferences, and advertising
Procurement Planning - Inputs
Standard forms and expert judgment
Proposals, evaluation criteria, and organizational policies
Procurement documents, and qualified seller lists
Source Selection Tools
Quality Control Outputs
Contract Close-out Inputs
Contract Close-out Tools
Contract Administration - Inputs
Contract Administration - Tools
Project Plan Execution - Outputs
Organizational Planning - Outputs
Project Plan Development - Outputs
Quantitative Risk Analysis - Tools
Quality improvement, acceptance decisions, rework, completed checklists, and process adjustments
Contract negotiation, weighting system, screening system, and independent estimates
Procurement Audits
Contract Documentation
Contract change control systems, performance reporting, and payment systems
Contract, work results, change requests, and seller invoices
Role and responsibility assignments, staffing management plan, oganization charts, and supporting details
Work results, and change requests
Interviewing, sensitivity analysis, decision tree analysis, and simulation
Project plan, and supporting details
Schedule Development - Outputs
Quantitative Risk Analysis - Outputs
Activity Duration Estimating - Outputs
Qualitative Risk Analysis - Outputs
Activity Sequencing Outputs
Risk Identification Outputs
Activity Definition Outputs
Risk Management Planning - Output
Scope Change Control - Outputs
Administrative Closure - Outputs
Prioritized list of quantified risks, probabilistic analysis of the project, probability of achieving the cost and time objectives, and trends in quantitative risk analysis results
Project schedule, supporting detail, schedule management plan, an resource requirement updates
Overall risk ranking for the project, list of prioritized risk, list of risks for additional analysis and management, trends in qualitative risk analysis results
Activity duration estimates, basis of estimates, and activity list updates
Risks, triggers, and inputs to other processes
Project network diagrams, and activity list updates
Risk Management Plan
Activity list, supporting details, and work breakdown structure updates
Project archives, project closure, lessons learned
Scope changes, corrective action, lessons learned, and adjusted baselines
Scope Verification Outputs
Performance Reporting - Outputs
Scope Definition Outputs
Information Distribution - Outputs
Scope Planning Output
Communication Planning - Output
Initiation - Outputs
Team Development Output
Integrated Change Control - Output
Staff Acquisition Outputs
Performance reports, and change requests
Formal Acceptance
Project records, project reports, and project presentations
Work breakdown structure, and scope statement updates
Communications management plan
Scope statement, supporting details, scope management plan
Performance improvements, and inputs to performance appraisals
Project charter, project manager identified and assigned, constraints, and assumptions
Project staff assigned, and project team directory
Project plan updates, corrective action, and lessons learned
Resource Planning Output
Risk Monitoring and Control - Outputs
Schedule Control Outputs
Risk Response Planning - Outputs
Schedule Development - Outputs
Risk Response Planning - Outputs
Risk Response Planning - Inputs
Risk Response Planning - Tools
Contract Close-out Outputs
Contract Administration Output
Workaround plans, corrective action, project change requests, updates to risk response plan, risk database, and updates to risk identification checklists
Resource requirements
Risk response plan, residual risks, secondary risks, contractual agreements, contingency reserve amount needed, inputs to other processes, and inputs to a revised project plan
Schedule updates, corrective action, and lessons learned
Risk response plan, residual risks, secondary risks, contractual agreements, contingency reserve amounts needed, Inputs to other processes, and inputs to a revised project plan
Project schedule, supporting detail, schedule management plan, and resource requirements updates
Avoidance, transference, mitigation, and acceptance
Risk management plan, list of prioritized risks, risk ranking of the project, prioritized list of quantified risks, probabilistic analysis of the project, list of potential responses, risk thresholds, risk owners, common risk causes, trends in quality and quantitative analysis results
Correspondence, contract changes, and payment requests
Contract file, and formal acceptance and closure
You are ready to enter a negotiating session with a group from Germany. The Germans have been known to be aggressive and assertive. What should you do?
During project implementation the client interprets a clause in the contact to mean one and you believe it means something else. What should you do?
Name 3 types of audits?
As a project manager, before reporting a perceived violation of an established rule or policy you should?
As a project manager, what is the most important activity to ensure stakeholder satisfaction ?
As a project manager you responsible for maintaining and ensuring what types of integrity?
According to PMI what is the most critical factor to the success of a project working internationally?
As a PMI member what happens when any party other than a member cited for noncompliance refuses to cooperate with PMI concerning matters under review?
What is one of the two conditions in which you as a PMI member must refrain from offering or accepting monetary payments or other forms of compensation?
What is meant by the term aggressive insight?
Document the dispute and refer the provisions of the contract that will address the dispute.
Maintain active listening
Ensure there is a reasonable clear and factual basis for reporting the violation.
Internal, system, and baseline
Personal integrity, project integrity, and product integrity
Documentating the requirements
Accordingly, PMI may terminate the ethics complaint.
According to PMI, it is leadership.
It is a constant self-reexamination to better understand one's own strengths and shortcomings.
Accordingly, when such payments or gifts do not conform with applicable laws and when they may provide an unfair advantage for themselves or the business they represent.
What is one condition under which a PMI member does not have to honor and maintain confidentiality and privacy of the customer?
What is one condition under which a PMI member does not have to honor and maintain confidentiality and privacy of the customer?
You co-worker is under investigation by PMI, do you need to cooperater in investigation if asked by PMI?
As a project manager what is the best way to demonstrate a professional manner with your fellow team members and stakeholders?
How can you as a project manager ensure individual integrity and professionalism?
Going of off your own experience in the field of project management, provide an example of how you can contribute to the project management professional knowledge base?
Why should you as a PMI member contribute to the project management knowledge base?
According to PMI, define transnational?
When dealing with an ethics case who decides the matter?
According to PMI, what materials are considered confidential in an ethics matter?
If granted permission by the customer, client, or employer.
If maintaining the confidentiality is otherwise unethical or unlawful.
By respecting personal, ethnic, and all cultural differences that may be present on the team or with the stakeholders.
Yes, you must cooperate with PMI concerning matters of possible ethics violations and other PMI matters. Failure to cooperate may result in your PMP designation being revoked.
By sharing lessons learned, best practices and research with other colleagues.
By adhering to all the legal requirements and ethical standards to protect the community and all stakeholders.
Working in an environment that is both global and local at the same time. It also involves creating a need for greater attention to and awareness of diversity of cultures.
To improve the quality of project management services, build on the capabilities of other colleagues and help advance the project management profession.
All material prepared by or submitted to the Project Management Institute
The PMI Ethics Review Committee, or the PMI Ethics Appeal Committee depending on the matter.
View more...
Comments